Earnings Call Speaker Segments

Operator operator
#1

We appreciate everyone being on the line. I'm the conference operator speaking. Good day, and welcome to the K92 Mining conference call covering financial results for the third quarter of 2025. <<operator_script>> Please note that this conference is being recorded. <<operator_script>> At this point, I'll hand things over to David Medilek, our President and COO. The floor is yours.

David Medilek executive
#2

Thanks, operator, and I appreciate all of you joining us for K92 Mining's conference call on the financial results for the third quarter of 2025. We hope things are going well for you and your families. Joining me on the line are John Lewins, our Chief Executive Officer and Director, as well as Justin Blanchet, our Chief Financial Officer. I'd also like to remind everybody that once management finishes its remarks, a Q&A session will follow the call. Since forward-looking statements will be made during this call, we ask that you refer to the cautionary notes and risk disclosure found in our MD&A and on Slide 2 of the webcast presentation. Also, please keep in mind that unless otherwise noted, every dollar figure mentioned on this conference call is stated in United States dollars. Now I'll hand things over to John for an overview.

John Lewins executive
#3

Thank you, David, and hello to everyone joining us. Safety comes first at K92 — it's our top priority. I'm delighted to report that during the third quarter the company had zero lost time injuries, which makes 9 straight quarters without an LTI — a remarkable accomplishment given that activity keeps rising as our Stage 3 Expansion moves forward. Across the past 2 years, we've seen a big lift in field-level risk assessments, hazard identifications, safety observations, safety technologies, and the size and skills of our safety team — all of them strong leading indicators of a solid safety culture. Safety remains one of K92's core values at all times, and we stay firmly committed to our ultimate aim of zero harm for our entire workforce. After the quarter closed, the company hit a major milestone: the official inauguration of our Stage 3 Expansion process plant took place on September 16, along with first production of our saleable concentrate. Attending the event were the Prime Minister of Papua New Guinea, the Honorable James Marape; the Minister for Mining, the Honorable Rainbo Paita, as shown in the photo; other distinguished government representatives, landowners, members of the diplomatic and business community, and the K92 Board and project partners. The process plant was delivered safely, efficiently and under budget — a major achievement for the construction team.

John Lewins executive
#4

The Prime Minister and the Minister for Mining were also present at a gold pour at the new process plant, which you can see in the video that accompanies this presentation. They also took a helicopter tour of the mine site and the regional exploration areas, along with an underground tour that highlighted several major infrastructure upgrades now completed — among them the twin incline and material pass, which are, of course, key enablers for our Stage 3 Expansion. In August, we were also honored to host a delegation led by the Mining Minister, the Honorable Rainbo Paita. That in-depth visit showcased the company's key Stage 3 Expansion growth projects, ongoing exploration activities and progress on the Konkua-Bilimoia Road Infrastructure Tax Credit Scheme project, as well as productive discussions with local community business leaders. K92 remains committed to transparent engagement and open dialogue with all of our key stakeholders. We truly appreciate the support from our stakeholders, which has been a major factor in our success. Now moving on to operations: during the quarter, the Kainantu Gold Mine produced 44,323 ounces gold equivalent at a cash cost of $694 per ounce of gold and all-in sustaining cost of $1,254 per ounce gold. On a co-product basis, cash costs were $797 per ounce gold equivalent and all-in sustaining costs were $1,330 per ounce gold equivalent.

John Lewins executive
#5

Like the chart shows, all-in sustaining costs have run well above cash costs from the start of 2023, and that's naturally because of K92's hefty spending on the Stage 3 Expansion. So we expect costs to come down substantially once the Stage 3 Expansion is delivered, and we'll get into that later in the presentation. Q3 mill throughput came in at 137,172 tonnes, matching budget, at a head grade of 11.2 grams per tonne gold equivalent. Having already hit over 80% of the low end of annual guidance across the first 3 quarters, and with roughly 4,900 gold equivalent ounces sitting in the commissioning stockpile at the end of Q3, K92 stays on track to hit its 2025 production guidance of 160,000 to 185,000 ounces gold equivalent. Turning to our key operational quarterly physicals, total material mined reached a record 353,770 tonnes, and several daily tonnes-to-surface records were also set in late September, showing the added material movement benefits we got from commissioning our first material pass during the quarter, together with surface trucks starting up in the twin incline. Total mine development was 2,477 meters. The operation keeps balancing lateral development priorities between finishing key underground projects, including giving priority to low equivalent lateral advanced jumbo activities like the Puma ventilation drive and the underground pastefill chamber.

