Sempra (SRE) Earnings Call Transcript & Summary
August 6, 2026
What were the key takeaways from Sempra's August 6, 2026 earnings call?
In the second quarter of 2026, Sempra reported GAAP earnings of $796 million or $1.21 per share, a significant increase from $461 million or $0.71 per share in the same quarter last year. Adjusted earnings also rose to $762 million or $1.16 per share, compared to $583 million or $0.89 per share in Q2 2025. Management affirmed their full-year 2026 adjusted EPS guidance of $4.80 to $5.30, maintaining a long-term EPS growth rate outlook of 7% to 9%, signaling confidence in their capital plan and operational execution.
What topics did Sempra cover?
- Strong Earnings Growth: Sempra's adjusted earnings increased notably, with a reported $762 million or $1.16 per share, up from $583 million or $0.89 per share year-over-year. Management expressed satisfaction with the performance, stating, "we're very pleased with our performance in the first half of the year, and think we're well positioned to deliver another year of strong financial results."
- Capital Recycling Initiatives: The company is progressing with the sale of a 45% equity stake in SI Partners, expected to close later this quarter, which will help simplify the business model and deconsolidate nearly $9 billion of debt. Jeff Martin noted, "this transaction directly supports our corporate strategy by recycling capital into our regulated utilities."
- Oncor's Growth Opportunities: Oncor is positioned for significant growth due to increasing electricity demand in Texas, with a capital plan of $47.5 billion and an additional $10 billion in incremental capital opportunities. Management highlighted, "Texas is continuing to experience unprecedented growth in electricity demand as evidenced by ERCOT's new all-time peak load of 91 gigawatts that was reached last month."
- Batch Zero Process and Regulatory Environment: The PUCT's approval of ERCOT's batch zero process is expected to facilitate large load customer interconnections, with 44 gigawatts of demand projected. Management emphasized the importance of this process, stating, "the key takeaway here is that we have a growing confidence in Oncor's execution of its base capital plan and incremental capital opportunities."
- California Wildfire Legislation: Management remains optimistic about potential wildfire liability legislation in California, emphasizing the importance of addressing livability and affordability. Jeff Martin stated, "I continue to believe that the right people are focused on the right set of issues, and I continue to believe that we'll see solid progress during this legislative session."
What were Sempra's August 6, 2026 results?
- GAAP Earnings: $796 million (compared to $461 million in Q2 2025)
- Adjusted Earnings: $762 million (compared to $583 million in Q2 2025)
- Full Year 2026 Adjusted EPS Guidance: $4.80 to $5.30 (affirmed guidance)
- Oncor's Capital Plan: $47.5 billion (includes $10 billion of incremental capital opportunities)
Sempra's strong earnings growth and affirmed guidance reflect a solid operational foundation and strategic focus on capital recycling and growth in Texas. Investors should monitor the progress of regulatory developments in Texas and California, as well as the successful execution of the capital plan, as potential catalysts for future performance.
Earnings Call Speaker Segments
Good morning, everyone, and welcome to the second quarter 2026 earnings call for Sempra. You can access a live webcast of this teleconference along with the slide presentation on our website, in the Events and Presentations section. Joining us today are several members of our management team, including Jeff Martin, our Chairman and Chief Executive Officer, and Karen Sedgwick, Executive Vice President and Chief Financial Officer. We also have Justin Bird, Executive Vice President of Sempra and Chief Executive Officer of Sempra Infrastructure; Caroline Winn, Executive Vice President of Sempra; Allen Nye, Chief Executive Officer of Oncor; Diane Wills, Vice President, Controller and Chief Accounting Officer; and other members of our senior management team. To start, I'd like to note for everyone that our discussion today will include forward-looking statements as defined under the Private Securities Litigation Reform Act of 1995. What actually happens could differ materially from what any such statements project. You can find the factors that might cause actual results to diverge materially discussed in the company's latest 10-Q on file with the SEC. Per-share earnings figures in our presentation are presented on a diluted basis, and certain non-GAAP financial measures will come up during our remarks. The slides accompanying this call contain reconciliations to GAAP measures, so please consult them; we'd also suggest you look over our 10-Q covering the quarter that ended June 30, 2026. I should also note that any forward-looking statements in this presentation are valid only as of today, August 6, 2026, and it's important to point out that the company takes on no obligation to update or revise these forward-looking statements going forward. Lastly, we've set up a new corporate update page on the Sempra Investors website where we'll post industrial updates, all while meeting our disclosure obligations under SEC Regulation FD. We encourage you to sign up for the e-mail alerts so you stay informed about any developments. With that, please turn to Slide 3, and let me hand the call over to Jeff.
