We appreciate your time in joining the second quarter call for Clearway Energy, Inc. Present with me are Craig Cornelius, who serves as this company's President and CEO, along with Sarah Rubenstein, our CFO. Beyond that, additional members of the management team are here in the room, ready to respond to any questions you may have. Prior to starting, let me briefly point out that during today's discussion, forward-looking statements will be included, and those rest on assumptions we consider reasonable as of this date. Materially different actual results are possible. Kindly look at the safe harbor contained in today's presentation, together with the risk factors found in our SEC filings. Additionally, reference will be made to financial measures under both GAAP and non-GAAP. Regarding details on our non-GAAP financial measures and reconciliations to the most directly comparable GAAP measures, kindly consult today's presentation. Specifically, note that during today's oral presentation, we might reference both offered and committed transactions, and may also talk about such transactions in the question-and-answer segment of today's conference. For a description of the categories of potential transactions and related risks, contingencies and uncertainties, kindly consult the safe harbor in today's presentation. Having said that, I will pass things to Craig.
Akil, thank you, and good afternoon to all of you. I'll start with Slide 5, which provides our business update summary. Clearway continues to be solidly positioned to achieve durable, best-in-class growth over the long haul. Our 2027 CAFD per share objective of $2.70 or better is being reaffirmed, and as we look further ahead, our visibility into the road map for potential deployment of $3 billion of corporate capital across 2026 through 2029 has only improved. That visibility underpins our confidence in aiming for the top end or better of our 2030 financial goals. These targets rest on projects within the Clearway enterprise that we control, and the swift commercialization momentum across our development pipeline keeps us confident in our capacity to hit them. On top of this core outlook, the maturing digital infrastructure business at Clearway Group offers meaningful additional upside. These are opportunities we look forward to bringing into CWEN's story more visibly in the coming quarters. Lastly, while it isn't included in the targets we've set, third-party project M&A continues to be a possible growth pillar for our fleet, since we're being presented with chances to add projects showing synergies with our core fleet that can be bought at returns accretive to shareholders under our established capital allocation framework. Against that backdrop, our line of sight to growth now extends well past 2030, and our record as one of the power industry's most dependable infrastructure providers gives us confidence in the runway that lies ahead. In the near term, transitory weather patterns during the first half of the year have affected our 2026 outlook. With low wind resource in that first half, and as described in the operational preview published in mid-July under our new enhanced disclosure practice, we are revising our 2026 CAFD guidance range to $430 million to $470 million. Sarah will give more detail during her portion of the presentation, but I want to stress our conviction that the underlying earnings power of our operating fleet is completely intact. Now to Slide 6. Fleet enhancements remain among our most capital-efficient growth pathways. This quarter, we achieved further tangible progress in moving them forward; across our ERCOT wind fleet, we've closed new long-term PPA transactions on all 3 projects we intended to enhance, extending contracted tenors spanning more than 600 megawatts out past 2040, boosting the pro forma EBITDA and CAFD these projects will generate, and substantially enhancing the predictability of our cash flows from these large, well-positioned projects. In addition, through our fleet enhancements growth pathway, our repowering program keeps executing as planned. We continue to expect roughly $600 million of capital deployed into this program at 11% to 12% CAFD yields, alongside attractive long-term internal rates of return and meaningful reinforcements to the projects' long-term life. Now to Slide 7. The build-out under our sponsor-supported growth initiative keeps moving forward, with every committed project staying on schedule during construction, while the following set of projects matures more quickly behind those. For the COD batches we have slated for 2026 and 2027, our construction schedules remain intact, and everything we intend to construct for CWEN within those batches is fully contracted. Royal Slope Energy Center is moving toward reaching financial close, with commitments expected shortly, and Honeycomb Phase 2 has just been presented as the following investment possibility for 2027, which completes the investment slate we have laid out for CWEN in that year. Peering ahead, our 2028 batch is shaping up into a strong year of possible expansion, with