John Lewins executive
#6

We're happy to share that October brought a major milestone for development rates, helped along by several infrastructure and operational improvement projects that were recently finished. We set a fresh monthly development record of 1,028 meters. That marks the first occasion K92 has gone past the 1 kilometer per month goal set out in the Updated Definitive Feasibility Study for the Stage 3 Expansion. This result stands out especially because, starting in June, one jumbo has been out of service at any one time for a mini-rebuild program run on site that is meant to boost equipment reliability. We are now finishing the rebuild of the last jumbo, with completion anticipated later this quarter. When that wraps up, it will in effect add one rig to our active jumbo fleet, which should further support strong development rates going forward. Beyond that, with additional key enabler projects nearing completion — these will be covered later in the presentation — we anticipate development and mine physicals will keep ramping up. Ore mined for the quarter totaled 152,485 tonnes, the second highest on record, with mining work carried out across 13 levels at Kora and Judd. Long-hole stoping was carried out to design. Process grades got a boost from positive gold grade reconciliation against the latest independent mineral resource estimate.

John Lewins executive
#7

The Stage 2a process plant kept up its strong performance, beating the Updated Definitive Feasibility Study recoveries for a sixth quarter in a row — 95% for gold and 94.6% for copper, versus 92.6% for gold and 94.2% in the Updated DFS. At this point I'll hand the call to our Chief Financial Officer, Justin Blanchet, who will go through the financial results for the third quarter.

Justin Blanchet executive
#8

Thanks, John, and good morning, everyone. In Q3 2025, K92 posted quarterly revenue of $177.5 million — a record — which was up 45% versus the same quarter a year earlier. Gold ounces sold came to 45,006 at an average selling price of $3,361, versus 45,248 ounces at an average selling price of $2,388 a year earlier. As of September 30, 2025, inventory held 7,913 gold ounces, covering both concentrate and doré — a drop of 500 gold ounces relative to June 30, 2025, reflecting the timing of sales. In Q3 2025, K92 recorded quarterly cost of sales of $43.8 million, versus $41 million a year earlier, or $35.5 million versus $30.7 million once noncash items are excluded. Higher underground activity and more tonnes mined drove the rise in cost of sales, with ore mined and processed year-to-date substantially above the prior year. That aligns with the increased mining and processing activity tied to the ramp-up of the Stage 3 Expansion. Q3 2025 cash flow from operating activities before changes in working capital reached $101.8 million, versus $61 million a year earlier — the largest quarterly increase on record.

Justin Blanchet executive
#9

By September 30, 2025, K92 held a record $185.4 million in cash and cash equivalents. Our working capital balance also hit a record, at $227.8 million, and we posted a record net cash position of $131.2 million. As of September 30, the company's loan balance stood at $55 million. K92's receivable balance as at September 30 rose 88%, or $39 million, compared with June 30, and a significant portion of that was collected in the first half of October, which drove a significant increase in our cash balance after quarter end. Importantly, the Stage 3 and 4 Expansion projects are fully funded, and our financial position is strong. We also have access to a significant amount of liquidity through undrawn credit facilities, with $60 million available to draw down on demand, plus an additional $30 million of liquidity through an accordion feature. We'd also like to highlight that our commodity price downside is protected through the cost-effective purchase of put option contracts, which extend until the end of 2025, allowing for 15,000 ounces of gold per month at a strike price of $3,000 per ounce. After quarter end, K92 purchased additional put option contracts allowing for 10,000 ounces of gold per month at a strike price of $3,500 per ounce in 2026.

