Neogen Chemicals Limited (NEOGEN) Earnings Call Transcript
November 10, 2025
Earnings Call Speaker Segments
Good day, everyone, and welcome to the Neogen Chemicals Q2 FY 2026 earnings conference call. Just a reminder that every participant line will be in listen-only mode, and you'll have a chance to ask questions once the presentation wraps up. If you require assistance at any point during this call, please signal an operator by pressing star then zero on your touchtone phone. Kindly note that this conference is being recorded. I'll now hand things over to Mr. Nishid Solanki from CDR India. Thank you, and over to you, sir.
Thank you, and good evening to all of you. Welcome to the Neogen Chemicals Q2 FY 2026 earnings conference call for analysts and investors. Senior members of our management team are with us today: Mr. Anurag Surana, Non-Executive Chairman; Dr. Harin Kanani, Managing Director; and Mr. Gopikrishnan Sarathy, Chief Financial Officer. We'll start with opening remarks from the management team, and after that we'll open the floor for your questions. Before we begin, the usual disclaimer: some statements made or discussed today may be forward-looking, actual results could differ, and a detailed disclaimer appears in the Q2 FY 2026 earnings presentation, which has been shared and uploaded on stock exchange websites. With that, I'd like to invite Dr. Harin Kanani to share his perspectives. Thank you, and over to you, sir.
Thanks. Good evening, everyone, and thanks for being with us on our Q2 FY 2026 earnings call. We'll take you through how we performed and give updates on initiatives for strategic growth and expansion. Our Q2 FY 2026 results were defined by operational resilience. A rapid PO effectively neutralized the temporary impact of the Dahej plant outage; production was quickly moved to our alternate plant and supplemented with capacity from key outsourced partners. That strategic maneuver ensured we kept our volume trajectory, but it did bring additional temporary costs tied to contingency production arrangements and plant rebuild expenses until the insurance claim is fully recovered. Certain of these costs linked to loss of profit will be claimed in FY 2027, in line with the planned resumption of operations at the Dahej SEZ Organic plant. That said, our core business held its market position and achieved stability, navigating persistent geopolitical uncertainty and volatile pricing. Ahead of the detailed financial overview from our CFO, here's a quick summary. We delivered 8% revenue growth in Q2 FY 2026, and gross profit improved by 16%, driven by 350 basis points margin expansion. However, as indicated, EBITDA and PAT were affected due to elevated operating costs. Let me now share a key update during the quarter-end review.
We've made meaningful moves to strengthen our corporate governance framework, consistent with the best governance practices out there. The board has given the green light to separating the Chairman and Managing Director roles, effective October 1, 2025. We're happy to share that Mr. Anurag Surana has been designated Non-Executive Chairman of Neogen Chemicals Limited, and Mr. Sanjay Mehta has been designated Non-Executive Chairman of our subsidiary, Neogen Ionics Limited. On top of that, we welcome Mr. TCN Sai Krishnan to the board as Executive Director of Neogen Chemicals Limited. Through these appointments — including naming a non-promoter family member as Chairperson — we're reinforcing how committed we are to strong independent oversight. Turning to the strategic expansion initiative in Battery Chemicals: a greenfield facility for Electrolyte using MUIS technology at our Pakhajan, Dahej PCPIR plant. We're moving quickly to commercialize this greenfield plant. We expect to wrap up mechanical completion before this year ends, then kick off trial production, with commercial production to follow in the first half of FY 2027 — that's April to September 2026 — and Electrolyte Salt in H2 of FY 2027, in step with the anticipated rollout of ACC battery capacities in India and rising non-FEOC global demand for the salt. To be specific, the extra time the salt requires is for fully homologating the technology from our JV partner in Japan, and that is what adds somewhat more time to it.
That momentum rests on some important approvals we secured lately. One of India's top gigascale customers has finished the demanding production part approval process — PPAP, as it's known — and has cleared our Dahej facility for long-term commercial electrolyte supply. That's a major milestone, and as of now ours may be the only plant in India to have reached this point in history. On top of that, key international customers have granted provisional approval for our lithium electrolyte salt, and we expect final approval in Q4 FY 2026. We're also working closely with a number of other international clients that have already approved our electrolyte salt samples; their final approvals are in progress and should come in Q4 FY 2026 or Q1 FY 2027. These achievements confirm our quality and establish us as a dependable partner in the lithium-ion supply chain. At an international event we took part in recently, the international community responded very positively to the joint venture, since we provide the only Indian combination of low cost from India plus reliability from proven technology for electrolyte salt — specifically LiPF6 from India — and customers have viewed that very favorably. The joint venture agreements between Neogen Ionics and Morita Investments are being executed. So we're delighted to announce this major strategic milestone: the creation of the first Indo-Japan joint venture in the critical battery material space.
The joint venture that has been set up by Neogen Morita New Materials Limited — which we'll refer to going forward as NML, and which until now has been a wholly owned subsidiary of Neogen Ionics Limited — is structured to draw on synergies and take advantage of the fast-growing lithium-ion battery market. NML's focus will be the manufacture, development, and sale of solid LiPF6 salt, an essential component of lithium-ion battery electrolyte, together with other related products. As a rule, this plant will be the sole non-FEOC compliant facility for Electrolyte Salt in India, and it draws on proven, established Japanese technology, which gives a substantial edge when it comes to cost, speed, and reliability. Per this agreement, NIL will retain at least 80% ownership of NML, while our JV partner MIL will hold no more than 20%. As you're aware, makers of lithium-ion battery cells in the U.S. have to follow foreign entities' concern guidelines in order to obtain the attractive U.S. government tax credit, which is also called the 45x credits. That demands a full switch to non-FEOC suppliers by 2027 where Electrolyte Salt is concerned. Because of this, most international customers are proactively speeding up their move to non-FEOC sources across 2026. Such a phase shift matters for them if they are to reduce compliance risks and guarantee they remain eligible for the tax credit without interruption. Being able to deliver a non-FEOC compliant, established LiPF6 technology solution puts Neogen at the leading edge of this mandated pivot in the global supply chain.
Our long-term plan is to become a stronger, technology-driven and agile specialty chemical leader, and we're carrying it out. Partnering strategically with MUIS and Morita is essential if we are to speed up our entry into the battery materials value chain, which is growing fast, and to lock in our position there. Even with global economic headwinds, we remain committed to growing volume, improving how efficiently we operate, and pushing transformative projects forward, and that strengthens our confidence in a robust long-term trajectory and in delivering sustainable value creation. That brings my opening remarks to a close. I'd now like to ask our CFO, Mr. Gopikrishnan Sarathy, to walk us through the financial highlights for the period under review.
