Sigma Lithium Corporation (SGML) Earnings Call Transcript & Summary
March 30, 2026
What were the key takeaways from Sigma Lithium Corporation's March 30, 2026 earnings call?
In the fourth quarter of 2025, Sigma Lithium Corporation reported revenues of $67 million, a decrease of 27% year-over-year, driven by a restructuring of mining operations and a challenging pricing environment. The company generated $31 million in cash from operations, reflecting a 35% increase from the previous quarter. Management maintained a positive outlook for 2026, projecting all-in sustaining costs of $592 per tonne and emphasizing strong cash flow generation, with potential free cash flow ranging from $218 million to $600 million depending on lithium prices.
What topics did Sigma Lithium Corporation cover?
- Revenue Performance: Sigma Lithium reported fourth-quarter revenues of $67 million, down 27% year-over-year. Management noted, 'We achieved $67 million in net sales in the fourth quarter of '25,' highlighting the impact of operational restructuring and market volatility.
- Cash Flow Generation: The company generated $31 million in cash from operations in Q4 2025, a 35% increase from Q3 2025. Management stated, 'This company was built for cash flow generation. We are a cash machine.'
- Debt Repayment: Sigma Lithium successfully repaid 60% of its short-term debt and 35% of total debt in 2025. Management emphasized, 'We paid 60% of our short-term debt and 35% of our total debt.'
- Production Guidance: For 2026, management provided guidance of 240,000 tonnes of lithium production, with an all-in sustaining cost of $592 per tonne. They noted, 'We have estimated that in the next 12-month period for Phase 1, we're going to probably have 240,000 tonnes of production.'
- Sustainability Initiatives: Sigma Lithium highlighted its commitment to sustainability, achieving 'Quintuple Zero lithium' with zero tailing dams and zero hazardous chemicals. Management stated, 'We are 100% sustainable.'
What were Sigma Lithium Corporation's March 30, 2026 results?
- Revenue: $67M (vs $92M in Q4 2024, -27% YoY)
- Cash from Operations: $31M (vs $23M in Q3 2025, +35% QoQ)
- Debt Repayment: 60% of short-term debt (vs previous levels, significant reduction)
- Production Guidance: 240,000 tonnes (for 2026, with all-in sustaining costs of $592 per tonne)
- Free Cash Flow Potential: $218M to $600M (depending on lithium prices)
- Total Debt Reduction: 35% (of total debt repaid in 2025)
Sigma Lithium's Q4 2025 results reflect a resilient operational strategy despite a challenging market environment. The company's focus on cash flow generation, debt repayment, and expansion plans positions it favorably for 2026. Investors should monitor the execution of Plant 2 and the performance of new revenue streams, as these will be critical catalysts for future growth.
Earnings Call Speaker Segments
Thanks for joining us for the 2025 earnings conference call. With me today is Ana Cabral, who serves as Co-Chair and CEO of Sigma Lithium. You can find our earnings press release, along with the presentation and corresponding documents, on our website. Please keep in mind that certain statements made on this call — including production guidance, expected company performance, updates on mining operations, the timing of our projects, and market conditions — may be regarded as forward-looking statements. We'd ask you to review the cautionary language regarding forward-looking statements in our presentation, MD&A, and press release. Before I hand things over to Ana Cabral, we're going to show a brief corporate video, since we believe the pictures will paint a thousand words about what's happening at Sigma.
Hello, everyone. Thank you, Anna, for that video showing our operations. As all of you can surely see, we take enormous pride in what has been constructed here in Vale do Jequitinhonha. So, with no further delay, I will move directly to the fourth quarter 2025 earnings release presentation, which addresses the complete full year 2025 annual financial results. We will be making a substantial number of forward-looking statements, and we ask that you please review the disclaimer for this presentation, which is going to be posted on our video. Sigma ranks as the biggest industrial mineral producer across the Americas. We have achieved operational excellence. Ours is a low-cost operation, and we are carrying out a high-growth strategy for 2026, 2027 and 2028. That is because we are a management operator company, where our interests are completely aligned with those of our shareholders, and those interests are to build long-term value. Resilience is our primary competitive advantage, and it stems from operational efficiency. That efficiency is, once again, a result of the fact that management owns the company. Even more importantly, we are situated in a country, Brazil, that is a politically stable, traditional mining jurisdiction, where the operating environment is very low-cost. Turning to sustainability, we are 100% sustainable. Ours is the Quintuple Zero lithium, which begins with 5 points. There are no tailing dams, so that is 0. We do not use drinking water — 100% of the water is reused and recycled from sewage, 0. We use 0 hazardous chemicals in our operation. DMS is essentially a physics-based process, so that is the third zero. We use 100% clean energy, so 0 dirty energy. And we have had 0 accidents with lost time for almost 3 years. Once again, a picture is worth a thousand words. Here is a picture of our waste tailings before and after the artificial germination program; it has been blended into the landscape. It is basically stacked-up rock, fully geotechnically stable. And we carried out the sustainability initiative of actually planting the rock into a green mountain. So what you now see is essentially the picture below. We are 100% sustainable. We produce the Quintuple Zero lithium. We have zero tailing dams; we have 0 drinking water. We have zero hazardous chemicals. We have 0 dirty power. 