Alstom SA (ALO) Earnings Call Transcript
November 2, 2026
Earnings Call Speaker Segments
Welcome to the Alstom conference call. <<operator_script>> At this point, I'll turn the conference over to the speakers so we can get today's call started. Please go ahead.
Good morning, everyone, and thanks for joining us on such short notice. I'm Martin Sion, CEO of Alstom, and with me is Bernard Delpit, Executive Vice President and CFO. Bernard and I will offer a few introductory remarks and cover today's announcements, and then we'll open the floor for Q&A. The year has gotten off to a challenging start, to put it mildly. It has underscored the need to trends across the organization and the need to strengthen our balance sheet. During my first few months in the company, I visited more than 35 sites. I met with Alstom teams, customers, suppliers and investors, and immersed myself in some of our largest projects. My objective was to move quickly from diagnosis to action. I know that changing an organization of this size takes time. And this is why shortly after joining, I launched several urgent actions to deliver early improvement across the company. This includes reinforcing lean management principles, strengthening accountability of project managers, but also simplifying processes to improve efficiency and accelerating cost saving programs, thanks to a better coordination across projects and regions regarding procurement so that we can fully leverage the scale of the backlog. Finally, I've also mobilized the dedicated teams of Alstom experts, which I like to call the tiger teams.
The job of these tiger teams is to push project teams—helping them sharpen how risks are identified and governed, improve planning, and make sure effective mitigation steps are actually in place. We've deployed these tiger teams on a number of critical projects, among them Coradia Max, a regional train platform that has been sold to multiple customers in Germany and Central Europe. That program sits at a crucial point in testing and homologation, and what the tiger teams have contributed has proven valuable in assessing where the project stands. To begin with, their efforts helped craft technical solutions and mitigation measures after major problems surfaced in the first quarter of the fiscal year, problems that pushed us to post production. Those technical solutions were wrapped up at the end of the summer. Then, in the second quarter, a separate dedicated tiger team pinpointed the need to recalibrate the testing phase so that validation and homologation requirements would be met. That has meant a longer homologation timeline and a later start of commercial service—something that only became clear recently. These shifts also carry knock-on effects throughout the wider Coradia Max portfolio, which is made up of projects. So the impact stemming from this platform is significant, and it is a key reason we are here today.
At the same time, I want to give some perspective on the fact that we posted strong results in the first half as well, and the difficulties on Coradia Max don't reflect the wider rolling stock backlog, for essentially three reasons. First, our other big projects are moving along nicely toward entering commercial service. Take Alstom's new high-speed platform, Avelia Horizon — it was homologated last May and, per our customer's decision, it begins commercial service this week. Second, a meaningful portion of the backlog has already reached serial production, where we're applying the proper planning discipline. Those projects are hitting their production targets. Examples include the commuter trains in France, locomotives in Kazakhstan and India, and regional trains in South Africa. Third, a further meaningful portion of the backlog remains in the development phase. Those projects stand to gain from the operational initiatives already in motion, along with the wider operational plans we are currently putting together. Outside rolling stock, our Services and Signalling businesses are proving out their full potential. There, the emphasis is different. We have to keep up the strong momentum and lift our ambitions so as to push growth and performance even further. I'll now turn things over to Bernard, who will walk you through the financial figures and the updated guidance for the current fiscal year.
Thanks, Martin. I'll walk you through the preliminary, unaudited numbers for the first half of this fiscal year. We produced 1,860 cars, which is below last year's level for the same period, mainly because of the slower cadence on the Coradia Max platform. Seasonality should push production higher in the second half. That said, we're cutting our full-year guidance to roughly 4,000 cars, versus 4,400 to 4,500 before, and Coradia Max is the reason. Sales came in at EUR 9.3 billion, up 3% reported and 2% organic. Lower-than-planned car production restrained that growth. In line with the revised production outlook, our organic sales growth expectation for the full year is now low to mid-single digits, versus around 5% previously. The adjusted EBIT margin for the first half is approximately negative 4%, compared with positive 6.4% in the same half last year. That roughly 10 percentage point decline stems entirely from the gross margin adjustment on Coradia Max and from conditions in the Central and Northern Europe region of Alstom. Consequently, our full-year adjusted EBIT margin guidance moves to around 1%, which implies a second-half margin of about 6.5%. Lastly, free cash flow for the first half was negative EUR 1.2 billion, a touch better than we had expected because milestone payments and down payments shifted from the second half into the first.
