Arihant Superstructures Limited (506194) Earnings Call Transcript & Summary
May 18, 2026
What were the key takeaways from Arihant Superstructures Limited's May 18, 2026 earnings call?
In Q4 FY '26, Arihant Superstructures Limited reported consolidated operating revenue of INR 181 crores, an 18.5% increase year-over-year, and a significant sequential growth of 43% from Q3 FY '26. The company's EBITDA rose to INR 30 crores, reflecting a 37% year-over-year increase, while the PAT was INR 12 crores, resulting in a PAT margin of 6.58%. For the fiscal year, total revenue reached INR 551 crores, up 10.5% year-over-year, with management signaling a positive outlook for FY '27, expecting project deliveries to exceed 2,000 units and revenue to reach around INR 700 crores, indicating strong operational momentum.
What topics did Arihant Superstructures Limited cover?
- Revenue Growth: Arihant achieved consolidated operating revenue of INR 181 crores in Q4 FY '26, marking an 18.5% increase year-over-year and a 43% sequential increase. Management noted, 'We are expecting a lot of deliveries... good numbers are going to come from multiple projects.'
- EBITDA and Margins: The EBITDA for Q4 FY '26 stood at INR 30 crores, with an EBITDA margin of 16.7%. This was attributed to the recognition of the World Villas project, which incurred pre-operating expenses. Management expects margins to improve in FY '27, targeting a range of 25-27%.
- Sales Bookings and Pricing: Sales bookings reached 395 units valued at INR 313 crores in Q4 FY '26, with an average price per square foot of INR 7,870, up 5.5% YoY. The management highlighted, 'We have been able to increase the price by INR 1 crore from the launch period.'
- Debt and Financial Health: The company's net debt was reported at INR 451 crores, with a goal to reduce it as projects advance. Management stated, 'We can achieve... our goal is to obviously reduce the debt... similar case will also happen in the other ongoing projects.'
- Operational Execution: Arihant delivered 1,721 units in FY '26, a fivefold increase year-over-year. The management emphasized strong execution capabilities, stating, 'We believe our strong sales traction along with increasing delivery momentum demonstrates our ability to execute efficiently.'
What were Arihant Superstructures Limited's May 18, 2026 results?
- Revenue: INR 181 crores (vs INR 158.5 crores est, +18.5% YoY)
- EBITDA: INR 30 crores (up 37% YoY, margin at 16.7%)
- PAT: INR 12 crores (PAT margin of 6.58%)
- Total Revenue FY '26: INR 551 crores (up 10.5% YoY)
- Sales Bookings: 395 units (valued at INR 313 crores in Q4)
- Average Price per Square Foot: INR 7,870 (up 5.5% YoY)
Arihant Superstructures Limited's strong operational performance and positive guidance for FY '27 suggest a favorable outlook for the stock. Key catalysts include ongoing project deliveries and stable demand in the premium housing segment, while risks include rising interest costs and geopolitical uncertainties impacting consumer behavior.
Earnings Call Speaker Segments
Good day, ladies and gentlemen, and welcome to the Q4 FY '26 earnings conference call for Arihant Superstructures Limited. <<operator_script>> Kindly be aware that this call is being recorded. At this point, I hand the conference call over to Ms. Kunjal Agarwal. Thank you, and the floor is yours.
Thank you very much. Greetings, and good afternoon, all of you. Speaking for Arihant Capital Markets Limited, we appreciate each of you being on this Q4 FY '26 Earnings Conference Call of Arihant Superstructures Limited. Joining us from the management side today are Mr. Ashok Chhajer, Chairman and Managing Director; Mr. Parth Chhajer, Whole-Time Director; and Mr. Udit Kasera, Chief Financial Officer of the company. So, with no more waiting, I'll pass the call over to the management for his opening remarks.
Yes. Thank you. Good afternoon, everyone, and thanks for taking the time to join this Arihant Superstructures Limited conference call, where we'll discuss the results and business updates for the fourth quarter and financial year 2026. I believe you've had a chance to go through our financials and investor presentations, which have been filed with the exchanges. At this point, I'd like to hand things over to our CFO, Mr. Udit Kasera, who will walk you through the financial highlights for the quarter, and after that, I'll share the key operational and business updates.