100% of our power comes from clean electricity. We have had 0 accidents for 2 years and 7 months, 5 zeros. At the bottom, a picture is worth a thousand words. You see the before and after of our waste tailing piles, which are basically the rocks taken out of the pits. Rocks, very stable, geotechnically stable. But beyond that, we have planted the face of those rocks with artificial germination. We basically did what we call proactive regeneration, and the picture shows how it looks now just a year after those piles were created. So geotechnically safe, sustainable, blended into the landscape, which further enhances the environment. We've established the world's fifth biggest industrial mineral lithium production complex. So what you're seeing in that image is a cutting-edge industrial facility that's been integrated with a mine. However, it isn't merely an industrial facility — it's a state-of-the-art clean technology lithium processing operation where we hit 70% lithium recovery, placing us among the sector's top performers, and it stands in contrast to processing approaches that are considerably less sustainable. Sigma serves as the economic driver for developing the Jequitinhonha valley. We elevated that valley toward prosperity. It's a vital area within Minas Gerais, which ranks as the second wealthiest state in the Republic. We generated 1,000 jobs, 11,000 indirect positions, and 21,000 beneficiaries through our social initiatives involving microcredit and small-scale agriculture. Additionally, we've provided drinking water access to 18,000 individuals. 85% of our workforce comes from the region. 50% of the economically active population has gained from our social programs. We've renovated, established, and constructed schools that place more than 500 children into after-school or school programs; we played a key role in delivering 6.8% GDP growth across the entire state of Minas Gerais; and on top of that, annually we provide 3 million meals so that new waves of people continue arriving to help construct this lithium valley; so we've built a company designed to last. It's a resilient enterprise that has prospered through lithium cycles. That's our accomplishment in 2025, and that's what we'll keep delivering in 2026 — large scale, low production costs, and traceability. We've recorded 0 accidents over 2.7 years; we maintain the world's highest health and safety standards, ranking at the top among all metals and mining companies. Yet more significantly, we've shown speed of execution, low CapEx for building and restructuring operations, like what we've accomplished with mining. And we operate in a low-cost country, which helps us achieve all of that. So now I'll walk through the operational and financial highlights of 2025, and I'll provide a preview of the estimated first quarter 2026; we've shown unmatched resilience over the last year to date. We produced cash flows amid 2025 lithium volatility. Our company was designed to last and withstand the cycles. Four key examples: we signed $146 million in offtake agreements with highly robust intrinsic values. Intrinsic value refers to the advancement we get from clients for the right to receive deliveries of tonnage over periods. The first offtake agreement was essentially to fund working capital. It was signed in '25 for deliveries across 2026. The total comes to $96 million for 70,000 tonnes of deliveries. The second was a $50 million typical offtake prepayment signed for 40,000 tons of annual deliveries over the next 3 years starting in 2026. Second, we've proven that a commercial strategy executed well can truly produce real results even in this market, even amid volatility. We've been monitoring seasonal patterns, and during Q4 of '25 along with Q1 of '26, we brought in $67 million in net sales — something made possible purely by this solid commercial approach. To start, we took advantage of lithium seasonality by essentially securing price adjustments during the fourth quarter, coordinating with our customers to schedule shipments and the final transactions, the resales of their goods across the 2025 contract period. That's what drove the fourth-quarter revenues. Even more significantly, we've produced cash flow from an entirely new business segment — selling lithium fines, specifically high-purity lithium oxide fines that we've run back through our industrial plant from our dry stack tailings. This began in 2025 and continued through 2026; we've reduced leverage on our balance sheet and paid down debt. That marked our third highlight. 60% of our short-term debt has been paid off. 35% of our total debt has been repaid across years like 2025; beyond that, point four, we've completely upgraded and reorganized our mining operations for safety, efficiency, low cost, cadence, and improved delivery. We moved away from using an outside contractor to having full operational control ourselves, and we're ready to show those efficiency gains and cost optimizations over the coming quarters.
Here are some images that, as the saying goes, are worth a thousand words. What you're seeing is the lithium fines piles being relocated over to the shipping halls that are already situated at the port. The outcome of those sales has in fact turned into money what we once referred to as a green premium, which doesn't truly exist. But the reality that we genuinely built this new product line from the dry stack tailings absolutely provided our investors with what we term a sustainability premium, which means real financial results stemming from the investment we made in a dry stack unit for the Greentech Plant; this page covers our offtake agreements. Those offtake agreements on their own made possible our mining upgrade, our lengthy debt repayment, and the capacity expansions. We have an announcement; we signed a 40,000 tonne a year standard offtake agreement that will bring us $50 million in a genuine prepayment, to be closed inside the next 3 months. That figure equals 120,000 tonnes to be delivered across the next 3 years. The use of proceeds is going toward our growth strategy; we also announced and signed the 70,500 tonne 1-year offtake agreement totaling $96 million. That offtake agreement covers deliveries throughout 2026, and its purpose is working capital; that's the working capital that made the mining upgrade and some of the debt repayments possible. Now in 2026, we have two additional offtakes to finalize. First, we're going to amend our contract for the equipment leases tied