Sanghvi Movers Limited (530073) Earnings Call Transcript
November 3, 2026
Earnings Call Speaker Segments
Good afternoon, and everyone, a very warm welcome to the Q2 and H1 FY '27 Earnings Call of Sanghvi Movers Limited. Kindly note that the investor presentation as well as the financial results have been made available on the company website and the stock exchanges. Furthermore, whatever is stated on this call that mirrors our outlook for the future, or that might be interpreted as a forward-looking statement, has to be considered alongside the risks the company faces. This conference call is being recorded, and both the transcript and the audio of it will be posted on the website of the company and on the exchanges. Please also be aware that the audio of this conference call is copyright material belonging to Sanghvi Movers Limited, and it cannot be copied, rebroadcasted, or attributed in the press or media without the specific and written consent of the company. Joining us from the management are Mr. Rishi Sanghvi, Managing Director; Mr. Gaurang Desai, Chief Executive Officer; and Mr. Pradeep Mehta, Chief Financial Officer. I would now like to invite Mr. Pradeep Mehta, Chief Financial Officer of Sanghvi Movers Limited, to give you the updates for the quarter and half year ended 30th September 2026. Thank you, and over to you, sir.
Thanks, Sam, and good afternoon, everyone. I'll walk you through how we performed financially and operationally in the second quarter and the first half of FY '27, and then I'll cover our balance sheet, cash flow and capital expenditure positions. At the consolidated level, revenue from operations in Q2 FY27 came to INR 277 crore, versus INR 210 crore in Q2 FY26, which works out to 32% growth year-on-year. Total income was INR 296 crore, a rise of 36% year-on-year. EBITDA reached INR 106 crore, up 20%, with an EBITDA margin of 36%. Profit after tax came in at INR 40 crore, against INR 36 crore in the corresponding quarter, while cash profit was approximately INR 78 crore. For H1 FY27, revenue from operation climbed 36% year-on-year to INR 657 crore, and total income grew 38% to rupees INR 689 crore. EBITDA rose 25% to INR 245 crore, with a blended margin of 36%. Profit after tax was up 22% at INR 106 crore, and cash profit went up by INR 181 crore. These results show healthy growth across the group, helped by scaling up our renewables energy and engineering and construction business and by the continuing contribution from the crane rental business.
To be more specific, revenue in Q2 came in below Q1. That was mainly due to where renewable project executions normally fall, the monsoon-driven modernization in domestic activity, and the timing of crane deployment in the Middle East. We largely see this as an execution and timing effect, not as underlying demand and environments getting weaker. In H1 FY27, the group revenue mix was roughly 62% from crane rental, 36% from <<inaudible>> engineering and construction, and 2% from project EPC. For the full year, we now expect a mix of broadly 60 to 40 between crane rental and renewable EPC, versus our earlier expectation of approximately 2/3 and 1/3. The stronger contribution from assets like renewables <<inaudible>> supports our absolute EBITDA and is accretive to return on capital employed, that is ROCE. Though even it moderates the blended reported margin percentage. In the India and Botswana crane rental business, H1 total income was INR 406 crore, and treat utilization today stands at 78%, with yield at 2.24%, and EBITDA margin is 46%. The margin movement compared with FY26 reflects a high share of ancillary and externally hired equipments, crane and trailer hire service, weight and carry, insurance, and one-time inventory, as well as the performance of the project EPC segment.
Every one of those items either ties back to how revenue is mixed or happens only once. The key point is that our core crane rental franchise is still in good shape, backed by a solid order book and a healthy flow of inquiries. For the GCC crane rental operation, H1 total income came in at 39 crore, with utilization at 86% and yield at 3.80%. We also posted a positive EBITDA margin of 24. That is plainly an improvement over how the business performed during its gestation phase in FY '26. In renewables, the original investment case keeps getting confirmed, with utilization higher and yields beating what we had expected. That said, the near-term ramp-up has been held back by shipping constraints, port congestion, and late deliveries of the cranes. This renewal EPC business brought in H1 total income of INR 365 crore and an EBITDA margin of roughly 14%. It stays asset light and very capital efficient, with ROCE of 63% on a TTM, or trailing 12 month, basis. We still expect sustainable margins to land inside the range we indicated as the business grows, though execution timing and POCM accounting can produce some quarter over quarter swings. Turning to the order book, as of 23rd October 2026 the group order book was INR 1,582 crore, a rise of 26% from the INR 1,253 crore we reported earlier on 24th July 2026.
