At this point, I'd like to pass the conference over to our Managing Director and Chief Executive Officer, Mr. Damien Nicks. Please proceed.
Good morning, everyone, and thanks for being with us on the webcast for AGL's 2026 half-year results. First, I want to acknowledge the traditional owners of the land where I'm standing today — the Gadigal people of the Eora Nation — and pay my respects to their elders past, present, and emerging. I'd also like to acknowledge the traditional owners of the various lands from which all of you are joining. With me today are several members of my executive team: Gary Brown, Jo Egan, David Moretto, Matthew Currie, and Ryan Warburton. I'll take us through the presentation, and we'll leave time for questions at the end. Our results for the first half showed strong operational and financial momentum right across the business, supported by better reliability and flexibility in our generation portfolio, growth in customer services, and higher margins, along with continued delivery of the transition of our asset base. It's pleasing to see customer satisfaction metrics continuing to improve, and we're working hard to support customers dealing with cost-of-living pressures. While the market saw unusually less volatility during the half than historical averages would suggest, longer-term forecasts for energy demand, and our expectations for volatility, remain strong. Importantly, stronger fleet availability and flexibility, together with excellent battery performance, helped offset the effects of lower market volatility caused by milder weather and fewer transmission constraints.
On the whole, EBITDA came in flat, and as we flagged, underlying net profit took a hit from higher depreciation and amortization—reflecting our ongoing investment in asset availability and flexibility—along with greater finance costs tied to more borrowings and higher facility interest rates, as we keep investing for growth and push ahead with the multi-decade transition of our business. We've declared a fully franked interim ordinary dividend of AUD 0.24 per share, consistent with our policy of targeting a 50%-75% payout ratio of underlying NPAT for the total FY 2026 dividend. As of today, we've narrowed the FY 2026 financial guidance ranges, reflecting a strong first-half performance, and I'll go through that at the end of this presentation. I'll also address how the NEM has gradually moved toward higher winter demand peaks rather than summer peaks, which partly explains the growing earnings skew toward the first half that we've seen in recent years. We're also rolling out a cost and productivity improvement program aimed at sustainable net operating cost reductions of AUD 50 million per annum, with the full benefit kicking in from FY 2027 onwards. Although financial outcomes were broadly stable, the fundamentals of our business keep getting stronger, with a significant improvement in operational performance during the half.
On the left-hand side, we experienced yet another stretch of heightened market activity, and during it we substantially expanded the number of customers we serve, lifted our already solid levels of customer satisfaction, and achieved better consumer margin. Excellent growth in overall customer services was posted by our customer markets business, driven mainly by expansion in energy services—this includes bringing on board Ampol customers—while services for telecommunications and Netflix customers also came in higher. Our customer satisfaction score rose to 83.8. Strategic NPS stays positive at +4, and spread-to-market churn holds firm at 5.3 percentage points—all of which strongly signal that customers are pleased with what AGL offers. Simultaneously, we achieved a 10% gain versus the prior half in consumer margin, which shows a return to more sustainable levels. Now to the right-hand side: for the first half we posted a stronger result on fleet availability and continue to expect improved fleet availability across the full year. Crucially, greater commercial availability together with better plant flexibility meant AGL could generate power at the moments when market conditions were most favorable. Even with volatility running lower, our expanding fleet of flexible assets earned an excellent premium of 20% over the time-weighted average price for the half—7 percentage points higher than FY 2025. Crucially, we expect that ongoing investment in flexible assets will cause this premium to grow over time.
And lastly, our operated battery portfolio keeps turning in outstanding results, contributing AUD 35 million in EBITDA — that's AUD 10 million more than the previous half. Once again, a robust outcome even with volatility unusually low during the period. Now let me share a few observations from the half, along with some longer-term trends and what they mean as opportunities for AGL. First, we saw new records for peak demand and, as I noted, the NEM is moving toward higher winter demand peaks compared with summer peaks. As I'll cover on slide 15, AEMO's long-term operational demand forecasts stay very favorable, reinforced by electrification growth, EV penetration, and data centres, which give AGL sizeable opportunities going forward. Importantly, our energy portfolio — especially our fleet of flexible assets — is well-positioned to capture the upside from operational demand that keeps rising and becomes peakier. I've already noted the unusually low volatility in the half, driven by milder weather and fewer transmission constraints. Over the longer term, though, as the NEM transitions, we do expect volatility to be higher across the cycle, for reasons I'll address later in the presentation. Once more, our expanding fleet of flexible assets is well-placed to capture the upside from that higher long-term volatility, delivering strong supply-side realized pricing and portfolio outcomes.