to the mining upgrade large-scale machines, which have been backed by an offtake for 3 years. At the start, it was for 11,000 tonnes. That number likely will rise based on the scale of machinery we can secure in the second quarter. So once again, the continuity of the mining upgrade toward a better, more efficient, more cost-efficient and safer operation. The second offtake we're close to finalizing is the 80,000 tonne a year for 3 years, which will bring us $100 million in a standard prepayment; that conventional offtake will have used proceeds to pay down the long-term debt that right now sits on our balance sheet as short-term debt because it matures in December of 2026. That was a 4-year shareholder loan that has been gracefully given to us by our shareholders in late 2022 to allow us to have working capital to commission our plant. So that debt will be replaced by an offtake, which is a very sound and very logical operational move for Sigma. On this page, we once again show how the competitive advantage of low costs creates resilience against the price pressures that lithium has experienced this year, especially coming from new regions, sometimes with product that isn't necessarily compliant or traceable, but more importantly, from the ongoing refining innovation that the main markets have shown by pushing the ceiling of this industry constantly lower. Take lepidolite, for example. Its ceiling used to sit at $20,000 to $25,000 per tonne; today it's roughly $17,000 to $18,000 per ton, and it may drift down toward a target of about $15,000 per ton — that doesn't really matter. Either way, we actually operate beneath the industry's floor, which is set by product arriving from the new supply regions in Africa. As long as we remain exactly where we sit on the cost curve, we enjoy operational resilience that lets us, say, sign offtakes with no floors and keep delivering excess returns whenever prices stay at present levels. On the left, we show that resilience through our total cash cost, meaning all-in sustaining costs plus interest. On the left, in green, you see the full-year achieved all-in sustaining costs plus interest alongside the guidance. We're basically in the same ballpark, so we felt comfortable issuing guidance of $532 for all-in sustaining costs plus $60 for interest for 2026. On the following slide, we show the figures on how we bring our people home safely to their families each day, day in and day out; this is what we work for; across 13 years of operations we have never had a fatality. We've been producing for nearly 3 years. Not one fatality. Even more important, we're approaching 2.7 years with 0 lost-time accidents. So our people head home daily and return to work the next day; that represents the highest operational global safety standard anywhere in the battery materials industry, and beyond that, we rank at the very top across all metals and mining companies. We once had 1,600 employees here. Today we have 1,000 employees. It's a large operation, and we still accomplished that — 966 days consecutively without accidents; we're extremely, extremely proud of it. So here's to numeric operational excellence. A number is worth a thousand words. The distinctive resilience and strong cash flows show up in every single one of the main items of our 2025 and first quarter '26 estimated operational performance. First, offtakes; in '25 we signed a $96 million offtake prepayment that let us obtain working capital by getting our production paid upfront. Then we just signed a $50 million traditional offtake covering 3 years of 40,000 tonne deliveries, totaling 120,000 tonnes to be delivered across the next 3 years; but upfront, through June this year, we will receive $50 million, a traditional typical offtake. Even so, we've managed to repay debt at a magnitude that is significant given the volatility in the low points lithium prices hit in 2025. We paid 60% of our short-term debt and 35% of our total debt. That happened essentially thanks to cash flow generation; this company was built for cash flow generation. We operate like an ATM. During Q4 of 2025, operations brought in $31 million in cash. In Q3 of 2025, the quarter before, that figure was $23 million, meaning our cash flow generation rose 35% from the third to the fourth quarter of 2025. Even more significantly, output volumes of lithium materials fell as a result of the complete restructuring we carried out in mining. Yet since ours is an industrial operation, we found another revenue stream. Essentially, we established a second business: reprocessing dry stack tailings into something we refer to as low-grade lithium fines. As a result, we held inventory amassed over recent years equivalent to 70,000 tonnes of the primary high-grade product in revenues. That stock became a fresh business line we call high-purity lithium fines. Thus, across the whole of 2025, we turned out 183,000 tonnes of high-grade premium lithium oxide. Across the whole of 2024, we turned out 240,000 tonnes of high-grade premium lithium oxide. That means our yearly production dropped 24%. Still, how did we bring in such substantial cash flow? How did we manage to repay so much debt? Essentially by launching a new business segment, which we refer to as sustainability monetization, the green premium expressed in figures.
