Capital Power Corporation (CPX) Earnings Call Transcript
October 29, 2025
Earnings Call Speaker Segments
Hello, and thanks for joining us today. Welcome to Capital Power's analyst call for the third quarter of 2025. Right now, everyone is in a listen-only mode. Following the speaker's presentation, we'll open things up for questions and answers. If you'd like to ask something during that portion, just press star one one on your phone. An automated message will then confirm that your hand is raised. Should you want to retract your question, press star one one once more. Please note that this conference is being recorded today. I'll now turn the call over to today's speaker, Roy Arthur. Go ahead, sir.
Good morning, everyone. I'm Roy Arthur, Vice President, Strategy, Planning, and Investor Relations at Capital Power. Thanks for being with us today as we go over the third quarter 2025 results, which came out earlier today. The third quarter report and the presentation for this conference call can be found on our website. On today's call, our President and CEO, Avik Dey, will give an update on our business. After that, Sandra Haskins, our SVP Finance and CFO, will walk through a review of the quarter and the company's financials. Avik will then wrap up the formal portion of the presentation before we open things up for analyst questions in our interactive Q&A. Before we begin, I'd like to remind everyone that certain statements about future events on this call are forward-looking in nature and rest on certain assumptions and analysis made by the company. Actual results could differ materially from the company's expectations because of various risks and uncertainties tied to our business. Please see our cautionary statement on forward-looking information on slide three of our regulatory filings, which are available on CDAR. In today's discussion, we'll be referring to various non-GAAP financial measures and ratios, also noted on slide three.
Those metrics aren't GAAP financial measures, they lack standardized definitions under GAAP, and so they probably won't line up with comparable metrics other companies use. We're offering these metrics as a supplement to the GAAP measures, which appear in the review of the company's results as management sees them. You can find reconciliations from these non-GAAP financial measures to the closest GAAP measures in our integrated annual report. We recognize that Capital Power's head office in Edmonton sits on the traditional and contemporary homeland of many Indigenous peoples of the Treaty Six Region and the Métis homeland. We recognize the diverse Indigenous communities present in these areas. Their presence keeps enriching the community and our lives as we learn more about the Indigenous history of the lands where we live and work. With that, I'll pass things to Avik.
Thank you, Roy. Good morning, everyone, and thanks for being with us. Before I start, I want to express appreciation and give recognition to the people who drive our strategy forward and who deliver on our growth and long-term resilience every single quarter. What we have accomplished would not be achievable without their efforts. I will also take a moment to acknowledge the upcoming retirement of Sandra Haskins, whose leadership and contributions have been instrumental to Capital Power's success. I'll say a few more words about Sandra at the end of today's presentation. With that, I will now review Capital Power's third quarter results. This quarter perfectly highlights our strategy in action with execution and value creation on multiple fronts, including contracts for assets with terms to 2040 and beyond in Canada and the U.S., and more recontracting opportunities in the near term. These efforts clearly demonstrate our ability to enhance contractedness across volume, price, and duration. This quarter, we have further strengthened our position as one of North America's leading independent power producers. Key highlights for the third quarter include advancing commercial optimization with the execution of a long-term contract with improved economics for Midland Cogeneration Venture. This extension enhances visibility of future cash flows and demonstrates our ability to unlock value for existing natural gas generation.
We’ve also put into service our first two battery storage facilities in Ontario — York and Goreway — which add 170 MW of capacity under contracts running through 2047. Both came in on schedule and below budget, and they strengthen our contracted position, broaden the portfolio mix, and support grid reliability in Ontario. Construction has gone nearly 12 months with an outstanding safety record, and these projects show what our team can do when it comes to execution. Work continues on three solar projects in North Carolina, each progressing on schedule and within budget, which reflects our focus on growing the renewables platform. We also completed the financial integration of the PJM assets we recently acquired — Hummel Station and Rolling Hills, the biggest acquisition in our company’s history. In their first full quarter, those facilities beat our expectations, making a meaningful contribution to Adjusted EBITDA and bringing more than 45 new employees and contractors into our longstanding base of operational expertise. Lastly, our portfolio produced 13.4 TW-hours, and we finished 65% of planned outage days for the year. As we walk through these accomplishments, one consistent theme stands out: lower-risk growth over the long term across the portfolio. At the heart of it is compounding growth in energy, expertise, and knowledge from the people at Capital Power. Taken together, these achievements underscore our team’s capacity to deliver consistently, diversify the portfolio, and execute with discipline to create long-term shareholder value.