Thanks, Dr. Harin Kanani. Hello, everyone, and welcome to the Neogen Chemicals Q2 FY 2026 earnings call. I'll walk you through the main financial highlights. Just a note that our figures are consolidated. Revenue for Q2 FY 2026 came in at INR 209 crore, which is 8% higher year-on-year. We got there on the back of steady demand and higher volumes in both the base business and the Lithium business. That helped offset the impact of the Dahej plant being unavailable. Neogen Ionics added INR 5.42 crore to revenue for the quarter. Organic revenue during the period was INR 184 crore, a rise of 12%, and Inorganic revenue was INR 24 crore. EBITDA for the quarter stood at INR 30 crore. Gross profit was flat, but the EBITDA margin percentage came under pressure from several things. Among them: higher employee costs driven by performance-linked incentives, long-term benefits, and strategic new hires. Second, steep increases in the insurance premium after the recent fire incident, along with higher job work and conversion costs. As Dr. Kanani mentioned, we anticipate recovering part of these expenses through the business interruption loss of profit insurance plan in FY 2027, once operations restart at the Dahej SEZ Organic plant. Neogen posted a PAT of INR 3 crore for Q2 FY 2026.
That number reflects the combined effect of a number of things that held back profitability — specifically, higher operational costs, as we mentioned earlier, increased finance costs tied to the capital we deployed for inventory and for rebuilding the plant after the Dahej fire incident, continued investment in the Organic Dahej SEZ zone while we wait for the final insurance payout for the fire loss, and the initial cost of Neogen Ionics, plus lower utilization at the Dahej plant pending both the final approval for Electrolyte Salt and delayed market demand for electrolytes. Turning to the key development during the quarter under review, to make sure we maintain our growth trajectory and operational stability, we have successfully executed a private placement of INR 200 crore NCD. Having these funds available immediately gives us the crucial financial flexibility to execute our ongoing growth projects. Importantly, this money will also provide the necessary liquidity to speed up the rebuilding of the Dahej Organic plant and enhance the timely progress. Finally, just a snapshot of our balance sheet highlights. Despite operational challenges, Neogen's financial foundation remains solid. The balance sheet is strong, ensuring uninterrupted business continuity and providing financial flexibility to pursue strategic growth initiatives. Standalone debt in this quarter stood at INR 722 crore, and net debt was INR 595 crore.
That roughly INR 200 crores rise comes from the NCD issuance, which was done mainly to fund the rebuilding of the Dahej plant until the final insurance claim comes in. Debt coverage is still healthy, as shown by a trailing 12-month DSCR of 2.1x. Consolidated total debt stood at INR 1,078 crores, and net debt was INR 900 crores. The company keeps strong liquidity, with liquid investments of about INR 167 crores as of the quarter end. That wraps up my remarks. I'll now ask the moderators to open the floor for Q&A. Thank you.
Thanks a lot. We're moving into the Q&A portion now. To ask a question, you can press star and one on your touchstone telephone. Should you want out of the queue, press star and two. We ask participants to use their handsets when posing a question. Ladies and gentlemen, we'll pause briefly while the queue is put together. Our first question comes from Arun Prasath at Avendus Spark. Go ahead, please.
Appreciate the question, and good evening to all of you. Dr. Harin, my first question concerns the guidance for the.
My apologies for cutting in, Mr. Arun, but we're picking up some noise coming from your end. Could you take a look at that, please?
No, my apologies, I don't believe so. Does it remain that way?
Please, go right ahead.
Arun, no problem — I can hear you fine. Please go ahead.
All right, thanks. Dr. Harin, my first question concerns the guidance for Battery Chemicals as we begin, particularly the salt. Previously, we had also sort of signaled that beginning in 2025 and 2026, we ought to witness a lot of—perhaps some U.S. customers who are launching their battery plant will begin placing orders. Well, we have observed a slight delay there. So what is causing the holdup in orders for salt from at least the overseas customers? And how confident are we this time that the present guidance will hold, and that we will restart the plant—the larger facility as well—on schedule? That is my first question.
Absolutely. Thanks, Arun. Another question from my side. I believe two key assumptions underpinned the guidance for our current year. The first concerned electrolyte demand from India. Once our Indian gigafactories — Ola and Exide among them — begin producing and ramp up, and as you've observed, Ola obtained its ARAIC approval only recently. Our expectation is that their ramp-up will occur during the second half and particularly in the next calendar year, 2026. From Q4 onward, we believe electrolyte demand should become stronger. In a similar vein, our understanding for Exide is that they will begin at the end of this year or early next year. Relative to our prior estimate of when these players would start, electrolyte in India slipped a bit, which resulted in lower volumes. That said, we are still monitoring how Q4 will turn out, and right now we are essentially looking at the Q4 performance of Exide and Ola demand. The final figures will also hinge on that. Compared with our earlier estimate, demand ought to have begun from roughly Q2, Q3 itself. India's electrolyte demand has been delayed. On the salt question, as we discussed previously and as I also noted in my opening remarks, you first go through quality validation, quality confirmation, and after that a very detailed procedure known in the auto world as prepack, where the approval is ultimately granted.
We're happy to share that for electrolyte, our prepack has now been successfully cleared. Regarding Electrolyte Salt, prior to the prepack, at the time of our final audit, we largely received a provisional approval. The customer asked for some further suggestions or improvements at our facility. A few of these are just software items, some additional instrumentation they want from us, some software systems they want us to update, and there are also some facilities they want us to improve. We expect the majority of this work to be finished by January or February 2026, since these were extra requests that came up during the final audit. Neogen has already been granted a provisional approval. Depending on our compliance and how we complete this, they will either use just an online procedure to approve us or perhaps make one more visit in January or February. As soon as that takes place, our commercial production of the salt can be sold on a regular basis. At present it is trial or something along those lines. I think this was something we had hoped to reach by September. Essentially in the first half, and on that basis in the second half, we would have it fully available for sale. However, given the current developments and the additional request from the customer, we expect it sometime in 2026, Q1 or Q2, sorry, calendar year 2026, Q1 or Q2.