And finally, the market is meeting the 41 GW of grid-scale and residential batteries that the NEM needs by 2035. Roughly 10 GW of that target has been constructed, though a substantial volume of fresh storage and generation capacity must still come online across the next 10 years. We keep advancing construction of our high-returning operational grid-scale battery projects, and I'll discuss the new products and initiatives that are generating value for customers of our residential batteries. On the whole, AGL holds a very strong position in an energy market that is evolving and transitioning. We've enjoyed an excellent half across the business as we push ahead with delivering our strategy to create long-term value. Led by the transition of our energy portfolio, we've kept making great progress. Our development pipeline has increased to 11.3 GW, compared with 9.6 GW at the FY 2025 full-year results in August. With the scale, maturity, and quality of that pipeline, we remain very well-positioned, with our continuing emphasis on timely and disciplined execution of the projects carrying the highest portfolio value. In the half, we signed two long-term power purchase agreements with Tilt Renewables to offtake electricity generation from the Palmer Wind Farm in South Australia and the Waddi Wind Farm in Western Australia.
These PPAs also help broaden the mix of electricity sources we rely on and back our goal of adding 6 GW of renewable and firming capacity by 2030. AGL secured a CIS contract for the proposed 600 MW Hexham Wind Farm in Victoria, and AEMO allocated 176 MW of peak capacity credits to the proposed Kwinana Gas 2 project in Western Australia. Building work has begun on the 500 MW Tomago battery in New South Wales, while the 500 MW Liddell battery should reach full operations of the 500 MW in the fourth quarter of FY 2026, with the first 250 MW operating progressively this quarter. Kaluza has built up some strong momentum over the past few months as well. As we mentioned in September, bringing on ENGIE as a third major customer represented another important milestone on Kaluza's journey and signals promising potential growth in other regions. To be more specific, this multi-year, multi-market agreement is Kaluza's biggest deployment so far. The deal more than doubles the number of contracted meters at Kaluza and, importantly, builds on the considerable pipeline growth Kaluza has shown over the past two years, with multiple platform deployments in retail and flex across six active markets. The retail transformation program is continuing to progress well.
Over the past six months, we've rolled out key capabilities as planned, and the benefits we committed to are tracking to plan. We've also signed a gas supply agreement with Esso Australia, starting in 2028, for 40 petajoules, with gas supplied from the Gippsland Basin across a five-year period, which strengthens our medium-term gas supply book. Today we're also announcing a long-term strategic partnership with Aussie Broadband and the divestment of our telecommunications business, and I'll cover this on the next slide. In early November, we announced an agreement to divest 19.9% of our 20% interest in Tilt Renewables for AUD 750 million, with the agreement expected to complete in the third quarter. We expect those proceeds will be deployed toward our investment in flexible, dispatchable capacity and will provide additional balance sheet flexibility. As I mentioned, today we're announcing the divestment of our telecommunications business and a long-term strategic partnership with Aussie Broadband, with our approximately 400,000 customer services to be acquired by Aussie Broadband in June 2026. This transaction delivers strong value, with AGL expecting approximately AUD 115 million in proceeds in Aussie Broadband shares. Importantly, this move also establishes a long-term partnership in which Aussie Broadband will deliver telco services under the AGL brand, ensuring continuity for our customers and creating a platform for shared growth.
There's also a chance for us to raise our equity stake in Aussie Broadband via incentives that reward telco growth under the AGL brand. Both companies are dedicated to a smooth migration for our customers across FY 2027. As part of this strategic partnership, AGL will serve as a sales and marketing channel for Aussie Broadband's telco offers under the AGL brand, with clear incentives in place to drive strong customer growth. Customer operations will be run by Aussie Broadband, which gives customers access to its award-winning service and high-quality products. Customers will keep benefiting from the convenience and value that come from bundling AGL energy services with telco services supplied by Aussie Broadband. Because of this, AGL will keep delivering the retention benefits that this bundled offering demonstrates today. With this approach, AGL simplifies operations, backs growth in bundled offerings, and reinforces long-term alignment via an equity-based partnership that puts both companies in a position to succeed together. Moving now to our operational performance for the half, beginning with our safety, customer, and employee metrics. Total injury frequency rates show a marginal increase. Even so, this metric stays significantly below FY 2023 and FY 2024. That's a good result, especially across two major qualified outages when our contractor workforce rises significantly, and we keep striving further to improve this metric.
I've already covered customer satisfaction, which rose to 83.8, and we recognize the lower employee engagement score — 69% — from the Pulse survey conducted in November. We're collaborating closely with our employees to boost engagement throughout the organization, especially given our recent restructure, which brought a reduction in roles across the business. As I noted at the outset, our customer markets performance was led by excellent growth in customer services, sustained strong customer satisfaction, and margin improvement in a competitive market. Total services to customers grew by 108,000. Growth in energy services came largely from the acquisition and successful integration of Ampol's energy customer base — approximately 45,000 services — and we also saw solid growth in telecommunications and Netflix services. Crucially, we've kept strong customer metrics, including our leading energy brand, digital offering, and loyal customer base, with a favorable churn spread versus the rest of the market of 5.3 percentage points. Once again, a strong result in a highly competitive market. On the right-hand side, as we indicated at the full-year results, you can see improvement in consumer growth margin on the prior half, reflecting a return to more sustainable levels.