We appreciate your joining us today. Our operating companies are delivering solid results, and our team is fully aligned around the objective of becoming America's premier utility growth business. That strong execution is evident in our financial performance so far this year, which shows double-digit growth in adjusted EPS along with positive contributions from each of our three growth segments. Karen will provide greater detail on our financial results later during this call, though on this opening slide, I felt it would be helpful to review our main priorities for the third quarter. The first of these is the pending sale of a 45% equity stake in SI Partners. The deal ought to wrap up later this quarter, and it backs our corporate strategy in a direct way: it streamlines how our business is structured, lets us redeploy capital into our regulated utilities — which removes the need for common equity under the base capital plan we have now — and takes roughly $9 billion of debt off Sempra's balance sheet through deconsolidation. Also, our capital recycling effort reaches into Mexico, where Sempra Infrastructure is moving along well on divesting Ecogas. A key regulatory green light came through recently, keeping that transaction on schedule to close later this month. To wrap up, beyond the update Sempra Infrastructure gave last week, the team is still concentrating on commissioning at ECA LNG Phase 1 — a top priority as they keep pushing that project toward full commercial operations. Sempra Infrastructure is likewise encouraged by the ongoing progress at Port Arthur LNG Phase 1 and 2, both of which are still on schedule and within budget. Let's move to the following slide. Texas keeps seeing extraordinary growth in electricity demand, as shown by ERCOT's record peak load of 91 gigawatts set last month. Given the expectation of substantial low growth ahead, Oncor is strongly placed to take part in what we see as an investment opportunity spanning multiple decades, centered on modernizing and extending the electric grid. Major investment drivers, including new high-voltage transmission projects and other system upgrades, are accounted for in Oncor's current capital plan. As you'll remember, Oncor is carrying out a 5-year base capital plan of $47.5 billion, along with $10 billion of incremental capital opportunities through 2030. During the first half of the year, Oncor has made considerable progress in solidifying these incremental opportunities — in particular the $4 billion of North and Central Texas transmission upgrades that ERCOT recently endorsed. Beyond that, Oncor has further incremental capital prospects: $3 billion in additional non-Permian basin reliability plan projects that ERCOT endorsed in 2025, plus $3 billion of investment that is part of the system resiliency plan filing Oncor is expected to submit next year. Looking forward, we also anticipate a fresh set of capital opportunities. For instance, this slide makes clear that any extra investments needed to serve load stemming from the batch zero process sit outside Oncor's $10 billion incremental capital opportunity. Let's move to the following slide, where we'll cover preliminary expectations regarding ERCOT's batch zero process. The PUCT recently gave the green light to ERCOT's batch zero process, and that sets up a system-wide method for choosing and ordering interconnection requests from large load customers. The timeline for the batch process is still uncertain, but 44 gigawatts of large load requests are expected to qualify as base or studied load on Oncor's transmission system. Broken down by classification, that covers 27 gigawatts of base load — defined as needing no further interconnection studies or allocation — plus 17 gigawatts of studied load, which will be assessed and assigned through a new system-wide reliability analysis. To give you a sense of scale, that 44 gigawatts of added demand represents a 140% increase over Oncor's current system peak load of 31 gigawatts. And importantly, this projected load meets all of the PUCT eligibility requirements. Oncor holds close to $6 billion in collateral from large load customers, including more than $2 billion tied to the 44 gigawatts of batch zero submissions shown here. Of those 44 gigawatts, it's worth noting that roughly 8 gigawatts is already connected to the system and keeps ramping toward full utilization. That shows demand growth in Texas isn't merely a forecast — it is actively happening on Encore's network. ERCOT is about to look at how the projects in the batch 0 process impact the transmission system that's already in place, and it will share the first results from that study. If ERCOT determines that Oncor needs to build more transmission, the capital spending on those projects would be added on top of Oncor's base capital plan and would amount to incremental CapEx opportunities. Looking ahead, Oncor plans to refresh its 5-year plan during our fourth quarter call, and because ERCOT's present schedule for pinpointing extra transmission projects is expected to extend beyond February of next year, we don't anticipate that the roll forward plan will contain new capital investments connected to batch zero. The main point is that our confidence is rising when it comes to Oncor carrying out both its base capital plan and additional capital opportunities, and we see more and more momentum building behind Oncor's long-term growth independent of how data center expansion actually plays out across the state. Now, please move to the following slide, where Karen will take us through our financial results.