Justin Blanchet executive
#10

Let me be clear — this isn't a hedge. If spot prices run above $3,000 per ounce in 2025 or $3,500 an ounce in 2026, we'll sell at spot. Think of it as insurance, and we keep full exposure to upside in commodity prices. As John mentioned, in the third quarter the Kainantu Gold operations turned out 42,244 ounces of gold; 1,323,538 pounds of copper; and 34,831 ounces of silver, which equals 44,323 ounces of gold equivalent. We sold 45,006 ounces of gold, 1,480,151 pounds of copper and 43,271 ounces of silver. On a byproduct basis, our cash cost came to $694 per ounce and all-in sustaining cost was $1,254 per ounce of gold. All-in sustaining costs in Q3 landed significantly under our net realized selling price of $3,361 per ounce. Across the 9 months ending September 30, 2025, byproduct cash cost per ounce was $669 and all-in sustaining cost was $1,202 per ounce — both under our 2025 guidance of cash costs between $710 to $770 per ounce and all-in sustaining costs of between $1,460 to $1,560. Worth noting: we'll see downward pressure on costs through economies of scale as operations ramp up and the Stage 3 Expansion is complete.

Justin Blanchet executive
#11

I'm handing things over to John now, who'll cover exploration and growth.

John Lewins executive
#12

Thank you, Justin. Now moving on to growth and exploration. First, an update on the Stage 3 and Stage 4 Expansions, which we expect will fundamentally transform K92 into a Tier 1 mid-tier gold producer. As I noted earlier, the Stage 3 Expansion process plant produced its first saleable production in mid-October. The Stage 3 Expansion, as set out in our Updated Definitive Feasibility Study, supports a throughput rate of 1.2 million tonnes per annum, producing roughly 300,000 ounces gold equivalent per annum at that run rate. Commissioning of the process plant is almost finished. Stage 4 should lift production further by expanding the Stage 3 process plant at a low capital cost to 1.8 million tonnes per annum, producing around 400,000 ounces gold equivalent per annum, with commissioning targeted for late 2027. The Stage 2a plant gives us additional capacity for future expansion beyond Stage 4. In late October, K92 was pleased to welcome a large group of analysts and investors for a comprehensive 2-day visit to the Kainantu Gold Mine, so they could see firsthand the major transformation underway on site and also showcase the mining-friendly jurisdiction of Papua New Guinea. These photos show key parts of the surface and underground site tours, including the new 1.2 million tonne per annum state-of-the-art Stage 3 process plant, shown on the image on the left, and the underground paste silo excavation, shown on the image on the right.

John Lewins executive
#13

The next slide — the image on the left — shows the primary fan chambers the visitors also toured. That excavation measures 15 meters wide by 9.5 meters high, runs 35 meters long at that profile, and tapers off across a total length of 75 meters. The picture on the right comes from the top of the material pass, which they visited as well. We'll go into more detail on these projects across the next few slides. In our view, the site visit made the strong momentum across the operation plain to see, along with the considerable progress on several transformation projects — progress that will support additional growth and productivity gains once Stage 3 and Stage 4 Expansions are delivered. I'll now give an update on construction progress for the Stage 3 Expansion, which as of 30th September 2025 had 90% of growth capital spent or committed, with the expansion still on budget. Turning to the major underground infrastructure transformation, the twin incline is finished. The first material pass is finished, and the Puma vent incline now sits within 40 meters of breakthrough. After the Puma breakthrough and energization of the primary fan system in Q1, the ventilation circuit will be set up so that both twin inclines serve as fresh air intake, which will then allow highly productive one-way traffic in the twin incline in late Q1 2026.

John Lewins executive
#14

The internal ramp system is moving forward quickly, and it will link the main mine and every mining front to the highly productive twin inclines. Completion is slated for Q1 2026 as well. Once it is finished, together with the Puma vent drive and the energization of the fan chamber, it will also allow all inclines to shift to a more efficient one-way traffic flow. The twin incline has already started transforming underground material handling efficiencies, as the image on the right shows compared with the image on the left, which is the existing incline used to access the main mine since commercial production began. The twin incline is capable of running trucks 50% larger than the existing single incline at a much faster speed, and it will also remove rehandling at the portal, since surface trucks will haul directly through the process plant after loading in that twin incline. Productivity gains from the twin incline infrastructure will be realized in stages as supporting infrastructure is completed and equipment is added. I'm pleased to report that in Q3, we completed our first material pass, using gravity to deliver tonnes approximately 350 meters vertically from the main mine to the highly productive twin inclines. This was further augmented by the introduction of surface articulated trucks into the twin inclines in September.

