Talen Energy Corporation (TLN) Earnings Call Transcript
February 26, 2026
Earnings Call Speaker Segments
Thanks, Michelle, and welcome everyone to the Talen Energy call for the fourth quarter of 2025. Joining us today are Mac McFarland, our Chief Executive Officer; Terry Nutt, our President; and Cole Muller, our Chief Financial Officer. Other senior leaders from Talen are also with us, and they'll take questions during the second half of today's call if needed. Our earnings release came out this afternoon, and the presentation came with it — you can find both in the Investor Relations area of Talen's site, talenenergy.com. During today's call, we'll be sharing some forward-looking statements that rest on our current expectations and assumptions. Actual results might come out differently because of risk factors and other matters covered in our financial disclosures and other SEC filings. We'll also be referring to certain non-GAAP financial measures today. Information that reconciles our non-GAAP measures with the most directly comparable GAAP measures appears in our earnings release and in the appendix of our presentation. With that, I'll hand things over to Mac.
Alright. Thank you, Sergio, and I want to welcome everybody to the call today. As we always do, we're grateful for your continued interest in Talen and for joining our calls. We finished the full year 2025 with solid results in Q4, bringing in the Freedom and Guernsey assets and running well through the early part of winter in December. And 2026 is beginning in much the same way, with strong overall performance from the fleet and the commercial teams through these cold winter months. I also mentioned that PJM and other operators did well too, keeping the grid reliable through some of the highest consecutive daily loads we've ever witnessed. We experienced quite a bit of elevated pricing and volatility; and taking everything together, 2026 has gotten off to a good start, and we are reaffirming the guidance range for 2026. Just keep in mind that this range excludes the recently announced Cornerstone acquisition, which we expect to close this summer. When I look back at 2025, we had said it would be an exciting year, and it certainly was throughout the IPP space, and here at Talen we got a great deal done. We signed the reliability-must-run agreements. We signed a revamped and doubled front-of-the-meter PPA with Amazon at Susquehanna. We signed and closed Freedom and Guernsey, and we delivered on the fundamentals of being an IPP, which means safely, reliably and profitably delivering megawatts to the grid, and that's thanks to all the Talen employees who make it happen. Looking ahead to 2026, we feel optimistic about the continuing long arc of the powering AI thesis and about Talen's place within it. As I've been saying, 2025 was a year of option development, and 2026 will be the year of rationalization. During 2025, as everyone in the space was rushing to develop options for data center development, and the power that goes with it, a bow wave of expectations built up across the industry for deals and more deals, whether those were virtual purchase power agreements or behind-the-meter developments. Investors were expecting the next big thing and the next big announcement. To some, 2025 fell short; for others who understand this long arc, they believe things will rationalize themselves out. Some projects simply won't make it while others will, some will be delayed and will need to be rationalized in 2027. But on the whole, we believe the long arc remains unchanged. As the CEO of Anthropic wrote in his recent essay, and I quote, "every few months public sentiment either becomes convinced that AI is hitting a wall or becomes excited about some new breakthrough that will fundamentally change the game; but the truth is that behind the volatility in public speculation, there has been a smooth unyielding increase in AI's cognitive capabilities". Again, that's a quote from the CEO of Anthropic. If you ask me, in that quotation you could swap out AI for IPPs, or swap AI for Talen as a company, and the meaning would stay identical. That is exactly what I mean by a long arc: our ability to serve data centers and AI has risen in a steady, unstoppable way. That being said, plenty of short-term chatter has cropped up that people can mix up with the sensible long-arc perspective — the reliability backstop auction, overbuilding, resource adequacy, regulated new construction behind the meter, front of the meter, local zoning. Each one matters on its own terms and they interconnect to some degree. Pull them all together and you get an enormous amount of noise, noise that can be misread or, worse, twisted into something it is not. Yet looked at realistically, none of them alter the long arc, and our dedication to the Talen flywheel strategy holds firm. For those of you investing, understand that we steer this long arc and aim to maximize value creation over the long term rather than reacting to short-term developments. We do not over rotate, and nothing has shifted our core belief that data centers are arriving, and arriving quickly. Across our fleet, we can sign contracts with these entities. We are assembling a more diversified fleet to back those contracts, and we are developing the capabilities to help bring new construction online. Regarding Montour, what is our plan B? Many people keep asking that, and they still are. To me, this looks like the ISA denial and the questions that followed the FERC ruling on our original Susquehanna plans. But what was our response? We stayed flexible, we retooled, and in the end we pivoted toward a stronger commercial answer. We are just as confident we can repeat that here. Short-term obstacles do not determine long-term success — your reaction to them does. So we keep pushing forward. Naturally, Montour is only one opportunity in our pipeline, though it is the best known, and that is probably my fault for discussing it so often. Across the PJM footprint we are developing many other organic and inorganic sites to advance the Talen flywheel further. That covers powered land opportunities along with new build opportunities. I realize a lot of you will want to probe this pipeline of opportunities. Before you do, let me say this: we will not go into them at any level of detail, and we no longer intend to talk about development in a public setting and repeat the frenzied speculation that followed a single decision by Montour County commissioners. Rest assured, though, that we work the pipeline daily and have options available to us. Regarding regulation, we're in discussions with policy officials across state, federal, and RTO levels aiming to establish the reliability backstop procurement, or RBP—previously known as the RBA—in PJM. This offers a onetime fix for resource adequacy, cutting system costs and buying time for genuine capacity market reform. That's precisely what our wide-ranging alliance of generators, hyperscalers, and utilities put forward recently during a PJM workshop. We're eager to keep talking about this vital policy shift. Meanwhile, we endorse prolonging the existing floor and cap for the base residual auction, so there's space to implement these more lasting reforms. Prior to handing things over to Terry, I'll wrap up with this point. Our approach—and thus our investment rationale—rests on tangible assets already in place that can enable data center expansion. Through this, we're transforming what used to be merchant generation assets vulnerable to commodity pricing into infrastructure holdings, which subsequently lowers capital expenses and boosts returns for those investing with us. Though our present portfolio still has growth potential, we're positioned for what's ahead too. Looking forward, we can expand our existing holdings via contracted new construction and upcoming inorganic powered land sites—a venture we kicked off last year, incidentally, building a pipeline of prospects as I've outlined before. Plus, we've assigned a portion of our leadership group to pursue this chance following the management shifts revealed last December. This is a sturdy, concrete framework grounded in present conditions, yet focused on upcoming expansion. We're ready for your inquiries. With that, I'll pass it to Terry.
