Fervo Energy Company (FRVO) Earnings Call Transcript
August 12, 2026
Earnings Call Speaker Segments
Thanks, and good morning to all of you for joining Fervo Energy's second-quarter 2026 earnings call. With us here today are Tim Latimer, our Co-founder and Chief Executive Officer, along with David Ulrey, our Chief Financial Officer. I want to note before we get started that remarks made during this session will include forward-looking statements as defined under applicable securities laws. Such statements represent management's present expectations and assumptions, and they carry both known and unknown risks and uncertainties that might lead actual outcomes to differ materially. For more detail, please see the forward-looking statements and risk factors laid out in today's earnings release and in the documents we file with the SEC. In addition, certain non-GAAP financial measures may be discussed today. Where applicable, reconciliation tables can be found in the appendix of the earnings release. I'll now hand things over to Tim to begin.
Thanks, Paxton, and welcome to everyone on the call. The last time we spoke, I stressed Fervo's founding belief, and it's worth saying again. Those very drilling technologies that sparked the shale revolution are capable of unlocking clean, round-the-clock geothermal power on a massive scale. As you're aware, we're in the middle of a power demand surge unlike anything seen in a generation — one that will probably shape how the American success story plays out in both artificial intelligence and industrial growth, and also how far affordable, dependable electricity reaches people. The stakes have never been greater, and I've never felt more certain that Fervo is uniquely built to seize this moment. From my standpoint, this comes down to Fervo proving success on four essential fronts. First, does Fervo hold enough pipeline to answer this historic call for power, and can our EGS technology's scalability take advantage of that pipeline? Second, does Fervo's modular take on enhanced geothermal energy align with the demand profile and reliability our customers are after? Third, does Fervo's method for local stakeholder outreach, development, and sustainability mean we honor our partner communities and keep our license to operate in those places? Fourth, can Fervo deliver in the field — putting gigawatts onto the grid while at the same time driving costs down through seamless execution, in spite of the many complexities that come with deploying large-scale infrastructure? The updates we're sharing today will show our progress on these fronts, but in plain terms, we're drilling quicker, reaching deeper and hotter, and negotiating hundreds of megawatts of commercial agreements, all while still executing at Cape Station. Before we get into it, I'll begin with a safety update. During Q2, our trailing 12-month total recordable incident rate came in at 0.34; these figures speak to our relentless focus on safety, supported by best-in-class operational management and a commitment to community and environmental stewardship. Early in my career, I served as a well site supervisor for drilling operations. That gave me a profound respect for leadership when it comes to safety. When Fervo was founded, we set out to show that you could lead on innovation and still hold to the highest standards of health, safety, and the environment. Our strong performance confirms that thesis, and we take pride in Fervo's leadership in bringing ideas such as Safe Seven and the life-saving rules to the geothermal industry. Those programs have directly produced our results. With that said, let's move to recent updates. First, our pipeline. This quarter, we shifted eight GeoBlocks — equal to 400 megawatts of capacity — out of early development and into advanced development. We moved 10.5 gigawatts spanning two geoclusters from land holdings into early development, and we grew our total geothermal mineral rights position to more than 650,000 acres. To make these moves concrete, we have eight GeoBlocks where our internal teams hit the key commercial resource characterization, permitting, and deliverability milestones needed to advance from early development to advanced development. To be more precise about those eight GeoBlocks: we've submitted an interconnection queue application, finished geological surveys, and obtained the permits needed for appraisal well drilling. Those GeoBlocks are now on the development path toward ready-to-build status. At this point we're working toward the definitive agreements and the remaining regulatory approvals that will get them across the finish line. Regarding the two geoclusters that shifted out of land holdings and into early development, DeGolyer and MacNaughton finished the heat initially in place studies, which confirmed 10.5 gigawatts of development potential — that confirmation served as the basis for shifting that capacity into early development. For context on that figure, it's over twice the four-gigawatt development potential that Cape Station currently has, where construction is underway on 500 megawatts; it also backs Fervo's multi-gigawatt geocluster model, which unlocks economies of scale that lower costs and de-risk future GeoBlocks. Going forward, we've set out deliberate appraisal plans spanning our geocluster portfolio, starting in Q4, intended to sharpen how we characterize the resource and to speed the pipeline along as it moves through development. Before I continue, it's worth talking about the scale of power demand we're seeing in today's market. The U.S. grid is confronting load growth at a level not seen in decades, propelled by the build-out of AI and data center infrastructure, the reshoring of domestic manufacturing, and electrification across the broader economy; this surge represents a generational opportunity for clean, firm power development. Although questions have arisen about how robust power demand from AI and other industrial users on the grid really is, Fervo's 24/7 carbon-free energy remains highly sought after by buyers in every category. Our present total of 658 megawatts of signed binding PPAs, together with $7.2 billion of revenue backlog, is evidence of that demand. Beyond those fully contracted megawatts, we hold gigawatts of demand at various stages of RFP, term sheet, and contract negotiations spanning a multitude of our geoclusters. To give you a sense of how diverse the need for firm power is, roughly 35% of our future capacity negotiations involve utility buyers, 50% involve hyperscalers, and 15% involve non-hyperscaler industrial customers. Fervo's GeoBlock development strategy fits directly with what those buyers want. Because we build independent modular 50 MW GeoBlocks, our systems carry a degree of redundancy, resiliency, and stability that our customers' needs demand. Should one GeoBlock require maintenance, that particular GeoBlock goes offline while the rest keep producing power. Speed and resilience are only part of what's required to actually get infrastructure built. Our power developments are also clean, carrying with them environmental stewardship, power density, and responsible land use that is hard to replicate with any other form of power generation. This matters critically to Fervo, and it sits at the center of who we are. Fervo constructs infrastructure meant to endure, and that's the reason Fervo stands as a founding signatory of the Geothermal Sustainable Development Pact — a pledge that is entirely voluntary, 100%, put together alongside essential NGOs including the Sierra Club and the NW Energy Coalition, aimed at reaching the very highest benchmarks of responsible development spanning six pillars: community engagement, workforce development, land use, water conservation and well integrity, induced seismicity, and emissions. No other approach to development will we take. Fervo's baseline is precisely the elevated standards that the Geothermal Sustainable Development Pact contains. Where water is scarce, Fervo will build solely with air-cooled condensers, which means our power plants will never face evaporative losses that place stress on nearby water resources; seismic activity surrounding our sites will always be monitored, assessed, and acted upon. Even more crucially, we'll collaborate intimately with our regulators and neighboring communities to deliver open data, analysis, and education regarding the primary risks tied to our projects. Beyond that, Fervo will partner only with customers and partners ready to bind themselves to a comparably rigorous benchmark of responsible development. As co-located and behind the meter GeoBlocks advance through our development pipeline, we are particularly careful when vetting and selecting those partners. Regarding this matter, recently, resistance has emerged throughout the data center development ecosystem from local communities who hold legitimate worries about what these data centers could do to their communities absent responsible development.
