Good day, everyone, and thanks for being with us. Joining us on this call are Gary Smalley, our CEO and President; Ron Tutor, who serves as Executive Chairman; and Ryan Soroka, our Executive Vice President and CFO. Prior to getting into our results, I want to remind all of you that on this call, forward-looking statements will be made, and those are grounded in management's present evaluation of current trends and available information. Our actual results carry an inherent risk of differing materially. Disclosures regarding the risk factors that might lead to those differences appear in our Form 10-K, which is being filed today. Unless the law requires otherwise, the company undertakes no duty to update forward-looking statements, whether as a result of new information, future events or otherwise. Also, on today's call, management will reference some non-GAAP financial measures. Information on those non-GAAP financial measures, along with a reconciliation, is available in the earnings release we issued today and in the Form 10-K being filed today, and you can locate both in the Investors section of our website. Thank you. With that said, I'll hand the call over to Gary Smalley.

Gary Smalley executive
#2

Thank you, Jorge. Good day, everyone, and we appreciate your participation. For Tutor Perini, 2025 was an outstanding year — possibly the finest in our history. Among the highlights: revenue reached a record $5.5 billion; we returned to robust profitability, generating $4.29 in adjusted earnings per share; and operating cash flow set a record for a fourth straight year, at $748 million, surpassing the previous year's high. The bulk of that massive cash generation came from what new and continuing projects contributed, while our record revenue reflects double-digit backlog growth — growth we anticipate will drive still greater revenue and earnings, improved profitability, and consistently strong cash flow during 2026 and afterward. On last year's earnings call, I laid out several of my leading priorities as Tutor Perini's newly named CEO at that time: maintaining a steady emphasis on cash, getting back to profitability, and setting earnings targets that were ambitious but still sensible — all aimed at substantially boosting shareholder value in both the near and longer term. I am happy to say we have fulfilled every one of those priorities, and collectively they have enabled us to deliver extraordinary share price gains and record returns for our shareholders. Enthusiasm runs high here at Tutor Perini, as well as among investors and other business partners, regarding the strides we have taken and particularly regarding what lies ahead. Being a Tutor Perini shareholder remains exciting, and to those of you who hold our shares, we thank you for your backing. Throughout every quarter of 2025, our revenue growth picked up speed steadily, and the record top line came mainly from what a number of bigger, higher-margin projects contributed. With many of those projects still ramping up, we anticipate they will produce additional double-digit growth in revenue and earnings across the coming 2 years. Civil, our segment with the best margins, accounted for over $2.8 billion of total revenue in 2025 — the greatest annual revenue that segment has ever posted. Consolidated operating income rose sharply in 2025, propelled by our bigger, higher-margin projects and by far smaller negative effects on earnings from legacy dispute resolutions than we saw in 2024. Beyond setting a record for annual revenue, the Civil segment also achieved its all-time highest annual operating income and operating margin in 2025. For the Building segment, operating income in 2025 was the best it has been since 2011; and notably, the Specialty Contractors segment became profitable again during the latter half of 2025, sooner than we had expected. We foresee better margins going forward for Building and Specialty Contractors, along with durably strong margins for Civil, as numerous newer large projects keep ramping up. We closed out 2025 with a healthy backlog of $20.6 billion, a 10% increase compared with the prior year, and a solid book-to-burn ratio of 1.34x for the year. The increase in our backlog came from $7.4 billion in fresh awards and contract adjustments booked over the year. The biggest of those was the $1.87 billion Midtown bus terminal replacement Phase 1 project in New York. Then there was the $1.18 billion Manhattan Tunnel project, also in New York, plus the UCSF Benioff New Children's Hospital in California, worth roughly $1 billion. Additionally, in California we recorded a health care development worth $538 million. Guam contributed $241 million of supplemental financing toward the Apra Harbor Waterfront repairs, plus a military defense initiative there totaling $182 million. In San Francisco, the Diego Rivera Performing Art Center at City College came in at $155 million, while Texas added $131 million of further support for an electrical undertaking, alongside an electrical development at Cook Children's Medical Center in Texas priced above $100 million. Looking somewhat earlier, over the last 3 years we have landed 9 mega projects representing roughly $16 billion combined, with just about every single one carrying a value of $1 billion or higher. In 2025, three of them stood among our top honors, and nearly all arrived after summer 2024 — just one did not. Each of these efforts brings notably strong profitability, better contract conditions, and extended timelines compared with plenty of the sizable jobs we secured in the past. On top of that, they provide clear sight lines for revenue and profits over the coming years. We expect our backlog to remain robust through 2026 and afterward. We anticipate adding roughly a billion dollars to backlog before this year wraps up, tied to the completed trade scope on Phase 1 of the Midtown bus terminal job in New York City. Also, funding totaling $204 million arrived earlier this month for the Eagle Mountain Casino Phase 2 expansion in California — a project we initially won and publicized last summer. Beyond that, Rudolph and Sletten, one of our subsidiaries, was picked not long ago for a sizable new health care development in California worth multiple billions, which is presently in preconstruction. As that effort, along with a number of other Building segment projects now in preconstruction, shifts into construction across the coming years, we look forward to booking substantial further backlog. On top of that, a large number of sizable bid chances continue to come up in our Civil and Building segments, and a good share of those ought to bring substantial activity to the electrical and mechanical units inside the Specialty Contractors segment. Among our most significant bidding opportunities over the next 12 to 18 months are a program believed to be valued at approximately $12 billion for the Sepulveda Transit Corridor, the $3.8 billion Southeast Gateway Line and the $700 million Metro Gold Line Foothill extension, all 3 of which are in California, along with the multibillion-dollar Penn Station transformation project in New York, the $3 billion Newark Liberty International Airport Terminal B project in New Jersey, very similar to the award-winning Terminal A project we recently completed, the $1.4 billion I-535 Blatnik Bridge project in Minnesota and the $1 billion I-69 ORX Section 2 project connecting Indiana and Kentucky. We're also chasing a number of sizable hospitality and gaming prospects, largely across the Southwest region of the United States. On top of that, we still see meaningful Indo-Pacific possibilities, which the federal government's Pacific Deterrence initiative is fueling. Our Guam-based subsidiary, Black Construction, has done exceptionally well, securing a range of new projects across that region, and it stays in a strong position to land further major projects in the years ahead. We continue to be very choosy about the opportunities we go after, keeping our emphasis on bidding work that carries favorable contractual terms, limited competition and higher margins. Because of when our big prospective opportunities are scheduled, most of them will start the bidding process around the midpoint of 2026 and continue into the first six months of the following year. And because we expect to record much greater revenue from work that is already in backlog, we think backlog will dip somewhat in the near term, then start growing again once we win our portion of the large new projects. So going forward, anticipate somewhat more uneven movement in backlog, with expansion still anticipated over the medium to longer term, rather than the consistent quarterly backlog gains we have posted in essentially every quarter for the last 2 years. Even so, expanding is still something we're focused on given current conditions, and we're confident we can add capacity when needed.