John Lewins executive
#15

That mix allowed us to set multiple daily-tonnage-to-surface records, among them 5,769 tonnes on September 27 and 6,404 tonnes on September 29. That works out to roughly 2.3 million tonnes on an annualized basis. We have a second material pass coming — one that lets us run dedicated passes for ore and for waste separately — and it's slated for late Q1 2026. As we mentioned before, once the Puma vent drive is finished and the primary fan chamber is energized, along with completion of the internal ramp system — both of those are set for Q1 — we anticipate additional near-term productivity improvements across the mine. We're also happy to share that the Phase 2 ventilation upgrade — which called for developing 2 large vertical fresh air intake raises — was finished recently, and it has produced a notable gain in our primary ventilation airflow, lifting it by roughly 30% to now more than 200 cubic meters per second. That has in turn brought a significant cut in our blasting reentry times needed to clear the fumes. Commissioning work on our centralized blasting system, aimed at cutting blast initiating time, is nearly done. And when that wraps up later this quarter, we intend to move to blasting twice a day, up from the current once per day.

John Lewins executive
#16

Taken together, these upgrades will add more hours of underground operating time each day, on top of the operational flexibility that comes from firing twice per day. We also expect reentry time to drop further once we break through with the Puma, which, as mentioned earlier, sits roughly 40 meters below the surface. That is projected to raise airflow to 250 cubic meters per second from 200 cubic meters per second. Combined with energizing the fan chamber, this is anticipated to produce a threefold rise in primary air flow versus present levels, reaching something above 600 cubic meters per second. That volume is well beyond what the Stage 4 Expansion requires and is built for life of mine. It could also be expanded further, to 740 cubic meters per second, by benching the Puma incline. As the images show, the fans are currently being installed. This project is scheduled for completion in the first quarter 2026. The underground mine has also recently been upgraded further with the completion and commissioning of the primary power station, which added 8.8 megawatts of generating capacity after the quarter end. That, of course, is our standby power. The plant can now power both the process plant and the underground mine, delivering better power reliability and synchronization with grid power to aid power supply stability.

John Lewins executive
#17

Our owners' team got this project done successfully, on schedule, and at roughly half the cost of the EPC tender bids we received — which is just one illustration of how the construction team has kept Stage 3 Expansion within budget. And from commissioning in mid-October onward, the operation has experienced minimal power disruptions affecting both the process plant and the underground mine, demonstrating the positive effects these key infrastructure projects will deliver by minimizing disruptions so we can increase our mine physicals. We also anticipate material operating cost benefits from the plant compared with the previous interim power plant configuration, since operating is notably better on fuel efficiency. Phase 1 of this power station's next expansion phase, to 10.4 megawatts, is planned for completion by the end of the year, and a further expansion to 15.2 megawatts — which is required for Stage 4 Expansion — is planned to be completed in the first half of 2026. Along with completing various infrastructure enablers for the expansion, mine development continues to open up 2 new fronts, the twin incline and the lower Kora, with 5 and 4 new sublevels being opened up, respectively. Both fronts are expected to be notable contributors to production in 2026.

John Lewins executive
#18

It's worth emphasizing that K92 has spent years making waste rock removal the priority in order to open the mine by developing sublevels, twin inclines, internal ramps and mine infrastructure. The plan maps shown represent levels from the lower Kora mine front, or front #2 on the prior slide, and they reveal not only the extensive development finished to date across multiple levels but also that not one long-hole stope has been mined yet from this front. Importantly, that means a significant amount of stoping inventory has been developed ahead of our expansion. The area inside the red ellipse is the K1 vein, where development is well advanced on approximately 250,000 tonnes of long-hole stoping ore. The twin incline tells a similar story. We plan to begin production of highly productive long-hole stoping in first quarter 2026 at the lower Kora front and late first quarter 2026 at the twin incline front, and these will be key drivers in the ramp-up of ore tonnes. I think it's also important to note that we have already demonstrated production rates of over 500,000 tonnes per annum from a single mining front on the main mine. Along with the completion of key enabler infrastructure projects and expansion to the number of mining fronts, we've made considerable investment in technology and equipment.