For the half, we achieved strong asset performance. That was supported by ongoing strategic investment in our generation fleet, since commercial availability and flexibility stay essential and extremely valuable in an energy market that is transitioning. On the left-hand side, we already discussed the better fleet performance for the half, which came mostly from increased wind and hydro availability. Both of the two major planned qualified unit outages were completed successfully, and their complex scopes of work were designed to enhance reliability and availability going forward. This strategic investment covered a low-pressure heater replacement at Bayswater, low-pressure turbines replacement at Loy Yang, and an updated critical spares program aimed at de-risking availability. Importantly, availability is expected to strengthen in the second half and to realign with the positive five-year trend in FY 2026. Our operated grid-scale battery fleet achieved an EAF of 99%, supported by advanced analytics and ongoing control system enhancements that optimize charge and discharge performance. In the period, the Torrens Island battery also moved to AGL site management of operations and maintenance, and this operating model will likewise be adopted across the fleet of AGL batteries after commissioning, giving AGL strength and control over asset performance. I will now turn to a more detailed discussion of the first half fleet performance, in which greater commercial availability and plant flexibility allowed AGL to generate value when market conditions were most favorable, despite a period of low volatility.
On the left side, you'll notice we achieved a solid rise in qualified commercial availability, largely because reliability improved and the unplanned outage factor came down. As I noted earlier, the reduced volatility we captured stemmed chiefly from spot price volatility in the NEM being unusually low during this half, which reflected milder weather along with fewer transmission constraints. Still, I want to stress that looking further out, as the NEM goes through its transition and qualified generation is steadily retired, new variable renewable generation enters the system and the grid works through fresh transmission build-out. We anticipate volatility will return to normal at levels above those seen in the first half. In January alone, the NEM logged 4.7 equivalent hours of market price cap. That exceeds the 4.4 hours logged across the whole first half. Overall generation volumes came in 2.8% lower, as reduced thermal generation utilization was partly offset by greater renewable output, especially from wind generation, which got a boost from the Rye Park Wind Farm coming online. Once more, even with lower thermal generation volumes, greater thermal fleet availability, together with nearly 3.3 GW of thermal fleet flexibility, let AGL generate at the moments when market conditions were most favorable, producing the robust realized supply-side pricing results you'll find on the next slide.
It's encouraging that our expanding flexible asset portfolio keeps producing solid realized pricing results on the supply side for AGL. Let me start by noting the unusually weak volatility we saw in the NEM during this half, relative to the very high, robust prior half — visible inside the orange dotted box. In the second half, we anticipate this will rise consistent with the historical pattern shown on the right-hand side of that chart. As I said, looking further out, we anticipate volatility will normalize at levels above those seen in the first half, since the NEM is going through a major transition over the coming decade. A premium over average market prices is still being realized by our flexible asset portfolio — a premium that has risen steadily since FY 2022, with a modest easing in FY 2025, though with a healthy uptick in the first half of FY 2026. Qualified flexibility investments, along with the inherent flexibility of hydro, gas, and batteries, remain the foundation of that premium. In residential battery adoption, AGL leads, beating the market in securing flexible load and the related value pools as customer demand speeds up. The chart on the left-hand side illustrates the substantial storage needed by 2035 as the NEM moves away from qualified generation: 40 GW by 2035 according to AEMO's latest forecast, versus just 10 GW currently in the system.
On the right-hand side, you can see how we're capturing value and innovating across emerging residential battery-enabled value pools as the market evolves. We've achieved excellent market share growth, with our residential battery customer base doubling over the past 12 months, outpacing broader market growth. We've also strengthened our flexibility proposition by launching AGL's first battery flexibility offering, Battery Rewards, alongside a partnership with leading battery brand Sigenergy. Our orchestration capabilities continue to expand with the launch of AGL Community Power following the acquisition of South Australia's virtual power plant from Tesla. In addition, we have significantly expanded OEM capability, driving growth in VPP signups. We're also innovating in emerging flexibility value pools through vehicle-to-grid trials and a network flexibility services pilot, FlexTogether, in collaboration with Endeavour Energy. Encouragingly, there are positive indicators for the demand in the NEM, which represents a potential tailwind for electricity pricing. We've seen peak demand records achieved in the NEM in 2025, as well as the continued strong long-term outlook for energy demand, supported by electrification, data centers, and the expected continuity of smelter operations in New South Wales. The first graph shows a significant uptick in NEM winter demand recorded during the super peak periods in 2025 relative to the last five years.
To be more specific, in January of 2025 Queensland hit a demand record for all time, while New South Wales and Victoria each set records for winter demand. As you can see, the NEM has increasingly moved toward higher winter demand peaks relative to summer peaks, which partly explains the earnings skew toward the first half that we've observed in recent years. In the middle, you can see that AEMO forecasts significant growth in electricity demand across the next 30 years under all ESOO scenarios, and the main drivers of that expected growth are electrification of the home, data centres, transportation, and the broader industry. Looking further into this, the right-hand side shows the forecast material uptick in demand growth driven by data centres that's expected in the coming decade, driven by rapid growth in domestic data centre development pipelines, particularly in New South Wales, Victoria, and the ACT, with significant supply required to meet this demand. Overall, our transitioning energy portfolio, and particularly our growing flexible asset fleet, is very well positioned to manage and leverage the upside of rising and reshaping customer demand. To conclude with market conditions before I hand over to Gary, this slide shows the observable curves for both swap pricing as well as the cap curves.