Back in September 2025, we signed a new long-term agreement with better economics for Midland Cogeneration Venture — the biggest combined electric and steam generation facility fueled by natural gas in the U.S. — pushing the contract out to 2040 and delivering 10 years of incremental contracted revenue. Michigan is a growing, appealing market for power. For Capital Power, this deal marks a significant milestone, since it underscores how essential efficient natural gas assets such as MCV are to keeping the grid reliable as electricity demand rises. Beginning in June 2030, under a new PPA, MCV will get enhanced payments for 1,240 MW, which is roughly 75% of its capacity. That brings long-term revenue stability and lifts annual Adjusted EBITDA by about $100 million — an 85% increase over the contract pricing the facility gets today. When we discuss recontracting our assets, we frequently mention preserving optionality for other opportunities. It's exciting to see one of those moving forward: we've signed a letter of intent with a leading co-location data center developer for a potential 250-MW project, which shows how our flexible generation platform can reliably and efficiently serve new load growth. This gives us a chance to capture superior economics from contracted capacity and to build a relationship with a leading co-location data center developer.
The MCV recontracting and other near-term recontracting opportunities tell a very clear story that our strategy of commercial optimization is delivering. We can extend contracts, improve economics, and secure long-term visible cash flows across core markets, all without taking on new build risk. It is a disciplined way to create value while strengthening the reliability customers depend on, and it builds on the theme of long-term lower-risk growth in years to come. This quarter, our battery energy storage projects achieve commercial operations. We are proud to add the 120-MW York and 50-MW Goreway battery storage projects to the Ontario grid, strengthening reliability and adding a new technology to our asset base. Not only were these our first-ever battery storage projects, but they were also delivered on time, under budget, and with an excellent safety record, a testament to our team's discipline and execution. Contracted through 2047, these facilities will add approximately $35 million in annual Adjusted EBITDA over time. In addition to achieving operation of our battery storage assets, we completed 70 MW of capacity upgrades at York and Goreway with contracts to 2035. Through our various growth and recontracting efforts, this portfolio has extended its weighted average contract life from approximately five years11 years.
Taken as a group, the Ontario projects show how our know-how across gas, renewables, and storage combines to produce dependable, flexible power along with value over the long term. Success across our North American platform is being driven by our disciplined approach. It stands as one more instance of lower-risk growth over the long term that we think we can keep delivering. During their first full quarter owned by Capital Power, the Hummel Station and Rolling Hills facilities completed financial integration and turned in a solid Adjusted EBITDA contribution, beating expectations through greater dispatch and robust pricing. The outlook for energy prices in the PJM market remains strong, and we keep crystallizing value for these assets through hedges with investment-grade counterparties, having established roughly 9 GW of hedges extending through 2027. We're likewise heartened by sustained strength in capacity pricing, which reached the cap of $329 per megawatt day in the 2026/2027 auction — roughly 20% above the 2025/2026 auction. Operational optimization and integration at Hummel Station and Rolling Hills offer yet another plain illustration of our disciplined growth and our capacity to execute, and that shows up in the robust financial results Sandra will take you through next.
Thanks, Avik, and good morning to all of you. The results we posted for the third quarter really show how strong our diversified portfolio is and how carefully we execute. We keep doing exactly what we told you we'd do: growing the business, generating steady cash flows, and maintaining a balance sheet that can back further expansion. Adjusted EBITDA for Q3 came in at $477 million, roughly 20% above where it stood in the same quarter a year earlier. That gain came from robust contributions out of our U.S. flexible generation portfolio after we brought in our PJM assets. Those improvements in the U.S. flexible generation portfolio were partly offset by weaker results at La Paloma and Decatur, which stemmed from generation. AFFO for the quarter reached $369 million, about 20% higher year-over-year, which mirrors the rise in Adjusted EBITDA and a current income tax recovery, partly offset by increased finance expense. Across the nine months of 2025, Adjusted EBITDA came to $1,166 million, 15% above the prior year's comparable period, powered by the very same factors affecting Q3 plus reduced emission costs and corporate expenses. AFFO for the nine months that ended September 2025 was $882 million, 40% above the equivalent period a year earlier, reflecting the same factors affecting Q3 along with a credit for parts at La Paloma and settlement of the off-call compensation.
Our financial results for 2025 so far put us in a solid position to achieve strong results for the year. To make sure the portfolio stays reliable and to better set up the business to take advantage of stronger market fundamentals after 2026, we're revising the maintenance schedule for the Alberta plant. Among the changes is an outage on our G3 unit in Q4 of 2025, which had previously been slated for 2026. That lets G3 — the most efficient coal-to-gas converted unit in Alberta — remain available through 2026, when we'll be carrying out planned outages on every other unit in our Alberta portfolio. Every newly installed turbine, including those at Genesee 1 and 2, goes through an infancy period that calls for more monitoring and maintenance to secure smooth operations over the long term. Because of that, G1 and G2 will see their previously scheduled maintenance outages in 2026 lengthened, though normal operations will still be possible in the interim. For Canadian flexible generation, the 2026 maintenance schedule will involve roughly 40% more outage days than 2025, with an expected capital cost of about $25 per kW of nameplate capacity. For our U.S. flexible generation assets, we anticipate sustaining capital costs of roughly $30-$35 per kW of nameplate capacity over the same period. Although that's elevated relative to prior years, we consider this investment prudent for maximizing asset life and efficiency, and we expect costs on a dollar per kW basis to come down in future years, averaging closer to $25 per kW across the fleet.