John Lewins executive
#19

On the left you see our tele-remote system for surface operations, which uses the fiber optic backbone underground to run loaders from surface — that includes during shift change and reentry, so we can get up to 24-hour operation per day. At the same time, we expect a substantial amount of new equipment to come in between now and the end of 2026, including 4 new loaders between now and June — 2 of those are replacement and 2 are additional units — and 2 new haul trucks as replacement around midyear next year. A new development jumbo joins our fleet around midyear next year, plus 2 explosive loading rigs, 1 cement agitator and 1 production drill rig. The surface truck fleet is expanding considerably for operation in the twin incline, with 8 new 60-tonne trucks planned to arrive in 2026. The first batch of 6 arrives in the first quarter. Recently, 5 new 30-tonne haulage trucks arrived on site and are being used initially to augment haulage from the twin incline ahead of the arrival of the 60-tonne trucks and the upgrading of the river crossings. Those trucks will then be repurposed to haul filter cake to the pastefill underground later in 2026. These trucks are planned to be owned and operated by one of our local joint venture contracting companies.

John Lewins executive
#20

With this sizable investment in the fleet, we're making sure there's enough capacity to cover equipment needs for both the Stage 3 Expansion and the Stage 4 Expansion. Commissioning work at the Stage 3 Expansion process plant is close to finished. Ore first arrived in September, and the first saleable concentrate was produced and shipped in the middle of October. As mentioned earlier, we held an official inauguration for the process plant on October 16. The Stage 2a process plant is now idled and can be reactivated if needed. We anticipate wrapping up commissioning of the new plant later this month and handing it over to operations. On the ancillary buildings side, the interim power station warehouse, the Kumian Creek camp and the primary power station are each finished. The maintenance facility, which carries low priority and isn't on the critical path for Stage 3, is slated for completion in late Q1 2026. During Q3 2025, we made considerable headway on the surface pastefill filtration plant, the surface storage facility and the underground pastefill plant packages. Civil works at the surface pastefill filtration plant are moving forward, as the image on the left shows, and are gaining from a recent move to day and night shift operations. Site establishment for the surface storage facility is nearing completion, with earthworks underway as the image on the right shows.

John Lewins executive
#21

We're getting close to finishing the major digging work on the underground pastefill plant, and we plan to hand it over to the projects team during this quarter. Detailed engineering is now finished. Every long lead item across all packages has either been ordered or is already sitting on site. We expect commissioning to kick off in mid-Q1 2026, and practical completion of the whole pastefill circuit is slated for mid-2026. We've also made a lot of headway this quarter on the surface haul road and river crossing project. That project lets us raise the surface truck payload from the current 20 tonnes up to 60 tonnes, and it also shortens cycle times. It means upgrading 3 river crossings, plus widening, straightening and improving gradients in selected areas so haulage runs more efficiently and payload goes up. Phase 1, which centers on the river crossing upgrades and widening the haul road so a higher-capacity 60-tonne trucking fleet can run, remains on track to wrap up by late Q1 2026. Phase 2, which centers on aligning and grading the road in select sections of the haul road, is due to finish by Q4 2026. Turning to exploration, we have 6 rigs drilling underground at the Kora, Kora South and Judd, Judd South systems, and on top of that we have 5 surface rigs turning at the Arakompa vein system and 1 rig drilling at Wera.

John Lewins executive
#22

At Kora, we have drilling underway at Kora Deeps, Kora North and Kora South Deeps, and the twin incline plus the 1205 Level drill drive are what give us access to the deeper zones. As the annotated intersections show, our drill program keeps extending high-grade zones, defining dilatant zones and stepping out mineralization. Our step-out program over the coming 12 months is mostly focused on Kora Deeps down to the 500-meter RL level, which is shown in the green rectangle. Drill drives and step-out drilling to the south are also planned. At Judd, the vein system is still significantly underexplored and open in all directions. Recent results have continued to expand the high-grade zone, as the selected annotated drill results show. Over the coming 12 months, as at Kora, step-out drilling will focus on depth extensions, shown in the green rectangle, in addition to southern step-out drilling. As our initial drill results at depth show, the system remains thick and well mineralized. Exploration activity at the Arakompa vein system, located approximately 4.5 kilometers from the Kainantu process plant, continues to advance rapidly. Drilling is now supported by up to 5 active rigs, and the deposit has grown substantially in both scale and geological understanding.