In Fervo's case, here's a chance to show how infrastructure assets ought to be built — responsibly, transparently, and in tight partnership with a broad set of local and regional stakeholders; that development philosophy isn't a recent invention at Fervo. Everybody who's visited Cape Station has noticed how much we value the community and how much we want to act as its partners over the long haul, its collaborators, and its champions for its causes. What's different now is how much this mode of operating sets Fervo apart from other builders of similar infrastructure assets. We increasingly think our approach of thoughtful development will be essential to supplying geothermal energy reliably and at scale. Next, I'd like to take a few minutes on behind-the-meter development more broadly, since we see it becoming a critical bridge between today's transmission grid and the near-term power demand that data center growth is generating across the United States. How fast power can be provided — bringing capacity online without getting stuck in lengthy grid interconnection queues — ranks higher and higher among the top factors our customers weigh when choosing an energy provider, especially as hyperscale data centers and large industrial loads seek to begin operations at a speed the traditional grid just can't keep up with. Thanks to Fervo's GeoBlock and geocluster approach, we're able to generate electricity immediately and connect to the grid later, giving us and our customers alike flexibility as grid timelines move. That modular architecture — the very thing that bakes reliability and redundancy into our systems — lets us site an initial phase of generation behind the meter, then layer on capacity incrementally as our partners' growth requirements play out across the medium and long term. Because output fluctuates somewhat with temperature, shifting by season and time of day, the EGS production profile matches up beautifully with solar, storage, and other generation types. The resource we depend on is the earth's own heat, drawn continuously from wells we own on site, so an EGS project sited behind the meter is shielded from any disruption to fuel deliveries. By pairing EGS with solar panels and battery storage, we expect our customers to reach a remarkably strong level of reliability at a total cost that remains competitive — and if necessary, that reliability can be bolstered by a modest amount of gas generation on site to cover rare, tail-end events. Power from Fervo's EGS provides precisely the modularity, reliability, and output that behind-the-meter development requires, and our customers are reaching that realization quickly. Even though behind the meter matters for future business, 100% of Fervo's geoclusters get built with a long-term grid interconnection plan in mind; we keep filing interconnection queue positions and signing interconnection agreements. This positions us to capture a $400 million opportunity. When transmission timelines can't keep up with what our customers need, behind the meter gives us a way to get power to them. This approach — combining behind the meter with front of the meter — is precisely what is speeding up our growth. As with past practice on our side, PPAs become public only once they're signed and legally binding, and we won't get out ahead of that. Even so, our behind the meter pipeline has real momentum, and we're optimistic about announcing something before the year is out. Of course, execution is what makes any of this possible. So let's turn to Cape Station. As a reminder, we're building 500 MW at the Cape geocluster, and the latest study there indicated over 4 GW of total resource potential. Our first installation, Cape Phase I, totals about 100 MW — three 33 MW GeoBlocks — and two PPAs cover it entirely. No multi-GeoBlock EGS development had ever been constructed anywhere in the world until this one. And we're doing two things that have never been done before. First: we drill horizontal wells and use multi-stage hydraulic fracturing. At Project Red, our pilot, Fervo was the first company in geothermal history to take this approach, and we're now the first to deploy it in a large scale development. Second: we team in-house engineers with trusted industry partners on equipment design and construction. To illustrate how well this works, in less than two years we've gone from a patch of dirt to a fully built power unit located just around the corner from utility scale generation today — and that $400 million of investment shows what that speed delivers. That's the speed to power our customers want. At Cape Phase I right now, the team stays focused on execution, prioritizing late stage commissioning and the ramp toward production. First power from Geoblock 1 is targeted during Q4 2026, with Geoblocks 2 and 3 delivering power by early 2027. Mechanical completion on Geoblocks 1 and 2 — a major milestone — is behind us now, and Geoblock 3 ought to hit mechanical completion within the next few months, consistent with our construction timeline. Commissioning at Geoblock 1 moves forward in stages, which lets us gather strong data, manage safety, and learn as we proceed. Our first set of wells is tied into the power plant now, pushing geothermal brine through the heat exchangers and spinning the turbines, and before we bring additional wells online we check pressure, flow, and safety systems at every stage. Wells will come online one after another, and for each one we confirm proper flow from the wellhead through the power plant and back to the well pad — a process that lifts output gradually over several months until full production is reached. Geoblocks 2 and 3 share the same design, and we expect to apply what we learned commissioning Geoblock 1 to keep fine-tuning the production ramp at the geoblocks that follow. For the upcoming expansion at Cape Station, we're putting in eight geoblocks, each rated at 50 megawatts — that's the template we'll follow going forward — and they should be operational in 2028. Since our manufacturing approach is standardized, Phase II takes the lessons from Phase I and applies them, which lets us achieve improved subsurface outcomes. The Fervo 2.0 well design served as the basis for Phase I, featuring laterals extending 5,000 feet, 7-inch casing, and temperatures near 400 degrees Fahrenheit. In contrast, Phase II uses the 3.0 well design, delivering 7,500-foot laterals, bigger 8 and 5/8 inch casing, and average temperatures of 430 degrees Fahrenheit. Last month, we shared results for Sawtooth 7, which is the ninth well drilled with Fervo 3.0. This well is our most complex build to date, reaching a measured depth of nearly 19,500 feet at 460 degrees Fahrenheit. Despite the added complexity and deeper drilling, spud to total depth took only 21 days, which is a fresh company record for drilling speed and equals the spud to total depth timing of our shorter, shallower Cape 1 wells. We expect these design and reservoir temperature changes, plus our faster drilling capability, to significantly increase power output per well and reduce cost per kilowatt. To illustrate simply, increasing the target temperature from 400 to 430 degrees Fahrenheit at Cape Phase II raises power generation by roughly 27%, while the power generation system consumes the same steel quantity and the wells keep identical flow. Practically speaking, Cape 2 ought to produce 27% more power than Cape 1, with about the same surface CapEx — a dynamic that could translate into roughly $400 million in added value.