You should also keep in mind that these expenses align with what we anticipated, and they don't diminish how we see the return potential of our assets, which we've discussed previously. Based on current Alberta forward pricing, implied spark spreads for Alberta merchant capacity are expected to increase by roughly 90% from 2026 to 2028. When we looked earlier this year, those same forwards pointed to a smaller rise. This change in expectations reinforces our belief that 2026 is the best window for carrying out these outages. Operationally and financially, this approach puts us in the strongest position to take advantage of improving fundamentals in Alberta after 2026. Even with revisions to planned outages and delays affecting Alberta projects, we are reaffirming the guidance ranges we updated in Q2 for our key metrics. For 2025, we still expect Adjusted EBITDA of $1.5 billion to $1.65 billion, AFFO of $950 million to $1.1 billion, and sustaining CapEx of $215 million-$245 million. Those ranges reflect solid execution so far this year and our confidence that our diversified portfolio can deliver stable, growing cash flows. With that, I'll pass it back to Avik to wrap up the call.
Thinking about the third quarter, one thing stands out: 2025 has been a year in which we delivered. Every priority for creating shareholder value that we laid out on our January guidance call has now been completed — from making our U.S. platform stronger to locking in improved long-term contracts. What matters here goes beyond a series of separate milestones; it is the strength of the collective, the team, and the consistency. Our platform is delivering precisely the outcome we built it for: stable contracted cash flows, with the flexibility kept in place to capture upside when markets shift. That is what comes from scale, diversification, and disciplined capital allocation all working in tandem. As of today, Capital Power ranks among North America's leading natural gas-focused independent power producers, with a 12-GW portfolio spread evenly across five core markets and supported by a team that is both experienced and passionate. That balance lets us manage risk, keep growth going, and fund new opportunities, all while safeguarding the strength of our investment-grade balance sheet. Going forward, the foundation laid this year puts us in position to serve the accelerating demand for reliable power and to deliver sustained value creation for shareholders in 2026 and beyond. This morning, we shared Sandra's plan to retire from her role on December 31st, 2025. Sandra has formed an integral part of our company's story, its growth, and its success.
Ever since she came on board back in 2002, Sandra has guided this company with integrity, strategic vision, and a steadfast dedication to excellence. We are deeply thankful for the 23 years she has given in service. Sandra, congratulations on a retirement you have truly earned. Scott Manson, who serves as our Chief Accounting Officer and Treasurer, is moving into the role of Interim SVP Finance and CFO. We have launched a search for a permanent SVP Finance and CFO, and we will announce a successor at the appropriate time. To help ensure a smooth leadership handover, Sandra will stay on in an advisory capacity through the end of Q1 2026. Before we move into Q&A, I want to remind everyone that our 2025 Investor Day event will take place on December 9th and 10th in Toronto. At our Investor Day, you will get a deeper look at how our portfolio of natural gas, renewables, and storage serves as the backbone of reliability today and the foundation for growth tomorrow. We are excited to show how disciplined execution, thoughtful capital allocation, and a focus on operational excellence will keep driving superior shareholder value, and we look forward to sharing our long-term vision and the next phase of Capital Power's growth journey with all of you in person. With that, I will turn the call back over to Roy.
Appreciate that, Avik. That brings the formal section of the presentation to a close. Operator, we're ready for you to open up the Q&A portion of the meeting now.
Thanks. Just a quick reminder — if you'd like to ask something, hit star one one on your phone and hold on until we announce your name. If you want to take your question back, just hit star one one once more. Bear with us while we put together our Q&A roster. Up first, we have Julian Doolan Smith from Jefferies on the line. Your line is open — go right ahead.
Hi, Tanner here, filling in for Julian. Good morning, and congratulations to Sandra. I just wanted to ask about the AESO large load Phase II. Obviously, it's in the pre-engagement phase. I just wanted to check in on your updated expectations for the process, for what the scope could ultimately be, and how you're viewing the way you're level setting expectations going into the engagement phase that begins later this year.
