Good day, ladies and gentlemen, and welcome to the Q2 and H1 FY26 earnings conference call for Ceigall India Limited. Please be aware that every participant line is currently in listen-only mode. Once the presentation wraps up, you will have a chance to pose questions. If you require help at any point during this call, just press * followed by zero on your touch-tone phone to signal an operator. Kindly note that this conference is being recorded. At this stage, I hand the call over to Mr. Vikas Varma of Ernst & Young LLP. Thank you, and the floor is yours, Mr. Varma.

Speaker unknown
#2

Thank you, Swapnali. Good evening, everyone, and thanks for being with us on the Quarter 2 and H1 FY26 earnings call for Ceigall India Limited. Before we move ahead, I want to remind everyone that this discussion could include forward-looking statements involving known or unknown risks, uncertainties, and other factors. These need to be considered alongside the company's business risk, which could make future performance or achievements differ materially from what such forward-looking statements express or imply. Joining us today to walk through the financial results and developments and to take your questions is the senior management of Ceigall India Limited, represented by Mr. Ramneek Sehgal, Chairman cum Managing Director, and Mr. Kapil Aggarwal, Chief Financial Officer. We'll begin the call with a quick overview of the past quarter, starting with Mr. Ramneek Sehgal. Over to you, sir.

Speaker unknown
#3

Good evening, everyone. I'm Ramneek Sehgal, MD of Ceigall. It's a pleasure to welcome all of you to the Quarter 2 and H1 financial year 26 earnings call for Ceigall India Limited. Our financial results, investor presentation, and press release have been posted on the stock exchanges and the company's website. I hope you've had a chance to go through them. Let me start with a quick macroeconomic overview. The Indian economy keeps showing strong resilience despite persistent global uncertainties. According to the latest estimates from the Reserve Bank of India, the nation's GDP is expected to grow by around 6.8% in financial year 26, which makes India one of the fastest-growing major economies. This momentum is driven by sustained infrastructure investments, strong domestic demand, sound macroeconomic fundamentals, and prudent policies. Global rating agencies have also taken note, with multiple agencies upgrading India's outlook in recent months. While weather disruptions early in the year temporarily slowed construction activity, they also gave us an opportunity to strengthen operational efficiencies and reinforce readiness for the upcoming quarters. Overall, we remain optimistic about sustained business momentum and macroeconomic stability as the financial year progresses. Turning to the company's performance. In the first half of financial year 26, we delivered consistent performance in consolidated revenue, demonstrating resilience in the face of the operational challenges the industry has faced.

Speaker unknown
#4

A major hurdle we ran into was the extended monsoon, which at its worst disrupted operations by holding up on-time delivery of critical materials and equipment needed for a number of projects. Even with those disruptions, our team has managed to work through these difficulties. This performance shows how dedicated we are to running things well and how we can adjust to outside forces. As of 30th September 2025, we still hold a strong, diversified order book worth INR 12,598 crores in total, distributed over 26 projects that are presently in execution and at allotment stages. Road and highway makes up 64% of that order book — a sizable share — which underscores a solid position in the vital infrastructure development space. On top of that, our strategic move into new segments is starting to produce encouraging results: renewable energy represents 22% of the order book, while industrial infrastructure and transmission and distribution account for 5% and 3%, respectively. This diversification strategy underlines how devoted we are to growing our operational reach throughout a broad set of sectors. It not only shows our commitment to adjusting as market conditions evolve, but also reflects the proactive way we spot and capture emerging opportunities. By widening our footprint, we are putting ourselves in position to take advantage of fresh trends and innovations, making sure we stay competitive and quick to respond.

Speaker unknown
#5

This strategic initiative reflects our vision for enhancing the nation's infrastructure and our mission to pursue sustainable growth amid a constantly shifting business landscape. Over the first half of FY26, we've effectively expanded into promising markets—particularly renewable energy, transmission, distribution, and industrial infrastructure. Through our strategic efforts in these segments, we secured numerous orders worth a combined INR 37.47 crores during this timeframe. Significantly, we came out as L1 for the Velgaon 400 kV substation tender, priced at INR 379 crores, which represents a major milestone as we enter the T&D sector. On the renewable energy front, we achieved considerable headway by clinching two projects in Maharashtra under Mukhyamantri Saur Krushi Vahini Yojana 2.0, carrying a combined value of INR 1,257 crores. In addition, we've been named L1 for the Morena Solar Park project in Madhya Pradesh, worth nearly INR 1,500 crores. These wins demonstrate our dedication to furthering sustainable energy solutions and our capacity to seize emerging chances within renewable sectors. Moreover, within industrial infrastructure, we obtained an award from GMADA in Punjab amounting to INR 431 crores. We also became L1 for building the bulk drug park at Una in Himachal, which has been allotted at INR 190 crores.

