Home / Transcripts / Tutor Perini Corporation (TPC) · May 6, 2026

Tutor Perini Corporation (TPC) Earnings Call Transcript

May 6, 2026

New York Stock Exchange US Industrials Construction and Engineering earnings 45 min

Earnings Call Speaker Segments

Jorge Casado executive
#1

Hi, everybody, and thanks for being with us. Joining us on this call are Gary Smalley, our CEO and President, along with Ryan Soroka, Executive Vice President and CFO. Prior to getting into our results, I want to remind all of you that on today's call, forward-looking statements will be made, and those are based on management's current assessment of existing trends and information. Our actual results carry an inherent risk of differing materially. Disclosures regarding risk factors that might contribute to such differences can be located in our Form 10-Q, which is being filed today, and in our Form 10-K, filed on February 26th, 2026. Unless the law requires otherwise, the company takes on no obligation to update forward-looking statements, whether as a result of new information, future events, or otherwise. On today's call, management will refer to certain non-GAAP financial measures. Information and a reconciliation of these non-GAAP financial measures can be located in the earnings release we issued today and in the Form 10-Q being filed today, and both of those can be located in the Investors section of our website. Thank you. With that, I'll hand the call over to Gary Smalley.

Gary Smalley executive
#2

Thank you, Jorge. Hello, everyone, and I appreciate you joining us. Ahead of discussing our first quarter results, we need to pass along some heartbreaking information regarding a recent event that affected the Tutor Perini family. Several weeks ago, while Super Typhoon Sinlaku was occurring, the Mariana — our offshore cargo vessel — capsized in the ocean with a six-person crew aboard, and that crew included two people who work for us, in the vicinity of Saipan, which lies in the Northwestern Pacific Ocean. For everyone here at Tutor Perini, this loss is beyond anything we can comprehend, and our thoughts, prayers, and most sincere condolences go out to the families of those crew members, to their loved ones, and to all who have been impacted in that community. We've kept in touch regularly with the families, sharing updates and offering our assistance; our dedication to them remains firm, and we'll continue cooperating with them to give any help we're able to provide. Our deepest thanks go out to the U.S. Coast Guard, the U.S. Air Force, U.S. Navy, and also the search crews from the Japan Coast Guard and the Royal New Zealand Air Force for how professional they were and the relentless work they put in across an intense search and rescue operation lasting almost fourteen days. Crew members' remains were recovered for one individual, while the remaining five could not be located. Prior to continuing, I'd like to take a brief pause so we can observe a moment of silence, paying tribute to the crew members and keeping their loved ones in our prayers. Thank you. Now, moving on to what we normally cover. We posted robust results for the first quarter, featuring operating cash flow that reached a record $147 million — easily the best first quarter figure in our history — which came about thanks to collections tied to both new and continuing projects. Revenue rose 11% compared with the same period last year, hitting $1.4 billion, marking the strongest first quarter top line since 2009, and that was fueled by input from a number of bigger, higher-margin projects that remain in their early phases with plenty of work still ahead. Ryan will soon walk you through additional specifics regarding our financial performance. As of the close of Q1, our backlog is still quite robust, sitting at $19.8 billion. We still anticipate that this will drive significantly greater revenue and earnings, improved profitability, and sustained strong cash flow throughout this year and afterward. The Civil segment achieved its best first-quarter operating income ever, rising 10% compared to the prior year, and posted a 12.6% operating margin. That's a solid showing for a first quarter, which tends to be slower for us because of seasonality. Operating income for the Building Segment climbed an impressive 56% year-over-year, with an operating margin of 3.5%. Our specialty contractor division is still performing well on the jobs it has underway, and its operating results have gotten better — you can see that in the slight profit it posted for the quarter — and we anticipate even more progress as the year goes on. Beyond that, we expect margins to rise across each of our three segments as a number of newer, larger projects