We anticipate that we'll keep encountering progressively hotter rock at Cape, which the Sawtooth 7 well demonstrates by hitting 460 degrees Fahrenheit, even though the design point for Cape 2 sits at just 430 degrees Fahrenheit; that gives us confidence in our capacity both to drive costs down and to deliver a lasting production profile. To put it another way, given how much our performance has improved so far, we still think the lessons learned and the innovations put into practice across Cape Phase II leave us on track to achieve an all-in cost of $5,500 per kilowatt, while our long-term objective of $3,000 per kilowatt remains clearly within reach. Finally, when it comes to how things are progressing at Cape Station, we're pleased to share that we've just grown our rig fleet, bringing a third Helmerich & Payne rig to Cape Station right on schedule with the wider Cape Phase II development timeline. That means we're raising how many megawatts Fervo is capable of drilling annually. To illustrate, assuming that at steady state each of our three rigs averages 1.5 wells per month, together those three rigs could drill roughly 54 wells per year. Assuming every production well produces around 15 megawatts of power, and assuming our injection-to-production well ratio holds steady, then our three rigs could drill more than 400 megawatts of capacity each year. Before handing the call to David, I'd like to take a few minutes on our technology and, more specifically, on how fast gains in drilling performance fundamentally de-risk our projects. From day one, Fervo's philosophy has been to learn by doing. Project Red, our initial pilot, was never meant to represent the final iteration of our technology. It was a minimum viable product, built to demonstrate the core elements of our design as rapidly and inexpensively as we could; namely, that we could drill horizontal wells through geothermal rock, generate fractures within the reservoir, link offset wells via those fractures, and sustain commercially relevant flow rates of geothermal brine through the system over time. It delivered on all of those counts. Since that point, we've iterated quickly. As I just described, every successive generation of our well design, from Fervo 1.0 at Project Red through the Fervo 2.0 and 3.0 designs we're currently drilling at Cape Station, has extended longer, hotter, and deeper than the one before it and produced a significant jump in performance. Our published flow test data revealed that Fervo 2.0 wells at Cape Phase I achieve a threefold rise in power output compared with the original Project Red wells. The Sawtooth 7 results I just took you through illustrate well just how much that improvement keeps compounding. Consider that pace and performance against our very first well at Project Red, which required more than 70 days for us to drill approximately 11,000 feet at 350 degrees Fahrenheit; over a period of roughly three years, we've dramatically reduced drilling time while considerably boosting performance per well. At times, people ask why we're so confident about how our system will hold up thermally over the long haul. What it comes down to is this: across a number of years and in many dozens of wells, we've demonstrated that Fervo is an organization defined by steady, ongoing enhancement, which reduces uncertainty down the road while simultaneously achieving operational results that are dramatically superior and dramatically less expensive. With longer laterals and improved field designs, there's a greater volume of stimulated reservoir per well, which translates into additional thermal resource in place along with a decline curve that flattens out more gradually. Whenever we reach rock that's hotter, every unit of flow coming out of those wells contains a step change more energy than any well we've ever drilled previously. Each successive generation of well that we've completed draws on the accumulated lessons that brought us here. Let me be clear: production temperatures from our wells are going to fall off. That's just the way the physics works. What really matters is whether we're able to learn enough to offset the effects on our projects by drilling makeup wells down the road that take advantage of everything we've learned cumulatively, so those makeup wells end up larger, hotter, less expensive, and considerably more productive than the ones we're drilling now. This is the way we — and every other business built on a resource — handle decline, and the data already demonstrates that the wells we'll drill going forward are probably going to be significantly more productive than those being drilled today. This strategy is what ultimately unlocks our biggest long-term objective: turning geothermal into the most affordable, most dependable power source anywhere in the world. We've already built the biggest collection of hard rock drilling data and analysis anywhere globally, and we keep adding to it each and every day; the speed of that progress makes us proud, and we're eager to share more of it with all of you in the coming quarters. Finally, considering how quickly things have advanced, as we just discussed, it's worth taking a moment to consider where Fervo stands in relation to the wider landscape. It should come as no shock that the enormous appetite for firm power has brought a surge of new technological approaches into the power sector, each with a long list of purported advantages and at differing stages of technological maturity. In our view, a few things hold true. New technologies are on the way, and a number of them are going to succeed, will get funding, and will ultimately contribute capacity to the grid; we strongly believe the world and society require that to occur. We also hold the view that if offtakers require clean, firm power prior to 2030, Fervo will probably be one of, if not the sole, options for obtaining it. From this point through the close of 2030, a period during which we anticipate having brought online more than 1 gigawatt of power capacity and cemented our standing as the dependable supplier of clean, firm power. We think Fervo will be nicely positioned for a remarkable stretch of growth in the mid-2030s and afterward; with that, I'll turn things over to David.
