Tamboran Resources Corporation (TBN) Earnings Call Transcript
February 12, 2025
Earnings Call Speaker Segments
Hello, and welcome to the Tamboran Resources conference call on the earnings release for the second quarter of fiscal year 2025. <<operator_script>> Please be aware that this call is being recorded. At this point I'm glad to hand things over to Joel Riddle, Chief Executive Officer. Thank you, sir. The floor is yours.
Thanks, and welcome everyone to the Tamboran Resources presentation of results for the second quarter of fiscal year 2025. I'm Joel Riddle, and I serve as Chief Executive Officer of Tamboran Resources. Eric Dyer, our Chief Financial Officer, is with me this morning. Before we dive into the materials, I want to point everyone to the disclaimer on Slide 2 regarding forward-looking statements. Turning to Slide 3 and the highlights from the last quarter. First, the company drilled and cased the SS-3 well successfully. That well featured a horizontal section spanning a full 10,000 feet and was drilled at 840 feet per day, a Beetaloo Basin record. Second, we finished the SS-2H well, pumping more than 35 frac stages and achieving record proppant intensity across those 35 stages. The company will aim for an IP30 flow test in April of this year. After the 30-day flow test on SS-2, we'll move to SS-3 to wrap up completion operations and target an IP30 flow test for SS-3 in June of this year. The company keeps advancing toward a final investment decision on the Shenandoah South pilot development project. During the quarter, we signed binding agreements with the APA Group to support building and constructing a 12-inch pipeline that links the SS pilot to the local 12-inch pipeline, moving gas from our pilot project into the local Northern Territory gas market, where we'll produce 40 million cubic feet a day across the next 15 years.
Initial gas from this project is still scheduled to begin in the first half of 2026. During the quarter, the company kept making solid headway on business development opportunities, including advancing a data center strategy that we would see as part of an expansion to our Phase 1 development. I'll go into more detail on this later in the presentation. And lastly, the company signed a nonbinding MOU with Santos, an ASX-listed E&P company, concerning progressing technical studies tied to the expansion of the Darwin LNG project. The company closed the quarter with a cash balance of $59.4 million. That follows receipt of an R&D grant of $6.2 million, and the company remains fully funded to deliver the IP30 flow test from SS-2 and SS-3 through the end of June of this year. Turning to Slide 4 and more detail on the progression of our Shenandoah South pilot development. As you can see from the map in the middle of the page, the company remains very focused on the 1-million-acre development area highlighted in yellow in the structure map on the left. As you zoom down into the middle of that 1-million-acre development area is our 6-well pad, where we've now drilled 2 horizontal wells.
These represent the initial 2 of 6 wells through which we expect to build out our 40 million cubic feet per day for this pilot development. As the image on the right shows, you're looking at a snapshot of the new Liberty equipment now sitting on site, which has been advancing completion work on our SS-2 and SS-3 wells. Once more, during the quarter, the company drilled the SS-3H well successfully to 21,169 feet, and that drilling was finished in 25 days. That works out to more than 840 feet per day in drilling performance, and it still stands as the fastest well drilled in the Beetaloo Basin to date. We geosteered the entire 10,000-foot horizontal section inside a 65-foot target. What we observed across that 10,000-foot horizontal well was a high-quality, contiguous Middle-Velkerri B shale and, most importantly, no faulting. The company began stimulation operations on SS-2 and SS-3 in January of this year. At SS-2, we completed 35 frac stages over the 5,500-foot horizontal section and set Beetaloo Basin records for average proppant intensity across those 35 stages. At SS-3, the company took precautionary, proactive steps to pause completion operations after detecting stress in a casing connection.