Thanks, Jeff. Earlier today Sempra reported second-quarter 2026 GAAP earnings of $796 million, which works out to $1.21 per share. For comparison, GAAP earnings in the second quarter of 2025 were $461 million, or $0.71 per share. Adjusted earnings for this year's second quarter totaled $762 million, or $1.16 per share. That's a sizable jump from the $583 million, or $0.89 per share, we posted in the second quarter of 2025. As Jeff noted, we feel very good about our performance through the first half of the year, and we think we're set up well to post another year of solid financial results. Let's move to the next slide. Moving on, we'll now walk through the adjusted earnings variances for Q2 2026 compared with the equivalent quarter last year. Equity earnings at Sempra Texas rose by $138 million, which came from new base rates — interim rates included — the UTM, additional invested capital, and customer growth, partially offset by greater depreciation, interest expense, and O&M. Because Oncor's comprehensive base rate settlement was approved in April 2026, our second-quarter results carry a favorable impact of roughly $50 million tied to the first quarter of 2026; that figure represents the gap between the newly approved rates and those previously in effect for that period. Now shifting to Sempra California. Profit rose $24 million, mostly driven by a larger CPUC base operating margin after operating expenses, plus stronger electric transmission margin, though lower AFUDC equity partly offset that. Sempra California also recorded $11 million less in earnings because of greater net interest expense and other items, partially offset by bigger income tax benefits. Over at Sempra Infrastructure, earnings climbed $26 million, largely thanks to reduced depreciation on assets held for sale and lower O&M and other costs, partly offset by higher income tax expense. Sempra Parent's results came in essentially flat versus the prior period. Let's move on to the next slide. We're reaffirming our full-year 2026 adjusted EPS guidance range of $4.80 to $5.30 and our 2027 EPS guidance range of $5.10 to $5.70, given strong results so far this year and progress on our key initiatives. We're also reaffirming our projected long-term EPS growth rate of 7% to 9%. Looking ahead, execution remains our focus — including closing the SI Partners transaction, strengthening the balance sheet after close, and continuing to advance our record $65 billion capital plan. That capital plan is centered on utility growth, with investments increasingly directed toward Sempra Texas. The growth we see there is supported by robust economic activity, rising electricity demand, and the need to modernize and expand the electricity network across the state. I should also mention that, as our confidence grows regarding the $10 billion in incremental capital opportunities at Oncor, we expect Texas to keep accounting for a bigger share of our business—our aim is for it to make up more than 60% of Sempra's total rate base in 2030. All of this together, this investment outlook reinforces how confident we are in Sempra's growth over the long term. Since Sempra's projected long-term EPS growth ranks among the strongest in the sector, we think the company continues to offer investors an appealing mix of present yield, durable earnings growth, and long-run capital appreciation. With that, we'd like to open things up for your questions.
This is Constantine calling in for Shar. To kick things off down in Texas, the obvious thing everyone's asking about is the data center pause — is that real talk or not? Do you see a risk that people push for generation, or even behind-the-meter solutions, rather than transmission build, and how would that hit time lines here, particularly given that you're pointing to the batch zero opportunities heading into next year?
Thank you, Constantine. Let me take the data center focus first. A key message we wanted to convey on today's call is that our long-term outlook for Oncor has improved during the past quarter. We continue to see a solid opportunity for our base capital plan to move forward, along with upside capital, and a central point in our prepared materials was that anything connected to the batch process would genuinely represent additional upside beyond that. Something we're monitoring in this setting is that public policy and a great deal of the recent conversation have focused on protecting Texas families from the added costs associated with expanding the grid to serve new load customers, including data centers as you mentioned. On that front, I believe the governor and the PUC have both shown real leadership, and that counts for something. Constantine, I'd add too that Sempra signed on to the President's Ratepayer Protection Plan, and together with Oncor, we support the framework the PUCT is moving forward now. That's quite relevant to what you're asking, because it's about making sure data centers first bear the entire cost of interconnection, and second, bring residential bills down by directing part of their tariff toward subsidies for ratepayers. You can see this same model showing up in other jurisdictions too. So on the whole, I believe that when more stakeholders take part in the process, it lays the groundwork for a framework that lasts longer. And I think that point matters a great deal to our stakeholders. The process now happening in Austin, with additional input and a more inclusive approach, is meant to build a more durable framework for market participants such as Oncor to put capital to work in content. When you combine that with the better regulatory compact we got through the UTM legislation last year and the gains from the recent base rate review, those are clearly major factors behind the stronger financial results you're seeing at Oncor.
Great. Perhaps a brief follow-up on that. So the quick return to normal, sort of, helps the Oncor CapEx update at year-end. Is there any way to think about that upside to the upside converting nearer to plan by that point?
Well, I think one thing that was sort of underlying the message here is that there's considerable flexibility within that base capital plan regarding how Don Clevenger and Allen shift capital around; and clearly, some positive steps have been taken to solidify the $10 billion of incremental opportunity. So I think investors can take from this call that we expect the roll forward capital plan at Oncor will increase. And I would anticipate a fair amount of flexibility in how they sequence projects. I think the team's near-term focus, and Allen's, is to make sure we're truly engaged in the ongoing process, particularly since I think that will also be helpful to them in firming up their plans this fall, and we expect to return to you on the fourth quarter call with a robust discussion around Oncor. And clearly, and Karen made this point, this is becoming a much bigger part of Sempra. And I think as you consider the KKR transaction, Constantine, putting that in context, it's all about our pivot to become a pure-play utility and allocate capital to the markets where we think investors will assign the highest value. And certainly, we believe that's Texas. I think the story in Texas continues to improve. Some of these near-term issues need to be dealt with, and that's obviously going to be a priority for Allen's team.