Good afternoon, everyone. To begin, I’ll walk you through the key financial results for the quarter we’re reviewing. Consolidated operating revenue in Q4 FY ’26 came in at INR 181 crores, which is an 18.5% rise Y-o-Y and roughly 43% sequential growth versus Q3 FY ’26. EBITDA was INR 30 crores, 37% higher Y-o-Y and about 4% above the prior quarter. EBITDA margin came to 16.7%, and quarterly PAT was INR 12 crores, with a PAT margin of 6.58%. For the financial year ended 31st March 2026, operating revenue reached INR 551 crores, up about 10.5% Y-o-Y. EBITDA was INR 127 crores, a 21% increase, and EBITDA margin improved to 23%, by approximately 200 basis points. Company PAT was INR 46 crores, with a PAT margin of 8.35%. Net worth as of 31st March is INR 450 crores. With that, I’ll pass the call to Mr. Parth for the operational highlights.
Thanks. Turning now to the main operational highlights for the quarter. In this quarter, sales bookings came to 395 units, equal to 3.98 lakh square feet of area and worth INR 313 crores. The average price achieved was INR 7,870 per square foot; in the same quarter a year earlier, that figure was INR 7,461 per square foot, which means the average selling price rose 5.5% year on year. The average price per unit sold came to roughly INR 79 lakhs. Collections in the quarter reached INR 169 crores. For the year ended March 2026, sales bookings totaled 1,155 units, equivalent to 12.58 lakh square feet of area, with a booking value of INR 977 crores — a 10% increase over the prior year. For the full financial year, the average price per square foot achieved was INR 7,769, versus INR 6,082 per square foot in FY '25, representing a 27% year-on-year rise in the average price achieved. The average price of units sold for this financial year was INR 84.62 lakhs. Collections for this financial year were INR 539 crores.
One of the quarter's key highlights was that we achieved OC for 2 towers in Arihant Aspire Phase 1, and in that we handed over 657 units — roughly 737,000 square feet of area across both towers. With that, FY '26 also turned into a landmark year when it came to project deliveries and execution, with the company delivering 1,721 units in total during the FY financial year 2026, a substantial increase compared with prior years. That sharp jump in deliveries shows the strong execution capability the company has, as we keep our focus on completing projects on time, and it marks the start of the larger delivery cycle, with subsequent phases and additional projects expected to reach delivery stages from FY '27 onwards as well. During the last quarter, we also launched a new tower called Benita at Arihant Aspire in Panvel, comprising 382,000 square feet of saleable area. This launch further strengthens our presence in the Panvel micro-market, where demand remains healthy, supported by better infrastructure connectivity. In light of current global macro uncertainties and energy-related concerns, the Prime Minister has also stressed how important prudent consumption and efficient resource utilization are. At Arihant, we remain well prepared to navigate such situations and have historically come out stronger through challenging cycles.
For the real estate sector, luckily, the customer journey stretches out far longer, and we book revenue across several quarters for particular units sold in a project's early phases. That lets us steer through short-term macro turbulence more effectively while keeping the business stable over the long term. In real estate, beyond location, 2 of the key success factors are sales velocity and the capability to execute. We feel that our robust sales traction, together with growing delivery momentum, shows our capacity to execute efficiently through different cycles. I'm pleased to report that our gross development value has risen to roughly INR 14,000 crores now, up from about INR 12,000 crores a year ago, even with higher execution and deliveries in FY '26. Improved realizations across ongoing projects have supported this gain, along with the strong infrastructure-led transformation now taking place in Navi Mumbai. Navi Mumbai International Airport has been operational for over 6 months now and is handling close to 150-plus flights daily. We are seeing a gradual movement of corporates and their ecosystems toward Navi Mumbai, which is boosting residential demand positively across several key micro markets where we have a strong presence. On the premium housing side, World Villas remains a strategically important project for us.
The integrated development that includes villas, hotels, and a gymkhana should generate annuity income streams over the long term for the company in the years ahead. As of March 2026, unsold inventory was at 71 units, carrying a book value of INR 14 crores, which reflects healthy absorption across our portfolio. Looking forward, we remain confident that Navi Mumbai is entering a long-term structural growth cycle, backed by major infrastructure development, better connectivity, and rising economic activity. Given our diversified portfolio, strong land bank, and disciplined execution capabilities, we believe we are well positioned to take advantage of these opportunities and create sustainable long-term value for all stakeholders. With that, I will now open the floor for questions and answers. Thank you.
<<operator_script>> Our next question is from Aneesha Agarwal, an individual investor.