Work to remediate SS-3 is still underway, and our goal is to keep the stimulation program going into this year's second quarter. Broadly speaking, we're aiming for IP30 flow rates from SS-2 in April of this year and an IP30 from the SS-3 well in June of this year, weather permitting. Turning to Slide 5. Our drilling performance has kept improving substantially versus the last well we drilled during the quarter at SS-3. That well took 25 days to drill, averaging 843 feet per day. That is 43% faster than the SS-2H well. Referring to the table at the bottom of the slide, you can see the performance gains we've achieved at SS-3, mainly driven by the top hole through to the Moroak section, which historically took between 10 and 11 days to drill. At SS-3, we now drilled that section in under 5 days. And in the horizontal section, which took 17 days at SS-2, we managed to drill it in 12.5 days. Total drilling cost at SS-3 came to roughly $10 million, and the company has identified considerable cost savings that will drive additional reductions and boost drilling performance in our follow-on pilot development wells being drilled in this year's second half.
Turning to Slide 6. Among the most encouraging aspects of this year's 2-well drilling program is how consistent the geology has been in our 2 wells, SS-2 and SS-3, when compared with the SS-1 pilot hole located roughly 3 miles to the south of these 2 horizontal wells. Across the entire horizontal section, we have observed very consistent quality along with a very gentle, undulating structure, and no faulting has been observed. Beyond that, very strong gas shows appear across both horizontal sections, and we believe this will translate into very good productivity in our well test on both wells. Now on Slide 7, a summary of the stimulation campaign at SS-2 and SS-3. At our SS-2 well, we completed 35 stages using our new Liberty equipment that is currently on site. That was carried out across a 5,500-foot section, and we pumped a proppant intensity of approximately 2,700 pounds per foot. That is a 26% higher proppant intensity than what we pumped at SS-1H. And most encouragingly, in 18 of the 35 stages, we successfully executed the full Tamboran v2 design, pumping greater than 2,800 pounds per foot and pumping in at 90 to 100 barrels a minute. We also managed to achieve 5 stages a day for the single well operation on multiple days, and this is in line with U.S.
On the operational efficiency front, we are in the process of cleaning up the SS-2H well right now, before we start an IP30, and we will have a result from that to report to the market in April of this year. As for the SS-3 well, we took proactive, precautionary measures to carry out a remediation of a stress that was observed in a casing connection. We expect that remediation to be completed within the next 30 days, ahead of stimulation activities restarting in the second quarter of this year. We view this as a chance to take the lessons from the SS-2H well and apply them to raise efficiencies and place a higher proppant intensity across the 60 stages we intend to pump in SS-3. Our target is an SS-3 IP30 flow test result in June of this year. Turning to Slide 8, which summarizes the completion designs across Shenandoah South 1H, Shenandoah South 2H and Shenandoah South 3H. As you can see, we have had the opportunity to apply what we learned from the SS-1H well to our recent SS-2H well, which we refer to as our Tamboran v2 design. In this design, we pumped 35 stages at a little over 2,700 pounds per foot, and we pumped 90 to 100 barrels a minute. We are anticipating -- targeting IP30 flow test results of greater than 10.7 million cubic feet a day.
Once more, our goal is to hit that IP30 flow rate by April this year. The learnings from the SS-2H well can be applied to our SS-3H well, and that gives us a chance to fine-tune the Tamboran v2 design, where we expect to pump 60 stages at over 2,800 pounds per foot and over 100 barrels a minute. For the Shenandoah South 3H well test we expect in June, we're aiming at IP30 flow rates above 19 million cubic feet a day. Turning to Slide 9. We're still on schedule to deliver our SS pilot project in the first half of 2026. What we learn from our 2 wells, Shenandoah South 2H and Shenandoah South 3H, will determine how many wells we drill as follow-ups later this year, and those will feed into a binding gas sales agreement of 40 million a day for 15.5 years with the Northern Territory Government. During the quarter, we signed binding agreements with APA Group for a 12-inch pipeline connecting the pilot project to the local Northern Territory pipeline known as the Amadeus Gas Pipeline, which will bring this 40 million cubic feet a day to the local Northern Territory gas market.
