Neal Nagarajan executive
#1

Hello, everyone, and good morning. We appreciate each of you who has dialed in, along with those of you streaming through the webcast. On today's call, we'll be discussing our financial performance for the fourth quarter and the entire 2025 fiscal year, which closed on December 31. Joining us are Amir Vexler, who serves as President and Chief Executive Officer, plus Todd Tonelli, our Chief Financial Officer, Senior Vice President, and Treasurer. This call comes on the heels of the earnings news release we put out yesterday. Earlier today, we submitted our Form 10-K report covering both the fourth quarter and the full year. You can find all our news releases and SEC filings — our 10-K, 10-Qs, and 8-Ks among them — posted on our website. A recording of this call will be made available on the Centrus website later this morning as well. I want to remind all of you that some of what we share on this call today could be classified as forward-looking information, which carries risk and uncertainty, including assumptions regarding Centrus's future performance. It's possible our actual results could differ materially from what those forward-looking statements suggest. You can find additional details about factors that might cause actual results to diverge materially from our forward-looking statements in the documents we file with the SEC, including our annual report on Form 10-K and our quarterly reports on Form 10-Q. Lastly, the forward-looking information we're providing today is time-sensitive and holds true only as of today, February 11, 2026, unless stated otherwise. This call belongs to Centrus Energy. Transcribing, redistributing, retransmitting, or rebroadcasting this call in any form is strictly forbidden without Centrus's express written consent. We thank you for joining us, and now I'll hand things over to Amir.