keep ramping up. During Q1, we recorded close to $700 million in fresh awards plus contract adjustments. Those additions made up the largest gains in our backlog, and all of them sit in California. On the funding side, we put $186 million toward Eagle Mountain Casino's Phase 2 expansion, another $97 million into a healthcare project that's now in construction, and about $66 million split between two mass transit efforts. With that strong backlog — the nine mega projects we've landed over the past one to three years are included in it — we have excellent visibility into revenue and earnings over the next several years. Recently, the Brooklyn Jail Facility in New York, one of our largest jobs, reached a key milestone. A topping out ceremony was held there to mark completion of the building's steel framework, with the final and highest structural beam put into position. As that final beam — decorated with the customary evergreen tree and American flag — climbed 15 stories to its resting spot on top of the building, workers and dignitaries looked on; once finished, the facility will span 1 million sq ft and contain 1,040 beds. This job, along with every one of our other major projects, is proceeding quite smoothly, with dependable business execution and robust financial results. As I've mentioned before, demand from customers is still strong, and we keep seeing many sizable opportunities to bid on projects, especially in the Northeast, the Midwest, the West Coast, and the Indo-Pacific region. Our view is that we're well positioned to continue winning our portion of new assignments in the latter part of this year and over the coming years. As we compete for upcoming work, we intend to remain highly discerning, and that approach will continue to lift and help us get the most out of value for shareholders. Our attention stays fixed on going after work with advantageous contract conditions, a smaller field of rivals, and better margins. On top of the robust appetite across the sectors we operate in, we anticipate that certain existing jobs will yield a meaningful amount of follow-on work, and that gives us greater confidence that backlog will remain at high levels. Consider the approximately $1 billion of additional backlog tied to the finished trades portion of Phase 1 of our Midtown Bus Terminal Replacement Project in New York, which we anticipate booking in the back half of this year. Beyond that, a number of Building Segment projects currently in pre-construction should transition into construction over the course of this year and the next. The largest of these is a healthcare project in California worth several billion dollars, with construction set to begin in late 2027, and at this point we carry just a nominal amount of backlog for it. Let's move on to a handful of the significant bid chances we intend to pursue over the coming 12 to 18 months. One is New York's Penn Station Transformation Project, worth several billion dollars; the U.S. Department of Transportation just announced a substantial sum of committed funding for it, and the development team that's chosen ought to be selected later this month. Next, in Minnesota, there's the I-535 Blatnik Bridge Project at $1.4 billion, with the contractor that's chosen expected to be identified next month. Also, another multi-billion dollar segment of California's High-Speed Rail Project is set to be put out for bids before this year comes to a close. Then we have the I-69 ORX Section 2 job, worth $1 billion, linking Indiana with Kentucky, which also goes to bid later this year. In Southern California there's the Sepulveda Transit Corridor Program, which people think carries a value of roughly $12 billion and is anticipated to be handed out across several contracts, with the first one expected to be put out for bid in the coming year. There's also the Southeast Gateway Line at $3.8 billion, again in Southern California, with bidding set for next year. There's also the Terminal B job at Newark Liberty International Airport in New Jersey, valued at $3 billion — it's very similar in scope to the Terminal A work we wrapped up recently at the same airport, the one that earned an award. Beyond that big roster of major opportunities I just walked everyone through, there's a whole additional set of pursuits across the Indo-Pacific region. Combined, those add up to more than $4 billion, and they include military infrastructure upgrades at Naval Base Guam, airport and harbor projects on Yap, and wharf and harbor improvement work in the Republic of Palau. Beyond that, we continue to see several fairly large healthcare project prospects on the West Coast, as well as chances in hospitality and gaming, primarily in the Southwest.

