Northland Power Inc. (NPI) Earnings Call Transcript
November 13, 2026
Earnings Call Speaker Segments
Good morning, and thank you all for joining us today. I'd like to start by going over the strong fundamentals we're seeing across the power sector and what they mean for Northland. Then I'll hand things over to Jeff, who will take you through the quarter's financial results. After Jeff is done, I'll come back to discuss our progress on our priorities and where Northland's next phase of growth is headed. This morning we also put an investor presentation up on our website, and it offers more detail on our growth focus areas as well as a few other subjects we'll cover on this call. Let me start with what's ahead. The opportunity in front of us is clear. As of Friday, November 13, 2026, four decades in, Northland has never seen fundamentals this strong for electricity. Demand keeps accelerating across our core markets, and several structural drivers are converging at the same time. Economies are electrifying. Data centers and AI are creating new sources of large-scale power demand. Industrial growth adds further demand. Beneath all of this sits a stronger driver, energy security. The need for resilient domestic power systems is pushing demand higher. Taken together, these forces are fundamentally changing how much electricity our economies require and the infrastructure needed to deliver it. In Canada, electricity demand is projected to double by 2050, driven by economic growth, industrial expansion, and electrification. For the past ten years, this nation has not invested enough in its power infrastructure. As a result, meeting the higher demand will require a substantial nationwide build-out of new generation, additional storage, and grid infrastructure. That represents an exciting opportunity. The same kind of structural change is taking place in Europe. During the summer, the EU introduced its Electrification Action Plan, and it aims to double the portion of final energy consumption that electricity accounts for — from 23% at present to 46% by 2040. In October, meanwhile, European natural gas prices reached EUR 100 per megawatt hour, which had not happened since 2022. This highlights the volatility that arises from continuing geopolitical tensions. Gas is a major factor behind power pricing in Europe, and that's evident in the elevated prices Poland and Germany have seen lately. The push for electrification, industrial competitiveness, and energy security is creating demand for additional generation, storage, and grid infrastructure within Europe; this chance, in both Europe and Canada, isn't dependent on any one technology. Power systems require additional wind, additional solar, additional storage, together with gas-fired generation, and Northland is strong across all of those areas. Over 39 years, we have built Northland by developing intricate energy projects and converting them into top-quality operating assets; we originate and spot opportunities. We assemble capital and partners. We steer through complexity, and we deliver safely at scale. That know-how carries over from one technology to another for us. We’ve worked across offshore wind, onshore renewables, energy storage, and gas-fired power, and that mix lets us pursue whichever technologies best match the needs and opportunities in each of our core markets. So at this stage, we pair that know-how with strong ties to governments, suppliers, lenders and, above all, our partners. It’s unusual for one company to achieve all of this simultaneously: technological expertise, deep market roots, local strengths, and the capacity to deliver complicated projects at scale and to a high standard. This platform gives us options, and we apply them with care—committing capital only in chosen cases, concentrating on areas where we have a clear edge and where we think the potential for strong returns over time is greatest. That enables Northland to convert rising electricity demand into stable, long-term growth and shareholder value. As of Friday, November 13, 2026, we keep performing well this quarter. I’ll now pass it to Jeff, who will walk you through the financial results, and afterward I’ll return to talk about what we’ve achieved on our priorities and how Northland is being positioned for the growth ahead.
Thanks, Christine, and good morning to everyone. I’ll go over our Q3 results and give an update on the investment program. First, adjusted EBITDA came in at CAD 280 million, which was 9% higher than the third quarter of 2025, thanks to initial contributions from Hai Long and Baltic Power, together with increased revenue at our natural gas facilities. Wind resources were above long-term averages this quarter, but they were lower than the strong winds seen in 2025, and that partly offset those positive effects. The quarter was also affected by an export cable outage at Gemini; we finished the repairs successfully in September, and the project is back to full operations. After insurance proceeds, which we expect by the end of the year, the net impact of the cable outage on our full-year results should be immaterial. Free cash flow was CAD 15 million, or CAD 0.06 per share, versus CAD 0.17 in the same quarter last year; that is mainly due to the lower European offshore wind generation I mentioned earlier. Net income for the quarter was CAD 201 million, compared with a net loss of CAD 456 million in the third quarter of 2025. As you’ll recall, in 2025 we recorded a non-cash offshore wind accounting impairment. We are reaffirming our 2026 financial guidance, with adjusted EBITDA expected in the range of CAD 1.45 billion to CAD 1.65 billion and free cash flow per share in the range of CAD 1.05 to CAD 1.25 per share. That reflects the ramp-up in Q4 production as Hai Long and Baltic Power move into operations. On the investment program, we reached commercial operations at Jurassic BESS ahead of schedule and under budget. Baltic Power and Hai Long are both generating cash flows and moving toward full commercial operations, with costs in line with our original expectations; in July, at Hai Long, we completed a 20-year, CAD 2.4 billion debt refinancing that strengthened the project’s capital structure and lowered our cost of funding. Also in the quarter, we closed financing for our two Poland battery projects, totaling CAD 185 million. Both projects are expected to come online and contribute to our 2030 targets. At the end of the quarter, Northland had access to approximately CAD 800 million of available liquidity, including CAD 80 million of cash on hand and more than CAD 700 million of available capacity on our corporate revolving credit facilities. Importantly, Northland’s results are largely shielded from the rising rate environment, since almost all of our consolidated debt is either fixed rate or has been hedged over the next 10 years, which exceeds the anticipated duration of a typical tightening cycle; on capital allocation, every project competes for capital. We evaluate growth investments against other opportunities to create shareholder value, including share repurchases and further strengthening of the balance sheet. That fits with how disciplined we are: any new investment has to clear our 12% levered after-tax return threshold. Given our investment-grade credit rating, we're in a strong position to carry out the growth plan, and this capital discipline is what supports it. At this point I'll turn it back to Christine for the growth update.