We took the lithium that was sitting in our fines within the dry stack piles and ran it through again, and that gave rise to an entirely new line of business — one that sells high-purity lithium fines. Those fines carry a lower grade, yet when you look at the money they bring in, they match what 70,000 tonnes of premium high-grade lithium oxide would be worth. So when you step back, volume isn't really the thing we're trying to fix. What we're trying to fix is cash flow, and cash flow came through, and the debt got paid down. Now here come the figures, and figures say more than a thousand words ever could and hold no opinion — figures are just figures. What this slide is meant to demonstrate, once more, is both the quantification and a visual of how a commercially successful strategy in fact assisted us in bringing in revenues during Q3 of '25 and Q4 of '25. Our clients are wonderful, and they are commercial partners. So the material gets sold to them. A final sale occurs and the risk sits with them. That sale is done at a provisional price, so a portion of the risk stays with us, while we also capture part of the upside. Put differently, when our clients resell their product — resell it onward to their own customers — we either record a profit sharing gain or a profit sharing loss. A year ago, we recorded a loss. This time around, we recorded a sizable gain. Once more, this came about by mapping seasonality, and seasonality in this sector is quite distinct; it shows up during the restocking window that follows September. The name for it is contract season, so our commercial partners collaborated with us to essentially carry out their final resales mostly once October of 2025 had passed, and that let us collect the rewards of a far stronger pricing backdrop than what had been seen across the entire year, on account of tariff volatility in the metals market. So if you look at the greens, the resales made by our clients are visible. If you look at the red, the sales going from Sigma to the client are visible. And if you look at the line, you see lithium prices along with the enormous volatility that occurred over the course of the year. Together with our clients, we seized not just the initial volatility peak, which arrived in August, but also the later curve of rising prices that unfolded across contract season starting in October 2025. That let us book more than $20 million in final price adjustments during the third quarter of 2025, and it let us book more than $14 million in final price adjustments during the fourth quarter of 2025. These revenues are substantial, so that is a quantification of what a sound commercial strategy amounts to. On this slide, I'll move quite slowly since there's a great deal of information to unpack; but once again, it's financial discipline that produced the high operating cash margins. High operating cash margins are where the cash flow we reported comes from. In 2025, comparing the fourth quarter of '24 against the fourth quarter of '25, our operating cash margin has risen substantially. When you set the whole of 2024 next to the whole of 2025, yes, our gross margins came down, and the reason is that pricing conditions during '25 proved extremely tough. What's fascinating, though, is that cash margins and the generation of cash flow stemmed from a single factor and nothing else: we managed to bring our costs down more quickly than our revenues fell. So even with the mining restructuring, even with prices swinging around, we stayed focused on what we could control, what we can control, and what we always control, and that means our costs. If you look at the bottom of the page, you'll notice that comparing the fourth quarter of '24 with the fourth quarter of '25 on a quarterly basis reveals a 77% reduction in costs. That goes far beyond variable costs alone. Turning to the annual cost reduction, you can see that from full year '24 to full year '25, costs fell 21%. So when we speak of these operating costs, we had operating costs, SG&A, ESG plus all others. So it genuinely represents an achievement of financial discipline. We're constantly cutting what we control. We're constantly optimizing costs. With that said, we can return to revenues; put differently, when you examine net sales revenues quarter by quarter, we've seen fluctuations, which once again simply show how volatile lithium prices were. Even more notably, going from the third quarter to the fourth quarter, when we restructured mining operations, net sales revenues dropped 41%. Yet when we look at our first quarter 2026 estimate, we more than made up for that drop. Why? Because we didn't just open this new line of lithium fines, the low-grade high-purity business we built from our dry stack tailings, but all the work we've done in mine restructuring also started producing results. So on an annual basis, revenues fell 27%. And so, looking at the bigger picture here, what's actually clear is that, yes, revenues fell 27% on an annual basis. Costs fell 21% on an annual basis. So costs fell less than revenues on an annual basis, but we were very quick to offset that and to fix it in the fourth quarter, where we cut costs and brought costs down by 77%. So this is how financial discipline gets demonstrated with numbers. On this slide, we show the quantification of the financial discipline, but now regarding balance sheet optimization. We have significantly deleveraged despite all the price volatility, despite everything that happened with revenues. From the fourth quarter of '24 to the fourth quarter of '25, we lowered our short-term debt by 60%. From the fourth quarter of '24 to the estimate of first quarter '26, which is actually the numbers we have closing, we lowered it by 68%; so the work continued. We didn't stop. Then, looking at the third quarter of '25 against current, we lowered the debt by 49%. So essentially, this amounts to a full overhaul of how we finance ourselves over the near term, and even in how we approach working capital — what that means is that our clients are effectively bankrolling our operations, thanks to the commercial partnerships we've successfully built with them. We structure things so both sides come out ahead, which means our working capital burden drops and we bring down leverage on our balance sheet. On this slide, I'm going to take it very slowly, since it lays out our outlook for cash flow generation. It's pretty simple; pretty straightforward. And once again, it simply shows how Sigma operates as a cash machine. Why is that? Because our margins are high. We're designed to generate cash flow. Our estimate is that over the coming 12-month stretch for Phase 1, we'll likely produce 240,000 tonnes. As we've demonstrated previously, across the year, we're set to deliver 200,000 tonnes. Well, thanks to our optimal cost efficiencies, we'll be achieving an all-in sustaining cost, interest included, of $592. That's what we estimate for the upcoming 12 months, just as we've laid out in guidance. That generates cash flows regardless of conditions. Should lithium fall back to $1,500 a tonne, we'd still be producing roughly $158 million in free cash flow after interest — free cash flow.
