This is a webinar and conference call. Everyone attending is currently in listen-only mode. Should you wish to pose a question to the company, please make use of the raise hand feature inside Zoom. At this point I will pass things over to Richard Hyde, Executive Chairman and CEO of West African Resources. Thank you, Richard.
Thanks, Nathan. Good morning, everyone, and thank you for being with us on West African Resources' September quarter conference call. Joining me today are West African's Chief Financial Officer Padraig O'Donoghue and Todd Giltay, our General Manager of Finance. Notably, this was yet another record quarter of gold production for West African. Quarterly output from our Sanbrado and Kiaka operations rose to 127,950 ounces, surpassing our run rate of 500,000 ounces of gold produced per annum. Notably, we did this at an all-in sustaining cost of US$1,570 an ounce, which also represents an improvement over quarter two. Once again, both production and all-in sustaining costs are tracking well toward meeting 2026 guidance of 430 to 490,000 ounces of gold produced at an all-in sustaining cost of under US$1,900 per ounce. Gold sales were strong this quarter, with 1,000 — sorry, 135,245 ounces sold at a realized price of US$4,240 per ounce, and we remain completely unhedged. Gold sales generated cash flow from operations of roughly A$458 million. An exciting milestone this quarter was the payment of a special dividend — our maiden dividend — of 20 cents Australian per share as a reward to our shareholders. With a strong cash balance of nearly A$1.2 billion at quarter end, together with $217 million of unsold gold bullion, we intend to accelerate our debt repayments over the coming 12 months.
Padraig will walk through the financial results in more detail shortly. On the operational side, during the quarter we kept getting things ready for production to begin at Toega. Our drilling program continued to turn in further strong results. Our team delivered all of this safely and responsibly, and no significant health or safety incidents were reported in Q3. At quarter end, WAF's total reportable injury frequency rate, or TRIFR, stood at 0.87. For the most recent reporting period available, the injury frequency rate for the gold industry in Western Australia was 5.7, which keeps underscoring how committed we are to safety. Turning to each operation, Kiaka stood out, producing 76,030 ounces in the quarter, which is a 13% rise versus last quarter, helped by a 15% lift in mill throughput. Mining stayed concentrated on the Kiaka Main Stage 1 pit, where ore tonnes mined rose 13% compared with the prior quarter. The Kiaka process plant turned in a strong operating performance this quarter. During the quarter, Kiaka sold 73,492 ounces of gold at an average realized price of US$4,262 per ounce. Year to date, Kiaka has produced 209,305 ounces at a site sustaining cost of US$1,660 an ounce, and has sold slightly more than 200,000 ounces at an average realized price of US$4,559 an ounce.
Also, Kiaka was holding close to 21,000 ounces of gold bullion that hadn't been sold yet, worth roughly A$125 million. Over at Sanbrado, quarterly output came in a bit lower at 51,920 ounces, a 10% decline versus the prior quarter, largely because of lower-grade ore mined from M1 South Underground. That drop was partly made up for at the M5 North open pit, where mined ounces rose 8% quarter on quarter. Year-to-date production at Sanbrado now stands at 1 — at 151,552 ounces of gold, with a site sustaining cost of US$1,732 per ounce. During the quarter Sanbrado sold 61,753 ounces of gold, realizing an average price of US$4,214 an ounce, which takes year-to-date gold sales to 149,468 ounces at an average realized price of US$4,537 an ounce. At quarter end, Sanbrado was holding 15,224 ounces of unsold gold bullion valued at approximately A$92 million. Alongside pre-strip mining work at the Toega open pit, which carried on through the quarter, 1.6 — well, almost 1.7 BCM of material was moved, in line with Q2. In a positive step at Sanbrado, the government of Burkina Faso granted approval during the quarter for the application to update the Sanbrado life-of-mine plan so that it includes the M5 South Underground. Development work at M5 South Underground has begun, and stoping is now expected to kick off early in the second half of 2027.