contracts either signed or awarded already covering over 2 gigawatts of projects in late stages — among them Swan, Solar, Catamount, along with the recently introduced Wildflower II and III solar plus storage projects, all of which are set to begin construction mobilization during the first half of 2027. Within our 2029 COD batch, we keep observing a growing number of identified investment possibilities entering our sights, which further cements the trajectory toward surpassing our 2030 financial goal. The volumes in the 2029 batch now contain roughly 2 gigawatts of late-stage solar plus storage projects, amounting to about $650 million in possible corporate capital investment. Consequently, roughly 70% of the growth investment required to reach the top end, or go beyond it, of our 2030 target has already been commercialized and is within view. Past the projects already commercialized, we hold a considerable surplus of projects under development compared with the roughly 2.7 gigawatts we would need to construct in that year; for CWEN to beat the top end of its 2030 targets, which gives us confidence in how resilient our plan is and optimism regarding possible upside to it should prudent capital allocation permit. Clearway Group is likewise aiming to finish the initial phases of generating capacity at its co-located digital infrastructure complexes during 2029, potentially delivering an upside investment possibility that might in time add to CWEN's earnings power in 2030 and afterward. Moving to Slide 9. Through every growth pathway we have up to 2029, our best-in-class development craftsmanship has substantially reduced the risk in our outlook for hitting the top end, or better, of our 2030 targets. Although we were glad to see that mirrored in our share price earlier in the year, we do not think our present price completely reflects the worth of our growth outlook, and we stay focused on performing the work required to narrow that gap. Our investors should expect us to keep executing with determination and capital discipline toward those long-term objectives that underpin that value. I hold complete confidence that Clearway will demonstrate it is among the finest risk-adjusted returns on offer within the energy industry. Moving to Slide 10. Now turning to how these possible growth investments convert into a long-term CAFD per share outlook; we hold strong conviction that Clearway Energy, Inc. We're set up to produce between 7% and 8% plus compound annual growth in CAFD per share for investors across 2025 through 2030, landing at the upper end of the range we established. As of now, more than $2 billion in identified growth is already secured for our 2027 through 2029 completion vintages, which constructs a clearly defined bridge toward reaching the top end or better of our 2030 target; this plan is disciplined and mirrors our steadfast commitment to directing capital into high-return investments that create lasting value for shareholders, with investment proceeding at a measured pace driven by deliberate capital formation within a prudent capital allocation framework. Moving to Slide 11. When we look past the current 5-year window, our visibility into growth opportunities for CWEN in 2031 and beyond keeps improving. The 2030 development projects are well diversified across technologies and markets, with notable depth in the Western U.S., a region where Clearway has executed successfully for a long time. Impressively, more than 1.5 gigawatts of those 2030 projects already have signed or awarded PPAs, which amounts to substantially more than half the megawatts required to support growth at the high end of our 5% to 8% plus long-term goal. With upwards of $500 million in potential investment slated for completion more than 4 years out, our enterprise enjoys greater long-term visibility than at any prior point. On top of our core development work, co-located digital infrastructure complexes offer substantial additional upside for CWEN. Clearway Group's pipeline now contains more than 17 gigawatts of co-located generation under development, with initial contracts for revenue already signed and more targeted for later this year, and with progression accelerated at its MISO South and Wyoming complexes in particular, capacity in development at these digital infrastructure complexes now exceeds 6 gigawatts and has been incorporated into Clearway Group's reported pipeline. We look forward to sharing more about this opportunity as it takes further shape. All together, the breadth and quality of our sizable and redundant growth pathways give us continued confidence in Clearway's ability to pursue and prudently fund the highest return growth opportunities available to drive long-term CAFD per share growth well beyond 2030. In line with our historical practice, we plan to communicate updated CAFD per share growth and capital allocation framework targets in our third quarter earnings call when we intend to roll forward our 5-year growth targets into 2031; with that, I'll turn the call over to Sarah, who will walk through our financial results in more detail.