Let's assume lithium stays around where it is now, roughly $1,800 to $2,000 a tonne. If that happens, one phase alone would generate free cash flow of somewhere between $218 million and $260.6 million. Then, when we double capacity — which will be ready by the end of next year — and with capacity and production prorated as we commission, you can sharpen your pencils and work out the math on how much cash flow two plants will give us. Even more important: when we figure all-in sustaining costs and all-in cash costs, the sole optimization we've made was on G&A and ESG. On the admin side, running these businesses doesn't require two of me or two of most of our staff, and interest will be halved since it applies to the entire debt we'll take on specifically to construct plant 2. So the real operational scale benefits from operating two plants with infrastructure already built and currently used for just one plant haven't been included. Sharing that infrastructure across two plants will likely deliver additional cost savings that aren't reflected in these cash flows. Even using this cautious take on doubling our operations and finding some savings in G&A and interest, we'd still end up producing around $600 million in free cash flow, assuming prices hold steady. Should prices fall back to roughly $1,500, that works fine as well. We'd still bring in $384 million in free cash flow, which is what's left after interest at those levels. The truly compelling part comes when we add a third line, something that could happen alongside the second line. That gets us to 770,000 tonnes of production, and once again, we're only factoring in efficiencies on G&A, ESG and interest; we've held interest flat rather than reducing it any further. We trimmed G&A once more, since—as I've said—when you've got three times as many plants, you don't need three times as many commercial or administrative staff. Interest stayed unchanged; G&A and ESG were the sole figures we brought down. So what's the upshot? With three lines, our total cash sustaining costs, interest included, fall to $495 per tonne. That means if pricing slides back to $1,500 by the close of '28, the point when we expect this capacity to be up and running, free cash flow could reach $581 million. Should prices hold at current levels, free cash flow could hit $900 million. That's a meaningful sum. This demonstrates that creating worth over the long haul requires shaping an enterprise designed to deliver operating efficiency, operational excellence, and a substantial amount of free cash flow back to shareholders. As management operators, our interests line up completely. We are constructing a business built to endure. When we run this company, our aim is to produce value for shareholders—not only for those of us in management, but also for those outside it. That leads us to this slide, which presents the cash flow bridge and the reasoning behind it. Once again, this gives you a more numbers-based picture showing that the strict execution we carried out in '25, and which we're still carrying out through '26, produced this kind of operational resilience even with extremely turbulent market conditions. We've been generating operating cash. That's the reason we haven't gone out to raise capital—we could produce enough cash to deliver and to carry out the plan, hitting our target. Let's begin back at the close of the third quarter of '25, when our cash stood at $6 million. Just as we projected and just as we talked through in those materials—and I'd urge you to revisit them—we stayed on that path of generating cash flow from operations. So looking at it on a net basis, we generated $31 million in cash from operations. That mostly came from final price adjustments on deals tied to sales that had been made on a provisional price basis, which we went over earlier. From there, we moved on to our cash operating costs. We directed CapEx toward the mining upgrade, and $26 million went toward covering debt repayment plus interest repayment, exactly the way we laid it out in #1 and #2. As for the debt repayment portion, that was strictly debt repayment, amortization of principal. The interest expense was the annual cash expense associated with the $100 million of long-term debt on our balance sheet. As a result, our cash position was unchanged from the third quarter of '25 to the fourth quarter of '25. That's the result of staying disciplined with our finances. Our cash position stayed intact—we didn't burn any. We knew a brand-new lithium fines operation was set to launch, and we had mentioned this in our third-quarter presentation as well. So in the first quarter of '26, we recorded inflows tied to cash sales of those lithium fines, which we finished and closed out as the year began. The lithium fines generated $30 million, and the premium high grade brought in $5 million. Those sales represented the first proceeds from our mining restructuring. Following that, we had a $24 million CapEx obligation related to the mining upgrade, the mining restructuring, and all the other things we had to get done. But because we hold onto our cash and because that new line of business—reprocessing dry stack tailings—brings in cash, we were able to do more than just cover our CapEx for the mining restructuring and upgrade; we also stayed current on debt principal repayment. As a result, we paid an extra $5 million toward debt, which means our cash position grew by 100% in the first quarter of 2026. Put another way, we doubled the cash position. So again, it all comes down to numbers. Numbers don't hold an opinion; and this aligns very closely with the cash flow discipline strategy we set out in the third quarter of '25. What we're handing you here is an advancement, or what we call a preview. There's an additional $14 million coming in from cash sales tied to what we refer to as the lithium fines operation — those reprocessed dry stacking tailings. On top of that, we expect to finalize a prepayment of $50 million under a genuine long-term offtake agreement before the second quarter wraps up. We also have roughly $32 million representing the initial installment tied to the $96 million offtake deal signed back in 2025 for high-grade premium lithium — that's the 70,000 tonnes we intend to deliver during 2026. So to reiterate, we ended the first quarter of '26 holding $12 million in cash, and a substantial inflow of cash is headed our way in Q2 of '26, given that we've essentially completed the bulk of the mining upgrade, which you can see reflected in the CapEx figure of $24 million paid during the first quarter of '26, along with the $4 million we kicked off in the fourth quarter of 2025. Now I'll spend a moment on the operational steps we've taken to restructure how we mine. This was carried out, once again, to build long-term value for shareholders. It was something we had to do. Gaining control over our mine was essential, because absent that, we could never have been positioned to hit the delivery cadence required to drive the capacity expansions at the second and third industrial plants.