Thanks, Mac, and hello to everyone this afternoon. Let's turn to Slide 3 to briefly go over what we did strategically in 2025. Over the course of the year, we rolled out the Talen's flywheel — a repeatable approach to creating value that draws on our dependable, scalable generation assets along with our commercial strengths to generate durable growth in free cash flow per share for shareholders. Under this strategy, we carried out the contracting piece of the flywheel via the Amazon 2.0 PPA signed in June, which shifted the transaction into a front-of-the-meter structure and increased the volumes to a total of 1.9 gigawatts. Deals like this one will generate cash flows that support other elements of our broader strategy. In July, we carried out the acquisition piece of our strategy, announcing the purchase of the Freedom and Guernsey plants, which added roughly 2.8 gigawatts of efficient CCGTs, including a meaningful foundational position in Ohio, and then brought those assets into the portfolio in late November. All year long, we kept our attention on maintaining balance sheet discipline, with the capacity to bring our net leverage down to below 3.5x by the close of 2026, while staying clearly focused on our shareholders by raising our share repurchase program to $2 billion through 2028; in 2026, we'll keep pursuing this path of maximizing value, concentrating on generating the most adjusted free cash flow per share while selectively looking into inorganic and organic opportunities that back the Talen flywheel. Now to Slide 4. Let's discuss how we're continuing to expand the Talen fleet via acquisitions. As noted earlier, we grew our presence in Pennsylvania by acquiring Freedom and extended our footprint into Western PJM by acquiring Guernsey. Not long after those deals closed, we reached an agreement to purchase the 3 cornerstone generation assets situated in Ohio and Indiana. Western PJM enjoys considerable data center tailwinds and access to dependable, low-cost natural gas from the Marcellus and Utica shales. And Ohio is a bustling data center hub that keeps expanding. On top of that, these acquisitions diversify Talen's generation portfolio by bringing in high capacity factor assets with high free cash flow conversion rates. These assets will further boost Talen's opportunities for large load contracting. As a reminder, we underwrite acquisitions on a merchant basis, using current forward market energy and capacity prices along with more normalized views in the out years. Signing offtake agreements on these assets generates extra upside potential. Now to Slide 5. The forces driving large load growth and the broader fundamentals of power demand remain constructive. One of the biggest forces is the substantial amount of capital being put to work by the world's most well-capitalized technology companies. Recent CapEx forecasts from the largest hyperscalers indicate significant spending increases in 2026 and beyond, including an estimated over $650 billion of spend in this year alone. We observe the increased data center capacity that spending produces appearing across multiple states where we either already hold or intend to establish strong generation positions, such as Pennsylvania, Ohio and Indiana. Taking a closer look at the fundamentals via the latest PJM peak load forecast covering the main regions in which we run operations gives us a picture of anticipated load growth across the coming several years. Even following recent adjustments designed to add more rigor regarding proposed large loads, this forecast indicates the PPL zone rising in peak load by more than 70% over the next 5 years, whereas the AEP zone goes up by more than 30% during that same stretch. Earlier this month, AEP disclosed contracted load growth of 4 gigawatts in PJM for 2026, mostly propelled by load growth in Ohio. About 90% of the 15 gigawatts of incremental load growth through 2030 that AEP reported is backed by executed take-or-pay electric service agreements. In the meantime, PPL likewise disclosed substantial growth within its territory and anticipates having 10 gigawatts of signed agreements before the first quarter of 2026 concludes. So how does all of this affect Talen? Two main outcomes: First, rising demand translates into greater run times for our current generation fleet, particularly our intermediate dispatch and peaking units; second, heightened demand will create more appealing economics for spark spreads and the possibility of offtake agreements. Shifting to Slide 6 and picking up on what Mac said before. The outlook for basic market fundamentals has not shifted at all. Talen's underlying value proposition is unchanged and continues to point up and to the right. The PJM capacity markets have mirrored these tightening fundamentals too, with the most recent 2 base residual capacity auctions closing the price gap. This pattern should persist, and PJM, backed by the governors and other stakeholders, has signaled its intention to pursue an extension of the price collar covering 2 additional base residual auctions. Regarding energy and spark spreads, we have witnessed appreciation in the forward curves for 2026 to 2028 between the end of July and the end of the year, with spark spreads and PJM growing more than 15% over that span. Moving to Slide 7. I want to give a quick update on our hedging activity during the past quarter. As a reminder, our hedging strategy is pragmatic rather than programmatic. It centers on keeping appropriate risk tolerances and financial discipline to underpin cash flow stability while still preserving room to seize upside as opportunities emerge. This affords our team the flexibility to add hedges when pricing is higher, as laid out on the right-hand side. As the graph in the table on the slide shows, spark spreads for the PJM market for 2026 to 2028 saw upward movements in the fourth quarter, which let our commercial team layer in extra hedges for 2026 and 2027 as those opportunities came about. I'll hand the call to Cole at this point so he can walk us through how we did financially and operationally.