Basically, the point where we expect the bulk of salt demand to pick up is either Q4 FY 2026 or Q1 FY 2027. Also, the U.S. government's requirement is that in 2027, to qualify for 45x credits, they have to move to non-FEOC compliance — so, a supply chain free of foreign entities of concern. Because of that, most customers, depending on how stringent they are, have said that some of the more cautious ones will begin switching from Q1, Q2, calendar year 2026. Those who are somewhat more price conscious would prefer to switch from Q3, Q4 of calendar year 2026. Basically, in 2027, everyone must switch. Before that, one quarter or four quarters earlier. That depends on the type of company and how much risk coverage versus cost consciousness they have. Most customers also plan to switch during calendar year 2026. Some starting from Q1, some starting from Q3, Q4, depending on those companies' internal policies. That is why calendar year Q4, which becomes H2 of FY 2027 — we are very confident that in H2 of FY 2027, demand will be very, very strong. We should see demand improvement in H1, FY 2027.
Fiscal 2026 didn't turn out as we'd originally expected. The main reasons are delays with Electrolyte and in getting final customer approval. A contributing factor may be that customers prefer to make the final switch in 2026 rather than the second half of 2025.
Got it. A quick follow-up on that point. We discussed the different stages involved in securing the approvals. In the end, we expect to receive them by, let's say, likely January 2026. Will that same group of approvals, and again, will the same procedures be applied for the greenfield facility too, or will it run in a fast-track mode? How should we view that?
It's going to move in fast track mode for a few reasons. First, our sense is that this is a facility where we're transferring technology, since the main equipment, the raw material, the specification — all of that basically stays the same. A lot of work gets reduced. Also, certain customer suggestions will be incorporated there in the greenfield facility as well. The third point is that customers will also be operating on a tighter timeline, because most of them want to switch in 2027. They'd have just one or two quarters to finish the procedure. From a procedure standpoint, we feel it will be much faster. While we've said the entire facility would be ready at full capacity in H2 of FY 2027, some trial production will begin even earlier. For example, even for Electrolyte, we're saying our first target was to complete everything by Q4 FY 2026. Mostly, for Electrolyte, we should even be ready for trial productions and stabilization by Q1 FY 2027. For the salt, we're targeting readiness by Q2 FY 2027. Some trial productions will start, and we'll try to do some of the validations also in line, at least customer visits and things like that.
Got it. Regarding the FEOC rules, customers need to move to sourcing from us, from India, or from other non-Chinese suppliers. What sort of U.S. volume do you expect? Not specifically for us—at the industry level overall, how much volume is there for players to go after in targeting this FEOC volume?
I apologize, I wasn’t able to catch your question clearly. Did you say non-U.S., sorry, U.S., and U.S.?
Let me restate the question. So you mean demand for non-FEOC Electrolyte Salt, which is the market we're targeting. In terms of tonnage, what sort of volume are you referring to — at least the portion that has already begun and that isn't tied up by long-term contracts with, say, the existing suppliers?
All right. So at present, the bulk of supply comes out of China, with the exception of a single Japanese supplier and a single Korean one — is that right? The majority of the shift would take place, and we'd be the third-largest company that they'd be granting approval to. Europe still has no supply on offer. The U.S. still has no supply on offer. There's one Korean firm that has been discussing getting started. Again, we don't know precisely how that will play out, but we're considerably ahead when it comes to contracted volume, interest in contracted volume, and the approval processes. My sense is we should largely be the number three or number four company out there. If you look at it from a capacity standpoint, our understanding is that Japan has capacity somewhere between 3 KTA and 5 KTA. The Korean supplier's capacity is roughly 2 KTA. Neogen would be adding approximately — okay, taking both salts together on the LiPF6, the greenfield — we're adding roughly 3 KTA at the greenfield, and counting our Dahej, we'd have roughly 4 KTA. I think we're in a similar order of magnitude, or somewhat better, relative to the players already in the market. We believe that, relative to Japan and Korea, customers also gain a cost advantage.
For at least a portion of these customers, a long-term agreement is already in place with pricing settled. I believe there are a few where we're still in pricing discussions. As for the major customer, we already have agreed-upon pricing. That pricing will already account for things, which essentially demonstrates that acceptance exists regarding Neogen's cost structure.
Could you give the U.S. salt demand figure in KT? You brought up non-Chinese supply capacity. How much demand comes from the U.S.?
Alright, so I figure if we’re looking at something in the range of 300 to 500 gigawatt hours, then total demand ought to land somewhere around 40 KTA to 60 KTA, assuming everything gets converted for a 300 GW output.
By which year will this happen, sir?
By 2027.
So of those 300 GW, what portion is running right now, and what portion is being built?
My sense is that right now we're already sitting at 140 GWh, maybe 150 GWh, and that capacity is already online.
Alright. Alright.
Additional capacity is coming online too, though real cell usage — or actual output of cells — sits at roughly 140 GWh to 150 GWh. That figure is only my own approximation. No official figure exists that states the total. It's simply an aggregation of the leading manufacturers, correct? Consider the big players such as Panasonic, Tesla, LG, and Samsung. Add SK On — if you total up their capacities and what they currently turn out, our estimate lands somewhere around that level.
My apologies for cutting in, Mr. Arun—could we ask you to please get back in the queue? There are participants waiting for their turn. Thank you. Ladies and gentlemen, so that management can take questions from every participant, kindly keep your questions to two per participant. Should you have a follow-up, you're welcome to rejoin the queue. Our next question comes from the line of Archit Joshi with Nuvama Institutional Equities. Please go ahead.
Hello, and good evening to you, Dr. Harin, and the team. For my first question—or really, if you could help us get a handle on the prepack, or the agreement we've signed instead—if you could shed a bit more light on how we should be reading this situation. Is this a contractual obligation that the customer has drawn us into? Does it give us visibility into, say, a certain volume of X? Would we be enabling, say, some amount of gigawatt capacity? Anything along those lines—if you could help us understand, we might be able to back it up a little better.
Prepack essentially amounts to your quality system approval — it also gauges productivity, capacity, and whether the product's quality is suitable. Beyond that, it's a sign of systems. Think of it as the equivalent of a U.S. FDA pharma customer arriving to grant you final approval, or the U.S. FDA itself coming in and granting final approval, after which your product can enter commercial usage. That's basically what it equates to. What repack means, put simply: suppose we're looking at the API world — the U.S. FDA has granted you approval, so your product can now be sold commercially in the U.S. market and can be consumed. You might run some trial production and so forth. Generally, before commercial supply begins, the prepack has to be completed. This is typically handled by each individual customer. One of the giga factories in India has already finished its prepack with Neogen. They're now free to keep purchasing electrolyte and incorporate it into commercial products destined for autos or other kinds of applications. That's essentially what prepack means. On a separate note, regarding volume commitments — as we said before, for Electrolyte Salt we already hold volume commitment agreements, which are distinct agreements covering pricing and payment terms, and so on.