Appreciate the question. We've mentioned this previously — first off, Phase I has us enthusiastic, with possible participants entering the province and truly getting the data center sector moving. When it comes to Phase II, we intend to participate actively. We believe our position is strong for Phase II because of the surplus capacity available at Genesee, and our overall view is constructive. We said this last quarter as well: the optionality our Genesee site offers, together with the surplus load there, puts us in a very favorable spot for that phase. And equally significant, for any party arriving via Phase I, we feel we are the best choice to supply VPPAs. On Phase I, I'd characterize early signals as encouraging, which makes us more optimistic about Phase II. Ultimately, this is an infrastructure undertaking. Having generation already in place that we are working on bringing online, along with how appealing our site is, we believe that ultimately leaves us well positioned.
Great, thank you. Perhaps this is a good spot to go a bit deeper on the MSSC discussion that came up in the quarterly report. Clearly, this proposed reform has surfaced before, and without a technical fix — which I understand you're looking into with AESO — it appears AESO may need a philosophical shift in how it views system risk stemming from a singular unexpected failure or outage. From a perspective standpoint, what signposts should we watch for that would show progress in these discussions, or maybe an evolution in AESO's thinking? Should we continue to see a long-term resolution of this issue as directly linked to the outcomes of the FFR or FNDR process?
That's a really good question. Look, I think the AESO has taken a very constructive stance in how they view the MSCC. The MSCC limit, at the outset, was established for G1 and G2 capacity. That 466 figure represented the initial capacity for G1 and G2. I think the clearest sign of how constructive they're being will come through the two-way dialogue we're having right now regarding the HPSO solution, because that dialogue will, first, validate single nodal capacity beyond 466, even though our solution guarantees we operate inside the current MSCC limits. As we think this through, it will also form part of the Phase II discussion. Overall, I think the onus is on us to show the technical viability of our solution, and we feel very good about that. As you'd have seen in the AESO disclosures, we've already been through preliminary testing, and the AESO has worked with us in a very constructive way as we strive to truly solidify the viability of one R option. Second, for the wider market, tackle the 466 limit and the possibility of raising it. I can't really say more than that, but I think the strongest indicator will be how we do when validating our own HPSO.
Thanks a lot — I really appreciate that.
Thanks. Give us a second while we bring up the following question. That question is going to come from Patrick Kenny at NBF. Your line is open. Go ahead, please.
Thanks. Morning, everyone. I'd like to begin with the co-location opportunity at MCV—could you give us some additional detail on when the PPA there might be finalized and when that customer could potentially come online? And please remind us what the ultimate brownfield potential for the site itself could look like, and whether you're able to scale this opportunity or perhaps bring in additional data center customers over time as well.
Appreciate that question, Pat. The way you know, capacity at MCV stands at a bit more than 1,600 MW. We've signed a long-term contract extension with CMS covering 75% of that capacity. This 250-MW contract, or LOI, with the data center provider is long-term in nature, yet it does cover 100% of the site's capacity. We do see possible expansion opportunities in and around our MCV plant. I can't get into specifics on that. On top of that, I'd note our customer here also has wider ambitions. I think part of what's resonating is the optionality of the MCV site in particular. I can't say specifically how many megawatts or how much acreage are available, or what that pathway looks like. What I would say is that although we haven't yet addressed pricing specifically on the contract, our outlook is quite constructive. First point. Second, these are long-term contracts that you can assume run well beyond 10 years, closer to 15 years. We have capacity and access to transmission and distribution, plus potential upside in Michigan as well and at the site. As we've indicated, we hold a handful of sites that all carry this capacity and potential, and we're actively working to monetize those available megawatts.
All right, thank you. Regarding the PJM assets, I noticed that both Hummel and Rolling Hills operated at elevated capacity factors during the quarter compared with your base guidance. I'm just curious whether that simply reflected seasonal strength over the summer, or whether you now believe this greater level of generation could be sustained going forward. And if that's the case, might you be considering bidding additional capacity into the auction market this December from either facility?
We really can't say anything about what we intend to do at the next auction. What I'd note is that the beginning of the quarter just ended looked closer to normal seasonal patterns. On the whole, we feel good about what we're seeing at both of them. Generation and dispatch have looked encouraging. Our view of the auctions is just as positive. The early indications for the quarter, and what we've observed, are favorable.
All right. Regarding the Arizona assets, if I may — just curious: given that Transwestern pipeline announcement came out recently, has it helped spark any fresh commercial talks with data center customers at Arlington or Harquahala, or maybe sped up some recontracting discussions with the local utilities, simply knowing that additional gas supply is on the way by the end of the decade to support the ongoing build-out of data center capacity statewide?