Thanks, Craig. Moving on to Slide 13, I'll walk through the financials for our second quarter, along with what's driving the updated outlook we've provided for the full year. During Q2, Clearway posted adjusted EBITDA totaling $409 million, alongside CAFD of $167 million, which lifts our adjusted EBITDA for the year so far to $666 million and year-to-date CAFD to $237 million. Solid execution came through in our flexible generation segment, matching what we had budgeted. Within our solar and battery fleet, lower resource and realized revenues weighed on results, though plant availability stayed at high levels. As for our wind fleet, resource came in below typical levels at both Alta and our ERCOT fleet across the quarter, extending the meteorological pattern linked to the El Nino-Southern Oscillation, or ENSO, that also influenced first quarter results. Now to Slide 14. With year-to-date results landing at the low end of our sensitivity ranges, we're updating our full year 2026 CAFD guidance range to $430 million to $470 million, down from the previous range of $470 million to $510 million. Resource is what's driving this revision, and the team still feels good about our long-term resource assumptions, which rest in part on our fleet's historical production. We've consistently been transparent that any particular quarter may see below-average resource. That said, we'd note again that our fleet has historically posted strong operational performance consistent with our long-term expectations. It's this multiyear historical backdrop that gives us confidence the underlying earning power of our fleet remains fully intact. Regarding the assumptions built into our updated range, the midpoint incorporates revised renewable production expectations, while the low end presumes the ENSO pattern continues through the second half of 2026. Consistent with our standard approach, the range also reflects various outcomes across other factors, such as the timing of growth investments and sensitivity to merchant energy margin in our flexible generation segment. On Slide 15, since Craig has already covered our growth pathways for reaching the top end or better of our 2030 target, I'll restate some key points about how we intend to prudently fund roughly $3 billion of corporate capital deployment from 2026 through 2029, plus the main pillars supporting growth funding into the 2030s. Across the 2026 to 2029 window, we still expect retained cash flows to add more than $500 million, reflecting our commitment to bring our payout ratio below 70% over the long term. Corporate debt remains a core funding source for hitting our 2030 target, with more than $1.5 billion anticipated to be raised between 2026 and 2029, of which $600 million has already been raised so far, all while staying true to our commitment to a BB credit rating, which equates to a target corporate leverage ratio of 4 to 4.5x. Beyond retained cash flow and corporate debt, external equity issued from a position of strength will be carefully deployed to meet our growth targets, with roughly $0.5 billion to $1 billion expected between 2026 and 2029, of which $50 million has been raised to date. Like we mentioned on previous calls, any such move would happen only if it clearly adds value, using approaches that keep price disruption to a minimum and sized as a percentage of our public float in line with what listed utilities typically show. On top of that, with the balance sheet and liquidity we have right now, we can be flexible about when we issue equity, and we're able to hold off and pick favorable windows for equity issuance through the rest of 2026, since we expect our growth story to be reflected more fully in our share price. Thanks to the success of our capital-light fleet enhancement work, by 2030 our base portfolio could produce cash flow that is more sustainable than what we expected earlier in the year, and that takes more risk out of our path toward hitting the top end or better of our 2030 CAFD per share target. This framework puts us in position to achieve the top end or better of our 2030 target while keeping the balance sheet discipline our investors look for. Beyond that 2030 target, as we work to bring our long-term payout ratio under 70%, we're well set up to cover the $500 million of corporate capital already identified in the 2030 COD vintage through modest external equity issuances. As a result, we have growing visibility into meeting our growth goals in 2031. We'd also like to point out how retained cash flow compounds and how that can meaningfully reduce the risk around our funding needs. With a payout ratio under 70%, we'll be in a strong position to sustain our 5% to 8% plus long-term growth objective far into the 2030s. We still see upside optionality to grow at the top end or better of that range during the 2030s, though we'll only put more capital into high-return investments when accretive sources of capital are on hand. We'll stay firm in upholding our investment and capital allocation discipline; with that, I'll hand the call back to Craig for closing remarks.