Thanks, Tim. I'll start by giving a brief look at the financial highlights from Q2 2026, then move on to our commercial and financing activities, and after that, our pipeline. In the second quarter of 2026, our operating loss came in at $28.7 million, mostly because of G&A expenses totaling $27.4 million and operating lease expenses of $1.5 million. The net loss for that quarter was $55.9 million. Across the six months that ended June 30, 2026, net cash used in operating activities reached $43.8 million. That figure mainly mirrors our $87.7 million net loss for the six-month period, partly offset by $61.7 million in non-cash expenses, which include a $40 million loss tied to the change in fair value of warrant liability, $10.8 million of stock-based compensation, and a $9 million loss on extinguishment of long-term debt. Changes in working capital also affected operating cash flow, using $17.8 million of cash. Capital expenditures during Q2 2026 totaled $226.5 million, versus $108 million in the same period of 2025. That reflects heavy construction work at Cape Station, plus more drilling and procurement for the next wave of GeoBlock deployment in 2028. With that in mind, we anticipate capital expenditures of roughly $850 million-$900 million across the second half of 2026, consistent with what we've previously disclosed. As of June 30, 2026, cash and cash equivalents stood at $2.1 billion, while current and long-term debts total $228.4 million. As a reminder, we finished our Nasdaq listing in mid-May, bringing in about $2.04 billion in net proceeds — considerably more capital than we'd initially planned. That raise has strengthened our balance sheet in a meaningful way, and we're intentionally deploying it across three focus areas. First, more capital toward commercial opportunities through 2030, where our focus is on securing access to long lead equipment and resolving other potential development constraints. Second, high return R&D that could speed our path toward the $3,000 per kilowatt CapEx target and improve our near-term asset performance. Third, positioning Fervo for growth in 2030 and beyond. You're already seeing that capital reflected directly in the pipeline results Tim took you through earlier. The appraisal drilling program we're getting ready to execute later this year is made possible by this raise. The through line is simple. The IPO capitalized our business in a way that will materially accelerate our growth and performance. Finally, our contracted backlog was $7.2 billion at quarter's end, representing 658 megawatts of contracted capacity. As Tim mentioned, we continue to see a healthy and growing pipeline of commercial conversations. Next, I'd like to level set on how we think about the coming months at Cape Phase I as the first 100 megawatts begins initial production and then ramps to full production in early 2027. There are a few distinctions worth clarifying. Getting to full capacity isn’t one instant — it’s a series of checkpoints. Mechanical completion has already been reached at GeoBlocks 1 and 2, and as Tim noted, we anticipate hitting that same stage at GeoBlock 3 right on schedule. Once mechanical completion is done, each unit goes through testing, verification, and optimization steps. That starts with cold commissioning, in which the power plants and electrical equipment get exercised without any geothermal brine present. Next comes hot commissioning, and there we genuinely send geothermal brine from the wellhead into the power plant, confirming that the heat transfer system, the turbines, and the air-cooled condensers all work the way they should. After that checks out, grid synchronization performance testing follows, and during that phase we might produce some test power. Money received for that test power is hard to predict, since market pricing usually governs it, which differs from revenue earned through our contracts. Just like with any newly built industrial facility, it’s ordinary to see early operational tweaks, short maintenance episodes, or stretches of curtailment while we fine-tune how the units perform. That’s baked into how we think about the ramp, and it’s simply what happens when a first-of-its-kind commercial development comes online. Later, once a range of administrative and contractual conditions are satisfied, we declare commercial operation under our contract and transition into steady state generation. We anticipate Geoblock 1 reaching full power generation near the close of Q4, while Geoblocks 2 and 3 move through a comparable sequence — first power in early 2027, then climbing to full power across the months that follow. As things stand, third-party analysts expect us to bring in a mid-single digit amount of revenue during Q4 2026, and our view remains that this can be done. To be candid, several things still have to fall into place over the coming months before that becomes real. For instance, the remaining work at the substation must be finished, and we have to coordinate successfully with a number of different grid counterparties to reach grid synchronization. On top of that, the hot commissioning work on Geoblock 1 has to be completed, and although we don’t anticipate anything unusual arising from it, first-time startups are famous for throwing up minor, fixable problems now and then. As I just said, we still believe we’re on track, yet we always prefer to be upfront about the possible difficulties we can see. In the same way, even though it’s premature to discuss 2027, we’d like to share a few early considerations as we get ready for our first full year of commercial operations. Put plainly, with our projects, some factors sit inside our control and others sit outside it. That isn’t a new feature of power development, nor is it something only Fervo faces, but it is the reality we’re working within. Regarding what we can control, we feel really good — 80% is how we’d characterize that confidence. The fact that we can drill at higher temperatures, more quickly, to greater depths, and at lower cost provides a massive offset against many items on our risk register. These results came to us faster than we had expected, and we think there remains substantial runway for drilling performance to improve even further. We also rely on a big group of partners, regulators, and other stakeholders—especially when it comes to transmission—who are dealing with circumstances in 2027 that are unlike anything else, which could cause Fervo to be curtailed for some stretch of time. With every one of those partners, we are collaborating intently to grasp the full spectrum of possible outcomes from these events, and we think they are specific to 2027 and won't happen again going forward. Let us be clear: Fervo's production, the way we build, and how our geoblocks operate have no connection whatsoever to these curtailment events. Bearing that in mind, for 2027 we presently expect to bring in revenue somewhere between $60 million and $80 million. This does not constitute our official revenue guidance. Because our assets are reliable and our revenue is contracted, the range we're giving you today is probably broader than what we'd normally offer. Still, since this marks our first year of commercial operations and any curtailments we face are rather atypical, we consider a wider range suitable at this point.
Then, because behind-the-meter geoblocks matter so much for what we do, I'd like to clear up a frequent misunderstanding regarding the economics of behind-the-meter generation — namely, the idea that it is fundamentally pricier for Fervo due to the extra build needed to hit high reliability levels. It's fair to say a behind-the-meter project probably needs added capacity to match the reliability the grid would provide otherwise, but that doesn't mean Fervo carries every bit of that extra cost; under the structures we're going after, Fervo must deliver firm geothermal power and the reliability that comes with it to the customer's private use network, whereas the customer must procure the extra generation and storage capacity needed to reach whatever overall reliability level they want. The cost structure for Fervo to deliver our share of firm geothermal power stays broadly in line with what we've said before regarding our front-of-the-meter contracts. There will be added expenses associated with getting electricity out to the actual locations, but we don't see these having any significant impact on the returns we expect across our projects as a whole. And one last thing before I finish up — I want to return to something Tim brought up regarding how much momentum we're seeing today among both existing clients and those we hope to serve; right now we're in the middle of a number of active origination discussions that involve many different kinds of customers at varying stages of development; on top of that, we're confident we can consistently obtain what we need from our supply chain, get the necessary permits approved, and keep GeoBlocks moving forward through our development pipeline. Taking everything into account, our projection is now for 1.1 gigawatts to be in place once 2030 comes to a close. That's 100 megawatts more than what we had previously anticipated, which was 1 gigawatt. This upward revision isn't something we make casually. As our confidence builds — with Bridge behind-the-meter projects proving themselves a workable substitute for grid-connected projects when you look at it commercially, technically, and from a financing standpoint — we think Fervo will gain extra speed in reaching the market. Our team's accomplishments this quarter make us immensely proud, and we're eager to keep bringing you updates as this portfolio develops. Operator, please go ahead and begin the Q&A session.
Hello, and good morning, Tim. At this point, your land portfolio has grown to 650,000 acres, and you mentioned lowering risk on an additional 10.5 gigawatts, bringing those into early development, plus 400 megawatts moving into advanced development. Has there been any change to your longer-term development plan? Has anything shifted earlier on your schedule? If you could also say a bit more about the appraisal drilling program that begins later this year. What is the target, more or less? What are you aiming to cover? Just a few additional details about that. Thank you.
