Alex Murray executive
#1

Hello, everybody, and thanks for joining Southland's call covering the second quarter of 2026. I'm Alex Murray, serving as Vice President of Corporate Development and Investor Relations. With me on the line today are Frank Renda, our President and Chief Executive Officer, as well as Keith Bassano, our Chief Financial Officer. Ahead of getting started, I want to note for all of you that forward-looking statements may be part of this call, as defined under Section 27A of the Securities Act of 1933, Section 21E of the Securities Exchange Act of 1934, and the Private Securities Litigation Reform Act of 1995. Such forward-looking statements aren't historical facts, nor are they guarantees regarding future performance. They carry uncertainty and sit beyond Southland's control. The actual results and financial condition of Southland could differ materially from what those forward-looking statements project. As a result, none of these forward-looking statements should be relied upon, and no obligation is undertaken by us to revise them; to review certain risks that might impact results, please refer to the Risk Factors section in our Form 10-K covering the year that ended December 31st, 2025, filed with the SEC on March 26th, 2026, along with the discussion in our Form 10-Q for the quarter that ended June 30th, 2026, filed with the SEC last night. Non-GAAP financial measures will also come up, and reconciliations are available in the press release tied to this conference call, located on the investor relations page of our website. Having said that, I'll hand things over now to Frank.

Frank Renda executive
#2

Thanks, Alex. Good morning, everyone, and I appreciate you being on the call for Southland's second quarter 2026 earnings conference. I'll start with a summary of the set of agreements we signed with our sureties. After that, I'll walk through our results for the quarter, covering the legacy dispute adjustments we booked in the period, how the wind-down of legacy projects is progressing, and how strong our current opportunity pipeline looks. Then I'll move to our strategic plan and capital structure. As all of you are aware, our sureties have supported us in two ways: direct funding and buying our term loan facility. We turned that continuing commitment into something formal — a financial assistance agreement plus a second amendment to our term loan facility. Taken together, these give us the runway required to finish our bonded work and leave the company with a capital structure that is far more sustainable. The financial assistance agreement sets the terms under which our sureties have supplied, and will keep supplying, financing for our bonded construction projects. Under this agreement, the terms hinge on whether particular sureties are issuing go-forward bonding or not. A bonding surety is one that signed the financial assistance agreement, has provided bonds to us since the retroactive effective date, and is expected to continue providing bonds going forward. The financing that comes from those sureties is known as bonding surety financing. This type of financing carries interest of 4% per year, with the accrued amount capitalized annually and added to principal. Bonding surety financing stood at approximately $59 million as of June 30th, 2026. If a surety provides financing but isn't giving us go-forward bonding, it's classified as a non-bonding surety, and the money it supplies is termed non-bonding financing. Non-bonding financing came to about $151 million as of June 30th, 2026. This deal establishes the conditions for our non-bonding financing setups with our non-bonding sureties. Those conditions cover how specific non-bonding financing will eventually be turned into senior non-voting preferred shares, in line with a preferred share term sheet included with the deal. Under the deal, every relevant surety panel has worked out the anticipated loss tied to the non-bonding financing meant to carry that panel's outstanding bonded projects through to completion. According to the preferred shares term sheet, the sum first converted into preferred shares equals whichever is lower: the non-bonding financing extended as of June 30th, 2026, or half of that panel's anticipated loss. When it comes to the non-bonding financing position we had on June 30th, 2026, our expectation is that we'll convert and issue preferred shares totaling roughly $151 million, with each surety receiving an allocation tied to how much it participates on the relevant panel. Each of these preferred shares carries a stated value of $1,000, and the liquidation preference matches that same stated value. In terms of ranking, they sit senior to every other class or series of our equity, they have perpetual