AirJoule Technologies Corporation (AIRJ) Earnings Call Transcript & Summary
May 15, 2026
What were the key takeaways from AirJoule Technologies Corporation's May 15, 2026 earnings call?
In the first quarter of 2026, AirJoule Technologies Corporation reported a net loss of $49.8 million, significantly impacted by a noncash impairment charge of approximately $55 million related to its joint venture. Despite this, the company is progressing towards commercialization with the operational launch of its first full-scale AirJoule Prime system and strong customer demand across various markets. Management maintained its guidance for modest revenue in 2026, with expectations for more substantial commercial revenue beginning in 2027 as product certifications are completed.
What topics did AirJoule Technologies Corporation cover?
- Commercialization Progress: AirJoule has successfully built and operationalized its first full-scale AirJoule Prime system, marking a significant milestone in its commercialization journey. CEO Matt Jore stated, "We are executing against that plan... we are on course. We developed our technology and are now a product company."
- Customer Demand and Market Opportunities: Management highlighted strong customer demand across various markets, particularly in data centers and residential development. Bryan Barton noted, "We're seeing growing traction for our data center application... opportunities in the residential development space continue to deepen."
- Financial Performance and Impairment Charge: The company reported a net loss of $49.8 million, primarily due to a $63.1 million loss from its joint venture, which included a noncash impairment charge of $55 million. CFO Stephen Pang clarified that this charge "has no impact on cash, no impact on the operational performance at the JV and no impact on our broader commercial trajectory."
- Product Certification and Launch Timeline: AirJoule is on track to complete product certifications for its Core platform by late 2026, which is critical for revenue generation. The company expects to launch the Core AWG variant targeting military and residential markets by the end of 2026.
- Middle East Market Engagement: AirJoule is actively engaging with UAE government leaders to promote its technology for water security, with plans for initial deployments in the region. Pat Eilers mentioned, "UAE leadership has signaled a clear intent to lead on water security through innovative technology."
What were AirJoule Technologies Corporation's May 15, 2026 results?
- Net Loss: $49.8 million (vs $45 million est, miss)
- Impairment Charge: $55 million (noncash charge impacting net loss)
- Cash Position: $31.1 million (sufficient to fund operations through 2027, no debt)
- Revenue Guidance: Modest revenue in 2026 (with more significant revenue expected in 2027)
- Operating Expenses: $3.6 million (includes $0.8 million reimbursed by JV)
- JV Operating Expenses: $5.5 million (reflecting ongoing development and deployment activities)
AirJoule Technologies is making significant strides in commercialization, particularly with its AirJoule Prime system and growing customer demand. However, the recent impairment charge raises concerns about financial health. Investors should monitor product certification progress and customer engagement as key catalysts for revenue growth in 2027.
Earnings Call Speaker Segments
Thanks, and hello everyone. Joining me on this call for our Q1 2026 earnings discussion are Matt Jore, our Chief Executive Officer, Pat Eilers, Executive Chairman, Bryan Barton, Chief Commercialization Officer, and Stephen Pang, Chief Financial Officer. Throughout today's session, we'll be referencing a presentation that you can find on the webcast platform as well as in the investor section of our website. I want to note that a number of the remarks shared during the prepared portion and in the Q&A portion constitute forward-looking statements involving risks and uncertainties that might impact our actual results and plans. Several of those risks lie outside our control and are described more thoroughly in the Risk Factors and Forward-Looking Statement sections of the documents we file with the SEC. While we believe the expectations we express rest on reasonable assumptions, they don't serve as guarantees of future performance, and actual results or developments could differ materially; at this point I'll hand things over to Matt Jore.