In Victoria, the forward curves are still flat, while in New South Wales they have softened over the past 10 weeks, and I have already discussed the factors behind the unusually low volatility seen in the first half. Broadly speaking, AGL is substantially hedged for FY 2027, and importantly, the present forward curves do not reflect the favorable longer-term electricity demand tailwinds I mentioned earlier, particularly since a great deal of recency bias is built into near-term forward pricing. Now I will hand things over to Gary.
Thanks, Damien, and good morning, everyone. It's great to be with you today to share our very strong operational and financial results, which put us in a position to keep pursuing our strategy of reinvesting cash flows back into strong generating asset returns. This slide gives an overall summary of our financial results, and I'll go into more detail on the slides that follow. As Damien said, our strong first-half financial result reflected better operational performance, with underlying NPAT of AUD 353 million and EBITDA at AUD 1.09 billion. As we said earlier, we had higher customer market earnings along with stronger fleet availability and flexibility and increased battery earnings, which helped offset the impact of unusually lower market volatility in the NEM. As we expected, EBITDA stayed flat and underlying profit was lower because of higher depreciation and amortization and finance costs. Today, we've announced a fully franked interim ordinary dividend of AUD 0.24 per share, in line with our targeted 50%-75% payout ratio of underlying NPAT for the FY 2026 dividend. AGL also currently expects to pay a fully franked dividend for the full-year. I'll talk about our improved cash performance shortly, and one of the main drivers of the higher net debt was investing cash outflows as we push ahead with the transition of our business.
That covered spending on the Liddell battery and the Kwinana turbines, plus buying South Australia's virtual power plant for about AUD 80 million. The key point is that our substantial investment growth — especially the near-term emphasis on firming assets — is meant to keep going, and right now it's producing high-quality earnings for AGL along with robust cash flow conversion as the business goes through its transition. On top of that, our deal to sell our equity stake in Tilt is a clear illustration of how we recycle capital when the timing is right and it's prudent to do so. We expect settlement in the third quarter, and we expect the proceeds to be redeployed toward our firming projects while giving the balance sheet extra flexibility. We are also looking into options for future funding vehicles to support deployment of a 2 GW+ wind farm portfolio. Before I go further, I want to mention that we have reviewed and restated our accounting concerning the classification of a number of renewable PPAs. The net effect on the balance sheet is immaterial. In addition, cash flow is unaffected, and there are immaterial impacts on underlying profit and on our credit metrics. Let me begin by walking you through underlying profit in more detail, starting on the left-hand side. The stronger performance in customer markets came mainly from margin growth across the consumer electricity and gas portfolios.
The increase in consumer electricity gross margin came from adding customers and from managing customer value in a disciplined way. Growth in consumer gas gross margin resulted from margin initiatives and from larger volumes that colder weather helped drive. That growth bar shows the first earnings contribution from South Australia's virtual power plant, which we bought from Tesla last July, along with earnings from battery hardware sales, which government initiatives have supported. Because we keep concentrating on disciplined cost management, customer markets OpEx came in lower thanks to continuing initiatives that deliver operating model benefits, partly offset by greater net bad debt expense stemming from revenue increases. Looking further to the right, even with stronger fleet availability, integrated energy earnings took a hit from lower qualified generation volumes and from a smaller amount of volatility captured than in the prior half, which was a stretch of unusually high volatility. The positive AUD 10 million bar for batteries reflects a full six months of Broken Hill battery operation, since that battery was being commissioned during the prior half, and also reflects stronger performance from the Torrens battery. As I'll mention shortly, we're highly pleased with how strongly our 300 MW operational battery fleet has continued to perform, contributing AUD 35 million in EBITDA for the half, which is a very strong financial result.
Moving on with how we manage costs, the OpEx gain at integrated energy came from fewer unplanned qualified outage days than in the previous half, from the sale of the Surat gas project, and from savings delivered by productivity and optimization programs. Central managed expenses rose slightly, mostly because of IT hardware and software spending as we keep putting money into our technology products and capabilities. When we reported full-year results, we flagged an uplift in depreciation and amortization for FY 2026 of roughly AUD 100 million. That rise stems mainly from our ongoing investment in thermal assets whose useful life is getting shorter, from growth that includes the anticipated start-up of the Liddell battery, and from a larger rehabilitation asset base. Please note we are now lowering our estimate of those depreciation uplifts by AUD 40 million, to about AUD 860 million; part of that comes from a continuing decline in environmental rehabilitation assets, chiefly at AGL Loy Yang, following confirmation of bulk water entitlements costs. Higher finance costs were mostly the result of a larger net debt position as we continue the transition of our business. And lastly, lower income tax paid mirrored the drop in underlying profit before tax.