On the salt side, agreements are already signed that essentially cover in full the 5,500 metric tons, or 5.5 KTA, of capacity we're putting in place. So for salt, we have complete agreements in hand. When it comes to the electrolyte, alongside prepack, we're likewise in discussions with customers about long-term supply volumes. In the same way, for electrolyte we intend to finalize long-term supply agreements. That said, for the most part, as you can see, India's giga factories are only now beginning to come up one at a time. A number of them — in fact most of them — will kick off in the second half of 2026. So there's a bit of time remaining before then. With those that have already started, we're actively talking with them to wrap up contracts for long-term supply. This work is in progress, but as of today we are the sole facility in India holding a prepack approval for electrolyte salts. On that basis, anyone wanting to purchase locally at this moment has to buy from Neogen and no one else. Our position is very strong, and it also provides confidence regarding the quality systems and the supply that Neogen is able to deliver.
Sir, Gopi said this relates to electrolyte demand, and I believe I heard you mention it covers the 5,500-ton salt commitment. So I'm a bit confused as to whether this applies to salt, electrolyte, or both.
Prepack concerns approval for Electrolyte. On a separate note, I said earlier that regarding the salt, a pricing commitment is already in place. When it comes to Electrolyte, prepack has been finished, though the pricing agreement is still being worked through. For the salt, the pricing agreement is complete. Provisional approval has been received, but the final prepack approval depends on our implementing several of the suggestions I brought up before. We're expecting that around January or February 2026. Yeah.
Understood. Understood. On a call with one of the battery makers, I heard that they're beginning with NMC battery output before moving to LFP. Does that affect how we see demand, depending on whether it's NMC or LFP?
From an electrolyte standpoint, the sole distinction between NMC and LFP — well, from a business perspective — is this: 1 GWh of NMC calls for roughly 400 to 500 metric tons of electrolyte. With LFP, the figure is about 1,200 metric tons. Take a 10 GWh NMC facility — demand would come to 5 KTA. For 10 GWh of LFP capacity, demand lands at approximately 12 KTA. That's the demand side. At a broad level, looking at total demand alongside the production that's coming — which is what we anticipate — once India gets to, say, perhaps 50 GW or 100 GW, the split would be 70%-80% LFP, roughly 10%-20% NMC, and 10% others. On that basis, we've arrived at an average consumption figure of 950 to 1,000 metric tons per gigawatt hour. Given the feedback we've had from customers, we remain confident the NMC/LFP mix may shift somewhat — 10%, 20%, even if it turns into 30% NMC and 70% LFP. Still, increasingly, when we consider the 30 GW, 50 GW, 100 GW level, LFP is going to be the driving force.
Demand is going to exceed what we originally anticipated. Our target of full utilization by FY 2029 stays the same. We would still be able to reach full utilization of our electrolyte facility without difficulty, and of course salt even sooner, by FY 2029.
Got it. One quick housekeeping item, if I can fit it in. Where would our gross debt top out? At what level do we hit peak gross debt? And what are the timelines for that? Also, inventory on the present balance sheet looks pretty elevated. Could you explain why we're seeing a jump of nearly INR 130 crore in inventory?
We expect peak debt to be INR 1,800 crore. We'd essentially hit that, let's say, roughly one year nearer to our full utilization level, so somewhere around FY 2028 is when we'd get there, when peak demand for the peak debt would occur. On your second question, also consistent with the revised commissioning date, our bankers have extended the start date for our greenfield site by about one year as well. That too will move our repayment schedule out by one year. This gives us extra comfort in maneuvering cash flows. So the delay won't have much of a significant impact on cash flow requirements, and we would stay comfortable thanks to the approval the bank has given us. Lastly, on your question about inventory, as you know, we had indicated that we lost around INR 180 crores of inventory in Dahej during the fire, INR 170 crore–INR 180 crore of inventory during the fire. The increase you're seeing over the last six months is essentially making up for the inventory we lost, because you can see we have regained our revenue performance. In fact, it is slightly higher compared to what we had around that time.
To keep that going, what we lost in inventory is being replenished at this point.
Got it. Thank you, and best of luck.
Thanks. Our next question comes from Abhijit Akella at Kotak Institutional Equities. Your line is open.
Yeah. Good evening, and thanks a lot for taking my questions. Just regarding the Battery Chemicals business, we had previously guided to roughly INR 300 crore of revenue. Obviously, things appear to be progressing a bit more slowly. I was just wondering whether you might want to perhaps update your guidance for this year and possibly next year as far as that business is concerned.
Sure. Given where things stand today, as I said before, because demand for our electrolyte has come in lower—even though we're prepared and the approval process took us more time—we now expect that to take longer. We won't be able to hit INR 300 crore this year. As we noted earlier, it was also going to be tough, but on the number, we were trying to get better clarity. Depending on how electrolyte demand actually shapes up in Q4, we expect roughly INR 30 crore-INR 40 crore for the current year. Looking to next year, we expect that again, many facilities will be coming online next year, particularly in H2. Again, it depends somewhat on how that plays out. We are more, and again, salt as well, most customers would be making the transition in 2026. Essentially, in FY 2027, they are doing the transition. In FY 2028, we have much stronger clarity on both Electrolyte and Salt. We feel at a minimum we should be able to deliver around INR 400 crore-INR 500 crore of revenue in the next financial year, which is essentially FY 2027. We remain on track to reach full utilization level by FY 2029.
This is the guidance we've provided: INR 2,400 crore to INR 2,900 crore, assuming the facility is fully utilized. FY 2028 will land somewhere between those figures. We anticipate Salt demand will be very strong, and Electrolyte will depend on how the ramp-up in India unfolds — essentially, the split between the India ramp-up and some customers who, for a brief period early on, will have to import electrolyte from China because of contractual limitations. How soon they choose to switch over to us will determine FY 2028 revenue, and we'll guide you further as we gain more clarity. We expect it to exceed INR 1,000 crore — at minimum, meaningfully above INR 1,000 crore — but within the range of INR 500 crore and, let's say, the INR 2,900 crore figure.
Appreciate that — that's a big help. Regarding the base business, we had this INR 850 crore plan for this year. That looks on track, correct? How do you see it shaping up next year?