Thank you, Jeff. Northland is at a pivotal moment. We are finishing up the major construction work we've had underway, turning years of investment and excellent execution into enduring cash flow, while also creating capacity for the growth phase ahead. That is exactly what the five-year plan we shared at Investor Day last year is built around. Energize 2030 has three priorities at its heart: deliver, strengthen, and grow. They don't happen one after another. All three are moving forward simultaneously, and each one boosts the others. Delivering well makes the company stronger. A stronger platform helps us execute and creates additional room to grow. Growing with discipline generates the next wave of cash flow and value. I'll start with deliver. In many ways, our record tells the story on its own. Across the four big projects we've completed most recently, we've hit the mark on all four, and a couple of them were industry firsts. Let's walk through them one by one. Both Oneida and Jurassic BESS finished ahead of schedule and came in under budget. The two offshore wind projects we have are still progressing as planned; that kind of execution strength is a key competitive edge for Northland. Getting large-scale infrastructure delivered on time and within budget is extraordinarily hard. Around the world, less than one major project in ten manages it. That's what makes four for four so remarkable. A single success could be chalked up to luck, and two might be explained by circumstances, but landing all four speaks to discipline and excellence in how we execute projects. At Northland, we apply that to every project we take on. When it comes to executing and operating projects, we rely on three pillars: strong partnerships, agility, and empowered project leadership. Let's start with partnerships. Big infrastructure projects need capital and specialized expertise. Our joint venture model combines both, and our partners collaborate with us to share risk, merge complementary capabilities, and deliver outstanding projects. As an operator, the real question is how we unite those partnerships. We function as a single team alongside our partners, we involve our contractors and suppliers, and everyone is aligned on a common objective. That's significant, and it's a major differentiator when it comes to delivering large-scale projects. Second, we tackle these big things with agility; we adapt quickly when circumstances change. Let me give you an illustration involving Baltic Power. While we were progressing through the build phase and bringing the turbines into commission, a vessel that our program depended on suffered damage during work on a separate project. That was completely beyond our control and totally unexpected. It opened up a risk of disruption to our construction timeline. Our team acted swiftly; we coordinated with our partners, with our suppliers, and with additional suppliers in our networks that we know, and we secured a replacement vessel arrangement very fast; we revised the execution plan so it would fit that different vessel, and above all, we kept the project on track. That capacity to spot the problem, decide fast, and adjust on the fly—that's agility in practice, and it's essential to how Northland carries out complicated projects. The third element involves handing project leaders genuine authority. Our project directors come with experience, they hold clear accountability, and they can reach senior leadership directly; those closest to the work are empowered to make swift decisions, resolve issues as they arise, and keep execution on schedule. Hai Long shows this method in action. When slower turbine commissioning created a revenue shortfall prior to completion, our teams responded across multiple fronts; we raised technical performance in the field. We extended the revenue contract. We completed a refinancing of the project debt, and overall we've strengthened the project's long-term worth for shareholders while keeping it on schedule. Alignment among partners, fast choices, and clear responsibility—that's the Northland way of executing; throughout this quarter we continued hitting key milestones across the portfolio, bringing major projects closer to finishing, adding new capacity to the grid, and advancing the next round of investment. During the quarter, Jurassic BESS achieved full commercial operations, coming in ahead of schedule and under budget; in Poland, Baltic Power reached first power and we completed installation of all 76 wind turbines. Right now, over 70% of those turbines are generating electricity, and we anticipate the rest will be doing so by year-end; construction has also begun on both battery projects in Poland. Turning to Taiwan, we've completed installation of Hai Long successfully. With turbine installation and energization finished, all 73 turbines there are now delivering power to the grid as of today. We're awaiting final approval from the authorities prior to handing the project over to operations. That's a tremendous accomplishment by the teams. A track record of excellence in execution makes our business stronger and expands our capacity to invest in what comes next, and that leads me to strengthen. We continue to reinforce the financial and organizational base that supports our strategy; we maintain investment grade ratings of BBB stable from both credit agencies. More than 95% of our revenue is under contract, and the weighted average contract life is approximately 14 years. As Jeff mentioned, we have for the most part reduced our exposure to increasing interest rates. That gives us a solid foundation for our 2030 investment plan. During Investor Day, we set out roughly CAD 6 billion of gross investment through 2030. An estimated 75% is anticipated to come from project debt, while Northland's capital and our partners will fund the rest. Capital recycling is an additional tool within that funding plan. Our goal is roughly CAD 300 million in net proceeds, focused toward the earlier part of this plan, and over the coming 18 months we see chances throughout the portfolio to achieve that. Timing will remain disciplined, however, and we'll recycle capital when value looks attractive, directing the proceeds into our growth projects that create value. The aim is straightforward. We direct our capital to its highest-value use, and we apply that same strength and discipline to our cost base. At Investor Day, we pledged CAD 50 million in yearly savings spanning G&A, development, and operating costs by the close of 2028. We’re making solid headway on that, and we anticipate those savings will start showing up in our results in 2027. We’ve also made the organization stronger around execution. In the quarter, Lyla Garzouzi joined us as Executive Vice President, with responsibility for health and safety, sustainability, and strategy execution. Lyla has over 20 years of experience in the energy sector, including senior leadership roles at Hydro One and Parkland. Making strategy execution part of Lyla’s mandate was deliberate. As we move into our next phase of growth, accountability, alignment, and disciplined execution throughout Northland are essential, and our Northlanders are at the center of that. During this year, we made multiple moves aimed at bringing the company in line with our expansion strategy and with the people who hold stock in us. As part of that second goal, we introduced a program letting employees buy shares. Here at Northland, acting like an owner is already something we expect of everyone, yet now the people of Northland can actually be owners and share directly in the value they build over the long run. That brings us to the following pillar, which is growth. When it comes to growing, our method is simple.