Appreciate it, Terry, and hello everybody this afternoon. Like Mac said a bit earlier, when it comes to the twelve months that closed out 2025, the adjusted EBITDA figure we're reporting comes to $1.035 billion, alongside adjusted free cash flow of $524 million; those numbers land above the top end of the updated guidance ranges we put out during the prior quarter, largely because the Freedom and Guernsey deals closed in November 2025. We've got over $2 billion in liquidity on hand, which covers $1.2 billion of cash plus the ability to draw the full $900 million under our revolving credit facility. Since our net debt carries the Freedom and Guernsey financing but reflects just 5 weeks of EBITDA contribution, calculating a net leverage ratio off actual 2025 EBITDA amounts to comparing apples and oranges, so it isn't a useful measure for 2025. Shifting to how we performed operationally. Safety stays our number one priority throughout the fleet, and the team put in a safe effort over a busy twelve months. The recordable incident rate came in at 0.55, still tracking under the industry average. Our fleet performed strongly, posting a 4.7% equivalent forced outage factor, and output reached roughly 40 terawatt hours, an increase of about 10% versus 2024. That came from a substantial rise in dispatch opportunities throughout our fossil fleet, which pushed generation and energy margin higher. Now to Slide 9. Full year 2025 financial results came in significantly above 2024 thanks to several drivers: stronger capacity prices along with RMR revenues that kicked in starting June 2025, AWS revenues continuing to ramp as that campus keeps advancing, 5 weeks of Freedom and Guernsey operations, plus better power prices after accounting for hedges. Those gains were partly offset by fallout from the Susquehanna Unit 2 extended outage during last spring, and by Susquehanna failing to receive the PTC in 2025 as well. In the fourth quarter, adjusted EBITDA came to $382 million while adjusted free cash flow reached $292 million. Worth noting that our adjusted free cash flow for Q4 2025 by itself topped the entire 2024 total, which shows the free cash flow growth this business is delivering, growth we can — expect will keep going as we head into 2026 and past that. On that note, looking at 2026 on Slide 10, we're reaffirming the 2026 guidance ranges we previously announced. Adjusted EBITDA is guided to a range of $1.75 billion to $2.05 billion, and adjusted free cash flow is guided to a range of $980 million to $1.18 billion. Everything there stays in line with what we laid out at Investor Day and leaves out any contribution from the Cornerstone acquisition that's still pending. As Mac noted earlier, even though our fleet performed well through the recent winter weather, we're still early in the year, and making adjustments midway through the first quarter isn't something we do. Slide 11 might ring a bell for anyone who tuned in last month when we announced the Cornerstone transaction. We're projecting continued growth in free cash flow per share, with our 2026 forecast coming in at more than double our 2025 actual results. Additionally, once the Cornerstone deal is completed, we expect it to generate an incremental yearly boost of over $4 to adjusted free cash flow per share. Although we show this benefit starting in 2027, there is potential for more in 2026, since we expect to finalize the transaction as early as this summer. Meanwhile, our base free cash flow per share keeps rising, driven by increasingly contracted cash flows tied to the ramp of our long-term AWS PPA. We still see further potential from the 4 growth levers we laid out at our Investor Day last September, with room for that uplift to add even more to our growing free cash flow per share. On the slide, we show this impact, and we note that we are already putting these levers into action, as shown by the Cornerstone acquisition. Our focus is on building a track record of delivering on chances to generate additional growth in the quarters and years ahead; we stay dedicated to giving capital back to shareholders via our previously announced $2 billion share repurchase program and through more data center contracting opportunities, such as backing the AWS ramp and possible acceleration opportunities set up in the existing PPA, and we are always assessing accretive M&A opportunities. We will keep up capital discipline and concentrate on the most accretive levers that meaningfully raise free cash flow per share available to investors, while pursuing compelling growth opportunities through the Talen flywheel. Now Slide 12. The strength of our balance sheet is a strategic asset that provides the flexibility to carry out the flywheel and increase our free cash flow per share. We stay dedicated to preserving sufficient liquidity and holding our long-term net leverage ratio under our stated target of 3.5x. As of February 20, our net leverage ratio, based on our current net debt level and the midpoint of 2026 EBITDA guidance, is 3.0x. Once the Cornerstone transaction closes, we expect to keep the ability to reach below 3.5x net leverage on a go-forward basis by year-end 2026. I'll hand it back to Mac.
Okay, thank you, Cole. With that said, Michelle, let's go ahead and take questions from the line.
Could I maybe get a bit more detail about how you guys are viewing the backstop auction? With all the policy uncertainty swirling around PJM in general, are your contract talks and negotiations still moving along? Does interest remain? And can contracts still realistically get done while PJM has all this uncertainty hanging over it?
David, this is Mac. I'll kick things off, and then others can chime in. So, to begin with, on the RBA — which these days is being framed as the RBP, something closer to a procurement than an auction, at least as we see it, since in our opinion it ought to run as pay as bid, and that's the difference people are drawing. I believe that's even how it's beginning to be labeled over at PJM. But anyway, my sense is that when you put in place — the whole idea behind the backstop is to step in and rely on the tariff that already exists in order to procure and satisfy a resource adequacy requirement for the out years, and doing so would ease some of the tightness, so to speak, in the market. Still, it remains — if it's executed at whatever the load projections happen to be, at those same levels, the result wouldn't be any different. That's where we come out on it. So the purpose is to supply what's needed to hold the reserve margin, since you're aware the most recent auction would have cleared above $500 had the $330 cap not been placed on it. In our thinking, though, that backstop procurement actually acts as a relief valve, and because of that, it lets contracts keep moving ahead. And it's among the things — it was among the tenets in the statement that came out from the NEDCs, the National Energy Dominance Council, that group, when they issued it, saying that beyond being onetime and limited, there should also be longer-term capacity reforms and then a return to the outcome, yet it ought to permit continuation of existing contracts. And I think as more certainty is gained while we work through this process, that clearly keeps supporting it. So practically speaking, we see that as a relief valve for doing existing contracts. And when it comes to existing contracts and the ongoing discussions there, spanning the fleet and spanning our pipeline of opportunities, those haven't decelerated. My view is that the regulatory uncertainty — who foots the bill, how it gets paid, how it gets allocated, how it gets procured, all of that — will sort itself out. But data centers keep coming and they aren't slowing down. And whenever you talk to anyone or listen to any of the analyst calls, from the chip manufacturers all the way to the hyperscalers themselves, they keep discussing the race to create data centers on the ground, powering them today, powering them in '28, and before long '29 will become the new '28. So I think as we move through that, it only helps the ability to keep those discussions going. We therefore don't see any slowdown to it. And we believe the RBP will ultimately provide for — will raise the level of those discussions.