Amir Vexler executive
#2

Thanks, Neal, and I appreciate everyone joining the call today. For Centrus, 2025 represented a milestone year, one highlighted by our December announcement that we would start manufacturing centrifuges commercially in order to serve the commercial LEU market along with our sizable backlog. Not long after that, in January, the Department of Energy chose Centrus to receive a $900 million HALEU Enrichment Award. With our buildout, America's return to domestic commercial uranium enrichment formally begins, backed by a de-risked, deployment-ready technology capable of serving commercial needs as well as national security ones. We expect our first new cascade of centrifuges to be online in 2029, with additional cascades arriving after that; we keep finding and putting into place ways to cut both our lead time and the unit cost. That work is underway from day one. Let me first go to our results, though. Because of how our business works, quarterly results can vary quite a bit, so in our view the annual results better reflect our progress; across the full year 2025, revenue came to $448.7 million, gross profit was $117.5 million, and net income reached $77.8 million. Most of the revenue we currently generate comes from our LEU business, and in the third quarter, Centrus obtained waivers from the Department of Energy allowing continued LEU imports for all deliveries already committed to U.S. customers in 2026 and 2027. That announcement brought more clarity and helps de-risk that part of our business. Let me now shift to our future commercial enrichment business and the roadmap going forward. Our base case buildout is designed to serve our sizable commercial LEU enrichment backlog of $2.3 billion as well as the requirements placed on us by the Department of Energy under the HALEU Enrichment Award. Taking everything into account, 12 metric tons of HALEU will be part of our base case. Any capacity added beyond that will come progressively and hinges on our offtake demand as well as our capital resources. I'm also glad to report that, as we keep working to secure additional low-cost capital, reaching our nth-of-a-kind costs should be achievable through our base case buildout. We began commercial centrifuge manufacturing in the first place to serve growing demand for commercial LEU, a space where we hold a time-to-market advantage. Demand for LEU driven by existing electrification needs and their growth will keep rising regardless of any demand from AI, data center advanced manufacturing, or hyperscalers, even as LEU supply grows constrained at a rapid pace. In the near term, domestic LEU demand by itself is projected to grow by roughly 6.5 million SWUs, driven by Russia's departure from the market plus added demand from restarts, upgrades, and newly pledged reactors. The LEU pricing curve, which saw a 24% compound annual growth rate between 2019 and 2025, signals this increasingly tight market and accumulated latent demand. Another market that could matter a great deal is national security. Today we are the sole production-ready choice for the national security establishment, and during the fourth quarter, the National Nuclear Security Administration informed us of its intent to sole-source certain uranium enrichment activities from Centrus. That might give us yet another way to access cheap capital. On the topic of financing, the HALEU Enrichment Award worth $900 million could end up above $1 billion, and it still has to be locked in via negotiations. This possible funding, obtained through a procurement process and carrying no debt or equity component, would accomplish two key things. First, it would give us an additional source of inexpensive capital, and we appreciate our government acknowledging how vital Centrus is to this market; and second, it backs the 12 metric tons of HALEU capacity before an advanced reactor market becomes commercially viable. We are ready to seize these opportunities since we spent the prior 12-plus months preparing the ground. To be more specific, those operational steps consist of: first, our November 2024 supply chain readiness program. Second, finishing phase two of the HALEU Operations Contract successfully by delivering 900 kilograms of HALEU UF6 to the Department of Energy under contract and generating well over 1 metric ton of HALEU UF6 for the department as of end of 2025. Third, adding roughly $300 million to our $2.3 billion contingent LEU backlog and making solid headway toward clearing those contingencies. Fourth, announcing the creation of more than 300 new positions at our Piketon facility and then bringing on more than 50 of those new hires in Q4. In 2025, we brought aboard over 140 employees combined in Piketon and Oak Ridge. Fifth, starting design work on our training, operations, and maintenance facility in Piketon, which will involve substantial renovation and rehabilitation of an existing facility, and sixth, persisting in pinpointing and putting into place ways to cut our lead time and unit costs as a day-one activity. Similarly, from a financial angle, those steps consist of: first, uplisting to the New York Stock Exchange to draw a more diversified set of institutional investors; second, validating foreign direct investment as another possible source of inexpensive capital by signing an MOU with KHNP and POSCO International; and third, raising capital to support the buildout, finishing the year with a cash balance of roughly $2 billion. Todd will go into this in more detail soon. Going forward, we will keep seizing our time-to-market edge in the domestic LEU market and our first-mover edge in the global HALEU market. Operational excellence is non-negotiable. Our first cascade timeline involves a substantial amount of time, effort, and investment at both our facilities to build on our operational momentum. As part of this effort, it is with great pleasure that I can announce that we just recently entered into an agreement with a best-in-class partner, Fluor, who will serve as our primary EPC in Piketon. To give stakeholders more clarity, we are ready to provide the following full year 2026 guidance. From a financial standpoint for the year, we are providing the following guidance: total company revenue of $425 million-$475 million, and total capital spend of $350 million-$500 million. On the operations side, here's the guidance we're giving. First, we're wrapping up agreements with the partners who matter most to us — particularly the ones needing long-lead procurements, significant scale items, and complex parts. These suppliers will provide either parts or equipment at either facility. Second, we're adding workers at both facilities, totaling no fewer than 150 net new employees. In Oak Ridge, at least 100 new employees, which is roughly 25% of the announced 400, and in Piketon, at least 50 new employees. Roles at both locations will span engineers, assembly technicians, maintenance technicians, enrichment operators, lab technicians, project management, and project controls. And finally — a big achievement from a design perspective — we will release our first certified-for-construction work package in Piketon; that's where a key plant system's design has finished necessary reviews and is formally signed and stamped for use by construction crews. Beyond that, we expect the majority of our construction partners' mobilization in Ohio to be done by the end of the year. As progress continues, we expect to share more details, including a timeline to the completion of our first centrifuge produced by our commercial-scale manufacturing process. That will be another groundbreaking milestone, since it represents the supply chain coming together and its ability to produce a centrifuge; with that, I'll hand the call to Todd and then return with some final thoughts. Todd?