Great. Perhaps a brief administrative point regarding the previously announced ECA delays. What's your thinking on some of the near-term offset as we head into year-end? And is there any sequential read-through from the USI transaction, or do those run on two separate tracks?
Yes. Thanks for asking that; and a little more than a week ago we issued a press release that provided something of a comprehensive update on Sempra Infrastructure. I believe there are a couple of key points relevant to your question. To begin with, the two very large projects at Purate, Phase 1 and Phase 2 alike, remain on time and on budget. They are moving along very well. Of course, whenever you go through a commissioning process such as the one at ECA, there is a considerable degree of complexity involved. I remain quite constructive regarding the work now underway to commission that project. But Justin — you'll remember Justin serves as CEO of Sempra Infrastructure, Constantine. It would help if you could share some further details on what you discovered in the root calls analysis? And what's your view on the timeline ahead this fall.
Yes. Hi, Constantine. As you remember, once we shipped the initial cargo from ECA in July, we halted the plant for scheduled maintenance and inspections. While that was underway, we found damage to equipment tied to the facility's mixed refrigerant compressors, and we're collaborating with our EPC contractor and the OEM, the original equipment vendor, on both the root cause and our remediation plan. Given where things stand, we anticipate the project hitting substantial completion in the fourth quarter of 2026, with sales under our long-term sale and purchase agreements beginning soon after; therefore we don't expect any further delay at ECA beyond that. And again, ECA is not the — sorry, substantial completion of ECA does not constitute a condition precedent under the SI transaction.
Maybe you could speak to some of the latest political commentary regarding the 765 kV approval process and share your thoughts on whether there's any risk of that changing — or just where do you see that heading from here? Any color on that?
Sure. Let me make a couple of points here. As I mentioned in response to Constantine's question, Steve, we still believe the long-term picture at Oncor is intact and improving. Obviously, as you point out, there have been some significant recent developments. And I'll make two quick points here. I think the theme is that we remain constructive. The most important thing we're hearing out of Austin is the need to make sure we're spending enough time to fully integrate the voices and concerns from landowners, and we want to make sure, obviously, that the process is inclusive. That's been a clear directive from the governor's office, and I think that's also something that PUCT is working hard to ensure happens. The key theme that I think you're hearing people focus on, Steve, is that if it takes a little bit more time in the process stage to get to what we think is a durable framework that allows us to invest capital with more certainty, we think this process will be time well spent. I would also note that in recent Senate hearings, it's very clear that there are two priorities being focused on. One is protecting landowner interest. And secondly, also making sure that Texas has the infrastructure needed to support its continued growth; and I think you saw some of that echoed by the lieutenant governor. And obviously, we want to make sure that the PUCT process — and Allen and his team will participate. I know it's been a very high focus for Allen to make sure that we're being inclusive of all the different voices that have a stake in the outcome here. And if I could, Allen, maybe you could provide a little bit more commentary on where you see the 765 process going from here?
Absolutely, Jeff, and thanks, Steve. So, how we're currently approaching the 765 matter is that, clearly, a hearing took place on the 29th that ran for roughly 15 hours, and after that came statements from Chairman < > and Lieutenant Governor Mattrick. As Jeff mentioned, broadly speaking, we're seeing about 2 main themes. First, I'd say state leaders are responding in a fitting way to concerns raised by landowners. Second, there's what I believe is a clear confirmation that a dependable grid and additional investment are needed in Texas; striking that balance is something we've worked hard at across all four of our Permian import projects. To offer a few examples, we sent notices to over 12,000 landowners, which exceeds what PUC rules require. We may have noticed over 11 — sorry, 1,000 elected officials. We filed 529 unique routes. We added 110 link segments directly because of public feedback, and hearings spanned 16 days. At this point, the — so the State Office of Administrative Hearings judges have issued PFDs in 3 of our 4 dockets. We expect the fourth sometime in mid-August, and those post orders now head to the PUC. The PDC can accept them, deny them, modify them, or ask for additional evidence; given the substantial reliability needs in the Permian, we're hopeful the PDC can resolve those dockets in a timely way. Regardless of what they decide, we're committed to and look forward to collaborating with our regulators, the impacted landowners. Obviously, our state officials as well, to advance a dependable grid that serves Texas and our customers while safeguarding landowner rights. So, as Jeff said, we remain constructive.
All right. And then a follow-up — or rather a separate follow-up, I suppose. Do you have any read on where things stand with the California wildfire liability legislation and, obviously, the related matters, and how confident are you that something productive will get accomplished there?
