Home / Transcripts / Bannerman Energy Ltd (BMN) · January 29, 2026

Bannerman Energy Ltd (BMN) Earnings Call Transcript

January 29, 2026

Australian Securities Exchange AU Energy Oil, Gas and Consumable Fuels earnings 23 min

Earnings Call Speaker Segments

Emma Culver executive
#1

Good afternoon, everyone, and thanks for tuning in to the Bannerman Energy quarterly update webinar covering the December 2025 quarter. My name is Emma Culver, and I serve as Investor Relations Manager here at Bannerman Energy — I really appreciate you all taking the time to join us this afternoon. With me today is Gavin Chamberlain, our Chief Executive Officer, and he'll give you a brief update on Bannerman, walk through the quarter's highlights, and cover all the progress taking place at the Etango project in Namibia. After that, we'll open things up for Q&A — or rather, Gavin will take your questions. Most of you know Zoom well, but in case you don't, the toolbar sits at the bottom of your screen and includes the Q&A option. Just type your questions in there, and once Gavin has finished his overview of the quarter, I'll work through them. At this point, let me hand things over to Gavin. We're saying good morning to him in Cape Town, and thank you for joining us despite the early hour — I'm sure everyone is eager to hear from you today, Gavin.

Gavin Chamberlain executive
#2

Thanks, Emma. Good morning, everyone, from Cape Town, where it's very early. It's such an exciting moment for uranium. Given how the spot price is moving right now, this really is a really, really good sector to be part of. What I want to discuss today is how much progress we achieved over the last quarter. We're very happy with where we've got to. In particular, our safety record — 16 years with no lost-time injury — really stands out as a highlight. The fact that the team on site has come to grips with the shift from what was effectively exploration into construction, and has kept up an LTI-free record, is really pleasing for me and for the rest of the team. As for the early works construction activities, we carried on with all of them during this last quarter, in line with budget and schedule, and significant new contractors are now on site and also progressing extremely well. Our detailed design and procurement work has kept advancing. We're moving well into the structural steel component of the dry plant area, and the wet plant is slowly but surely starting to gain traction as well. On long-term infrastructure, construction of the permanent water supply line has taken off and is progressing in line with our expectations, and we're very pleased with the contractor we appointed in that area.

Gavin Chamberlain executive
#3

So clearly, I think during the previous quarter we discussed the fact that we'd completed the factory acceptance test on the HPGR — that stands for high-pressure grinding roller — and it has now been delivered successfully to site. I think that's, again, genuinely solid evidence that the plans we put in place for importing equipment for the project have now been tested and have delivered, and the team at site has once more come through with flying colors. We feel very comfortable that we got every delivery box onto site without any real clearance problems in-country. We ended the quarter with a strong cash balance of $89 million Australian dollars, and we still hold additional liquid assets valued at 12.7, and obviously no debt whatsoever at the moment. As I mentioned, as I said at the start of my introduction as well, the uranium price had risen nicely to $87, but has kept up this trend, and we're very pleased to see this now becoming a reality in our lives. Emma? I thought we would share a couple of photographs, because a number of you may already have visited site, and a number of you may be joining us — which we're really looking forward to — in February.

Gavin Chamberlain executive
#4

For anyone who hasn't visited or won't get the chance to join us in February, here are a couple of photos showing the progress we've made on site. What you're seeing is the heap leach pad, 1 kilometer long by 300 meters wide, and we've now finished the first three cells and remain on track to finish it consistent with the construction schedule. Another contract that began operating during the quarter involved blasting, crushing, and screening the drainage material we need for the heap leach pad. This is among the original capital saving ideas proposed during the FEED phase, where we have material on site that we blast, then crush, and then carry out all the sieving needed to bring it to spec, and that material will subsequently be used in the drainage on the heap leach pad. The other major contract that truly gained momentum last quarter was the concrete contract. They've begun work in the primary crusher, and it's encouraging to see that the reinforcement is already nearly at ground level, with 50% of all the reinforcement already installed.