Originally, back in August, we guided to a 3% rise in FY 2026 operating costs. But thanks to a disciplined focus on cost, we're tracking better than we first expected and now forecast an increase of just under 2%. We expect the effects of inflation in FY 2026 to be more than offset by the significant and accelerated productivity initiatives that have been implemented across the organization. Today we're also providing further detail on our cost out program in FY 2027. That program is targeting an overall sustainable cost benefit of AUD 50 million per annum after CPI, with CPI again expected to be fully absorbed by productivity benefits in FY 2027. Briefly touching on CapEx. In line with our strategy, approximately AUD 760 million is expected to be spent on growth this year, with the majority of capital deployed to advance our high-returning firming projects being approximately AUD 650 million. This growth outlay is expected to comprise roughly AUD 190 million for the remaining project costs for the Liddell battery, with first operations and revenues expected in the third quarter. In addition, it includes approximately AUD 360 million of the estimated AUD 800 million total project cost for the Tomago battery, with the bulk of the remaining spend expected in FY 2027.
When it comes to the Kwinana turbines, roughly AUD 85 million is expected to be spent in FY 2026, and then the rest of the spending in FY 2027 comes to approximately AUD 100 million. On top of that, growth spend in customer markets is going to be aimed at expanding our energy as a service offering for commercial and industrial customers, along with electrification solutions. That sizable investment in growth is what really unlocks future value for the business. Please note that the FY 2026 sustaining CapEx forecast has not changed since August. As I said earlier, our 300 MW operational battery fleet keeps delivering excellent performance, contributing AUD 35 million of EBITDA for the half. That comes even though we saw a stretch of unusually low volatility in the NEM during the half. Taking 30 months of performance from FY 2024 through half year 2026, the Torrens battery is producing an excellent annualized yield of 24%. To be clear, that figure is annualized EBITDA divided by the total project CapEx costs of AUD 189 million. With the strong operating performance of both the Torrens Island and Broken Hill batteries, we remain confident in targeting the upper end of our 7%-11% IRR range for our grid-scale battery projects, noting that these are ungeared post-tax asset level returns.
Just as a reminder, we have 1,000 MW of projects currently under construction, and those are expected to come online in the years ahead. Full operations for the Liddell battery are expected to begin in the fourth quarter of FY 2026. That covers the full 500 MW, and commissioning of the first 250 MW is targeted for the third quarter. The Tomago battery should begin operations in late 2027. The graph displays actual and expected earnings for existing and committed projects only — and note that we have a few additional late-stage battery projects that we're focused on, which I'll cover on the next slide, and each of those is expected to take roughly two to three years to build once FID has been reached. This substantial investment in firming assets is intended to deliver high-quality earnings for AGL, along with strong free cash flow conversion as the business transitions. Importantly, we keep advancing our development projects and pipeline, which now sits at 11.3 GW. We have excellent optionality in that pipeline and aim to deliver projects with the best strategic fit and expected returns that exceed our hurdle rates. On the left-hand side, you can see the priority late-stage battery and wind projects that we're focused on, including the 500 MW Tuckeroo battery in Queensland and the development of wind farm and battery projects for the Pottinger Energy Park alongside our joint venture partner, Someva Renewables.
I'm glad to report as well that we are looking at potential future funding structures to support building out a portfolio of wind farms of 2 GW or more. Since 2016 we've gained substantial expertise in capital partnering alongside Tilt to speed up delivery of wind and solar generation across Australia, and we expect to give the market an update at the appropriate time. Please be aware that AGL has ceased work on the Gippsland Skies offshore wind project. Moving on to cash performance, where the headline was better underlying cash flow and cash conversion, I'll take you through a few of the main movements. Underlying operating free cash flow came in AUD 24 million higher, primarily because of the unwinding of government bill relief provided to customers during the prior corresponding period, partially offset by more margin calls during the current period. Most of the significant items stem from ongoing delivery of the retail transformation program, and other investing cash flows take in the acquisition of SAVPP for roughly AUD 80 million. At the bottom of the screen you'll see that operating free cash flow, once the effect of bill relief timing is excluded, rose AUD 9 million, mostly because of reduced income tax payments, partly offset by greater sustaining capital expenditure on our thermal assets aimed at preserving availability and reliability in a market that is transitioning, as this half has demonstrated.
On a positive note, our cash conversion rate—leaving out margin calls, rehabilitation, and bill relief timing—rose three percentage points, reaching 93%. Before handing things back to Damien, I'll wrap up by covering net debt, credit metrics, and the strength of our funding position. On net debt, a major factor behind the rise was about AUD 320 million spent on growth and strategic acquisitions—expenditure that covered the Liddell battery, Kwinana turbines, and the SAVPP acquisition. Additional drivers included AUD 168 million in fully franked dividends paid out to shareholders, plus sensible spending on asset flexibility and availability. Just as importantly, our Baa2 investment-grade credit rating is intact, with room against covenants. Now looking at the right-hand side, funding is still solid after we successfully issued a AUD 500 million AMTN in September across seven and 10-year tenors. That issuance drew more than 10 times oversubscription—a great result that marks AGL's comeback to the public bond market following 10 years away, and further proof of wide lender backing as we keep executing our business strategy and decarbonization plans. Liquidity is in good shape too, at close to AUD 1.2 billion in cash and undrawn committed debt facilities.