Gary Smalley executive
#3

Just to remind everyone, most of these opportunities are only now entering the bidding stage, and we expect them to be awarded around the middle or the back half of 2026, or else to keep going through the bidding process into next year. Given that schedule, plus the much larger revenue we anticipate booking this year from work that's already in backlog, our near-term expectation remains a slight sequential decline in backlog, after which growth should resume as we win our portion of the big new projects. We have confidence in our capacity to keep growing backlog over the medium to longer term, even while profitability, free cash flow, earnings growth, quality, and safety stay our key performance measures. You'll remember that back in November, our Board of Directors approved our very first quarterly cash dividend, at $0.06 per share, along with a share repurchase program of $200 million. Today the Board declared a further $0.06 quarterly dividend, payable on June 4th. Earlier in the year, during the first quarter, we finished the initial buyback under that repurchase program, acquiring roughly 278,000 shares in the open market for $20 million, at an average price of about $72 per share. Going forward, we anticipate making more opportunistic buybacks under this authorization as a way of returning excess capital to shareholders. Now let's move to our outlook and guidance. To begin, I'm happy with how strongly the year has started, with results coming in as we expected; favorable macroeconomic tailwinds keep working in our favor, producing robust, lasting market demand across every segment, which bodes well for upcoming awards, growth, and value creation. Ours is a resilient business, and our confidence holds in an outlook of steady revenue and earnings growth across the coming several years. Taking into account our outlook and how we read the current market, we still expect double-digit revenue growth and strong earnings in 2026, with earnings rising even higher in 2027, by which point many of the newer large projects in backlog ought to be under construction. So we are reaffirming 2026 adjusted EPS guidance of $4.90-$5.30 per share. That guidance still incorporates a substantial contingency for outcomes and developments in 2026 that are unknown or unexpected, among them the chance that future project pursuits succeed less often than anticipated, possible project delays, slower ramp-ups on our newer projects, and any unforeseen settlements and or unfavorable legal rulings tied to resolving disputes. We also still anticipate robust operating cash generation in 2026 and beyond, thanks to rising project execution activity on our newer mega projects and the expected resolution of the remaining legacy disputes. Before handing the call to Ryan, I want to say a few words about one of those remaining legacy disputes. During the previous month, an adverse court decision came our way, and damages of roughly $175 million were levied against us. This stems from a conflict involving our client over the W/Element Hotel located in Philadelphia — a Building Segment undertaking finished during 2021, which also welcomed visitors that same year. We hold a strong opposing view of this outcome, and we are convinced it fails to represent what the facts of the matter warrant. Out of respect for the judicial proceedings, and because this litigation remains active, we won't speak in detail regarding what we regard as notable legal shortcomings within the court's ruling. Our plan is to file an appeal, and we will keep aggressively using every suitable legal avenue both to protect ourselves from the damages granted to the customer and to recover sums owed to us under our contracts. An appeal typically requires two years, possibly more, meaning this latest event marks one more stage in what has become a drawn-out legal battle. Following the decision, and having carefully examined our claims involving the owner along with specific subcontractors, we are recording a charge to earnings in the first quarter that is immaterial. I appreciate it. Having said that, I'll now hand the call to Ryan so he can walk through the specifics of our financial results.