Our focus is on the core markets of Canada and Europe, where we hold operating assets, have experienced local teams, possess market knowledge, and maintain established relationships. This allows us to move more quickly and deliver stronger returns. At last year's Investor Day, we set a goal of adding 1.4 GW to 1.8 GW of new capacity by 2030. As of today, we have line of sight to at least 90% of that goal. Construction is underway on 300 MW, and a further 900 MW has progressed to our mid-stage development stage gate and remains on track for development by 2030. Significantly, a large portion of that growth stems from building on assets we already have. Let me walk you through a few of the projects we are working on right now. First, we are focused on extracting more value from assets already in our portfolio, which at Northland we refer to as value enhancement initiatives. We are pursuing this through two main avenues: hybridization in Europe and repowering in Canada. In Europe, the rationale for investing in batteries and hybridization is straightforward, especially in markets where renewable penetration is high. Wind and solar generate power when the resource is available, not necessarily during the hours when power is most valuable. Storage shifts that energy to the hours when it is worth more. It also provides access to capacity and ancillary service revenues that wind and solar on their own cannot capture; this is a technology we understand well. We have demonstrated battery storage experience and a track record of delivering these projects at or under budget and on or ahead of schedule. We are bringing that capability to the renewable assets we already operate; in Spain, we are advancing nine co-located battery storage projects totaling more than 250 MW and 1,000 MWh across our existing renewable portfolio. Every project sits alongside wind or solar that we already operate, using grid connection and land rights we already hold. The market need is evident. Spain is aiming for more than 60 GW of additional storage capacity by 2035. We see further hybridization opportunities at our Gemini offshore wind facility in the Netherlands. There, together with our partners, we are advancing 100 MW and 400 MWh of co-located battery storage. Gemini holds a structural advantage because at that project our grid connection lands onshore, so our storage can use the same grid access as the offshore wind farm. With this battery at Gemini, we can shape a portion of the output from the 600 MW offshore wind farm, creating a quasi-firm power product for part of that production; this project also unlocks additional revenue streams, including capturing price spreads and grid and ancillary services that wind alone cannot. This is pioneering work. Northland expects to be among the first operators globally to pair large-scale offshore wind with co-located battery storage. In Canada, we are applying that same value enhancement mindset, but the focus there is on repowering. The concept is simple; we are replacing older equipment at sites we already operate with newer technology available today, so we get more from the infrastructure we already own. Repowering extends the life of assets; it requires little capital and takes less time. That's growth with solid returns. What helps is that a lot of what's required already exists. Because land, grid connections, and operating infrastructure are in place, development can follow a simpler path and deliver appealing returns versus beginning from zero. Currently, nine solar repowering projects are moving forward in Ontario. Since these facilities were initially constructed, technology has come a long way. Modern panels and inverters generate more power from the same land and grid connection, and most of the original development cost and risk now sits behind us. Combined, hybridization and repowering offer a capital-efficient route to growth by extracting more value from assets we already hold. We also plan to push ahead with onshore greenfield projects. In Alberta, we responded to shifting market conditions by turning a solar project already in development into a standalone battery storage project, creating new value through a strategic change in design and market opportunity; regional grid congestion and a developing storage market are driving this, and we're building on what Jurassic BESS in Alberta has achieved; it shows how at Northland we draw on our established market presence and technical expertise, together with agility in thinking and project execution, to chase growth opportunities. We continuously look for and capture new opportunities where market needs match our capabilities. Nova Scotia offers another strong illustration. The province requires additional power and is running several procurements to close capacity gaps beginning in early 2027. Demand is rising, infrastructure is getting older, and added capacity is needed to support the evolution of its power system. That opens an opportunity across all the technologies Northland excels at. We've established a position there. During this quarter, we added roughly 350 MW of mid-stage development opportunities in Nova Scotia. What makes Nova Scotia attractive to us is that our core technologies can operate together within one market. Onshore wind can deliver renewable generation into the system, storage can move that power and add flexibility, and gas can supply reliable capacity when needed. Looking further ahead, we see a chance for offshore wind to contribute generation at scale. As one of the world's leading offshore wind developers and operators, Northland offers deep expertise and an outstanding track record in offshore wind. As a Canadian company, we would be glad to bring that expertise home. We have been actively working with governments to create the conditions that unlock commercial investment, applying lessons from our global experience. We gave feedback that developers such as us require clarity on the commercial and regulatory framework to properly evaluate opportunity and risk. We also gave feedback that technical information is needed so we can make informed investment decisions. That's why we welcomed the Government of Canada's CAD 100 million commitment to offshore wind readiness in Nova Scotia. Putting money into that underlying resource along with site data matters a lot if we're going to unlock this fresh opportunity for Canada. More work lies ahead, yet we genuinely see long-term potential across Atlantic Canada, and in our view Northland holds the strongest position to deliver on it. Zooming out to offshore wind as a whole, we remain a leader there, with 3.5 GW under construction and in operation spanning four countries. What sets us apart is an outstanding record of carrying big, complicated projects all the way from development through financing and construction and into operations that are safe and successful. We constructed Asia's largest offshore wind project, and Poland's first as well. Both of those were delivered to a world-class standard; in the U.K., we keep moving our Spiorad na Mara project forward through consenting and at the same time hold on to flexibility regarding timing and capital commitment, and we keep looking into other exciting offshore wind prospects around Europe. As I mentioned at the start, what lies ahead isn't tied to any single technology. With electricity demand rising, power systems require additional generation and additional storage. They also require capacity that is more flexible and reliable so the system stays balanced; that leads me as well to the capability Northland has held longest, namely natural gas-fired power. We have run gas generation in Canada for decades, and right now we see opportunities inside our current portfolio and also via new greenfield development.