We've also kicked off procurement for the 40 million a day facility. Approvals for our Shenandoah South pilot project will be wrapped up over the next few months, and that comes before a final investment decision we expect to make in mid-2025. Once again, the project is still on schedule to produce first gas at 40 million cubic feet a day during the first half of 2026. Turning to Slide 10. As I noted in my opening remarks, the company is examining a chance to grow our Phase 1 development by adding more gas supply that could support a data center strategy. The map on the left shows that Australia is turning into a major hub for data centers. Right now there are more than 200 data centers in Australia, and we think the Northern Territory can be a growth area for new data centers, thanks to the fiber optic cables already linking the Northern Territory with other parts of Australia and, even more importantly, with Asia Pacific. Those fiber optic cables pass roughly 30 miles from our Shenandoah South pilot project, and in our view that opens up an opportunity to pair gas from the Beetaloo Basin with energy for new data centers being built in the Northern Territory.
We’ve begun commercial talks with prospective partners about building several data centers in the Northern Territory, and as we keep advancing this strategy, we’ll provide further updates to the market. Turning to Slide 11. During the quarter, we also signed a nonbinding MOU with Santos to assess expanding the existing Darwin LNG plant that Santos operates. Under this nonbinding MOU, technical studies will be considered to examine developing new supply from the EP 161 permit we hold jointly and linking it to the Darwin LNG expansion, where we expect as much as 6 million tonnes of new LNG capacity to be constructed at Darwin LNG through brownfield expansion. We think this presents a really strong opportunity to potentially integrate that Darwin LNG expansion with our Phase 3 NTLNG development. Turning to Slide 12. The company finished the quarter with a cash position of $59.4 million. That figure includes $6.2 million the company received through an R&D credit during the quarter. The company is still fully funded to deliver IP30 flow rates for our SS-2 and SS-3 wells. In addition, Tamboran is assessing a range of options for funding the remaining wells in our SS pilot development and the associated infrastructure as well.
Beyond that, the company keeps looking at possible farm-out opportunities as a way to speed up our Phase 2 and Phase 3 developments. Such farm-out opportunities might involve drilling extra wells to help mature reserves that would support infrastructure connected to Phase 2 and Phase 3 of our business plan. Turning to Slide 13, you can see the upcoming catalyst beginning in March, when we'll start flow testing on our SS-2H well and aim for an announcement in April on our IP30 from this SS-2 well. After the SS-2 well test, we'll proceed to stimulate and flow test our SS-3 well, with a target of announcing the IP30 flow test results from SS-3 in June. In mid-2025, we'll aim to make a final investment decision on our SS pilot program, which will again target first gas from this pilot project in the first half of 2026. Thanks very much, and I'll hand the call back to the operator for our question-and-answer session. Thank you.
<<operator_script>> Kalei Akamine from Bank of America has our first question.
I suppose, to start, with the pipeline lateral, the pilot, the MOU, and this data center news, you all have been quite busy, and we like seeing that. My first question concerns the upcoming flow test, and maybe it has 2 parts. So for the first part, could you remind us why a gap exists between completion and the flow test? And second, could you remind us what the normalized flow test was for SS-1? And I guess what I'm getting at is when you consider your target for SS-3 at 19 million cubic feet per day, to us, that seems a touch conservative.
Much appreciated for that question, Kalei. To start with the first one, regarding the interval between when stimulation wraps up on SS-2 and when we conduct the SS-2 flow test: once more, we're currently cleaning up that well. We'll be running 2-7/8 inch tubing in the hole, and over the coming few weeks we'll be unloading the well. As soon as gas breakthrough occurs, our IP30 will get underway in early March. That schedule also incorporates a 10-day soak period, and we've included that soak because of what we learned at SS-1 — specifically, the extended shut-in that lets our completion keep generating super high <<inaudible>> inside the shale, which stems from the heavily desiccated mid-Velkerri shale into which our completion was pumped. And so that additional 10 days has demonstrated a direct benefit, based on our SS-1 well. That's why we're taking the extra time prior to kicking off our IP30 flow test. On the conservatism that's embedded in this, you're exactly right. If you take the productivity observed at SS-1 and extrapolate it across the full 10,000 foot of horizontal in SS-3, you get roughly about 19 million cubic feet a day.