Thanks, Sarah. So, looking back, we achieved quite a bit of progress during this quarter along the road toward creating value and growth over the long haul; we are still solidly on track to hit our 2027 CAFD per share target, and our conviction stays strong that we can reach the upper end, or even surpass it, of our 2030 CAFD per share goal. During the next quarter, we intend to push forward on the efforts that provide us visibility to extend our CAFD per share growth target into 2031, which we plan to make official when we hold our third quarter earnings call, and at the same time we will keep satisfying our long-term payout ratio objective of under 70%. Along with a growing quantity of retained cash flow that will finance growth as time goes on, our company finds itself in an excellent spot to fulfill its long-term CAFD per share growth target of 5% to 8% or more far into the 2030s, with only modest needs for outside equity, while preserving the optionality that comes from a position of strength to reach the upper end, or better, of that range. Everyone at the Clearway enterprise is united around generating value for each of our investors, and our execution remains strong. We have unshakable confidence in our capacity to keep producing long-term value. With that said, operator, let's begin taking questions.
Craig, for the digital infrastructure customers, how much does it matter that they have safe harbor equipment and projects? Or do they care more about price flexibility, meaning maybe you could hold that equipment back and send it to different customers instead?
That's a good question. As you can probably picture, it's given us an edge when it comes to positioning some of these complexes. That said, it's possible that pricing power exists that doesn't depend on qualifying for a tax credit, depending on the resource mix, the location, and how novel one of these complexes is. We're quite far from having to seriously weigh that difficult decision, since we've already managed to make safe harbor qualification investments totaling almost 15 gigawatts, and we can allocate that both toward the renewable projects we're moving forward with in our core business and toward the renewable portions of the projects we've decided to prioritize for the first of the set we intend to build over the next 5 years in co-located digital infrastructure. But as we look further ahead and consider how to position these resources so they're value competitive for data center owners, we feel fairly confident that even if the renewable portion of the projects we're developing doesn't claim a tax credit, it's still a resource that makes economic sense for them.
Understood. And when it comes to customers that aren't hyperscalers — the digital infrastructure buyers — what are conditions like at present for the other C&I customers? It seems like PPA pricing has climbed because of inflation in balance of plant costs. Are some customers hitting pause at the moment if their needs aren't urgent?
If you look at the identified projects we've put in our pipeline, the great majority of the customers we're working with who aren't hyperscalers are, in fact, utilities. That gives us a much clearer read on that market. And for us, Mark, that market remains extraordinarily strong. Over the past several years, the underlying principle has been that when a project can credibly be finished within the next 36 to 48 months, has an established interconnection position, and has a route to securing the permits required for construction, the load serving entities in this country definitely want to purchase its output. And in places where selling straight to hyperscalers is an option, they do that too. It remains true that in that narrow group of projects where we're building assets — in market structures allowing sales to commercial and industrial customers — we still have interest. We've disclosed that we're now above 8 gigawatts of contracted or awarded projects so far this year. That definitely includes C&I customers. There are markets such as PJM where resources we're developing carry both energy value and sustainability value. And at times the customer who isn't a hyperscaler is the one with the greatest willingness to pay. Broadly, though, our current focus is on serving the utilities that have been the backbone of our business up to now, and there we find it remains quite feasible to reach agreement on what the resources we're developing are worth. And in markets where we can sell more widely, we certainly see a blend of C&I customers and hyperscalers, though generally the greatest willingness to pay appears to sit with a hyperscaler.
Understood; everything there sounds encouraging. And this might be my final question. Regarding where the stock has moved back to, I realize you brought up third-party M&A, but given the current share price, does that perhaps cause you to hold off and concentrate for now on organic development, making that opportunity clear to investors before you dive back into M&A?
Yeah. I'd say that's roughly the practical narrative. One thing we keep in mind is that throughout the 13 years our public asset holding company has been listed, we've been choosy and successful during periods when its cost of capital is particularly accretive, pursuing synergistic project acquisitions. And whenever it isn't where we'd like it to be, or valuations for third-party acquisitions, in our view, don't genuinely reflect their intrinsic value, we pull back. And what's rather virtuous about our business model is that our organic pipeline is extensive enough to reach the top end or better of our goals. So right now, when it comes to third-party M&A, we're productively digesting some of the assets we bought last year and enhancing them, as you can see, in the case of one we're already repowering that we purchased. And our organic pipeline is so extensive, not to mention the digital infrastructure projects we're developing, that we're able to truly direct our attention toward exceeding the top end of our goals purely through projects we control ourselves.
