Good day, everyone, and welcome to the Q3 FY ’25 earnings conference call for Housing Limited. Just a reminder that all participant lines are listen-only, and after the presentation wraps up, you’ll have a chance to ask questions. If you need anything during the call, please signal an operator by pressing zero on your phone. Please be aware that this conference is being recorded. I’ll now turn the conference over to Mr Binay Sergar from ENY. Thank you, and the floor is yours, sir.

Binay Sarda analyst
#2

Thanks, Muskan. Hello, everyone, and thank you for being on this Q3 FY ’25 earnings call for Ashiana Housing Limited. You’ve been sent the results along with the investor presentation by mail, and these are also available on the stock exchange. If you haven’t received them, just write to us and we’ll gladly send them your way. Joining us today to walk through this quarter’s results and take your questions are Mr. Varun Gupta, Whole-Time Director, and Mr. Vikash Dugar, CFO. We’ll begin with a short overview of how the company performed during the quarter, and after that we’ll move into the Q&A session. I’d like to remind everyone that any statements on this call reflecting an outlook for the future, which might be treated as forward-looking statements, need to be considered together with the uncertainties and risks they face. Those uncertainties and risks are included in, but not limited to, what we’ve stated in the prospectus filed with SEBI and the subsequent annual reports, which you’ll find on our website. With that, I’ll hand the call over to Mr. Vikash Dugar. Over to you, sir.

Vikash Dugar executive
#3

Thanks, Binay. Good afternoon, everyone, and I hope you and your families are staying healthy. Welcome to our discussion of Ashiana Limited's performance for the third quarter of FY '25, and thank you for joining us today. During the quarter, area booked came to 6.77 lakh square feet in Q3 of FY '25, compared with 3.35 lakh square feet in the third quarter a year ago and 7.29 lakh square feet in the second quarter of FY '25. Bookings in the second quarter were higher because we launched Ashiana Amarah Phase 4 in Gurugram. This quarter we saw very good bookings across our projects. The value of area booked stood at INR454.16 crores in the third quarter, versus INR672.54 crores in the second quarter of FY '25. For the nine months of FY '25, total presales were around INR1,362.02 crores, versus INR935.68 crores in the nine months of the previous year, an upside of 45.56%. 5.19 lakh square feet in the third quarter, versus 4.77 lakh square feet in Q3 FY '24, versus 6.01 lakh square feet in the second quarter of the current year. That quarter-on-quarter decline of 13.6% was mainly because of a position of graph-related restrictions. Total construction for the nine months of FY '25 was INR16.11 lakh square foot, versus 13.7 lakh square feet in the same period last year.

Vikash Dugar executive
#4

Our guidance for FY ’25 presales remains at INR2,000 crores. That said, it will hinge on how quickly bookings move following last quarter’s launch of the Ashiana Amarah Phase site. Turning to financials, total revenues came in higher for the quarter, as we had expected, at INR139.93 crores versus INR59.53 crores in the second quarter, which reflects project deliveries in the third quarter. In the same vein, our PAT for Q3 FY ’25 was positive at INR10.88 crores. The main driver was 2 new phase deliveries, Tarang Phase IV in Phase VI in Jaipur. PAT also carried a onetime impact from an INR5 crores payout related to the GST Metro Trios hotel. That has been presented as an exceptional line item in the P&L. However, with delivery anticipated across more of Phase 2 and Phase 3 in the last quarter, we expect a profitable Q4 FY ’25. Pretax operating cash flow came in at INR120.42 crores in Q3 FY ’25 versus INR78.18 crores in Q2 FY ’25. For the 9 months ended FY ’25, pretax operating cash flow was INR273.53 crores. Cash flows remain healthy thanks to higher collections, supported by improved sales across projects. A third senior project has been launched in Chennai under the name Ashiana Sourabh located.

Vikash Dugar executive
#5

Beyond that, Ashiana Ekansh Phase IV in Jaipur and Ashiana Amodh Phase II in Pune are also set to launch in Q3 FY ’25. With that, I’d like to wrap up my comments. At this point, we’ll be glad to take any questions or suggestions you might have. Thank you.