This breaks down as INR 683 crore from India and Botswana — that's the crane rental operation — plus INR 45 crore from car crane rental in GCC, and 854 crore from the renewable P&C business. Our total inquiry pipeline was approximately INR 6,700 crore, giving us a solid funnel across all business segments. Working capital performance also came in noticeably better over this first half of the year. At the group level, DSO was 81 days, with India and Botswana crane at roughly 89 days, renewables P&C under 60 days, and GCC at 165 days. In GCC it dropped from 201 days in Q1 down to 165 days in Q2, a reflection of the collection push we've made, and we'll keep prioritizing billing discipline, the certification cycle, and collections. Turning to the balance sheet, it stays strong and supports our next growth phase. Consolidated net worth rose to INR 1,398 crore as of 30th September, while gross debt was INR 805 crore. Taking into account a treasury position of <<inaudible>> INR 414 crore, that leaves net debt at INR 391 crore. Gross debt to equity therefore works out to 0.55 times, comfortably inside the FY '27 ceiling of 0.72 times, and our weighted average cost of borrowing is 8.28%.
Every other ratio sits within a comfortable band, and our cash flow convertibles look healthy. So in this first half, the cash flow we consolidated from operations came to roughly INR 231 crore in H1 FY '27, which works out to 82% of the entire FY '26 figure. That's what we managed to deliver inside six months. Turning to capital expenditures, the FY '27 CapEx ceiling is set at 583 crore, and that covers the carry forward CapEx from FY '26 along with the revised plan for FY '27. Of that total, INR 182 crore had already been capitalized during H1 FY '27, including 90 crore in Q2, so INR 401 crore is still left to be executed over the second half of FY '27. That means approximately 96% of our planned tool goes into revenue generating assets. In the Middle East, logistic disruption, vessel availability constraints and port congestion from the affected areas have pushed back the timing of our crane delivery. That is the part that hit our revised CapEx. But this portion of phase out CapEx has been re-phased into FY '28 — a disciplined response to the timing situation, not a shift in how we view the market over the long term. <<inaudible>> is being aligned with contracted demand and prioritized toward the highest return assets.
During the second quarter in India, monsoon conditions also held utilization back. <<inaudible>> deployment should pick up once project activity returns to normal levels. With that said, I'll now turn things over to Mr. Gourang Desai, our Chief Executive Officer.
Good afternoon, everyone, and thanks for being with us today. Let me start by talking about the conditions in which we're operating. When you examine the macroeconomic picture, India remains the major economy expanding at the quickest pace, with GDP up nearly 7.8% during the April to June quarter, comfortably above what had been anticipated. Since then, the RBI has changed its FY '27 growth projection upward to 7.1%. What matters more in our case is that this expansion is driven by investment. To put it plainly, fixed capital formation rose by nearly 12% this quarter, which is double the rate seen a year earlier. Investment today makes up roughly 34% of GDP. We are keeping the risks in mind. The conflict in West Asia has driven up crude prices and inflation, and in October the RBI lifted the repo rate by 25 basis points. Even so, the underlying momentum of growth is solid, and in our view the investment cycle still has many years ahead of it. Now, a brief update on the industry sectors in which we operate. I'll begin with infrastructure. Project approvals have kept coming, at least through this quarter. This September, the cabinet gave the go-ahead to railway projects valued at INR 20,000 crores. Then in October, we cleared an INR 1.8 lakh crore green energy corridor for power transmission.