Gary Smalley executive
#3

Even though our civil business should keep generating the bulk of our growth and profits going forward, just as it usually has, a sizable share of the work in our Building segment's backlog is earning margins well above what we've historically experienced. Take, for instance, the 2 mega projects we have for New York City Jails — their margins align with those of big, complex fixed-price building jobs. On top of that, today's large health care campus projects involve more technical complexity than the traditional commercial office buildings of the past did, so they too bring in better margins. Back in November, our Board of Directors gave the green light to our very first quarterly cash dividend, at $0.06 per share, along with a share repurchase program worth $200 million. Then today, the Board approved an additional $0.06 quarterly dividend, which was paid on March 26. Now let's move on to our outlook and guidance. Tutor Perini keeps gaining from supportive macroeconomic tailwinds that are fueling robust, sustained market demand for construction services across every segment. We expect these tailwinds to last, given the considerable funding already committed and the fact that for decades, right up until recently, our country underfunded and deprioritized the kind of major infrastructure investments now underway. Drawing on how we see the current market and business outlook, we're projecting double-digit revenue growth and solid earnings in 2026, with earnings climbing even higher in 2027, when newer large projects ought to be under construction; for 2026, we're looking at adjusted EPS between $4.90 and $5.30. Just like last year, we've built a substantial amount of contingency into our guidance for unknown or unexpected outcomes and developments in 2026, including the chance that future project pursuits succeed less often than anticipated, possible project delays, slower ramp-ups on our newer projects, and any unforeseen settlements and/or unfavorable legal rulings tied to dispute resolutions. We also still anticipate robust operating cash generation in 2026 and beyond, thanks to greater project execution activity and the expected resolution of remaining legacy disputes. We've kept chipping away at those remaining legacy disputes and achieved excellent progress in 2025, settling certain long-standing matters. This year is already off to a strong start, as we recently agreed in principle on one of our bigger disputes involving a project completed long ago; we expect to wrap up a settlement agreement within the coming days, and it won't materially affect our earnings. That said, the settlement should bring in roughly $40 million for Tutor Perini in the near term. Given our enormous backlog and abundant bidding opportunities, Tutor Perini's outlook stays incredibly positive, even past 2026. Thank you. With that, I'll hand the call over to Ryan to walk through the details of our financial results.