I'd like to begin with the guidance. With the revised guide, you said the low end presumes that the ENSO-related weather pattern continues through the second half here. I'm just curious what wind resource assumption is now baked in at the low end. How does that stack up against the assumption you'd use at the midpoint; and then I'm wondering whether you can share how conditions have been trending in July and August? Is it nearer to P50-type levels or still more in line with what you saw in the first half?
At the time we reset the guidance range, resource conditions in July had already been taken into account, and those were built into the midpoint of the updated range we gave. And we're only a handful of days into August, so few that it isn't really statistically significant at all. We had baked into the midpoint expectation something below a P50 production resource for Alta, in particular, which, as you can appreciate, looms large, along with our resources in ERCOT, which likewise showed renewable resource worse than a typical meteorological year. So to reach the midpoint of that $430 million to $470 range, we're not fully counting on a P50 resource in the second half of the year; so that's kind of a first answer to the question; and when it comes to fleet performance, controllable performance in the fleet keeps holding up well. We tried to set the bottom end of that range in a way that would be conservative so that we could be sure we would land inside the range as we move toward the end of the year. And as an organization, as we normally do, we're going to aim to try to deliver on the top half of the range we've articulated.
Understood. All right, that's quite useful. Perhaps moving on to digital infrastructure — the Wyoming complex now appears to be aiming for its first generation in 2029, with full capacity in 2030, while I believe the target last quarter was 2028 for that first generation. So I'm just curious what caused the timing to shift? And at this point, when do you expect CWEN could get its first investment opportunity in that complex? And if you do invest, what kind of potential upside might that bring relative to your 2030 CAFD per share target? Would you treat that as supporting a level above your long-term target?
Yes. Well, taking it in reverse order, as we've said, investment opportunities tied to these complexes represent extra upside beyond the core business. And that really shapes the response to your question regarding when an offer could come. We view these as genuinely significant and appealing assets that Clearway Group is developing, and we're conscious of the chance to pace ourselves regarding when any particular one would be best brought to CWEN as an investment opportunity, since in every case where we're developing these projects, we're aiming for 20 to 25-year revenue contracts. Regarding Wyoming, the first generation we have planned there will in fact still be finished at the end of 2028. And the 2029 to 2030 time window really captures when we would anticipate serving load there via a data center for the first time, and that is paced by what we believe would be the timing of the transmission solution enabling service of a data center load. But development of that complex keeps moving forward, really on track with what we targeted in the prior quarter; and we're quite excited about both that complex and others on this list in how they leverage pre-existing development resources we already had in place, preexisting customers, consistent with Mark's question, tax credit qualifications we've obtained previously, and we feel fairly confident given the engagement we have ongoing with customers around, in particular, those first 2 complexes that we mentioned, that we have created resources offering a really responsive solution for what data center customers need. And so we feel pretty good about the track we're on with that project.
Anuhea Elliott here, filling in for Julien. To start, the deck gives additional specifics about colocated digital infrastructure, such as possible corporate capital upside of roughly $400 million to $500 million for every gigawatt of generation that comes online. So I suppose, could you help us frame what a realistic scale and timeline would look like for these data center-related investments as they become part of CWEN's growth plan? And more specifically, I suppose, which milestones ought we to watch for prior to assigning them tangible value?