John Lewins executive
#23

The graphic shows how recent drilling has grown the Arakompa bulk tonnage zone to roughly 1.1 kilometers along strike and 800 meters vertically, with an average true thickness of 39 meters. That bulk zone is still open in several directions and keeps showing strong potential for large-scale, near-surface bulk mining. Among the latest key intercepts are 96 meters at 2.6 grams per tonne gold equivalent and 62 meters at 1.1 grams per tonne gold equivalent. We're also excited by the porphyry style copper gold mineralization discovered in drill hole KARDD0065, which steps out 250 meters to the south of earlier drilling. That was our first hole testing a 600-meter by 600-meter copper-in-soil anomaly, and it intersected 690 meters at 0.3% copper equivalent, including 395 meters at 0.38% copper equivalent within that 600-meter by 600-meter copper-in-soil anomaly. The intersection is interpreted as distilled to a potassic porphyry core, and it marks the first porphyry style mineralization found at Arakompa, a highly prospective target for ongoing drilling. This step-out discovery reinforces the scale of Arakompa and strengthens our understanding of the project as a large integrated system that links high-grade vein mineralization with a potential porphyry center beneath. Our latest drilling also keeps defining the high-grade AR1 and AR2 loads along strike and at depth, confirming continuity within the broader Arakompa system.

John Lewins executive
#24

We're also identifying what could be a thick, high-grade zone, and the standout intercepts really highlight it — 7.1 meters at 27.9 grams per tonne gold equivalent, 14.5 meters at 17.3 grams per tonne gold equivalent, and 20.6 meters at 9.9 grams per tonne gold equivalent. Taken together, those results show strong vertical continuity extending as much as 200 meters, with a substantial true thickness of 7.3 meters, which strengthens the case for a high-grade core inside the Arakompa system. Arakompa has moved ahead remarkably fast, going from only 2 holes reported in early 2024 to 67 holes reported, with 5 drill rigs operating right now. That quick scaling of the drill program reflects both the outstanding results we've received so far and how large the system is, since mineralization keeps extending along strike and at depth. We're still on track to deliver a maiden mineral resource for Arakompa in the first half of 2026. Beyond Arakompa, we've also started drill testing the newly discovered Wera vein system, a large low-sulphidation epithermal gold system measuring 3.5 by 3.5 kilometers, situated roughly 10 kilometers southwest of Kora and Judd. The initial exploration work, centered on rock chips and trenching, defined several mineralized structures with many high-grade samples, including assays reaching up to 26.3 grams per tonne gold.

John Lewins executive
#25

What matters here is that no prior operators have ever entered or tested this zone, and it sits inside the very same mineralized corridor that contains Kora, Judd and Arakompa. The potential of this new greenfields discovery has us quite excited, and we await the results of our maiden scout drill program. Finally, we want to point to the substantial pipeline of highly prospective exploration targets. Colored icons show where exploration is currently focused, while black icons mark locations we intend to drill over the next 24 months. Drilling in the near term is planned at the historic Maniape target, roughly 1.5 kilometers west of Arakompa, and at the Mati, Mesoan target, which lies within 1.6 kilometers of the current mine workings. A new small footprint heli-portable drill rig, set to begin drilling in late 2025 to early 2026, will be used for both programs. These targets constitute the next phase of near-mine exploration, which is designed to broaden our understanding of the wider mineralized system and could potentially extend non-mineralization corridors. With delivery of the Stage 3 Expansion, we anticipate not only a major inflection in our production and free cash flow, but also a significant ramp-up in our exploration budget, with the aim of advancing many of these highly prospective targets concurrently. Two additional surface rigs have been ordered, with commissioning scheduled for Q1 2026 for future ramp-up.

John Lewins executive
#26

At Arakompa, we could have as many as 5 rigs operating, plus 1 rig at Wera and 6 rigs dedicated to expanding Kora and Judd underground, which puts K92 in a strong position to wrap up yet another productive exploration year. To sum up, Q3 2025 represented another robust quarter for K92 across operations, finances, projects, exploration, and safety. Our record net cash balance and mine cash flow mean the expansion is fully funded. We are tracking well against our 2025 operational guidance, and we feel confident about sustaining the positive momentum in mine physicals for the rest of the year and on into 2026 as we capture the benefits from delivering a number of key underground infrastructure and operational improvement projects. With that, operator, we would now like to begin the Q&A session.

Operator operator
#27

<<operator_script>> Our first question this morning is from Harrison Reynolds of RBC.