When you look at what's actually happening on the ground, the heavy steel bridge launches on the Mumbai–Ahmedabad high-speed rail corridor are a perfect illustration of the complex lifting work this pipeline generates. In cement, capacity is projected to increase from 686 million to 850 million tonnes by FY '30, with roughly 70 million to 75 million tonnes coming on stream this year by itself, and demand is anticipated to rise 7% to 8%, which drives plant reduction and waste heat recovery work for us. Steel capacity should climb from approximately 20 million to 30 million tonnes by FY '30. The safeguard duty reduces imports by nearly 1/3, which supports domestic expansion and once again plays into the hands of heavy lifting. Refining: in October, BPCL established a dedicated project company for a proposed greenfield refinery and petrochemical complex in Andhra Pradesh, with an investment outlay of almost INR 1 lakh crores. Thermal: roughly 36, or almost 39, gigawatt is under construction, and a further 23 gigawatt has been awarded, as the government aims toward almost 300 gigawatt of thermal capacity by FY '30. That hands us a steady stream of boiler and turbine work to lift. Nuclear power: the Shanti Act has opened the sector up to private players, and groups such as Tata, Reliance and Adani have responded to the first small modular reactor tender.
Capacity, then, is aimed at rising from 8.8 gigawatt to 2.5 gigawatt by FY '30. Wind — one of our dominant segments — added a record 6 gigawatt in FY '26, up by 46%, with 29 gigawatts under construction and a target of 100 gigawatt by 2030. So although we stay watchful about pressure from steel cost escalation, having a presence across these sectors lowers how much we depend on any single cycle. Let me move to performance. Pradeep covered this briefly, and I will be quick here. We delivered a strong first half. Revenue from operations grew 36% to INR 656 crores. EBITDA grew by 25% and PAT grew by 22%. And in Q2, revenue grew by 32% with an EBITDA margin of 20%. As Pradeep mentioned, our order book in just 13 weeks grew by 26%, and we are close to almost INR 600 crores of order booking with an inquiry pipeline of INR 6,700 crores, which gives us a strong visibility for the rest of the year. On utilization, it was 78% for the first half with a yield of 2.24% in line with FY '26 levels and within our historical range of 73% to 84%.
To pick up on the seasonality point Pradeep raised: India's Q2 utilization came in at 71%, versus 86% in Q1, which mirrors the usual monsoon dip. Even so, that figure beat the 70% we posted a year earlier, and yield improved to 2.20% from 2.04 — sorry, an improvement to 2.20% from 2.04. For the Middle East, utilization reached 86% across the first half, climbing to 87% in Q2, with yield at 3.8%, comfortably above our 3.5% target. Now we move into the second half, our seasonally strongest stretch, when India utilization typically rebounds sharply as project work restarts once the monsoon ends. Our revenue mix is shifting, and I won't spend much time on that since Pradeep already covered it. Looking forward, we're confident we have a strong runway of support for our core business, the growing asset-light crane stream, and 2 growth engines. I mean, Saudi CapEx has been deferred. Let me give a quick update on the Middle East as well. Shipping and port disruption in West Asia has pushed back new crane deployment in Saudi Arabia, and we've shifted part of the CapEx to FY '28. So this is a timing issue, not a demand issue.
The cranes we've put in place are heavily utilized and generating returns beyond what we targeted, and the business is EBITDA positive. We're phasing investment in step with orders and giving priority to the high-return assets. CapEx I won't discuss since Pradeep has already covered it. Pradeep also noted that we've made solid progress on our DSO, which is down to 81 days from 116 in Q1. Our customer satisfaction score has climbed from 7.5 to 9.18 this year, a milestone for the company. On safety, if I may say so, it stays nonnegotiable for us. I mean, we've picked up numerous safety awards, among them GE's contractor Gold Standard recognition. And we hold safety close to our hearts. We keep building a stronger organization to support growth. So on the digital journey, CRM and HRMS are now live. We'll be focusing on bringing in talent. Our offer to join ratio improved to 86%. Retention fell to 6.5% in the first half. And on our culture, we're working toward Great Place to Work. So given our first half year performance and order book, we reaffirm our FY '27 guidance of total income of INR 1,400 crores to INR 1,500 crores and EBITDA of INR 525 crores to INR 575 crores.
Demand is healthy across infrastructure, industry, and energy, and we have a growing renewable platform along with disciplined capital allocation, so we feel confident about delivering on Elevate 2030. That said, I want to thank each of you for your time. Thank you.
<<operator_script>> Our first question is from Sunil Jain of Nirmal Bang Securities.
Congrats on the strong order book growth. Sir, my question first is a data one, just about the order book. Your order book now stands at INR 1,582 crores — will that be executed during the current year, or might some of it spill over into next year as well?