Understood. Yes, that added detail is helpful. Then, regarding the procurement, are there upgrades or new builds you view as possible chances to submit bids into it?
We're pursuing a number of possibilities on the new build side; we do believe upgrades ought to qualify if that's what you're asking, if your question is specifically whether we have upgrades, the majority of upgrades we possessed at Susquehanna were installed roughly 10 years back; so not much exists there that you might hear about from other producers; however, there are prospects we've been developing while considering every type of generation, be it batteries, CTs or CCGTs as we advance those prospects. And look, given a 15-year contract at the right price, the math can be made to work. So clearly, we're preparing for that; and after the rules become more defined, we would examine how we might take part.
I'm attempting to connect what we've been told by PPL and AP with the contracts you're signing for generation. Take, for instance, the remark you yourself cited in those slides — PPL anticipates 10 gigs of load covered by ESAs once the first quarter wraps up, which is roughly another month away. In what way does that tie into your position as the biggest generation provider within the PPL territory and the signing of generation agreements meant to support that 10 gigs of load?
To be precise, that list isn't something we possess. PPL holds it, so regarding its specific contents, they're the ones you'd need to ask. Still, I believe it strongly reinforces the point raised in the previous question — namely, that things aren't decelerating and that PPL continues enrolling ESAs. When you enroll ESAs, procuring energy and capacity isn't strictly required, yet what you are doing amounts to a pledge to cover network upgrade costs and everything else involved. From my perspective, that's an extremely encouraging indicator — one confirming that nothing is decelerating. As for what appears on that list, we don't have it. Clearly, though, we're developing our own pipeline of prospects and intend to take part in that area moving forward.
Okay, Angie, regarding ESA, that represents step number one. Without one, data centers won't sign contracts under a PPA, correct? So I see that as simply a solid sort of forward signal that PPAs are on the way. And to put it plainly, we've already announced roughly 2 gigawatts of actual PPA within that area. So again, I'll let PPL detail their own tally, but right there you've got 2 out of the 10.
All right. All right. As you know, we're just sitting tight, so perhaps there's some awareness about...
Angie, I'd simply like to tack on one more thing: our approach involves hyperscalers, yet there are also others doing development — I'd term them co-locators — the standard data center operators who construct and hook up facilities, then rent them out. In that case, power and capacity often can be — or under the previous way of doing things, were — merely passed through. Right; so as Cole mentioned, under our approach you secure the ESA initially and afterward obtain the power and capacity. Yet certain approaches simply draw from the grid, with power acting as a pass-through. That means the lease — whoever executes the lease — whoever commits to that lease — must make the call to arrange for power and capacity in that situation. Still, hyperscalers and similar players, plus the development approach we use, involve powered land, securing the ESA, securing the power capacity, and once you combine everything, you arrive at what we accomplished with Susquehanna.
All right. My next item concerns Slide 11, which I recognize is identical to the one shown during your Analyst Day presentation. Two points, then. First, regarding the possible additional benefit to free cash flow per share that you present for 2028 — does that mean there's no such potential benefit for, let's say, 2027? That's point one. And point two: when you show us the additional 1 gig of data center PPAs alongside the Susquehanna contract moved up by 480 — is it merely that figure, 480 on one side and 1 gig on the other? Is it simply a way of measuring? Or does it represent essentially what you'd anticipate occurring as possible additional benefit? In other words, is it basically the ceiling once more for further data center PPAs and further ramp under the Susquehanna contract through 2028?
Yes. Let me give a bit of background about the slide in general, Angie, to address what you asked, and then Cole will handle the 480. When this slide was presented at Investor Day, we concluded with the 2028 outlook. What we were doing was displaying levers available to us that would push free cash flow per share even higher; as for when they'd land, all of them were calculated from a 2028 base. As for when they'd land, if you look, we moved Cornerstone ahead into 2027, and we likely can shift part of it into 2026 given the anticipated closing here. So we're actually — additional benefit exists beyond this guidance. What we were doing was simply illustrating that, treating 2028 as the final year shown, we wanted to demonstrate there are further levers available to generate additional value as we observe the flywheel being implemented. One of them was the — and none of this incorporates any buyback; and indeed, that's the reason we placed the plus signs at the top of this, though it didn't — where it reads $4 plus or $31.10 plus, $31.40 plus at the top of the bars. Yet none of this includes share repurchases, correct? So we laid that out. We included the accretive M&A. We moved that ahead. Why don't we discuss the 480, and afterward perhaps I can address the final item on the chart.
Right, the 480 and the 1 gigawatt were only meant as illustrative figures, so people can form their own estimates and scale from there, correct? So come 2028, the contract, as previously disclosed, reaches just the initial 480 megawatts; therefore we simply presented what would be needed to reach 960. Going all the way to 1920 was an option, but we figured that wouldn't really add much value. Our aim was to demonstrate the effect of each 480. Then regarding the data center — the new data center PPA consumed a typical 1 gigawatt. Could it be greater, potentially, and you could scale upward from that point.