To give a quick overview, our business is a completely integrated industrial mining operation. There's a proprietary cleantech technology we use that generates what we refer to as clean lithium; put simply, we have a mine tied directly into an industrial facility. And as I said, halting the mine doesn't halt the industry. Naturally, our goal is running the mine at maximum output while the plant gets fresh rock; yet the plant is capable of many things since we have dry stack materials; however, when we consider doubling capacity and tripling capacity, that means our mines must run at maximum output and in ideal cadence so the plant can hit the 70% recovery levels it truly is — it has proven it can reach during Q4 2024. Picture a blast furnace. If we switch it on and off, it won't hold those efficiency levels; thus, if the same quantity of material isn't fed into those dense media separators each hour, it won't hit 70% recovery. And for that, we require mine planning and mine execution that supplies piles or supplies fresh rock to the ROM pad in consistent quantities, at minimum on a weekly basis; so that's essentially the whole idea behind a 100% vertically-integrated operation. Here's an image of a Greentech Plant at night, absolutely a gorgeous, gorgeous industrial installation; this is what we've accomplished with the Greentech plant that lets us reach the 70% recovery. We had a 2.0 version of the plant, and that was the version we ran from July '23 until November 2024. That one wasn't recovering 70%. It was recovering anywhere from 50%, low 60s, nearly 60%. The dry stack tailing units weren't functioning the way we wanted regardless. We actually spent a significant amount of CapEx to bring the plant to what we call the current stage, which is the 3.0 version that we intend to double and triple, meaning we're constructing another one of this and then we're constructing a second one of this. But for that to occur, as we mentioned before, we need mine and plant operating in cadence. How did we reach the 70% recoveries? We automated industrial operations. We have software, we have scatter, we have algorithms. We have automatic anomaly detection. We have automatic correction recommendations. It's self-learning metallurgy, self-learning for mineralogy. It's a bot that essentially keeps improving and improving and improving when it's fed the same mineralogy. This is an image of our fully automated control room. Then there's the mine. The mine required quite a lot of work. It was utilizing less than efficient small equipment. It was utilizing too many pieces of equipment. At one point, there were 48 small 40-tonne trucks moving through the mine. So a great deal had to be done there. First, we had to fix geometry. It had to be widened. And in this image, you can already observe what widening the geometry has produced. So we completed an intermediary strip whose purpose was to broaden the geometry, extend the mine life, boost access, and unlock other zones containing ore nearer to the surface; what we did, then, is essentially open extra mining fronts at this point to speed up the ramp-up. How did we accomplish that? Through deploying bigger machinery, a bigger fleet, to strip material more quickly. Bigger machinery, then, raises efficiency for the excavators, for the trucks, right across the board. At the same time, though we mainly carried this out during Q4, the Greentech Plant kept running. So we re-processed the lithium materials out of the dry stack tailings across Q4 '25 and Q1 '26, achieving superior recovery — not that 70% recovery, yet it enriched things sufficiently to produce decent cash flow, a decent sale value, a decent value added, so it could generate the cash flow and the revenues we delivered both later in Q4 and also across the whole first quarter. So what we hope will occur, and we've already watched it occur now in March, was recoveries moving nearer to 70% as we go back to feeding fresh rock into the plant; now here's how we'll carry all of that software knowledge over to the plant. We began and we keep going. So we have fast mining put into practice for mine planning; that same software is in place for fuel control. We have fatigue automatic software detection. We have a cost control app sitting on iPads and iPhones for every mine operator. So we have loading and blasting simulations for optimal results with minimum loads, minimum vibrations. So we're carrying the same software technologies, the same intelligence, into the mining operation. And that begins in the control room for mining, which is right here, as you can see in this image. This image shows the first wave of bigger machinery. The machinery will grow bigger and bigger. This is, kind of, the small large equipment. So — yet more crucial than that, we own production control. We drive production control. Mine planning belongs to us, blasting control belongs to us. We brought in a third-party driller for blasting. So we're handling various contractors with our own in-house mining team. That lets us gain confidence about deploying bigger machinery, about investing in bigger machinery, and about essentially performing the calculated analysis of where we ought to be blasting for safety, for optimal geometry, but also for efficient ore recovery. Now I'll discuss how we'll keep expanding; we are restarting construction of Plant 2 this year; so we're going to double industrial capacity for the high-grade premium lithium oxide; and we're not that far off; put another way, once we reach it, we'll move from the 240,000 tonnes we're guiding to 520,000 tonnes, and that isn't that far away. What matters even more is that we could potentially construct 2 and 3 back-to-back. That means the construction crews would stay on, since the amount of CapEx required here is really quite small and the return on that CapEx is extremely strong — finishing the second plant would run us $80 million, while a third plant would come in at $100 million. So $180 million lets us lift output from 240,000 tonnes per year to 770,000 tonnes per year. That is a big jump, and it ranks among the most efficient CapEx ratios anywhere in the industry. So this shows what's possible when we double production and then triple it. We operate the fifth largest industrial mineral complex globally; in the Americas, we are the number one lithium mineral producer. But in this space, all of our peers are present. There are the lithium producers in the Americas extracting from the lakes in Argentina, and that group covers the Chilean and the American producers; there are also the Australian producers, plus the producers from Africa.