Speaker unknown
#6

These accomplishments really show how we're focused strategically on broadening what we offer and strengthening where we stand in the important infrastructure sector. Through steady diversification of the orders we hold, we're setting the business up for growth that lasts and for resilience in an industry that keeps changing. In the quarter, we saw 2 major things happen with our HAM portfolio. First, we reached financial closure on the Southern Ludhiana Bypass project, which is a key milestone in how we're executing on schedule. Second, at the moment we're awaiting the PCOD for the Bathinda-Dabwali project, and we expect to get it soon. Beyond that, we have 7 additional HAM projects in execution right now. As of September 2025, the company has put in INR 515 crores of equity across these HAM projects. On top of that, another INR 87.8 crores went in during October 2025, so total equity infused as of today comes to INR 603 crores. This investment, which is strategic in nature, reflects how committed we are to building up our project portfolio and making sure our projects are delivered successfully. We also received the quantity for the Ludhiana-Bathinda project in the quarter. I'd also like to point to what we're doing with technology and artificial intelligence. The company is actively looking at integrating AI and tools driven by data throughout different functions, such as business development, procurement, finance, and human resources.

Speaker unknown
#7

At the start, our main emphasis is going to be on making the bidding process more efficient by putting these AI and automation tools to work. Those same tools are going to be used for monitoring projects, making sure we hit our project timelines, and even for O&M. As things move forward, we intend to roll these solutions out across every function within the organization. I've brought on technology experts who are busy developing customized tools built around our particular requirements. Turning now to our debt position as of September 30th. Standalone, our total debt came in at INR 614 crores, versus INR 635 crores as of March 2025, which shows continued deleveraging. That figure comprises INR 136 million in equipment term loan, INR 2,702 million in terms loan, and INR 3,310 million in working capital loans. The standalone debt-to-equity ratio was 0.3 times in H1, FY 2026, against 0.4 times in FY 2025. Consolidated, total debt came to INR 13,412 million as of September 2025, compared with INR 13,967 million in March 2025. This comprises INR 604 million in equipment term loan, INR 2,777 million in term loan, INR 6,720 million in HAM term loan, plus INR 3,310 million in working capital loans.

Speaker unknown
#8

In H1 of FY 2026, the consolidated debt-to-equity ratio came in at 0.7 times, again lower than the 0.8 times recorded in FY 2025. We're actively putting together plans to bring down our outstanding debt by a significant margin across the full year. That effort forms part of a broader financial strategy intended to strengthen our balance sheet and improve our overall financial health. Through this focus on reducing debt, we aim to bring down our interest expenses, boost our financial flexibility, and build a more sustainable capital structure. Looking ahead, we're very confident and optimistic regarding the future of the sector. We're actively looking at avenues to broaden our footprints across different segments. Our commitment to investing in advanced construction methodology and cutting-edge equipment puts us in a perfect position to satisfy the growing demands of infrastructure development. We expect a significant rise in tendering activity from the National Highways Authority of India after the recent announcement of the list comprising 124 projects with a project capital cost of INR 2 trillion. Of these projects, 81 are structured under HAM and 12 fall under BOT projects. Our company is strategically focused on capturing these opportunities, especially given the high margin nature of these contracts.

Speaker unknown
#9

Also, since we rank among the top firms in EPC, we feel confident about our ability to handle a substantial share of these projects. Ceigall has put in bids worth INR 14,320 million in total across a range of sectors, which shows both our broad capabilities and our strategic focus. Within that overall figure, Ceigall has deliberately spread its bidding activity across several sectors. Our bids consist of INR 88,860 million in the road segment, INR 48,960 million in the railway segment, and INR 6,000 million in the renewable segment. This wide-ranging approach not only shows our versatility but also mirrors our dedication to meeting diverse infrastructure needs and pushing sustainable energy initiatives forward. I want to point out that the technical and financial norms of the bidding process have been tightened in both EPC and PPP mode in order to curb reckless bidding. These changes involve a requirement for higher net worth, additional performance security, revised land acquisition, clearance requirements, and a greater emphasis on PPP projects. Such developments are a good sign for players like Ceigall. Our well-established reputation and expertise put us in a favorable position to take advantage of this coming wave of opportunities. On the whole, we anticipate a significant rise in order awarding by NHAI, particularly given the recent slowdown in order awards. This expected increase not only mirrors the government's commitment to infrastructure development but also fits with our strategic growth objective in the sector.