Yet I believe that also matters a lot in explaining why that facility was the new 1 gigawatt data center. When you consider it, Angie, and you consider the ramp occurring at Susquehanna, as Cole just laid out, any fresh data center PPA, and this might perhaps contribute to somewhat more of a conversation. I stated we won't talk about Montour, but perhaps we'll unpack it a bit for you. And — yet that 1 gigawatt data center PPA is really, in all likelihood, beyond 2028, because when you consider the timing of when you must construct data centers such as what is happening at Susquehanna, there would be a ramp rate, and that is why we presented that out there on '28. That one is probably the least probable to be accelerated sooner, because even if a contract were signed today on the so-called Montour deal or some other virtual PPA throughout our pipelines of opportunity, delivery of those megawatts will not occur in 2028; and this is something I find quite interesting, returning to the Montour question of whether Montour occurs today or occurs 6 months from now, it really makes no difference to when the megawatts would flow under that kind of arrangement, since they will not be delivered until '28 and they will ramp up from there, in all likelihood. So that is why I mentioned there was plenty of sort of near-term discussion and sort of frantic outcome surrounding the County Commission vote. Yet when you examine it in the delivery of the megawatts, we remain on that long arc, as I described. The long arc has not shifted. It is a near-term hurdle; now would we — rather the commission vote the opposite way? Certainly, without question. But we are commercial, and we're going to figure that out. And we have numerous other opportunities in the pipeline that present themselves to do the same thing. And so that is what we're looking at, which is adding another gigawatt data center contract, but delivery won't begin until '28, and it's almost irrelevant when it's signed in 2026.
Could I squeeze in a single follow-up regarding that? What makes it tied in any way to the Montour location? Since, once more, we're only supposing it might involve AWS. After all, AWS operates additional locations within the PPL territory. Plus, as you mentioned, you already hold assets there — your Susquehanna 2.0 contracted supply, plus those other locations already being built out as data center sites. So why wouldn't I be able to sign a PPA covering a portion of those other locations under development, meaning the effect on '28 EBITDA would probably be likely?
Great observation — and you're essentially arguing our case for us, since these are virtual PPAs. I'll return to address your specific question shortly. Yet consider Susquehanna: when we shifted it to front-of-the-meter, recall that we noted a key feature of that deal was our obligation to serve any location across Pennsylvania. That connects to the 480 acceleration — should additional data centers exist, they may come in under that agreement sooner, though afterward they'll face this: building beyond the 1920 means adding further megawatts at the back end, and that's Amazon. Purely Amazon. Others exist beyond Amazon alone. As for whether it must be tied to Montour — not always, all right? We're talking 1,200 or 1,000 megawatts, or 1,200 megawatts, or 960 megawatts, whichever figure is correct — let's simply use 1 gig. Must that agreement be attached to one particular location? Not always. Since, once more, everything hinges on the delivery point. Still, it does matter when you consider that, as a data center builder — be it Amazon or anyone else — you require locations with a clear path to construct the facility so the megawatts can be routed there, all right? Thus, though they're somewhat connected, they aren't always distinctly locked together; they could be, yet there's no requirement for that.
I was hoping we could dig a bit deeper into a few of the opposing forces at play in Pennsylvania, particularly given what Governor Shapiro said most recently, and now with all of this PPL load showing up in the forward curve. So where do the plants we already have and the ones we might add fit into this? Is the spare transmission capacity enough to handle all of it? And at what point do we need to begin considering new construction, and how does that connect to the political messaging?
Right. My sense is that the political messaging centers on keeping costs down and on having enough resources available. And as I've said, our view is that the RBP is the solution to that. It also works as a pressure-release mechanism. In every one of the proposals, as I see it, there's an assumption that existing contracts get a carve-out when it comes to spreading costs. That's among the items people have been discussing. For instance, when you go out and procure, and the NEDC put out $15 billion as the figure, how do you divvy that up? Yet if new loads already had a contract in place, they wouldn't bear any of it; that's more or less the norm across the various coalitions — ours and the others — where contracts already in existence get an exemption. So once more, that lets us keep going. Whether that cost-sharing and the remainder of the RBP will work out is still unknown; but for now, as I keep saying, there's nothing standing in the way. So folks are working through the steps of getting things arranged and determining what their next move is regarding the RBP. That said, let me hand it to Cole and find out whether he wants to add anything here.
Yeah. What I'd add to that, Michael, is that I believe there's broad agreement that data centers are on their way, and those loads will keep growing and ramping up across 2027, 2028 and 2029, and onward beyond that. I'm not aware of a whole lot of — a whole lot of new generation capable of actually meeting that load. So we're staying — we remain focused on discussions involving existing generation. Clearly, at some point new generation has to come online; those choices have to get made before long. Clearly, the RBP represents one avenue, a bilateral contract represents another. And I believe we've stated pretty consistently that in our view, over time this will begin moving toward something like hybrid models, where existing gen carries the first 3- to 5-year build-out of the data centers throughout Pennsylvania, Ohio, Indiana and so on, and then ultimately gets supported by a second thing — either an upscaling of a PPA or a second PPA — which lets new generation sort of close the gap from that point.
When it comes to new generation, it's either power that customers supply themselves or new capacity secured via the RBP. That's the reason all of this remains in flux, but essentially you taper off the current arrangements and transition onto the new ones, and whether that arrives through the RBP or folks supply their own power hasn't been settled yet. Still, as Cole mentioned, that's the direction where things are going to move.