Even though we rank as the world's fifth biggest industrial mineral complex and hold the top spot among industrial mineral producers in the Americas, our position globally as a producer sits at number 8. Now consider what occurs when we double, and then triple. Doubling takes us from #8 up to #6 or #5. Tripling then moves us to #4. Every one of these companies carries a valuation far above what ours is. As a matter of fact, we get valued as though we weren't producing at all. So doubling output and tripling output doesn't merely change a number — it plainly proves we can stand among those higher rankings, with a valuation that rises alongside it; that's precisely what building long-term shareholder value means for us. And doing this is our plan. This slide illustrates how near we are to reaching that point. During the fourth quarter of '24 and the first quarter of '25, we decided to speed up construction of Plant 2. Sadly, tariff volatility caused lithium prices to fall by over 50%. So we put CapEx to work, and we put our liquidity to work, in the fourth quarter of '24 and the first quarter of '25, directed at that construction. Well, that news isn't so good. We got through it, we delivered across '25, as we've demonstrated. We prevailed since the business had been structured so it generates cash flows and survives through organic cash flow generation. But here comes the good news. We're nearly there. Civil foundations are nearly complete; so what remains, really? Ordering equipment and assembling equipment — and that can happen fairly quickly. At the first plant, ordering equipment and assembling equipment took us well under 12 months. So completing the second plant this way is in fact a highly expedited construction exercise, covering procurement management for equipment and assembly management for equipment. And that's all. This is fully licensed construction, fully licensed operation, and doing it rests entirely within our control. So Sigma stands in a very strong position to deliver substantial returns to shareholders in 2026. And here, we'll show you why. This slide demonstrates how Sigma's continued cash flow generation, production cadence in '26, and growth through building Phase 2, which will yield 520,000 tonnes of lithium, will certainly set us up for a re-rating of our stock. Why? When you examine our peers producing lithium industrialized oxide from minerals in Australia, they hold a larger nameplate production along with significantly larger cash flow. Yet as our production rises, our cash flow will rise by much more than that, because we hold this competitive advantage of high margins, low cost, and operational resilience. Thus our rise in nameplate production will deliver a disproportionately bigger rise in cash flow generation. What's more, that occurs no matter the pricing environment, thanks to our low-cost operational resilience. The next slide simply shows how we'll get there. We've shown operational discipline. In '25, we hit our targets across the board. That's the picture you see on the right-hand side. We brought down leverage and paid off debt, lifted our operating cash margins, and established a brand-new revenue stream. These days we sell high purity lithium fines out of our dry stack tailings. Our mineral reserves grew by 40%, demonstrating that we can run for 66 years with 1 line, beyond 25 years with 2 lines, and in all likelihood past 25 years with 3 lines. Our commercial strategy got stronger, essentially by seizing seasonality. During the fourth quarter, we monetized final prices consistent with contract seasonality, and we signed 2 major offtakes — close to $150 million in offtakes — with $96 million to finance working capital across '26, supporting the upgrade and restructuring of mining operations, plus a $50 million standard offtake that will essentially go toward building Phase 2. So how do we keep hitting targets across the board in 2026? We'll bring mining operations back to steady-state production — that integrated mine plant cadence we've demonstrated previously — restoring the rhythm of what we refer to as premium high-grade lithium. We'll complete the financial close on the offtake transaction already signed, and we'll close 2 additional offtakes, as we disclosed during our offtake discussion here. We'll get the development bank disbursement tied to funding already spent on Phase 2, and talks are underway with several more banks regarding Phase 3. We'll repay $100 million of shareholder debt, funded by one of the offtakes under negotiation — 80,000 tonnes per year over 3 years. And we intend to commission Plant 2, the Greentech 2, before 2026 ends. With that, I close — with great pride close out the 2025 full year results, a year in which we crossed the Rubicon amid arguably one of the most volatile lithium environments this industry has ever witnessed. Now we step into 2026, flooded with substantial cash generation stemming from numerically delivering operational efficiency. So with that, I wrap up this presentation for the 2025 full year. We're extremely, extremely proud of our team; immensely proud of how we operate, how tirelessly we worked to cross the Rubicon of one of the most volatile lithium pricing environments I've ever witnessed, and I've spent 10 years here as a C-level executive. We achieved this with no capital raise. We achieved this with no disruption to our operations; we head into 2026 from a far stronger position. Why? The resilience we hold is essentially quantified; we already secured our revenues by creating an entirely different product line; we restored production cadence by the close of the first quarter, and we enter '26 with approximately $48 million in quarterly revenues, a major feat given we're only now emerging from a volatile 2025. All of it with zero dollars of new capital raised — purely organic, disciplined cash generation. And that is the quintessential competitive advantage of this company. The efficiency gains from our operations came through and are captured in the figures we presented. Our team has our deep appreciation, and I'd like to express gratitude to every client and stakeholder who stood by us, working alongside us as we closed out '25 and stepped into '26 from this much stronger footing. There will be a separate presentation covering plant construction, but for now we'll share what our plans are. As the earlier slide indicated, the only things standing between us and added production are, in essence, restarting equipment orders, putting that equipment together, and commissioning the facility. That process can move pretty quickly. Based on how long the prior plant took, completing it in less than 12 months is quite feasible. Our equipment orders will be placed during the summer, following the end of the second quarter. The rationale is that the offtake agreement we recently signed will serve as the primary catalyst for us to make the deposit and prepayment on the equipment required for Plant 2's construction. In our view, actually building and commissioning that line will require somewhere from 8 to 12 months. As a result, full commissioning of Plant 2 should occur in early 2027.