Ryan Soroka executive
#4

Thanks, Gary. Hello, everyone. To start, I'll go over what we achieved in Q1, and then I'll share a few thoughts regarding our balance sheet along with the assumptions behind our 2026 guidance. When I make comparisons, they're to Q1 of the prior year, unless I note otherwise. As Gary said, we brought in a record $147 million in operating cash during the quarter, which is a 542% jump versus a year ago and far above any Q1 cash flow figure we've ever posted. It's great to watch the cash flow momentum we built in last year's record-setting year carry forward into this one. The cash flow we saw this quarter came mostly from collections tied to newer and ongoing projects, which shows both a big rise in project execution and better management of working capital, with just an immaterial portion coming from resolving disputes. We expect to keep producing strong cash flow in 2026 and afterward, with the bulk of our cash coming from organic operations — meaning new and existing projects — and boosted occasionally by cash gathered after disputes are resolved. During the first quarter of 2026, we brought in $1.4 billion in revenue, which was up 11%. The primary driver of that increase was additional work being performed on a handful of sizable, more recently acquired, higher-margin projects within the Civil and Building Segment, especially in the Northeast. Those projects included Midtown Bus Terminal Phase 1, the Manhattan Tunnel, the Manhattan Jail, and the Newark AirTrain replacement. For the Civil Segment specifically, revenue came to $698 million, marking a 14% gain, driven by greater execution activity across a number of the same projects I just mentioned — each of which still has considerable work remaining. That figure represented the strongest first-quarter revenue the Civil Segment has ever posted, reflecting the durable and steady demand that Gary highlighted. For the Building Segment, we brought in $473 million in revenue, which is a modest increase compared with Q1 of the prior year, and later in this year we anticipate the segment's revenue growth will rise considerably. All of our key Building Segment projects — among them the Brooklyn and Manhattan Jail projects in New York, along with a sizable healthcare campus project in California — are moving ahead without problems and each still has a great deal of work remaining. Revenue for the Specialty Segment reached $219 million, up a strong 24%, and growth in that segment continues to be powered primarily by increased activity across a range of electrical and mechanical projects in New York and Texas. The Specialty Segment's robust revenue growth started in the second half of 2025, and we expect it to keep going this year and next as those projects and other newer mega projects move forward. Operating income for the quarter came in at $59 million, a decline of 9% from last year. Our operating income benefited from better contributions out of all three segments, but a $23 million rise in shared-base compensation expense during Q1 of 2026 versus Q1 of 2025 offset those gains, largely because our stock price was substantially higher in 2026 than in the same period a year earlier, which impacts the fair value of liability classified awards. Just to remind everyone, our shared-base comp costs should go down in 2026, and they'll drop even more sharply the following year, since a portion of those liability-classified awards vested at the close of last year and the bulk of what remains will vest before 2026 ends. We've stopped granting liability-classified awards altogether, and that ought to cut earnings volatility in a meaningful way beginning next year. Civil Segment operating income came in at $88 million, a 10% gain and the best first quarter the segment has ever posted, with segment operating margin of 12.6%, which is a really solid outcome for a first quarter given the usual seasonality. The rise in operating income mostly came from work we did on a number of higher-margin projects that are picking up pace. That gain was partly canceled out by a $60 million unfavorable adjustment during the first quarter of 2026 on a mass transit project in California. That adjustment came from revised estimates tied to change order negotiations that are still going on, and once those talks wrap up with approval, we expect them to generate a meaningful amount of cash. For the Civil Segment, we're looking for margins to remain between 12% and 15%. Over in the Building Segment, operating income reached $16 million, which is a solid 56% improvement, thanks to contributions from some newer, higher-margin projects in New York and California that still have a lot of work left to do. For this segment, operating margin came in at 3.5%, compared with 2.3% in the prior-year period. The improvement largely reflected the benefits of the increased higher margin project execution activity I mentioned earlier. Our expectation for Building Segment margins is a range of 3% to 6%, driven by continuing contributions from selected higher margin projects. Turning to the Specialty Contractor Segment, operating income for the quarter was approximately $600,000, compared with a loss from construction operations of $7 million in the first quarter of last year. Most of that year-over-year gain stemmed from benefits tied to the higher level of project execution activity on the electrical and mechanical projects I discussed earlier. Many of these projects remain in their early phases and are expected to scale up substantially over the coming several years. During this quarter, the Specialty Segment booked several minor, non-material project adjustments that were unfavorable, stemming from legacy disputes, which weighed on its results for the period, even though the segment stayed profitable and posted a substantial improvement compared with the prior year. For the first quarter of 2026, Corporate G&A expense came in at $45 million, compared with $18 million a year earlier, and the increase largely reflects the considerably larger share-based compensation expense I mentioned. Income tax expense for the quarter totaled $17 million, producing an effective tax rate of 30.1% for the period, compared with $13 million a year ago, which produced an effective tax rate of 23.2% in that period. This year's higher effective tax rate is driven by a substantial jump in share-based compensation expense, nearly all of which cannot be deducted. At Tutor Perini, net income attributable to the company for the first quarter of 2026 totaled $26 million, equal to $0.48 in GAAP earnings per share. A year earlier, in the first quarter, the figure was $28 million, or $0.53 in GAAP earnings per share. Excluding stock-based compensation costs and the associated tax advantage, Tutor Perini's adjusted net income for Q1 2026 came to $55 million, translating to $1.03 in adjusted earnings per share. That compares with $34 million, or $0.65 in adjusted earnings per share, during the equivalent quarter last year. Adjusted EPS rose a robust 58% compared to a year earlier, as you can observe, reflecting the substantial margin contribution and exceptional results delivered by our projects and backlog. Turning now to the balance sheet: record cash generation enabled us to continue reducing total debt, which finished the first quarter at $399 million. At the close of the quarter, our cash and cash equivalents stood $404 million above total debt, which is a very strong net cash position — an improvement of $533 million from a year earlier, when we had net debt. At the end of the first quarter of 2026, cash available for general corporate purposes came to $321 million, an 18% increase from $271 million at the end of 2025. Our balance sheet has never been stronger, and with our solid net cash position, we have excellent flexibility in allocating capital. We're expecting to take care of refinancing those senior notes we already have at some point near the middle of the year. Doing that would let us lock in a better rate on interest and push out when our debt comes due, and it ought to bring down our interest costs quite a bit from here on. And to wrap up, nothing has shifted regarding the 2026 guidance assumptions I laid out three months ago. Appreciate it. At this point I'll hand things back to Gary.