There's re-contracting upside at the Canadian sites we already own, because the plants, the grid connections, and the operating teams are already there. Beyond that, we see greenfield opportunities in Eastern Canada, Western Canada, and Ontario, including our 120 MW Collisard project in Alberta. Also during the quarter, we closed the financing for our 2 Poland battery projects totaling $185 million. The value proposition here is straightforward. As more variable renewable generation comes onto the system and electricity demand climbs, the need for dependable capacity climbs with it. Data centers, of course, are another factor driving that demand growth for gas-fired power; we've had many engagements with hyperscalers, and interesting opportunities seem to be emerging, though we remain disciplined. What we need is creditworthy counterparties, suitable contract structures, and returns that compensate us for risk. Capital discipline comes first, and we're seeing some positive momentum there; multiple growth opportunities lie ahead of us, and, as I said at the outset, the fundamentals for electricity demand are the strongest our sector has seen in nearly four decades. Northland is ready for this opportunity; the team, the capabilities, the market positions, and the discipline are all in place. Deliver, strengthen, grow. That is the path to 2030, and we're confident in our ability to execute and to create value for shareholders. That concludes our prepared remarks, so operator, please open the line, and we'd be happy to take questions.
Morning, everyone. That revised growth forecast makes the prospect of 350 MW of development and investment in Canada genuinely exciting. Christine, given that Canadian projects have historically struggled to compete with returns on offer elsewhere around the world, could you break down the risk-adjusted return dynamic and explain how your thinking has shifted since last quarter?
Thank you, Baltej. Throughout all of this, I'd say our thresholds have stayed the same. Every project has to compete for capital. When stronger returns can be found in other locations, that is where our money goes. Even so, our teams have done an excellent job identifying opportunities in Canada that we think will hit or beat our return thresholds. To be candid, I laid down the challenge to them. This year, all of us on the investment committee collectively laid down that challenge: we want to put money to work in Canada. When I was at the Canada Investment Summit earlier this year, it was clear that thinking within Canada has shifted too — there's a recognition that the country needs to build. We see that need, and we understand that for capital to be deployed, the returns must make sense for everyone who deploys it. That change in tone from Canada's leadership is an encouraging sign. It's encouraging that the teams have managed to surface project concepts meeting our criteria, and that shifts my outlook on Canada in a favorable direction. Naturally, results will tell the story—as these initiatives progress, they'll need to secure a final investment decision and satisfy what we require. I'd say my optimism on this front is stronger right now than it has been in quite some time.
Great. Now shifting to the Spanish hybridization for batteries, which you've brought up a few times. Which key milestones are still outstanding for that ahead of a potential FID in 2027? And on the return threshold, how much does the FID decision hinge on securing capacity payments through Spain's newly established capacity market mechanism?
Baltej, when it comes to hybridizing our existing sites, a capacity contract isn't something we depend on, because in effect, hybridizing our own sites creates a firmer product, if I can put it that way, since it means we then capture price arbitrage on our own electrons. Our baseline model would have us producing those electrons into the grid at a contracted price, whereas here we can sell those electrons at better pricing opportunities. In Spain, that's what provides the uplift, and we find the rates of return very attractive. Even more important, the Spanish grid requires more storage to deliver for the people of Spain. It's a nice convergence of two things there: it helps our returns, and it also helps the system. So as far as being able to move those projects forward, they have been advancing throughout this year. The teams have done very good work; so our stage gate process for triggering the final investment decision is really about making sure all the technical requirements are satisfied from a commercial feasibility perspective and our grid conditions. We make sure all the permitting is in place, and we don't see any showstoppers there. So it's really just making sure then that we have the right technical solutions and that our supply chain will deliver on the terms we expect. On all of those things, I don't see any yellow flags at the moment. The teams are moving forward, and the projects are advancing well.