The Sanbrado mine plan overall has room to maneuver, so we expect this later start to barely affect 2027 gold output. As for the explosives manufacturing and storage facility at Kiaka, permit approval is still pending, though we are finding ways to work around that. Explosives availability got better over the quarter, helped by stronger performance from the current supplier and by bringing on a second supplier. That let us put more attention on waste-stripping work at the Kiaka and Toega open pits, yet explosives supply is still an operational bottleneck that we keep managing. Talks have carried on with Burkina Faso's state-owned Société de Participation Minière du Burkina Faso, or SOPAMIB, about its purchase of the 25% shareholding in Kiaka SA for 70 billion CFA francs, roughly A$174 million. We anticipate wrapping this up in Q4. I'll now pass things to Padraig, who will walk through our financial results in more detail. Thanks, Padraig.
Thanks, Richard. During the September quarter, the WAF Group brought in A$813 million in gold sales revenue, driven by a record 135,245 ounces sold, which fetched an average realized price of US$4,240 per ounce. Q3 delivered a substantial cash build for the group. Notional net cash — figured as cash plus bullion, less debt — rose by US$220 million over the quarter, landing at US$710 million as of 30 September 2026. As we reported in our Appendix 5B, operating cash flow for the group came to A$458 million in Q3, and we closed the third quarter sitting on a record cash balance of roughly A$1.2 billion. Cash used in capital investing activities during Q3 totaled A$77 million, made up of A$25 million for Sanbrado, A$26 million for Toega, and A$26 million for Kiaka. Financing activities consumed A$38 million of cash in Q3, including A$22 million in loan repayments and A$9 million in interest payments. After the quarter closed, WAF shareholders were paid their special dividend of 20 cents per share, which came to A$229 million in aggregate. Richard, back to you.
Thanks, Padraig. As I mentioned, we're getting closer to starting production at Toega — construction of the mobile maintenance workshop, the office, and the ancillary infrastructure was largely finished during the quarter. Mining work centered on pre-production stripping at the Stage 1 Toega open pit, which I visited recently while on site, and it looks magnificent. The haulage contractor is scheduled to mobilize in late Q4, and we expect Toega ore deliveries to the Sanbrado mill to begin in early 2027. Exploration carried on in Q3 as well, with more than 13,000 meters of infill drilling aimed at the Toega underground resource — that program is still running, and results should come shortly. At Sanbrado, we published results from diamond drilling at the M5 South Underground, which targeted conversion of inferred mineral resources between the 1800 and 1600 levels, roughly 500 to 570 meters below surface, plus grade control of the lower levels of the ore reserve. The diamond drilling returned thick zones of high-grade mineralization, including a best intercept of 27 meters at 6.7 grams per tonne beneath the current ore reserves at the M5 South Underground, confirming the potential for significant ore reserve growth. We also reported results from M5 North at Sanbrado, and we're incorporating those into an updated resource model to support a final pit design update, alongside an optimization of the Sanbrado open pit mining schedule, which is also underway.
We anticipate releasing a revised 10-year output projection during Q1 2027. Through the rest of 2026, drilling will keep going as we wrap up our US$20 million exploration spend covering over 100,000 meters of planned drilling at our production centers and the exploration zones around them. Turning to environmental results, in September 2026 we began presenting WAF's 2025 Responsible Mining Report to national and regional governments along with other stakeholders. Year to date, plant nursery output at Sanbrado has risen from roughly 20,000 seedlings to almost 32,000 seedlings. Social investment efforts in Q3 stayed focused on education, health, and economic development. At the 2026 awards for the Australia Africa Minerals and Exploration Group, or AAMEG, our Sanbrado Trades Training and Qualification program earned recognition, and we received the Excellence in Social Development award. This program lets employees turn their hands-on work experience into nationally recognized trade qualifications while they stay in paid employment. To put this program in place with the Sanbrado maintenance department, Sanbrado worked alongside the government of Burkina Faso and the national training organization, CFPEM, and more than 100 employees have now finished their final assessments. At Kiaka, community health projects keep moving forward, with two new health centers over 50% complete, and refurbishment work underway at the existing facilities.