Appreciate that, Tom. Hello everybody, and thanks for being here on the call covering our Q1 2026 results. When we spoke on the previous call back in March, we described 2025 as a period in which we laid the groundwork for commercialization by way of the first deployments at our joint venture alongside GE Vernova, while 2026 would be the period where we transition away from those standalone deployments toward selling products on a commercial basis. That plan is what we're carrying out. So far in 2026, we've moved forward with discipline on the AirJoule Core platform, finished constructing our inaugural AirJoule Prime full-scale system at the facility we operate in Newark, Delaware, and kept pushing customer engagements forward as we build the commercial pipeline for 2027 and the years after. Before I get into the specifics of that progress, let me take a moment on the macro picture. The water resilience tailwinds we've talked about on earlier calls haven't eased up. If anything, they've picked up speed. Each quarter, water scarcity becomes a more central piece of industrial planning. Lately, several hyperscalers have walked away from data center projects worth multiple billions of dollars because communities opposed them over water access. Investors managing assets worth more than $1 trillion — institutional ones — have pressured those very companies to reveal, site by site, how much water they consume. The signal to the broader market is unmistakable when the world's largest cloud providers walk away from projects of that scale over water access. This year, data center moratorium bills have appeared in no fewer than 12 U.S. states. According to documentation from Bloomberg, approximately 2/3 of American data centers constructed since 2022 are located in regions already experiencing quantifiable water stress. Water demand from compute and infrastructure keeps accelerating, alongside drought and regulatory strain — none of it is letting up. That is precisely the challenge AirJoule exists to address. Now let's talk about where AirJoule comes into play, especially when it comes to data centers. The industry deserves credit for the progress it's made in reducing water use. Closed loop systems, direct to chip cooling, and steady gains in Water Use Effectiveness, or WUE, all represent genuine advances. Among the most sophisticated hyperscaler facilities, the top water usage effectiveness numbers you can find today are roughly 0.1 liters per kilowatt hour. Since those campuses run at hundreds of megawatts, or possibly gigawatts, the overall volume of water they consume is still significant and requires major permits. Beyond the initial fill required to charge the system, there are continuing demands for replenishing closed loops, adding humidity, and meeting domestic needs. Even data centers with top-tier efficiency still go through millions of gallons, and AirJoule can lower their reliance on several sources and aquifer rights by producing water on-site. Looking at what we've accomplished in 2026 up to this point, starting with productization: we made our AirJoule Core platform more capable and longer-lasting by methodically refining how air moves through it, how heat is handled, and the coating applied during the contactor process. At this stage, the core design is basically finalized. On the certification side, our UL and water quality efforts have moved ahead, which puts our systems in position to meet even the toughest regulatory requirements. Bryan will share more on that in a moment. As for our flagship Prime platform, the inaugural full-scale AirJoule Prime unit has been finished at the Newark, Delaware site and is currently operational. That's a major milestone. From the outset, Prime was built with scalability as a core consideration, and we'll explore that further shortly. Turning to commercialization, we're experiencing robust customer interest across a key set of markets, and Bryan will detail where we are expanding our most active engagements; as for the balance sheet, our combined cash position carries our operations through 2027 with zero debt, and Stephen will give you further specifics in a moment. Here's the key takeaway: we remain on track. Having built out our technology, we are now a product company. The way we're organized internally reflects that: we have strong leadership on the product engineering side, and every work stream is connected to a product roadmap. What we're doing over the course of this year lays the groundwork so that in 2027 and the years that follow, we can build a commercial pipeline at scale. At this point I'll pass things along to our Executive Chair, Mr. Pat Eilers.
Thanks, Matt, and hello everyone. Before Bryan takes us through the product and commercial side, I'd like to give you an update on governance as well as what's happening in the Middle East. Our proxy statement, which we filed on April 15th, disclosed that as of May 28, 2026, Max Baucus will be leaving the AirJoule Technologies Board of Directors; I want to extend the whole board's thanks to Max for what he has done for the company. While representing Montana, Max completed six terms in the U.S. Senate, and he also held the post of U.S. ambassador to China. From the time we formed the company, he has been an outstanding director. His deep background in public policy, international affairs, and industrial strategy proved enormously valuable as AirJoule grew into what it is now. We appreciate everything he has given us and wish him the best going forward. I'm happy to report as well that Stu Porter has taken on the position of Lead Independent Director of the Board and will additionally chair our Nominating and Governance Committee. Since the company's formation, Stu has been an active, engaged director, and his guidance in these new capacities will reinforce our governance and help along our path to commercialization. Now for the Middle East: worries about water security keep mounting there, since the region relies on desalination. AirJoule is still working closely with government and regulatory figures in the U.A.E. to spread understanding of how our technology, through distributed AirJoule placements, can strengthen the resiliency of water infrastructure. Leaders in the U.A.E. have made clear they intend to lead on water security by adopting innovative technology. In our view, the AirJoule value proposition fits well. Our route to commercialization in the Middle East starts with the first proof of value installations at prospective clients in the U.A.E. From there, we intend to scale throughout the U.A.E., the wider GCC, and Global South markets able to benefit from those reference deployments. Over the rest of 2026, we anticipate raising AirJoule's profile at influential industry and thought leadership gatherings, frequently alongside the Global Climate Finance Centre, Masdar, and the UAE Ministry of Foreign Affairs. All of this builds toward our taking part in the UN Water Conference, co-hosted by the U.A.E., in Senegal, in Abu Dhabi in December 2026. I'll hand things to Bryan now for our product and customer progress.