Todd Tonelli executive
#3

Thank you, Amir, and good morning, everyone joining today's call. I'd like to begin by taking you through the results, and after that I'll give you more specifics on a few items Amir covered, along with our financial guidance. On both the operational side and the financial side, 2025 represented yet another year of strong execution as we strengthen the business and get it ready for this industrial buildout. For 2025, total revenue came in at $448.7 million, which is up $6.7 million, or 1.5%, compared with the full year 2024. Within the LEU segment, revenue reached $346.2 million in 2025, essentially level with the $349.9 million recorded for 2024. Notably, uranium revenue fell 54% versus the prior year, landing at $55.6 million, partly reflecting a sizable one-time uranium sale during the fourth quarter of 2024, while SWU revenue rose 21% compared with a year earlier, an increase of $51.9 million, powered by a 23% jump in the volume of SWU sold. Our technical solution segment posted $102.5 million in 2025, which is $10.4 million, or 11%, above 2024 levels, with the gain coming from a $10.5 million rise in revenue from the HALEU Operations Contract. For 2025, total gross profit was $117.5 million, up $6 million, or approximately 5%, versus 2024 gross profit. Full year 2025 cost of sales in the LEU segment dropped $21.3 million, or 8%, to $234.7 million. LEU segment gross profit for 2025 climbed $17.6 million, or about 19%, reaching $111.5 million, mostly because more SWU was sold and because contract and pricing mix lifted the margin on SWU sales, with part of that offset by lower uranium gross profit. At the technical solutions segment, 2025 cost of sales grew $22 million, or 30%, to $96.5 million, mainly reflecting a $22.8 million rise in costs incurred under the HALEU Operations Contract, partly offset by lower costs tied to other contracts. That segment's gross profit for 2025 fell $11.6 million, or 66%, to $6 million for the reasons just described. Costs incurred in phase two after November 2024 have carried no fee, since that portion of the contract is still undefinitized and awaits final resolution. It's also worth noting that a scheduled, permitted fourth quarter shipment from Russia did not depart as planned because of a shipping issue. Pushed into the first quarter of 2026, that shipment would have lowered the average cost per SWU and had a positive effect on gross margin and net income. Also during the year, we incurred nonrecurring G&A costs of $3.6 million tied to voluntary tax withholdings and $1.1 million tied to CFO transition costs. To paint a clearer picture of our earnings and to account for possible variances in future shipments along with our quarterly earnings fluctuations, starting next quarter we will present financials on both a quarterly basis and a trailing 12-month basis. Moving to backlog, as of December 31, 2025, the total company backlog was $3.8 billion and reaches out to 2040. Backlog in the LEU segment was roughly $2.9 billion. The following covers future deliveries of SWU and uranium, mostly tied to medium- and long-term agreements, along with fixed commitments, plus $2.3 billion in contingent LEU sale contracts and commitments — $2.1 billion of that total sitting under definitive agreements, and $200 million of it still contingent on signing definitive agreements. As of December 31, 2025, our technical solutions segment backlog stands at roughly $900 million, encompassing funded amounts, unfunded amounts, and unexercised options. Those options pertain to the company's HALEU Operations Contract. Moving to capitalization: during 2025, we brought in gross proceeds of $533.6 million via two ATM programs. Through our November 2025 ATM program, announced recently, we generated gross proceeds of $390.4 million at an average price of $269.21 per share. Together with cash produced by our business and our oversubscribed August Convertible Senior Note issuance, we closed the year holding an unrestricted cash balance of $2 billion. And, as Amir mentioned, we were just selected for the $900 million HALEU Enrichment Award, an amount that could grow to slightly more than $1 billion, including $170 million in additional options. We remain in negotiations over our final contract with the DOE, one structured around milestone payments; given our funding and the demand visibility we have from customers, our present plan is to bring HALEU production online ahead of the decade's end and then produce 12 metric tons of HALEU annually. This war chest gives Centrus the capacity to start funding operations and stand up the supply chain while making required investments in facilities, machinery, partners, and workforce throughout the buildout. Looking ahead, we will keep prudently shaping the balance sheet to back this sizable, first-of-a-Kind industrial buildout of one-of-a-kind centrifuge technology capable of satisfying both commercial and national security needs; we believe our funding is sufficient for near-term capital requirements, and our existing LEU backlog along with potential HALEU Enrichment Awards ought to let us hit our milestone of achieving nth-of-a-kind costs. At the same time, we are exploring other low cost to capital avenues to further strengthen the capital stack, among them national security-related funding, future prepayment or offtake arrangements, and possible foreign direct investments. Keeping a healthy cash balance affords added flexibility when negotiating with any such potential partners, while also bringing us nearer to clearing the contingency surrounding our LEU enrichment backlog. On guidance: as Amir covered, we are offering both financial and operational guidance. Let me go deeper into the financial points he raised. For 2026, our financial guidance is as follows: total company revenue between $425-$475 million, whose midpoint of $450 million equates to flat year-over-year growth, and total capital deployment between $350-$500 million. Capital deployment for 2026 will also encompass prepaid expenses that do not show up as CapEx yet affect free cash flow, as we invest in our partners while they scale up ahead of our production. With that, I will hand it back to Amir.