Well, look, when it comes to confirming natural gas's long-term worth, this pipeline announcement is likely among the largest single data points supporting U.S. gas-fired generation over the past 5 to 10 years. A big pipeline expansion — a $5 billion project, 42-inch line — doesn't get built unless customers are lined up and off-take is secured. As for where we stand between Arlington and Harcahulla, we've had very constructive talks across the last year and a half about upgrades, recontracting, possible growth opportunities, and those are ongoing. I wouldn't characterize them as better owing to the pipeline announcement. The reality is we've been in those discussions for the last two years and taken part in that wider dialogue confirming load growth in Arizona and the need for additional gas to serve those load-serving entities. I'd say interest in the market continues. I wouldn't say it's greater because of the pipeline announcement, but I think our conversations, along with others, have contributed to the pipeline and to firming up the outlook for the Arizona market.
All right, that's great. Thank you, Avik. Sandra, congratulations on the retirement that's coming up for you.
Thanks. Give us a second here for the following question. That next one is from Benjamin Pham at BMO. Your line's open — go right ahead.
Good morning to everyone. Before anything else, I'd like to add my congratulations to Sandra on her retirement. Then I have a couple of questions, and if I may, I'll start with Alberta. Regarding the maintenance schedule you've outlined through 2026, does that really set you up for a different maintenance approach after 2026? Rather than a cycle of every two years, could you simply run the plants hard for four years to take advantage of the pricing situation?
No, Ben, that has nothing to do with it. We already had scheduled maintenance on the books for next year — the usual course outages for those units. What we're really doing is tackling a broader scope of work, driven by certain operational changes that were flagged and that we want to implement during the early stages of commissioning. They've pinpointed additional work they'd like to carry out. Because of that — and since the joint ventures we hold in Alberta are likewise scheduled for outages next year — it was shaping up to be an exceptionally heavy outage year, and that's what led us to pull G3 forward into 2025. Next year will be an increase compared with the last few years, when planned outage days in Alberta stayed fairly low while we worked through repowering Genesee 1 and 2. Once we move through 2026 and 2027 and prices begin to rise, we'll reach a point where outage cadence returns to something more normal. The scope of work will naturally hinge on run hours and so forth, but mostly it's about getting ahead of some of those issues early, which fits with how we handle maintenance and operations.
I think it makes sense for us to tackle all of this right away and make sure we have the availability and reliability moving forward, so that we don't wind up with an added delay or have maintenance pushed out even more. This simply puts us back on a schedule that's closer to normal once we get past this first stretch.
All right, understood. Also, please share your hedging position from the deck at the back and at the 12 gigs for 2026. It doesn't appear that, merely because you're moving some maintenance around G3, Ford, you're overhedged for 2026 — just doing a quick high-level map on it. Is that right?
Correct. Next year we'd essentially be level, meaning baseload stays flat.
All right. Perhaps on the final point, you could offer a few remarks regarding the forward curve, which has risen quite substantially compared with where it stood at the start of the year. Could you discuss the trading activity and liquidity in those later years? Is it essentially just Phase I getting reflected in the forward curve?
After the Phase I announcement, we definitely saw an uptick in those later years. That's clearly a driver, along with the normal course you'd expect as additional supply gets absorbed by the market. You begin to see prices rise. The Phase I announcement is definitely a catalyst. Regarding our hedge position and liquidity, I'd say we're more hedged than we might otherwise have been when looking out through 2027 and 2028, simply because of some of the longer-duration hedges we hold. Liquidity still isn't as robust as what you'd see in the nearer term. We're fairly significantly hedged through 2027 and, to a lesser degree, once you reach 2028, where our hedging is more modest.
All right, that sounds good. Congratulations once more. Thank you.
I appreciate that.
Thanks. Just a moment while we go to the following question. That next question is from Maurice Choy at RBC Capital Markets, calling in on the open line. Please proceed.
Thanks. Morning, everyone. I'd like to return to what you said about Phase I of the AESO large load connection. Avik, you noted earlier that VPPAs could be offered as part of Phase I. We're also aware that a third-party developer has secured more than 900 MW out of the 1.2 GW allocation. First, can I check whether your 375 MW allocation from Phase I is still yours? If it isn't, what's the overall strategy for you here?
Yes, Maurice. I can verify that the $375 million isn't ours. We noted that during the previous quarter. As for what might or might not be included, I'm unable to speak to that, since nothing has been announced or disclosed at AESO. We're fairly confident that Alberta will see projects. We're also fairly confident that for anything requiring an in-service date of 2029 or sooner, we'll be well positioned to offer energy risk management or a PPA if and when those get announced.
Got it. So as a quick follow-up on that, what milestones do you figure are still outstanding before the announcement comes? Is it purely a matter of government policy? Is it simply finishing the final details? How near are we to that, and to your VPPA?