Ryan Soroka executive
#4

Thanks, Gary. Hello, everyone. I'll begin with a look at how we performed for the year, then go over the fourth quarter, and after that I'll share some thoughts regarding our balance sheet along with the assumptions behind our 2026 guidance. Unless I note otherwise, all comparisons are being made to the corresponding period a year ago. One of the standout items in 2025 was definitely operating cash flow. As Gary said, we produced a record-breaking $748 million of operating cash flow for the year, which is a 49% increase over the prior record of $504 million set in 2024. For the fourth year in a row, we set a record for cash from operations. The improvement stemmed largely from collecting well on both new and continuing work, which shows how much better we've gotten at executing projects and handling working capital. Dispute resolutions played a smaller part in 2025 compared with prior years. Looking ahead to 2026 and past that, we expect cash flow to stay strong, mostly driven by the core business — that is, fresh and current projects — with the occasional lift from settling disputes. For 2025, our top line was $5.5 billion. That's up 28%. The main driver of that strong growth was more work being performed on some sizable, more recent civil and building segment jobs in the Northeast, Hawaii and Guam. The Newark Airtrain replacement was among them, as were the Midtown Bus Terminal Phase 1 project, the Brooklyn and Manhattan jails, the Honolulu Rail project and the Apra Harbor Waterfront repairs project in Guam. On the civil side, revenue got to $2.8 billion, which is a solid 34% gain, and that reflects more execution activity on some large, higher-margin projects in the regions I just mentioned, all of which still have substantial scope of work remaining. That marked the Civil segment's best-ever yearly revenue, which shows the strong, lasting demand for our services that Gary mentioned we're experiencing. Over in Building, revenue came in at $1.9 billion, a 15% increase, mostly from more work happening on the Brooklyn and Manhattan Jail projects in New York, plus a big health care campus project in California — and all of those still have a considerable amount of work left to do. For Building, this was the strongest yearly revenue since 2020. Specialty Contractors posted $844 million in revenue, a solid 43% jump, and that growth was mainly fueled by more activity on the electrical and mechanical pieces of several of the big civil and building projects I just referenced. In the Specialty segment, we didn't really see revenue take off until the back half of 2025, and we're anticipating that momentum will carry through this year and the next as those initiatives, plus other newer ones, move forward. On operating income, the lift came from better margin contributions across a number of Civil and Building segment projects, along with the fact that we didn't have the same net unfavorable adjustments weighing on last year's results. That income climbed considerably even with share-based compensation expense rising by $110 million, a jump connected to our stock price nearly tripling in 2025, which changed the fair value of liability classified awards. Looking ahead to 2026, we expect our share-based compensation expense to come down, and then drop much more sharply in 2027, since a portion of those liability classified awards have already vested, and the bulk of what remains will vest before 2026 is over. Liability classified awards are no longer something we issue, and that ought to meaningfully cut down on earnings volatility. For 2025, Civil segment operating income almost tripled, reaching $391 million versus $138 million in 2024, and the segment's operating margin for the year came in at 13.7%, which sits inside the 12% to 15% range we had anticipated. That marked the segment's highest operating income and operating margin ever recorded in any year. Most of that surge was driven by the work tied to the segment's higher project activity I referenced, along with the fact that we didn't have some net unfavorable adjustments like last year. If you go back to earlier in 2025, we booked favorable adjustments from settling certain change orders, plus revised estimates that came out of better performance and a strong closeout on a domestic mass transit project. Those gains were mostly canceled out by an unfavorable adjustment in Q4 — largely noncash — connected to resolving a legacy dispute on a tunneling job in Canada. Operating income for the Building segment reached $58 million, which is a big swing from the $24 million operating loss we posted in 2024. Looking at 2025, this segment posted a 3.1% margin, recovering from a negative 1.5% the prior year. Two things powered that big gain: the greater volume of higher-margin project work I referenced earlier, plus the fact that we didn't repeat some unfavorable adjustments from the previous year. As for the Building segment, we're looking for margins between 3% and 6%, with certain higher-margin projects providing the lift. Over in Specialty Contractors, the business got back into the black during the back half of 2025, coming in better than we'd anticipated, though for the full year it still recorded a modest operating loss of $7 million, an improvement from the $103 million loss booked in 2024. This better result came mostly from work tied to the greater activity I described earlier, involving the electrical and mechanical parts of some Civil and Building segment projects. A lot of those efforts are still at an early point and should scale up substantially across the coming years. Another factor behind the gain was that we didn't repeat some unfavorable adjustments from the prior year on a number of jobs that had already wrapped up. On the corporate G&A side, the figure stood at $211 million for 2025, versus $110 million for 2024, and that rise stems largely from the much larger share-based compensation expense we recorded in 2025, which came up before. For 2025, we recorded income tax expense of $61 million, which works out to an effective tax rate of 30% for the year. That compares with 2024, when we had a tax benefit of $51 million and an effective tax rate of 29.3%. Net income attributable to Tutor Perini for 2025 came to $80 million, or $1.51 of GAAP earnings per share. In 2024, we had a net loss attributable to Tutor Perini of $164 million, or a loss of $3.13 per share. If you set aside the impact of share-based compensation expense after accounting for the associated tax benefit, adjusted net income attributable to Tutor Perini for 2025 totaled $229 million. On a per-share basis, that equals $4.29 of adjusted earnings per share. Compare that with 2024, when adjusted net loss attributable to Tutor Perini was $124 million, meaning an adjusted loss of $2.37 per share. Now let's look at our fourth-quarter results: across all segments, we achieved a strong turnaround in the fourth quarter with respect to revenue, operating income and margins. To build on what Gary said, we saw our top line accelerate quarter over quarter throughout 2025, with notably robust gains in the back half, and that momentum continues into 2026. Our top line came in at $1.5 billion, which represents a 41% jump compared with $1.1 billion during the fourth quarter of 2024. For the quarter, Civil segment top line was $732 million, marking a 32% gain. Building segment top line hit $512 million, rising 45%, and Specialty Contractors segment top line stood at $263 million, climbing 63%. As I mentioned earlier, this robust expansion was driven by heightened project activity across a number of jobs that are picking up pace and still have considerable work left to complete. In Q4 of 2025, our Civil segment brought in $72 million in operating income — a huge jump compared with the $4 million we recorded for the same quarter in 2024.