Operator operator
#6

Many thanks. We’ll now start the question-and-answer portion. If you’d like to ask something, you can press R&1 on the touched telephone. Should you want to take yourself out of the question queue, you can press RN2. We ask that every participant use a handset when asking a question. Ladies and gentlemen, we’ll wait a moment while the question queue assembles participants; left press star and one to ask a question is from the line of Rohit from PMS. Please go ahead.

Analyst analyst
#7

Good afternoon to you as well. So, sir, a few questions from my side. In our previous discussion, we talked about a potential site somewhere in Bangalore. Is there any update on that, sir? That was my first question.

Varun Gupta executive
#8

All right, so the Bangalore deal is progressing. In fact, there are certain conditions — CPs — that the landlords must complete regarding the land approval lag. So once those are satisfied, I believe the deal will go through.

Analyst analyst
#9

Is there any timeline on that, sir? I mean.

Varun Gupta executive
#10

My hope is that this quarter, though over there they’re dealing with a regulatory-type problem. So at times the responsibility isn’t only the landlord’s — the government bears some of it too. Still, my hope is that this quarter we’ll be able to get through, and if not this quarter, then next quarter for sure.

Analyst analyst
#11

And sir, broadly from BD's perspective — I mean, we've been stating that we'll proceed slowly, given how elevated land prices are and the land that's available. So it's now down to roughly 25 lakh square feet, if I'm taking that out — and of course this doesn't include Bangalore, but just at a general level, could you give us a sense of what's likely to happen in this year? Is there anything that could sort of bring it back up to, say, 40, 50 lakh, which is what we were kind of saying — I mean, we feel whatever we sell each year is roughly that kind of run rate. So if you could probably help us on that point.

Varun Gupta executive
#12

We also disclosed an agreement we've signed for a 20-acre parcel in Jaipur, all right? That agreement is now in place, and it would add another 20 lakhs-plus square feet overall.

Analyst analyst
#13

So that isn't included in this, correct?

Varun Gupta executive
#14

That isn’t included here, because, once more, it remains only at the agreement stage; we haven’t finalized it, and the landlord still has certain obligations in the cities involved. This was probably disclosed last quarter, at which point you would have issued a special announcement to the stock exchange that this is taking place. We are awaiting the landlords’ receipt of some regulatory clearances so that we can proceed. So that will contribute. And we are negotiating one additional partial of roughly 7 to 8 lakh square foot, and those stocks are also in progress. So there is — and on top of that, we have about 50-odd lakhs square foot to launch across existing projects as well. Yes, INR48 lakhs. So there is some — we still have three years of the stock. It isn’t entirely gone, right? So I thought I would clarify that too.

Analyst analyst
#15

Right, fair enough. I was only trying to say — and then, another thing — so I won't be covering Jaipur and Bangalore, where 20 lakh each was implemented?

Varun Gupta executive
#16

No. So Bangalore would probably add somewhere between 10 and 12 lakh, and Jaipur would be just about 20 plus lakh only.

Rohit Balakrishnan analyst
#17

And that 78 lakhs that you mentioned we're also going after — is that in Jaipur as well, or?

Varun Gupta executive
#18

No, that one’s in a different location. It’s also a senior living project. But once more, it’s at a very early stage. I’m hoping we’ll be able to pull it off.

Analyst analyst
#19

And sir, was Amarah launched during this quarter?

Varun Gupta executive
#20

Amarah is 5 years old and hasn't come to market yet. Our plan is to introduce it in two weeks — that's two weekends from now.

Rohit Balakrishnan analyst
#21

And sir, I mean, what are you hearing on the ground in the micro market where you are located there?

Varun Gupta executive
#22

So the markets are softer than they were probably 8, 9 months ago, right? That said, we’re not — it’s not — we’re confident we should have a good launch. And for me, let me frame it this way: markets are more normal, they aren’t weak; that extraordinary exuberance the market had probably 9 months ago isn’t there anymore, and that’s fair. Normal markets are probably the best place to be. Exuberance on either side isn’t very good. So I think the market is in a good space. But we’ll find out how the launch goes in 7, 8 days, yes, we start, and then probably in a month, we’ll know how things actually stand with real evidence.