So because of that, the '27 guidance isn't about output—it's about the capacity we'll have installed, and we'll keep the market posted as things develop. What we can tell you, though, is that we're nearly finished: three-fifths of our schedule for building Plant 2 is behind us. What's left before we hit that output level is buying, constructing, and commissioning—things we've demonstrated we can do pretty quickly. So we're not working with gross prices; we're working with adjusted prices. When you consider the nameplate price, we pull it from SMM; then we usually ship product at a 5.2, 5.3 lithium oxide grade. So under older contracts, the adjustment divides that oxide level by SC6. Under newer contracts, we divide by 5.5. The outcomes end up roughly the same. So the prices shown in that table are net prices. As I'm sure you all know, gross prices hit $2,400 only 2 days ago. So $1,800 and $1,500 sit well under the present nameplate price level at Shanghai Metals Market. Sadly, I don't have that figure, and I'm hardly an oil specialist. What I can tell you, though, is that 15% to almost 20% of the fossil fuels we consume here are simply the fuels that drive the trucks moving around our operations. Put differently, by law every liter of diesel in Brazil contains 15% biodiesel. That percentage is now set to rise. So in a sense, we're 20% less affected by rising diesel prices than any other nation on earth, thanks to this wonderful program we call biofuels, which was in fact established 30 years ago amid the last oil crisis, for precisely this purpose—Brazil's energy security. And we benefit from it when it comes to our emissions. So our trucks produce 20% fewer emissions because the fuel legally contains 15%, and we're adding around 20-ish percent biofuels to every liter of diesel. Well, I was talking about our Phase 2 plans; and once again, we'll keep providing market updates on that fairly regularly. For Phase 2, come summer, we'll be placing equipment orders; so near the second quarter we order equipment. As we showed, the growth offtake we signed will fund that—$50 million, more than enough to prepay or put down a deposit on the equipment we require. To be precise, what now lies between ordering that equipment and production is basically assembly. Under the earlier plan, we had 1,000 workers on site assembling that plant, that line. That took 8 months. We used what we call air procurement for certain parts that were delayed, so we could shorten delivery times. We rely heavily on what we call acceleration techniques, which are included in this budget. If we go with the accelerated schedule, that means an additional $7 million goes toward more staff, additional shifts, and air freight for certain pieces of equipment. So what’s the implication? It’s that we could have a plant built by Q1 of 2027, if we kick things off in the summer; and after that comes commissioning. Why is it advantageous to build a facility that is an exact replica of one we will have been running for nearly 4 years by that point? That’s the plant we truly understand. Consequently, we think we can meaningfully shorten commissioning; and even more crucially, start reaping benefits right away, beginning at the same recovery levels rather than enduring the learning curve — going from 50% recoveries up to 70% recoveries that we went through between the 2.0 version of the plant and the 3.0 version; so without getting into more detail, we’re quite confident we’ll have Plant 2 at some point in the first half of next year; but that’s why we’re drawing a clear line between installed production capacity and production itself. Production hinges on commissioning, and we’re going to keep the market thoroughly updated as things progress. Now Plant 3. Plant 3 is something we’re genuinely very proud of because, given our operational success, given our cost resilience, and given our strength as a business through cycles, what we demonstrated in 2025 has not been overlooked by the major development banks around the world, by the major players around the world, by the major financiers around the world. So we do have ongoing discussions about building Plant 3. Building Plant 2 and 3 simultaneously is not a new idea. In fact, back in December '22, when we filed our DFS for expansion, that was the plan. To that extent, we put money into building infrastructure for 3 lines. The intention was to proceed with 1, 2, and 3 in sequence and maximize what we refer to as construction synergies. Unfortunately, lithium took a downturn in '24, and we swiftly shelved that plant, and we limited ourselves to just the first plant. By the close of '24, we restarted Plant 2, and we went all in, again, with the tariff volatility in '25, we shelved that plant and we limited ourselves to Plant 1. But carrying out 1, 2, 3 is in fact what we have been designing this industrial complex for. Why? We put the money into the infrastructure, and that was no small achievement, meaning we have the water to supply 3 lines. We are licensed to supply 3 lines. We have the sewage inbound treatment station to supply 3 lines; we have the power substation to build — to supply 3 lines. So from an infrastructure standpoint, we are prepared for 3 lines. And that’s why we’re thrilled to actually say that, that has not been overlooked. Also, there are, shall we say, plenty of options available regarding where we can secure funding, with the right type of debt, development financing debt, to construct these 3 lines. I can't recall the figure offhand, but I can discuss power. There will be zero impact on power; put differently, if you consider power, ours is locked in at $2 per kilo — $0.02 of $1, so $0.02, $0.02 of $1 for each kilowatt hour. That's locked. One key thing, power here in Brazil comes from renewables; it's generated by a hydroelectricity dam; plus we hold a 5-year agreement, scheduled to end 2.5 years from today. So power is going to be fine for us. Diesel is the part that's somewhat trickier to clarify. Firstly, since biofuels are included in the blend, and the law requires that. Secondly, since our oil company is owned by the state, and it operates what we refer to as a diesel compensation account, functioning as a shock absorber when there's an oil crisis. Put another way, diesel expenses aren't passed directly to consumers whenever they rise worldwide. Petrobras soaks up part of that shock at first through what we refer to as the oil compensation account, then it lets it out into the market.
The reason for that is because trucks handle the bulk of transportation within the nation, and since truckers operate as independent businesspeople, they need enough lead time to plan so they can pass those expenses along to their clients. So with that information in hand, we'll circle back to you regarding what share of our costs comes from diesel. Well, I'd like to express my gratitude to each of you. And really, to everyone who is watching us, for your confidence. We made it through 2025, a year that ranked among the most turbulent ever for lithium, and we delivered precisely what we promised — showing resilience, proving operational excellence, and carrying out our plan. We've already kicked off '26 on a tremendous note, thanks to everything we picked up during 2025 about growing more and more and more resilient. So that represents the effort — the combined effort of our leadership group, our employees, and the team based in Vale do Jequitinhonha, basically operating in what we refer to as racing horses mode. We brought the flap down, kept our eyes on our own lane, and ran our own race without glancing sideways, staying locked on the goal; that's the way we've been managing this business, and it's the reason we got these results. So once more, I'd like to give thanks on behalf of our management-operated shareholders here who work at the company and control it — we want to thank every one of our outside shareholders and restate that our interests could not be more closely aligned. No other company in this industry is management-owned and management-operated, with employees holding shares; so to all of you watching, we're all in this together. And I want to thank you for remaining our shareholders, because we got through 2025, and we are in an outstanding position to produce a stellar 2026.
Appreciate it. That brings the Sigma Lithium conference call for the fourth quarter of 2025 to a close. Should you want more information and specifics about the company, kindly head over to the company's site, www.sigmalithiumresources.com. Feel free to hang up at this point.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Sigma Lithium Corporation transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Sigma Lithium Corporation earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.