Yes, that's still on schedule. We'll also be aiming for full utilization in the coming year, at a level of, say, somewhere in the INR 950 crore to INR 1,000 crore range. As we shared before, in the year after that, with no CapEx and simply running the plant at full optimization, we'd like to target at least double-digit growth over that, at least based on what we can see today.
Thanks a lot. I’ve just got a couple more questions before I rejoin the queue. First, what’s the amount of debt servicing we might have lined up for the next 12 months? If you could just help us with that figure — perhaps the principal plus the interest obligation scheduled over the next 12 months. The other thing was on the Battery Chemical side: it seems like in recent weeks and months, prices in China have begun rising quite significantly across all kinds of Battery Chemicals. What exactly might be going on there, and what do you expect for how that market might develop?
Absolutely, and thanks for raising that. Regarding the total repayment we owe over the coming 12 months, on the term loans it comes to only about INR 40 crore to INR 50 crore. As for interest, the main piece is our working capital interest, since most of the project finance-related interest gets folded into the project cost. That won't affect us, with the exception perhaps of the Dahej-related CapEx within Ionics. The bulk of the Pakhajan greenfield site sits inside the project cost, and that has already been factored into the project investment. On the ordinary interest we pay on working capital, the larger share is still pending receipt. We have gotten INR 80 crore, but the remaining roughly INR 250 crore, along with loss on profit and additional rebuilding cost from the insurance, is still to come. That figure of about INR 300 crore is what we expect to receive over, say, the coming 12 months. As those funds keep coming in, our interest cost — essentially the working capital interest that is elevated right now — will taper down and improve. That is roughly the estimate for the repayments we need to make. On your second point regarding pricing in China, we have also heard there is a very strong movement in Electrolyte Salt and, to some extent, in electrolyte cost as well in China.
A lot of the Chinese players were selling essentially at the cost of raw materials plus what I'd describe as labor. A number of them aren't even factoring in expenses like power and fuel. My sense is that some of these firms couldn't keep going and began shutting down. On top of that, demand looks stronger now. The excess capacity in China — at least among the solid cell manufacturers — has disappeared at this point. Given the robust demand for battery storage worldwide, India included, the capacity of the quality cell makers is now nearing full utilization. That eases the pressure on them to sell cheaper. As a result, we've observed battery material prices stabilizing, and the same goes for Electrolyte and Electrolyte Salt; to some degree, cell costs are probably heading higher over the years ahead as well.
Understood — thanks very much, and all the best to you.
Thanks.
Thank you. We ask that each participant keep their questions to 2. Should you have a follow-up, please rejoin the queue. Our next question comes from Jason Soans at IDBI Capital. Please go ahead.
Yes, thanks a lot for taking my question. I have just one. Mine relates to the insurance payout. I just wanted to know — I mean, those things were going along fine, but there's probably some delay in receiving that insurance payout, which is why we also had to raise some funds. If you could just give us some color on why this insurance payout is delayed.
Up until June, the insurer was essentially just looking to verify what caused the fire through a number of rigorous tests, and all the permissions had been secured. After that process wrapped up, they released the first interim payment, which essentially signaled acceptance of the claim. Now, as you're aware, there are two stock claims plus the MPP — that is, the rebuilding of capacity, the CapEx-related claim. Against the CapEx-related claim, they have already provided INR 80 crore to us. Once we finish this INR 80 crore, which we expect during the current quarter, we would end up fully utilizing it, because we are also on schedule to complete this by Q4 so the plant becomes available for the next financial year. When we complete that INR 80 crore, they will provide the next interim payment against it. On the stock side, after the fire and after handling the CapEx-related claim, they began processing. Simply because the claim amount is large, at times there are one or two rounds of review on their end, back and forth, with extra queries that we are answering. At times they also bring in external experts. We are again pushing the insurance, and we hope that during the current quarter — so in Q3 — we should finish receiving the stock-related claim, at least the majority portion of it.
The last installment tied to rebuilding CapEx—since we carry replacement-basis insurance, it isn't the loss's cost but the cost to replace it—will only be settled definitively once the plant is ready. We'll receive some amount by Q1 of next year. As we've observed, certain costs have risen due to some outsourcing, some employees, some standard cost at Dahej continuing. All of that will form part of the loss-on-profit claim. That typically is expected around Q2 or Q3 of FY 2027, since the calculation and the working on it begin only after the plant has been rebuilt. That exercise itself will get started. For us too, it's the first time. When a claim is large, it simply takes them a bit longer to go through each and every stage.
Yeah. Broadly speaking, even with a few delays, things are proceeding as planned. What I mean is, it matches what we estimated, correct?
Yes.
Correct.
Right. We have to be, that's according to the estimate. That's why we're paying somewhat above cost, yet we're able to keep our operations running at full stage. We're continuing our growth. We're doing what's needed for whatever we had planned around employee retention and employee motivation. Those programs have also carried on. CapEx has carried on at the same pace. There's no delayed CapEx or anything like that because of a lack of funds. I think those are the positives stemming from the INR 200 crore bond we issued.
Yes, sir, yes. Just so I have this straight — I mean, regarding the commissioning of the battery cell facility in India, which, as you said, has slipped, would it be fair to estimate that as a one-year delay, right? With names like Ola, Exide, and Amara Raja, it's probably a one-year delay, with the whole EV domestic supply chain being built up in India. Would that be a fair take?
Right, I’d agree with that. In a way, we had thought Ola would begin during the first half. Getting their cell approvals and reaching full commercial scale ended up taking somewhat more time, correct? In some sense, I’d describe it as a delay of six months to a year. What we’re largely seeing is that by 2027, most of the players who had made plans would begin manufacturing. 2026 is somewhat difficult. Calendar year 2027, which is FY 2028, we see very strong demand. Another thing that has happened while the delay has occurred is that consumption of the cells keeps rising. I think with EVs, there is a good positive response. More and more people are coming. We see very strong demand for energy storage, or what is best called battery energy storage demand. That demand has grown stronger. So everyone is trying very hard to obtain cell capacity as quickly as possible.
Alright, just one last question from me. For 2026, naturally, you had come out with revised standalone guidance. From what I gather, the Battery Chemical piece gets taken down owing to all that has happened around the delays. You mentioned INR 30 crore to INR 40 crore for 2026 and INR 400 crore to INR 500 crore for 2027. Now, as far as standalone goes, that guidance is being retained by you. Perhaps you indicated that 2027 will likely be judged purely on the base business. What I mean is you called it double digit at best. Maybe you will push hard for double digit as we head into 2027.