Analyst analyst
#23

Correct, correct. So that INR2,000 crores really hinges on that, doesn't it — I mean, Amarah.

Varun Gupta executive
#24

That depends on it. It depends on how that turns out. Yes, 100%.

Rohit Balakrishnan analyst
#25

And just one final question. I mean, do you have any early thoughts about what next year might look like when it comes to launches? And is there anything regarding presales you'd like to share?

Varun Gupta executive
#26

Our planning process happens at the start of March, so mid-March is when we'll finalize things precisely. My goal is to get a few new projects underway. We've got additional land in Jaipur as well as the Jamshedpur parcel. The company's aim would be to launch all 3 of these projects during the residential year. And perhaps at least one among the three that we're hoping to pick up this year — we're currently in discussions, and we've mentioned Bangalore, Jaipur and one more — I'll try to get one additional one of those launched in the next.

Operator operator
#27

Operator: Thanks. Our next question comes from Himanshu Upadhyay at PMS. Go right ahead.

Himanshu Upadhyay analyst
#28

There's something I wanted to ask about what's written on Page 46 of the annual report — we've talked about acquiring 7 million to 8 million within the next five years, and expecting sales of INR1,100 crores to INR2,000 crores along with a profit of INR2,000 crores. What that effectively works out to is 18%, 19% of PAT margins and nearly 30% of EBITDA margin, okay? Generally, the high margins like these that we've seen tend to happen only when land prices have gone up and the sales value per square feet is improving, okay? Do we believe — are we assuming that such prices are continuing, or will keep rising in the near future, and that sales velocity will stay good?

Varun Gupta executive
#29

So the assumptions here are that the whole inventory we currently hold gets used up over the coming five years. That works out to roughly 11 lakh square foot of unsold stock across projects that are ongoing, around 48 lakh square foot in upcoming phases, plus about 25 lakh square foot of land bank. Our assumption is that by 2030, all of it will be consumed. That consumption is what we'd report as revenue, likely including the ongoing projects. Two things have taken place. First, operating leverage is coming into play, so margins are getting better. As you can see, we're also giving a sense of what future delivery revenue might look like. We expect a rising trend next year at 1,300 plus. After that we're looking at 1,700 plus, and the year following that, again 1,700-plus, against the revenues we have now. And it won't improve increase, so operating leverage will come into play along with internal margin improvement. Second, much of the rise in land prices and apartment prices has already occurred. Some projects we hold were picked up at great times in 2021, in 2022. As and when those projects kick in, we'll have good margins on them, as expected.

Varun Gupta executive
#30

I think that improvement in the margin profile ought to occur for that reason. So, when we look at future projects, we aren't building in meaningful price hikes. Our assumption right now is that prices will likely creep up in line with inflation and nothing beyond inflation at this point in time. But in these projects, that kind of shift has already shown up — take Ashiana Amarah: what we assumed when we acquired the land versus what we're selling at today is very different, and that's a big kicker; likewise across Ashiana and all of these projects, we've seen prices rise. We've also enhanced our mix by shifting more and more toward senior, and we expect better margins in senior living since it's a more specialized product, one that took us a lot of time to refine. So we suffered earlier, but improvement is visible there now. So a whole host of factors is at play. And over the next 5 years, I expect us to average high-teen margins at the PAT level. And that is something we definitely expect to happen.

Himanshu Upadhyay analyst
#31

Regarding price depreciation, which occurred under the traditional lens—what we had, right—so that gives us confidence that we should obtain that amount of money. And that is what we think we are seeing in portfolios, or leads being generated, reviews, or lead conversion taking longer, or prices—people are negotiating more in the market when you say the market is much more stable, at least in Northern India, okay? Could you give us some.