So this order can be executed within this financial year. But in the E&C business, there’s always a 10% chance that things could get deferred because of various ROW issues and that sort of thing. Other than that, it’s all executable this year.
Given that your revenue guidance ranges from INR 1,400 crores to INR 1,500 crores, and additional orders might come in during the upcoming period that could be executed within the current year, does that mean there's also a chance you'll surpass your guidance?
As a management team that believes in guidance that is both abundant and prudently cautious, we reaffirm the range we previously guided to, between INR 1,400 crores and INR 1,500 crores. I'd like to restate that in the Engineering and Construction business, revenue is uncertain and revenue recognition gets delayed, since delivery on certain projects isn't within the company's control when it comes to grid connectivity, PPA offtake, site availability, WPC supply from the OEMs, and also monsoon delays that are now stretching into the third quarter. Some execution delays may also arise from our own internal challenges in delivering the project schedule for our customers. Given this, there is an 8% to 10% overflow of the existing order book, which we now communicate as INR 1,582 crores for this financial year that may spill over into the next year. So if you do the math, between INR 140 crores and INR 160 crores can spill over, which puts us back within the range of INR 1,400 crores to INR 1,500 crores.
Being cautious makes sense, sir. Sir, my second question has to do with the Middle East, since we're pushing some CapEx into next year. And the other thing is, given the limited CapEx we'll be carrying out this year, what are the chances of margin improving? We're running at breakeven level. So is there any room -- how much room exists for margin improvement from here in the Middle East?
The overall CapEx plan — that's roughly INR 80 crores to INR 90 crores — is being pushed to the next financial year. Saudi Arabia's business remains EBITDA positive at this point. Looking at how the quarter went, we actually turned a cash profit there in Saudi Arabia. Scaling up is still going to be a challenge, since we can't put more CapEx into the country. Demand, though, is there. Our inquiry flow is adequate. And once that CapEx can move forward, the scale-up will take place inside Saudi, and we expect the EBITDA margin to improve in the full-year guidance for next year.
So if this issue gets sorted out sooner, is there a chance you'd bring that CapEx into the current year itself, or would it be pushed to next year?
This isn't solely about the conflict in West Asia. The conflicts there have caused a prolonged disruption to logistics and the shipping chain, and normalizing that will take quite a while. So we're also waiting for shipping costs to return to normal before we mobilize some of the larger cranes we had planned.
<<operator_script>> Our following question is from Akshay Jawahar, who is with Banyan Tree Associates.
Thanks for the kind words about the solid order book expansion. I’d like to start with the margin decline in the cranes segment. From what I gather, the margin bridge shown in the presentation also captures the effect of other income. When I look at FY ’26, the contribution from other income was lower. My point is that the drop from 53% to 46% is partly offset by a 1.5% to 2% rise in other income, so are there additional major cost-side factors behind the margin contraction, since there is a 2% other operating cost—a negative 2%—but that would also include the 2% margin uplift from other income. So what else is driving the margin reduction?
Okay, let me first tackle what you're asking about. To start with, other income doesn't affect the EBITDA margin we outlined. That margin is calculated before other income hits the P&L. EBITDA margin does include other income. But in segment reporting, there's the thing you're pointing to on Page 31. So there appears to be a drop in the crane business's overall margin. That happens because of the accounting policy. When we report by segment, there's a single line item for a crane accident that we wrote off this quarter. So it shows up as operating expenses. Yet the income sits on the other income line. So in the segment reporting you'll see a mismatch. But looking at the overall margin, it stands at 46%...
No, look at Page 31 — what I mean is the bridge on Page 33, Page 33. There you've got another operating cost margin movement of negative 2%, and no exceptional item is mentioned anywhere in the results, so I'm kind of lost, sir...
Right. So regarding that minus 2%, when we break it down, one line item is the incentive we provided to the leadership team as well as the frontline workers — something we talked about in the Q1 presentation — because for this H1-to-H1 bridge, that's one of the reasons.
That's also been laid out on its own within the bridge.
Turning to other operating costs — you're correct that we've already reflected the minus 1% onetime incentive there. Beyond that, though, other operating costs stem from the change in the PF law, which mandated statutory requirements we have to fulfill, plus insurance cost, and that will even out over a period of time.