Ryan Soroka executive
#5

Operating income and margin were far softer in 2024, and the primary driver was a one-time $32 million reduction in earnings. That charge arose after we reached a successful agreement on change orders tied to a West Coast project, which had much lower margin and carried less risk. Without that negative adjustment I mentioned previously, the Civil segment's operating income and margin in Q4 2025 would have been significantly better. In the fourth quarter of 2025, the Building segment posted operating income of $11 million, compared with a $41 million loss from construction operations during the same quarter in 2024. Gains from several projects with better margins helped drive that gain, and we also didn't have last year's negative adjustment tied to a government building job in Florida. For the quarter, operating income in the Specialty Contractors segment reached $11 million, equal to a 4.4% margin, versus a $20 million loss during 2024's fourth quarter. As this segment takes on more work in our big civil and building projects, its results continue to strengthen considerably. Down the road, we anticipate that this segment will reliably deliver margins between 5% and 8%. Turning to the fourth quarter of 2025, net income attributable to Tutor Perini came in at $29 million, equal to $0.54 of GAAP EPS. That compares with a net loss attributable to Tutor Perini of $79 million, or a GAAP loss of $1.51 per share, in the fourth quarter of last year. Adjusted net income attributable to Tutor Perini for the fourth quarter of 2025 reached $58 million, or $1.07 of adjusted earnings per share, compared with an adjusted net loss attributable to Tutor Perini of $78 million, or an adjusted loss of $1.49 per share, in the fourth quarter of 2024. With that, I'll move on to the balance sheet. Throughout 2025, we reduced our overall debt load by 24%, and our CIE went down by 13%. The decline in CIE was driven largely by billings and collections, some of which related to settling a number of matters that had previously been in dispute. As we work through the remaining legacy disputes, our CIE ought to continue trending lower over time. With record cash generation, we ended the year in a solid net cash position — cash and cash equivalents topped total debt by $327 million, versus a net debt position of $79 million at the close of 2024. At the end of 2025, cash available for general corporate purposes stood at $271 million. To wrap up, I want to say that our financial position has never been stronger, and the net cash we hold provides us with a great deal of latitude when it comes to allocating capital. Last, I'll walk through a few assumptions tied to our guidance that will help with your modeling. For 2026, we expect G&A expense to fall somewhere in the range of $400 million to $410 million. Depreciation and amortization should come in at roughly $50 million for 2026, split between $48 million of depreciation and $2 million of amortization. We anticipate interest expense of $40 million to $50 million in 2026, and approximately $3 million of that figure will be noncash. Our effective income tax rate for 2026 should be in the neighborhood of 27% to 30%. As for noncontrolling interest, that figure ought to come in somewhere between $75 million and $85 million. Diluted shares outstanding on a weighted average basis for 2026 are projected at about 54 million. As for capital expenditures, we anticipate roughly $125 million to $135 million, and the bulk of that CapEx in 2026 — somewhere around $75 million to $85 million — will be owner-funded, covering large equipment items on certain big new projects. Thank you. With that, I'll hand the call back to Gary.