Yeah. Appreciate that question, Steve. I'd say one thing that genuinely strikes a chord with me is that the central priority for state policymakers, in my view, is aimed at the correct objective. Livability is the core theme at play. And when you consider the white paper put out by the utilities, the input from the CPUC, and the report the earthquake Authority supplied, I believe it's genuinely acknowledged, Steve, that the current situation isn't working, and to really tackle this livability question, you have to be prepared to engage with a broader ecosystem of interconnected factors. Let me give you a few, and one of them is that this legislative session has a strong emphasis on making housing more accessible and more affordable, on taking steps toward a more vibrant insurance marketplace, and on active consideration of new safeguards to mitigate risk for our families — and in addressing that whole ecosystem, I think considerable attention is going toward making sure that providers of utility services stay financially strong. So the emphasis, Steve, has to be on sound public policy for the state of California and on getting to the core of the livability issue. And if you look at some of the reports issued by both Moody's and S&P, they're plainly centered on ensuring that some form of legislation emerges that keeps utilities from moving into a higher rate environment and continues to let California remain economically competitive. So I'd wrap up by saying I think Governor Newsom and the leadership of both houses are owed a great deal of credit. They are very actively engaged on this matter. This is plainly, Steve, no simple undertaking, but I remain convinced that the right people are concentrated on the right set of issues, and I remain convinced that we'll make solid progress over the course of this legislative session. I'll leave it there and see whether you have further questions.
There's one area where I was hoping to get a bit more detail, and that's the large load pipeline in ERCOT — let me think here; so I suppose, just as I'm working through it — you've now updated the total interconnection queue at Oncor to 298 gigawatts. Last quarter, I believe you referenced 127 gigawatts of advanced pipeline. And at this point you've got the, clearly, digging deeper into batch zero, which sits at 44 gigawatts; so I suppose I'm just hoping for a bit of assistance in grasping how those relate. Is there still a substantial advanced pipeline of realistic data centers, at what point might those arrive? And how would you sort of put that in context alongside batch zero?
Thanks for asking. I'll offer a few remarks and then hand it over to Allen. But the way I'd frame it is that throughout the United States, it makes no difference if you're in PJM, or you're in the call is you're in ERCOT. We, as a country, are wrestling with how to tackle problems related to being short or net short dispatchable generation. We're working on approaches that let large load customers join the system and approaches to satisfy that growth and ensure we can assign costs in a way that shields the residential consumer. So think of this, David, as a beginning point, is a national issue. What strikes me as exciting is there's an unmistakable signal that Texas is open for business. One matter where there's strong agreement across the legislature and the executive branch is that they wish to keep advancing the Texas Miracle; and that ties back to the batch process that ERCOT is leading. Picture a scenario in which you have close to 500 gigawatts of generation on the sideline, waiting to join the system and likewise more than 400 gigawatts of large load customers. That batch process is meant to sequence generation alongside large loads. So as time goes on, it will be a sequencing effect designed to balance what we expect will be extraordinary load growth. Now here's the challenge, getting the process right matters a great deal, it's complex. And you've seen many different voices take part in the process. I believe Oncor's long-term story will keep improving; this state is focused on the right issues. And I heard someone I spoke with recently, the CEO of the U.S. Chamber, who offered a remark, David, that truly struck a chord with me, which is you may not be able to solve every problem in this country with higher economic growth, but you can't solve any problems without it; and I think Texas understands that. And I think a lot of goodwill is being expended, ensuring we have the right framework to let folks invest the capital required to serve the needs of stakeholders. Allen, if you don't mind, could you take us through roughly where things stand with your queue and what you expect the path ahead to look like?
Yes, absolutely, Jeff. Appreciate it, David. I believe your figures are accurate. To clarify, within our service area we currently have 44 gigawatts sitting in the batch zero process. You brought up the 127.5 figure from the prior call. What links those two figures is that 127.5 represented what we submitted under RTP, while 44 reflects batch zero. The gap comes from the batch zero rules being finalized in June, which differ from the RTP submission rules. Under batch, requirements included completing studies, posting 50,000 megawatt of financial security, attestations of site control, and contracted resources — that kind of thing. So that explains the spread between 127.5 and 44. On your question of whether a lot remains outstanding — clearly, you also mentioned 298. For the total queue overall, I believe we stood at 283 previously. Then, as you'll see in our earnings release, we discussed some of our growth figures. But to answer directly: yes, more is out there. Year-to-date total active requests for transmission POIs are up 15%. Excluding data centers, LC&I new requests rose 8% quarter over the same quarter last year, and active ones climbed roughly 22% — second quarter '26 against second quarter '25. So we keep seeing genuinely strong growth and genuinely strong interest. And yes, more is out there.
Great, yes, I appreciate that. And on a related note, I just wanted to get some clarity on the extra batch zero capital investment opportunities — specifically when you might be able to frame that up and put a number on it. Does that come after April of 2027, next year? Or could we get it midyear, timing-wise, just as ERCOT works through the batch process?