Gary Smalley executive
#5

Appreciate that, Ryan. So to sum things up, 2026 has gotten off to a great start for us, with first quarter results that were outstanding — highlighted by operating cash flow hitting a record $147 million, healthy revenue growth, adjusted EPS coming in at $1.03, a 58% increase compared with the same period last year, and a backlog that remains robust at roughly $20 billion. That backlog gives us confidence in our capacity to produce double-digit growth in both revenue and earnings, along with consistently strong annual cash flow, throughout 2026 and afterward, as the projects we've recently taken on move through the design phase and into construction. Performance across our business remains strong, and we anticipate that our reliable project execution will keep up. Tutor Perini's long-term prospects continue to look extremely promising, thanks to the current backlog made up of long duration, higher margin projects with better contractual terms, the operational enhancements we've implemented within our Specialty Contractor Segment, ongoing favorable macroeconomic tailwinds, and robust funding from both public and private customers, which is driving lively market demand and many significant bidding opportunities. Just as importantly, we feel we are moving nearer to the point where every one of our segments will be performing at full capacity, which will let us show our growth and earnings potential more completely. Thanks very much. With that, I'll hand things over to the operator so we can take your questions.

Michael Dudas analyst
#6

Good afternoon, gentlemen.

Gary Smalley executive
#7

Hi, Mike.

Ryan Soroka executive
#8

Hi there.

Michael Dudas analyst
#9

My thoughts and prayers go out to those families too.

Gary Smalley executive
#10

I appreciate that.

Michael Dudas analyst
#11

To start with you, Gary. You mentioned a number of sizable projects that are going to be put out for bid in the back half of this year, 2027. Could you maybe size that up against what work might be finishing up in certain of those areas, and it looks like there's a tremendous amount of business available in the Northeast, particularly around New York, and definitely in California. I mean, once again, everywhere, but, you know, how do you weigh, like, where the chances sit, your ability to take on work, and maybe even see if you can share a bit more about Guam, since you brought up some fairly big numbers and some possibilities in the Pacific, which certainly ought to have a solid tail given all the money that's been poured in over there.

Gary Smalley executive
#12

Yeah. Yeah, terrific, Mike. You know, to begin with, a few of these chances are already in the pipeline, so to speak; they've been turned in. We're awaiting the outcomes. You know, we ought to find out something, as we discussed in certain cases, later this month, at some point in certain cases next month. On capacity, look, you should feel completely confident that we won't chase something we can't manage. We do have some work that's winding down in California, and we'll tap some of those resources to staff this other work. Every job we're going after, we have people ready and eager to go, and we will carry out the work properly. Yeah, I don't believe that should be a worry. If I were to look at what's available and what we'd anticipate booking, assuming we get, you know, anywhere near our fair share, I'd say it's going to be a, you know, by far a net gain. There are simply so many chances, as you pointed out. The chances that we have as we sit here today and we compare that to the last time we spoke, there's more available. Some of it's moved nearer to, you know, becoming reality. In other cases, there are fresh chances that we're going after. You know, the pipeline is abundant, and we think we're well positioned for, you know, a good number of these chances. You know, if we reach a point, and we'd love for this to occur, if we reach a point where, you know, we can't take on any more, then we'll stay on the sidelines; we're not there yet; we don't think we will be there at this stage; we, we look forward to, you know, when we get together another quarter or two to report on a bigger backlog as these chances come home.

Michael Dudas analyst
#13

Thanks for that. For my next question, Gary, when you look at how margins performed — which, again, for the Q1 results looked pretty strong pretty much everywhere — but the way that plays out as we go through 2026, is it simply a matter of volume and capacity being brought up? Are there comparable other spots where, between the bottom and top of those ranges, something could help you get there as opposed to perhaps delaying them into, say, 2027?