All right, that's great. Appreciate it. I'll hand the line over and follow up with you afterward.
Thank you. Morning, everybody. Christine, I appreciate the thorough rundown on the new 900 MW of mid-stage projects. To build on what Baltej asked, the hurdle is a 12% levered IRR. Could you help us understand what range of project returns you'd anticipate from these new projects? I'm simply trying to get a read on how wide the spread is, from the lowest to the highest return, across this new portfolio.
Yes, this is Jeff, and Christine will likely add more detail. My framing, and you can see this especially in the front end, is that it's essentially more weighted toward batteries. Our investment focus is really that hybridization, where we hold physical exposure in production. As Christine described, in that setting, making a quasi-firm product, or getting as close to one as we can, actually drives realizations and gives you a more consistent revenue stream. That said, the larger the merchant share in battery, the more we'd expect to rise above that floor and reach into the teens. Obviously, you'd want to see a faster, I'll call it straightforward, payback on those. My way of looking at it is that something onshore, with lower execution risk and contracted, would clearly sit near the bottom end of the range. Then, as we go up with greater merchant exposure, we need a quicker payout and would lean more into the teens.
Yes, Jeff, I think that's a reasonable way to frame it. Fundamentally, I'd say we've been examining batteries for some time, but the constant issue is whether we have the appropriate products on hand, and whether we can actually deliver within a timeframe that makes sense. Now that we've demonstrated such strong execution on our two major battery projects, and now the two currently being built in Poland, that gives us considerably more confidence; so the business case is evident, and we also recognize that it's electricity's intraday pricing that genuinely creates the difference, clearly, when it comes to batteries. If you look at the Spanish market specifically, the price at peak hours versus the price at low hours shows a fairly substantial delta between them. I believe that's simply a consequence of having substantial renewable generation on the grid. So we just see quite a strong opportunity space there for us, and we're proceeding with those at pace.
Thank you for that, Christine. A follow-up on asset recycling. You mentioned the CAD 300 million in proceeds that you expect will help fund the build-out through 2030. EBSA delivered a solid quarter. Part of that came from currency, though some of it also appeared to be healthy rate-based or asset-based growth. Could you talk about how that could tie into the asset recycling plans, and more broadly, what might be a target for an outright sale or a partial sell-down?
Well, we won't discuss the specifics of what we're doing on that, but overall, I would say we have a capital recycling goal. I referenced the CAD 300 million earlier. As we look across the portfolio, we see opportunities where, as we've discussed before, assets have other better owners, and those other better owners should probably have them. We also see that we have more value accretive places to deploy our capital, and we would like to be able to redeploy that capital. We don't comment on which assets are in that process, but we do see line of sight to being able to execute on that over the coming 18 months.
Yeah, Sean, I think it really boils down to wanting more than one option available; we've discussed where the capital is headed under our plan in Canada and Europe. There are other elements as well, obviously, as we get closer to COD and operations on certain projects, there's an opportunity to, shall I say, unlock some funds from some of these projects as they come through. Every bit of that plays a role, but we'll be prudent about it, and it always comes back to Christine's point regarding the shareholders, and you want to have several choices. I think we see choices here over the next 18 months.
Nice, thanks for walking us through that.
Good morning, and thanks. One quick follow-up on the Spain battery storage project. I'd like some clarity: is it right that the battery storage projects won't get capacity payments, and that their return will come mainly from firming up power production? Is that accurate?
Nelson, here's how I'd put it: we anticipate a capacity market process taking place in Spain during 2027. That stays on the table for certain players, particularly some of the bigger projects, who may see it as possible upside. The way we've justified these projects economically assumes they're simply linked up as they currently are through the grid connection we already have, and that they wouldn't take part in the capacity auction. I'd frame that as a possibility rather than something we need. The real question the teams had to answer was whether we could advance these projects at this point—and whether the economics justify doing so today, or whether we should hold off until a capacity auction. The economics are plainly favorable at this moment, so we can begin advancing them, put the capital to work, and start realizing returns.
All right. Regarding those projects you picked out, are they the kind that are getting close to the end of their contract term? Or — my understanding is, I'd assume that if projects are contracted, they'll get that fixed return. Could you just clarify whether your focus is on contracted assets, or on assets that could roll off contract and end up more exposed to merchant power prices?
It's a mixture, since we have plenty of sites in Spain. We talk about Spain as if it were one monolithic block, but we have many sites throughout Spain. Each of those moves forward independently; sometimes, as you correctly note, if it's rolling off contract, that's very clear; other times, even when it is contracted, we still can use the battery for arbitrage, and it will be coming off its — these assets do come off contract down the road. There's kind of a combination one-two punch of ancillary services price arbitrage at the front end, and then even more as it comes off contract. Every one of these looks somewhat different, so I appreciate that if you're trying to model it, that's probably not the greatest insight I'm giving you there. But each of them is a bit different, though I'd say across all of them, we see a really clear business case. Maybe we can follow up with you on some details that might help you out with that. But I can tell you that all of them meet or exceed our thresholds.
All right, great. So on gross investment, I understand that within your 2026 to 2030 plan, gross investment comes to roughly CAD 6 billion; but if we look at a specific set of projects totaling around 900 MW that are to be finished by 2030, could you give a rough estimate of the gross investments? For instance, would CAD 2 billion work as an estimate, or would CAD 2 million per MW be a reasonable figure?