Amir Vexler executive
#4

Appreciate that, Todd. The approach we're taking—expanding capacity for both LEU and HALEU—sends an unmistakable message to prospective buyers that Centrus has hit a significant turning point and stands ready to serve tomorrow's enrichment requirements. Without Centrus in the picture, the marketplace would be stuck depending on a two-player oligopoly of government-supported rivals who all share one common vulnerability when it comes to centrifuge production risk. When customers place orders with Centrus, they reduce risk for their own operations, and we gain the certainty we need to ramp up. On the LEU front, the technology had already been demonstrated, and our position within the LEU enrichment supply chain is now equally established. The anticipated shortfall between what's available and what's needed, for utilities both here and abroad, keeps getting larger. Domestically, we keep hearing signals from the administration, by way of regulators, and from utilities that need will keep climbing as they pursue American energy dominance and energy security. Turning to HALEU, we're now moving forward to scale up production and take full advantage of being first to market. We had already been in discussions with hyperscalers regarding possible prepayment arrangements or offtake-style deals down the road—yet another avenue for securing inexpensive capital financing. What we're showing here is that we anticipate having at least a portion of that capacity online prior to the close of this decade, and before the advanced reactor sector reaches maturity. As for our government partners, we thank you once more for the award and eagerly anticipate backing the national security establishment to the greatest extent we can. We're beginning a crucial industrial expansion effort in support of the worldwide nuclear industry's expansion and America's energy independence. We can't wait to share further updates as we take this thrilling next step. Having said that, I'll hand things over to the operator so we can take questions. Operator?

Ryan Pfingst analyst
#5

Yeah. Morning, everyone. I appreciate you fielding my question. Perhaps we can dig a bit deeper into the schedule; it seems you're aiming to beat that 42-month projection you mentioned previously. Could you share what kinds of efforts might accelerate that — additional capital, other government initiatives, or anything else we ought to know about?

Amir Vexler executive
#6

Morning, Ryan. I'm grateful for the question. Thanks for joining us today. You're highlighting something that matters more and more to us, clearly, now that we've started actually producing centrifuges and meeting certain obligations. Carrying out these plans has turned into, and continues to be, a top concern for us. So, as I mentioned earlier during my comments, getting better constantly and being able to lower per-unit expense while moving quicker is essential as our capacity grows; this has to happen simultaneously, and I can tell you we've got a significant number of people focused on it, and we're putting resources behind it. It's clear to me we already possess a solid roster of chances we're acting upon; we have a strong set of collaborators we've made public, such as Fluor, a partnership we take great pride in. They're the finest at what they do. There are others we're engaged with that haven't been disclosed yet, and down the road we'll share news about those. Bottom line, being able to operate more efficiently, cutting per-unit expenses, and moving faster remains a priority for us, just like I said on day one, and we're carrying it out simultaneously. Keep watching for further developments as we move ahead with this process.

Ryan Pfingst analyst
#7

Great. Thanks, Amir.

Rob Brown analyst
#8

Morning. Congrats on everything you've accomplished. Regarding the LEU commercialization effort, does that capacity build-out follow roughly the same schedule as the HALEU ramp? And at what point does the backlog shift from contingent to something more final?

Amir Vexler executive
#9

Morning, and thanks for joining the call and for asking. Let me restate your question to be sure I've got it right. First, you're asking about the contingency tied to our sales — when does that become a firm commitment? Is that correct?

Rob Brown analyst
#10

Yeah, that's right. Thanks.

Amir Vexler executive
#11

Yeah, so at this stage, we're not going to dive into a lot of specifics about the contract. It goes without saying that, like I said earlier, we've got the intention and the plan, and we're moving forward toward delivering on what we've promised; that LEU commitments backlog we announced matters enormously to us; and once more, I won't speak to the particulars of the contractual arrangements, but that's precisely what we're working to carry out, and we fully intend to honor what we've committed to.

Rob Brown analyst
#12

All right. Appreciate it, Amir. I'll hand things over now.

Amir Vexler executive
#13

Thanks so much.

Eric Stine analyst
#14

Good morning, everyone.

Amir Vexler executive
#15

Hey, good morning.

Eric Stine analyst
#16

Morning. Hey, so perhaps regarding CapEx only. We're grateful for the 2026 CapEx guidance. Could you discuss, if that's doable, perhaps how evenly that CapEx is anticipated to be spread across the year? And then too, when we consider the figure you provided, is that roughly a typical figure on a yearly basis as you progress toward that initial 2029 operational date? Or, I mean, is this figure one that's more typical? It's the opening year, and you probably either it rises from there or is reduced later on.

Todd Tonelli executive
#17

Yeah. Thanks for joining the call. What I'd say is, looking beyond 2026, clearly, our CapEx outlay and the manufacturing process becomes more linear. At present, at this moment, the figure we've given as guidance is capital spend. So that does encompass some long lead procurement, possible prepayments on supplier agreements, and also engineering work at our Piketon facility; so the opening year isn't indicative of the linear spend that I expect to see during the 2027 through 2029 period because of those factors. What I will say is, as we progress through the year, any time we notice an adjustment, we'll mirror that in the guidance, and we'll try to keep you. That's why we want to let the investors know as best we can where we're going to be over the next 12 months, but also on what demand turns out to be from a plant standpoint at both manufacturing and Piketon; we'll work toward refining that guidance, but the initial year does encompass some prepayments and long lead procurement.