Thank you, David. I believe you have the timeline right. Clearly, we'll look to update both Sempra's roll forward 5-year plan and Oncor's on the Q4 call. And I think in my prepared remarks, we spoke about the fact that we believe that visibility into the additional capital we need to support the batch process as it moves forward, along with the information we receive after that. I think we'll need to revisit how we can keep being as transparent as possible following Q4, but we're excited to bring those additional numbers to you at the right time.
I just wanted to see if we could get a bit more clarity specifically on the batch process — really, what the actual next steps are. From what I understand, a good cause exception has been requested from the PUCT, and do you all believe that it gets acknowledged and then we basically continue along with the prior schedule? Or are we essentially on pause until we get past the November election — and any thoughts from Oncor on whether we could see additional legislation in the next session around those two would be helpful.
Yes. I'll offer a couple of comments, and Allen, I'd appreciate it if you do as well. I think one of the things we've made clear on this call — and I know you're on top of this, Nick — is that we've laid out a path here, and we feel good about the base capital plan at Oncor; our confidence in the additional capital opportunities is improving. And certainly, we think there will be a big backlog of new capital opportunities that fall outside of both of those two first buckets. As this goes forward, I mean we're seeing strong leadership, I think, from Governor Abbott. The PUCT has obviously taken up the issue as well; and I think as it goes forward, we'll have more visibility to it in the next few months. But Allen, maybe talk about what your expectations are for the process being firmed up and whether you think there'll be potential legislation would be helpful.
Absolutely, Nick. From our perspective, Governor Abbott's August 3 letter is clear—it requires a full verification and audit of every data center prior to interconnection. The near-term effect is, I believe, precisely what you outlined — earlier, ERCOT was set to inform TDSPs on August 7 regarding which loads might qualify for batch zero, but now it appears ERCOT plans to confer with the PUC on how to proceed and to request approval of a good cause exception tied to the batch zero timeline process at the PUC open meeting on August 20; thus you have indeed centered on August 20 as the next major milestone at which we could gain further clarity about what will happen. One more point to note: from our standpoint as well, those projects destined for batch zero were at all times going to go through validation to confirm they satisfied the new rules' criteria. And now that the comprehensive audit has shifted to the front end—in effect reversing the earlier sequence—we believe this helps the process by opening up greater participation early on and could produce a framework at the back end that lasts longer; that's about all we can say at this time.
Yeah, I think that’s a really solid observation as well, and the way this is set up is almost like reordering a process that already exists. I think the governor designed it thoughtfully to ensure there’s more input at the front end; so if we end up with a more durable framework on the back end, Nick, I’d call that a win for everyone involved in the process.
That's very clear. Thanks for laying those out. Now, if I could return to the California legislative questions. I understand there's been broad discussion that this issue affects more than just utilities in the state, correct? And everybody needs to contribute something. How should we think about where you're drawing the line on possibly trading off things such as future contributions to the Phase 2 fund?
Absolutely. Let me offer a few thoughts, and then I'll turn it over to Caroline Winn, Nick, who leads California. But in what I said earlier on today's call, I think it mattered greatly that Sempra, along with other market participants, be framed correctly; and for us to get successful legislation, it truly requires ensuring it stays focused mainly on public policy and better livability, correct? So when you consider the utility side, I'd say this is less about advocating for a "utility Bela bill." It's more about ensuring everyone is united around the effort of improving the environment for California families. And I believe one result of that will be substantial benefit to California families when load serving entities are financially healthy. So that, I think, will matter. As for the legislation itself, we've been engaged. We're working through all the different constituencies. I've been quite pleased with the state's leadership, and I genuinely feel good about the part Governor Newsom is playing. I think it's somewhat early for us to get ahead of the process without having bill text, Nick, before us. So I think it's important not to judge it yet. And we examine the bill in its entirety and the benefits to the full list of stakeholders before we take a position on any bright lines regarding what we might expect; but Caroline, I know you've done considerable work in this area. Could you provide some further detail for Nick's benefit?
Absolutely, glad to. Hello, Nick—what heartens us is both the continuing conversation and, more importantly, how many different solutions are on the table. And it's good to see wide acknowledgment that a more lasting wildfire framework would serve California well; even so, I share Jeff's view: judging any particular proposal now is too early, since we still need actual bill text to review and a clear picture of how it would function within the larger package. You can rely on us, though, to keep engaging constructively through the final three weeks of session—yet we don't wish to run ahead of the process. Let me close with this: our priorities haven't shifted—we will run the system safely, carry out our wildfire mitigation plans, keep financial discipline, and put investment into the system in a manner that benefits customers, communities, and long-term shareholder value. Any legislation will be measured against those principles, and we can share our assessment when the time is right.