Yes, Nelson, this is Jeff. I won't go into each one in detail or anything like that, but you're correct. During Investor Day, we mentioned roughly CAD 6 billion, and as I recall the equity piece was a bit over CAD 1 billion, around that figure. The money for that came from our own internal cash flow; we've got some balance sheet room along with this capital recycling, and we have solid visibility into all of it in order to hit or beat the plan. Stepping back, I'd say the Investor Day plan produced $0.40 of free cash flow growth once Hai Long and Baltic are up and running, and we finished with capacity that doubled. I'd say we're inside that capital envelope. There's nothing here, we're on track to deliver it, and it fits within the capital frame we set out.
I'd like to add to that as well, Jeff: that CAD 6 billion figure also covered certain projects delivering after 2030. I don't want to cause any confusion here today, since we're discussing what can deliver for 2030 within our plan, but naturally the business keeps going in 2031, 2032, and 2033, and actually plenty of projects are coming online in 2031, 2032, and 2033 too. The capital spend we have at present helps support the projects that will deliver year on year beyond that. Not all of that capital is going toward these particular projects.
100%.
All right, just one final point of clarification before I rejoin the queue. Christine, you brought up Ontario solar repowering and the use of new equipment. A lot of those solar sites, as I understand it, are 10 MW sites right now, and you said the equipment will be replaced. Will you basically swap out the equipment ahead of the contract or the EPA expiration, so that you can produce more power under that same contract? Is that the plan?
We're going to replace as soon as we possibly can, because the gain in performance we're seeing is remarkable. As probably many people on the line are aware, the cost has dropped dramatically, so the technology has gotten better and the cost has fallen, so the business case is very clear. We're going to do that as fast as we can, and we simply see it as a good opportunity, and frankly, the province of Ontario needs it. It benefits everybody. We'll execute on that. I would have had it done yesterday if I could, but in the real world that isn't physically possible, so the teams are pushing forward with that as quickly as we can.
Great, thanks. I'll get back in the queue.
Morning, everyone. I'd like to zero in a bit on Baltic and Hai Long. With commercial operations coming up soon, how have those assets been doing when it comes to turning wind into electricity, and on uptime? Is there any operational detail you can share so we can tell whether they're trending below or above plan?
Broadly put, my view is that here at Northland we're expecting the following: the offshore wind assets already in our portfolio deliver very high reliability; as for the newer ones, we expect them to reach that same standard over about the first twelve months of running — it doesn't come about instantly. Nailing that ramp takes the team a while. Every one of those projects also brings in new turbines from Vestas and Siemens. Our people are picking up knowledge and getting the work done on that front. There is a ramp. You're absolutely right to point it out. We're getting solid results on this front, though they're not yet where we anticipate them landing once everything is fully running and we've logged additional operating hours. Some of that simply reflects operators becoming familiar with the equipment and our overall execution on the operational side improving. Shifting out of construction and into operating the assets is a transition we planned out quite intentionally, and that transition is happening right now. From where I sit, everything there is tracking to what we laid out and to our expectations as a business; however, our plans accounted for a ramp-up period, meaning we don't jump straight away to the long-term reliability those assets are expected to reach.
Okay, thanks for that. Let's turn to the Canadian projects, then. Looking at the battery project in Alberta and the Nova Scotia projects, could you give us a bit more detail on the contract durations you'd be targeting, whether you'd be open to taking on some merchant exposure in Alberta, and roughly where those would sit against your typical capital returns profile?
I have to wonder whether you're actually sitting in on our investment committee when you pose a question like that. Our teams bring forward several proposals for how they view the revenue stream, especially for large standalone BESS projects. They always come in, and I've mentioned on prior calls that I like a portion of that to be contracted, but the teams present scenarios with more or less contractedness, adjusting up and down based on what we expect in the market, what happens with renewable penetration and battery penetration. There are a lot of moving parts as we model these. But the bottom line, to cut through it and keep things simple, is that we need to see this is the best place to put the capital. So if risk is going to be higher, we need to see higher returns. If risk is lower, then we're closer in to 12%. That's why, when we talk about risk-adjusted returns of 12% +, every team that comes into investment committee always wants to know what the bright line test is. The reality is that the only bright line test is you have to be 12% +, but how big the plus is will depend on the risk profile and how well you understand your market.
Yeah, Rob, I would say we discussed hybridization and the places where we have physical production. I think, directionally speaking, if you look at the Canadian batteries, I would expect a bigger capacity component and a shift in the opposite direction, just to steer it a bit, it's more of a continuum, but considerably more toward the capacity side.
Yes, I’m with you on that. Canada’s market isn’t like Europe’s; it’s simply a separate market. In many—actually, every—location where we operate, including Canada, it isn’t a single market. It varies from one province to the next. I believe the key point is that we have many different models, which is why relying on one bright-line test isn’t the right approach.
Okay, thank you.
Thanks. Morning, everyone. To follow up on the battery projects, especially the hybridization ones, could there be a chance to install batteries that ultimately enable a corporate PPA? I'm just wondering, Jeff, how you're thinking about financing these projects. Is it possible to place project-level debt on them right from the beginning?