Eric Stine analyst
#18

All right. Thanks a lot.

Jed Dorsheimer analyst
#19

Hey, everyone. Appreciate you fielding my question. Nice work on the progress. For my single question, regarding hitting the nth-of-a-kind, I'm curious whether I'm interpreting this the right way. My assumption had always been that reaching it perhaps required the 3.5 million SWU, and it appears that isn't true, that this goal can be met using lower capacity. So I'd like to know if you could offer a bit more context regarding the capacity needed relative to reaching the nth-of-a-kind target. Thanks.

Amir Vexler executive
#20

Yes. Morning, Jed. Thanks for joining. Good question. The nth-of-a-kind will be reached well ahead of the 3 million SWUs, as you said. I'd say that, from my perspective, this is a significant thing to share with the analysts here, with shareholders and investors. As you're aware, among the biggest hurdles for any newcomer to the market is the nth-of-a-kind cost. And the reality that we are starting out, we're constructing toward a particular volume and capacity, and the reality that we can complete the first-of-a-kind within this brief span of time, I consider extraordinarily important. As always, I'm very cautious. We aren't revealing complete costs, so I'll leave it at that. But I think your question has been answered. And as I said, the reality that we're getting past the nth-of-a-kind cost is a major announcement, a major accomplishment for us.

Jed Dorsheimer analyst
#21

You already covered that. Appreciate it. Excellent. Many thanks.

Amir Vexler executive
#22

Thanks as well, Jed.

Joseph Reagor analyst
#23

Hello, Amir and everyone. I appreciate you fielding the questions. I think the majority of what I wanted to ask has already been covered, though I did want to briefly address, when we think ahead about the next couple of years, whether the government has begun to shift its position regarding that January 1, 2028, deadline on imports from Russia. Has any openness emerged to talk about it, considering that within the U.S., you should be the first to reach the market, and that there really won't be domestic supply in 2028 and 2029?

Amir Vexler executive
#24

Yes. Well, that's another solid question. Thanks for joining us on the call too. From my vantage point dealing with customers and prospective customers — whether they're on the LEU side or the HALEU side, meaning the current commercial fleet or the advanced reactors under construction — I can share what I see. It appears a substantial amount of demand is building up in and around those years near the end of the decade. We're witnessing considerable demand in that space. Regarding the government side, honestly I have nothing I can share, since there's really nothing to share. Nothing exists in the public domain that voices any worries; however, as you're aware, the genuine worries and the genuine momentum will originate from the customers, the industry, the utilities themselves, should the issue ever arise. A few of the leading indicators, which I referenced earlier, we're already encountering through intensive conversations and dialogue centered on HALEU. As you know, we're delivering HALEU supply before advanced reactors become commercially viable. That, then, generates substantial demand too. Just to remind everyone, HALEU isn't merely enrichment of HALEU. It calls for considerable enrichment of LEU and LEU capacity too. So there's a force multiplier in play that will only sort of become apparent over the coming few years. But returning to your initial question, there's nothing to share from the government side. And should the government ever take notice of it, it absolutely will need to begin with the utilities and the customers themselves calling it out as a problem.

Joseph Reagor analyst
#25

Okay. Thanks. I'll turn it over.

Amir Vexler executive
#26

Thank you.

David Choe analyst
#27

Hi, all. Morning. I appreciate you taking my question. So, just quickly, the 2026 guidance shows revenue staying level compared with the prior year. Could you perhaps walk us through a few of the contractual mechanics behind your long-term supply deals, and then tell us whether, and at what point, we ought to anticipate some sort of increase that tracks the shifts we've observed in long-term SWU pricing that follow certain indices? Thanks.

Todd Tonelli executive
#28

Yes. Our guidance is therefore unchanged. We selected the midpoint. And clearly, many elements, clearly, surround that guidance. Like we said during the call, one shipment clearly affected our results at year-end, from gross profit right through to net income and earnings per share. Such difficulties are among those we encounter simply because shipping gets delayed. I'd note this had nothing to do with any permits or any waivers that were required for any Russian material. Yet we do see potential upside beyond our guidance. The market keeps strengthening; we've observed some record-high spot prices in SWU. We're hoping those dynamics persist. However, much of our supply is under contract, from two foreign sources in both cases. We're at ease regarding our supply side. What we aim for is maximizing margin on the revenue side and sales to our customer.