I believe we'd begin by concentrating on the investment program we've laid out for CWEN in the main body of the materials, and thank you, Anna, for asking. That investment program, structured around core projects in our development pipeline, is what allows us to hit the top end, or better, of the $3.10 in CAFD per share 2030 target we've established. Because each of those projects is consistent with our historical investment program and because we have clear visibility into them, our first priority is to keep advancing every one of those projects through their planned development, the receipt of everything required to close financing and begin construction, and to slot them progressively into CWEN's investment program along with its expected growth profile, CAFD per share, and reduction of payout ratio over time; and as you can see in some of the materials, which I believe we've summarized on Page 9 of our earnings presentation, that program generally seeks to deliver an investment opportunity of approximately $900 million a year to $1 billion a year for Clearway Energy, Inc. as we progress through 2027, '28, '29 and 2030, and the raw material of the projects we're developing in our core business provides that opportunity. When it comes to the digital infrastructure projects, as you can see from the disclosures we've provided, the most natural first investment opportunity for CWEN would probably be out in 2030, when the first of those complexes come together. Given the size of the generation mix of each one of these, they would present an opportunity either to substitute for the projects we are developing in our core business as an investment opportunity for CWEN, or, to the extent it had access to capital and could make those investments accretively, to increase the scale of its investment program as we look out to the decade beyond 2030. So I think what you could probably look to is that once those projects get commercialized and we reach a point in time where they are equivalent in commercial definition to what you see for other projects we put in our identified opportunity list, they will end up in an identified opportunity list like that, and you'll be able to see characteristics of the revenue contracts and scale of the projects we're creating. You could consider those in a manner similar to how you view other recognized initiatives that come with an investment road map for T1.
Understood. Now turning to my second question — regarding that deal you announced not long ago with T1 Energy, could you take us through exactly where the FEOC compliance exposure sits? Also, how do you view Section 232 and the resulting inflation concerns in connection with this T1 arrangement?
Sure. What I can speak to broadly is the supply program we run as a whole. I believe you've been able to observe us across time. If there's one thing we take particular pride in when it comes to our craftsmanship, it's our capacity for policy aware development and for running a supply chain that stays ahead of various kinds of policy disruptions as time passes. I'd say we were among the earliest in the industry to see and welcome the idea that foreign entity of concern considerations would enter U.S. policy across many dimensions. Well before such factors made their way into the Big Beautiful Bill, we had already reworked our sourcing approaches with a range of established or up-and-coming companies. Whenever we worked with them, whenever we requested that they design supply chains, whenever we purchased from them, what we sought was for them to build supply chains covering component parts, service materials, and intellectual property that would render them shielded from U.S. policies — or at least less vulnerable to U.S. policies aimed at restricting procurement of power equipment from Chinese-controlled enterprises. So across the whole development program we've mapped out through '27, and almost entirely through 2028, we have already secured the equipment destined for those projects; we have already set the standards those suppliers must meet, and given that foresight, those standards, plus how we've qualified projects for tax credits, we feel very confident in where we stand on every one of those projects. When we look past 2028 toward projects finishing in 2029, we've enjoyed a strong chance to help shape the nascent domestic cell and module manufacturing sector, where firms such as T1 — though not only T1 — have begun taking sensible steps by locating additional solar cell manufacturing here in the United States, and by striking arrangements with predecessor companies concerning intellectual property and continuing manufacturing support that answer to U.S. law. With every company where we've signed supply agreements — and there are no fewer than 4 with whom we've signed module supply agreements, T1 among them for future supply — we put them through rigorous paces, and we feel quite good about what T1 and its team have done to position themselves as a core supplier to us and to the broader industry in the years ahead.
Regarding the PPA restructuring for Elbow Creek and Langford Wind — it seems there was an upfront expense to terminate the hedges, which I believe got financed, and afterward the projects were recontracted at a higher price. So looking at CAFD at the project level, does it go up right away on day 1? Or is there some stretch where you're servicing part of the debt or the hedge break cost before any CAFD improvement shows up? Could you walk through that profile?
Sure, I follow what you're asking. We're genuinely proud of what our team accomplished here. Every one of those restructurings adds to EBITDA and CAFD starting in month one after they take effect, and that's been borne out in practice; the deals, as we structured them, leverage the bank relationships already in place that had set up commodity hedges to establish a price floor for those assets. And through those very same institutions, we're able to finance away the prior settlement obligations, using a structure that lets the projects deliver higher CAFD to us even as that debt gets paid down over time. So we feel very good about what was done with those assets to get them into a position where they hold a fully fixed price contract across the coming 15 years with truly outstanding customers, plus an increase in EBITDA and an increase in CAFD and a remarkable extension with dependable cash flow going forward. As best we can determine, we're the first company in this industry to have found a method for pulling that off. And we're very pleased with where it leaves the projects and very proud of the effort our team put in to make it possible.