All right, so moving forward, should we think of an operating margin around 46%? Broadly, that seems consistent — the go-forward margin would be nearer to 46%, correct? Since the PF cost will keep being incurred, and the shift in revenue mix also looks fairly steady apart from that one-time incentive I mentioned, the other costs don't appear to be non-recurring as we go forward, right?
Akshay, you're partly correct — to some degree, contract labor costs will put pressure on margin. That said, Q3 and Q4 carry an offsetting effect as well. Once we're at full scale, this overall margin will average out, since we anticipate higher yield and utilization in Q3 and Q4. So variable cost won't be an issue, and fixed cost will be absorbed more effectively in Q3 and Q4.
So what's actually behind the rise in other income at the moment? You said something regarding income from insurance costs — apologies, I didn't catch that.
One of our assets has been impaired — it actually encountered an impairment. As a result, an insurance claim has come in for that asset.
All right. So when it comes to other expenses, the insurance claim itself lands in the other income component, not there. Is that how I should understand it?
That's correct.
Our following question is from Shriram Palaniappan with I Thought PMS.
Sir, could you give us the present range for how the cranes we have in India are distributed by age?
We don't disclose that, since it's competitive information that's price-sensitive. So we won't provide details on the age breakup. But as you can see, over the last 5 years we've deployed more than INR 2,000 crores of CapEx. Between 2020 and 2028, we would have put in place more than INR 2,000 crores of CapEx, which works out to more than 30% to 40% of our gross block. So that can serve as a reasonable proxy for figuring out the age of the cranes.
It looks like we’ve lost the connection for that question. So let’s proceed to the following question. <<operator_script>> Our next question is from Ajay Raj Singh Jhala, an individual investor — please go ahead.
Starting off, I'd like to ask what our working capital investment is likely to be for this year. And how do we see that trending going forward? Could you provide a few figures on that? Then for my second question, I realize you won't share a breakdown of the details, but could you give us some help on what the replacement cost of our current assets would be — that's all.
Across every segment and each of our businesses, the working capital draw from 1st April 2026 through today stands at 0. To this point, none of the working capital limits anywhere in the group have been tapped. Our cash flows and the collections we receive from customers are what carry the businesses. That covers your first question. Now, on your second question about replacement cost: that figure is a theoretical exercise, and we haven't calculated it in-house, since many factors feed into it — technology, currency depreciation, how much used equipment is available in the market, plus other taxation and accounting complications. A crane's useful life runs beyond 40 years. That makes it very hard to determine what the replacement value of a crane would be based on how old it currently is, okay?
Beyond the second question, I’d like to understand more clearly how the yield figure for the crane is calculated. Is that calculation based on what the crane costs to acquire?
Right. So the way monthly rental yield works is you take the monthly hiring rental and divide it by your historical cost of acquisition. So that's on a gross...
Our next question is a follow-up from Mr. Shriram Palayanappan at I Thought PMS.
Sir, even with utilization at 86% in the Middle East, our EBITDA margin stands at 24%. So you said we should expect an increase — but how would that happen, sir, given that utilization is already at the highest end?
I want to make sure it's clear that our start-up costs affect the EBITDA margin. During the first 6 to 8 months, we incurred costs while not yet generating revenue, and our commercial operations started sequentially after that. So the 23% EBITDA margin reflects the start-up cost we took on to establish the business. As time goes on, this will normalize, with the industry average margin sitting between 40% to 45%. And we're confident that, thanks to our 37 years of operating experience and our ability to run on a lower cost base, we will lift that EBITDA margin by 1 or 2 percentage points once we are fully deployed at scale.
Riya Mehta with Equitas Investments has the next question.
Let me start with Saudi. We've been hearing from quite a few capital goods and EPC companies about execution difficulties and similar issues tied to the current geopolitical situation. How do you see execution playing out there? I realize CapEx has been pushed back, but what's actually happening right now on execution in Saudi when it comes to deployment and so on?
Yes. Utilization serves as our stand-in for execution. The greater the utilization, the more work gets done on the ground. In Q1, we stood at 86%. For the first half, the figure is 78%, which mirrors a monsoon-driven slowdown. Still, we aren't observing any domestic slowdown on the ground stemming from the geopolitical situation in India. Within the GCC, we do see projects slipping, mainly because of logistics challenges plus the availability of manpower and material at site for execution. So in that region, delays of 1 to 2 quarters are showing up. Even so, utilization there stays strong at 86%. Therefore, once we reach full scale, some effects of the situation could appear in the form of logistical delays. But to date, our -- and I stand by the statement that utilization is a proxy for on-ground execution.