I’ve only got a handful of questions. Between Q3 and Q4 FY ’26, World Villas Phase 1’s total sellable area by itself rose from 4.14 lakh square feet to 10 lakh square feet — that’s a pretty big percentage increase — while units went only from 176 to 180. In a similar way, Town Villas sellable area almost doubled, from 30 lakh square feet to 58 lakh square feet. The Q3 highlight referred to a 3.5-acre joint venture being singled out at Jok-Manivali, which takes the township to 96.5 acres. So is that entire area increase attributable to that single 3.5-acre JV addition? If that’s the case, the implied FSI per acre looks extraordinarily high. Can management reconcile that figure and confirm whether there was any additional regulatory approval or plan revision?
Yes. So, to make things clearer for all our investors and shareholders, we changed the RERA carpet area that existed in the World Villas and Town Villas project over to sellable area. That way, the yardsticks used for judging all the elements driving costs as well as sales on any project can be compared far more easily and comfortably, and that is the reason the area increase is being seen. Beyond that, there is clearly some design modification in the villas as well — carpet areas for each villa have gone up somewhat, so that has contributed to the larger area too, but the bulk of the increase comes from switching carpet area to sellable areas, so that for an investor it becomes simple to track and compare other cost factors against the other ongoing projects we have on an equal footing.
All right, sir. And sir, for World Villas, with that INR 3.5 billion of CapEx, are you thinking about raising any equity funds at all? Or is the whole thing going to be funded through debt?
No. So the primary funding for this will come from the project's internal accruals along with debt. We aren't looking at any particular equity raise for the World Villas project.
All right. And sir, because of the weak rupee, is there any disruption on the supply side? For instance, what share of your construction material costs is tied to imports? And have you taken hedging positions to guard against more currency depreciation?
Yeah. So clearly, the geopolitical situation right now isn't so great, and it's hitting the cost and manufacturing sector in a big way. We're seeing that costs could shift anywhere from 3% to 5% for a company like ours as well, in the short — well, over the long term. We'll just have to wait and see exactly how much of an increase actually happens. But based on the prices that are ongoing today across all the commodities, they've gone up compared with where they stood 3 months ago.
Okay, sir. And sir, similar to what we heard in PM Modi's recent speech, do you see any chance that demand could weaken among NRI buyers, who are an important segment for premium projects such as World Villas?
Yeah, we've been seeing more inquiries for premium projects across our portfolio coming from NRI buyers. There's been a rise, and some of those have converted too. So interest from the NRI buyer segment has picked up over the last 2.5 months.
So there’s no risk of that, like, after PM Modi’s appeal to cut consumption.
Sure, it's really an appeal to the whole general public that we have here in the country. But even so, business has to keep moving. That means there's an added cost we're going to have to absorb, somewhere in the range of 3% to 5% above what we had anticipated. And we can recoup that by raising the selling price on the remaining units. So as far as the company goes, there isn't really any risk.
Raj Kumar, an individual investor, is up next with a question.
Hi there, can everyone hear me okay?
Yes.
I’ve only got a handful of questions. Last quarter, you said you were seeing better foot traffic at World Villas. This quarter, though, just 4 villas were sold. Is there any risk there? And what does the wider demand picture look like?
Look, the uptick in villa walk-ins has clearly been a positive sign for us. And decisions aren’t always made right away. In a segment like this, people need more time to decide and finalize. So for a product of this kind, the turnaround time on any transaction falls somewhere from 75 to 120 days. So it will clearly show up in the quarters ahead.
So what are the expectations for the next quarter? Like, any kind of expectation...
Giving you a precise expectation for each project isn't something I'm able to do. There's no way to provide an exact count of what to expect. That said, we do anticipate strong figures during this financial year. The project is coming along nicely. At present we're building roughly 112-odd villas, and things are moving forward really well. Naturally, that development will increase the unit's value. And my sense is we'll be able to capture considerably more within this financial year.
Sure, that's fine. Just one last question from me. Could you provide something like a margin differential across all 3 segments — premium, affordable, all 3 of those? Can you break out the margins for each of them?
When we consider taking on any project as a company, we look for a 33% EBITDA margin across every segment, along with PAT margins of around 24%. Certain projects will clearly deliver higher margins — for example World Villas and Town Villas, where our land cost is far, far lower. That gives us an improved margin, with EBITDA margins of almost 45%, 47% on these 2 projects. But this happens purely because of the low land cost and the early mover advantage the company secured over the last 2.5, 3 years, which was timed very well, since the MTHL - Atal Setu and the airport have both been inaugurated in the last 1, 1.5 years. So that advantage sits with us, and it will show up in the company's balance sheet over the coming 4 to 5 years.