Apologies. No — we had stated INR 950 crore to INR 1,000 crore for 2027. For FY 2028, it's essentially full utilization of the capacity we already have. What we said for FY 2028 is that, since we don't want to undertake significant CapEx, we're confident of delivering double-digit growth without that CapEx. If, for instance, we see very strong demand in organolithium — because we've seen it in both Organolithium and the CSM business — actually, despite the fire, our CSM business contribution came to almost 16%, and we're seeing very strong demand there. Should demand prove very strong, we would do some additional CapEx for FY 2028. Right now, our aim is that with the same setup we can deliver at least double-digit growth. We're targeting revenue somewhere around INR 1,150 without CapEx. If we see very good demand and a good reason to proceed, we'll take a call in FY 2027 on that. It's FY 2028 that I was referring to for the double digit.
Alright.
Between INR 950 crore and INR 1,000 crore.
Alright, sure.
There's nothing different to report.
Thanks a lot. Okay. I really appreciate it, sir, for taking my question. Thanks.
Thank you. Ladies and gentlemen, we'd ask that each participant keep their questions to two. Should you have a follow-up, feel free to rejoin the queue. Our next question comes from Nikhil Agarwal of Money Stories Asset Management. Please go ahead. Yeah. Good evening, sir. Thanks for the opportunity. I had a question about how you manage debt and cash flow. I just wanted to know the current CapEx in INR that we've already completed, and what amount is left. Also, what will the debt and interest level be once the CapEx cycle we have is done, and how do we plan to handle the interest cost? Thank you.
Yes. So far, we've completed CapEx of about INR 620 crore. We expect another INR 500 crore by the end of this year. As our existing capacity expansion is finished next year, we will complete the INR 1,500 crore CapEx across our Dahej and Pakhajan sites. On the Neogen Chemicals side, we're mostly rebuilding the plant. Perhaps when we do that rebuilding, if there's some extra capacity or an improvement that insurance doesn't cover, we'll have to pay for it. That's something you'd only learn after the final insurance evaluation. Maybe some incremental CapEx for our R&D and pilot facility, plus maintenance CapEx at our other sites. We aren't considering any large CapEx on Neogen Chemicals this financial year or next. It should all be double digit, no triple digit kind of CapEx in Neogen Chemicals. On funding, we already have 70%, so 70% is debt funded, which is already secured for our Neogen Ionics purpose. Also, further, as part of the JV, we would also receive some additional funds coming in as equity contribution from our JV partner. That will basically fund Neogen Ionics.
For Dahej, our contribution has actually already been funded pretty much entirely—kind of significantly, in fact. We've already put up a significant portion of the greenfield funding ourselves. From a Neogen standalone basis, we don't anticipate investing too much more into Neogen Ionics, since the majority of the funding has come in, and some of it will partly come from our joint venture partners. In Neogen's case, most of the insurance proceeds would come through, and most of that would serve as funding. As a matter of fact, we've already funded the inventory-related expenses. Once that funding arrives, it will help us bring down debt or keep some liquidity so we can basically plan for any unexpected requirements. That's essentially the idea. Then, further, as I explained, once the Dahej facility comes online in, let's say, Q1 of next financial year, we'll have a one-year moratorium. When our Pakhajan facility comes online in FY 2027, we'd get one more moratorium from the start date. Repayment, again, that too at a ballooning level. The bulk of the repayment burden in Neogen Ionics would fall in FY 2028 and FY 2029, and by that time we would already be hitting full utilization level. Cash flow from the company itself would be sufficient to repay the debt there.
Alright. Alright, thank you, sir. I appreciate the question.
Thanks. Our next question comes from Reena Shah at Shubkam Ventures.
Yes, sir. I'm already on the line.
Ms. Reena Shah, you're up next for your question. Your line is open.
Hello, sir. Thanks for giving me the chance to ask. I'd just like to get a clearer picture of the costs you incurred as a result of the fire incident. Are those one-time costs, or do they recur?
Reena, as you're aware, whenever you file an insurance claim—particularly a big one—the insurer usually raises your premium in the couple of years that follow. Our renewal came up in July, August. Since then, the cost of our insurance, the premium, has gone up significantly on account of that. So yes, some of the contribution is coming from there. That will last, say, a year or two. After that, it essentially returns to a normal sort of insurance level. In a similar way, certain costs we're bearing involve activities where, lacking capacity, we must outsource some stages of manufacturing. Also, some of our capacity, or fixed expenses at the Dahej site, remain. A portion of these expenses can be claimed under our loss on profit. Making a provision for that is very difficult. In the current year, you'll see them showing up as higher expenditure in other expenses. We believe most of those would be recovered from the insurance in the next financial year. Naturally, once the Dahej plant is running, this additional expenditure would no longer exist. We would return to our normal EBITDA levels in relation to that.
So is there any update to your margin guidance?
Honestly, forecasting this is quite tough. I'd say for this year, prediction is a bit challenging. When we reach full utilization next year — INR 950 crore to INR 1,000 crore standalone — we're expecting that same 18%, give or take 1% to 1.5%, margin. As utilization rises further and we move into FY 2028, there could be improvement beyond that as our CSM and Organolithium business begin contributing more. On Neogen Ionics, we keep targeting 20% ROC as our margin. EBITDA margin is really hard to forecast given lithium price volatility. It could fall somewhere between 16% and 20%, depending on lithium prices and other raw materials. For Neogen Ionics, essentially our target is a 20% ROC.
Thanks. For next year, you've guided INR 400 crore to INR 500 crore for Neogen Ionics. Under your assumptions, how much of that comes from source and how much from electrolyte solutions?
Our expectation is that the split will be roughly even—about 50% from Electrolyte and 50% from salt. In any case, should demand run somewhat higher, we'll be prepared to supply additional volumes of both Electrolyte and Salt.
Alright. Alright, I believe that covers everything on my end. Thanks.
Appreciate it.
Thanks. We’ll take the next question from Ankur Periwal at Axis. Go ahead.
Yeah. Hi, Dr. Harin. Thanks for the chance. Apologies if my question repeats something. I hopped on the call a little late. First, just a clarification about that 1-year extension in the moratorium for debt repayment. Does that apply only to principal amounts due, or will the interest outgo be extended as well?