Let me handle the first part of that question and say yes, adding the batteries, I believe, essentially makes these projects sturdier and more resilient across the long run. However, we can't hybridize in every location. Wherever hybridization is possible, we are essentially evaluating it, and the business case is obvious that in nearly every location where it's feasible, we ought to, so we do. But it's because this does generate a different profile for the electricity output. That's what interests us. So you're absolutely right there, Mark, regarding how we're handling it with batteries. Sadly, for certain assets, you lack the option to hybridize at the site. In that case we do examine whether we'll place batteries somewhere else within that same market to create a sort of synthetic firm power. We're evaluating that. It's a somewhat more complicated investment choice, but that too is being considered in certain of our markets.
On the debt side, I’ll step back a bit: obviously, when your merchant percentage is higher, that affects your capacity to place project debt at a given level or gearing ratio. Even so, we need to be prudent regarding how much we commit there so that we retain sufficient equity to handle, say, intraday volatility. As Christine mentioned, overall we do see this lowering the risk profile across the portfolio. I don’t want to get ahead of all that, but you’re right—effectively, if you look at contracted near in, our plan included roughly 75% debt funding across the entire CAD 6 billion we discussed. Clearly, it would be below that, precisely because merchant exposure is higher, yet that remains within our funding plan, and we’ll be prudent about it and provide an update in due course. Still, it’s all a continuum, and in many cases, if you have a quick payout and we see the intraday spreads there, it might be something where you use a higher equity percentage than you would ordinarily expect.
I suppose I'll just.
All right.
— ask a follow-up once more, since you brought up corporate PPAs, and naturally, we've got a solid track record with corporate PPAs; we remain in talks with prospective off-takers regarding a large share of what we produce. Whenever we look ahead, we're continually weighing the choice of re-contracting against PPAs against keeping merchant exposure. So our teams assess that all the time, and as a company we watch it carefully to determine what the proper balance is there, and that answer will differ throughout the portfolio, simply based on market conditions.
This simply gives us greater commercial flexibility, since you’re able to provide various tools to various off-takers, so it’s just much more commercial flexibility, and it strengthens the deepening into the core markets.
I'm also wondering about bringing in projects at the mid to late stage — for example, you bought those assets in Nova Scotia, and you did the same with the battery projects in Poland. Do you see additional opportunities of that kind, and how do you find them while still meeting the target return threshold you need to meet?
I'm glad you raised the question about what the market looks like right now, because we actually see a large number of opportunities that match that description precisely. What we like is entering a project where teams are already doing excellent work originating in the early phase and carrying things through the early stage of the project. But when it comes to actually procuring, constructing and financing the project, that calls for a skill set in which Northland is especially strong. We do see that in some cases companies wish to remain involved from that point as part of the process, while others simply want to do the origination and then step away, redeploying back into new origination. Both models suit us, but we are constantly screening, and we see a fairly healthy pipeline of opportunities there. We are highly selective. I'd say that for each one we do, there are many, many more we have declined; obviously we never discuss the things we have turned down along the way, but across the year, even among those that reach our investment committee, not every one gets through; still, I know the teams screen and investigate quite a few. It forms part of the funnel for us because, naturally, where we see those opportunities and they represent a better use of capital, we will deploy into them, even ahead of things we might have originated ourselves. Again, it's the best way to deploy capital and achieve the best return. But stay tuned there. You will see more in that stream.
Just following up on what you said last, Christine — should we take it, then, that reaching the 2030 targets means those kinds of projects, picking off the advanced ones, are probably among the most workable routes to get there, rather than origination, which might take a bit longer in development timeline?
I'd say we have both. We've discussed this — we've effectively found enough to hit the target as things stand, and beyond that we have far more that simply isn't yet at that magical development stage where we'd start talking about it. But we have plenty of opportunities that can get us there. Outside the company, we're also still screening opportunities that could fit that. I'd say it isn't a preference; it's just that the best opportunities are the ones where we'll deploy the capital.
That works for me.
Hello, and thank you. Good morning, everyone. I'd like to begin by discussing the growth pipeline. It declined a bit, to 7.4 GW versus the prior quarter, and you're putting in a couple hundred megawatts of Canadian additions. Could you share what dropped out of that figure? Did one of the Scotland projects get removed from it?
Ben, this is Jeff. I believe it's closely connected to something Christine has addressed on earlier calls and, I think, hinted at again here as well: we always run an internal contest for capital, or high-grading, essentially seeking to bring things into the portfolio while killing projects. What I'd say is that where it really came from was high-grading the Canadian development pipeline. We identified the opportunity emerging in Eastern Canada, we high-graded the portfolio, and then we let other options go because we simply didn't see capital being allocated to them. That's essentially what happened, and it all sits within that Canadian onshore.