Since that isn't our project, I'm not in a position to say where a different project sits in the queue or how their negotiations are going. What I can tell you is that, given where we stand in the market and the call we made on the $375, we recognize that several projects are in play, moving forward in the queue, and will probably emerge from the Phase I process. The point I'd return to here, Maurice, is our choice on the $375 versus preserving option value on the $1,000. It comes down to our overall business plan and our focus on long-term contractedness, on maximizing value per megawatt at our plants and PV per KW, and on long-term pricing. We have a strong bias, especially in Canada, toward these bigger projects, since we believe they're more likely to deliver long-term contracts. That isn't true in the U.S., given how mature that market is and how much capital and how many players are pursuing capacity there. Because Alberta is a new and emerging data center market, we still favor scale, owing to the likelihood of turning that into long-term PPAs.
Got it. Just to wrap up on that same topic, there has clearly been plenty of talk about possibly bringing nuclear energy to Alberta. I know we've covered this previously, but I realize it's still very early days. From Capital Power's point of view, how do you see your role, and what conditions would need to be in place before you might consider investing in this technology in the province?
I think if we set aside the technology itself — the specific SMR technology — and just ask whether nuclear is viable in Alberta, that's the question we've been working on. We've brought in a best-in-class partner in OPG, and both the province and the federal government have supported our examination of nuclear's viability in Alberta. The province has made its interest very clear in figuring out whether nuclear can work in Alberta. We're still in that early phase of A, consultation, B, validating the technology, and C, understanding how nuclear would fit within the existing framework — the electricity framework for the province. We do believe there's ultimately a role for nuclear, but we don't yet have validation for how we would contract those assets in the existing energy-only market. We can't get ahead of ourselves through the process. This would be a long-term commitment. We haven't had load like this. There's initial investment required to bring the industry to Alberta. The province has said to date that the existing market structure will continue, and you have to find commercial ways to bring in load. Where these projects are longer duration and highly capital-intensive, today they are not economic to do or to FID or to spend material capital on.
Looking ahead, from a system planning standpoint, our job is to handle that load growth across 10, 20, 30 years, and to grasp that technology—and to understand, when and if it gets approved as a viable technology, how we ultimately commercialize it. That's a long-winded way of really saying that today it isn't economic. We're excited about it. We're exploring it alongside best-in-class experts. We're collaborating with government. We're keen to move to the next step. From a Capital Power perspective, when it comes to capital allocation or directing risk capital toward it, that's not something we expect to do in the short to medium term unless something material changes on the commercial side.
All right, that’s great detail — and congratulations to Sandra and Scott as well. We’ll reconnect at Investor Day.
Thanks. Give us a second for the following question. The next one is from John Mould at TD Cowen. Your line is open — go ahead, please.
Hello, and thank you. Good morning to everyone. First, I want to offer my congratulations to Sandra. I appreciate all your support through the years, and congratulations to Scott too. Turning back to MCV, you managed both to extend that contract and to have this potential co-location piece for the merchant capacity. As you look across the remainder of the U.S. fleet, are there other sites with similar characteristics where you could potentially do both? Is it really more a matter of one or the other — either extending your existing contracts or pursuing something on the co-location side? In those markets, how does customer appetite for the co-location solution compare with the interest you saw in Michigan?
Thank you, John, for that question. We have several opportunities across several sites. In terms of outcomes, what we're concentrating on includes upgrades, expansions, recontracting, and the data center opportunity. Across our fleet, we have one or more of those opportunities at Hummel, Rolling Hills, Arlington, Park, and La Paloma. Those are the ones I'd flag as nearest term. What I'd say — and this is something we projected and advocated at our Investor Day in 2024 — is that we believe this is really about finding balanced energy solutions. What that means today, in practice, is that you have to work with, cooperate with, and collaborate with load-serving entities, as we demonstrated at MCV. For us, the way we're pursuing this opportunity set is really by talking to everybody and understanding how we balance the needs of our partners and fellow players in the market, the load-serving entities, and what their objectives are against what our customers' objectives are — whether that's a data center provider or some other large load — and finding ways to make win-win solutions, whether through upgrades, expansions, working with load-serving entities, and ultimately marrying those opportunities with our own, whether behind-the-fence co-location or grid-integrated, grid-connected opportunities.
Regarding the data center opportunity in particular, as I've mentioned previously, we don't see a substantial opportunity in building those data centers behind the fence, given reliability requirements. It's possible to do it, but the generation cost needed to support five-nines reliability would far outweigh the economics of the price per megawatt required to make it work. We regard being able to grid connect as a significant advantage. Working with stakeholders in those markets is going to be critical for successful outcomes. That's again why we're bullish on the Alberta opportunity set, because transmission distribution exists there. Whether our role involves selling power and/or providing a site that we can sell, this is what we've observed and learned in the U.S. market, and that's what we've been leveraging in our approach in Alberta.