The average tenor on our debt has gone up slightly, and nothing significant comes due before FY 2027. We also expect the proceeds from the Tilt divestment to close by the third quarter, which gives us balance sheet flexibility and a funding source for our firming projects. Thanks, and back to Damien.
Thanks, Gary. I'll wrap up now with our FY 2026 guidance. As I said earlier, we've tightened the ranges for FY 2026 financial guidance, reflecting a strong first half powered by better consumer margins. We now expect full-year operating costs to come in below what we previously indicated, thanks to disciplined cost management, and depreciation should also be lower than we indicated last August, given greater certainty on water prices for the future rehabilitation of the Loy Yang mine. As expected, earnings are weighted toward the first half, consistent with the usual seasonality of customer gas and electricity demand, along with the gradual roll-off of lower-price legacy gas supply contracts. Importantly, we're also targeting AUD 50 million in sustainable net operating cost reductions in FY 2027. All in all, it's been a great first half. Thank you for your time, and I'll now open it up to any questions.
We’re now ready for questions. If you’d like to ask one, please press the star key and then the number one. Before you ask over the conference line, could you mute any other devices you may have? We’ll handle one question at a time, and if there’s time available, we’ll come back around for additional questions. Our first question is from Tom Allen at UBS. Tom, please go ahead.
Thanks, James. Good morning, Damien, Gary, and the wider team. To begin my question, I'd note that over recent months many investors have been asking about how the weaker wholesale price outlook now reflected in futures markets will affect things. AGL's result today, then, shows that your electricity portfolio is still in the money, with realised price premiums that are stronger relative to average prices, and the batteries are doing well even though volatility has been below average. So my question is this: can investors have confidence that, as long as AGL keeps generation availability strong, there is upside risk to present market estimates for underlying EBITDA over the medium term, which are presently projected to be roughly flat across FY 2026 to FY 2028?
Thanks, Tom. Good morning, everyone. Let me unpack that question a bit. What I'd say is that we have observed a softening in the New South Wales market over the past 10 weeks. I wouldn't characterize that as any kind of structural trend. Conditions during that stretch featured quite mild weather along with solid generation. My description would be that winter has become the new summer. That's genuinely the case. And the volatility we experienced was truly atypical during the first half. We highlighted 4.4 hours, an incredibly low figure for that first half. In January alone, within a single month, we recorded 4.7 hours. So we view it as a return to cyclical norms, so to speak. The other major factor driving all of this is demand. Demand will play a significant part. Across the first half we saw multiple records set in three states, so that peakiness in demand is going to persist. That's the basis for our confidence. On your question about the asset itself, we're very pleased. Precisely as we told the market back in August, we anticipate better availability.
When you consider those assets and how they operate, commercial availability matters enormously as well, along with the flexibility we're able to extract from our entire portfolio—not only the coal assets. As our results show, that adaptability genuinely allowed us to achieve a robust outcome on the generation side.
Alright, Damien — appreciate it.
Appreciate that, Tom. Moving on, Henry Meyer of Goldman Sachs is our next questioner. Henry, the floor is yours.
Morning, team. Appreciate the update. First off, I was hoping you could walk us through what's behind these PPA restatements to leases. Would the AUD 45 million EBITDA benefit from last year hold fairly steady in 2026? I'm just trying to break down the guidance increase — how much of it comes from the accounting change versus how much is underlying.
Okay, thank you, Henry. So to start, we've clearly chosen to restate how those legacy PPAs are accounted for. The key point is that cash is completely unaffected, and the effects on the P&L, the balance sheet, and equally important, the credit metrics, are very immaterial. You're able to see the adjustments in the prior period comparisons, and you cited a few figures. What I can tell you about the current period is that those adjustments to the numbers are extremely immaterial and definitely far smaller than what we saw in the prior period. So from our standpoint, they're very immaterial, and that ought to be taken into account. There is a bit of shifting geography to these adjustments. On the balance sheet, in effect, we have reversed a portion of the onerous provision and set up a matching lease liability and right of use asset. But once again, you can see the balance sheet impact is very immaterial as well.
All right, thank you, Gary.
Thank you, Henry. Our following question comes from Anthony Moulder at Jefferies. Anthony, please proceed.
Yes. Morning, Damien. I wanted to pick up where Tom left off, since it sounded as though the interconnector problems are going to get fixed. At some stage we'll have an improved interconnector with South Australia. Demand keeps rising, as we all are aware. Volatility will remain present. That expectation you have of elevated volatility — where does it stem from? Is it coal generation exiting? That appears to be more of a longer-term matter. I'm simply trying to grasp the confidence you hold regarding that elevated volatility over the nearer term, prior to that coal generation eventually departing, please.