Yes. That's a terrific question, and I would say that inside every one of those categories, you're looking at an ongoing process of optimizing growth. Where do we find the strongest customer demand? That shows up as higher pricing. Where do we find permitting frameworks that let us keep advancing project development? Where do we find either fast interconnection queue timelines or chances for behind the meter arrangements that sidestep that queue timeline? So inside each category, projects are continually being reshuffled. When it comes to the timeline for growth, everything matches what we expected. What you're observing with our larger acreage position and our projects advancing through the pipeline, as David said in his remarks, are items that genuinely became possible thanks to the additional capital we raised through the IPO, which, as David noted, exceeded what we had originally anticipated. We're thrilled about this. Had you asked us 12 months ago where we'd be, this pipeline has matured further than we would have predicted, since the IPO proceeds let us devote both time and money to items such as assembling an appraisal rig program more quickly and locking up additional acreage, especially given that acreage costs have climbed quite substantially. I'd say we're progressing more rapidly than we first expected in developing this pipeline, and that results from the combination of greater IPO proceeds unlocking it. Strong customer demand remains something we keep seeing. On appraisal drilling, we're quite enthusiastic. It will closely resemble what we did at the Project Blanford prospect 12 months ago. A number of our projects have solid geologic models. We can conduct surface studies and geophysical studies that help us unlock subsurface insights, yet the gold standard for verifying temperature at depth, which ranks among the most critical criteria in our techno economics, is really to drill one of those wells down to depth. That's what we expect to do at our prospect later this year; geologic information of that kind will let us choose where to place our first laterals, inform additional geologic modeling, and accelerate the process from there. Once again, these are things made possible and running ahead of our earlier expectations because of the IPO proceeds; so we're genuinely excited to be scaling up an appraisal program across some of our Nevada prospects and beyond.
That's great, thanks. Regarding what you said about Sawtooth 7's results, and building on that, could you remind us of the count of 3.0 wells that have been drilled by now, and the number still required to complete the drilling programs for Cape Phase II, as you'd put it? I'm also curious whether you might be thinking about bringing in a fourth or perhaps a fifth rig so this moves faster. Thank you.
Yes, that's an excellent question. So, when we shared the Sawtooth results, I believe we noted that this was well number nine for us, and we've kept three rigs running to bring new wells online at a fairly steady pace. One of the new approaches we've introduced to geothermal—something made possible for the first time by the technology from our partner, Helmerich & Payne, and their FlexRig 3 rigs—is batch drilling. This lets us place several wells on a single pad. We can improve the sequencing since we're able to batch drill the surface sections, the intermediate sections, and then the production sections. So instead of delivering one new well roughly every 21 days, we're essentially drilling four or eight wells on a pad as a batch. We'll complete them all together at the end. Sawtooth 7 was the final well drilled on its pad. Right now we have those three rigs drilling actively, so we've also drilled substantial portions of additional wells since that time. As for the total well count, we expect there could be as many as 80 wells within the Phase II drilling program. We're already quite far along in that effort, with roughly 10% of the wells completely drilled and large portions of the rest drilled out. What we keep observing is that the same innovations that let us move down the learning curve so rapidly and hit that fast drilling time on Sawtooth 7 are still unlocking better and better performance. We'd expect that pattern of quicker drilling and cheaper wells—even with the extreme temperatures and the greater depths we're drilling to—to carry on through the whole Cape Phase II drilling program and beyond.
Great. Thank you, Tim.
Hi there. Morning. I'd like to revisit what was said regarding 2027. Could you give us a bit more detail on those curtailments you seem to be hinting at?
Sure. Morning, Dylan, and thanks for asking. Regarding 2027, I believe our comment during the call was that we anticipate revenue in the $60 million-$80 million band, and we attempted to signal that this represents quite a broad span. To reiterate, none of this relates to Fervo's output, our wells, or how GeoBlocks are performing. The actual cause is curtailment affecting the transmission lines running between the Cape Station site and our end customers. We have been monitoring this for quite a while, and with 2027 getting nearer, the situation is naturally becoming more evident, so we decided this was the appropriate moment to start addressing it. We believe this is specific to 2027, when that transmission operator adds another asset into its line. The curtailment stems simply from integrating that asset into the network alongside it, and there's nothing beyond that.
All right, that's useful. Thanks. And then, a quick secondary question — regarding that additional 100 megawatts by 2030, could you tell us which of your regions might accommodate that without much trouble, and what's your thinking on the economics for it compared with the Phase I and Phase II economics at Cape Station?
Yeah. Excellent question. Naturally, we'll share more on this down the road, but I hope what comes across is that what we're seeing when it comes to origination gives us enough enthusiasm, and these discussions are advancing enough, that we feel confident raising that goal from 1 gig to 1.1 gigs. On geography, the thing we appreciate about our portfolio is the enormous optionality it offers across the board. When you look at that funnel showing how GeoBlocks advance from one level to the next, you can clearly tell we're pushing things along quite quickly; it holds multiple geoclusters sitting at different stages. We believe we've got several prospects with really strong likelihood and high quality that we can pursue here; we're also advancing transmission and permitting throughout those geoclusters. What we're seeing there pleases us. It's probably fair to say our resources in Nevada and Utah are further along; our expectation is that those projects probably originate there, though we do keep that optionality available; on economics, we'd say what these commercial negotiations are showing us aligns with prior experience — pricing spanning $100-$130 a megawatt hour; we believe everything under discussion here will land right in the middle of that band.
Yes, hello, and I appreciate you fielding that. I'd like to revisit perhaps the production increase during the latter half of this year. Regarding those PPA agreements, could you elaborate somewhat further on how they function concerning requirements for output capacity at any specific moment? Some worry or discussion has arisen that damage-related payments could be owed simply because of how things scale up and the formal commencement date. We're merely attempting to reason through that. Thank you.
Yes. Hello, Chris, and I appreciate that inquiry. Clearly, this is something we're monitoring closely. A few separate factors are at play. First, every one of our PPAs differs, so the manner in which they operate shifts as time goes on. What we possess at Cape Phase I during our scale-up is in fact wider than a strict, immediate check — do you have 10 megawatts, 30 megawatts, or 100 megawatts delivered on schedule? We have, in effect, a stretched-out schedule to reconcile that across the year. We remain confident in our capacity to produce that output and observe progress there. As for liquidated damages, that is certainly significant to us and something we consider. In our view, those liquidated damages, in the majority of instances, are not material to the P&L. Typically, what we observe is that certain trade-offs exist. By that, we mean we could accelerate bringing things online, which might carry the drawback of skipping a full commissioning stage where we examine every possibility and fine-tune the asset. I believe our management's perspective is that choosing that path would be wrong. I think what you're ideally picking up from us is that we will place the well-being of the asset and the showcasing of the essential IP ahead of everything else. We consider that the correct trade-off versus LDs that probably won't be material in most instances.