Gary Smalley executive
#6

Thanks, Ryan. To sum things up, 2025 was the strongest year we've ever had. We set records for operating cash flow and for revenue, which was up 28% from the prior year. Operating income and profitability were solid, with our Civil segment — which carries high margins — posting its best annual results ever, and we closed the year with a healthy backlog of $20.6 billion, a 10% increase over last year. Given that enormous backlog, we feel good about delivering double-digit growth in both revenue and earnings, along with another year of strong cash flow in 2026, as our newer projects move from design into construction. Tutor Perini's prospects look extremely promising for the next several years, since we keep benefiting from supportive macroeconomic tailwinds and robust funding from public and private customers, which is driving steady demand across the market and plenty of large bidding opportunities. Like I said before, this is a thrilling moment to be part of Tutor Perini, whether you're an employee, an investor or another kind of business partner. Thank you. With that, I'll hand the call to the operator so we can take your questions.

Steven Fisher analyst
#7

I apologize for the noise in the background. Congrats on a really solid 2025. To kick things off, just a few questions about the guidance. I'm curious whether you could describe the coverage that your backlog provides for the outlook. Given all the bookings you've got, my guess is it's quite strong. But I'm just wondering whether there are specific things that still need to occur and be booked for you to reach those figures; and then on the cadence side, the first quarter is typically somewhat soft compared with the entire year because of seasonality, and clearly we've seen some really harsh weather across parts of the country during the first quarter. So I'm just wondering whether there are any expectations you'd like to set there?

Gary Smalley executive
#8

Yes, Steve, I appreciate the congrats; this is Gary. Yes, to begin with, we have excellent visibility into the results for 2026 and honestly past that. Very little needs to occur for us to reach the figures that we've laid out. Some extra awards are going to come in that could improve things, and there are certain awards baked in that we're anticipating that, strictly speaking, we would need to reach the figures, but that's going to take place. It isn't as though we're counting on some big projects to arrive for us to be able to reach 2026. Regarding seasonality, you're correct, Q1 is generally soft for us. That's normally how it works. This year will be no different. What's mainly happened in New York with the big snowstorm. That hasn't really — it won't have much of an effect. We have contingency for that; we've also budgeted anticipating Q1 would be soft; and then I should also mention Manhattan Tunnel. We're back at work following roughly a 2-week suspension. And all of that is factored into the guidance as well, factored in by — with contingency; so we feel good.

Steven Fisher analyst
#9

Excellent. And looking at it through the lens of backlog, it seems you're anticipating some — I believe "lumpiness" was your term. Yet you mentioned certain potentially bigger contract wins coming in the latter half of the year. I'm just wondering, ought we to anticipate a bit of net burn against the backlog during this year? Or is there, in your view, sufficient opportunity remaining to more or less hold it stable around the current levels? And then perhaps the broader question concerns — maybe on the civil side, do you hold any perspective regarding where we stand in the cycle of larger projects? I recognize this is a space where competition has been fairly limited for you lately. I'm simply wondering where you believe we are in that broader cycle.

Gary Smalley executive
#10

Certainly, Steve. Well, addressing the final portion first, we again have solid visibility into many of these bigger civil projects. Our belief is they're progressing at the rate we anticipated and moving along well. And we don't reveal every sizable project out there, only the largest ones and those most probable to occur soon. We have — regarding the earlier portion of your question, please remind me...

Steven Fisher analyst
#11

Do you expect the backlog to shrink overall during this year?