Gavin Chamberlain executive
#5

Once again, we're really pleased with how the concrete contractor has kept things moving. The primary crusher is going to stay 10 meters above ground level, and what you see there is roughly a 30% completion on the concrete work. Emma? Yeah. On top of that, the concrete contractor has also carried on with the tertiary crusher, which appears in this photograph, and with the stockpile tunnel foundations too, which was a real highlight for us. It was one of the largest pours completed in Namibia in a long time — more than 1,200 cubic meters of concrete placed in a single continuous pour. We're very proud that across all these activities, the contractor, the site management team, and my own team on site have kept meeting their schedule and stayed within budget. I think at this point I'm quite comfortable taking questions from anyone on the call. Really, our message is that we're continuing with our work, we're prepared, and we're currently in line with our financing as we move ahead to keep progress going on site.

Emma Culver executive
#6

Alright, thanks, Gavin. And thank you all. Please go ahead and drop your questions into that Q&A box and submit them so we can start the discussion. James, I can see your hand raised, but I just need you to type the question in for me so we can see it come through. Gavin, I think to kick things off, regarding how many personnel are at site right now, what's our headcount there? I believe we're now at close to nearly 400. How has that process unfolded, and have there been any notable problems at site as a result of that growth in personnel?

Gavin Chamberlain executive
#7

Emma. That's a good question. The figure has risen to slightly below 400. The last time I looked, I believe it was 373. Before our employees can enter the site and begin working, two steps are required. One step involves getting their medical checks done, while the other involves completing our induction. I have been extremely pleased with Wood as our on-site safety consultant. They have established a very solid process and have ensured that nobody has had to wait around for inductions. In fact, the process has run very smoothly. As far as I recall, the longest time anyone needed to get onto the site was slightly less than a week, which, judged by international standards, is genuinely quite low and a very significant positive for the on-site team. The fact that we have been able to grow so effectively during the quarter, from 100 right up to 400, represents a truly meaningful step forward and gives me substantial confidence in our site team's capacity to take this to the next stage, which is when structural steel will arrive on site.

Emma Culver executive
#8

With the spot price carrying momentum and work at the site moving forward, could you give us any additional clarity on the project's FID and how that is coming along?

Gavin Chamberlain executive
#9

Emma, providing a lot more clarity is quite tough, but the bottom line is that we remain on schedule for reaching FID, consistent with where our bank balance sits and how things are progressing. Our expectation is that within a window of 6 to 12 months, FID will be wrapped up. What I'd add is that once FID is settled, there will be no need for us to decelerate the project. We're able to stay on the timelines we have now and hit the objective we set ourselves, namely bringing uranium to market by 2029.

Emma Culver executive
#10

Thanks, Gavin. Turning to contracting strategy — how are you and the team viewing it? Do you plan to add more contracts on top of the ones already in place? These are utility contracts. Will they lean more toward base escalation, a hybrid structure, or market-linked pricing, given the activities?

Gavin Chamberlain executive
#11

Yes. Clearly, the uranium market is quite strong at present. Olga is in fact over in the US right now attending a conference, and we keep engaging with all the utilities. We'll go on responding to RFPs. What we're doing, though — as we mentioned after signing the first two contracts — is that any new agreements must be inked at a price we feel good about. We'll keep pricing our RFPs so the message comes through regarding what we want on pricing. We won't hurry into putting pen to paper on contracts. We're at ease with the coverage we currently have when it comes to pricing, but naturally what we're after is to gain from a uranium market that keeps climbing.

Emma Culver executive
#12

Regarding the budget, we're saying that we're on track with it — how much of the budget has been used so far, and what amount of spending is left? Well, we actually have a genuinely useful slide covering this, and I wish I could pull it up. I might be able to, but, Gavin, perhaps you can address that point even without the slide, in terms of what's been spent on the project and where things stand with it.