Thanks, Caroline. And Nick, to wrap up: I said earlier that many people have reached out to us seeking our perspective on this. What I keep returning to — and I believe I've been quite clear — is that I'm constructive. My honest view is that we'll see some solid legislation this session, and I'm genuinely pleased with the leadership coming from key folks. I don't want to get ahead of the process. Caroline is absolutely right. There's a long way to go. We want to see the text language. It's a very complicated exercise; but the reason I'm constructive is, I think it's the right thing for the state. I think it's the right thing for livability. I think it's the right thing to improve affordability; and when you line it up around what's right from a public policy standpoint, then it becomes just a good old-fashioned leadership challenge, and I'm pleased with the people that are stepping forward to address it in Sacramento.
I hate to let you down, but < > for being here today < > for making the time.
That's fine. Thanks.
I realize there's been plenty of interest in this. Regarding the transmission side of the business — the earlier-stage projects, that is — do you have any perspective on whether timing has shifted for some of those certificate of convenience and necessity approvals, given everything that's happening, or would you say things remain on track?
Yes. I'd say — I would characterize them as on track, and I'll turn it over to Allen; but first let me offer a quick point that might be useful to you, Paul. Oncor's base capital plan stands at $47.5 billion. Of that base capital program, only roughly $5 billion is devoted to 765 import pathways tied to the Permian. My sense is that Allen and Don have sufficient flexibility within their capital program to adjust the timing and sequencing of those projects as needed. We still feel good about Oncor's 5-year capital plan and look forward to coming back in Q4 to update you on how we might grow it going forward; but Allen, on the specific question of where things stand with the CCNs, you feel things are on track, and we'll add additional color for Paul's benefit.
Yes. There isn't a great deal for me to add. I'll just say that I take the statements from Chairman Warner and Lieutenant Governor Patrick very seriously. We plan to collaborate with landowners and work through this process. Right now, it's simply so recent. I don't really have a very solid grasp or belief regarding what will happen, what time lines might shift, or what — I think we're just going to wait and see.
All right, that's clear. Then a quick follow-up regarding batch zero. You brought up those 8 gigawatts of load that's already being processed. Could you expand on that a bit? Does capital need to go toward it? And is that also part of the upside capital bucket? If you could shed some light on that 8 gigawatt scope?
Yeah. When you look at the 44 gigawatts we identified on today's call, the reason we highlighted those 8 gigawatts is that those are projects that have progressed and are already interconnected. So the only point being made is that for the customers already interconnected, their total utilization isn't at the 8 gigawatt level. They're connected already, and their load is expected to grow over time up to 8 gigawatts; and why that matters, and I believe we pointed this out, is it demonstrates that this load growth isn't merely a prospective opportunity. It's something arriving on the Oncor system right now.
Keeping with the Oncor upside CapEx, the batch zero sequencing versus your 4Q update looks quite clear. Could you discuss other opportunities that might land in that upside bucket from the 4Q update — presumably items such as SRP would stay in there — but I'm just trying to consider what else could turn into upside that isn't being talked about at present.
Thanks for that question, Richard. On our Q4 call we laid out how we approached the upside opportunity at Oncor; you may want to go back and reference that; but in the materials we have now, looking at Slide 4, we discuss the $47.5 billion base capital plan we announced 4 months ago. And as you can see, we've laid out the three buckets making up what we call the $10 billion incremental capital opportunity. That's $4 billion tied to these recently endorsed DSW projects, billion tied to non-Permian 765 projects. And you had it right — they do expect to make a system resiliency and filing next year. They've set aside roughly $3 billion of capital for that. That figure can shift a little. And as you point out, other opportunities may reach us before we announce this coming February. But I think we're quite constructive on those two buckets combined, the $47.5 million and also this $10 billion opportunity. And I think, Richard, one of the main things we've fielded many questions on since our last call is how this batch process fits into our current plan; and I think a really clear takeaway for us has been that the batch process is plainly an incremental opportunity beyond the $47.5 billion and beyond the $10 billion of aside capital they have, the challenge will be, as that process unfolds, we don't think we'll have much more definition on the batch-related capital until later in 2027.
Understood. Let me try putting the question another way, I suppose. So the $10 billion you're citing right now—is that all potential upside, more or less what you're basing things on? And then presumably part of that flows into the base with that 4Q update, while what's left remains upside—or are there other opportunities and programs you see that could backfill whatever shifts into the base?
Well, I appreciate you clarifying that. Let me step back a bit, since I think the past serves as prologue here. If you look back to where things stood in February of 2025, at the 100% level, Oncor had a $36 billion capital program along with roughly $12 billion in upside opportunities. Over the course of the year, they kept developing that pipeline, and by the time February of this year arrived, they had taken the $36 billion and the $12 billion and rolled out a brand-new base capital plan of $47.5 billion; and then, Richard, they restored that opportunity bucket to $10 billion. And I think that's probably roughly what we expect. We expect all or portions of the $10 billion to get rolled into the $47.5 billion. And I'm quite confident that Don and Allen will come back with a very large upside beyond that. That's what we'll cover on the February call.