Got it. Just so I understand. With a contract that runs longer, those projects clearly are able to carry more debt, or nonrecourse debt. So going forward, are there any plans to bring nonrecourse debt into those projects that now have longer-term contracts?
No, no. I think if leverage were something we'd add to assets in our fleet, the portion of the fleet where it generally makes the most sense to do so would be our solar projects; but overall, we feel fairly good about how our capital formation plan is set up — we'll selectively pursue both organic cash flow from the fleet we already have as well as corporate sources, and keep drawing from our operating fleet the project level or portfolio level cash flows that assets are providing today.
All right, understood. And now, a brief follow-up regarding the Wyoming project, as it's the first one scheduled to go live. Could you remind us how those projects are contracted? For instance, is there a hyperscaler or some customer already secured? Has a deal been signed? Or are you still in discussions with multiple parties, or are the developers still negotiating with several parties?
Yeah. I believe we haven't actually provided details about the contracting status for that project, but it's a complex currently in advanced discussions with prospective customers who would serve as the customers for it. There would be just one customer. As for the MISO South complex, that project complex already has contingent revenue contracts with the data center development enterprise, and those will ultimately be substituted by long-term agreements with a hyperscaler we decide to partner with. So regarding when we anticipate finalizing those kinds of long-term contracts for the Wyoming complex, that timing will be driven by the continuing technical advancement of the resource at that site and the strategies for delivering a data center load there. Still, we take real pride in the pioneering aspect of what we've built at that complex and its potential to expand over time, perhaps even past the 4 gigawatts of planned capacity we have in place, and we're hopeful that well before reaching the 2030 date, it would ideally lead to a permanent equity investment opportunity where we'll have a customer secured to support that development work.
I just want to make sure I understand — the agreements that were inked regarding digital infrastructure, those mainly concern the building out of those assets rather than the final client, which is, I believe, what you mentioned when answering the earlier question.
Correct, that's accurate.
I was hoping to clarify that point. After that, I'd like to understand how you view the CAFD yield percentage for certain opportunities of that kind compared with the roughly 10% to 11% range seen in solar and storage. Is it still too soon to tell on that? Or do you have some idea of what the market would support there?
Our approach to those complexes mirrors how we treat the core renewable and battery assets in our pipeline. In the current market, for assets with genuinely scarce value and pricing power, our objective is to secure 20- to 25-year contracts featuring favorable settlement provisions, which deliver high-quality risk-adjusted returns throughout that contracted cash flow period. As for the complexes we're building here, we truly are designing, commercializing, and structuring them as a collection of renewable and battery or natural gas toll resources resembling the other projects in our fleet. Therefore, we'd anticipate the returns and CAFD yields they can offer would appear comparable to other projects we develop within our core business; and as mentioned earlier, and as we hope we'll keep gaining from the concentration of our investor and analyst community. Our core business stands in an excellent position to keep offering a similar investment proposition across a quantity of assets that would carry us right to the top end or beyond of our targets. So I believe when the time comes for us to decide how to capitalize these generation resources tied to a co-located data center, you could expect us to consider contracting and capitalizing them in a manner consistent with our core business. And the timing for when they'd be presented as an investment opportunity for CWEN will be dictated by their commercialization and the remaining outlook for growing Clearway Energy, Inc., along with its capital formation framework.
Yes. Okay, that all tracks; and when I look at 17 gigawatts of possible opportunities there, at $400 million per gigawatt, that comes out to roughly $7 billion or more of possible corporate capital opportunity around the 2030 to 2032 timeframe. I'm just wondering, that's a fairly big jump up from the rates we're doing near term, which are already impressive. So how should we think about, I suppose, either the sequence of steps for incremental reinvestment past the 70% payout equity, assuming it's accretive, like would we aim to begin using partner capital again, can you maybe just provide a bit more detail on the sequence of steps once the numbers begin getting somewhat larger?