And Michael, perhaps I can build on what was just said. Clearly, with regard to the PJM talks happening about the RBP, and specifically in relation to Governor Shapiro, his team is part of that; they are taking part in the conversations. They have listened to the proposals put forward by the various coalition groups; they are participating actively. Broadly speaking, I think the idea is that more gen will be procured as this goes along. So I believe they back that. And so they stay active and stay involved, and they are right there among it alongside all the other stakeholders.
All right, fantastic. Next, I was hoping to probe — you brought it up — I realize you'd rather not discuss specific opportunities one by one, yet when it comes to your development queue, the organic ones, the inorganic powered land, perhaps give us a bit more detail on how you balance the economics and the speed there? I'd assume you already hold plenty of land, though maybe explain the value proposition behind the inorganic powered land piece.
Yeah. Michael, that's a terrific question, and honestly, if we lived in a perfect world where the only thing that mattered was chatting with investors, it's a topic we'd love to dive into. The trouble is, whenever we open up about it, either a commercial trade is staring us in the face or we wind up setting an expectation regarding some particular result. That's the reason I gave those opening remarks. It isn't that things aren't happening at a frenzied pace here at Talen — they are; and it centers on our current sites, and it centers on sites that don't currently exist but belong to others who'd like to partner with us on various things, yet we won't dive into the details of those or our methods, first because it's commercially sensitive; and second because it generates those expectations. So look, we set those expectations regarding Montour, and that's on us. No question. And — but we'll sort that out. There's Plan B; plus there are additional opportunities in our queue that deliver more of this for us. I mean, had we — suppose Montour had proceeded, just to lay out the hypothetical, had Montour proceeded and a deal had been announced there, everyone would ask, what's your next deal? Well, it's not like we complete one deal and then turn our attention to the following deal. We're pushing on many fronts simultaneously, all right? And what we came to understand is that there was simply this kind of fixation on a single outcome there, which honestly isn't going to shape that long arc I was attempting to lay out, that long arc which keeps expanding; that long arc which keeps expanding alongside AI capabilities and likewise our commercial capacities to make these things happen. Our commercial capacities to build new build, our commercial capacities to contract new build, our commercial capacities to contract existing as Cole just mentioned or a blend of the 2. And so we're pursuing, more or less, all of the above. We're pursuing getting ready to bid into the RBP provided we can locate the appropriate pricing mechanisms and provided the world unfolds the way we believe it ought to with regard to the RBP, we're going to add to all of that and it simply turns into a question of where we direct things. But we did allow ourselves, frankly, to get trapped in a bit of that binary mindset that Montour would determine what Talen is going to be. And that single problem isn't the only reason we won't pursue it — it also holds back our capacity to build other items. So starting now, we're moving away from it. That likely doesn't give you what you were looking for, and — but sadly, this is the route we're taking.
I'd like to expand a bit, I suppose, on a few of the points you just made; and since the hyperscaler is heading to DC next week. I'm just curious, I guess, what you believe might come out of that? When the conversation turns to them supplying their own generation, how does Talen see that? And what effect do you think that would have on market architecture?
Jeremy, Mac, let me start. We have no idea what they will pledge. People have speculated about what they will pledge. What I believe you have witnessed is a public pledge from each of them to cover their fair share. How fair share gets defined is intriguing. From where I sit, and we've stated this in many a forum, you don't — PJM is an RTO built not on this idea that the next incremental megawatt pays for the next — of load pays for the next incremental megawatt of generation. That has never been the situation. You have states short on generation that have covered transmission costs and are utilizing it. You have LSEs that are extremely short; we happen to sit in an LSE that's long in Pennsylvania and PPL and long transmission that can absorb these things. So everything will come down to how they define what they've committed to regarding fair share or paying for it under that definition, I have no clue what they will pledge, Jeremy.
Understood. That's reasonable. We'll observe the outcome; and I was curious whether we might steer the discussion toward, I suppose, contracting in the context of gas contracting, perhaps how those talks have developed over time? And whatever remarks you can offer regarding hyperscaler willingness to bear the gas risk? Or might there be arrangements involving fixed capacity along with a heat rate component? I'm just curious what you might — how those discussions have shifted over time, and where you expect them to head?
Jeremy, this is Cole. Well, I believe we've discussed this on several occasions. I think — not to be affluent, but it hinges on the counterparty, correct? So certain hyperscalers could be more willing to accept the cost variability of gas and others less so; so you brought up a few distinct variations of contracting. I think it's enough to say, we've examined many different structures both internally and alongside counterparties. And I think there are multiple different paths to ultimately contract and safeguard ourselves under any structure here. And we've got a commercial desk led by Chris that can also handle that position. And if we contracted in that fashion, we would clearly have a different premium structure within the PPA to kind of account for that element; so I think there are a variety of different structures. And obviously, once we have a deal announced, we'll likely discuss that a bit more.
To build on that — Cole's point is spot on; it all comes down to what a given party prefers. Still, if someone buying this asked my advice, I'd tell them the right approach is having whoever handles commodity risk carry that risk and compensate a specialist to do it, unless they intend to hold that exposure on their own books. That's precisely what we're built for. It's the same thing we've described regarding our ability to extend credit support for this purpose — handling gas price exposure, overseeing physical gas delivery into our plants and all the related pieces, and even when it's purely financial, controlling that financial exposure tied to gas. So that complete package is the service we aim to deliver; as Cole noted, customers may select individual pieces, yet that's what our recommendation would be.
I found a lot of the responses in the commentary helpful. I simply wanted to ask a follow-up about how you're attempting to characterize the situation involving RBA, the ratepayer protection pledge, and a few of the remarks you gave Michael. Do you still believe you're able to sign gas with incumbent generation under a front-of-meter framework? I'm also trying to figure out whether you're essentially saying this would now only happen with additionality and a new build commitment. Could you perhaps make the expectations there very clear?
