Bannerman Energy Ltd (BMN) Earnings Call Transcript
July 27, 2026
Earnings Call Speaker Segments
Good afternoon, everyone, and welcome to our quarterly webinar covering the period that ended 30 June 2026. Thanks to all of you for being with us today. If you don't know who I am, my name is Emma Culver, and I serve as Investor Relations and Communications Manager at Bannerman. With us today is our Managing Director and Chief Executive Officer, Gavin Chamberlain, who will soon give an update on Bannerman and the Etango Project. After that, we'll move into some Q&A. Down at the bottom of your screen, there's a Q&A tab. Please open it up, type in your questions, and we'll go through them once the highlights are done. Right now, I'll pass things over to Gavin, who is with us from Namibia. Good morning, Gavin. How are things looking on site at Etango? I'll share my screen so we can go through these updates for the quarter.
Good morning, Em, and good morning to every investor and stakeholder joining the call. Em, these are genuinely exciting times. Each visit we make to site shows us further progress. I'm looking forward to walking everyone through the quarterly results and taking some questions and answers. In my view, the standout for the quarter was truly our strategic financing progress on the conditions precedent, where we've advanced considerably. We remain confident at this point that the final CPs and completion of the transaction ought to be expected in quarter three of 2026. That's genuinely positive for us; it lets us proceed along the schedule we've already set out, and we feel confident we will in fact get there. Beyond that as well, we posted a strong quarter on cash control, as always. We maintain firm discipline when it comes to managing our cash flow. We closed the quarter holding $53 million of cash assets plus liquid assets of a further $11.5 million. Bearing in mind too that we've already committed another $36 million to contracts currently ongoing on site, and our total project spend to date stands at $69 million. One thing I find really pleasing is seeing the actual rise in the long-term uranium price across the quarter, now at $97 per pound, which clearly supports where we intend to take this business.
Regarding the actual progress on Etango early works, we'll show a couple of photos in a moment too, but on the early works front, construction is still running in line with both the budget and the schedule. More than 560 people are on site right now, and we're very happy to report that we've reached 1.1 million LTI-free man-hours on this project alone. In the past we've spoken about safety results for the whole company, but on this project by itself we've already hit 1.1 million, and that's a strong sign of how much the site team and the site contractors value safety and safe construction practices. Okay. As I mentioned, 560 personnel on site, 1.1 million, and I really wanted to share this photograph since it gives you a sense of the camaraderie that has built up on site. That's the usual early morning safety briefing before work begins. I simply love this photo, which is why I wanted to share it, but also to once more underline the emphasis on staying LTI-free as we head into the rest of construction. Our bulk earthworks have gone very well this quarter. We're at 92% complete now, and that contract ought to wrap up in the next quarter.
The photo shows the earthworks for the heap leach pad, which are almost finished. The remaining work involves concrete on site. We made substantial progress this quarter. At this moment the primary crusher stands above ground level, and that is what the picture before you shows. You've likely been following this for roughly the past year, since we began with excavation photos, and now we're at last approaching the conclusion of the concrete work itself. My estimate is that by the close of this quarter, we'll be able to show you — next quarter we'll be able to show you the crusher building once it's complete. This image really conveys the scale of the dry plant area. In the foreground is the stockpile area, leading toward the silo visible in the background of the picture. It shows where the concentrated activity on the project is taking place, and at this stage that activity is mainly concrete work. Earthworks at this location wrapped up during the prior quarter. That last silo marks the end of the dry circuit, which is likewise now advancing considerably above ground level.
Excellent progress on that front — and as I’ve mentioned, it’s likely the most intricate pour anywhere on the site, and it’s coming along nicely. That covers the finished concrete work for the secondary and tertiary screening building. Beyond the site itself, we’ve made substantial headway on the permanent water supply line. Phase 1 of that contract stands at 87% complete. As a reminder, Phase 1 of the contract involves the connection to the NamWater reservoir, crossing the river and passing beneath the road, then halting on the far side of the road while awaiting pipe delivery. All the plinths have been installed up to the first pump station. That essentially wraps up the quarter’s summary. As I said, it was a genuinely strong quarter, both in terms of deals and the continued progress on the existing schedule. Emma, I think if there are any questions, I’m ready to take them at this point?
Yes. We'll get started, Gavin. Thank you very much for that update. Anyone who wants to take a closer look at the photos can find them on the website within the most recent presentation. Gavin, could you walk us through the CPs? What remains to be satisfied? How are they progressing? And what makes us confident that it will close in Q3?
Yes. Thanks, Emma. That's a good question. Regarding CP satisfaction, anyone who read our earlier announcement about the deal would recognize that there were a number of CPs. During the last quarter, we made significant progress. To begin with, the CNNC shareholders had to approve the transaction, and that was achieved and closed out. We also required approval from the Namibian Competition Commission, which has likewise been approved and closed out. Beyond that, there were some infrastructure contracts that we needed to finalize. People will have noticed that we signed the NamWater agreement during the quarter. In addition to that, we've also secured the acid storage facility lease, and our power contract had already been signed. On the infrastructure contract requirement, we've met all the CPs as well. The sole CP still outstanding, which has been submitted and is in progress, is the NDRC and Ministry of Commerce approval in China itself. It's effectively the two remaining approvals from the Chinese government and regulators insofar as the deal moving forward is concerned.