That's really the direction we're pointing to. Clearly, since we're achieving greater stimulated rock volume by boosting proppant intensity — which we've been pumping for SS-2 and anticipate continuing to pump in SS-3 — there's a possibility we'll see rates higher than that.
Thanks for that context. My second question concerns the Santos MOU. From what we understand, Santos holds an interest in EP 161, where your company is the minority partner, and that differs from EP 98, which is where your pilot work is focused. So what I want to ask is about how broad the study is. Is their aim to de-risk EP 161 before proceeding? Or would de-risking your stake in EP 98 be enough for them to go ahead with the MOU?
Yes, that's a really good question. In the deepest portion of the basin, we observe that the rocks between EP 161 and the pilot area on EP 98 are quite similar. So there are 2 depocenters: one to the east, where the 161 block is concentrated, and the second major depocenter lies in the western part of the basin. We therefore have data from the most recent horizontal wells drilled on EP 161 in 2021, where we flow tested for more than 90 days on both of those wells. That information genuinely pointed us toward the SS-1 stimulation we pumped last year. So we perceive considerable symmetry between what we're doing under the SS pilot program and the number of pilot wells we're drilling this year — very similar to techniques we would be applying with our partner, Santos, on EP 161. In many respects, we can therefore derisk the EP 161 opportunity relative to what we're doing on EP 98. This forms part of cracking the code on the completion design. As for the DLNG expansion we're working on with Santos, I think we're likewise keeping an open mind regarding where gas could be sourced to supply that expansion train.
That will also be included in the study we're completing with Santos during this year.
So how do we go about reducing risk on 161 going forward? Which wells are they planning?
There's a chance for us to put down more horizontal wells during 2026. Right now, we're talking about drilling 2 horizontal wells on EP 161 in 2026. And we're hoping to lock in that work program sometime this year — ideally by midyear.
Thanks, I appreciate that.
The main point I'd like to stress is that getting our partners involved right from the start matters a great deal, so that when we consider a Northern pipeline linking the Beetaloo to Darwin, we pursue it together with every operator in the Beetaloo. That is really part of Tamboran's effort to bring Santos into their expanding LNG development. And clearly, when we look at NTLNG, we see substantial opportunity for integration.
Scott Hanold from RBC Capital Markets has our next question.
Could you give us a bit more detail on some of the stress detection you found in the casing? Just a little background there. Was it mechanical or reservoir related? And from your talks with your service providers, have they come across that in other places? Or is it more a matter of getting to know the Beetaloo?
Yes. Excellent question, Scott. What we're dealing with here is a mechanical problem that the company picked up on as we were exiting the hole in the vertical portion once the fifth stage had been pumped on SS-3. A stress anomaly was detected, so after halting the stimulation work, we went back in with a camera and an acoustic tool to obtain improved detail on the nature of that anomaly. And in the interest of being overly careful, we made the decision to strengthen that section while, at the same time, carrying on with stimulation on SS-2 and proceeding toward a well test there. Once the well test at SS-2 wraps up, our expectation is to return to SS-3, pump the 60 stages still remaining there, and obtain a flow test in June. That's how we intend to proceed. What this gives us, then, is a chance to capture the learnings from SS-2 — on the completion side as well as what the flow test reveals — and apply them to the 60 stages we plan to pump on SS-3. One point I want to emphasize: none of this relates to the reservoir. It's entirely mechanical in nature. Issues of this sort occur every day of the week across the Permian, Marcellus, and Eagle Ford in the U.S.
The service providers advising the company on this matter are extremely experienced and knowledgeable, and we don't think this is a problem we could resolve with high confidence. Once again, we're keeping a sharp eye on safety. We're keeping a sharp eye on attention to detail. And so, when we noticed this slight anomaly, we concentrated on figuring out where it was coming from in the vertical section and sought to remediate it. So that should give you a little bit of color.