maturity, and they may not be converted into any other securities the company issues. The deadline for issuing these instruments is September 30th, 2026, and nothing else in the equity stack can take priority over them unless the applicable surety panel consents. Once the projects belonging to the relevant surety reach completion, the preferred shares get trued up either higher or lower to reflect the actual loss, and that final preferred share amount is capped at 50% of the actual loss. Should the amount issued at the outset be greater than 50% of the actual loss, the extra portion goes back to being unsecured indebtedness. At completion, the total preferred shares outstanding works out to 50% of actual loss. Whatever part of the non-bonding financing does not get preferred shares issued against it will be unsecured indebtedness, carrying no interest and with no mandatory amortization payments, apart from certain net cash flows from claims plus 5% of annual operating cash flow. Once our bonded projects reach substantial completion—and as long as we haven't defaulted by then—each surety will waive the unsecured debt component of its non-bonding financing. This forgiveness is contingent on either those bonded projects achieving substantial completion or all dispositions of those projects closing within 20% of the applicable expected loss amount. We also secured an amendment to our senior credit facility as part of this agreement. So long as we remain in compliance with that facility, the amendment locks the interest rate at 4%, with accrued interest being capitalized and added to principal, and it halts both scheduled principal payments and the early termination premium. If that relief were to terminate ahead of schedule, the original interest rate would be reinstated retroactively. Taken as a whole, that works out to about $27 million in relief on cash debt service over the coming 12 months. During the second quarter, roughly $71 million was advanced by our surety partners to back active bonded projects, lifting cumulative surety advances to $210 million, not counting the Washington State Convention Center. That they keep stepping up shows belief in our plan as well as how we intend to execute. Now to the quarter's numbers: revenue for the second quarter came in at $113 million, which includes a revenue reversal of about $102 million tied to non-cash adjustments stemming from negotiations and resolutions of legacy disputes. We posted a gross loss of $71 million for the quarter, largely the result of the unfavorable legacy dispute adjustment, which cut into gross loss by roughly $94 million. We're still going after every path available to us to recover what we're owed, and we anticipate making headway over the rest of 2026 when it comes to settling these items and turning them into cash. Meanwhile, our legacy portfolio keeps getting smaller. What's left is $46 million in material and paving backlog, plus $35 million in non-M&P legacy backlog. Conditions in the markets we serve are holding up well, too. Money from federal, state, and local infrastructure sources keeps flowing into active bidding for water, bridge, marine, and tunnel projects. Turning to backlog, we closed out the quarter at $1.68 billion, compared with $2.03 billion when the year began. With the financing agreement now complete, we expect bonding backing and bid submissions to continue climbing. In our view, combining greater financial latitude, a legacy portfolio that keeps getting smaller, and healthy market appetite leaves us well placed to convert future opportunities into wins over the coming months. That's evident in the Phase Three Winnipeg North End Sewage Treatment Plant contract we announced not long ago, secured alongside our partners Aecon and NWH, worth about $190 million to Southland. There are a number of pursuits in our pipeline right now. These include additional packages at the Winnipeg North End Sewage Treatment Plant, the Claiborne Pell Bridge rehabilitation project in Rhode Island, the I-10 Calcasieu approach bridges in Louisiana, the MoDOT Liberty Bend Bridge design build in Missouri, the Bermuda Swing Bridge replacement, the MTA Bronx-Whitestone Bridge rehabilitation in New York, the Outerb ridge Crossing repairs for the Port Authority, and many tunnel, marine, and bridge opportunities across our core markets. In short, we have reached an agreement on a key piece of the strategic plan we presented in March. Our surety partners have provided capital to support execution. We've reworked our senior credit facility so that it provides substantial relief on cash debt service, and the broader financing agreement has now been completed. On that note, I'll pass things to Keith for the financial portion of the call.