<<operator_script>> Our following question is from Aditya, who is an individual investor.
So my first question for you, sir, is this: PAT fell 15.9% year-over-year even though revenue rose 10.5%. Interest costs climbed 65% to INR 677 million. So what's the plan for deleveraging? And when do you expect net debt to equity to improve from where it stands now at 1.81x?
Look, we've got debt spread across a number of projects. Debt is needed in a project's early phase, and as the project moves forward, that debt gets paid down. At present, besides construction finance loans — I mean, besides the residential business, we're also building annuity assets, and those will need debt, with some of it sitting at a long-term stage as we go forward too. So we can get to — I mean, obviously our aim is to bring down the debt, which currently stands at roughly INR 451-odd crores, that's the secured debt, INR 453 crores to be exact. So our aim is to trim some of it in certain ongoing projects, but then it will be added on in the annuity asset projects. So I think it could go up by another INR 50-odd crores from here. I mean, to give you an example, our Arihant Aspire loan, which comes from Tata Capital, had an outstanding of about INR 82 crores at the end of September. And at the end of March, we're at INR 40 crores. And in this financial year FY '27, which is underway, we'll repay that entire debt. So as the project moves toward the nearing completion stage, we were able to pay off all of the debt through sales and internal accruals.
This same situation is going to apply to our other projects that are currently underway, such as Arihant Advika at Vashi and the World Villas. As those projects move forward, the corresponding debts will be settled in due course.
Right, sir, and one more thing I'd ask you: operating cash flow has come in negative for 4 years running now. So when does the company anticipate free cash flow turning positive?
My view is that starting with the coming financial year, free cash flow ought to move into positive territory, since at present — across the last 2, 3 years — we've been raising funds so our projects could be completed on schedule, and that shows up in the deliveries we achieved in FY '26, which will keep going and improve further in FY '27 too. So over the next 2 years, 3 years — certainly within 2 years — we'll be positive on cash flow going forward.
Another thing people are asking is that unit sales dropped 26% from a year earlier, even though presales value went up. That points to a pretty big move toward products with higher ticket prices. Was that deliberate? And what does it mean for your positioning in affordable housing?
Look, we've got everything on the table. That said, mid-income and luxury housing performed better last year. So the picture is shifting. Even now, affordable housing still accounts for a large share when it comes to transaction counts. But going forward, the company is also placing more emphasis on the mid-income and luxury segments. We're quite pleased with this shift, and we expect that momentum to carry on in the future too.
All right, sir — building on that question: you shipped 1,721 units in FY '26, a 5x increase year-over-year. So might you provide guidance on delivery volumes by project for FY '27 and FY '28?
Looking at it project by project, it's tough to pin down, but we're anticipating a large figure in this financial year too when it comes to deliveries. It should comfortably exceed 2,000. Among the projects in the pipeline are Arihant Aalishan Kharghar Phase 2, then Arihant Aspire Della Tower, and Arihant Advika at Vashi. These will therefore make a substantial contribution to delivery volumes during the current financial year, FY '27. And clearly, in Q1 — I mean, we'll be looking for deliveries of Arihant Anaika 5 and Arihant Aaradhya. So overall, things look quite encouraging regarding the delivery lineup and the completion of several projects in this financial year. As for ready stock, anything approaching possession will see strong movement, and that should generate healthy cash flows for the company too.
Alright, one more question from me: given gross debt of INR 873 crores along with unsecured loans totaling INR 361 crores, how much does the cost differ between secured and unsecured borrowings? Also, what does the repayment schedule look like for the unsecured debt?
Unsecured debt carries a blended average of 13%, 13.5%, while secured debt currently averages roughly 12.5%. That puts the company's blended cost of debt at about 12.75%. On repayment of the unsecured portion — the loan comes from the promoters and becomes payable when enabled. As projects approach completion, we should be in a position to pay back those loans. The secured lenders, however, get first priority. After that is settled, we then repay the unsecured.
All right, sir. So — okay. And the final thing I want to ask you is whether you're looking at any equity raise to fund the World Villas plus hospitality CapEx of INR 3.5 billion. Or is that going to be funded entirely through debt?