Appreciate that, Pat. There are four things I'd like to cover this morning: our AirJoule Core platform, which comes in two product variants, our first AirJoule Prime build, and our commercial engagements; after that, I'll wrap up with a quick view of the remainder of 2026. Turning to the AirJoule Core platform: back in 2025, we intentionally chose to concentrate our build efforts there, since AirJoule Core and AirJoule Prime rely on a shared sorbent chamber architecture — meaning each AirJoule Core installation also reduces risk on the route to AirJoule Prime. During this year, we've enhanced how the AirJoule Core system performs and holds up by optimizing it systematically in three respects: airflow distribution, thermal management, and contactor coating. The first generation AirJoule Core design is now locked. Minor dimensional tweaks could still come as manufacturing is finalized, but the form factor we have is one we can scale. Updated product spec sheets are now posted on our website, airjouletech.com, and anyone curious about the technical specifications should take a look. We intend to bring the Core platform to market in two product variants aimed at two distinct markets. First is the AirJoule Core AWG variant, with a targeted commercialization launch of late 2026. Core AWG's primary customer focus is the U.S. military and small residential deployments. With the U.S. military, we're working together via our existing Cooperative Research and Development Agreement, or CRADA, alongside the U.S. Army Engineer Research and Development Center. That CRADA combines AirJoule's waste heat to water platform with ERDC's tactical water recovery research to provide resilient water supply solutions for forward deployed personnel. The second variant is the AirJoule Core DH, with a targeted commercial launch in 2027. Core DH is materially the same product as Core AWG. It's the same hardware, optimized through process configuration and controls for dehumidification application. This variant targets the global installed base of conventional desiccant wheel dehumidification systems for humidity control between 30% and 50% relative humidity. Let me take a moment on the dehumidification opportunity, since this marks the first time we're presenting concrete performance data publicly. AirJoule's metal-organic framework sorbent regenerates at 60 to 70 degrees Celsius, versus 120 to 150 degrees needed for conventional desiccant wheels. That gap is fundamental. It makes heat pump-driven regeneration possible instead of electric reheat or natural gas. Our initial performance data indicates up to roughly 40% energy savings compared with incumbent desiccant wheel technology in our target operating ranges, and we anticipate additional gains over the coming few quarters as we head toward the product launch. Our initial target markets for Core DH are dry storage and cold storage facilities operating between 30% and 50% relative humidity. Last year, we announced an MOU with a defense contractor to collaborate on this dehumidification application. This engagement has shaped our Core DH development, and we expect other markets and applications to follow; now let me hand things over to AirJoule Prime. Like Matt said, we've reached a significant milestone: our first full-scale AirJoule Prime system is finished and running outside at the Newark site. On the upcoming earnings call, we'll share a substantive update regarding how it performs. From the very beginning, the AirJoule Prime was designed with scaled manufacturing in mind. Inside the Prime are 16 vacuum chambers, procured cheaply from well-established vendors, while the rest of the bill of materials consists of off-the-shelf parts like valves and pumps. The sorbent-coated contactor stands as the sole bespoke piece, and we build it ourselves. Prime's overall design is now locked. Going forward, only sorbent-level enhancements and fine-tuning of individual components will occur. Everything we did throughout 2025 to optimize Core — especially thermal management and airflow — fed straight into how Prime was designed, and we expect that to carry over into Prime's performance. Prime is designated or designed to deliver up to 2,000 L per day or less than 200 Wh per liter when paired with low-grade waste heat, with a maximum power draw of just 12.5 kW and configurability across waste heat sources from 60 degrees Celsius and above. In the coming months, we'll keep optimizing this system in Newark; this initial Prime unit is slated to be deployed in Europe through our Net Zero Innovation Hub collaboration; meanwhile, we're constructing a second Prime system that will act as our in-house showcase unit at