To be perfectly clear: yes. Our view is that contracting with the existing assets can continue.
Other people <<inaudible>>.
The answer is affirmative. Do we anticipate that we might construct a farm at some point down the road? Absolutely. I don't mean to sound dismissive in saying this. The simple fact is that the response is yes. Our view is that the ability exists to accomplish that; our view is that the interest and hunger exist to accomplish that, and we are actively pursuing it.
Then, just to follow up — I realize that during the Montour hearing in particular, Amazon raised the point that this wouldn't really be an additionality deal, and they discussed where the supply chain stands right now; and I'm aware that a few of your peers on their calls have been saying things along the lines that they might have new-build gas and be using turbines, or bridge power, that other companies have already procured or that nobody has a slot for. So perhaps you could speak to what your current EPC relationships look like, or your capacity to pursue something either in-house through a partnership or inorganically, in order to lock down the supply chain further so you can actually deliver on that?
Sure. Glad to address that. And just so you're aware, I was only attempting to make it plain that we believe the ability exists to do so. I wasn't trying to come across as harsh there; but regarding turbines and EPC relationships and all the rest, our perspective, and the rationale behind why we've built up and put money into its existing assets, is exactly on point, which is that we believe there's still the capability to use existing assets to contract. A lot of data centers exist out there at present that are examining whether they sign for a longer duration, the existing ones, correct? You saw that in a recent PPA announcement involving the existing data center load. I think that as far as new build goes, and there's a good deal of conversation about new build, we look at new build quite simply. New build is going to require either prevailing in the RBP and holding a 15-year contract that permits a — removing the merchant risk of the capacity, thus enabling financing, or new build is going to require a contract. And so if you possess either of those, okay, and a minor distinction with the RBP versus, say, bring your own power or new build generation, as Cole explained in the hybrid. You're going to need the offtake agreement. In our opinion, it's the offtake agreement that determines this, not necessarily the turbine orders or the EPC. And the first group that holds an offtake agreement will discover all sorts of people who want to put money into it, all sorts of turbines that want to be part of it, and all sorts of EPC providers that will want to be part of it, since it's a live project once you have either that contract or the RBP award. So hopefully, that addresses the question. I think that — I take your point, we do have relationships with those; we placed Dale in the spot in the Chief Asset Development Officer role, specifically to focus on technology, costing, EPC work, et cetera. That's very important, but what's most important is the offtake.
Mac, I won't put you on the spot about whether you believe contracts could be signed right now. But I did want to ask — when we think about the hedge book as we look ahead through 2027, there's a great deal of upside optionality there — how should we expect that to keep climbing gradually as time goes on? Or is it possible — will we — do we feel fine simply leaving it open, given that the forward curve still doesn't completely capture how tight things are?
Thanks, Nick. Our Chief Commercial Officer is going to come in on this one. But look, I'll speak to the macro picture first and then Chris can address the spot side, though we identified an opportunity last December, as Terry described during his opening remarks, when prices rose enough to remove some '27 volume from the table, or to secure it using hedges, okay? We take that step not out of any obligation — as we've mentioned, our approach is pragmatic rather than programmatic. We don't set fixed thresholds, like by a certain date we must have a certain hedge position. So when we evaluate things, we've said for several quarters that we hadn't necessarily witnessed the forward market reacting, yet we did see the forward market react and we were slow to follow that <<inaudible>>; at this point I can't claim we're seeing it, and as we sit here today, sparks have risen since our Investor Day presentation, at one stage they climbed sharply relative to it and afterward declined again, they're swinging around constantly. What's encouraging is that the overall trajectory points up and to the right, and we think that aligns with our fundamental view, yet we don't believe there's any need to go out and hedge. So giving you a precise answer to your question is difficult, but let me hand this to Chris.
Correct, that's what you said. My sense is that in earlier quarters we were relying on our deliberate duration in certain of the further-out periods, anticipating that these bouts of volatility would keep showing up more often; and that's what occurred with this winter, and we anticipate it will keep occurring throughout the year, with tighter supply and demand giving us opportunities in real time to keep unwinding hedges; so we've set targets. We have ranges. Deliberately, we've stayed at the lower end of them, and we'll keep adding to them whenever the market gives us compelling opportunities.
Yeah. I believe that's a key piece, and when we emerged from — this is somewhat a stroll through the past, I suppose — but once we got out of <<inaudible>>, folks were asking, how will you offset this and so forth, we issued explicit goals of 60 to 80 and 40 to 60 prompts and prompt plus 1. Those serve as guardrails; so — yet Chris is the one running that position. We hold conversations with Terry, the risk management side, Cole, Chris, all come together; we discuss it. But while you're running a sizable portfolio, you simply can't in the end arrive at '27, long 10,000 megawatts. And that's what we're beginning to turn into with the Cornerstone acquisition, with the Freedom and Guernsey acquisitions. So you've got to seize a few of those chances to <<inaudible>> a portion, though it isn't a situation where you're compelled to remove it. We're able to choose how we'd like to angle that portfolio depending on our underlying thesis.
Right, and Nick, perhaps I could build on that as well — when a larger share of the portfolio is contracted margin, then in terms of the cash flow support we require, there's progressively less reason to lock those things in. So again, when we look at our hedging program, we're examining two things: how much contracted margin, or contracted cash flow, backs the business so we can cover our P&I payments and handle the essential requirements. Yet as an increasing portion of contracted margin comes from the AWS deal, hedging turns into something a bit more opportunistic. That perspective will remain as we go forward. And I believe that's an advantage we genuinely enjoy having.
