We appreciate everyone holding on. I'm the conference operator, and I'd like to welcome you to the webcast covering West Red Lake Gold Mines' results for the second quarter of 2026. <<operator_script>> This session is being recorded. <<operator_script>> At this point, I'll hand things over to Shane Williams, our Chief Executive Officer. The floor is yours.
Good morning, everyone. Thanks for being with us today to go over West Red Lake Gold's second quarter results. With me on the call today are Harpreet Dhaliwal, the company's Chief Financial Officer, and Jaclyn Ruptash, our Vice President of Corporate Communications. Before I begin, I'd like to encourage listeners to review the cautionary language regarding forward-looking statements contained in our news release and MD&A issued yesterday, which are available on SEDAR and on our website. I just want to start today by stepping back a little and looking at where we've come over the first 6 months of commercial production at Madsen. A significant part of our focus earlier this year was on underground development and establishing and setting up additional mining areas to give us greater flexibility within the operation. In Q2, we started to see the benefits of that work come through in our operating results. So this quarter, we achieved a number of milestones. We mined approximately 75,000 tonnes of material during the quarter, and that was a 46% increase over Q1. The grade improved to 4.3 grams per tonne, resulting in 10,000 -- just over 10,000 tonnes of -- mined ounces, which was a large increase quarter-over-quarter.
Gold output rose to 8,576 ounces — a 51% gain — while gold sales climbed 34% to 8,200 ounces. The team's progress this quarter has us pleased. And it's worth reminding everyone that this step forward wasn't confined to a single area of the operation. We achieved faster mining rates underground, better grades, and greater mill throughput, and each of those fed into the higher gold production — all of it part of the continuing ramp-up of a high-grade underground mine. The mill ran at roughly 842 tonnes per day on average, which is near — actually it exceeds current capacity during Q2, and it's up 47% from Q1, with recoveries held at approximately 95%. The mill's ramp-up has been very pleasing to us. It's holding its recovery, which is design recovery. And on top of that, we're getting tonnage above its permitted capacity. Meanwhile, our mining rates let us build a surface stockpile by the end of the quarter, which clearly gives us that important indicator of the progress we've made. It provides operational flexibility between the mine and the mill, which is a key part of our strategy as we look into the rest of the year.
We are therefore creating flexibility on the ground. We have spoken consistently about how important it is to develop ahead of ourselves and to establish multiple mining fronts. That gives the operating team more optionality around mine sequencing. So Q2 demonstrated considerably higher operating levels than Q1. And importantly, that operational progress is translating into significant stronger financial performance. With that, I'll turn the call over to Harpreet to review the financial results for Q2.
Thanks, Shane, and good morning, everyone. As Shane described, the jump in output for Q2 fed straight through to better financial results, and one element of that was a meaningful gain on our unit costs. All-in sustaining costs fell 30% from the prior quarter, landing at USD 3,284 per ounce sold, versus about USD 4,700 per ounce in Q1, which puts Q2 all-in sustaining costs inside our 2026 guidance band of USD 2,800 to USD 3,600 per ounce. Cash costs likewise came down 23%, to USD 2,000 per ounce sold. A key point: because Madsen carries a fairly large fixed cost base, producing and selling more gold in the quarter meant those costs were spread over more ounces, which helped drive the unit cost improvement. The 8,260 ounces of gold sold during the quarter brought in roughly $49 million of revenue, up 17% from the previous quarter. Income from mine operations rose 31%, to about $20 million, and our operating margin strengthened to 41%, up from 37% in Q1. We also recorded substantial gains in adjusted EBITDA and adjusted net earnings. Adjusted EBITDA climbed 54%, to approximately $22 million, versus $14 million in Q1. Adjusted net earnings rose 98%, to roughly $13 million, or $0.03 per basic share, compared with $6.4 million, or $0.02 per basic share, in the first quarter.
One more outcome worth pointing out is our free cash flow. In Q2, we brought in $9.7 million of positive free cash flow. We also put $6.3 million of non-sustaining growth capital into the quarter, mainly tied to ongoing progress on the Fork access drift and the Madsen shaft refurbishment project. We closed Q2 with roughly $31 million in cash and cash equivalents. And as cash generation from the operation increases going forward, our plan will be to weigh reinvestment in Madsen against our continuing debt repayment obligations. So on the balance sheet side, our real focus is keeping financial flexibility as the operation keeps moving forward. Now that Madsen is in commercial production, capital management remains a priority for the company. Overall, I'd say Q2 showed the financial effect of the higher operating levels Shane talked about, with increased gold sales helping drive stronger margins, reduced unit costs and positive free cash flow. More information on our financial results is available in our Q2 financial statements and MD&A. With that, I'll hand it back to Shane.