Jeff Grampp analyst
#29

Morning. I'd like to ask about the schedule you folks released for that first enrichment capacity. What I'm wondering is whether there are additional key milestones or obstacles that would do more to concretely reduce the risk attached to that schedule, which you could share as things move along? And which ones would those be? I'm basically asking how you're able to publicly report movement toward lowering the risk on that schedule.

Amir Vexler executive
#30

Thanks. Yes. Appreciate you joining the call. That's yet another excellent question about execution. When you consider how long it takes to reach production, much of that comes down to cycle times on our side, cycle times among suppliers, the timelines our suppliers are willing to lock in, and the way we structure our supply chain. Every one of those items is in progress, like I mentioned, at this very moment and alongside the actual initial construction of our centrifuges. Like I noted before, we're evaluating various partners and various approaches that could make us more efficient and quicker. My expectation is that once those efforts bear fruit and there's news worth sharing, we will absolutely be extremely open about how we communicate it. We'll find efficiencies throughout this process, and I'm confident additional announcements are coming. I think that covers the question. One thing worth highlighting is that demand appears to be cresting right around the point when our capacity comes online. Regarding the question from the analyst earlier about supply and demand being out of sync, our projection is that this will indeed occur. Our expectation is that there will be constraints on supply and on the capability to satisfy demand; therefore we're doing all we can to speed that delivery to the market. And once more, the illustration I gave there: should we begin to observe genuine contractual interest in HALEU — and we're already talking with multiple OEMs, and that's starting to materialize, particularly following our announcement of the $900 million award from the DOE — we're experiencing tremendous involvement from many of those OEMs. As soon as those turn into concrete orders, which I expect will happen quite soon, that generates enormous demand for LEU too. So my sense is that everything will come into much sharper focus as we pass through the significant milestones both this year and over the coming few years.

Todd Tonelli executive
#31

Let me just say as well that how vital our supply chain is cannot be overstated. We are putting a great deal of effort into ensuring that chain satisfies the requirements of national security; therefore those actions needed to fulfill what that chain demands must be handled with care; we need to act prudently and confirm that every base is covered. As soon as we satisfy those national security supply chain demands, that lets us go at a somewhat faster pace. So we will keep giving updates over the course of the year and in upcoming quarters regarding how those milestones may be monitored, and we will hold ourselves accountable.

Jeff Grampp analyst
#32

Excellent, excellent. I value those insights. Thanks, everyone.

Analyst analyst
#33

Hello, Ted speaking, covering for Vik. I appreciate you letting me ask. Might you go over your HALEU output goal? Measured in metric tons, it appears to be about sufficient to serve as an initial fuel load for a single advanced reactor. So might you verify if that figure reflects anticipated market need along with the requirements you're observing from the DOE task orders?

Amir Vexler executive
#34

Yes. Yeah. Good morning. I appreciate that inquiry. From my perspective, your question centers on capacity and what it genuinely signifies for the industry when it comes to meeting some of those early requirements, whatever they turn out to be. It's important to keep in mind that the DOE program was designed to spark the market. What we had was a market lacking demand that anyone could firmly commit to; the Department of Energy wisely decided, in effect, "Here's our approach: we'll put money in, build up the capacity, and then let the OEMs sign contracts for it." And just as intended, that's now beginning to happen. Right now, we've got OEMs forming a queue and engaging in talks about the capacity that will soon be open. To put a finer point on it, what does that figure actually signify? That hinges on the design, on the particular OEM, and on how big their reactor is. It also hinges on the way they choose to set up their supply chain and which enrichment they'd need. Let me highlight two points for you. First, as we've stated, our clear goal is to possess capacity for both LEU and HALEU, and we're making headway on both. Second, we aim to meet the requirements of the commercial sector and national security, and we're making headway on those two as well. There isn't a precise figure I can give you for that. What I can say is that we'll keep growing our facilities whenever that becomes necessary, and we're working as hard as possible to secure the greatest amount of offtake and demand we can. Should the situation call for it, we'd scale up our plans to match. For us, this serves as a solid launch and baseline when it comes to what we're assuming about capacity.

Analyst analyst
#35

Understood, that's quite useful. One more question from me. Regarding the guidance, can you remind us of the way pricing gets determined within the contracts? Is it possible to share how much of the planned deliveries for 2026 already have their supply cost locked in?

Todd Tonelli executive
#36

Sure. Within our guidance, we don't discuss the contractual makeup of our contracts. What we've stated is that we do have secure supply from two foreign sources, and that gives us comfort around our guidance and confidence that we have everything in place, both waivers and, as I mentioned, normal shipping channels to move forward.