Yeah, it’s going to be a combination of internal accruals and debt, with debt making up the majority. We aren’t looking for equity specifically for this project, since the land has already been acquired. The approvals are in hand. So the only remaining step is to construct and build out the assets, and debt costs the company roughly, say, 10%, which is reasonable, because equity cost would be much, much higher than debt. So we aren’t seeking any fundraise specifically for this project. At the company level, we may consider some fundraise at a later stage, but nothing today.
Our next question is from Vishal V, an individual investor.
Sir, my question relates to what we see in the EP: units sold have dropped from INR 1,500 to roughly INR 1,155. Area sold has also come down, from 14.61 to 12.58. Yet the value of our sales has gone up, from INR 887 crores to INR 977 crores. So what is the realization trend? What was the average realization for the quarter and for the whole year? And what trend are you seeing in the area where you operate?
Yes. So, Mr. Vishal, in the prior year, the average realization per square foot was INR 6,082. And during this financial year FY '25, it came in at INR 7,769 per square feet. So we've recorded a 27% rise in average realization, and that's largely because a greater share of sales came from the premium and mid-income product categories.
All right, sir. And one more question, sir: what would the FY '27 target be when it comes to presales?
We’re therefore looking at a compound annual growth rate of 25% to 30%.
<<operator_script>> Our following question is from Roshni, an individual investor.
Sir, I’d like to ask about World Villas. World Villas Phase 1 is just 23% complete, with 55 units booked out of 180. So what’s the sales velocity target, and what’s the completion timeline?
I mean, for this financial year, we're expecting sales of roughly 65, maybe 70-something additional units. And as for the completion timeline for the whole project starting from today, it appears it will extend to 2030. As for Phase 1, the target for Phase 1 is completion by October of 2027.
Understood. And sir, the 5-Star Hotel in Panvel along with the 4-Star in Koproli reflect a fresh business model. So what is the expected timeline for CapEx? And when do we expect hospitality to deliver its first revenue contribution?
Regarding the hotel we're building at Panvel Chowk, located within the World Villas project, our brand should be locked in by the end of this first quarter, and work is already underway. Excavation has been finished. We anticipate that 3 to 3.5 years from now, the first revenues will begin to be triggered. As for the new hotel at Koproli, it was just finalized very recently. So at present it sits at the approval stage. That project will call for an investment of roughly INR 60 crores altogether. But the timeline for it too — since it's a smaller-scale development — will be about 3 years from now as well.
Understood, sir. One more thing, sir. GDV has risen to INR 1,400 crores (sic) 14,000 crores from INR 1,250 crores (sic) 12,500 crores a year ago. Could you break down how much of that gain came from price appreciation and how much from new project additions?
Look, in the last year, the only new land that got bought was for the Town Villas project. So before that — I mean, as of the end of March 2025, we stood at roughly 78 acres. I believe we added another 20-something acres during this financial year. That's the new acquisition we completed over the last financial year. The big jump in GDV, from INR 12,500 crores up to INR 14,000 crores, has come from across all the projects. Because of the airport and the infrastructure growth surrounding it, we've projected stronger prices, and we're already achieving higher prices today than what was projected a year ago. So that's the main factor, aside from the newly added land, behind taking GDV from INR 12,500 crores to INR 14,000 crores.
Understood. Sir, would you mind shedding some light on the project pipeline for FY '27?
We have quite a few projects in progress at the moment. We're expecting new launches at Arihant Aspire — another tower — and we should be opening Arihant Avanti at Shilphata. Also, by Q4, we should expect Town Villas to launch as well. Those are 3 new projects we anticipate kicking off during this financial year too.
Our following question is from Amish Kanani, who is with Knowise Investment Managers.
Congrats on a solid Q4 compared with at least the prior year. Sir, the question is twofold. First, Q4 carried a very thin margin even with the growth. So could you give us a sense of why that didn't really show up in our EBITDA margin, which has dropped to 16.7%, and because of that our full-year margins have, well, they did improve year on year, but they've slipped to 23%. So first, was there anything specific in Q4 that hit our margin? And with that in mind, could you give us a sense of whether, since the premium mix of our project is getting better, we should assume things will improve going forward on an annual basis?
Right. So during Q4, we began recognizing revenue for the World Villas project. As a result, margins came down — clearly, that's from interest costs, and also because the first time a project is recognized, every pre-operating expense gets recognized alongside it. So the big chunk of marketing costs and so on that we'd incurred also fed into the cost base for this quarter. Looking ahead, naturally, we expect — this relates to World Villas, which...