Payables during H1 are lower than they were when March closed, which is what we anticipated. For the whole year, our free cash flow expectation is now negative EUR 1.5 billion. That gap stems mainly from milestone payments shifting into later years, since homologation schedules have stretched out on 6 of the Coradia projects. It additionally mirrors continuing uncertainty in the Middle East given the geopolitical climate. At this point I'll turn things back over to Martin.
What we've taken away from the tiger team exercise really matters. Those lessons are paying off—they're either helping us solve problems or surfacing more engineering and planning issues that still need attention. We'll keep applying this method to tighten up how we deliver on key projects. The reviews should wrap up by the close of this fiscal year. What they uncover is feeding into the operational plan currently taking shape. Naturally, the free cash flow picture we now anticipate for this year means the group has to bolster its balance sheet so it can hold onto its investment-grade rating. So, with the Board behind us, we're starting a debt reduction program of roughly EUR 2 billion, blending organic and inorganic steps, all to be carried out by September 2027 at the latest. Liquidity has already been boosted by an extra EUR 2 billion credit facility on top of the ones we have, plus the EUR 1.6 billion in cash sitting on our balance sheet at the close of September. As I said earlier, the near-term moves we've set in motion are already making a difference, yet we must push further and make deeper changes to how we run the business so that we get it right first time, every time. With that in mind, we're examining our organizational setup and the way we operate.
The principles guiding us are straightforward: more simplicity, clearer accountability, and sharper focus on development risks, drawing on what we learned from Coradia Max. We'll also examine where additional value can be unlocked through organization, product portfolio, and footprint. These work streams are already in motion, and we'll communicate decisions as they're made. The overall outcome, along with the medium-term financial trajectory, will be presented at the Capital Markets Day in the second quarter of 2027. Everyone at Alstom is focused on strengthening project execution and putting the company on a successful trajectory. And even if the situation is difficult, I am confident in Alstom's future. We operate in a growing market. We have a strong competitive position, and we have the levers to realize our full potential. That concludes the introduction, and we will now take your questions.
<<operator_script>> Our following question is from Andre Kukhnin of UBS.
I wanted to grasp the first half first. So you mentioned that a 10-point margin delta comes mainly from Coradia. That means we're talking about EUR 950 million. Could you just walk us through how much of that is, say, higher operational costs? Is a large share of it penalties that are being paid or provided for the customer? And what has to happen in the second half for that 6.5% margin to actually materialize, please?
Alright, Bernard here — I'll handle this one. So we won't be providing the complete breakdown of that EUR 950 million figure you brought up. That said, yes, it covers penalties as well as extra costs. Those are the primary factors. And once the program wraps up in H1, we've factored in the entire reassessed impact.
Understood. And regarding the plan to deleverage that EUR 2 billion, could you give us a sense of the mix between organic and inorganic options within it, please?
At this point, it's too early to give you a breakdown of the plan. We're just beginning it. Some processes for the disposals that typically form part of a program like this have already been started, and we're working on the remaining parts of the deleveraging plan. As you know, we had already won in '23 and '24. So I'd say it will work the same way when it comes to the sequence of preparation and execution.
Gael de-Bray from Deutsche Bank has the next question.
Could you tell me what portion of the backlog comes from the Coradia platform? And where does the gross margin in the backlog stand now at its new level?
I can address that. The backlog contains 6 Coradia Max projects, and together they come to roughly EUR 5 billion in size. On the gross margin within the backlog, I don't — perhaps you could pick that up, Bernard.
Yeah — the Coradia program's gross margin has gone negative at this point.
And when you look at the group overall, could you give us a sense of where that figure stands at present?
Gael, what was the gross margin in the P&L for H1?
It's in the backlog.
Regarding the backlog, I expect that figure to land near 18%, since the bulk of the decline stems from program contracts that have now slipped into negative territory.
Alright, and this might be my final question. I'm also trying to get a sense of how far you're willing to go when it comes to the divestment piece of the deleveraging effort. Would you be open to selling one of the strongest assets in the portfolio — Signalling, for instance?
Like Bernard mentioned, since I came on board we've already begun looking at what might be sold off. A new CEO doing that strikes me as entirely normal. And we're concentrating on operations that make money, clearly, since that's the point of saving in this situation, but — operations that wouldn't sit at the heart of what we do.
Our next question is from Akash Gupta at JPMorgan.
I have a couple too. First, on the full-year outlook: at the midpoint, you're cutting production for this year by roughly 450 railcars. I'm wondering how much of that comes from Coradia, and whether there are non-Coradia projects as well that are behind this revision to your production target?
Alright, Akash, I'll handle this one. What I'd say is that the Coradia Max project accounts for the vast majority of the revised production outlook. The gap is coming from Coradia.