Stephen Gengaro analyst
#37

Thanks. Good morning, everybody.

Amir Vexler executive
#38

Morning, Steve.

Stephen Gengaro analyst
#39

I'd love to hear whatever you're able to share about this. As we consider the capital expenditures you're making to expand capacity across the coming 10 years, how do you view where SWU prices are headed, in a way that underpins the economics of that? And obviously you won't hand me the precise figure, but how should we think about SWU for HALEU versus LEU? And in your own view, how does that interplay unfold?

Amir Vexler executive
#40

Yes. All right. I appreciate the question, Stephen. I appreciate you joining us today. I believe this is a significant subject to address, since we frequently discuss expenses, which represent a crucial component of the project and the factors we are weighing. In the same way, the SWU prices available in the market and our capacity to secure contracts at elevated SWU prices or more advantageous SWU prices is a key factor for us. So the matter of how one perceives the trajectory of SWU prices in the marketplace, I believe, is something we examine, argue about, and track quite carefully on an internal basis. In my opinion, SWU prices will move lower solely if either of two circumstances occurs. Well, if either of two circumstances occurs. Either demand declines — put differently, we would begin taking reactors offline — or essentially, the supply side will exceed the demand. I certainly pray the first scenario does not occur. Nothing suggests it will. And regarding the second, the bulk of the disclosed capacity additions, whether from us or from our rivals, rests on contracted SWUs. So essentially no one is out there constructing what I would describe as just-in-case or ready-to-serve SWUs that they would be keen to unload and sell into the market. All of which is to say that, in my opinion, as supply grows tighter near the close of the decade and as utilities begin issuing solicitations, I believe that would keep exerting upward pressure on SWU prices. And so that clearly reinforces our business case. That reinforced our investment and our case for our shareholders; that genuinely is my perspective on the matter. Now, this does not even account for a few of the additional and bonus and possibilities that exist. So should advanced reactors emerge as a leading force in the market, should someone step forward and declare a major construction of advanced reactors, that will exert still more pressure on not just HALEU and, as I said before, on LEU SWU capacity too. I believe that would represent a substantial upside and a substantial opportunity too. We experienced a significant geopolitical occurrence in which the biggest enrichment producer globally has effectively ceased to trade in the Western market; and I believe the consequences and the aftershocks of that will not be resolved for quite some time, from my perspective.

Stephen Gengaro analyst
#41

Great. That's great color. Thank you.

Amir Vexler executive
#42

Thank you.

Sameer Joshi analyst
#43

I appreciate you taking the time to answer, and nice work on the solid headway. My query concerns the $900 million tied to the DOE task order. Since advanced reactors probably won't be connected to the grid until the end of the decade, is it fair to think of these 10-year contracts as effectively five-year ones, with cash received early on?

Amir Vexler executive
#44

Good morning to you, thanks for joining, and that's genuinely a great subject to dig into. As I said before, we're currently talking with many parties regarding what they require, what we're able to provide, and a number of commercial conversations are underway too. My perspective is that we'll aim to secure the largest possible commitments from suppliers. Clearly, commitments that stretch further out benefit us more; pricing would capture that as well. When you consider contract pricing, every one of those factors gets factored in. Your point had to do with getting cash sooner on certain of these contracts. Naturally, these are all items we're always working to fine-tune, and we'll keep fine-tuning them to serve our shareholders' best interests, especially since the bulk of the SWUs we sell are what I'd describe as expansion SWUs. Those are SWUs we're putting capital into; so without question, we'll be seeking to fine-tune each of these items. Past that, I'll hold off on saying anything about particular contracts or their terms and conditions.

Bill Peterson analyst
#45

Yeah. Hello there. Good morning to you, Amir and Todd. I appreciate all the specifics, including the guidance figures for the year. I wanted to ask whether you could go deeper on which opportunities exist to achieve that 42-month window you mentioned, and also, I'd say, to expand more broadly. What I'm really asking is this: which parts fall under your own control, and which depend on suppliers or other outside parties? How much hinges on raising more money, on talks with suppliers and partners, or on what I believe you referenced earlier — government clearances tied to national security?