Regarding World Villas, that's fine. From here on, it stays the same.
Looking ahead, margins should clearly get better, since the older backlog of expenses from before operations and from marketing has already hit the P&L, and on top of that the new sales plus construction progress will help us achieve stronger margins down the line. Also, PAT margins came down because interest costs were higher this financial year compared with the last one. That said, we anticipate raising our EBITDA margin in FY '27 and bringing it into the 25% to 27% range, as contributions from the new projects will add further to the P&L.
Okay, thank you. So, sir, on an annual basis our presales have hit roughly the INR 1,000 crore level, and collections stand at around INR 540 crores, which have held steady over the last 2 years. However, revenue remains stuck somewhere between INR 500 crores and INR 550 crores, and that tells us there is a great deal of work needed on delivery and, in a sense, execution. So, first, when could this gap, if you will, be closed — meaning when do we see revenue reaching, let's say, a level above INR 1,000 crores? We hear you indicating presales growth of maybe 25%, 30% from here, so perhaps in our model we can assume presales of some figure, say around INR 1,250 crores. But as for actually delivering projects, completing them and handing them over, when will revenue likewise make a leap, if it does at all — could you give us a sense of that based on the execution timeline as it stands today, sir?
Right, so we use the percentage completion method. As the project moves forward, revenue gets recognized proportionately. As I mentioned, we're expecting a lot of deliveries in this financial year as well. So solid numbers will come from several projects lined up for closure and possession during this financial year. That will bring us more revenues, like Arihant Aalishan at Kharghar, Aspire at Panvel, and Arihant Advika at Vashi. So these are key projects that will contribute to the company's revenue at large. And because of that, we'll be able to jump forward from this INR 500 crores, INR 550 crores top line by, say, to around INR 700-plus crores this year.
Thank you, sir — that helps. And on World Villas, sir: Phase 1 didn't gain momentum quite as strongly as one might have anticipated, considering the activity around, let's say, Navi Mumbai Airport. So the question is whether Phase 2 will be launched only once we've achieved reasonable traction at World Villas 1. Do you have any thoughts on that, sir?
Yes. Look, when it comes to also pushing velocity, we have to be careful that we're able to earn the right margin — the margin we work for. So on this project too, we're very mindful of that. We don't want to simply hand over prices to customers just so we can do more velocity. What matters to us is making this project stand out. Obviously, in terms of design, it already stands out today. Nothing in the whole vicinity competes with it, but we want to make a good amount of money from this project, because from the launch price until now, we've also raised the selling price. That's the reason velocities have come down recently. But at this point the customer understands that they will have to pay a price if they want to participate in this property. And we'll see that reflected in this financial year very smoothly.
Sure, that's really good to hear, sir. We kept prices steady rather than, you know, selling at a discount. Sir, is there any indication of the sort of price increases you've seen — some sense of it? Because I remember noting that 1 villa was around, say, INR 3.5 crores when we launched, and in terms of per square feet price or per villa price, what percentage increase have we taken, sir? You did mention the overall GDV value going up. Maybe we can infer it from that, but could you give us some sense, sir?
For World Villas, prices have climbed by nearly INR 1 crore plus, in terms of realization levels, compared with where we began. So it's — we have several categories. There are 3 configuration types, and then plenty of options. As a result, pricing differs depending on what the customer picks to purchase — certain buyers take elevators, certain ones don't take a pool, certain ones take bare shell, certain ones take finishing. So the pricing varies. Still, on the whole, we've managed to raise the price by INR 1 crore since the launch period. That's why you'll see improved numbers going forward as well. Throughout the sector, rates have risen too, thanks to the infrastructure development we have seen in this part of the city. Looking ahead, clearly, with the geopolitical situation now, we are bound to raise prices further for the balance inventories across all projects, since we cannot lose on the margins. So clearly, it will be a wait and watch. But I think demand remains strong across multiple housing segments. We continue to witness great traction, great interest across all the products we are catering to, and there is — I mean, fortunately, the population is healthy enough to help us — help the company as well as help the economy get through this phase that we are going through.