Yeah, absolutely. And on the full-year EBITDA guidance, you mentioned a range of INR 525 crores to INR 575 crores. Given H1, are we still holding to that guidance?
Definitely. I’d attribute that to H1 rather than HI.
<<operator_script>> Our following question comes from Prashant Jani, calling in from Moneybee Investment Advisors.
My question is about wind E&C. So, are our contracts mainly fixed price or cost plus, or do we have a price escalation clause in place that lets us pass through increases in fuel, diesel, and transportation prices?
In the E&C business, none of those cost escalations get passed along to our customers. That contract is fixed-price.
All right. Now, on the business mix — right now it sits at 31% in FY '26, and our goal is roughly 40% in FY '27 for E&C. So how are we looking at this across the coming 2 years?
You can find that breakdown of revenue or segment mix on Page #18 of our investor presentation, and it covers the next 2 years.
Sunil Shah from MM Catalyst has the next question.
Sir, if you look at Slide #27 in the presentation, it provides a breakdown of the order book. Our order book stands at INR 1,582 crores, and within that, the Middle East, Saudi Arabia and others account for INR 45 crores, which is not even 3%. In a similar way, on the gross block side, our total gross block is closer to INR 3,400 crores, but the gross block we have deployed in the Middle East is under 4%, at roughly INR 148 crores. Sir, it is clear that nobody controls the situation in the Middle East — that is a fact. However, our exposure there is not even 3% of our total business, as I understand it, whether in terms of the order book or the gross block we have deployed. Sir, if the situation drags on, which no one can predict at this moment, would we not, as a strategy, consider the India opportunity for additional growth? Would that be one way to think about things should the situation there continue for long? Because it is only 3%, 4% of the business we are doing. So could you help us understand your thought process on the strategy in a situation like this, where logistics costs are so prohibitive that meaningful business could be at risk over there?
Is there anything you can tell us about that?
Before I get to your question, I want to first discuss the initial investment thesis behind our entry into the Saudi Arabia market. The way we see it, Saudi Arabia represents a $1 trillion construction opportunity, and in our view it's fundamentally driven by 3 areas. Today: one, primarily defense; two, oil; and three, the global commitments that the Kingdom of Saudi Arabia has made with respect to the FIFA World Cup and the World Expo. Setting aside oil and gas and defense, for oil and gas and these global commitments, there's a tremendous amount of construction activity taking place in the Middle East. As a consequence, demand for cranes is high. Even in H1 — the current situation began in February 2026 — in H1, we've been able to maintain 86% utilization at a 3.8% yield and a DSO of 165, which has come down from 201. So the Saudi Arabia market is one of high demand and high yield, and we're able to collect our receivables, which in that region is pretty standard between 150 to 170 days. Now the oil and gas space, as well as the global commitments, which has resulted in a massive infrastructure buildout, continues to give us very large visibility going forward on demand for cranes.
Our hypothesis still holds true today, based on the audited performance and the figures we've shown. That covers one part of your question. The second part you asked concerns the strategy and what we do <<inaudible>>. First, we have a live inquiry pipeline worth more than SAR 216 million. Right now we can't service that inquiry pipeline because we can't get enough cranes onto the ground. Every crane we've imported into Saudi Arabia this financial year has moved from port to site, or Qatar has moved from port to site, which signals extremely strong crane demand. Now, if a situation arises where, for whatever reason, in the near future or in the very long distant future, we need to shut shop and pull out cranes — our equipment isn't like a plant and machinery, such as a chemical processing plant or a manufacturing plant. These are all mobile assets. We can relocate them easily. In fact, at the peak of the war, we moved a 600-tonne crane from India to Saudi Arabia to meet the demand available in the country.
Moving assets is definitely part of what our operating metrics cover. And should the need arise, we will make that move. But from both the promoter side and management, we see a huge business opportunity — a genuine opportunity on the ground. And it isn't just that we see an opportunity; we're capitalizing on it. And as you mentioned, the exposure comes in at under 5%.