Moving to the second item, the deleveraging program. I believe you cited EUR 2 billion by September '27. Naturally, you hold some strong assets that others would covet, yet that could affect margins going forward. Also, in the release, I think you said you're still aiming for 8% to 10% over the medium term. So my question is whether you'd be open to something like divesting a minority stake in certain businesses, for instance? Since your previous debt reduction plan, some companies in India have sold minority stakes in their Indian operations, given the high valuations there. I'm not sure about the profitability of your Indian business, but you have a sizable business there. So I'm just wondering whether that could also be on the table, or whether it isn't something you can consider?
Akash, I’ll handle this one. At this point, we’re not going to provide specifics about which assets will be divested. What I’d say is that it reflects a mix of strategic consideration around what counts as core versus noncore, along with a more financial view of how future margins are affected compared with the proceeds those disposals can generate now. So I’d call it early stage, Akash.
Yeah. And maybe just finally, I think there’ll be a question today about how you arrive at that EUR 2 billion figure. I think for this financial year, you’ve got EUR 1.5 billion negative. But does that also mean that in the first half of the next fiscal year, we might see another EUR 500 million of outflow, which is why you’re aiming for EUR 2 billion rather than more or less?
Yes. Let me put it in maybe somewhat simplified terms, but clearly. Of the EUR 1.5 billion in negative free cash flow this year, I'd say roughly EUR 1 billion ought to reverse across the coming years, since those are progress payments that are rate shifting. As for the margin deterioration of, let's say, 0.9 that we booked in the P&L, that will hit free cash flow to the tune of EUR 1 billion to EUR 1.5 billion at completion. So cumulatively, you land in a range of EUR 1.5 billion to EUR 2 billion of need for the ranging.
Our following question is from Vlad Sergievskii at Barclays.
I've got three questions, and I'll go through them one at a time. On the first one: you're now forecasting negative EUR 250 million of free cash flow for the second half of this year, where previously you expected roughly EUR 1.5 billion positive. Meanwhile, you're anticipating a catch-up in car production and a return of your margin to around 6% in that same second half. Could you tell us what's changed in your planning assumptions for the second half specifically, driving this swing of roughly EUR 1.7 billion to EUR 1.8 billion in cash flow generation for the second half?
All right, let me set the record straight on a couple of points. As I mentioned, the EUR 1.2 billion in H1 included some left shifting from progress payments that we had expected — expected in H2, sorry. So my take is that the revision sits at roughly EUR 1.5 billion, rather than the EUR 1.8 billion figure you brought up. Next, the bulk of that revision stems from cash coming in from the Coradia and German projects that is shifting to the right. And as I noted in my introductory remarks, we have built in some caution as well, given the uncertainty we are seeing in the Middle East. So it is a mix of cash in that is shifting high plus, I would say, some fresh assumptions regarding commercial momentum, driven by the geopolitical backdrop.
That's very clear. My next question is about contract assets. In March, those were roughly EUR 6.5 billion. So my belief is that they'll come in higher during the first half. From what you know as of today, could you lay out any material write-downs against that contract asset figure?
No, I don't believe that's the case. What we're announcing today will mostly result in a higher provision for loss at completion, in my view.
Got it. And this last one from me will be very quick. Have you had a chance yet to talk with Moody’s about those preliminary figures? Looking at your full year guidance, it appears that on all 3 measures you’ll have difficulty hitting the downgrade triggers — margin, cash flow and leverage. So please, any feedback from Moody’s?
Reflecting on our conversations with the agency isn’t something I’m in a position to do. So my guess is that the agency will keep you updated, but an open dialogue with Moody’s is something we maintain.
Martin Wilkie with Citi has the next question.
Martin here from Citi. Coming back to that EUR 5 billion figure in the backlog, that's Coradia — my understanding is there are several contracts within a wider program covering the train design itself. So, are all of the contracts inside Coradia now treated as onerous, or only the early ones? I just want to get a sense of how that works from an accounting standpoint on each contract. And on that EUR 5 billion, what period does it deliver over, just so we understand the time frame in which we should expect a 0% gross margin on those Coradia contracts?
I may not have every one of your questions, but I believe the focus is on the gross margin for the Coradia contract. What Bernard said about the Coradia contracts being negative holds true across all 6 projects. The key thing to grasp is that the plan behind the Coradia project involved a first development that would cover most of the homologation work needed for the other one. As a result, the delay we're experiencing on the one — on the first one — is creating a knock-on effect across the remaining 5. On top of that, it's a contract carrying significant penalties, and that's what produced the cliff effect you notice when you look at how large the degradation is in the short term. When we refer to EUR 5 billion, that figure concerns the rolling stock contract, obviously, and not the service contract.