Sure. Sir, my final question, sir. Regarding CapEx, I had observed that significant CapEx will be required for developing this World Villas — particularly the hotel and the gymkhana we are planning. In that light, sir, if you could give us some sense of, first, we probably have presales, a lot of things. So perhaps the normal residential construction could be self-funded, the way I understand it. But if you can give us some sense of what the CapEx is for this year, including the new hotel you mentioned at INR 60 crores, what would be, say, the new CapEx for this year? And whether it is self-funded or whether we need to worry about debt increasing even from here?
So for the gymkhana and the hotel development, we'll be taking on debt — and in this financial year, we expect to do a CapEx of roughly INR 75 crores on those 2 assets. That much debt will get added. As I mentioned earlier, at the same time, projects that are moving ahead and nearing completion, such as Arihant Advika at Vashi and Arihant Aspire — debt on those is beginning to be repaid as well. So on the whole, debt might go up by another INR 50 crores from where we are now. That's what we're envisaging. As for CapEx, we plan to spend somewhere around INR 400-plus-odd crores on construction this financial year across all the projects. So that's the CapEx target we've set.
So if we include that INR 75 crores — I mean, counting the INR 75 crores from the gymkhana and the hotel — is that the right assumption, sir?
Yes.
<<operator_script>> Our following question is from Raj Shah, an individual investor.
Can everyone hear me?
Yes.
Yes. Sir, my question is about the GDV. What would the GDV be for the latest phase of Arihant Aspire? And in the last quarter, how much of the booking has been recognized?
Unclear stage we kicked off -- hello?
Yes, sir. We can hear you.
Sorry, I didn't catch your question — which phase are you asking about?
The latest stage of Arihant Aspire.
So yes, we did launch Phase 4 — that's Phoenix Tower — and it comes to INR 382 crores, representing 382,000 square feet of total developable area. The CapEx on that project, then, is expected to land at roughly INR 190-odd crores for this tower specifically.
Alright, sir. My next question is also more about the industry outlook. So with the geopolitical uncertainties that are ongoing, are you seeing any shift in how customers behave, especially delays in booking decisions on the part of end users? And on top of that, how is the company handling the effect of construction costs that are rising? And do you anticipate any meaningful impact on project margins or on your demand going forward?
And yes, everyone is watching the situation, with some customers feeling panic, but we aren't seeing any decisions come to a halt. Of course, some customers may need more time, yet we aren't seeing any slowdown in transactions. Deals are carrying on at levels similar to those before the war began. As for construction cost, clearly whatever is sold will have to stay at roughly the same price, but we'll need to recover the incremental cost going toward construction from the remaining unit sales. So I think there's nothing to worry about. And to point out, we're doing very well in projects that have already seen deliveries in earlier phases or are expected to be delivered within a near timeline. So we aren't seeing any challenges as such across many projects. So things are progressing very well. Obviously, this is a time when people will have to wait and be patient. And I think there could be surprises ahead for the Indian economy.
Tanya Arora, an individual investor, has the next question on the line.
I've got just a couple of quick questions. The first thing I'd like to find out is where things currently stand on wrapping up the 5-Star hotel that was part of the World Villas project.
Yes. So we're nearly at the last stages, and hopefully by the end of this quarter, we should be able to come back with the name that we've finalized.
Have we actually found a hospitality partner or a brand management brand at this point?
Yes.
And could you give me a quick update on the gymkhana segment as well — for example, how many total memberships we've sold to date? And what does the membership pricing structure look like right now?
I'll have my sales team follow up with you on that. I mean, we've completed, let's say, more than 800 memberships. They'll respond to you regarding the pricing involved. That's -- that shouldn't be discussed or combined with the financial developments we're covering here.
That concludes the question-and-answer portion. Ms. Kunjal Agarwal will now take over the conference for closing remarks.
We appreciate the management and everyone taking part in Arihant Superstructures' Q4 FY '26 conference call. At this point, I'll pass the call over to the management for their closing remarks.
Thanks to all of you for being with us on today’s earnings call. We trust that we managed to answer each of your questions in a way that left you satisfied. Should anything else come to mind, or if you’d like more details, please don’t hesitate to get in touch with our team — the Investor Relations team at Valorem Advisors — or reach out to our finance team. Our thanks also go to Arihant Capital for hosting this call on our behalf. Thank you so much.
Thank you. That brings this conference to a close on behalf of Arihant Superstructures Limited. We appreciate your participation, and you're welcome to disconnect your lines at this point. Thank you.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Arihant Superstructures Limited transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Arihant Superstructures Limited earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.