the Newark facility, aiding customer demonstrations and proof of value engagements all year long. On the certification front, we'll seek UL certification for AirJoule systems covering electrical components, whereas water quality certification gets handled case by case, subject to what customers need and where they're located. Notably, FDA bottled water standards are already satisfied by our products, and they will also comply with California water quality standards — the toughest regulatory benchmarks in the U.S. Our view is that engineering for compliance with the most demanding applications leaves us well positioned throughout the remainder of our addressable market. Now let me shift to customer engagements that build a commercial pipeline in 2027 and beyond. Starting with hyperscale data centers. As discussed before, AirJoule's value proposition for data centers is that we can utilize low-grade waste heat to produce pure distilled water on-site. Generating water on-site provides operational resilience and bolsters water stewardship and community license, things hyperscale operators increasingly require. Right now we're collaborating with a leading hyperscale operator on a thorough evaluation of AirJoule Prime's economic and technical performance at specific data center sites. That effort has sharpened our grasp of the value AirJoule can provide when tethered to waste heat. Drawing on that grasp, we recently released a white paper laying out AirJoule's economic advantages for both water-cooled and air-cooled data center configurations. By generating distilled water on-site from atmospheric humidity, AirJoule can help ease water permit constraints affecting new data center construction. Since a 100 MW data center has the potential to produce $3 million-$5 million each day, <<inaudible>> Net Zero Innovation Hub for Data Centers. Reusing waste heat from data centers has become a significant regulatory priority across Europe under the EU Energy Efficiency Directive, and we're having close discussions with the members of that consortium to meet that need. As mentioned earlier, our inaugural Prime unit is scheduled to be deployed in Europe alongside the Net Zero Innovation Hub to show how AirJoule integrates into a data center and can turn waste heat into pure water. Next, residential development. We're expanding a co-development framework alongside a global partner focused on water-scarce U.S. residential markets in the U.S. Southwest. The Southwest is increasingly a place where residential development projects face restrictions because of insufficient water security. Our AirJoule platform tackles that limitation head-on, and in the first quarter, we finished deploying an AirJoule Core system at the Red Dot Ranch Foundation site in Pescadero, California. That pilot confirmed off-grid water generation supporting Red Dot Ranch's climate positive housing development. Third, water delivery and truck distilled water. The worldwide water distribution market comes to roughly $50 billion, and across many U.S. markets, distilled water goes for more than $1 per gallon, pushed not by raw supply, but by the logistics of trucking water from distant wells to the customer. Working with a waste heat partner, AirJoule's waste heat to water economics can bring operating costs to under $0.10 per gallon, placing us well in this supply chain. We have early-stage discussions in progress with waste heat providers, distributors, and end users regarding potential future collaborations. Last, the Middle East. In January, we announced an exclusive distribution agreement with TenX Investment covering six Gulf countries: the U.A.E., Oman, Qatar, Saudi Arabia, Bahrain and Kuwait; we're pacing deployment activity to match regional conditions and the availability of production-ready hardware later in 2026. Bringing it all together, we're enthusiastic about the opportunities in front of us; we're witnessing growing traction for our data center application. Opportunities in the residential development space keep deepening with our co-development partner, and the launch of our dehumidification product is drawing customer interest. Through the remainder of 2026, we will finish commissioning our first Prime system at Newark and get ready for its deployment in Europe through the Net Zero Innovation Hub. We will deliver our first commercial Core systems; we will release additional dehumidification performance data and expand customer engagements for the Core DH variant; we will keep building the deployed base and contracted customer relationships that underpin scaled commercial activity in 2027; with that, I'll hand it over to Stephen for the financial update.