All right, and thanks for that added detail. So my follow-up really concerns the stimulation work overall. I realize you may have ramped up activity on the frac side somewhat beyond what you first envisioned, and perhaps pulled back when it came to the final decision. Could you walk us through part of the reasoning behind the differences between a few of the initial plans and the way you intend to frac this? Does it come down to service availability? Is timing the factor? Or is it your view of what the reservoir is able to handle? Just share a bit of detail on how you arrived at that figure and why it has shifted somewhat in both directions?
Absolutely, and that's a good question, Scott. So we came in with the design we refer to as Tamboran v2, targeting a stimulation intensity of 2,800 pounds per foot, pumping at rates up to 100 barrels a minute. And we had tightened the spacing in our design when we had a shorter lateral on SS-2. So we used the chance to reduce the spacing compared with what we observed on SS-1 — roughly 165 feet down to 130 feet. Once we began pumping at that 130-foot spacing per stage, we observed stress shadowing, and placing all the proppant became somewhat difficult. So we optimized that completion in something close to real time. And we decided to return to 165-foot spacing on our stages. And I was quite pleased to see all the proppant we were pumping get placed. We ended up placing roughly 0.5 million pounds per stage. We could see the 2,800 pounds per foot once we widened the spacing somewhat and pumped at 100 barrels a minute. What encouraged me most, I think, is that over the last 15 or so stages, we were consistently pumping above 2,800 pounds per foot.
Across the most recent 10 stages, we pumped at roughly 3,000 pounds per foot and as much as 110 barrels per minute. What that has really demonstrated to us is some learning regarding, kind of, the proper stage spacing, so we avoid getting into the stress shadowing between the stages that, again, is one of the lessons the Marcellus operators went through early on: how do we get our stage spacing right. Within this SS-2 well, we were able to learn in real time to really optimize this completion design, and I'm feeling very good about, kind of, the next 60 stages for SS-3 having taken this learning forward.
Charles Meade from Johnson Rice has our next question.
Joel, I'd like to follow up on the questions Scott was asking. I think that chart in the bottom right of Slide 7 does an excellent job of telling at least part of the story — it shows that once you made that change, you basically tore off the stages and then really pumped away the sand. I want to ask: you mentioned stress shadowing between stages. Does that point to rock that's perhaps a bit more permeable than what you'd typically see in a U.S. onshore unconventional? And is that what necessitates the larger stages? Also, did you add perfs so you could put away all of that sand when you made the stages longer?
So first off, yes, we did put in some additional perfs. That accounts for part of the greater stage spacing. We added more perfs. And I think many factors play into how these stages get placed. But I think one reason we can place as much sand in proppant with wider stage spacing comes down to rock quality. Higher porosity and better permeability are 2 pieces of that. One thing that has us quite excited, again, part of the analog we've consistently referenced, is how the Beetaloo shale resembles the Marcellus closely. So we built our completions to match what works in the Marcellus. That's where we began in SS-1. But what we're seeing is that the more stages we pump, the Beetaloo will develop its own signature. And the chance to fine-tune the completion design in real time stems from the sort of pressure regime we observe here, 0.6 PSI per foot. It stems from the porosity and permeability being a bit better than even what you see in the Marcellus. So all of this is trending in a good direction, I'd say, both in terms of confirming the completion design against the rock quality we observe, and in being able to pinpoint the optimal completion for the Beetaloo, rather than just copying the Marcellus — this is why we refer to this as a v2 design.
The focus here is squarely on the Beetaloo. Being able to accomplish this at such an early point in the program gives me a lot of encouragement. In the Marcellus, if you recall, perfecting a design of this type required hundreds of wells, and we know our window for moving down the curve is far shorter—the team is performing excellently. Faron and ops crew out in the field are working shoulder to shoulder with Liberty. As we pump each stage, we're doing real-time modeling. That's what a modern 21st century oilfield looks like: while stages are being pumped, you receive actual information and actual data, and you make optimizations from one stage to the next. You don't wait until the entire horizontal has been pumped before tweaking your design—you do it in real time. So I'm extremely upbeat about how the rock is responding to this design, and it gives me considerable encouragement when we look ahead to SS-3.