Gary Smalley executive
#14

That's precisely right. Volume is the whole story. The first quarter, you know, is consistently our softest quarter. It's tough to, you know, predict how the first quarter will turn out. It's more difficult than the rest since you can't know how much — you know, we had no idea we'd get all that rain in Southern California, for instance; and we had no idea that, you know, New York your direction, Mike, I scrapped a trip due to, you know, how terrible the weather was and the airport shutting down and that kind of thing. There's just no way to know. As we move forward, you know, over the course of the year, volume rises. On top of that, our margins should rise. Those bigger projects we've been signing, you know, are in the process of ramping up at this moment. They'll only grow more robust as the year goes on, and part of that comes from weather, but, you know, other, you know, other elements too — they're simply at an early stage of their development, so they're about to start blowing and going. A few already have. The rest will pick up further steam as we keep going. My expectation is that 2026 gets stronger quarter by quarter. 2027 will simply carry on from there.

Michael Dudas analyst
#15

Excellent. Thank you, Gary.

Gary Smalley executive
#16

You're welcome. Thanks.

Judah Aronovitz analyst
#17

Hi there, and good evening. I appreciate you taking my question, Steve Fisher. For my first one, I saw that the wording regarding 2027 EPS expectations was switched to "significantly higher on the upper end of the 2026 guide," whereas before it simply said "higher." Is that accurate? And if that's the case, what is it that gives you greater confidence at this point compared with 3 months back? Could you speak to how confident you are about reaching that earnings level in 27? More specifically, has that work already been secured in backlog, or does additional work still need to be booked?

Gary Smalley executive
#18

Yes. If no further work were booked by us, 2027 would be a blowout year, and so would 2026. There will be additional work that gets booked, so things will be even better. What provides a bit more optimism or confidence for us, Judah, is that time has passed; we observe how matters have unfolded. We observe how the new work is advancing; we observe how settlement discussions are advancing. Taken together, all of that leaves us as confident as we possibly can be. Look, we affirmed guidance rather than raising it, and going forward that's something you should generally expect—perhaps a raise, or at minimum consideration of one; this time we did consider it, since we feel much better about how everything is taking shape; at the same time, we want to keep our approach conservative. Yes, our confidence is greater, and it simply comes down to the way all the details are converging at this moment. We're quite pleased with where we stand regarding execution of all this new work, and we're also very optimistic about building on the strong backlog we already have.

Judah Aronovitz analyst
#19

All right, that's clear. Glad to hear it. For my next question, regarding inflation, what's currently showing up in the business, and how at ease are you with the contingencies you've set up — say, in places where re-indexing to inflation isn't possible? Thanks.

Gary Smalley executive
#20

Yes, that's a fair question, since you even pointed out that in certain situations, you suggested we can re-index alongside inflation, and indeed we can; where we're still getting hit by inflation just like everybody else, well, look, we're protected; our approach to contingency has been quite conservative, but we also have that buyout discussed previously on calls, where right at the start we focus on locking down commitments with subcontractors as well as vendors, ensuring that any pricing shift gets transferred to them. When it comes to inflation, we're in good shape.

Judah Aronovitz analyst
#21

Got it. Thank you.

Gary Smalley executive
#22

Okay. Thanks, Judah.

Liam Burke analyst
#23

Appreciate it. Evening to you, Gary, Ryan, and Jorge.

Gary Smalley executive
#24

Hello there, Liam.

Ryan Soroka executive
#25

Hello.

Liam Burke analyst
#26

Gary, the balance sheet you have now is far more solid. The amount of cash on hand is excellent. You are giving money back to shareholders. With liquidity as robust as yours, are you able to take on bigger projects without needing to bring in a joint venture partner?

Gary Smalley executive
#27

You know what? It definitely does. Naturally, that is the way we would prefer to operate, since our joint venture partners are terrific and we value the contributions they make. That said, when we are capable of handling the work ourselves rather than giving away 20% or 25% or 30% of margin in cash to those partners, that is the situation we would love to be in. Of course, being a company in a stronger position, which is what we have now relative to a year ago and the year before that, does give us chances to take on more things independently.

Liam Burke analyst
#28

Okay. When we discuss bidding activity and the possibility of projects growing, does that broaden who we're up against, or is the situation basically unchanged? One factor is that work in data centers has drawn certain rivals away from the jobs you're pursuing.