Ankur, up until the project is finished, the interest is already folded into the project cost. Only once production begins does interest on that portion become payable, and that runs for one year. Repayment then kicks off the year after — in year two, we'd begin paying it back. That's how it was before as well.
Yeah, that’s right.
That was the same situation earlier. Now we have a one-year extension where interest payments can begin after one year, with repayment occurring the following year, depending on when we actually start.
Right. Capitalizing interest is well understood. The interest payment comes after a lag of one year. Then repayment is another year out.
That's correct. Yes.
Is that clear?
Since the beginning of production.
Starting right when production began.
They’ll likely take it into commercial production. Yeah. Yeah.
That's reasonable. My next question concerns the salt segment. I understand there have been postponements with the facilities in India. Looking at it worldwide, what has demand looked like for salt? And then, is there any additional capacity planned on top of that?
Apologies — I didn’t catch the last sentence you said. Could you repeat it for me?
Apologies. Regarding salt, first, what have client conversations been like on the demand outlook and so on? Second, are there any plans to expand salt capacity further?
Absolutely. Customers have responded really positively to the Morita joint venture. A lot of them genuinely valued it, since it provides considerable peace of mind. At the outset, we were in active talks with just 1 or 2 key customers, but today 3 to 4 big consumers are engaging with us actively. As noted during our call, a few of them even accelerated their sample approvals. At this point they've finished approving the samples. Beyond those 3 or 4 major players, another 2 or 3 smaller ones have likewise begun working alongside us. We can now reach a wider customer base. Customers feel greater confidence regarding the new capacity that will soon be available. I'd say all of this has been quite encouraging. Many customers, for their part, now have better clarity on 45x-related credits and are eager to have a non-FEOC supplier in 2026. As I mentioned, some wish to kick off homologation in Q1 or Q2. Others prefer waiting until Q4 so they can benefit from a lower China price to the greatest extent possible. Their shipment only happens at the end of the quarter — Q4, I mean. Their shift will essentially occur for consumption in 2027.
It's very clear to everyone that by 2027, they're looking for a supplier that isn't FEOC. Neogen is now seen as a really strong contender, particularly following the JV, since that just boosts how reliable the customer perceives them to be.
Okay, sir, on the pricing of the product — will Chinese salt serve as the benchmark for setting that price, or how are we approaching it or negotiating on that front?
Okay, sorry. Before we get to that, you had also raised the question of salt capacity. As I mentioned previously, based on our current customer base alone, we would exhaust that capacity sometime between FY 2028 and FY 2029. That also hinges on whether we consume the salt ourselves for electrolytes. We're offering customers choices on this as well, since—as you pointed out—it comes down to pricing relative to China. Throughout last year, when China's pricing was extremely, extremely low, customers still preferred our product, driven by FEOC and by the supply constraints. The single greatest boost China gave us in marketing our product was the restrictions they declared starting 8 November, because that genuinely rattled customers. At any moment, if China declares, "We won't supply this, and we won't supply that," and if Electrolyte Salt gets added to that list tomorrow, they'd be hit very hard over something that costs very little. Because of that, every customer is eager to purchase. They're even more eager to buy from Neogen. Yeah, I believe the benchmark generally sits outside China—are you the cheapest? That's what everyone in the international market keeps asking.
Neogen — at least for the contracts we've signed — the answer there is yes. That's exactly why they keep talking with us. More customers are in discussions with us about their demand. We'll continue to monitor it. Yeah, we do see a strong need that by FY 2028 or FY 2029, we may require additional salt capacity. We feel that 2 KTA is something we can add fairly easily, since it won't cost that much. We won't do it until the greenfield site is fully up and running and we have clarity on approvals, and supplies begin. After that, we'd take perhaps nine months or 12 months and add 2 KTA, provided demand stays strong and customers commit to larger volumes with us for 2028 and 2029.
Sure, that's helpful. One quick follow-up on that. You could add two thousand-odd tons, say, within a year — that's mostly debottlenecking. If you wanted to add, say, a greenfield expansion, how much could we do, and what's the usual time it takes to carry that out?
The 2 KTA is simply an enlargement of the manufacturing block I already have. I’m able to add a further 5 KTA as well, and for that we’ve already completed some of the infrastructure work. The 2 KTA takes between 9 and 12 months. The additional 5 KTA, I’d say, perhaps 15 to 18 months. If we need to go past that, once again, we still have room at Pakhajan. We could, one more, say, 18 months or so, if we have to go beyond 10 KTA.
My apologies for cutting in. Could we ask Mr. Periwal to please get back in the queue? There are participants waiting for it.
Of course. Of course.
Thanks. Our next question comes from Rohit Nagraj at 361 Capital. Please go ahead.
I appreciate the chance to ask. To start with, after every project is finished by FY 2027, what would the gross block probably look like? Regarding the INR 1,500 crore of debt at peak levels, what average cost of debt are we looking at? Thank you.
Gopi, do you want to take that one?
My apologies. Could you please ask that again?
Right. So by FY 2027, once all the CapEx is fully in place for both the legacy business and the new Battery Chemicals business, what gross block should we expect to see? And on that peak debt of INR 1,500 crore, what would the average cost of debt be?
The average cost of debt is going to vary, since every one of our interest rates is variable. Certain ones are tied to the repo rate, and others are tied to the MCLR rate. When the interest rate shifts, those things will shift along with it. On the gross block side, we ought to be looking at a gross block of roughly INR 2,000 crore on a consolidated basis. Yeah, it should come in at about INR 2,000 crore.
Okay, just to clarify — so at the current interest rate, the debt cost would land somewhere nearer 7%-8%?
It's a bit higher, since this is a project loan. Typically, project loans carry a slightly higher rate than a standard term loan. Usually, once COD is reached, the interest rates do come down.
Okay, that helps. On the second question about scaling up Battery Chemicals—so from INR 500 crore to, say, INR 2,500 crore—Dr. Harin, you mentioned the ROC we're looking at is 20%. Since that scale-up will occur between, say, INR 500 crore and INR 2,500 crore, will ROC initially come in lower? Because of that, the margins we're expecting from a constant lithium prices standpoint of, say, 20% might be lower at INR 500 crore. Once we reach the peak, margins at, say, current lithium prices would be roughly 20%. Is that assumption correct?
Yeah, just one thing to fix there. I think you said INR 2,500 crore — what I have is INR 1,500 crore for the battery business, covering Salt and Electrolyte together. They're all combined. Just to clarify that point. Yes, you're right that the 20% ROC applies on a stable basis once we're at full utilization. During an intermediate phase such as FY 2027 or FY 2028, it might come in somewhat lower.