All right, thank you for the detail. Turning perhaps to the Alberta opportunity, from what we can see so far regarding pre-engagement on Phase II, it appears that in some form you will likely need to supply your own power for Phase II. To capture that gigawatt-scale opportunity, if you were to site something at Genesee, would new build be required there? I noticed that beyond the spare capacity available at Genesee 1 and 2, a 1.5 GW early-stage combined cycle project also appears on the connection list at that location. What is your thinking there? How do you weigh the relative appeal of putting capital toward possible new build in Alberta against more gas and M&A in the U.S.?
Sure, that's a good question. First, as part of our entry into Phase II in Alberta, we aren't considering new build. Second, we could consider it if a customer existed for it, but you have to consider how long these assets last compared with contracting terms. On new build in Alberta, we would not accept merchant exposure. Third, compared with the U.S. or Alberta—and I'll concentrate more on expansion and repowering than on straight new build, because I believe it's unlikely we'd pursue a new build unless we had strong partners and a strong off-take agreement—those opportunities appear more common in the U.S. today than in Canada. From the expansion and repowering standpoint, we view those as better near-term opportunities, since you have clearer visibility of an in-service date that satisfies customer needs. When we consider new build capacity in Alberta, the challenge becomes how to examine a new build and have an in-service date that satisfies the customer's needs. That's why we feel so strongly about our market position. Through our repowering project in Alberta, we've already paid for completed new build capacity that is available now, and we believe that puts us in a very good position relative to the market.
When it comes to new build pieces, construction exposure, or development capital exposure, our current preference leans toward the U.S. market.
All right, I appreciate it. That's all from me. Thank you for answering my questions.
Thanks. Just a moment while we bring up the following question. That question is going to come from Robert Hope at Scotiabank. Your line is open — please proceed.
Good morning, everyone. Congratulations from me too to Sandra and Scott. Perhaps to continue what we were discussing about Phase II: have there been any shifts in the customers you're engaging with there, or in the amount of backing you're seeing for your sort of next round of projects for Phase II?
No, I wouldn't say there's been a shift in tone, or different discussions, or a greater number of them. Alberta has drawn interest all along. With the guardrails now in place for Phase I and Phase II, that interest is still there. Once we have clearer visibility into what came out of Phase I, my expectation is that we'll see additional interest, especially from larger customers. I'd put it this way: interest hasn't grown or shrunk. It has stayed the same.
All right, thanks for that. To build on it, the Phase II process the AESO laid out is pretty lengthy. Considering where you stand and the fact that 450 MW at Genesee sit unused at present, could that process be sped up in some way? Are you talking with the government or with the AESO, given that your circumstances differ somewhat from a straightforward bring-your-own-power approach?
Overall, I'd say the AESO and the ministries have taken a constructive approach to how Phase II should proceed. My sense is that there will be some tailored discussions with individual parties. Right now, our clear priority is securing approval for our technical solution, since that approval is what opens the door to 566 for us. Beyond that, we have extra capacity on hand. From where we sit, the order of events — which doesn't depend on the Phase II process — is this: get our technical solution validated, get the AESO aligned with what we're proposing, and get those volumes unlocked. I expect our Phase II conversations will be constructive. And most importantly, Rob, when you look at our portfolio, the way we see it is that whether it comes through Phase II or Phase I — and you look at the strip on pool price in Alberta — our task is to maximize value per megawatt from our plants and our dispatch. Whether we sit in Phase I or Phase II matters less than the odds that we can move to contract pricing and contract volumes at attractive pricing across short, medium, and long-term horizons. We feel really good about that opportunity set at the moment. The longer Phase II drags on, and the more volumes get absorbed in Phase I, and the more interest the market shows, the better liquidity I think we'll see at the back end of the curve — and the more chances there will be for us to go contract, which is exactly how we're viewing the opportunity set.
We're going to keep that option in place at Genesee, since I genuinely think our site ranks among the most appealing locations anywhere on the continent for a big data center. That comes down to fiber access, water access, interconnection, plus the topography and the location of Genesee, which sits outside Edmonton. Every one of those factors is a plus for the market as a whole. Above all, we have a strong conviction that we're in the best position to sell power into a market that keeps tightening over the short to medium term. Alberta's outlook looks pretty favorable at the moment when we consider the market tightening, the pricing picture, and how few generators and how little capacity exist there. Sitting at the favorable end of the merit curve — with the lowest heat rate plant, the most efficient plant in the country, and the biggest plant delivering net power to the grid — we believe our position is quite strong.
That's excellent. I appreciate it.
Thank you. Just a quick note — if you'd like to pose a question, hit star one one on your phone. Mark Jarvi from CIBC is up next; your line is open, so please proceed.
Yeah, thank you all. Congratulations, Scott and Sandra, and Sandra, thanks for all the time over the last couple of years. Working with you has been great. Just regarding Midland and that data center customer, could you discuss any regulatory approvals, how the contract is structured, and what needs to get done there? I think Pat asked something like when the load could ramp. If you could maybe just give us some color on when this might move forward.