Thanks, Harpreet. As we look forward, what we're really focused on for the rest of 2026 is keeping up the momentum we've built and creating more flexibility throughout the operation. A major piece of that, and a key focus for us, is the underground development. We're continuing to develop ahead of the mining areas we're currently working and to build up production inventory. We're also pushing forward development and technical work at the 904 complex and at the satellite Fork deposit, and we expect both to play a key role in our 2027 production. Importantly, both are also non-remnant areas, which will obviously allow us to -- which will derisk the operation. So at Fork, we're advancing the access drift. That access drift is now 50% complete, and development and drilling at the 904 underground complex continue as we establish additional access to these large non-remnant areas. I was on site last week, and I also viewed this 904 area, and it's a very exciting part of the project as we see lots of open headings, lots of stopes, and it really opens up the potential of the ore body and our ability to ramp up much higher. So there's a lot happening underground.
We are actively mining right now. We're advancing development ahead of schedule, drilling and getting additional zones ready so they can feed into future production inventory. Alongside that effort, we're putting money into infrastructure as well. The shaft refurbishment, as you saw, is a central piece of that. As our mining and development go deeper, the shaft takes on a growing role in the operation. So the intent is that as we go deeper, it raises the efficiency of getting ore and waste up to the mine and also helps bring operating costs down. Clearly, hoisting material through the shaft costs far less than trucking it. So the shaft equipment — as we discussed, we set out a Phase 1 and a Phase 2 — most of that equipment is now on site, and refurbishment work continues toward the next phase. That will let us raise hoisting capacity to roughly 700 tonnes a day. At the mill, we're likewise concentrating on adding capacity. We hit our throughput faster than we had anticipated. So in the back half of the year, we're also working toward lifting processing rates to about 1,000 tonnes per day. We're making solid progress at the mine on our ability to ramp up.
So in the second half of the year, we're aiming to raise output to 1,000 tonnes per day through the mill. We've shown that the mill is capable of running at those levels and possibly beyond — closer to 1,300 tonnes per day. To handle that greater throughput, we're planning to install an additional crusher. We're also progressing through the permitting work needed to back sustained processing rates over the longer term. That said, when we run at elevated operating levels, there are naturally risks we need to manage throughout the operation. We're mining on multiple fronts at faster rates and moving more material between the mine and the mill. A range of factors can affect this performance from one period to the next. As we go underground, we're encountering variable ground conditions in certain areas, which has led to dilution above what we normally target, since we're targeting and hitting more oversized material along with more dilution. That larger material is hard to process in the existing crushing circuit, which is why we've adjusted underground sequencing as we work through these areas. It's also part of the reason we're considering an additional crusher.
The expectation is that this will enhance how oversized material is handled and boost throughput, which makes the crushing circuit more efficient and supports greater throughput through the mill. A key issue also occurring in the market right now is a shortage of labor. So in the industry we are seeing some labor constraints, especially when it comes to experienced underground miners. That is another factor to weigh as activity levels rise. This is something occurring across the industry as a whole as we keep working through it. That is where having a large stockpile on surface becomes essential. It provides us with more flexibility between the mine and the mill and helps keep a steady source of mill feed, processing material from the stockpile while also replenishing it with newly mined ore, and we maintain the inventory as we work through varying operating conditions. So as we look toward the balance of the year, the focus is really on execution and greater consistency at these operating levels, from development and sequencing underground to how efficiently we move and process material through the mill. As we do that, we are positioning Madsen to support our broader growth strategy, with Madsen as the operating and processing hub and additional ore source feed being advanced around it.
Rowan plays a central role in that opportunity. We submitted the technical report, and we backed the revised Rowan resource as well, which featured a 70% boost in indicated resources while keeping the high grade of roughly 13 grams per tonne that has shown up consistently at this deposit. That work leaves us more confident about Rowan as we weigh it together with Madsen within our proposed updated pre-feasibility study, which the team is progressing and bringing toward a conclusion. It also gives us another feed source for the Madsen mill. We've advanced through the initial 6 months of commercial production. That offers a solid base for what lies ahead, at Madsen and across our wider Red Lake portfolio and strategy. We also anticipate continued news flow over the rest of '26, including assays from drilling we recently finished at the Starratt-Olsen satellite deposit, assays from drilling underway in the 904 complex, more progress at Fork as we push the decline forward, and, importantly for us, the updated pre-feasibility study, in which we aim to merge Madsen and Rowan into one operating entity; we expect to release it in mid- to late September and remain on track for that timing.
With that, operator, I believe we're ready to open the line for questions.
<<operator_script>> Our first question: with first-half output near 14,000 ounces, what's your view on the full-year guidance?
Thanks. Yes, we anticipate that production for the full year will fall inside our 2026 guidance. So the way the production profile was arranged in the first half was to be weighted toward the second half. And I think when you look at the step-by-step we observed from Q1 to Q2, as you can see, operational progress has been achieved. As more mining areas became available to us, mining rates went up, and we've built a surface stockpile, which gives us flexibility between the mine and the mill. So for us, the focus for the second half is really on building that consistency as we move through the balance of the year.
Moving on to the next question, could you outline the company's approach for handling its existing debt, and also share how you're viewing the balance sheet as the remainder of the year unfolds?