Understood. Appreciate it. Perhaps, following up on a different subject, you mentioned certain possibilities for moving oil and gas drilling methods across to your wells. What additional technological breakthroughs are you currently pursuing or testing, and what are the general expectations regarding when that might eventually become part of your broader drilling operations and produce further step change along with lower costs? Thanks.
Yes, that's an excellent question, and we've achieved a number of meaningful victories when it comes to adapting oil and gas technology to handle our tougher geologies that are both. Several elements must be taken into account in this situation. The diameter of our wells exceeds that of standard unconventional onshore oil and gas wells; that is one distinction from the oil and gas sector. Our temperatures run hotter than those found in oil and gas wells. And clearly, drilling through granite, given the material properties of granite, means it's a far harder rock to bore through compared to shale. Much of this involves upgrading to the appropriate materials, particularly as we go toward greater depth. Certain items, for instance, that we've recently put into practice and that have produced favorable outcomes — just to offer one instance on the completion side — is the understanding that performing the deeper Phase II wells would, if we aimed to pump at the efficiency we desired, demand higher pressures. Thus we have, for instance, gone out and obtained specialized equipment to handle the temperatures, casing diameters, and pressures encountered in our operations, which has in fact resulted in a rise in stage success rate. Just to provide one illustration of technologies we are transitioning over: the capacity to conduct well stimulation at elevated pressures. So substantial instances keep emerging there. Another technology we've tested out several times across the past couple of quarters and are becoming more and more assured about is moving to a rotary steerable system for drilling some of these deeper and more difficult wells. This is a sophisticated technology that lets you keep your drilling program in the rotating phase, where you can drill more quickly while still attaining the directional trajectory of our systems. There were some initial difficulties adapting that technology to geothermal because of the temperatures and properties of the granite. But collaborating with our partners, we believe we've sort of refined that to the end, and that's merely one of those instances that as it moves from trial to a more routine component of our drilling program, which is roughly the stage we're at right now with that specific technology. It will keep producing considerably better drilling results. There's simply a lengthy list of these sorts of innovations that we're currently engaged in.
Understood. Many thanks.
Hi there, good morning, everyone. Perhaps stepping back a bit — I recall it was under 2 months back when you mentioned that the bigger capital raise was unlocking additional opportunities. You raised the 2030 goals. There's a new rig in place, plus a fresh drilling program. Should we view that as what it enables for you, this new capital, or are there other items we ought to hold off on and watch for? I've got a follow-up after that.
Hi, Ben. Excellent question. What I'd say is this is certainly a piece of it, and maybe I'll split those apart somewhat. The third rig we brought in at Cape Station falls under the standard development path for the Cape Phase II project; that particular one was essentially something we'd planned, so perhaps I wouldn't place it in the category of being tied straight to added cash. Conversely, however, the extra 100 megawatts, I'd say, does connect directly to that, along with the appraisal drilling program we're about to begin. When we consider what's needed to bring on more megawatts ahead of the end of 2030, appraisal is certainly a component of that. That's the thing that lets us move into definition and begin contracting those geoclusters with more specificity. Other work streams we'll have involved there include permitting interconnection queues, essentially reducing risk around the development and deliverability of those megawatts. On the flip side, it boils down to long-lead equipment. Our supply chain is quite strong, whether from an oilfield service and equipment standpoint, or the Organic Rankine Cycle turbines we rely on. The electrical side is hardly a secret in the market — it's somewhat more strained; that's precisely where we're directing a portion of this added capital to guarantee we've got that equipment ready when required; regarding other things on the horizon, Tim has mentioned some of our opportunity register on the subsurface development side. My expectation is that we're finding some truly fascinating methods to put modest amounts of capital to work in order to de-risk both our existing projects and our future pipeline.
All right, excellent. I'd like to dig into the behind-the-meter piece. Can you walk us through how that actually works? You brought up that higher costs came up in discussion. When a data center gets developed, how should we think about that timeline lining up with your own build-out schedule? Would construction on a data center begin prior to your completing the power plant, or afterward? In such a deal, would you be supplying the auxiliary equipment that's required, or perhaps extra generation or stationary storage too? Maybe just give us a bit more detail on how you'd expect this to unfold.
Yeah, those are excellent questions, and they're among the things we've had to grapple with, since behind the meter is, as we often put it, an easy concept to toss around but extremely difficult to actually pull off. All those tricky specifics are what you genuinely need to sort out together with your partners to make it happen. One thing that excites us, I'd say, is that we've managed to cut our construction schedules down dramatically, particularly when compared with other technologies. When it comes to generating electricity from the first few GeoBlocks at a prospect, our speed from spud to sales has become fairly fast. Because of that, we do anticipate that our projects will develop concurrently with data center projects. We don't believe they'll typically hold off until our projects are up and running before proceeding, especially in any behind-the-meter or islanded setup. We do expect that construction will happen at the same time; in fact, this is where I'd say the GeoBlocks are a genuinely strong advantage for enabling that. What we're attempting with our customers is to match up the expansion of our prospects — perhaps that means starting with 4 GeoBlocks, then adding 4 more 6 months down the line, and 4 additional ones 6 months after that. That's just an illustrative case of how it could function. What that allows is for us to stage our capital deployment and growth in step with our partners' capital deployment and growth. They're able to build out and roughly size their powered shells to match bringing these assets online. When we collaborate with our partners, I think they see that we hold a rather distinctive asset. Being able to construct power plants with zero fuel supply risk, generating 24/7 carbon-free energy at sites capable of reaching a gigawatt scale across numerous locations in the West — that's something they view as highly appealing and quite unique. Many of these customers intend to grow their deployments across several years, turning these into flagship holdings inside their portfolios, simply because you cannot really locate that combination of characteristics anywhere else. That's roughly the way we view it, and we clearly think it moves much more quickly than waiting in the interconnection queue, and that's the reason we're pursuing this hybrid strategy, since we lack queue positions that align with what our customers need timing-wise. Regarding our model and the higher costs involved, certain elements exist — be it redundancy or resilience of the electrical infrastructure, or various components needed to guarantee proper power quality — that we wouldn't be investing CapEx in for a grid-connected project. As we noted on illustrative slide two, we additionally see value delivered to our customers through hybrid methods that pair our assets with solar and storage to fulfill their goals around high reliability requirements. We're collaborating with partners on that front. Thinking about this tactically, Fervo has consistently been a company with a fairly maniacal focus. What we think is the single thing we excel at beyond anyone globally, which nobody else can duplicate, is swiftly building out enhanced geothermal systems assets. At the same time, we believe numerous trustworthy companies exist that can handle electrical system design, solar development, and those other aspects that aren't as distinctive to Fervo; we typically limit our scope to what we're best at, which is top-tier enhanced geothermal systems development, plus partnering with firms that manage the remaining supply chain pieces to collaborate with our customers in constructing these microgrids. That could change down the road as we gain more knowledge, but we cherish focus at Fervo, and we remain laser-focused on leading the industry in EGS development. Even for these behind-the-meter projects, that's where our attention lies too.