Appreciate the question, Mark. Yes, some regulatory procedural approvals are going to be needed. When an in-service date for this project might land is something we can't state at this point. Our belief, though, is that within the coming 6 to 12 months, working alongside our customer, we can firm up both the opportunity and the contract. Beyond that, I'm not able to provide additional color at this time. Given that we already have power in place and existing capacity as well, you can take it that the in-service date falls into the short to medium term rather than the long term.
Got it. So returning to the Phase I monetization idea and the VPPA — compared with the point when you first raised that concept on the Q2 call and where we are now, how would you describe the level of confidence? Would you say it's greater today than it was three months back?
Regarding the very idea that we can sell power into this market, our confidence remains unchanged, since we already had strong confidence about it in Q2 as we worked through the details. I don't believe our confidence could be any greater now than it was at that point. It's likewise the same when it comes to our capacity to price power into this market. The one thing I'd say is that the market probably has more exposure to is that there are rumors of projects that are coming online. We're eager to see which projects actually come through and get announced, and how we can support their build.
I hear you. It does appear that, in your view, the megawatts at Genesee that aren't able to dispatch at present could reasonably be treated as fresh megawatts for Phase II. You didn't come across as very enthusiastic about adding new generation absent a long-term contract. How about other technologies — batteries, any solar? Might you consider supplying a data center site at Genesee by way of virtual VPAs with other developers that provide gas?
Are you asking about other companies putting gas on our property?
Not exactly, though it would be closer to a VPPA structure in which they either construct the facility or upgrade assets that already exist. For the data center at Genesee, the answer could involve a degree of on-site or nearby generation, along with additional electricity supplied via VPPAs.
Yeah. I mean, on that front we're completely open-minded. I think that's genuinely been our stance throughout, which is that when it comes to finding creative ways to contract power for customers, we're one of the best — if not the best — whether that's bespoke or in partnership with others. To answer your question about whether we'd be open to other investments at our site: solar, no. Batteries, maybe. Again, it really comes down to contractedness and terms, and whether we can make our cost of capital. I think the growing opportunity — and this is a point I've made before — is that our job in this market, whether it's us or any of our competitors, as an industry, our goal is to sell more power and bring in more demand. As an industry, I think we're doing a good job of that. On a relative basis, given our fleet, I think we're exceptionally well-positioned to sell that power. On Genesee, I think we're open-minded. I'm not opposed to building, but today, I don't see a long-term PPA to substantiate that investment. If and when that comes at us, we'll look at it. We'll pursue it. I think with Phase II, we'll see what other customers come to the table.
Honestly, I'm feeling fairly positive about things. Whoever posed that question, I can't recall, but regarding where pool prices are headed and the more bullish curve we're seeing for 2027 and 2028 — sure, there was some upward movement after June, near when Phase I was announced, though that's now over four months back. That strengthening of the price outlook for 2027 and 2028, I believe, broadly reflects the market's confidence that demand in Alberta will keep growing. At this point it's really just a matter of timing. Will we actually see a substantial share of that load land in 2027, 2028, or 2029? On the whole, the backing for elevated prices and a tighter supply picture looks quite favorable for Alberta, in my view.
Got it, that makes sense. You pointed out a few U.S. sites that have multiple options available. I believe those would be Arlington Valley, Harquahala, Rolling Hills, and Hummel. If you were to pursue upgrades or expansions at any of them, would gas constraints be an issue?
There's no one-size-fits-all response I can give you there, since every location differs. Take us, for instance—we face no such limitation. As I mentioned, the available capacity at Rolling Hills came with our acquisition of it, though Hummel offers us none. At a couple of our WEC plants, we do believe upgrade opportunities exist. For a data center, or co-locating one, we don't see viability on an upfront basis. The way I view our portfolio right now is this: roughly 2.6 gigawatts of contracted capacity in the U.S. runs out between 2029 and 2032, and we hold a bit more than a couple gigawatts of fully merchant capacity in the U.S. Our aim is to find ways to optimize that and grow it. The answer varies by site. As I noted earlier on this call, at the locations I identified, each one carries one or more of those opportunities.
Understood. Alright, I'm eager to catch up in 2 weeks.
Thanks. At this point I see no additional questions. I'd like to return the conference to Roy Arthur so he can give the closing remarks.
We’re grateful to all of you for being with us today. Your ongoing interest in and support of the Capital Power story mean a lot to us. With that, we’ll bring the call to a close now. Thank you.
That brings us to the end of today's conference call. Thanks for joining us, and you can go ahead and disconnect now. Everyone, have a great day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Capital Power Corporation transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Capital Power Corporation earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.