Gary Smalley executive
#12

Well, our plan indicates that by year-end we'll be somewhat above our present position. I should bring up this idea of lumpiness, since I believe we've spoiled everyone to a degree, because during the past 2 years, we've seen backlog increase in nearly every quarter. This time around, that didn't come to pass—we saw a small percentage-based tweak. I'd like everybody to understand it may be more uneven than what we've seen during the past couple of years, when it felt like each quarter brought a fresh high. Even so, there's a strong pipeline and plenty of solid opportunities out there. Consider this: across roughly the last 18 months, we came out on top in 9 of 11 big awards. Whether that success rate holds, I can't say, but it ought to stay solid, since we go after the projects we're best suited for and believe we can win. To sum up, I believe this all results in an increase in backlog. I can tell you it's on its way, whether that happens before the year closes or sometime next year. That said, pinpointing when exactly those projects will land in backlog is difficult. My main point is that things may be somewhat more uneven than before, yet growth is definitely ahead of us. One final thing: our revenue is going to reach an unprecedented high. After a record-setting 2025, the figures for '26 and '27 will climb even further as we move ahead. What that tells you is that keeping backlog at the same level requires a substantial volume of awards. To put it another way, that's what's behind the note of caution.

Alex Rygiel analyst
#13

Gary and Ryan, that was a really strong quarter. Congratulations. I've got a few questions. Gary, could you expand a bit more on the way contract terms have improved on new awards, and explain what that will mean over the longer term for Tutor Perini?

Gary Smalley executive
#14

Yes, we can do that. Look, previously, when there was more intense competition for the projects we went after, the bigger ones, we wanted to revise contractual terms, but we couldn't, since there was always another party willing to accept those terms and sign the contract. What we've now managed to accomplish, given the limited competition, is to collaborate with our customers, our owners, to secure improved payment terms, improved terms regarding no damages for delay — particularly in New York — just damages, plus provisions covering differing site conditions, items that previously could and at times did hurt us, and items like no damage for delay, which, given how the statute is drafted, is difficult to get around in court should you end up there. So removing that contract provision now is definitely advantageous. So I believe what you'll observe is fewer disputes down the road. And then — and part of that stems simply from the fact that it's truly a clarification of terms. But I also think we'll be less likely to wind up in court, because the pendulum has shifted more toward our side, more to the middle, so that I think you'll get negotiations, meaningful negotiations, before reaching court, which keeps you from having to go to court.

Alex Rygiel analyst
#15

Then, turning to the second point — regarding Rudolph and Sletten, to be clear, were you referring to a health care facility worth multiple billions of dollars? If so, could you say a bit more about it? Also, do you have any thoughts on what opportunities might arise in the next few years when it comes to high-tech manufacturing and reshoring?

Gary Smalley executive
#16

Sure. To start with the multibillion-dollar project: because it's confidential, there isn't much we're able to share. On the multibillion-dollar aspect, the figure sits nearer to $2 billion rather than any amount higher. Beyond that, we're limited in what we can provide, except to say that we're in preconstruction. Typically, whenever a project reaches preconstruction, our track record indicates a 90% plus likelihood that it will move into construction later on. That's our expectation — we believe it will ultimately become a construction contract for us. As for when, some portion should land this year, though most likely the bulk will arrive in 2027. Now, would you like to go into your second question?

Alex Rygiel analyst
#17

And after that, do you notice emerging chances coming out of big production sites, semiconductor fabrication plants, and similar things, plus how might that unfold across the coming few years?

Gary Smalley executive
#18

No, not truly. Naturally, that isn't something affecting our civil segment. However, regarding the building segment, what we're prioritizing at present is health care, a few educational facilities, along with certain multipurpose facilities, hotels, casinos, that sort of thing; yet that is genuinely where we're concentrating.

Adam Thalhimer analyst
#19

Nice work on such a solid year. To kick things off, could you share additional detail regarding the Canadian project? Also, what was the size of the hit that Civil took in Q4?

Gary Smalley executive
#20

Sure. During Q4, if my memory serves, the figure came to $42 million. That entity is a consolidated joint venture, so what I'm citing represents the JV's share. Earlier in the year, there was also roughly a dozen — $12 million or $13 million. That matter is now closed out. A Midwest project of about the same size, possibly slightly larger, which we booked across what was likely the final 3 quarters, pretty much cancels it out. In any case, this ranks among our bigger disputed items. Our judgment was that settling it beat going the route of litigation.

Adam Thalhimer analyst
#21

Yes, definitely. So what number of legacy jobs still need to be settled?