Gavin Chamberlain executive
#13

Right now, if you look at what we've spent plus what we've committed, we're sitting at roughly just under one-third of the total budget. There are still two big contracts left to award — the construction contract for the structural steel, and the construction contract for electrical and instrumentation. On the mechanical side, we've made considerable progress; although there's no payment commitment yet, we do have orders in place that lock in pricing on mechanical equipment covering a large share of the project as it stands. I'd say we're in a reasonably good position when it comes to understanding where the capex is heading, and for the time being we have a fair level of confidence that we'll stay in line with the overall budget.

Emma Culver executive
#14

When it comes to the contractors working on site, are we noticing any problems with how they're performing? And is there anything that worries you at night, I suppose, Gavin, regarding the way things are progressing on site with those contractors?

Gavin Chamberlain executive
#15

Yes. As you might be aware, every contractor we currently have working on site is Namibian. That fits into our approach of making contracts smaller so that local Namibian firms can realistically carry out the work. The progress they've made, along with their dedication to safety and to keeping to schedule, has genuinely astonished us. It's almost as though they're pushing beyond what's required, eager to demonstrate that Namibians are capable of delivering. Right now we couldn't be happier with how they're doing on site.

Emma Culver executive
#16

On the domestic utility supply agreements, what's the status? I'm aware that construction has begun at the permanent water station, but as for the arrangements with NamWater and NamPower, where do those stand?

Gavin Chamberlain executive
#17

Yes, NamPower has signed and sealed the agreement, and we have paid them their first deposit as well; they have actually begun designing the substation. On the power side, we are 100% comfortable that this has moved ahead. On the NamWater side, we are still waiting for the final signed contract, but we do have a binding MOU that allowed us to actually commence construction of the permanent water line. We would not have commenced with that unless we were comfortable with the MOU. All parties have signed it. Unfortunately, NamWater has been slightly diverted at the moment by looking at the finalization of the second desalination plant. At the moment, it appears that government will approve the second desalination plant round about mid-year this year. That is the latest news that we have received. Once again, I need to stress that we do not require the second desalination plant, but it has been a distraction to NamWater. Our contract is that they will supply us with water; whether it comes from the existing desalination plant or the new one actually does not affect us. There is sufficient water in the existing desalination plant.

Emma Culver executive
#18

All right, so I’ll reword a question we’ve received somewhat. Regarding the construction work currently under way at the site, does that still keep intact the upside production flexibility tied to the expansion scenario, should demand from AI materialize? Are we still in a strong position and ready to capitalize on that? Perhaps you could just walk us through, I suppose, where we stand on when those crucial decision points arrive concerning that expansion, and which option we would select.

Gavin Chamberlain executive
#19

Yeah. From that angle, it's a genuinely good question, since power and water are really the two main design considerations for the extension. For both power and water right now, we're putting in a system that's capable of actually handling the extension. With the water line, we'll raise the pressure and therefore raise the flow. In our MOU with the Department of Water, we've in fact already addressed the point that we will potentially boost the supply at some stage. From a water standpoint, we're comfortable, and from a power standpoint, the overhead power lines are sized for both projects. We have no problems when it comes to the infrastructure. Then, obviously, the infrastructure already on site has been laid out in such a way that we can actually construct the extension while the main plant is running. From that angle, if there were a push to speed up construction of the extension, we'd be able to do so with no real problems when it comes to running the Etango-8, as we call it, versus the Etango-16.

Emma Culver executive
#20

Thanks, Gavin. We have a question here about, I suppose, labor and the workforce in Namibia. The capability the team currently has is very well suited to building this project. I think you've worked with many of the project team before. Them well. We're quite comfortable with that. What's the strategy for sourcing and securing skills as we move into that operation phase, and how's the dynamic on the supply of labor, especially in Namibia? There could be a few of them.