Yeah. No, that tracks. And Cole, real quick, just a bit of a cleanup question, I suppose, just regarding Cornerstone. Now clearly, that's going to hinge on when things land, when the acquisition closes. But is it reasonable to sort of take that $500 million in EBITDA and simply spread it over the period starting at close through 2026? Or does 2027 have some growth baked into it?
Nick. Look, I'd call that a solid run rate figure. So choose whatever assumption you like for a close date, and I'd say 12 months forward from that point is a good round number.
If you were looking to be a bit more exact, you have to keep in mind that additional worth exists in the July, August, December winter period as well throughout that, but it's a nice round number.
Well, you all are aware that precision isn't really my thing; so that's okay.
Twelve months back, had someone brought up new build, my sense is that topic wasn't truly on the table when discussing Talen; yet today it seems like this is at minimum fairly believable that we could have something in place before the year ends, particularly via the auction. And I'm curious about how you approach decisions on capital and balance sheet management across the coming 2, 3 quarters, since you could have some — clearly, you'd only proceed if incentives line up, but you could be incentivized toward some sizable new build. How do you consider possibly being — would you take a less aggressive stance with the balance sheet, or if chances come along with the shares trading low or an acquisition, you won't alter what you've been doing over the last year or 1.5 years?
Craig, this is Terry. Perhaps one small nuance to what you said. We've consistently stated — and this ties in nicely with what Mac mentioned a few minutes ago; we've consistently stated, provided we have the proper certainty, be it via an offtake agreement or a highly clear underwriting case involving an off-taker, we'd be thrilled to pursue new builds, correct? I believe that's always been among the points we've brought up; with that said, I think the RBA potentially delivers that clarity, correct? Should we find ourselves in a procurement process where a 15-year commitment is available, that's extremely — that's what's required to underwrite and successfully finance building a new asset. That's a difficulty this market has faced over the past several years; it isn't about whether you're capable of constructing something. It's about whether you're capable of financing it, especially in PJM. Now regarding the second portion of your question, we're constantly balancing and seeking the highest and best use for our capital, be it repurchasing shares, be it pursuing M&A, be it undertaking new build, and we're constantly targeting high teens returns, correct? I mean we want to ensure we remain disciplined in that approach. And that's why you've witnessed us switch among — I mean, even across the last several years, we've switched among a number of those various strategies and every time we're examining returns that are considerably high. I mean just to offer 2 or 3 of those instances, we've completed a substantial amount of share repurchase over the past 2.5 years. I mean we repurchased over $2 billion worth of stock, near roughly 24% of the total float of the business at an average price of $149 a share. And those were genuinely strong strategic moves and an excellent use of our balance sheet and our capital. Consider the deal involving Freedom and Guernsey — those acquisitions deliver free cash flow per share growth that's accretive by more than 40%, correct? So whatever generates the strongest returns is where we'll always steer capital and deploy our balance sheet. That's something we bring up constantly. When we're gathered around the table weighing what the smartest destination is for that next dollar, we work through that whole set of options. In fact, it's quite close to what you'll find laid out on Slide 11 regarding how we approach expanding both the business and the free cash flow.
<<inaudible>>
Go ahead.
You go ahead.
No, go ahead, Craig.
I was working through yet another angle here, since you've got buybacks in play, acquisitions happening, plus that organic growth from new builds — and it feels like there might be greater clarity, or at least potential clarity, that this could become more tangible and incentivized before this year wraps up compared to how it looked before. Yet you also have this entire conversation that's come up during today's call regarding how to handle fuel and commodity exposure on long-term gas-fired PPAs. That calls for balance sheet capacity too, particularly if you're — well, if your cash flow is really strong, whatever happens to your balance sheet across 2 or 3 years won't matter, it'll be dry, correct? However, should you sign a PPA with delivery happening next year, that capacity might be needed. So I'm sitting here thinking that with new builds plus fuel risk management combined, there may be more balance sheet considerations today than existed 12 months back.
Craig, I'd say that's a solid question. Let me just — in framing it, you mentioned that 12 months ago new builds weren't on your mind. My recollection is that 12 months ago, we indicated we'd evaluate new builds, we had them under consideration, though it was framed as a 2030, '32 timeframe matter. Now we're 12 months further along, and '29 has become the new '28 regarding data center power, meaning we're 12 months nearer to it, and on top of that the RBP has extended this further. My view is it truly hinges on which structure you pursue, since based on how the PPAs are shaped, regarding the RBP for instance, you hold the energy, and it simply enters the book like Chris, it's really — you're getting a capacity payment, that's how you approach bidding there, which handles your cost and enables the financing, potentially within a project finance structure, something we haven't pursued. So within that system, less balance sheet might be needed than you'd assume. If we pursue longer-term PPAs requiring credit support, we figure that out. We consider whether posting an LC is possible, doing first lien arrangements, and so on. So your question doesn't have a simple answer. I understand. Still, what we've consistently stated is that we — this is the reason we toggle things; we have the SRP; we have net leverage at 3.5x; we've demonstrated we can toggle between those. As Terry mentioned, execute share repurchase when necessary, build up the balance sheet with a clear intention of bringing it back down within space to pursue M&A. Ultimately it hinges on when we arrive there and how the opportunity appears. Yet my sense is we'd simply see it as a question of switching among the various elements at our disposal so that things function, provided the appropriate returns exist alongside the appropriate contract. So I believe our time is nearly up. Have we got — two additional? What was it you were saying?
Yes, we've gone over our allotted time.
So I believe we'll wrap up at this point. My apologies — I'm aware a few folks were still waiting in line and we didn't reach them, and we'd be glad to field any follow-up questions for Sergio and everyone else on our side. Thank you all for your interest in Talen, and enjoy your evening.
This concludes today's conference call. Thank you for participating, and you may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Talen Energy Corporation transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Talen Energy Corporation earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.