The Kiaka Livelihood Restoration Program is advancing as well, and infrastructure for agriculture, livestock, and market garden initiatives is close to being finished. Participant training and equipment distribution will be the focus of the next phase, and a fresh cohort of vocational training participants has already begun trade studies at a national training school. Across every area, our teams keep collaborating to produce outstanding outcomes: a record quarter of production, robust cash flow, and excellent community results along with rewards for our shareholders. West African is on a growth path, and we do not intend to stop. We look forward to additional drilling results in Q4, as well as scaling up activities at Toega before gold production begins in Q1 2027. We remain solidly on track to achieve our 2026 production and cost guidance as we move toward our objective of 500,000 ounces of gold produced each year in West Africa. Thank you once more for your interest in West African Resources today. I will now hand it back to Nathan for questions.
Thanks. One quick reminder — if you want to ask something, just use Zoom's raise hand feature. Our first question is from Richard Knights at Barrenjoey. Go ahead, Richard.
Hey, Rich. Congratulations on what was a pretty incredible quarter. I guess I'm just wondering how you're weighing the trade-off between making calls on capital management and putting that capital to work potentially somewhere else. Obviously, you're bringing in close to half a billion dollars each quarter now in cash flow from operations, so you've got some decisions to make. I'm just curious how, broadly speaking, you're thinking about that trade-off. Oh,
Okay, so near term, our clear priority is reducing what we owe. Over the coming 6 to 12 months, we anticipate retiring those obligations. Beyond that, we're continuing to fine-tune how Kiaka operates — we don't believe it's running at its best just yet. In my view, there's room to improve, especially when it comes to power reliability. We've brought in an HFO power station; it has reached West Africa, with a portion of it still sitting in Ghana. A substantial amount of the equipment is already at the site, and installation is set to begin early next year. Building out a 40-megawatt HFO power station will be a six-month program. That remains a fairly substantial piece of work we need to complete, and it will firmly support Kiaka's output down the road, since with the grid connection we already have, plus 30 megawatts of diesel and 40 megawatts of HFO, we'll have power well beyond what's needed to run those mills at full capacity. We have several initiatives underway right now, Richard, though we're also glad to accumulate some cash, and we'll think about what to do with it afterward, perhaps early in 2027. Those are certainly the key programs in front of us at present.
Yeah. All right. Could you refresh my memory on the capital figure for the power plant? Oh,
That amounts to a little more than US$50 million.
Yes, fine. Relative to cash flow, it's minor. Maybe one more point, specifically about the paperwork concerning the Kiaka interest being transferred to the government — that has slipped somewhat. I'm just curious how the engagement is progressing on that front, and also whether you've had any discussions at all regarding the possibility of simply obtaining clarity on your roughly 85% ownership position in Sanbrado as well?
To be honest, the talks we've had with SOPAMIB have been quite friendly, and we're nearly finished with the paperwork for that 25%. Regarding the 85% held in our other operations in the country, at this point the government hasn't raised any discussion of raising its stake there, and our dialogue with them on that subject remains quite candid and open. As things stand, nothing has changed, and we're on the verge of finalizing that 25% in Kiaka.
All right, thank you, Rich. What a strong quarter. That's all from me.
I appreciate that.
That brings us to the end of the Q&A session, so I'll now return the floor to Richard for his closing comments.
Thanks, Nathan. And once more, I appreciate all of our shareholders joining us this morning. For the company, Q4 will be yet another robust quarter on the production side, and we'll be putting out our drilling results from the underground targets at Toega, as well as from M5 North, plus additional drilling results from M5 South Underground. Watch for those, and I just want to say thanks to everybody for calling in this morning.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete West African Resources Limited transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to West African Resources Limited earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.