Understood. One quick item from me on that, then a broader question. On Page 6 — looking at your lateral graph — the label reads total gas average 7%. Should that be read as gas-filled porosity? Is that how to interpret it?
You've got that right.
All right. Then there's the larger matter, Joel — you brought something up, and here's the context; I'd like to request a brief update from you regarding how you see the domestic natural gas market in Australia, since I believe it's somewhat unclear to most people listening on this call. And maybe, as part of that response, you mentioned potentially farming out in the back half of the year to secure the next 4 wells at the Shenandoah South project. From my vantage point, it appears you're drawing increased interest from domestic participants — both E&Ps and consumers — though perhaps that isn't the situation. And maybe you could expand on what you're observing domestically there.
Yes. So to start with, demand within the country on Australia's east coast sits at roughly 1.5 Bcf per day. That figure has remained level for a great many decades now. We don't expect that demand to shrink at any point in the near future. But getting to your point, moratoriums have appeared in New South Wales and Victoria. There's essentially no new exploration at all to speak of along the east coast. And a key supplier to the domestic market has been the Bass Strait field, which Exxon operates, and that field is in terminal decline. So looking ahead 3 to 5 years, we foresee a shortfall exceeding 1 Bcf per day opening up. That comes from government figures. The government regulator issues a report each quarter, and it has been highly consistent about that '28 to '30 window, when you begin to see meaningful shortfalls. And so our effort is to get ahead of that. We believe a pipeline running from the Beetaloo to the east coast to backfill this domestic market will be essential. We're aware that LNG import terminals are under discussion among various gas suppliers as a solution. Our view is that is not -- we think a pipeline out of the Beetaloo is a far superior answer for the Australian consumer, since there's potential for cheaper gas entering the market compared with importing LNG from beyond Australia, along with lower emissions.
In Australia, our focus is very much on lowering what consumers pay. Cutting carbon emissions also matters a great deal to us. And the Beetaloo pipeline, targeted for as early as 2028, satisfies both of those objectives. To offer a bit of context, imported LNG carries roughly 5x the carbon emissions of gas delivered via a Beetaloo pipeline. So if the goal is to cut carbon emissions here in Australia, a large pipeline running from the Beetaloo to the east coast is the answer.
We now move to Jeff Grampp of Alliance Global Partners, who has a question for us.
Joel, I'd like to pick up on something — an earlier question came up about expectations or benchmarks for IP rates, so to speak. It seems like we're basically extrapolating from the results of the 1H. But with the bigger fracs you've completed and intend to keep completing, I'm wondering how you're approaching the analysis of what those larger fracs are worth, so it can guide later development and keep the optimization going.
Yes. Look, on the IP30, we're going to wait and see. As a reservoir engineer with that kind of background, one thing I'm quite keen on is seeing not only the IP30 but how those flow rates hold up across 12 months. That's really the whole point of the pilot — to observe well tests extending past 30 days. The 30-day IP, I believe, will provide an indicative picture of the uplift we might potentially get from greater proppant intensity compared with SS-1. That, I think, is the data point I'm after. From there, though, as we progress through the year, what we learn from the IP30 will shape how many wells we believe are needed to deliver that 40 million a day in our pilot. We'll then begin to zero in on what productivity from this portion of the deal looks like. And that, in turn, will let us plan a much larger development as we examine longer-duration flow tests coming out of these wells. It will give our team considerably more comfort regarding the potential to book reserves and to begin looking at a much bigger well plan.
Thanks, that's genuinely useful. On my follow-up — apologies if I overlooked this, and I don't believe it's come up yet — but regarding local sand, is there anything new on the possible sourcing alternatives? Obviously, from a well cost savings standpoint, that was a significant potential line item. So I'm just curious whether there are any updates from recent discussions or progress on that front.
Yes. So, we're still moving forward with the local sand solution. There's a wash plant we intend to source and have deployed in the field later this year, and the goal is to hopefully put that sand washing plant to use for these follow-up pilot wells. Alongside that effort, we're advancing approvals at the Northern Territory level so a full-scale sand mine can be approved, and we're working to have that sand mine positioned to be operational in 2026. Permitting, then, is moving ahead. We're also in discussions with a few potential partners we could collaborate with on building that local sand mine. And as we keep making progress on this, we'll provide further updates to the market.