And as for that last one of the 6 contracts, over what period does it actually come through — just so we can grasp how many years it's going to be a drag?
I can't give you the exact date for those final deliveries, but service entry is going to begin in 2028, and it ought to wrap up around the start of 2030, roughly speaking.
<<operator_script>> Our following question is from William Mackie of Kepler Cheuvreux.
Yes, I have a few questions, if I may. First, I'd like to ask about the gross margin reset you've implemented. You've focused a great deal of attention on the largest projects involving Coradia Max, but you also referenced Northern Europe, and there are some legacy issues concerning certain stream programs. So how much of this reset is attributable to Coradia? And which other projects have likewise been reset as part of this adjustment?
Alright, I can handle that, and I won't use the reset language. Actually, we've already brought financials in line with the new schedule — a very recent one — for the Coradia, covering 6 projects. So this is a very large program. And yes, it does have a knock-on effect on other programs sold in or from Germany. But the Coradia Max issue makes up the vast majority of what we're discussing here.
All right. The second one is probably about the technical visibility you now have on finishing homologations and getting into service across those 6 Coradia Max projects. Delays have happened more than once. How much confidence should we place that the timeline ahead is now fixed and achievable?
I completely grasp that question. And that's precisely why, over recent months, we brought in specialists from across the entire company, along with the Tiger team, to collaborate with the project team — to evaluate how solid the hypothesis really is and to figure out how we can assist. On the technical front, thanks to the issue that came up a few months back, it has worked. We've identified fixes to get past the problem that caused production to halt in July. Regarding the testing and validation plan, it's fair to say the tiger team did pinpoint some notable weaknesses. At this point we have a plan that is robust, and it has been validated with the most knowledgeable people at Alstom. I am reviewing it quite often. And as of today, I'm confident this will be the final rescheduling we carry out for the Coradia. That's a commitment we're making to the customer, and we needed to be transparent and to reflect this situation in the financial situation.
My final question concerns cash — specifically the EUR 2 billion recovery program. We have talked several times about certain inorganic steps. Could you share your view on how that might divide between organic and inorganic? And then, in more detail, which organic actions are you considering?
It's too early to get into that level of detail. This is something we'll work on, and we'll work through it together with our Board.
I’d just add that, in my view, a big portion of that EUR 2 billion is likely to be inorganic. And when we say organic, what we mean is talks with clients — we’re working with our clients to go over payment terms and perhaps make adjustments to the contractual terms we have with them.
Delphine Brault from ODDO BHF has our next question.
I've got two questions. First, based on what you're seeing right now, where do you think your net debt-to-EBITDA ratio will end up at the close of H1? Or, to put it another way, what's your EBITDA level at present?
We’ll go through that with the complete data set, Delphine. If you consider — by definition, if you consider the leverage ratio at the close of H1 with that kind of deterioration, I don’t believe that’s the most important question. What matters is how we view it on a forward-looking basis, not just in March but also in September, since we said we intend to carry out our deleveraging program by the end of September. So the plan is to return on that basis to something entirely consistent with Moody’s expectation for an investment-grade company.
And then secondly, would you be open to the French state coming into your capital, or to a strengthening of it, given that BP is already involved?
To put it plainly, that's not a topic we're covering in this discussion.
Actually, no — that hasn’t come up. Given how big an employer we are in France, backing from the French government is clearly there, I’d say, but nothing of that kind has been talked through with them.
Andre Kukhnin from UBS has the next question.
I just wanted to ask about Coradia Max — what's the expectation right now for the homologation timeline?
The date we shared is the end of — well, I’d put it in months instead of <<inaudible>>, given the financial <<inaudible>> in March '28 for the first Coradia project. And the rest are <<inaudible>>.
Right, my understanding was that homologation happens first, and after that there's still some time before service entry. Does that still hold? Because I believe service entry is slated for 2028, or is that calendar...
Yeah, that’s something we should also talk through with the customer. So I won’t get any more specific than that.
All right. All right. I just want to get this straight — well, to be sure I've got it right — that you were already building these trains. And you were building them prior to the first issue coming up, and then you fixed it. And the H1 result takes in the expense of retrofitting those trains already built, along with continuing production. And at this point there's a second issue that you'll likewise need to retrofit...
Yeah — absolutely, you're right. What we found back in Q1 of this year was that certain technical issues existed, and those issues required extra retrofit work. That's the reason we held production back from rising, so we could avoid a higher number of vehicles needing retrofits. Our technical specialists have come up with a way to carry out these retrofits on an industrial scale. And the first retrofit is part of the H1 picture we're showing you today.