Keith Bassano executive
#3

Frank, thanks, and good morning, everyone. I'll give you an overview of our financial results for Q2 2026. You can find further details and more information in the financial statements, footnotes, and MD&A, which we filed on Form 10-Q yesterday evening. Revenue for the quarter was $113.3 million, compared with $215.4 million in the same quarter of 2025. We recorded a gross loss of $71.2 million for the quarter, versus gross profit of $13 million in Q2 2025. This was driven by unfavorable adjustments related to claims on several legacy projects. During the quarter that closed on June 30, 2026, we performed a thorough review of how much we expect to recover on claims tied to a number of projects, including ones that are largely finished, factoring in recent events and fresher details regarding when recoveries might come in and how large they could be. As a result of that review, we reduced the projected worth of some claims and booked a cumulative catch-up adjustment, which cut into revenue and gross profit for the period to the tune of $102.3 million and $93.6 million, respectively. Although the company keeps pursuing recovery of amounts it believes are contractually owed, when these matters will be resolved and how they will ultimately turn out remains uncertain; the adjustments reflect derecognition of claim positions on work that has already been constructed. Our contract assets balance fell to $272.3 million at the end of the quarter, down from $389.4 million at year-end. The bulk of that balance is tied to legacy projects where construction work is already finished. Selling, general and administrative expenses for the second quarter totaled $16.7 million, up $3.1 million, or 23.1%, versus the same period in 2025. That growth was driven primarily by a $3.2 million increase in bad debt expense tied to legacy adjustments, which was partially offset by a reduction in compensation expense. Business transformation expense of $1.2 million was included in second quarter selling, general and administrative expense. For the quarter, interest expense totaled $7.3 million, a decline of $2.7 million, or 26.5%, compared with the same period in 2025, primarily attributable to a lower total debt outstanding. Cash interest for the quarter was $4 million, versus $8.5 million in the first quarter. That variance stems mostly from suspended interest service on our senior term loan. Other income reached $6.4 million, compared with $0.6 million in the prior year period, chiefly due to gains on asset sales. The improvement here is tied to something we're doing as part of our strategic plan — selling off assets that aren't central to the business and bringing our debt down. This quarter brought us an income tax benefit of roughly $1.6 million, compared with a benefit of $61,000 during the same quarter a year ago. Our effective tax rate came in at about 2% for the quarter. During our previous call, we noted that in the third quarter of 2025 we set up a valuation allowance against our domestic deferred tax assets, and by the second quarter of 2026 that allowance sits at roughly $147 million. One thing worth flagging for everybody: having that valuation allowance in place doesn't limit our ability to make use of those deferred tax assets later on. Looking at Q2, Southland stockholders saw a net loss of $84.3 million — that's $1.55 per diluted share — compared with a net loss of $10.3 million, or $0.19 per diluted share, in Q2 of 2025. EBITDA in Q2 was — $73.4 million, versus — $4.2 million in the same quarter of 2025. Like I mentioned before, $93.6 million in non-cash unfavorable adjustments related to our comprehensive reassessment of claims recoverability were the main factor behind this quarter's EBITDA. Let me now walk through how our segments did in the quarter. Our Civil segment brought in $41 million in revenue, versus $81.5 million in the equivalent period of 2025. Civil recorded a gross loss of $27.1 million, compared to a gross profit of $14.3 million during the same period last year. In our Transportation segment, revenue came in at $72.3 million, versus $133.9 million for the equivalent period in 2025. Transportation reported a gross loss of $44.2 million, compared with a gross loss of $1.3 million in the prior year's comparable period. Within the Materials and Paving business line, second quarter revenue reached $11.7 million alongside a gross loss of $16.3 million, compared to $21.7 million in revenue and a $3.8 million gross loss during the same period in 2025. M&P currently represents approximately 3% of total backlog. At the end of the quarter, our backlog stood at roughly $1.68 billion. Of that amount, we anticipate converting around 38% into revenue within the coming twelve months. Over the quarter, our surety partners provided roughly $70.6 million in advances through our general indemnity agreements to help keep projects moving forward, which lifts cumulative advances under those agreements to $209.8 million, leaving out the Washington State Convention Center. When you factor in the funds tied to the Washington State Convention Center judgment, surety payables came to $298.9 million as of quarter end. Not a single one of those amounts comes due earlier than August 13th, 2027. As for the Washington State Convention Center, the terms of repayment remain under negotiation. Frank mentioned this too — we've now agreed on a second amendment to the senior credit facility. Under this amendment, the rate is locked in at 4%, and rather than paying that interest in cash, we defer it, capitalizing it as payment-in-kind interest that gets added to principal. With this credit amendment, the scheduled quarterly amortization payments are suspended, the early termination premium is suspended, and certain early maturity triggers connected to our other indebtedness are eliminated. The facility's maturity remains September 2028. Additionally, the amendment does away with our financial covenants going forward. Under the previous terms of the facility, we had to keep at least $20 million of liquidity at all times, and a minimum EBITDA covenant was tested under defined circumstances. As amended, those requirements apply only to periods prior to March of this year. Even though getting these deals signed is a positive step, we're still centered on wrapping up the older projects, strengthening the balance sheet via monetizing assets and the surety partnership, and delivering on our main operations. At this point I'll hand the call back over to the operator so we can take questions.

Julio Romero analyst
#4

Excellent. Thank you. Hi there, good morning to Frank, Keith, and Alex. We really appreciate you all fielding our questions.

Frank Renda executive
#5

Good morning, Julio.

Keith Bassano executive
#6

Morning.

Frank Renda executive
#7

Morning.

Julio Romero analyst
#8

Hello, and congratulations on getting the financial assistance agreement and the second amendment finished. With those now executed, could you perhaps assist investors in grasping what shifts for Southland going forward when it comes to liquidity, whether you expect a need for extra surety funding past what's already being supplied, and what all of this implies for bonding capacity on new work ahead?

Keith Bassano executive
#9

Yes, this is Keith speaking. I'll begin with liquidity. This agreement gives the company the liquidity required to carry out our bonded work. The sureties have been incredibly supportive. You observed that even more this quarter through an added $70 million of bonding support, or pardon me, rather than surety payable support, to assist with supporting the bonded work. We've witnessed steady backing from the sureties, and this agreement makes that backing official.

Frank Renda executive
#10

Regarding bonding, Julio, during the opening six months of the year, our bidding activity took place while bonding capacity was limited as we pushed through that transaction. With the deal now closed, we anticipate a full bonding program backing the long-term plan. The Winnipeg North End contract we disclosed in July carries a value of roughly $190 million, which will be counted among Q3 awards, and with the deal complete, we look for bidding activity to increase.