Varun Gupta executive
#32

It's not just Northern India or Gurgaon — it's worldwide. Otherwise, looking at the previous quarter, our sales were spread fairly evenly across projects. That quarter wasn't one where Gurgaon played an especially big role, if you check its share in Q2. Leaving Gurgaon out, we did roughly 430,000-odd square feet — 435,000 square feet. So far this year, again excluding Gurgaon, we've reached 5.5 lakh square feet. That 5.5 lakh square feet exceeds the whole of Q1, which came to 440,000 square feet, with no Gurgaon contribution in Q1. So when you look at what's going on, I'd say markets generally are robust and keep performing well. It's only in Gurgaon that things are, I'd say, a bit more stable — clothing rates are somewhat lower, visits are somewhat lower. Still, it isn't a weak market. What we're seeing is that Gurgaon is more normal now, because nine months ago Gurgaon had a different kind of exuberance, one that none of the other regions of the country where we operate had, okay? So I'd say Gurgaon has normalized to how other parts of the country generally live, however you look at it. That's my take.

Himanshu Upadhyay analyst
#33

So, Ashiana, is it reasonable for us to expect that launch to happen in Q1 of FY ’26?

Varun Gupta executive
#34

No, that shifts into Q2 or Q3 of the coming fiscal year. So regulatory changes came in at the last minute, and because of that we've gone back to the drawing board on our building plans. As a result, we'll need a bit more time to secure the regulatory approvals we expect.

Himanshu Upadhyay analyst
#35

Has there been any change in FSI loans?

Varun Gupta executive
#36

Oil projects aren’t affected by this, but the way we designed the project was tied to a particular style and set of rules built around that specific design change. So FSI stays the same.

Operator operator
#37

Thanks. We'll take the next question from Shah at RBS Advisors. Your line is open.

Analyst analyst
#38

I'd like to ask, for Q3 of fiscal year '25, what would your numbers be for the third quarter?

Vikash Dugar executive
#39

Could you say that again?

Analyst analyst
#40

Regarding those figures for January, February, and March 2025, so that we can get the complete picture when it comes to revenue as well as EBITDA margin.

Vikash Dugar executive
#41

We don’t disclose the EBITDA margins.

Analyst analyst
#42

Yes. On revenue, we’re expecting a rough fourth quarter.

Varun Gupta executive
#43

Regarding those projected revenues shown on Slide 15 of the deck, if you take a look at that. And we should finish up somewhere around INR550-odd crores for the year, perhaps including other income, INR575 crores for the year. So you're looking at roughly INR300 crores of revenue to be reported for the.

Analyst analyst
#44

That would be INR300 crores, and it would be repeat business for the last quarter.

Varun Gupta executive
#45

Right, that is our expectation. A few projects need to be handed over. They're at the OC stage — the 2 large ones are being delivered in Gurgaon and in Jaipur, and Ashiana Amarah Gurgaon is heading into OC stages. So once OC comes through, development and construction will be complete, and we're waiting on that for Amarah — honestly, I think we're eager to move all the stock. That's what we expect. That said, Q4 will be very, very largely — because Ashiana Phase 2 is basically a project selling at effectively very low margin, or no margin at all, carrying a hangover from the prior cycle's high; I think it's one of the few projects still left for us that still drags on the balance sheet, right? So that one, and Ashiana too, aren't very heavy on margins. So we expect margins to be very muted in FY '25. But with FY '26, as I mentioned earlier, from FY '26 onward we expect the game to start shifting significantly, since better margin projects get delivered from FY '26 onward.

Operator operator
#46

Thanks. Our next question comes from Rohit's line. Go ahead, please.

Analyst analyst
#47

Okay, just two more questions. Sir, I believe on the previous call — and I think this came up fairly recently — you mentioned being hopeful about roughly INR2,000 crores of cumulative profit across the five years starting FY ’25. So when I look at your slides, you've already sold — or rather, you have inventory — meaning you launched projects valued at about INR5,500 crores, and of that you've sold close to INR4,400, which is to be recognized over the coming three years, including this year, correct? So that leaves four years after, including FY ’25. So sir, from this point, to reach that incremental INR5,000 crores, INR6,000 crores of projects that need launching — meaning selling them and then recognizing them over the following 4 years — wouldn't FY ’26 end up being very heavy when it comes to launches?

Varun Gupta executive
#48

Well, so from my perspective, we went ahead and launched all 3 projects outside of what’s on our project list — that’s Jaipur, Pura — and we’ll need to secure one of the 3 projects we’re currently in talks with. If we bring those in during the next financial year, I think we’ll be on track.