Thanks, Gavin. About the NaCC — the Namibian Competition Commission — and the CP, is there anything you can tell us? That was one we figured might take longer. Obviously, we're very glad to have it behind us. Could you just walk us through it?
Yes, Em. That really was a big achievement on our side. We pursued it together with CNNC as partners. The approval we received came with a couple of conditions that had to be met as we move forward. It was very fair, because many of those conditions are in fact less strict than the approvals for the actual mining license. The other good thing about it — and I think this is the takeaway people should get — is that CNNC and we have committed to reaching a 90% Namibian employee ratio within five years. There has been a lot of fear around the question: will this just be another mine run by the Chinese, and so on? For a number of years now I have been saying that this is a Namibian mine for Namibians. The fact that CNNC was party to this agreement and has signed off on the requirements for both employment and procurement going forward, I think, is a significant step toward showing people that we truly mean this to be a Namibian mine for Namibians. As for the targets we set, we are actually meeting all of those targets in terms of ratios at the moment. Some of them are challenging, but with a little bit of work, we are 100% confident we will achieve them.
By "a little bit challenging," I mean we have to establish systems, yet there are 5 years available for us to accomplish this. The real focus is on hitting the procurement targets, and those targets are reasonable, but a plan must be put in place so we can be sure of achieving them.
Yeah. Great. Still on the subject of CPs, Glenn has sent in a question. Does the NDRC have a deadline for responding, or is it just a matter of how long a piece of string is? And have we recently seen any approvals of foreign investment in uranium outside China?
That is a really strong question. As we see it, we have confidence, and here is why: there has been considerable engagement between CNNC's executive management and MOFCOM — that is, the Ministry of Commerce — regarding approval. They have already held a number of meetings with MOFCOM at a senior level. Following the submission of the original document, they have responded to questions and answers. To the best of our knowledge, MOFCOM has no outstanding questions. In effect, MOFCOM is processing the matter and adhering to its standard regulatory procedure on the way to completing the approval. The good news is that every question and answer has now been addressed, and submissions have been provided to MOFCOM.
Thanks, Gavin. We have a few questions coming in about capex and the budget. Let's begin with capex for FY '27. Should the market expect spending to be comparable over the coming couple of quarters to what we've seen? How does that ramp-up look in terms of expenditure?
Yes, definitely — for the upcoming quarter, it should look very much like what we delivered this quarter. The reason is that the earthworks contractor is wrapping up, so his spending will come down. We've also placed the five long-lead items for the mechanical equipment in the dry plant, and that will obviously offset the drop in earthworks spending. At least for the next quarter, expenditure is going to be quite similar. Once the deal completes, we'll shift into markedly accelerated spending as we place the structural steel contracts, which are currently being adjudicated and will be ready to place on completion. That will drive a significant rise in expenditure. We are fully aligned with our September 2028 commissioning date, based on the deal's late start at the end of September. Any completion ahead of that will likely have a positive effect on the schedule going forward.
Thanks a lot for that. Regarding reimbursement, CNNC has committed up to US$27 million from 1 July through to completion — how is that tracking right now? Yeah.
Spending so far has stayed in line with what we laid out at the start. That $27 million ties straight to the $60 million ceiling on capital expenditure, and we set that capital spending plan around reaching the end of September. As deal completion draws nearer, we might decide to pull forward part of that spending, purely to make sure we hit the $60 million cap and collect the entire $27 million reimbursement. We are not going to exceed the $60 million, and we are definitely not handing money to anyone for nothing.
Thanks. One more thing on capex: how should we view the cost pressures affecting that $353 million estimate? What percentage effects are you seeing right now, and when should the market expect an update? Clearly, up to now we've said that at the close, if anything falls outside that plus or minus 10%, but could you bring everyone up to date on that, Gavin? Yeah.
Right now we're doing well versus the budget. One of the highlights of the quarter, I'd say, was that the five orders we placed for mechanical equipment in the dry plant area landed on budget — actually slightly below what we'd originally budgeted. Because we'd agreed escalation formulas in advance when placing those contracts, our approach meant that despite the Middle East crisis and the war happening there, the pricing on those equipment pieces was never impacted. At this point we're tracking well. Regarding the 353 plus or minus 10%, I should emphasize that the plus or minus 10% covers unknown unknowns, like the war. For the known unknowns, a contingency sits inside the 353, and we're tracking well against it. The 353 plus or minus 10%, I believe, is secure, and we're confident we can hit that number.