Thanks, everyone.
Hello, and I appreciate you taking my question. So, for the first one, perhaps, Dave, could you shed some light on how the cadence would shape up between the 60 and the 80, keeping in mind that interconnection is something you can't control? Let's suppose the 60 would represent a front-end loaded reduction relative to those earlier expectations of the 80. Would you be able to walk us through what that cadence could look like at both the lower end and the higher end?
Sure, glad to take that, Jed, and thanks for asking. What this really comes down to is how long that curtailment lasts — which might be pretty evident. We're collaborating tightly with the folks over there so we can better grasp the way they assess the chance that it runs either longer or possibly shorter than what they're expecting. That's essentially the source of that 60 to 80 range. When we consider how the 60 might play out, we picture a prolonged curtailment in which bringing that asset online isn't quite as smooth, from their standpoint, as they presently expect. And then, clearly, right up to 80, since our contracts are set up in a way that lets us actually go beyond our targeted expected energy; we do have some capacity to recover megawatt hours and get revenue back for 2027. Those represent the full spectrum of outcomes we're weighing. I'd say what occupies our thinking continuously is: what steps can we take to manage this and shape it? We believe there may be a few additions we could make to the system that would either reduce how much we rely on that or boost output from the asset. That's the work we'll be doing through Q4 and Q1 of 2027; with any luck, we'll have more to share at that point.
Thanks, that helps. Tim, recently I caught Mike Rowe on a podcast talking about how we don't have enough workers and the gap this country will have to deal with because of it. I'm just curious what you're doing to soften the blow on the labor side, given that you have a pretty big ramp coming. How are you trying to get ahead of this issue and deal with it? And in 2017, would you count that among the things that might drive costs higher for the business?
Sure, that's a terrific question, and it's a topic we spend a lot of time on. It's helpful, I think, to split things apart, because two segments of our operations pull from workforces that are fairly separate from one another — namely, the drilling portion of what we do and the portion focused on constructing power plants. Because of that, our methods differ somewhat between them. When it comes to drilling, we're fortunate to sit right next to a sector that likely possesses among the most powerful homegrown supplier networks and worker bases ever assembled. I bring this up often, since my own history in oil and gas drilling means I've watched global rivalry intensify alongside industrial growth in China and elsewhere. Among the very few claims you can make with total confidence, one is that America leads the planet in the strength of its workforce, its supply chain, and its equipment supply chain when it comes to drilling services; we were recently at a site just last week alongside quite a few people, and it's remarkable any time you visit a drilling or completion location to see that the individuals handling supervision on-site bring decades of experience, and the sheer depth of highly trained personnel available there is genuinely thrilling for us. So on the drilling side, we truly don't anticipate any labor difficulties whatsoever, simply because that pool runs so deep and has demonstrated such resilience. As you're aware, the rig count these days amounts to only a small share of what it was 10 or 15 years back. Consequently, plenty of experienced people exist who are capable of performing that job. The area where we feel somewhat more strain is power plant construction, since frequently the trained personnel we need are the same ones sought after by competing power generation facilities and other data center projects, and that's the spot where things get tighter. Still, I believe we've got an initiative in place that has us quite enthusiastic — especially our approach of cultivating strong ties with suppliers at the local and regional level, which has worked out very well for us. We've previously shared and discussed our collaboration with Industrial Builders, the lead construction contractor for Cape Phase I, who brings extensive geothermal expertise. Our relationship with them spans multiple years and is excellent, and since they're located in Idaho, they're situated quite near many of our project locations. In our view, forming these lasting, substantial partnerships with the correct construction companies acts as a major buffer against this strain. Beyond that, we're taking a very forward-leaning stance, which connects somewhat to our community outreach approach of establishing apprenticeship and workforce development initiatives to keep that pipeline supplied. We've hired quite a few people locally around Southwest Utah, covering roles ranging from operators all the way to making real use of our partnership with SUU, Southern Utah University, through a geothermal apprenticeship program that has also turned into a source of recruits for us. This traces back to when we set that program up years ago. I think even before folks began discussing labor shortages or companies battling each other for workers amid all these construction booms, we were already taking steps ahead of time to prepare tomorrow's workforce on the power plant construction side. Our approach of collaborating with local and regional construction partners who recognize the enormous upside in Fervo's multi-year investments in their communities, plus what we're doing around apprenticeship and other training avenues with educational institutions, gives us a great deal of confidence that we'll be well positioned to thrive in a labor market where competition is fierce. This is something we devote considerable thought to, but I believe Fervo has an excellent strategy moving forward for the drilling side of the business as well as the power plant construction side of the business.
Thanks, Tim.
I appreciate it. Hi, everyone. I'm grateful you're letting me ask. If we could return to the behind-the-meter topic for one additional moment and build on what was discussed. On your slide five, I completely understand that your team only makes announcements once there's something solid to share. That's great. Regarding the one currently in progress, about which you mentioned during this call that an update might come before the year is out, does that fall behind the meter or in front of it, or did you give any details on that? And then I have another question related to slide five.
Sure, I'd say that when you look at how much demand we're seeing from customers, there's a fairly sizable number of talks that have moved into advanced negotiation, and those cover both front of the meter and behind the meter; it also kind of hinges on what's unique about each individual asset. You've also got hybrid setups, where part of a project might sit front of the meter and part behind the meter too. Looking ahead, I'd expect us to put out PPA announcements that span both of those contract structures, and it's really a continuum, with some falling in between. So I don't know whether that fully answers what you asked, but considering how far we've come in advanced negotiation with several parties, it's sort of a mix of all of it.