Speaker unknown
#10

Beyond that, we’re also aiming to widen our footprint in the international market by bidding on major projects overseas. As soon as we get any updates on this call, we’ll keep you informed. At this point I’d like to pass the call to our CFO, Kapil Aggarwal, who will go into more detail on our company’s financial performance. Thank you, everyone.

Speaker unknown
#11

Thank you, Ambani sir. Good evening, everyone. I will now take you through the financial highlights for the second quarter and first half of FY26, beginning with the standalone performance. For Q2 FY26, revenue from operations stood at INR 7,870 million as compared to INR 8,970 million in Q2 FY25. However, on an H1 FY26 basis, the revenue from operations came in at INR 16,053 million, registering a modest 1.4% year-on-year growth. EBITDA for Q2 FY22 stood at INR 918 million as compared to INR 1,019 million in the corresponding quarter last year, translating to an EBITDA margin of 11.7%. For the first half, EBITDA stood at INR 1,853 million with a margin of 11.5%. Profit after tax for Q2 FY26 stood at INR 559 million with a PAT margin of 7.1%. For H1 FY26, PAT came in at INR 1,118 million with a PAT margin of 7%. On a consolidated basis, revenue from operations for Q2 FY26 stood at INR 8,066 million, up 4.5% year-on-year from INR 7,722 million in Q2 FY25. For H1 FY26, consolidated revenue grew 3.1% year-on-year to INR 16,447 million. EBITDA on a consolidated level stood at INR 1,136 million in Q2 FY26, translating into an EBITDA margin of 14.1%.

Speaker unknown
#12

For H1 FY26, consolidated EBITDA was INR 2,227 million, reflecting a margin of 13.5%. PAT reached INR 562 million in Q2 FY26 and INR 1,075 million in H1 FY26. Turning to execution, we currently have 26 ongoing projects, with a total order book of INR 125,980 million. These include 15 EPC projects, seven HAM projects, 10 O&M projects, one DBFOT project, and three tariff-based projects, covering multiple sectors like roads, highways, tunnels, railways, metros, airports, runways, and bus terminals. With a well-diversified portfolio and a robust order pipeline, together with the government's continued emphasis on infrastructure development, we are strategically positioned to sustain our growth trajectory and deliver sustainable long-term performance. Our diverse range of projects across various sectors not only mitigates risk but also allows us to capitalize on emerging opportunities in the market. With that, I conclude my opening remarks and would request the moderator to open the floor for questions. Thank you.

Speaker unknown
#13

Thanks a lot. At this point we'll move into the question-and-answer portion. If you'd like to pose a question, you can press star and one on your touchtone phone. Should you want to drop out of the queue, just press star and two. We ask that participants speak through their handsets when asking. Ladies and gentlemen, we'll pause briefly while the questions queue up. Our first question comes from Vaibhav Shah of JM Financial. Please go ahead.

Speaker unknown
#14

Right, so we've noticed a fair amount of subdued execution across the first half, with revenue growth coming in at just 2%. For FY26 overall, how are you viewing revenue growth for the full year, and also what EPC margins are you aiming for across the entire year?

Speaker unknown
#15

That's a fair question. Because of the monsoon and how long the rain lasted, naturally, as you can imagine for any EPC business, the second quarter looks this way. Still, yes, we genuinely expect a lot from our quarter three and quarter four. As we guided earlier, we would see growth of the same kind as before, roughly 10%-15% versus our performance last year. That answers the first part. The second point is on EPC. Margins in EPC remain the same as what we have delivered previously. Yes, once the debt comes down, that will have an effect next year. Thank you.

Speaker unknown
#16

Second, regarding the appointed dates — those are still pending for VRK-11, VRK-12, and Southern Ludhiana Bypass. When do we expect the appointed dates to come through for those projects?

Speaker unknown
#17

For VRK-11, we anticipate it happening at some point prior to December 31. With Southern Bypass, again we expect that before December 31. As for VRK-12, our target is to reach closure ahead of March 31, 2026. My expectation is that come March 31, 2026, every one of our HAM projects will be underway in execution.

Speaker unknown
#18

What's the land status across all 3 of those projects?