Amir Vexler executive
#46

Yeah. Well, good morning, Bill. I appreciate that question. What you're digging into, I believe, is precisely where our most significant internal discussions are focused at this moment. Like I mentioned, execution matters above all. Delivering on what we promised matters above all. At the same time, we need to be capable of creating opportunities and outperforming what we pledged. When you consider those opportunities — and I'll stick to broad terms and broad themes — we stand apart because we manufacture our own centrifuges. We clearly possess the ability to manufacture our centrifuges; we also work with partners who serve as suppliers. So much of what we do truly sits inside our own control, and we enjoy quite a broad scope of flexibility when it comes to creating those opportunities; take, for instance, matters such as cycle time for certain components we produce, plus engaging, motivating, and drafting agreements and relationships with suppliers so they're motivated toward quicker lead times, and making sure we organize our supervision, making sure we organize our internal procedures to deliver the finest quality, right the first time, and the best yield achievable. To me, that's basic, foundational manufacturing excellence, and we're collaborating, bringing in specialists in that area, drawing on every bit of knowledge and experience available out there to assist us. So far, the progress has left us pleased. And like I mentioned before, we genuinely anticipate sharing further announcements about our performance, whom we're teaming up with, and the value that delivers for the project and the shareholder. I'm not sure I can get any more specific than that, but overall, these are the themes we're going after. And like I've stated many times, I consider this among the most critical subjects we're pouring effort into right now.

Todd Tonelli executive
#47

Let me jump in here. A key element when it comes to putting money to work is making sure the balance sheet is strong. Because we can see clearly what we'll spend not just across the coming 12 months but across 24 months, we're able to guarantee that capital gets deployed without that schedule slipping, no matter what the market does. Under no circumstances do we wish to find ourselves compelled, when markets are heading lower, to go out and raise costly capital and thereby harm our shareholders. So we'll take an optimistic and opportunistic approach with our balance sheet, ensuring we have enough capital to protect ourselves and that we don't let that schedule slip when it comes to putting capital to work to hit our manufacturing rates.

Bill Peterson analyst
#48

Appreciate the color, Amir and Todd.

Amir Vexler executive
#49

Thank you.

Todd Tonelli executive
#50

Thanks.

Lawson Winder analyst
#51

Thanks a lot, operator, and good morning to you both, Amir and Todd. I appreciate the update today. I also want to extend my congratulations regarding the $900 million in support of your HALEU buildout. Along those lines, I want to drill into something that may be a very obvious question, but I'm simply not entirely clear about it, which is this: over the longer term, what's your approach to sourcing the LEU feed for the HALEU? Or to frame it differently, what portion of your LEU output will be dedicated to your HALEU output, and what portion of that 3.5 million SWU will then be left to meet LEU primary demand? Additionally, if that LEU capacity can't be used to provide the HALEU feed, what other options are there, particularly given that Russian supply will be gone after 2028?

Amir Vexler executive
#52

All right. Good morning. That's a solid question. I'll answer it quite generally, and let me know if you'd like me to go into any further specifics. In general terms, our intention, plan, goal, and strategy is to get as much capacity as possible out of the facility we are constructing. Like I said, we began with a particular baseline scenario, and from there we'll keep adding on in stages. That approach depends on customers making commitments — we're chasing those hard right now, and since we announced the $900 million, the interest has been really strong. Depending on what kind of contract it is, those commitments could let us keep growing our output of LEU, HALEU, or both. Speaking broadly about our HALEU buyers, my aim would be to get the most out of the SWUs we supply, so I'd want an agreement that covers delivering HALEU alongside LEU, and clearly lets us enrich both. I won't get into the details of any particular agreement, conversation, or negotiation currently underway. What I can say is that we aim to deliver LEU enrichment along with HALEU enrichment at the highest and fullest capacity we're capable of. On the second half of your question: suppose, just as a hypothetical, that a HALEU contract exists but the LEU feed needed for it falls short. Typically, from a contractual standpoint, that isn't a problem. There are structures written into contracts, whether set up by us or by the customers, that allow other suppliers to step in for that purpose. As I mentioned earlier, my expectation is that we'll see tightness as the decade draws to a close. Even with what was just mentioned, customers can still sign up for feed if the situation calls for it. Still, going back to my main point, our aim is to get the most out of both sides, since running the plant at greater scale matters a great deal. All right. I really appreciate it. That background is excellent. Thanks.

Neal Nagarajan executive
#53

Much appreciated, operator. That brings our investor call covering both the fourth quarter and the entire 2025 fiscal year to a close. As we always do, I'd like to express our thanks to those of you listening over the web as well as the analysts who joined by phone; we're eager to talk with all of you once more in the coming quarter.

Operator operator
#54

Thanks. That brings today's call to a close. You're free to hang up now, and we appreciate you joining us.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Centrus Energy Corp. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Centrus Energy Corp. earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.