Thanks, Bryan. I'll take you through the financials for Q1 of 2026, then share some perspective on where we see the outlook and our liquidity. But before I get into operational highlights, there's one item in the results I should address. We booked a non-cash impairment charge of roughly $55 million, and it runs through the equity method investment line for our AirJoule JV. That comes after the adjustment we made last quarter and, same as that one, it's accounting related. Normally we assess the fair value of that JV investment once a year, but because our share price fell last quarter, we ran an interim assessment. Since the test is measured at quarter end, and on that date our share price sat at a trough, the assessment produced a write down for the quarter. Worth noting: since the period closed, our share price has come back meaningfully. I'd also like to emphasize what hasn't changed. There's no effect from this charge on cash, none on how the JV operates, and none on our wider commercial trajectory. As you've heard on this call, the JV's technology development, its customer pipeline, and its progress against milestones all continue tracking in line with what we expect. Now to our financial results: for Q1, AirJoule Technologies reported net operating expenses of $3.6 million. That figure includes $0.8 million of administrative and engineering expenses the JV reimbursed to us under a statement of work. Our net loss for the quarter came to $49.8 million. The biggest piece below the operating line was a loss from investment in AirJoule JV of $63.1 million, mostly due to the impairment I just described. That's partly offset by a $14.7 million tax benefit. Back to the joint venture: total JV operating expenses for Q1 were about $5.5 million, and during the quarter the JV got $10 million in capital contributions from AirJoule Technologies to back ongoing productization, manufacturing, and commercial deployment activities. AirJoule Technologies closed Q1 with $31.1 million of cash on the balance sheet. Cash across the systems combined with the JV totaled $35 million, with no debt. For the full year 2026, our guidance on cash spend at both AirJoule Technologies and the JV is unchanged from what we gave previously. Our liquidity is enough to fund our operations, the JV, and our planned commercial deployments through 2027. Going forward, we anticipate modest paid deployment revenue at the JV in 2026, with commercial revenue becoming more meaningful starting in 2027, once our Core product finishes its certifications and our first Prime deployments also come online. We keep strong flexibility when it comes to managing our capital position and balance sheet. We'll also stay opportunistic and disciplined as we evaluate any financing and strategic opportunities that strengthen our balance sheet and support long-term value creation. With that, I'll hand it back for the Q&A portion of the call.
Thanks. Morning, all. Appreciate you fielding my questions. Congrats on having the first completely assembled unit ready. I suppose my question is fairly simple. What's needed at this point for customers to perhaps go ahead and commit to orders for these units? Is some kind of pilot deployment required before they put in bigger orders? If you could take us through how the sales process works from this point to possibly getting these into the field. Thanks.
Appreciate that, Amit. We actually see a few distinct paths through which customers can convert. Certain ones want to see pilots. Certain ones feel fine seeing the system running with performance data from the real world. Naturally, there are customers too that are desperate for water, if you will, and are keen to proceed. We're holding a variety of discussions with many different customers, guiding them along that path. Each customer differs regarding what they must see before they commit.
Got it. Thanks. So, as you, uh, make certain adjustments and enhancements to that assembled unit, about how much additional performance gain, and so on, do you figure there is that you might be able to pull out of these levels?
Yes, I'm eager to be in a position to address that more completely. Since the system only became operational today, we're excited to kick off the optimization work and what we refer to as a shakedown of that effort, so we can truly observe the baseline performance and then determine how much farther we can push it through a range of upgrades. Those upgrades could span everything from fine-tuning individual components—fans and pumps, for instance—by improving their efficiencies, to modifications at the sorbent level, which involve things like the thickness or the amount of sorbent contained in each contactor. We should anticipate seeing adjustments and performance gains across the next several months, and we'll give a more substantive update on our upcoming quarterly call.
Got it. Perhaps just one final thing — that unit which is completely put together, could you possibly end up installing it at a customer's location, you know?
Yes.
So you're upgrading it, right?
Yeah, that's a fair question; we're going to go over the specifics of how this unit gets deployed on a later call, and we haven't shared or put out the details concerning that, but deployed it will be.
Thanks, everyone. That's everything from me.
Morning, and congrats on all the progress and the work being done. So, my first question would be: with the Core and Prime designs now stable, could you give us some detail on the plan for bringing unit costs down?
Yes, thanks, Jeff. The main efforts around lowering unit costs are actually taking place across the rest of 2026. These are, as I mentioned earlier, along the lines of sourcing the pumps and fans that offer the best combination of cost, quality, and efficiency, plus certain other components found throughout the system. That effort is underway for Core and getting started for Prime, and we expect to work through a substantial portion of it during the quarters ahead, leading up to the Core AWG system launch at year-end, and then, of course, wrapping the whole process up ahead of the Prime and the DH unit launches. Once we get further along, we'll share a more substantive update; validating the quality and performance of the incoming components will take time, but that represents the large majority of what we're doing.
While we're on this topic, let me also ask: is the sorbent you're currently planning to use already stable, or are you continuing to evaluate other MOFs, maybe ones coming out of research at GIF?
Yes, we are looking at different MOFs as part of our typical research pipeline, so that we have a complete understanding of every sorbent — MOFs and non-MOFs alike — that might influence our core performance. I would say we're agnostic when it comes to MOFs, and our goal is to have the best possible technology in our product. At present, the sorbent we've scaled and can obtain in large volumes at a cost-effective price is doing very well. It sets the benchmark for us, meaning any other material would need to show substantial performance to justify its place in a variant of the product.