Gary Smalley executive
#29

Right. If anything has shifted, I'd tell you honestly that compared with last quarter, there's likely very little difference. Look, the pattern has been toward reduced competition, whether we're talking about data centers or simply the amount of work like what we've described. Certainly, you won't see greater competition — not in the near term, the medium term, or even as far ahead as we can look — given the sheer scale of work and how few of us are capable of handling the complicated projects we go after. I'd say competition is likely somewhat lower and will probably stay below where it stands today. We definitely aren't seeing new rivals enter the market at this point.

Liam Burke analyst
#30

Great. Thank you, Gary.

Gary Smalley executive
#31

Yeah. Thank you.

Min Cho analyst
#32

Thank you very much. I'm grateful for the chance to ask my questions. To start, I want to ask about Black Construction. From what I understand, that's a business with higher margins for you. Could you discuss the yearly run rate of revenue there, and also what's in backlog? How large do you think that business could become? If you could also address any bottlenecks that stand in the way of generating more growth from Black Construction, that would help. Thank you.

Gary Smalley executive
#33

Yes. Hello, Min. In the past, we've generally preferred not to say too much about specific business units and the sort of contribution they bring to Tutor Perini's overall consolidated results. I suppose, to try to respond to what you asked in some fashion, we're examining Black. Revenue I won't discuss, though backlog I will. It's above $1 billion. You know, when you consider the run rate, a portion of their work lasts, you know, two to three years. A few other projects take, you know, somewhat more time, perhaps four, five years. You know, we're aiming to expand that; the capabilities are in place there; for us it's an extraordinary business, just a workforce with tremendous talent. You know, expect that. Doubling probably isn't in the cards, but from that, you know, starting point it could increase considerably.

Min Cho analyst
#34

Great, thank you. And regarding your latest Army Corps MATOC award tied to the Energy Resilience and Conservation Investment Program: how much of that $2 billion falls inside what TPC would consider its addressable business? If you could also briefly describe the kinds of construction projects likely to come out of it.

Gary Smalley executive
#35

Every bit of it sits inside what we're capable of and what we're strong at. As for the sort of work, you know, that becomes available through that MATOC, it ranges. It could be building work, it could be civil work, it could be specialty work too, work done by specialty contractors. Our workforce at Black, in Guam, and in the nearby areas — as I said earlier, they're highly talented — but we're also quite diversified. Whatever work exists out there, we're able to handle it. We also have PMSI as one of our business units, and in the same way, wherever in the world they operate, they're well equipped to perform every kind of building work or every kind of construction work. Their focus tends to lean more toward the building side. Honestly, with those two entities combined, there's hardly anything we can't take on.

Min Cho analyst
#36

Great. Let me try to fit in just one more. Could you say a bit about where Tutor stands right now when it comes to going after certain mission-critical, high-tech sorts of projects, such as data centers or semiconductor campuses?

Gary Smalley executive
#37

Sure. This is something we're examining quite carefully; on the specialty side, we're in fact already performing some data center work. Right now we're looking into ways to grow that. We want to be certain we don't abandon the core market, since we know that someday — and who can say how far off that will be, maybe 5 years or 10 years away — the data center work will likely not be around forever, or at least won't be as robust as it is today. We need to be sure we remain well-positioned to handle the work that is our standard bread and butter. Meanwhile, data center work is really exciting for us. We view it as a chance to widen margins and lift revenue too. So we're watching it very closely, and I believe that before too long, definitely before the year ends, you'll be hearing more from us about perhaps a new strategy for pursuing some of that market, or at least pursuing it more than we do at present.

Min Cho analyst
#38

Excellent, I really appreciate it.

Gary Smalley executive
#39

At some point, we'll also discuss it more in public. It's just that we aren't quite at that stage yet, though we are moving nearer to it.

Min Cho analyst
#40

Great. Thanks for the color.

Gary Smalley executive
#41

Thank you.

Adam Thalhimer analyst
#42

Hello there, good afternoon, everyone. That was an excellent quarter.

Gary Smalley executive
#43

Yes, thank you, Adam.

Ryan Soroka executive
#44

Thanks.

Gary Smalley executive
#45

We're happy.