Right, absolutely. So in the deck we put in a few slides, and slide 13 is likely the one to look at. First, you can simply observe that HY 2025 was a period of very high volatility. HY 2026 was unusually low. In that half we also saw fewer transmission constraints. Then, looking into H2, if you check where the trend is pointing, those trends tend to be higher in H2 as well. So our confidence isn't really that there won't be different periods with somewhat higher volatility and somewhat lower volatility. It's over the cycle. We see volatility in the system. That's how the system was designed. And as both new assets come in and new assets come out, we'll see that volatility continuing to play through the marketplace. And we see HY 2026 as unusually low.
Just to pick up on that point, are you not observing any decrease in volatility as additional households adopt batteries and solar, and once that interconnector is restored to service?
I mean, when you consider what this market actually needs, it comes to nearly 45 GW of additional battery capacity. That's a massive requirement, and today there are about 10 in the market. So a tremendous build-out is needed over the coming 10 years. And on top of that, as assets leave the market, you'll see that volatility keep moving through the cycle. So I'd say battery volatility will remain a factor. That's the reason we keep putting money into large-scale batteries, since we believe those batteries still hold tremendous value, and we're making solid progress on getting more of them online.
I appreciate it.
Thanks, Anthony. Moving on, we have Ian Myles of Macquarie. Please go ahead, Ian.
Nice transition. Congratulations on the outcome. Could you expand a little more on the batteries? You’ve mentioned firm batteries becoming available for 12 months now, and you actually haven’t reached an FID. I’m somewhat curious about what gets you to that FID. And I’m also somewhat interested in the government batteries appearing at the retail level. Are we seeing any kind of retail-level implications for demand growth, since they would likely replace some of the need for grid-scale electricity?
Yes, thanks Ian. So to unpack that question, the first part concerned firm power. We're still making really strong headway on that portfolio. Nothing has reached the market as of yet. The way I'd frame it is that we're applying strict capital discipline to deliver the appropriate batteries into the market at the appropriate moment. That isn't to say we won't deliver any from firm power. Right now we have a number in the pipeline. The ones we're clearly taking to market first are Tomago and Liddell. Those were the furthest advanced, though we'll keep going. I think the answer is that over time you'll see some of those batteries join the portfolio. We have an enormous amount to build across the coming, what is it, three to four years. And so you'll see us steadily moving those through depending on where we believe we can achieve the best returns in the best segment of the market. Then turning to the second part of your question, which concerned the consumer, interestingly, and what has it been? I'm not sure, 250,000-odd batteries at this point. What we've observed in certain instances, which I think is equally interesting, is that a number of those customers wind up consuming more energy because of this.
What we really need in the system, then, is the capability to coordinate those batteries so that value ultimately gets shared between the customer and the system, and also so we can help manage some of that demand. In my view, both residential batteries and grid-scale batteries are going to play a part. That's why, when I look at Jo's customer business, we're currently outperforming when it comes to the number of batteries. We're both signing contracts and adding customers to the VPP. Back in December — I believe it was December — we made a big change that lets us connect far more batteries into our systems. Previously, that was fairly limited. So now we're seeing many more people connect. The focus now is on making this as simple as we can for our customers. The transition is complex, so we want to ensure it's simple for them, and that they also capture that value from the battery along the way.
Alright. Thank you, Ian. Moving on, Gordon Ramsay of RBC is next. Please go ahead, Gordon.
Much appreciated, and well done to Damien and the leadership group on a solid outcome. My question concerns your cost reductions and how you're positioned against low negative pricing. How much has Bayswater's two-shifting approach contributed to cutting costs and shrinking exposure to stretches of low and negative prices, and in what way will availability across the asset fleet get better over the second half of FY 2026?
Thanks, Gordon. So, let me begin with the cost side of things. We've clearly announced today that we're targeting AUD 50 million net — and to be clear, that's a net cost reduction by FY 2027. What I mean is that this figure comes after inflation is absorbed as well. So it's a substantial number. It spans both labor and non-labor right across the entire organization. It's never easy to pull off, but we're progressing well, and even in this half we're beginning to see the benefits flow through, and you'll see the full-year benefit by FY 2027. On your question about Bayswater specifically, we're still running the two-shifting trials, and we'll keep at it. We're having some real success. The team is performing excellently. We've done quite a few trials — honestly I've lost count now because there have been so many. For us, it's really about getting our hands on all the data and all the information at this point. That way, from both a trading standpoint and an operational standpoint, we can optimize when those assets come out of and into the system. On the last one we ran, I believe we came in and out within 30 seconds of our target time.
That's quite impressive for large equipment of that kind. But once more, we remain in the pilot stage. I think the way to consider assets such as these, both Bayswater and Loy Yang, is that optionality will exist around two-shifting. Optionality will exist around mothballing. Optionality will exist around sweet spot running. Those are all the kinds of things we're working through. So as you move into the coming five, 10 years, you're genuinely making choices about how you operate the assets quite differently, but you have the data supporting it. Because to your point, what's critical, and as we said at the full-year, is getting asset availability to where we want it to be. You saw that show up in the half, which was great to see. We see further improvement into the second half. And that's all about the investment we're making in the assets, both on availability and flexibility. So we'll keep seeing improved performances in the fleet.
Thank you. Thanks, Gordon. Rob Koh from Morgan Stanley has a further question for us. Please go ahead, Rob.