This might be a bit, you know, premature, though probably not given how you folks plan ahead. I'm just curious whether you can share what sort of planning or effort is underway regarding the move to contract manufacturing in 2028. Is that still the year you're aiming for? At what point in that year do you anticipate it starting to genuinely ramp up?
Yeah, we've already held the first talks with contract manufacturing assembly houses, so to speak. As we've discussed on, you know, earlier calls and materials, off-the-shelf components make up the bulk of our system. So, you know, there are assembly houses or, you know, contract manufacturing partners that are ideally suited to take our assembly instructions and scale up to deliver the volumes of the Primes and Cores that we require. Those conversations have started. Naturally we're not prepared to reveal or any specifics regarding the full maturity, but we're still making plans for, you know, when that will occur so that we can be ready. 2028 sounds right in terms of like the, you know, the volume scale that we're expecting and into future years. We're really, you know, letting customer pull lead in terms of, you know, volume and then the capability to meet that volume will align.
All right, that works for me. I'll handle the remaining ones separately and hand it back to the queue. Appreciate it.
Thank you, Jeff.
Hi everyone, and thanks a lot for fielding my question — also, congrats on everything you're accomplishing on the path to commercialization. So, given that the Core design is basically finalized at this point, could you walk us through what remains to be finished before the Prime design is locked in? From what I gather, the two systems share essentially identical underlying technology. Is the plan to get a clearer picture of how Core holds up in real-world conditions, and then apply what you learn to refine Prime's final design?
Appreciate that, Alex. Nearly every bit of the engineering work got finished by way of the Core, since it's really the same sorbent chamber architecture — we simply placed 16 sorbent chambers into it. As we proceed with Prime, we'll be fine-tuning that core engineering design. We don't anticipate any meaningful engineering changes. There may be certain items as we begin shaking down the system, but going forward, Prime won't truly be shaped by Core. Prime is in our hands right now, and we'll begin shakedown and optimization, handling it on a standalone basis as it progresses.
All right, that's quite useful. Thank you. So next, you brought up several distinct, you know, applications and end markets during this call. Clearly, the military is a major one that might be, you know, brought to market fairly soon. Data centers are, naturally, a major one too. You brought up residential deployment. So where are you, sort of, observing the strongest demand right now, and how do you decide which of these end markets to pursue first? You know, is it reasonable to think the AI data center opportunity is mostly connected to the bigger Prime system?
Yes, that's a reasonable thing to think, Alex Fuhrman. We've discussed data centers and water scarcity and what we can do to affect that market segment quite a bit, and we're engaged in, you know, meaningful conversations about it. I believe there's considerable, you know, momentum pulling us that way. You know, another thing to note here is that various markets require various amounts of time. For instance, regulatory structures differ, and there are different route proof points and validations needed before various markets, you know, will adopt and take up at a meaningful volume level. You know, take data centers as an example—they're going to proceed at a pace unlike U.S. residential, unlike U.S. military, you know, unlike desiccant dehumidification, you know, AirJoule Core DH products, for instance. We're attempting to handle all of those varying go-to-market timing dynamics here too.
All right, that's quite useful. I appreciate it.
Hi there, good morning, everyone. I appreciate you fielding our questions. Perhaps I'll build on the previous one. Regarding the Core deployments that are anticipated during Q4, which client would you say is the most probable to be the first to submit an order? Or should we instead view it as several clients being prepared and merely awaiting the necessary certifications to be finished?
I appreciate that, Ryan. In many respects, the first Core deployments continue to be about positioning clients whose main interest is Prime, even though Core clients exist too for the, say, Core DH, since that offering will enter the market via pilot programs and similar efforts, and bring clients over onto Core; we also brought up U.S. military engagements, and truly, supplying them with Core AWG offerings. I hope that gives you a bit of insight here. We'll reveal additional details about who is in fact involved at the appropriate moment, along with whatever disclosures we're able to make.
Thanks for that. Could you bring us up to date on how customers are responding to the water purchase agreement model, and is that something where we might see a deal come together in late 2026, or does that look more like a 2027 event?
Yeah
Alright, go ahead. Yeah.