We'll take our next question from Anish Kapadia at Hannam & Partners.
To start, if we consider only the opening half of this calendar year, what net CapEx figure do you anticipate will be needed to complete the wells? Then, moving ahead, how are you currently viewing the best-case scenario regarding financing alternatives and the expected timing for that financing tied to the Phase 1 development? I also notice farm-out discussions are still being referenced. I'm curious whether those are essentially paused pending results from 2H and 3H, or whether they are in fact gaining momentum thanks to the encouraging signals you're seeing in global LNG markets right now.
Yes. That's a really solid question, Anish. So the costs sitting in front of us are two well tests at 30 days apiece. Each one of those well tests comes in at roughly $2.5 million to $3 million net to the company. On top of that, there's about USD 10 million to USD 12 million in completion costs that still remain as part of the SS-3 well. So those, I'd say, are the near-term costs bearing down on us as we work to deliver IP30 flow rates across both of our wells. And I want to emphasize that the information coming out of those two wells is going to guide how many wells we need to drill in the second half of this year to meet our 40 million cubic feet a day contract. As things stand, we've taken a conservative approach and assumed four wells will be necessary, but there's an opportunity to potentially drill and complete fewer wells and still deliver that 40 million a day. So the capital tied to drilling will get determined over the next few months, depending on what we see from the well test. We're evaluating a range of debt facilities to help finance the infrastructure connected to the pilot.
Things are moving along well on that front, and we expect to wrap up the financing over the coming months. Keep in mind that the gas sales agreement we executed with the NT government is a CPI-linked contract at a fixed price, and that gives us the chance to draw a solid share of the CapEx needed for the pilot. We could raise that through debt. That's the reason we stay focused with a range of debt providers on this. On the farm-out side, I'd note that we are holding quite a few discussions with prospective partners, and we'll keep pushing that forward throughout 2025.
And given the encouraging data you've seen on drilling time, along with expectations for further improvement there and what's shown up so far regarding completion costs plus the sand, do you have any refreshed thinking on what development wells will cost going forward? Or any updated targets on where you figure you can land for drilling and completing these wells?
Absolutely, and that's a great question. So for the 2 wells, drilling costs run roughly $10 million per well, and that's drilling only. Then, based on the SS-2 and the 35 stages we pumped, it comes to approximately USD 15 million. So drilling and completion all-in is about $25 million, which is where we stand today. Going forward with the follow-up pilot wells, we'll again be looking to incorporate a local sand solution. On the completion side, that gives us a material cost reduction of around $4 million on sand, as we see it. We also anticipate further savings from bulk ordering of equipment. That covers steel and cement, and those are savings we expect as we move into a continuous drilling program. Beyond that, on the completion side, there's an opportunity to use zipper fracs, which would let us pump 8 to 10 stages daily. On SS-2, we're pumping 5 stages a day. That's a single well. Once we begin drilling and completing multiple wells, zipper fracs, I believe, will let us double the efficiencies in the number of stages pumped per day. Obviously, that translates into cost savings. So that's -- I just want to emphasize that the company stays very, very sharply focused on how we reduce cost as we move into a development.
In our view, there is a route to bringing D&C costs down to roughly $16 million all-in. That figure is what we are aiming for. It is our objective. And given the last couple of wells we drilled in the pilot here, I think we are on track.
That brings our Q&A portion to a close. I'll now hand the conference back to Joel, who has some closing remarks.
Thanks so much — I really appreciate all the feedback and the questions, and I’m looking forward to an extremely exciting stretch over the next few months for the company. I also look forward to giving everyone another update when we report next quarter. Thank you very much.
Thanks. That brings today's conference to a close. At this point you're welcome to disconnect your lines, and we appreciate your participation.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Tamboran Resources Corporation transcript - plus 133,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Tamboran Resources Corporation earnings transcripts and 133,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.