Thanks. Let me clarify — this is a question from Andrew Heintz about what's on the critical path to construction, or for construction. Those 5 contracts in the dry plant area are being placed because that will protect that critical path, or is there something else we should keep in mind so that the 2028 critical path stays on track?
Yes, that's a solid question from Andrew, since we deliberately awarded those contracts, and the actual purpose is to help guarantee that, from a scheduling standpoint, we have some slack built in. They aren't on the critical path, but we chose to award them at this point so we can create a bit of buffer for unknowns at the back end. As things stand, we've awarded them. Delivery will occur comfortably inside the critical path, and on top of that they'll give us extra float across the construction as a whole.
Thanks. Moving on from capex, here’s a question: is the $53 million cash balance inclusive or exclusive of commitments? That one’s pretty straightforward for us to answer: it does not include future commitments, and those commitments will be paid out over the coming quarters. Right, Gavin?
Right, yes. An extra $36 million has been committed by us to project construction, though those contracts extend well into next year. It isn't the case that this $36 million will be used up within the coming couple of months. For context, the concrete contractor remains on site at least through March next year, the crushing contractor until close to mid-year next year, and the pipeline contractor is likewise not scheduled for completion until the end of the year. Existing contracts are covered by that $36 million, along with those five dry plant mechanical equipment orders too, and those will also be delivered only during next year. That $36 million is distributed across a number of months. Yeah.
Great, I appreciate the clarity. Moving a little deeper into the project now — do we have any visibility at this point on whether Bannerman will pursue the XP route or the XT route? Could you walk us through your thinking after Etango-8?
Yeah. I'd say our strategy hasn't really shifted much, other than it now leans more toward the expansion scenario rather than the extension one. The reasoning behind that strategy is that Etango-16 would be in production five years after we start production at Etango-8. From a financial standpoint and a practical construction standpoint, that's what makes the most sense to us. Obviously, we'd be constructing Etango-16 while Etango-8 is still operating, and then, five years after production begins, both plants would be running at the same time.
Got it. Do you have any backup plans in place for water supply in case NamWater runs into problems?
Yes. Regarding NamWater, the agreement we finalized is quite favorable for us, since it provides for supply from both the current desalination plant and the new desalination plant that has been announced. The new desalination plant is scheduled to come online before the mine is finished, so in effect we will have a dual supply. The contract we signed permits supply from both sources. I want to emphasize that the current desalination plant has enough water for our project.
That's exactly why we began work on the permanent water supply — Gavin, is it the final piping at the feeder station that remains to be done? Right.
At the feeder station, connections to the reservoirs were already in place, and by getting this contract signed and paying the deposit, we've now accomplished two things. We secured our capacity in the supply line — that is, the volume of water flowing from the desalination plant to Swakopmund — we've locked in our share of that capacity. Beyond that, we've also secured the final existing fitting in the reservoir at Swakopmund. Yeah.
Great. We have another question from Glenn: he realizes we don't have to sign offtake contracts imminently, but he's curious whether you could offer any perspective regarding the contracting landscape and which terms might be attainable if you actually are in talks. I think it's likely the wider question of where the market stands right now, Gavin. The spot market appears quiet, and equities clearly follow that. As you mentioned, the long-term price rose this quarter, $4. What are we currently seeing in the market for contracts? Yes.
A lot of what I'm sharing comes from what others have told me. During our contract negotiations, we've kept a very low profile. With the 60% offtake secured with CNNC, we think we now have the benefit of some breathing room. Realistically, we wouldn't begin pursuing contracts actively and aggressively until roughly six months prior to entering production, and that, I believe, should let us secure notably better pricing than what's available to us today. From what I've picked up in the market — and you always want to keep your ear to the ground — it sounds like market-related deals currently offer floors in the mid-$70s and ceilings ranging from $130 to $155. As for the utilities themselves, we're seeing a preference for fixed price escalated, and I believe people are now able to negotiate those at just north of $100.
Great. Let's take a look. WNA season is coming up, and people always call that the contracting season. We'll see how it goes. That's every question we have from this side, Gavin. Any final thoughts from you? Have you been out at the site during the past week since you were there? Yeah.
Right now I actually have the entire Australian board here with me, and we have a major site visit lined up for tomorrow, which should be quite exciting for the local team too. We did do a site visit last week, just to confirm we won't run into any surprises while we're on site. I have to say, my only surprise is how well they're actually managing to construct. These Namibian contractors are world-class, and they're doing a fantastic job. Once again, I always want to close by thanking the whole Namibian team and the entire Perth team, who are letting us actually move this project forward according to the plan, along the lines of what we've always strategized. A big thank you to everyone involved.
Thanks, Gavin. I appreciate all of you being here. Should any questions come up, feel free to get in touch with me whenever — I'm always reachable and always glad to talk with our investors. So please do reach out, and we look forward to connecting with you again next quarter. Thanks, Gavin.
Thanks, Emma, and I appreciate all of you for being on this call. Thank you.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Bannerman Energy Ltd transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Bannerman Energy Ltd earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.