Gary Smalley executive
#22

Yeah. I'd say roughly 12. It's — and yes, there are a few, we have approximately 12. And those carry some weight. There are a few smaller ones out there — cats and dogs, so to speak — that matter less; and like Ryan mentioned a moment ago, he's correct, we began with roughly 50. So we've moved from around 48 down to 12, and we're gaining ground on several of the rest. As you heard, one was just resolved in the past 1.5 weeks. So we'll keep that focus. We're hopeful that a few go our way, correct? A few are write-ups, not write-downs. And we're hoping that's true for what remains, but only time will reveal. But meanwhile, we've attempted to set aside — put aside contingency, not only for that, but for plenty of other unknowns; so we believe we have sufficient contingency to handle any unforeseen delays, anything that simply wasn't forecasted, including the possibility of any write-downs stemming from litigation outcomes.

Adam Thalhimer analyst
#23

All right. Setting that aside, it was truly an excellent quarter. And then...

Gary Smalley executive
#24

Indeed, it was.

Adam Thalhimer analyst
#25

Then I'd like to ask — you mentioned something regarding construction starts in 2027. I realize you won't provide '27 guidance, but I was just hoping you might say more about that and clarify what you mean concerning visibility for 2027.

Gary Smalley executive
#26

Right. Adam, you just called it a great quarter. With that in mind, well, look, despite that write-down, it was a great quarter. I believe that demonstrates how strong what we're building here is, thanks to this new work we have; and that new work takes us beyond '26 and into '27. And you're correct, we don't guide multiyear, but '27 is going to be better than '26. I think that's clear. Around this time last year, we said '25 is going to be good, '26 is going to be better and '27 is going to be better yet, and nothing has changed from that guidance.

Liam Burke analyst
#27

Ryan, the projects you're pursuing keep getting bigger and more complicated. Could there be a danger that resources become stretched? And what impact would that have on how you bid?

Ryan Soroka executive
#28

Yeah. As things stand right now, we have definitely not encountered any resource limitations. One thing worth noting is that most of our workforce comes through the union halls. That means we have arrangements set up — either tied to a specific project or made directly with the union — to ensure that labor gets provided. So as far as we're concerned, when it comes to the craft workers on the ground each day, no restrictions exist, and we don't expect to face any down the road.

Gary Smalley executive
#29

When it comes to management, I believe we've discussed before that this is exactly where we've been concentrating, since the unions have consistently excelled at supplying us with skilled labor whenever we required it. However, as our business has expanded, we've taken a highly proactive approach — in fact, we're continuously in recruiting mode — to bring on the project managers and project executives necessary to oversee this work, and we believe we're in strong shape on that front. We're constantly searching. If anyone listening wants to apply, we're always on the lookout. That said, we believe our current staffing is already at the right level to support future growth.

Liam Burke analyst
#30

Great; and you said earlier that specialty margins might land in what we'd describe as the mid-single-digit range. That business has historically barely turned a profit at best. So is the approach here the same one you use for building and civil? Or does this business have something distinct going on that will drive a fairly substantial shift in profitability?

Gary Smalley executive
#31

Yes. Look, I think what's taken place is that we've managed to eliminate certain bad contracts — ones with unfavorable terms and work at lower margins. Today we've got work at higher margins with better terms. A great deal of the litigation and many of the disputes now sit behind us there, the bulk of them. And so look, if you examine the final 2 quarters of 2025, I believe there was a 2.7% operating segment margin followed by a 4.4% operating margin for the segment across just those last 2 quarters; that's the trajectory we're on at present; that's what the work we're currently doing is generating. And so our 1% to 3%, it's really — there's contingency baked into it. We're aware that the work we hold in hand will fall within that mid-single-digit range. But then we want to be sure we hedge it somewhat against any unforeseen outcomes. Still, we feel quite good that as we get through '26 we're going to see that 5% to 8% range we've discussed for quite a while.

Michael Dudas analyst
#32

Gary, as we head into 2026, you mentioned those 9 mega projects and $16 billion of backlog. So looking ahead through 2026 and '27, how should we think about the revenue conversion from those projects over the coming couple of years — will it come from improved T&C, a stronger backlog, or a higher-margin backlog that's already been booked? And given the targets you've put out to the market, I'm assuming there are comparable targets when it comes to the margin expectations you have right now? Or are there some ranges or opportunities in other places down the road?