Let me build on that a little, because I genuinely value the question and I've gone over it several times. That top-line number for the overall pipeline is bound to move, since we carry a lot of early-stage concepts, but not all of those early-stage concepts can or ought to make it to a final investment decision. Even if they're strong projects, they may be strong projects with metrics that don't suit us, or a risk profile that doesn't suit us, or that are located in markets that don't suit us. Several factors could explain this: perhaps the market had it right before and no longer does, or perhaps we're staking a claim in a market that isn't right at present but might be shortly. Every one of those elements keeps shifting within the pipeline continuously. That partly explains why, in the reorganization we carried out under the strengthen phase of deliver, strengthen, grow, we consolidated all development spending beneath a single umbrella, led by one person who holds a seat at the executive table. We're extremely deliberate about where our DevEx spending goes—directing it toward projects we believe will return the strongest value and preserve future flexibility. The executive committee reviews this regularly to see where our focus and effort are being directed. One reason we've concentrated on Canada and Europe is that it lets those DevEx funds stretch further, and it ensures we're putting energy into what makes the most sense for the company overall. From my perspective, that ranks among the most significant internal shifts we've made to ensure we're truly advancing the strongest value opportunities. Some other assets in the portfolio may not be right for the present moment, yet they certainly belong to a later stage. There are thrilling, excellent prospects out there; they simply need more time before they reach maturity. None of that suggests any flaw in them; it merely indicates that now isn't the appropriate moment for them. You'll notice some shifts within that broader pipeline, since we keep actively developing it. In my view, seeing that pipeline move is a healthy sign.
Understood. Thanks. Perhaps I should return to EBSA, which came up in a question earlier, and I realize you said it had passed—it might be non-core. It is non-core. EBITDA has risen substantially, and performance has been fairly strong compared with at least what we originally anticipated. My thinking is that, going forward, if a monetization of that asset happens, the rate case would be relevant to it. Could you bring us up to date on when EBSA's next rate case is scheduled, and when a decision might be expected?
Yes. Jeff speaking. I'll begin with the current year alone and then move to the rate cases. In effect, what you see here is that we are pushing EBITDA higher; the peso has appreciated against the Canadian Dollar, as I recall by close to 30% year to date, through the end of the quarter. So that has clearly been a major driver of our EBITDA and provided some benefit there. As for the rate case, I would say it is really anticipated around the early portion of 2028, if my memory is right.
I'll just note that the Northlanders who deliver every day in that Colombia utility do a tremendous job. That piece of our business is different, since it's a utility while the remainder of our operations isn't a utility; so yes, it's different, and you're right to flag that. Still, the Northlanders carrying out that work daily are doing us proud. You're right to point out that they're delivering well in an environment where electricity goes right to consumers every day. They're growing the rate base. They're doing a good job. So we're proud of what they do, and they're part of the portfolio.
Understood. Allow me to slip in — pardon me — just one quick question about the free cash flow per share guidance before I continue. It now sits at 9%, up from 6% previously, and that change comes purely from shifting where the calculation begins. Looking ahead, how are you thinking about the timeline? Will you extend it to 2030 or 2031? Will you keep moving the front end of the year forward? How should we frame that?
Yes. Look, this is Jeff speaking. I mean, stepping back, what we did was set out our five-year plan, and we stated that by 2030, we would deliver $0.40 of free cash flow in new growth on top of the $0.80 from the two projects that are close to completion or moving into operations. We stand behind that commitment. But as Christine said, targets have to be continually set further out. Look, cash flow will shift, years roll forward, yet we are maintaining the $0.40 by 2030 and remain on track to deliver it. Then we will come out as we keep advancing the business. Life doesn't stop; it's a giant conveyor belt, and we'll keep setting targets past that over the next couple of years as we go, updating the market at our Investor Days whenever they occur. What I would say is thank you both; we believe in the $0.40. We are not pushing that out. We will deliver it. We are on track for it, and we will establish further targets beyond that to keep growing the business.
Yes, it's absolutely true that our business keeps expanding as time goes on. We're attempting to tie this back to a position we shared last year. During our Investor Day, we discussed the upcoming five years. I'm happy when people want to begin discussing what lies past those five years, since we have a great deal happening within the company and we're a long-term business; we believe the long-term macros are genuinely favorable. The teams have all sorts of projects that will create value past 2030. Still, the near-term emphasis is on the period from now through 2030. You can sense our conviction when it comes to delivering on 2030. Past 2030, there will be additional things. That's what Northland does; that's where we excel.
Okay, that helps. Thanks.
Oh, sorry about that. Christine, since you mentioned opportunities beyond the five years, I want to pick up on that. One slide shows new offshore wind, and Poland is on it. Without naming the obvious project, could you give us an update on your existing partner, ORLEN, and that relationship, and what we might potentially see for future development in offshore Poland?
Baltej, we're reviewing plenty of offshore wind opportunities across Europe. Maybe we don't discuss it enough, I'm not sure, but I'd begin by noting that our capacity to deliver these projects is world-class, and the industry recognizes it as world-class. We see a fair number of opportunities where we could deploy, and we keep assessing them. There are processes underway, and we don't comment on any process that's ongoing, including in Poland or with our existing partner. If you have questions about that process, you should ask them about it. But certainly, I'd say we're active throughout Europe when it comes to reviewing and evaluating new projects. Of course, we have a preferred list of things we'd like to do more than others, but we see lots of opportunity where we could deploy. It's a good place to be. We're lucky to have teams who are exceptional at delivery, and that puts us in this very good situation. Of course, we have our own project in Scotland that we're also progressing, and then we see a number of other projects that are currently held by others but could certainly be within the Northland portfolio in the future.
All right, thanks a lot.
I'll keep this short. Thanks to all of you for being with us today. We appreciate your ongoing support, and we're looking forward to talking with you in February when we report our full year and Q4 results.
This concludes today's conference call. Thank you for participating, and you may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Northland Power Inc. transcript - plus 131,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Northland Power Inc. earnings transcripts and 131,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.