Absolutely, I'm happy to take this one. As you're aware, we closed Q2 holding $31 million in cash, and we produced roughly $9 million in positive free cash flow. So all in all, our situation today is clearly quite different from what it was back when we first arranged these debt facilities. In the first half of the year, we began making principal repayments on the Nebari loan. That said, it's worth keeping in mind that when these existing debt structures were originally set up, they were built as short-term, back-end loaded financing, and the real purpose was to supply the capital required to restart Madsen and get that mine to commercial production. Beyond that, the Gold-Linked Notes were likewise part of our early financing approach, and those payments were designed to step up as time went on, in line with the growing ounce output from the operation. With all that said, now that we've moved past the shift from development into production, we're actively reviewing ways to bring down our cost of capital, which ultimately is just a prudent step in managing capital. And with that in mind, clearly the present gold price is a help to us, and we are generating cash from operations.
Also, just to flag, we still have those $0.68 warrants outstanding, and they expire this November — so that’s really only a couple of months away. If exercised, they could serve as another source of capital. And to give warrant holders some context: if they exercised at, say, today’s price of roughly $0.95, those warrant holders would get an extra 40% return on top of what they earned on the share portion of that equity financing from that period. So overall, yes, capital management is definitely a key priority for us. It’s something we’re heavily focused on, and we’ll keep focusing on it for the rest — for the second half of the year. So with that, I think we can move on to the next question.
The second quarter represented a substantial improvement over the first. Which main risks could threaten our ability to keep operating at those levels through the second half?
Yes. I believe Q2 showed that the mine can run at that kind of level. And certainly, going forward, the real task is achieving that consistency. So, as I mentioned before, activity has gone up considerably throughout the operation. We're handling several mining fronts, faster mining rates, and we're pushing more material through the mine and mill. As I -- one example I want to touch on is underground mining, which carries a number of potential risks. Ground conditions vary a great deal. So we've encountered some ground conditions in several areas. That isn't uncommon in underground mining, but it can impact mining rates, grade sequencing and how efficiently material passes through the mill. So that's really one focus behind adding a secondary crusher. It lets us ramp up production through the mill and boost our material handling and efficiency in that crushing circuit. That's another reason we focus on the stockpile, and it gives us an added layer of flexibility. So we're processing material from the stockpile while replenishing new material. So it gives us that consistency across the operation.
Labor is another item I want to address. The supply of skilled underground miners is limited throughout the mining sector, and especially in well-established jurisdictions such as Red Lake. As you're aware, competition for seasoned miners is intense. That matters, since many operations industry-wide are dealing with people-related difficulties. Still, we've assembled a solid team at Madsen, and while we have experience, some turnover is occurring. Hiring, training and keeping people is a constant priority. As operations progress, we're also gaining a clearer picture of the skills and experience required in various parts of the mine. These are all standard features of a normal ramp-up, but they also underscore how much weight we place on building our own capabilities and generating added optionality inside the operation. The more developed mining areas we have, the greater the team's flexibility to modify sequencing when conditions shift. That pushes our thinking past the existing Madsen Mine plan. Fork plays a central role in the 2027 production profile. Over the longer horizon, Rowan contributes as well — an additional source of high-grade feed ore for the Madsen mill.
So as we develop those extra mining zones around this site, we're lowering how much we depend on any single section of the mine and generating a wider output level — that's genuinely our approach built around the hub-and-spoke model, and we're progressing toward it at Red Lake with Madsen and Fork, leveraging Madsen's existing infrastructure as the central hub. And a crucial piece of that is really going to fall into place once we release the updated pre-feasibility study. We're aiming for mid- to late September on that. And I believe it will truly showcase the optionality as well as the genuine worth of the Red Lake area and the platform we've built there. So there are plenty of catalysts ahead, I think, for the company as we go forward. And yes, with that said, I'll move on to the next question.
Assuming that improvement holds up through Q2, what additional cost reduction is still possible?
Yes. So the main thing that will drive additional cost gains is really scale and consistency. As we said, Madsen Mine carries a fairly high fixed cost base, and that's comparable to a lot of other mines in Canada. So as we move more tonnes and produce and sell more ounces, those costs get spread over a bigger production base. And we saw that operating leverage show up really clearly in Q2, which led to a 30% reduction in all-in sustaining costs. That said, beyond that, there are also other efficiencies we keep working on underground and through the mill. So over time, the shaft will give us another chance to improve material movement, and obviously it's going to reduce, hopefully — it will reduce haulage requirements and costs, and that will help us bring our costs down further. But there's definitely room for more improvement. And the biggest lever for us is really going to be consistency in operating at higher levels, which we expect will really turn into better unit costs over time. So yes, we certainly do see costs coming down, but as we said — as I said, it really comes back to scale and consistency.
If we can increase our output, that will lead to improved costs.
That brings our question-and-answer portion to an end. Shane Williams, I'll now hand the conference back to you for any closing comments.
Yes. Thanks — and thank you all for being with us today. Look, we feel good about the progress we showed in Q2, and I want to thank the whole team at Madsen for the effort that went into delivering these results. So our focus is on keeping that work going and carrying it forward through the rest of the year while we build the foundation for Madsen's long-term growth. Thank you to our shareholders for your continued support.
That concludes today's conference call. You're welcome to disconnect your lines now. Thanks for joining us, and enjoy the rest of your day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete West Red Lake Gold Mines Ltd. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to West Red Lake Gold Mines Ltd. earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.