Yeah. Good morning. Let me add my voice to those congratulating you on the result. I’m not sure whether your whole management team is with you there. I thought we might try to pose a question and let some of the other team members have a chance to speak. I suppose my question has to do with what Mr. Brown mentioned about a new 2 GW wind vehicle potentially coming to market. Could you perhaps give us some color on that in terms of what kind of PPA prices you are seeing? Does AGL need to provide capital to that vehicle? What kinds of things do you need to see to reach FID on new wind farms at this point?
Robbie, you suggested I stick with hearing my voice. I'll go straight to Gary.
Oh, goodness. That wasn’t what I meant at all.
Hi, Rob. Look, this is really at a very early, preliminary stage regarding the possibility of a funding vehicle. So we're currently exploring that. And if you think about it, we have a number of wind projects that are very exciting opportunities — one of them has already had a CIS awarded to it — which are, hopefully, coming to FID within the next, let's say, 12 to 24 months. So we've flagged previously that we would be examining funding capital opportunities for those. So as I said, it's early days, but we would be looking to bring a strong, high-quality funding partner into a potential vehicle. We'd likely take a small equity stake in that, but ultimately we'd really be looking to partner with someone with a low cost of capital. It's difficult to talk about what PPA prices are. It's far too early, but as you'd expect, they would typically be market-driven type prices.
Alright, thanks a lot. If I could perhaps slip in one more question along similar lines, regarding your spending at Kwinana — you've provided the figures for the turbine costs. My assumption is that FID hasn't been reached yet, but might you be able to give us some indication of the balance of plant cost we ought to be considering?
Rob, at this moment I’m not going to provide that. We’re still working our way through it. We’re genuinely optimistic about WA and the growth in that market. Let me just say watch this space as we keep working through it. You’re right. We’ve given you the engines. We haven’t given it to you all yet, but we’ll keep watching that space because I think the growth in WA with both the peaker and Waddi Wind Farm and that business, we’re really excited about what we can do over there. So I’ll come back to you at another time.
Yes. All right. That's fine. Thanks a lot.
Appreciate that, Rob. Moving on, Dale Koenders from Barrenjoey is next. The floor is yours, Dale.
Good morning, everyone. First off, regarding that AUD 50 million cost-reduction initiative, I'd like some clarity on slide 20, where the forecast shows that cost increase for 2026. Should we take it that FY 2027 costs then come to AUD 1,780? Is that correct, or is part of that cost saving being achieved this year?
Yeah. So the way to think about it, Dale — and I'm partly echoing what Damien said — is that it's a net reduction of AUD 50 million. That's clearly after inflation's effects. So we'd expect to see a reduction of roughly AUD 50 million year-on-year.
About that. All right, on a year-over-year basis. And then when we consider what you said earlier regarding the EBITDA guidance, specifically the flat outlook for EBITDA — that was clearly stated before this cost reduction and before electricity expenses declined somewhat. Should we view those as the two major variables for 2027, and are they still mostly canceling each other out, or are there additional variables we ought to consider?
Let me be very clear on this: we haven’t issued guidance for FY 2027. What I think that discussion was really about was probably consensus compared with the forecast we’ve released. So at this point, we have not given any guidance for future periods.
All right. Could you give us some color on the various factors we ought to be considering? It looks like cost reduction and power prices are in play, along with rising battery earnings. Are there any other elements we should keep in mind?
Yes, I believe that's correct. So first is cost reduction—well, not first, since there's no strict sequence. Second, wholesale electricity price movements will matter. Third, I'd point to the business's continued performance along with how operations and plants are running. That's another factor. And oh, right—sorry, I need to include battery earnings as well. We mentioned that in the prior results too, Dale. Our position remains the same as last August: as batteries come online, battery earnings will exceed the earnings lost from coal and gas. I think it's worth continuing to state that publicly, because battery performance has been surpassing what we expected. The results make that visible, and that's precisely why we keep investing heavily in that area.
All right, thank you, everyone.
Thanks, Dale. We have a final question coming from Henry Meyer of Goldman Sachs. Henry, go ahead.
Thanks, Ian, for doing another one. Beyond the Tomago contract expiry at Bayswater, could you say how you expect Snowy might provide that power, and whether Bayswater would have to back any kind of swaps, or what prices you'd anticipate as that contract rolls?
Yes, thanks. First off, it's good to know the Tomago smelter is going to remain in the system, both from an industrial standpoint and from a people standpoint. We don't yet have any specifics on how that will flow through Snowy. Everything we've gathered from the press suggests it will go through the Snowy vehicle. As for how Snowy can then service that, that's really a question for Snowy. From where we sit, we clearly recognize that we've got one of the lowest cost — we hold the lowest cost generator in New South Wales. So we're well positioned in the market, whether that's Snowy or other opportunities.
Understood — thanks.
Thanks, Henry. Since nobody else has anything to ask, that brings our question-and-answer portion to a close. Thanks to all of you for tuning in.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete AGL Energy Limited transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to AGL Energy Limited earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.