I have basically one big-picture question regarding Texas, and then one about the balance sheet. Steve brought up the 765 earlier and possible delays connected to news we've been hearing. We're talking about holdups in the batch zero process. Is that the same nimbyism issue at play? It just feels like the timing of both things happening, or the news we've seen over the last three weeks, has hit a peak. Is it the same problem going on in ERCOT?
Look, Anthony, I think I'd frame it this way: all across this country, a variety of elections are taking place in November. There's a big focus on affordability. Your politics—Republican, Democrat, or independent—don't enter into it. Our focus is on finding ways to ease the burden on American households. Texas, in my view, isn't shielded from that either. Clearly, there's a process moving forward, Anthony, in which we're undertaking things at scale that no one has ever attempted. And should it come to pass, Texas will be where it happens. So I'd say the chance for electricity demand growth here is extraordinary. Alongside it, I'd add, is an extraordinary chance for capital. And I think plenty of well-intentioned people are gathered in Austin, working to ensure our process is the right one; and I think Allen has set exactly the right tone. Our goal is to be constructive in this proceeding. We aim to help meet certain stakeholder requirements; and should the result be that things take somewhat more time in order to improve the process for all involved, and we come away with a lasting framework, that strikes me as very good for Texas and beneficial over time; our outlook on Oncor keeps getting more positive.
Great. So let me shift direction here—on Slide 11 you mention Moody's. If I remember right, you're at BAA2 with a negative outlook, and they moved it to negative back in January of 2025. I'm just wondering whether there's any timing for when they take another look, or any data points they want to see before that negative outlook changes.
Yes. Thanks for asking that. Clearly, what matters most for us right now is collaborating very closely with Justin and his team to get the KKR transaction closed, and that remains on schedule for this quarter. And Karen, maybe you could speak to how valuable that transaction is from a credit perspective as well.
Absolutely, and thanks, Anthony. So the main focus right now is completing the KKR deal. As you recall, as part of our strategy, we collaborated closely with the rating agencies to shore up our balance sheet. That will assist us in increasing our funding capacity and really help us reduce some parent debt. So once the SI transaction closes later this quarter, we anticipate deconsolidating over $10 billion of debt from the balance sheet and seeing those outlooks improve. Regarding your Moody's question specifically — it's not only about completing the SI deal and deconsolidating; they were also monitoring how the SI Projects are progressing. They pay attention to particular milestones, and pipe installation is one they've singled out as significant, which Justin noted we're on schedule for. So we anticipate it will reach the level they're looking for around year-end. My guess is the changes won't come until early next year. Still, we do sit down with the rating agencies on a regular basis, we're where they want us to be, and we've been told we can strengthen the balance sheet. Beyond that, Jeff and I have discussed the chance to genuinely make the balance sheet better down the road, keeping a buffer of at least 50 to 150 basis points on average over those thresholds, and those thresholds are getting better; so I'm excited about where this takes us.
That's a really good point, and I think what you're watching us do here, Anthony, is build a stronger equity story. We're delivering solid financial results for both the quarter and the first half of the year, and we clearly have a credit story and a balance sheet story that are proving out. So we intend to bring all of that together in the second half of the year and, obviously, to meet what our stakeholders expect on the credit side.
I just want to ask one follow-up about some of what was said earlier on this call regarding California. When you consider the possible outcomes here, if no legislation moves forward this session, is there anything you could see changing with your GRC filing or other aspects of your investment strategy in California that we should keep in mind?
Yes. Thank you, Carly. Let me take you back to some of the information we put out in February. You'll remember that at the enterprise level, our utility platform is growing at roughly 11% annually at the enterprise level. If you included the extra upside at Oncor, that figure would be nearer to 13%. Within that growth portfolio, California is now growing somewhat more slowly. Rate base in California is growing at approximately 5% for us. And I believe we've got the right approach there when it comes to ensuring we meet the state's needs on safety and reliability, and there's a nod to affordability with that. I know this question has come up both for Edison and PG&E, or in a somewhat different situation, as I think we have the opportunity to keep executing our current capital plan; as for the legislation itself, I don't want to begin speaking to hypotheticals without the text in front of us. I remain constructive on legislation in the state. And I think we've got our capital plan dialed in at about the appropriate level for the future.
Alright, to wrap up, I want to thank each of you for being here today. We really do appreciate the time you’ve taken to participate. And before we close, I’d like to pause for a moment to congratulate Karen on being named the incoming CEO of the Southern California Gas Company. Also, congratulations to Justin on his appointment as Sempra’s incoming Chief Financial Officer. These are significant rotational moves, and they reflect Sempra’s long-standing tradition of developing leaders throughout our organization. We expect those rotations to take effect around the closing of the SI Partners transaction, which we are targeting for later this quarter. Lastly, we hope to see a lot of you at the Citi Conference in Las Vegas next week. If anything else needs follow-up, please contact our IR team with your questions. That brings our call to a close.
Thank you for your participation. You may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Sempra transcript - plus 131,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Sempra earnings transcripts and 131,000+ others is available through the