Okay, so at this point, how many trains have you built on this already? And is there any indication you can give us for year-end? I think that would help explain the cash swing — the cash recovery.
Let me frame it another way, Andre. For the total car count in H1, the shortfall is mostly — I'd say roughly 2/3 of it — attributable to Coradia, and that will keep increasing in H2. What I mean is, the gap stems from Coradia, since obviously we were counting on a ramp-up during H2. So we'll have the figures ready for our November discussion. But what you should take away is that the shortfall versus the production plan we expected comes mostly — the majority of it — from Coradia.
Okay, okay, understood. So I take it that during 2027 you'll still have them sitting on your balance sheet as you produce them, prior to actually shipping and receiving payment in 2028? Or would there be milestone payments during 2027 tied to how far homologation has progressed?
We are extremely — we are cutting back, if not taking down to close to zero, how many Coradia cars get built during this fiscal year, as we wait for all the testing to wrap up so that we can ramp up on a sound basis next year. That is what we did.
Regarding the vehicles we've already built during the initial 12 months.
Daniela Costa of Goldman Sachs has the next question.
I wanted to get a sense of how you're sizing up what went wrong on these contracts. Is the execution phase entirely to blame? Or is there anything about the original contract terms that, looking back now, you'd say should have been different? Just in terms of the orders you're taking at present — obviously you're still booking a lot of them — are the conditions you're signing those orders under meaningfully different from before in any way? Or would you say that wasn't an issue to begin with?
That's a fair question, and thank you for it. I think, in terms of — what I'd say is that the issue is that we find ourselves dealing with a combination of problems: development project management that could have been better, along with terms and conditions that are extremely stringent. And my belief is that, in the current tender, those terms and conditions would have been spotted during the tender phase, and the outcome would have looked different. On the project management side, in the actions I've set in motion since coming on board, we're strengthening how projects are managed so that we can ensure a situation like the one we're dealing with today does not arise. And should it arise, it ought to be caught far earlier, so it's prevented from growing to this kind of scale. And all of that is going to be built into the shift in operational routine and organization that we're currently working on.
To put a finer point on it, the P&Cs driving that effect this year aren't present in our other contracts. They aren't in that contract either. And just to be clear, they aren't identical across all 6 Coradia contracts. Only 2 of the 6 carry this kind of heavy hit from terms and conditions.
Our following question is from Jonathan Mounsey at BNP Paribas.
Just a couple of things, if I can. First, let's begin with the free cash flow guidance for the year, which I believe is minus EUR 1.5 billion. You state that you're committed to strengthening the balance sheet by EUR 2 billion. I'm just wondering, why not more than that? Because we do have free cash flow this year. I assume there will be costs involved in executing a turnaround plan across the group. Some headroom, in case further project issues arise elsewhere in the group, would seem sensible. And potentially you've got, I don't know, fines from customers who are having to wait for delayed trains. It really feels like when you add all of that together, you're going to be materially deleveraging. You say that the key shareholders who hold Board memberships are supportive. Wouldn't it be a good idea, with their support, to raise more money? And the second question, just to understand: obviously, at present, while you have that investment-grade credit rating, your metrics don't really meet that threshold, which is why we need to strengthen the balance sheet. I'm just wondering, you announced a new revolver. It has no financial covenants. First of all, do you need to draw on that revolver?
To me, at least, the absence of financial covenants is maybe a little surprising. Maybe you could comment on the interest rate that you have to pay in order to get that.
All right. Regarding how we arrived at the EUR 2 billion size, that's something we've been discussing in light of where we stand, the forecast we currently have for this year, and the cash we expect to generate next year. So I believe it strikes the right balance. We went over it in detail, and I think it has been validated. So I won't be sharing any additional figures with you today. This reflects our assessment, and I believe it's the correct one. As for the revolving credit facility, it exists to provide a degree of reassurance about how we'll handle liquidity across the coming quarters. And it gives us a window in which to strengthen the balance sheet. So once more, even if -- this isn't the same number, but it addresses different circumstances. And I think that's what we need to do, also in order to achieve what I'd describe as a strong liquidity position.
Ladies and gentlemen, we appreciate your questions. I’ll now return the conference to the speakers for their closing remarks.
I appreciate everyone joining this call today, and we’ll be together with you in 2 weeks for the complete first-half presentation. Thanks once more.
Take care.
Thanks, everyone. That wraps up the live presentation. You’re welcome to disconnect at this point.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Alstom SA transcript - plus 131,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Alstom SA earnings transcripts and 131,000+ others is available through the