Julio Romero analyst
#11

Great, and thanks for that detail. For my next question, regarding those preferred shares you're planning to issue—$151 million—what's the right way for common shareholders to view this? Will this be a lasting part of the capital structure? Or is it more of a short-term stabilizing measure that you intend to redeem? If you could, just put that in context for the common shareholder.

Frank Renda executive
#12

Sure. These shares are perpetual. Optional redemption provisions will be part of our negotiations. That said, those discussions are ongoing right now. There's no conversion feature on these.

Julio Romero analyst
#13

OK, wonderful. That's great. I appreciate you fielding the questions, and I'll pass it along.

Ben Taxdahl analyst
#14

Hi, everyone; this is Ben Taxdahl sitting in for Christian Schwab. I've got just a single question regarding those legacy dispute adjustments, and more specifically, looking forward. Internally, do you folks have a sense of when these adjustments will wrap up and, I suppose, when things will return to normal operations?

Frank Renda executive
#15

Yes. In the quarter, once again, these came about from a thorough re-examination of anticipated recoverability related to our claims across the project portfolio. Getting into these agreements mattered greatly for the company and mattered greatly for the business; as a result, we now have added stakeholders in the claim recoveries. We carried out this re-examination and will keep assessing claims every quarter. However, we see this as a one-time adjustment for the quarter.

Ben Taxdahl analyst
#16

Okay, folks, that's all I had. I appreciate it.

Frank Renda executive
#17

Thanks.

Julio Romero analyst
#18

Hey, everyone. I appreciate you letting me ask a follow-up. Regarding that joint venture award you announced last month, which is now in your civil backlog as of Q3, what share belongs to you? At what point do you expect it to start generating revenue? How long is that project supposed to run? Are there other efforts comparable to Winnipeg, in terms of prior-year engagements, that could turn into construction awards or later award phases down the road?

Frank Renda executive
#19

Sure. On the Winnipeg project, we're handling phase I. What we're discussing here is phase II, and we anticipate bidding on several more phases over the months and years ahead. As for our share, it's $190 million of the construction contract — a $190 million contract slated to wrap up in 2030.

Julio Romero analyst
#20

Alright. Thank you so much.

Frank Renda executive
#21

Julio, would you mind saying that latter part of your question again?

Julio Romero analyst
#22

Hey, can you hear me?

Frank Renda executive
#23

Yes.

Julio Romero analyst
#24

All right. Yes. Suppose there are additional projects comparable to Winnipeg, meaning you got involved or submitted bids alongside a joint venture partner around 2023 and 2024, and currently you aren't actively pursuing work of that scale — or at least I'd assume you weren't during the first portion of this year. Still, are there any other projects like that one, in the sense that they could realistically move toward an award during the latter half of this year or in 2027?

Frank Renda executive
#25

Yes. We have a fair number of projects of that kind. A few of them, we anticipate, will become potential construction contracts during the second half of the year or at the start of next year.

Julio Romero analyst
#26

Alright, that's good. Since I'm already in the queue here, I suppose if there are a couple of additional projects in the pipeline, that would read as a favorable signal regarding the ongoing backing you're receiving from your surety partners, as well as your bonding capacity.

Frank Renda executive
#27

That's right — we anticipate bid activity picking up during the back half of the year and beyond. Demand across our sector is strong. Water, wastewater, bridges, marine — every one of those areas is something we plan to pursue deliberately. We'll keep landing those shorter-cycle jobs, and there are plenty of options to select from, plus surety support down the road is going to be a real asset.

Julio Romero analyst
#28

Excellent, and from a geographic standpoint, in which areas are you observing demand from the private sector for those offerings?

Frank Renda executive
#29

Right now, there is genuinely a great deal of activity nationwide. You're hearing about data centers truly launching everywhere. However, when it comes to infrastructure projects, Texas, Florida, the Northeast — every one of our main markets offers plenty of work to select from.

Julio Romero analyst
#30

Great, and I appreciate you answering these additional questions. Thank you.

Frank Renda executive
#31

You're welcome, Julio.

Julio Romero analyst
#32

Thank you.

Frank Renda executive
#33

As we bring today's session to a close, I want to express appreciation to the people who work for us for the loyalty and hard work they keep showing in constructing some of the toughest infrastructure efforts throughout North America, particularly while we navigate this period of change. My thanks go out as well to the surety partners we rely on for the backing and collaboration they keep providing as together we strive to set Southland on a more solid course ahead. I appreciate all of you for being here today, and I'm eager to share our next update with you on the upcoming call. Thank you, everybody.

Operator operator
#34

This concludes today's call. Thank you for attending. You may now disconnect.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Southland Holdings, Inc. transcript - plus 133,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Southland Holdings, Inc. earnings transcripts and 133,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.