Okay, sir, that's fair enough. Best of luck with this matter. Sir, just one thing. As of now, our gross block in that specific region comes to INR 148 crores in terms of exposure. In terms of numbers, if you could help us understand how large the gross block might be by the close of this financial year and by the close of the next financial year, so we can get a sense of how it will play out. Naturally, it can't be predicted. We are <<inaudible>>.
You can find that information on page 29.
<<operator_script>> Our following question comes as a follow-up from Mr. Sunil Jain with Nirmal Bang Securities.
Sir, my question is more about the E&C business. Installation across the industry in India is similar to last year, yet your revenue has grown over 40%. So how are you managing to gain market share? What extra or different things are you doing that let you pick up that share?
So Sunil, as you're aware, our country has elected over 20 gigawatts of wind energy out of the 55 gigawatts that exists. Sanghvi Movers Limited, the parent company, therefore has a very long legacy and a long history in this particular sector. Now, when it comes to Sanghvi Future Renewables and the growing order book, first, it's a strong signal from our customers, and that comes from our project delivery track record. Second, we are now providing full scope services to the independent power producers, where we handle land permits, approvals, the mechanical scope — which includes the crane, intercutting and installation — the electrical scope, which includes the USS, SCADA, 33-kilowatt lines, engineering and design, and civil works, which includes the WTG foundation, the crane pad pathways, et cetera. So the growth in the — while in your words, what you're saying is the installation has been on par, but your revenue is doubling, it also reflects our ability to secure orders with our customers on the basis of our track record, on the basis of our long history in this sector delivering more than 20 gigawatts of <<inaudible>>, and on the basis of taking more of the large-scale composite jobs.
Thanks, sir. And sir, a related question — with a lot of 2, 3 new players, a large group has come into this turbine manufacturing business, like Adani and JSW. So are they — can we also get jobs from them?
Yeah, Sunil, that's a good question. On Page #24 of our presentation, you'll see we covered the industry conference that took place recently in Chennai. And under point #2, we noted that framework discussions and MOUs are in place with OEMs, which position us as an exclusive EMC partner.
Akshay Jawahar from Banyan Tree Associates has the next question.
I just have a question about the borrowings part. So I think on Q1's con call previously, we basically said that part of the margin decrease was also due to the restatement of the forex loans on account of the INR and USD depreciation. Looking forward, even the additional borrowings we made in the current quarter — will our loans always be in USD, or is it also, to the extent, like how much of our mix is in INR denominated loans, and is it also possible to have INR denominated loans, sir?
Okay, Akshay, that was a restatement done on a mark-to-market basis regarding the intercorporate deposit we extended to KSA. Under accounting rules, we have to reinstate the <<inaudible>> using the rate in effect as of that text date. So yes, during Q1 it hit the P&L negatively; in Q2, though, the currency movement offset that effect. In short, it is purely an MTM accounting entry.
Right, so that was on the inter-corporate deposits rather than the loans we took from banks — is that USD denominated, or is it INR denominated?
When it comes to India, our borrowing is done in INR; for KSA, we borrow either in the local currency or in USD, and those currencies are pegged...
Our next question comes from Rohan Mehta, who's on the line from StratEasy.
I’ve just got one question. For the project EPC segment that ran into some kind of mishap, could you give me some guidance on how that will play out going forward?
Project EPC is one of our business verticals that we don't report on a standalone basis; instead, it sits within the stand-alone results. We're currently winding that segment down, and we expect to finish the revenue recognition in Q2 and Q3 of this year. Because of that, management anticipates reversing the negative EBITDA shown on Page #31 — the negative operational EBITDA on Page #31.
Our next question comes from Saket Kapoor, who is calling on behalf of Kapoor & Co.
Sir, regarding the cash flow of the plant on a consolidated basis, I believe the PPE written off comes to roughly INR 9 crores. Could you explain what the nature of that is? And what were the figures for quarter 2, sir, and quarter 1, if you're able to give the breakup...
As I believe we covered this point earlier in the session, one of our assets was impaired, so an impairment of INR 9 crore on that asset had to be incurred. That said, the insurance claim has come through, and it shows up in other income...