All right, that's excellent. Thank you. I just have one additional question. Looking at slide five, this reflects your present perspective on hyperscalers at 50% of data centers, large C&I at 15%, and so forth. Correct? Internally, do you maintain a projection you're operating from regarding the potential scale of behind the meter, and does that shift as time goes on? Basically, is that 50% mostly just a response to a grid that's constrained at the moment? Could you share anything about what you anticipate that becoming across the coming years?
Okay, that's a fair question, Sunaina. What we're seeing involves a few distinct factors. First, regarding the roughly 50% we're engaged with on the hyperscaler side, our aim is to demonstrate that while the AI hyperscaler surge is massive and acts as a tremendous driver for our company—something we're feeling very strongly at this moment—that doesn't imply other power sources or consumers don't also require the reliable power we deliver. Throughout the industrial sector and among other non-data center industrial consumers, we currently maintain a solid variety within our origination mix. Concerning behind the meter in particular, we view it as a substantial prospect. Over roughly the last 12 months, there were inquiries about the way parties would ultimately secure behind-the-meter arrangements that could be financed. We've now observed the market begin to announce multiple agreements of this kind, which truly prove that behind the meter is achievable—technically and contractually, as well as from a financial and debt angle, which is essential for getting these projects constructed. We perceive a tremendous chance in that space, yet that doesn't diminish the benefit the grid delivers. I'd say we're tremendous supporters of the grid, and believe our customers share that view. Where chances exist to utilize the grid, exactly as Tim Latimer mentioned, we'll pursue that and we'll do both. However, behind the meter is becoming a highly efficient link for customers who frankly require power immediately, faster than the grid can adapt to serve them, and later on when we'd favor—and I believe they'd favor—having those assets connected to the grid.
Great. Thank you, David.
Hi, everyone. I appreciate you making room for me here. I suppose, well, it's obvious that quite a few questions and a fair bit of chatter have been circulating in the market regarding perhaps the technical sides of EGS development, such as well production outcomes, water loss or consumption, and seismicity. Tim, you touched on this somewhat during your opening remarks, so perhaps you could help inform the general public and the investor community about those technical dimensions of EGS, and even speak to obtaining that $421 million in non-recourse project debt financing for Cape Phase I along with how much due diligence went into it. I believe it would be beneficial for everyone to hear your perspective when it comes to helping put to rest and ease some of those worries that exist out there.
Yes. I'm grateful for the chance, Derek, and that's an excellent point. I believe people frequently overlook that we finalized earlier this year that $421 million debt package. It's non-recourse project finance debt, which represents something of a landmark for enhanced geothermal systems. I think it has been fascinating for us to observe, I'm not sure, the keyboard warriors or others attempt to weigh in on various technology results when frequently they lack subject matter expertise in geothermal, and they also don't possess access to the data that the independent engineers and the underwriters of a process such as that did possess. I think when we examined this, it's something we take considerable pride in. First of a kind project finance is kind of the holy grail when it comes to scaling new hardware technologies. We got across that finish line owing to how robust this is. What we heard back from our banking syndicate regarding diligence questions fielded and scrutiny applied to the project is that it was unlike anything they had ever witnessed previously, simply because the complications of geothermal and new technology meant an enormous amount of scrutiny was placed on it. So this project received a significant amount of review from a deep bench of qualified independent engineers and underwriters who evaluate everything from scenarios involving water loss to scenarios involving thermal decline. I think the results speak for themselves, that those folks with access to the data, with access to the field results, and with the right subject matter expertise to examine this, recognize the technology maturity and grasp the things we've discussed at length, like how thermal decline isn't some binary output; that's frequently how we see the conversation framed, as either a yes or a no, but actually, it's something that, as I said in my opening remarks, thermal decline is something that occurs because physics works. You're extracting heat, and consequently, you expect that reservoir to cool off over time. Yet when you genuinely take the time to dig into the numbers and construct financial models, it becomes clear that outcomes across a broad spectrum for something such as thermal decline can vary widely, since we're able to reduce that decline by drilling hotter, newer wells within our make-up well drilling program — which, from the standpoint of project returns, is actually quite capable of being mitigated. I value the chance to say this again, because that is what we believe it signifies in terms of project finance: the people who possessed all the appropriate subject matter experts along with data access and scrutiny concluded that these projects were bankable; for us, that carries far greater weight than any of the noise and speculation you might encounter out there, and in my view it genuinely reflects how mature our technology has become.
Great. No, I believe that's quite useful. So for my follow-up question, David, this one may be directed at you, though it just builds on what we were saying about thermal decline and the make-up well topic. I suppose it would help if you could explain it from something like an NPV for each well standpoint, and also the make-up wells drawing on the surface facilities that are already there. I realize they'll be wells that are hotter and produce more, but maybe also from an NPV angle, with every new well taking advantage of what's already in place, and give us some help on the economics of the project as a whole.
Yeah. Derek, I appreciate that question, since that's really how we view this ourselves, and we'd like others to adopt the same perspective. There are a few advantages we enjoy in this situation, and you hit on one of them quite precisely: the wells we'll drill going forward will represent a significant improvement over those completed before that asset reached COD, simply because we've kept gaining knowledge and kept drilling within those particular fields. Another edge we have here is straightforward — the time value of money. When we look ahead to drilling additional wells, it's worth remembering that roughly 50% of our pre-COD CapEx goes toward drilling, completing wells, and the well pad facilities tied to them, while the other half covers the power cycle and surface power generation equipment. So what we're really discussing is drilling just a piece of that first half — the subsurface-related portion — and clearly that work happens several years down the road. As a result, the impact on project returns is fairly limited. What we frequently observe is that given the spectrum of possible results regarding what we can supply under our PPAs — and since our PPA pricing is favorable — the returns indicate that under most circumstances, adding one more well would be our preference, since that newly drilled well produces more than the wells we initially brought online. That allows us to supply more than the anticipated baseline quantity of power under those PPAs, which we view as a appealing chance to put capital to work at a strong return.
Great. Appreciate the color, guys. I will turn it back.
Thanks. That wraps up the conference call for today, everyone. We appreciate you joining us. You're free to hang up now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Fervo Energy Company transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Fervo Energy Company earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.