Analyst analyst
#49

So that's the current fee, plus either the Jaipur one or the Bangalore one.

Varun Gupta executive
#50

Provided we secure that, success is ours.

Rohit Balakrishnan analyst
#51

All right. That's something we ought to keep an eye on this year when it comes to launches. So those 3 existing ones you mentioned — right, setting those aside — is there any timeline at all for the launches? Would it be H1 or H2? Any thoughts?

Varun Gupta executive
#52

They should land early in H2. That leaves us roughly 4.5 years to bring them in. So there will be plenty of time for us to get them.

Rohit Balakrishnan analyst
#53

And sir, just one more question on the prior quarter — I believe you said that on a reported basis, profitability this year would be very close to last year's. So that would basically make

Varun Gupta executive
#54

Yeah. Sorry, I’ll just cut you off—we did provide guidance on that. So one specific project, Ashiana, is one that was supposed to deliver the bulk of the profit, even with low revenue; it’s a project with a very high GP margin. Historically, we’ve been missing the delivery period there by a quarter. So it was in Q4, and it’s moved to Q1 of next year. So some of the things were under power control, and we executed. But this year, the graph regulation in NCR was heightened—basically, the pollution threshold at which they stop construction was reduced—and we probably lost 2025 strategies of the construction period delivered this year, the estimates. And what we were expecting in March has now gone to me. So that’s, unfortunately, what happened.

Analyst analyst
#55

So essentially, looking at next year with delivery revenue, here's something that's going to occur — perhaps less so where revenue is concerned, but more on the profitability side?

Varun Gupta executive
#56

Yeah, there'd be a bit of a yes.

Analyst analyst
#57

And sir, I mean, we don't really have anything significant when it comes to unsold inventory, do we? Here, I can see these two projects, and out of the 2.65 lakh square feet, one is in Jaipur. So when it comes to the sample rate, when do you figure these two will be sold out? I'm asking about Phase 2, V and VI. It's not very high, but I just wanted to get a sense, because it goes to like 50% inventory looking very low, but I just wanted to get your sense.

Varun Gupta executive
#58

So I think that will be finished in the first half of the next financial year — possibly the whole financial year. That's the broader picture, and on that I have nothing to say. And the third item: we've put together something like a crack team in Bhiwadi to get moving on a lot of ready unsold stock, and their focus was Ashiana Town. Ashiana Town, basically, we've now cleared it — it had been our heaviest piece. So they went after that one first. Now that it's done, that team will move on, since it probably wants to get active. So the first quarter of next year is when we begin to get a sense of whether you're able to get results. You see, if our strategy works in the first quarter next year, then we'll be done in the next financial year; if the strategy doesn't work out, we go back to the drawing board and try something else in the quarter after that. I think that's where we are at in

Operator operator
#59

Our following question comes from an individual investor named Rahul. Mr. Rahul, hello? Please go ahead with your question. The next question comes from the line of an individual investor.

Rahul analyst
#60

Sir, I just wanted to ask — did the deliver area in Amarah go up by roughly this quarter’s renovation, or is it commercial?

Varun Gupta executive
#61

No, it was simply a matter of how the calculation was carried out. A few portions of the area got left out of our trading chart, which we're now reviewing internally. And that turned out to be right, since our plans had been revised.

Rahul analyst
#62

All right, so that came in at 5.3 times.

Varun Gupta executive
#63

Correct.

Operator operator
#64

Since no one else has a question, I'll pass the conference back to management for their closing remarks. Sir, the floor is yours.

Varun Gupta executive
#65

We appreciate everyone joining this call and for your patience through all the questions and answers. Should we not have gotten to any questions, please don't hesitate to write to us or contact us directly. With that said, we'd like to bring the call to a close. Much of the material we've discussed is available on our website. You're also welcome to e-mail your questions if you need any further clarification. Thanks again for taking the time to be with us on this call. Thank you.

Operator operator
#66

That brings us to the end of this call for Ashiana Housing Limited. We appreciate everyone being with us, and at this point you're welcome to hang up. Thank you.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ashiana Housing Limited transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Ashiana Housing Limited earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.