That gets netted off in that case. And sir, on the CapEx part for the first half, we've done CapEx to the tune — on a basis to the tune of INR 231 crores, and we also have closing balances to the tune of INR 57 crores, INR 58 crores. So what should the CapEx number be for H2? And how will the debt — our debt number align to it — have long-term borrowing that has moved up to INR 578 crores...
The FY '27 capital expenditure plan is laid out in detail on Page 29. This year's total planned CapEx comes to INR 583 crores. During Q2, we capitalized INR 90 crores, with capital of INR 182 crores. The remaining CapEx should be approximately INR 400 crores. In our business, CapEx typically lands in Q3 and Q4 after the monsoon — at least on the domestic side — since crane offtake is higher and project execution picks up once the monsoons are over. As for the debt-to-equity guidance, you can find it on page number 18. The projected debt to equity for FY '27 will be around 0.7 to 0.75.
And, sir, how much do we have coming due in the present year?
Your question is about the payments due this year on the terminal, right? Roughly INR 120 crore is left, and that's what we have to pay during H2.
<<operator_script>> Our following question comes from Manish Bhantia, an individual investor, on the line. Please proceed.
My question concerns how we're going to fund the expansion plans. Look, up to now those plans have mainly been financed through internal accruals, which come from strong cash flow from operations, along with debt, correct? But now that we're seeing the cost of debt rising, and at the same time we have aggressive international expansion plans, so are we looking at, you know, weighing options for raising capital, perhaps via a rights issue, or, you know, listing one of our subsidiaries through an IPO, in order to raise funds, you know, not just to finance our expansion plans but also to retire debt so as to improve profitability at the net level and at the same time improve EPS? Because if our EBITDA margins are, you know, getting impacted, then at least at the net level, you know, we can improve profitability.
At this point, no — we aren't planning to raise any equity.
Our next question comes from Satish Awati, who is calling on behalf of S. L. Awati and Co.
Sir, my first question concerns the order book. That figure you cited of INR 1,582 crores — does it represent the balance as of 30th September, or has part of it already been executed during H1?
That represents the entire order book for FY '27.
All right. For FY '27, what does the total come to at this point? What's the balance sitting at now?
Our backlog, excluding the audited figures and the published figures.
All right, sir. Sir, my second question: on your earlier Q1 call, you said the yield came in at 4% of GCC. Now you're citing 3.8%. So could you just walk me through how that came down, or...
The yield has declined since pricing has softened as overtime was cut back during this quarter. What’s essentially happening is that supply chain disruption means material and manpower can’t reach the job site. As a result, cranes aren’t being run on overtime in Q2 in the KSA region. Q1 carried an OT impact. In Q2, there was less OT because supply chain disruption delayed manpower and material availability at site.
So this is going to go up next quarter, right?
In a perfect scenario, that would be the case.
Since we’re short on time, this will be our final question. Our next question comes from Ajay Singh Jhala, who is an individual investor — please go ahead.
My question relates to KSA, and perhaps you could answer it at the India level as well. What sort of IRR are we targeting on those cranes and the ancillary equipment we're currently putting money into? That's all.
So normally, IRR is an internal metric that we've set ourselves for deploying capital as part of how we allocate it. What we ask investors to focus on is ROCE, ROE and yield. In India, the yield we're targeting is roughly 2%, and in KSA we're targeting somewhere between 3.8% and 4%. The ROCE we've guided to is about 16%, and return on equity is roughly 16% too. We've also provided forward guidance on return on capital employed at a blended level on page number 18 for FY '27 and FY '28.
That was the final question. I'd like to turn the conference call back over to management for closing remarks.
Thanks, Sam, for moderating this discussion. I appreciate all the investors and participants for spending part of your busy day with us. I'd also like to express my gratitude to the management team and to my employees Abhijit, Pradeep, and Gaurang, who have joined us on this call. Beyond that, my thanks go out to every one of our employees working on the front lines, representing the company on your behalf. And lastly, happy Diwali to everyone, and we'll see you again at our Q3 presentation.
Thanks a lot, and happy Diwali to you as well, sir. That brings us to the end of this conference call on behalf of Sanghvi Movers Limited. Thank you.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Sanghvi Movers Limited transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Sanghvi Movers Limited earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.