Gavin Chamberlain executive
#21

Sure. Obviously, the Namibian government is putting substantial pressure on us to train and develop Namibian people too. A mining training center that Rössing established quite a few years back is still operating, and plenty of local workers are already completing those training courses — they're available and actively seeking jobs right now. Namibia has an employment shortage; I don't think we have a people shortage. Our operational readiness effort will concentrate heavily on upskilling and ensuring the right skill levels are in place for us. We recently brought in a new COO for Bannerman Mining Resources Namibia who comes from a mining background, and driving the operational readiness process will be one of his key duties. Donnie, his initial priority is solidifying the first stage of operational readiness — which is essentially how you lock in your people and the timing of when you hire them. We have a timetable for that tied to the construction schedule, and it will fall under the in-country COO's responsibility.

Emma Culver executive
#22

Gavin, with the South African rand climbing the way it has, does that shift your view at all on how quickly you're awarding contracts for on-site work? Is there any motivation to pull forward particular parts of the construction?

Gavin Chamberlain executive
#23

I'd say there's generally a certain amount of incentive at play. That said, the approach we've taken to contracting on this project is that we've awarded several mechanical contracts in order to lock in vendor data, while simultaneously fixing the price of that supply. To a significant degree, we've already dealt with the exposure tied to the SA rand's appreciation. No particular contracts would be placed sooner because of financial shifts in the exchange rate. As I mentioned, we still have two major contracts to award, but with those, getting the quantities correct matters more to us right now than fretting over the exchange rate. As everyone is aware, the rand's exchange rate does tend to bounce around somewhat, and we monitor it closely. Right now, we don't intend to alter any of our contracting strategies.

Emma Culver executive
#24

Thank you, Gavin. No further questions had come through — well, actually one has just arrived. Isn't that typical: these last-minute queries that show up right as you're about to wrap things up. Is there anything we can say about the proposed legislative amendment concerning the 10% free carry interest in new mines in Namibia? Does Etango count as a new mine? No, it does not. Gavin, I'll hand this one to you, though I believe this is genuinely an important point. We did cover it last quarter, but there has been a change at Namibia's mining ministry. For anyone who isn't up to speed on developments there, could you just bring us up to date on that?

Gavin Chamberlain executive
#25

Yes. So there's a new mining minister now. The minister who made that statement about 10% has been taken out of his role, and a new mining minister has come in. Our local chairlady sat down with the mining minister yesterday, and that meeting went very well. When we're over in Namibia on the investors visit, Werner and I are also going to go and meet him face to face. The talk about 51% ownership and so on has calmed down a lot. As a matter of fact, we aren't hearing it anymore. We're fairly confident that we definitely hold an old license, not a new one. Even where new licenses are concerned, it has faded considerably. Right now there's much more attention on oil and gas. That isn't to say we've eased off and that we're 100% at ease, but we do think it won't have an impact on us. We also don't want it hitting other mines down the road, since those other mines might one day belong to us.

Emma Culver executive
#26

One question on this: what's the thinking behind adding another partner to the project? How much interest has the project been drawing? As most of you know, and as we reported in the quarterly, we have a strategic funding workstream in motion. It's been in motion for a good while now. Gavin, do you want to say anything about how it's going? My sense is you're quite pleased with the team and with what's been achieved on that front.

Gavin Chamberlain executive
#27

Yes, absolutely. Over the past six months, interest has risen dramatically, and far more people are actually engaging with us. As I mentioned, we think that within 6 to 12 months we'll be ready to announce our FID, and as everyone knows, that FID is entirely tied to securing the final funding for the project. We feel quite good about how far we've come over the last couple of months.

Emma Culver executive
#28

Alright, thanks. That's where I'll wrap up the Q&A. Should anybody have further questions, just send me an email — I believe most of you already have my address. Feel free to write to me with anything else you'd like to ask. Gavin, many thanks for being with us. There's an updated video, roughly two and a half minutes long, I believe, that shows the progress on site since the December quarter. Anyone who'd like to stay and watch it, please remain on the line, and I'll share my screen and get that video started. Gavin, thanks once more for joining us. Thank you, everyone, for being on the call, and get in touch whenever you have any questions. Thanks so much.

Gavin Chamberlain executive
#29

Thank you, Emma. And I appreciate all of you for joining us.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Bannerman Energy Ltd transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Bannerman Energy Ltd earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.