Adam Thalhimer analyst
#46

That was a good one from Min. Mind if I stay on it? Do you see yourselves potentially pursuing data center projects in other segments, or only in the specialties?

Gary Smalley executive
#47

Yeah, at this point it's a bit premature to, you know, go beyond, you know, what I've already told you, Adam. You know, specialty is likely where we're seeing, you know, the most, let's say, immediate, kind of chances. But other areas are on our radar too. That's something that, you know, Management is discussing. We'll have more conversations about it with the Board once we find out a bit more. Definitely, there's plenty of, yeah, enthusiasm, on our end, as we consider possibilities that might be available for Tutor Perini.

Adam Thalhimer analyst
#48

All right, that's helpful. On the repurchase program, I had a question — it was encouraging to see $20 million come through in Q1. What kind of cadence should we expect going forward?

Gary Smalley executive
#49

Sure. That's definitely a topic where, would we be repurchasing at an average price of $72, correct?

Ryan Soroka executive
#50

That's right.

Gary Smalley executive
#51

I think that's right.

Adam Thalhimer analyst
#52

Great job.

Gary Smalley executive
#53

Yeah, indeed. Internally, there was a bit of back-and-forth about this, since our stock has performed really strongly across the past 12 months or so. A few of us felt so convinced that we even put our own money in, like I did. Over the past several months, I've made that move twice. For me, the repurchase was fairly straightforward. Now that we're sitting around 90-ish, it's less attractive to us. That said, we recognize plenty of growth lies ahead. My sense is we'll stay flexible, and opportunities will present themselves; we aren't laying out a plan like, "Alright, we'll spend $X million each quarter or every six months." Instead, we'll evaluate where those chances arise, balance them against cash requirements and how fast our cash reserves are growing, and decide from there. I realize that isn't a precise response, but we're quite conscious that substantial capacity remains for the buyback. We're extremely optimistic about the current opportunities and about where the share price might keep heading. Whether personally or at the company level, I expect additional moves ahead. Once again, the timing just isn't clear to us.

Adam Thalhimer analyst
#54

Adam, thanks. On the refinancing I mentioned would happen within the next few months — you're asking about the likely structure and how much interest we could save.

Ryan Soroka executive
#55

Absolutely. As things stand right now, our intention is to refinance notes 1 to 1. That could shift somewhat. Based on what we're seeing in the market, we're anticipating interest savings somewhere in the range of 400 or 500 basis points. That said, a certain amount of volatility persists tied to geopolitical matters currently unfolding. We'll have to wait and see how that plays out. At the same time, we also plan to review our credit facility, correct? Our aim there is to increase its size and push out those maturities. In the end, what we're trying to achieve is refinancing certain notes while capturing meaningful interest savings, then lengthening the maturity, plus securing a substantial extension and maturity on the credit facility too.

Adam Thalhimer analyst
#56

All right.

Gary Smalley executive
#57

What we're aiming for is to reach a level in the 6% range, as opposed to that awful rate we're dealing with at present on the bond spread.

Adam Thalhimer analyst
#58

Yeah, that would be fantastic. So, my final question. Ryan, you provided the margin guidance for the remaining segments, but I didn't catch one for Specialty. I was wondering what range you're aiming for there; and also, how much of their business right now is for other TPC segments?

Ryan Soroka executive
#59

Certainly; for 2026, we're likely targeting what you'd call the 1.2%-3% span. In the end, we anticipate Specialty will climb to the 5%-8% span. I mean, listen, we still have a bit of a drag from some legacy disputes. That's the reason I'm somewhat moderating 2026 to that 1%-3% span. Currently, roughly 2/3 of Specialty's backlog involves, is on, let's say, projects for other Tutor Perini subsidiaries.

Adam Thalhimer analyst
#60

Great. Thank you, guys.

Gary Smalley executive
#61

Thank you.

Ryan Soroka executive
#62

Thanks.

Gary Smalley executive
#63

Thanks to each of you for joining us today; we're eager to keep producing outstanding results and to talk with you once more in the next quarter. Thanks once more.

Operator operator
#64

That brings us to the end of today's call. At this point, you're welcome to hang up. We appreciate you joining us.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Tutor Perini Corporation transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Tutor Perini Corporation earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.