Okay, and one final point of clarification regarding Electrolyte and Electrolyte Salt. You said we have 5,000 tons of salt capacity right now, plus there's additional electrolyte capacity. Given the contracts we currently hold with customers, what portion of that 5,000 would get used internally? You also made clear we can either sell Electrolyte Salt or the electrolyte solution. From what we understand today, how much would be consumed captively? Thank you.
Right now, every customer is making that decision. The Indian electrolyte customers are, in essence, also competing with China. Electrolyte does need to be produced locally, and some of them are weighing it: "Hey, if the Chinese electrolyte salt costs less, why not just source it directly from China?" Naturally, a few face constraints owing to their PLI, since they want local manufacturing. Some prefer it for reasons of business stability. That question is somewhat hard for me to answer, because over the coming 12 to 15 months customers will be the ones deciding. That is among the points of clarity we are looking for from the customer. One advantage on our side: if a customer says, "Hey, source it from China," we have a JV partner that already operates a plant in China. From China as well, we can supply them electrolyte salt that is stable, of relatively good quality, and reliable. Together with our customer and our partner, we will optimize. As far as we are concerned, if we sell both the electrolyte and the salt rather than consuming it internally, then with the same investment the revenue potential could be even greater.
Naturally, in such a scenario, the total margin and the ROC on the electrolyte side may come out somewhat different. On the whole, I believe it should still be a positive. That's a matter the customer will decide. It's hard to give an answer. Once we respond to that question, we'll also be responding to her next capacity increase, since if that comes to pass, we'll certainly require capacity by FY 2028 and FY 2029, when we reach full utilization on the electrolyte side.
Understood, sir. Appreciate all the clarification, and best of luck.
Thank you. The following question comes from Tej with Nevesher. Your line is open. Hello there—can you hear me? Yes, we can hear you. Go right ahead. Thanks a lot for the chance to ask. Just one question from me. You mentioned that beginning next year, additional demand will arise from suppliers examining the non-FEOC supply chain. What I'd like to know is this: suppose a supplier purchases electrolyte from a source outside China but still, say, has to depend on a Chinese line or, let's say, Chinese lithium carbonate—would that count as FEOC, meaning non-compliant? I just want to get clarity on that.
Right. To be fully compliant, the whole critical mineral supply chain has to be free of foreign entities of concern. So in that situation, how would the — I mean, how would OEMs manage? I mean, how could manufacturers in India comply? From what we understand, everyone setting up a plant has Chinese lines, correct? And the sourcing is from China. So in that case, how does FEOC compliance help us? This is a U.S. requirement. Companies selling in the U.S., to get the benefit, they must meet the non-FEOC requirement. Still, it's more relevant to our Electrolyte Salt business. For that business, this policy matters, since we're trying to sell into the U.S. supply chain. For our Indian customers, some of whom have ACC PLI localization targets, electrolyte and how much salt we produce becomes relevant again for them, because if I make it from scratch, the localization percentage is much higher. If I'm getting, say, salt from outside and mixing it in India, then I'm making the electrolyte here, and the localization percentage is lower.
That's going to vary based on where the customer is localized. It applies only to localized customers seeking localization and holding ACC PLI benefits. As for non-ACC PLI, currently there's no distinction. The government has committed to reviewing import duties on cells and cell components in 2026. Our sense is that with the supply chain and production now coming in, there will be some form of protection or support for Indian cell manufacturing and cell supply. We're actively responding to customers and to government policymakers, and through our association, we're making presentations. We're hopeful that we, along with cell producers, will receive some kind of additional support to ensure India can have a fully backward integrated supply chain for cell production. Okay. Got it. Got it. Great. The last question is, correct me if I'm wrong. I read somewhere — I mean, the players would, let's say, choose a local supplier because, let's say, for electrolyte to come from China, it would take roughly one, one and a half months. But then the properties of electrolyte change, right? So that's why local suppliers would prefer a local supplier. Is that understanding correct? Yes. Typically, electrolytes have a shelf life of about three months.
Also across this 3-month period, there is a certain amount of degradation. Strictly speaking, if you examine most of the large cell manufacturers, they use up electrolyte in 15 days. Ideally, Indian firms would want to do the same. Okay. Perfect. Perfect. Thank you very much, sir, and best of luck.
Thanks. We’ll take the next question from Jason Soans at IDBI Capital. Jason, please go ahead.
Thanks for the follow-up. I just want to get clarity on one fundamental point. You mentioned that lithium salts come in from China cheaply — at a very low rate, I mean. I'd like to know whether you are bringing lithium salt in from China, and then, if the other ingredients are added and this electrolyte solution is produced, could a player with a large pocket do that in a cost-effective and simpler way, let's say? If it's relatively simple, then what advantage does the MUIS technological type give us? Because my understanding was that having the MUIS type in place should have created a strong entry barrier for us when it comes to making the electrolytes. I just want to weigh both of these things. If the salt is imported from China, is it very cost-effective for a player with large pockets to make electrolytes?
Producing electrolyte is the area where Mitsubishi's technology is applied. Electrolyte quality hinges, naturally, on raw material quality as well as on how well the electrolyte is produced, right? What sets us apart is the manufacturing process. Should another party produce it too, again, mistakes would arise, or at times the process would lack efficiency. Manufacturing costs can also climb. That is exactly where Mitsubishi's technology plays a role. Those are two separate questions.
Right. Understood, sir. So your point is that the quality — naturally, the MUIS technology is going to give you improved quality along with a stronger likelihood of approval. Is that what you're getting at? That's the advantage. In essence, that's the source of the edge. All right. Got it. Got it. Appreciate it. Appreciate it.
It will also bring us greater productivity. Their process is highly efficient across 30 years. So, in fact, operating costs can be lower too when compared with some years.
Sure. Sure. Thank you.
Thank you. Ladies and gentlemen, that was the final question for today. I'd now like to hand the conference over to management for closing comments.
We appreciate everyone being here today. We believe all of your questions have been answered. If anything further comes up, our investor relations team can help. Thanks for spending time with us, and we look forward to speaking with you again next quarter. Thank you. Good evening to all of you, and have a great day.
Thank you. On behalf of Neogen Chemicals, ladies and gentlemen, that brings this conference to a close. We appreciate your participation, and you can disconnect your line at this time.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Neogen Chemicals Limited transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Neogen Chemicals Limited earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.