Yes. So anyone who's followed our business develop over time would know that our core development pipeline has been kept at roughly 30 gigawatts fairly consistently for several years. And the pace of investment we've established for Clearway Energy, Inc. has typically been governed by its access to capital, how accretive returns are on capital use, and a business model intended to produce at the high end of a CAFD per share growth rate matching the returns leading value utilities deliver. And if that's what we're after, if our aim is to produce 7% to 8% plus CAFD per share growth annually, what that roughly amounts to as you move into the next decade is a need to put in something like $900 million to $1 billion annually and then build up slightly as you move deeper into the 2030s. And that is a very sound business model for the company, which we have no plan to break. So while you see a total aggregate generation capacity in development of up to 17 gigawatts of digital infrastructure, 6 of which is included in the 32 gigawatt pro forma Clearway Group pipeline under development. We don't intend to drastically change the business model we have now that works quite well. And so we regard these projects as part of the raw material within Clearway's overall enterprise structure for value creation. And we'll seek to optimize which of those ultimately become part of an investment program for CWEN alongside the other development projects in our core pipeline; and where we succeed at executing a portion of that pipeline, if we succeed even on a handful of those, then I think you're right to expect that partner or third-party capital will be involved in capitalizing those projects both during the construction period and the permanent period. And what you should think about and what others should anticipate for Clearway Energy, Inc. is that we continue to have.
All right. That's great. All right, my first question is this: since you're concentrating on PJM and there's so much regulatory activity happening in that area, are you intending to take part in what PJM is currently doing to bring in additional supply — the reliability backstop procurement, for instance?
No, we aren't offering any remarks about that. Honestly, we feel quite good about the assets we've built in PJM; whenever there's an opportunity for them to connect to the grid, we can build and sign contracts for them in a manner that's financially beneficial and meets what customers need. We definitely pay attention to how well battery resources have performed elsewhere in the nation when it comes to creating a swift reliability resource that helps tackle wholesale market conditions in a way that benefits ratepayers. And I'd like to think regulators will treat that as evidence. Still, looking at our broader development pipeline, as you can tell, the large majority of what we're building sits in the American West and in regulated markets, where the route to serving load — and doing it in a way that's favorable to ratepayers — is somewhat more straightforward. So we wish PJM's regulators the best, and of course, we'll be prepared to provide resources that fit their market design.
Great. That helps. Then one final item, and it's brief, from my side. Regarding your 2030 CAFD guidance, there's an offset included tied to base portfolio moves. Is that merely standard asset degradation? Or does something different sit inside that offset?
We aim to stay cautious at all times in the way we build uncontracted revenues into our forward outlook, and we do it in a manner that's suitably conservative, so we can be sure we'll hit or beat our long-term targets and in time be capable of scaling them up, which is what we've historically done. And — so one way to view it is that the possibility of weaker energy or capacity prices is roughly what establishes the low end of that range. What would let us aim at the high end of our CAFD per share range, or above it, would be better results on those sorts of attributes especially; and honestly, at this point we feel fairly good regarding that outlook. So without question, one element of what we do, and will do, as we revisit our long-term outlook is to factor in our forward contracting activity across portions of our current fleet, factor in fleet improvements such as the ones we announced on our wind assets, and those rank among the possible drivers of CAFD per share performance in 2030 and later on the upside.
And Craig, perhaps I should also mention that the effect of corporate financing does appear to create somewhat of a downward pull there, so that could be another thing you're picking up on, Heidi.
I appreciate all of you being here today and for the continued backing you give Clearway. The effort we're putting in to maintain one of the most robust clean energy fleets in America is something we take pride in, and we couldn't be more enthusiastic about what we intend to do to expand it by a large margin in the coming years, supplying more and more of the electricity that our nation sorely requires. Operator, please go ahead and end the call.
We appreciate everyone joining in. That brings the program to a close. You're welcome to leave the call now. Have a good day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Clearway Energy, Inc. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Clearway Energy, Inc. earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.