Speaker unknown
#19

The land situation along Southern Bypass is quite straightforward. For VRK-12, we've already made our submission for the appointed date, with the stipulation that 55% of the land had nearly reached the point where execution can begin, and the department aims to secure cleared land within the coming six months. By the time we finish executing that 55%, which will take a minimum of 8 to 9 months, the land will have been handed over to us clear.

Speaker unknown
#20

If land acquisition for the remaining portion gets delayed, that won't create risk. Given that we're still open to beginning execution, is the ministry permitting the appointed work to proceed even when land is under 80%?

Speaker unknown
#21

The land situation is clear. The only remaining piece is the forest clear, which constitutes the balance of this project, and we expect to obtain it by March, and I believe we will secure that land. If not, the contract states quite plainly that any land not cleared within 180 days will be descoped from the project. At a minimum, we have mobilized, and we intend to execute the project because the rates are attractive, the old project is in place, and we want to carry it out, and we want to do this with the land that is available. We want to execute the project on the available land.

Speaker unknown
#22

Could you give us a number for the land percentage on Southern Ludhiana Bypass and VRK-11?

Speaker unknown
#23

On Southern Bypass, I believe we ought to have 80% of the land cleared by December, and then we'll begin the work in full swing. This is a continuation of the Ludhiana-Bathinda project of ours. On Ludhiana-Bathinda, as you saw, we received the appointed date on 29th of September, and we have already raised the first bill, and it's performing very well. It's the continuation of that project, and our target is to start it in December. VRK-12 is in a similar situation, though yes, the land position for VRK-12 is somewhat lower, at around 55%, and we are pushing and requesting the government and NHAI to secure additional land for us as soon as possible.

Speaker unknown
#24

Regarding VRK-11, the percentage of land

Speaker unknown
#25

On VRK-11, that's the one we're aiming for. We'll kick off just a single project since we've already mobilized on site. You can appreciate that once you're mobilized, with your crews in place, salaries being paid, and camps set up, you want to get one job started. Then for VRK-11, our target is that we'll take it at least when acquisition reaches close to 80%, which falls around March 31 — that's what we're aiming for.

Speaker unknown
#26

Sir, I'm a bit confused here. VRK-11 is March 25, and VRK-12 is December 25.

Speaker unknown
#27

Yeah, yeah.

Speaker unknown
#28

All right. Sir, one final point — you said our target for FY26 is 10%-15% revenue growth. If I take even 10%, which is the bottom of that guidance, revenue growth in the second half would come to 17%. Can that really happen — growing 17% in the second half so we hit the low end of the guidance?

Speaker unknown
#29

As I mentioned, work on the Southern Bypass has already begun — actually, apologies, we'll be starting the Southern Bypass next month. Ludhiana-Bathinda is already underway. Both Ayodhya projects are currently under execution, so it's achievable. The only reason we couldn't do it is the rainfall or monsoon, but apart from that, once a project has started, execution isn't a problem. Completing projects ahead of schedule is our USP. That's our USP.

Speaker unknown
#30

Alright, sir. And finally, regarding the EBITDA margin. In the first half, after excluding other income, EPC margins come in at roughly 11.5%. For the second half, should we expect a similar margin, or could there be some improvement?

Speaker unknown
#31

The figure will be comparable. Naturally, all entrepreneurs aim to make it better, yet it will remain comparable to the guidance given to investors.

Speaker unknown
#32

And sir, when it comes to 2027, is it fair to expect some margin improvement?

Speaker unknown
#33

No need to apologize.

Speaker unknown
#34

Looking ahead to 2027, is it possible for us to see margins improving somewhat?

Speaker unknown
#35

Sure, we’ll work on getting those margins better.

Speaker unknown
#36

Okay. And sir, there's one data point I wanted. What would the EPC value be for the orders we've won this year?

Speaker unknown
#37

I—

Speaker unknown
#38

Several BOT projects were in the mix.

Speaker unknown
#39

We’ve only taken an EPC value of roughly INR 12,000 crores. INR 12,400 is actually in my—

Speaker unknown
#40

No, no. What I mean is the orders we've booked so far this year — the order inflow.

Speaker unknown
#41

No, this new order.

Speaker unknown
#42

Order intake came in at a new level.

Speaker unknown
#43

My estimate would be roughly INR 4,000 crore.

Speaker unknown
#44

So this is the EPC value, correct?