Harrison Reynolds analyst
#28

Nice work on a solid quarter, K92 crew. It was great to witness the substantial advancement and momentum at the site in person when I was there back in October. I have just a few questions. To start, I was hoping you could discuss cost performance along with sustaining capital expenditure. It's encouraging that ASIC has come in under expectations and below the guided range once more. Could you share what you anticipate for sustaining capital spending in Q4 and perhaps rolling into early next year, and also break out how much of this result reflects cost discipline and items landing beneath budget as opposed to capital that has not yet been spent?

David Medilek executive
#29

Yes. Thanks, Harrison. I'll take this one — John's flight got in late this morning. So regarding sustaining capital, we anticipate it will be elevated in Q4 and continue through 2026. There are a few reasons for that. First, as you saw in the presentation, there's the haul road upgrade. The river crossings count as growth capital for the Stage 3 Expansion. The haul road upgrade is sustaining. And that work will carry on through 2026. A big portion of it is completed in the first half of 2026, but a component exists for certain sections of the haul road — select areas that do get upgraded in the latter part of 2026. Another thing I'd like to point out is the lateral advance. We've clearly ramped up the lateral advance, delivered a development record in October, and we're certainly looking to build on that, not just in Q4 but in 2026 as we keep ramping up, ultimately targeting the 1.2 kilometer per month rate that's required for the Stage 4 Expansion. Just on input cost, we've done a good job when it comes to input costs. If you look at labor, if you look at fuel, if you look at power, there's clearly the opportunity for economies of scale with the improved material movement rates that you'll get in Q4.

David Medilek executive
#30

When it comes to guidance on both ASIC and cash costs, we're definitely positioned favorably for the rest of the year.

Harrison Reynolds analyst
#31

That's encouraging to hear. And perhaps to shift topics for a moment, I'm looking ahead to the Arakompa resource next year, and I appreciate all the specifics you gave in the earlier comments. And it's still early days — but it could be worthwhile to get your current thinking on how quickly this might become an ore source for the Stage 2 mill, and also what the focus will be once the resource is out — whether that means continuing to step out and grasp the deposit's scale and size, or de-risking it and working to move it into the reserve category and get it into the mill as soon as possible.

David Medilek executive
#32

Absolutely, and thank you, Harrison, for raising that. For us, Arakompa is a really thrilling opportunity. The project actually contains 2 distinct types of projects. One is the high-grade vein system portion, with AR1 and AR2, which the results have shown you, and John covered it during the conference call. What remains evident is that more drill density is still needed in order to properly delineate those high-grade zones. A lot of the drill holes sit at spacings beyond 100 meters. There are certain places where we have tightened things up, and the results we have received there are genuinely strong. One of them is that discrete, thick high-grade zone featured in the presentation. As we step out toward the north, we are seeing the host rock change into the same host rock as Kora and Judd. So we are quite curious about what that might mean as we move nearer to that artisanal working shown on the plan view. So there is definitely that high-grade vein system upside, which makes sense as a feed source for the Stage 2a plant, though in the end it needs additional drilling to solidify it. And then there is plainly a bulk project as well, which we keep defining.

David Medilek executive
#33

What I want to highlight is that the project we see as potentially extending past Arakompa is Arakompa and Maniape together. If you look at Maniape, it has similar host rock, and historical drilling reveals truly genuine parallels with Arakompa — both show bulk intercepts as well as potential for high-grade veins. So what we have at Arakompa gets us excited. We'll find out how far we progress toward a resource, which we're aiming for in the first half of 2026. It definitely could serve as higher-grade feed for Stage 2a, though we really do need to let the drill bit play out here.

Operator operator
#34

<<operator_script>> We have no more questions right now, so that brings our Q&A portion to an end. I'd like to hand the conference back to David Medilek for any closing comments.

David Medilek executive
#35

Yes. Thank you all for being with us today and for your ongoing interest in K92 Mining. We take a lot of pride in what was accomplished this quarter, on both the operational and financial fronts. I'd also like to pause and express appreciation to our employees, contractors and partners for the effort and commitment they've shown, as well as to the various levels of government and our communities for their continued backing. Should you have additional questions after today's call, please feel free to contact our Investor Relations team. Thanks once more for participating, and we look forward to bringing you an update on further progress in the next quarter.

Operator operator
#36

That brings us to the end of today's conference call. At this point you're welcome to disconnect your lines. Thanks for joining us, and we hope the rest of your day goes well.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete K92 Mining Inc. transcript - plus 131,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to K92 Mining Inc. earnings transcripts and 131,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.