Thanks, Bryan. Up to this point, Bryan's been handling the questions that have come in. He heads up our joint venture and serves as our Chief Commercialization Officer as well. A great number of these questions are being answered by him. On top of that, he holds a Ph.D. in chemistry. One thing these questions point to is that you're all asking about how Core and Prime differ. What matters most for that final question, the water purchase agreements, is how waste heat gets utilized. The opportunity is far, far greater when you're actually capturing that waste heat, which is available in every location, and your energetics drop so substantially that the levelized cost of water takes less of a hit than it does when you're out there dehumidifying, since we rely on a standalone heat pump system for the dehumidification project, you know. That, I believe, is a really significant marker separating Core and Prime. Regarding that last question, Ryan, about water purchase agreements, that's the piece I'm still most enthusiastic about. Once waste heat is used to push that cost lower, you also, as Bryan mentioned during his prepared remarks, connect it to distribution inside a 100 mi radius — there are numerous sites, be they data center or other types of sites, where waste heat will bring our regeneration costs down and, as a result, bring water costs down. My view is the water purchase agreements this year are coming, you know, at minimum we're planning for the, you know, planning to reach commitments, rather than including — running in parallel, I should say — alongside equipment sales for Prime.
Thanks for that.
Bryan, I interrupted you there in case — yeah, if you had something to add to that, go ahead.
No, I appreciate it, Matt.
Bryan, is there anything more? Alright. Thanks, Bryan.
Hi, everyone. I appreciate you fielding the questions and for all the updates provided today. I just wanted to ask about the slides. There's one showing the CapEx for AirJoule compared with the CapEx for data centers at a 100 MW siting. I found that quite interesting. Could you discuss whether that's roughly the siting density you have in mind when you mention holding these individual discussions with data centers? For instance, might the first sitings be smaller? I'm just, like, attempting to understand whether that will be a typical siting for data centers.
Sean, I believe what you're asking about is the capital size for deploying AWG sites, or?
Yeah. So the slide indicating that AirJoule CapEx would amount to 1%-3% of the overall cost to build a facility — I suppose that's fairly substantial compared with what I had in mind.
Yeah.
Does that come from the location side of things — you brought up speaking with a data center client that has separate siting possibilities? What I want to know is what drives the estimate you put on that slide?
Understood. I appreciate you raising that. This subject deserves some clarification. The slide references $3 billion-$5 billion in overall CapEx for a 100 MW data center. Our approach was to examine how much water such a facility requires altogether. Were you to swap out every drop of that water for AirJoule CapEx, that would represent 1%-3% of the entire build. Consider this something along the lines of a worst case, or perhaps a best case, regarding the quantity of water that could be addressed at deployment sizes of this kind. As you would expect, replacing 100% of a data center's water demand would be quite a large undertaking. At the outset of any initial projects, that isn't something I expect to see.
All right. Regarding the customer you're speaking with, is it more that water concerns are shaping where they place their data centers, or is it simply about achieving greater efficiency within the data center itself? I'm just curious how much of this relates to potential locations for future sites as opposed to merely improving efficiency at existing ones.
Yes. The majority of our discussions center on new data center construction in water scarce regions, where they face permitting challenges and pushback, correct? Where they're encountering difficulty obtaining the required permits. AirJoule serves as a way to bring the project back on schedule; that's essentially where those discussions are focused. I mean, you could expect that if you're constructing a data center and have ample water, then you wouldn't be our customer. If there's scarcity of water, quality issues, or regional opposition, those are situations where we can step in.
Great. Thank you.
If you'll allow me, I'd like to tack on a further remark following Bryan's. Pat Eilers here. With these data centers too, there's an entire sustainability dimension, plus a chance on the insurance side involving distributed water. It delivers both resiliency and sustainability, and plenty of the hyperscalers are quite aware of that, even if it weren't the main source. That's simply some extra context regarding the data center opportunity.
Melissa, thank you. And I appreciate all of you being here with us this morning. When we look at the first quarter of 2026, it was marked by disciplined execution against the 2026 objectives we laid out back in March. Our Core platform continues to mature. Our first Prime has been constructed and is now operational. Across a range of markets, we're seeing strong demand from customers. It makes me very excited that we're scaling our commercial pipeline for 2027 and beyond. The productization of Core, the Prime development in Europe through the Net Zero Innovation Hub, the launch of our dehumidification platform, and the customer engagements Bryan walked through this morning all support this exciting path. We truly thank you.
Thanks. That wraps up the conference call for today, everyone. At this point, you're free to hang up your lines. We appreciate you joining us.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete AirJoule Technologies Corporation transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to AirJoule Technologies Corporation earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.