Gary Smalley executive
#33

Look, I believe margin will just keep building as time goes on, and that's likely true across all segments as these 9 — the big 9, as we call them — keep ramping into full production. So I think that will definitely help earnings, and it will help revenue generation as well. And as those projects keep maturing and keep advancing, I think we'll see some margin improvement. And look, with the new work we're pursuing, we — as you bring in more work, and this has been our strategy, we have been, I'd say, I'm not sure if I'd call it more aggressive on margin, but we're expecting bigger margin. You begin to fill your coffers; and each time we land another project, we push margins higher the next time, and it depends somewhat on competition; so I can't say there's a ceiling on that, or that there's no ceiling and that margins will keep growing forever. But at this moment, that's the environment we're in where — and that's where our focus is.

Michael Dudas analyst
#34

So the customers, they're becoming more — perhaps it isn't to their liking, yet they're growing more at ease with that set of conditions, considering how constrained the market is?

Gary Smalley executive
#35

Yeah. I suppose there's a way to phrase it like that, Mike. What I'd offer instead is that they appreciate our work; they appreciate who we are. They appreciate the results we deliver. They appreciate how good it is; they appreciate how promptly it gets done. And when you put that together with situations where rivals, at times, aren't submitting bids, or at times, we're plainly the superior offering, whether that comes down to how good the work is or to both quality and cost. So those elements, I believe, mean we're competing for projects. It isn't as though they're simply giving it away — passing it over and handing it to us against their wishes. My sense is we have a strong future ahead. We're — what came before is propelling what comes next, and what came before is simply dependable delivery; and sure, our margins are climbing, yet that reflects the marketplace we operate in. And it would be unwise of us not to, given — when we take stock of our rivals and examine what lies ahead of us.

Michael Dudas analyst
#36

Nicely put, Gary. Ryan, given the impressive work you've done on the balance sheet across the past several years, how will that support the business and the opportunities ahead when it comes to project size and possibly operating more as sole source rather than through partners? And how do you think about a more — the ideal balance sheet size, or what sort of recapitalization might we expect considering where you stand with the debt, the maturities, and the cash we'll have, plus even more that you'll be producing over the next few years?

Ryan Soroka executive
#37

Yes. Those are all good questions. I'll do my best to take them in order. To begin with the balance sheet and the debt currently on our books, 11.8% is clearly a hard coupon to accept, and it's definitely something we intend to refinance, likely around midyear, which we expect to deliver meaningful interest savings. We're hoping for a reduction of 500 basis points. When it comes to how much debt we carry, we feel good at roughly that 400 level, especially if we push it out to a longer term. That way we get certainty around liquidity, along with that longer-term liquidity perspective. Regarding, clearly, the operating cash and free cash we've generated over the past 3 years at a record pace, having that cash available also provides a stronger long-term liquidity outlook and gives other stakeholders, such as the sureties, confidence to — as we evaluate some of these upcoming chances to bid that sole source instead of needing to bring in a JV partner. In 2026 by itself, we're discussing, what did we say, $75 million to $85 million of noncontrolling interest. We would certainly prefer to retain that in-house.

Gary Smalley executive
#38

I'd call that a solid answer. Now let me raise something else that hasn't gotten much attention here; earlier in this call, we talked about better terms in our contracts. I mentioned fewer lawsuits. So — going back several years, we put a great deal of money toward legal costs; and with the headway we've made across the past two years, that figure is declining. We anticipate it dropping even more. Of course, legal costs are a requirement in business, and definitely in this sector. Still, my sense is you'll observe our legal costs shrinking more and more, and that will fuel additional profit gains as well.

Michael Dudas analyst
#39

That isn't such a bad situation, is it? I just want to make sure, Ryan — when you give that interest expense guidance, no refinancing or recapitalization is baked in, right?

Ryan Soroka executive
#40

Well, we widened the range. And so...

Michael Dudas analyst
#41

Okay.

Ryan Soroka executive
#42

Sorry...

Gary Smalley executive
#43

So halfway through the year...

Ryan Soroka executive
#44

Right, right. What we've basically baked in is a refinancing, let's say around the midpoint of the year.

Michael Dudas analyst
#45

I simply wanted to make that point clear.

Gary Smalley executive
#46

Once more, thank you everyone for your interest and for joining us today. As we move ahead, we're eager to keep producing solid results. We'll speak with you again in 3 months. Thanks.

Operator operator
#47

Appreciate it; that brings today's conference call to a close. Feel free to hang up your phones now. Thanks for joining us, and enjoy the rest of your day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Tutor Perini Corporation transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Tutor Perini Corporation earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.