Speaker unknown
#45

3,700. The EPC figure stands at 3,700. We had given our investors guidance of roughly INR 5,000 crore. We've already hit INR 3,700 crore, and roughly four and a half months still remain.

Speaker unknown
#46

All right, thank you, sir. I’ll rejoin the queue.

Speaker unknown
#47

Glad to be here.

Speaker unknown
#48

Thanks. Our next question comes from Prince Chaudhary at PINC Wealth. Please go ahead.

Speaker unknown
#49

Hello.

Speaker unknown
#50

Hello.

Speaker unknown
#51

Hello there. Yes, hello sir. I have a question about that T&D order we won not long ago. I'd just like to get a clearer picture of what kind of contract this is. Will we actually be the owner of the transmission asset, or is our role limited to EPC work only?

Speaker unknown
#52

We're going to do both. We've taken on a project as a developer, and we will handle the EPC work on it. There's a distribution job we have to carry out in Velgaon, which sits in Maharashtra. What we have to do here is fix the 400 kV substation. We've done plenty of utility shifting in the past as well. On this one, we are set to receive INR 58.5 crore in annuity each year from the Maharashtra government across the next 35 years.

Speaker unknown
#53

Sir, ROE is going to be regulated at roughly 12%. Would it be fair to read it that way?

Speaker unknown
#54

Possibly even stronger than that. The return on equity would come in higher.

Speaker unknown
#55

Right, sir — on the renewable side too, we’d need to build a solar park and hook it up to the grid, and we’d own that asset. Is that how it works?

Speaker unknown
#56

That’s precisely right.

Speaker unknown
#57

What price per unit of electricity will we actually be charging?

Speaker unknown
#58

The range is INR 2.72 to INR 2.84.

Speaker unknown
#59

In certain cases, the government supplies the land, and there the tariff comes in lower. On the other hand, in places where the government isn't supplying land, we have to lease it ourselves, and there the tariff runs higher.

Speaker unknown
#60

Sir, have we signed any PPA yet, or will that happen only after we develop it?

Speaker unknown
#61

No. Obviously, absent the PPA, development won't happen. We're waiting on that PPA. The letter of award has already come through. The PPA itself, we expect to have shortly.

Speaker unknown
#62

All right. And sir, once that solar power is generated, will we also be building a transmission asset for it, or will someone else handle that?

Speaker unknown
#63

No. These need to be hooked up using the 11 kV wire. That's within 1, 2, or 3 kilometers. It isn't a major undertaking. Beyond that, should a transmission line be involved as well, we're prepared to bid and secure that too.

Speaker unknown
#64

Alright, thank you. And sir, regarding order inflow, are we looking at it for the coming six months, or for the next 18 months? Along with the pipeline —

Speaker unknown
#65

Like I mentioned earlier, projects valued at INR 40,000 crores have already been quoted by us. Bidding activity is taking place each month on a large scale, and projects totaling INR 37 crores are already in our hands. Our guidance to investors was to secure roughly INR 5,000 crores, and four and a half months remain for us.

Speaker unknown
#66

Okay. Sir, given that we've been moving into renewable and also shifting our product order mix, are we going to see any margin improvement? Do you foresee the margin profile improving from here?

Speaker unknown
#67

We’ll certainly aim to do that. What we’re telling our investors is that guidance matches the margin we currently have.

Speaker unknown
#68

Sir, regarding how intense the competition is when we bid for the order — is it a case where we have to give up margin, or are we getting the orders at a good margin?

Speaker unknown
#69

I mentioned that we've submitted quotes worth INR 40,000 crores. At a minimum, we need to secure INR 30,000 crores of those projects. Our EBITDA margins are something we won't go below. On that point we stay consistent. Yes, we've been bidding more, and that's because we now have close to 10, 11 verticals. You can picture it — we've already quoted INR 40,000 crores. That doesn't mean INR 40,000 crores will come to us, since we aren't so aggressive as to chase those projects at any cost. Yes, it's very clear on our side that as a concessionaire we must have our IRR, and as an EPC player we must have the EBITDA margins.

Speaker unknown
#70

Right, sir, understood. Thanks. Appreciate you taking the question.

Speaker unknown
#71

Thanks. It’s a pleasure.

Speaker unknown
#72

Thanks. Before we move to the next question, a quick reminder for everyone on the line: you can press star and 1 to ask a question. Our next question comes from Bala Subramanian at Arihant Capital. Please go ahead.

Speaker unknown
#73

Good evening, sir, and thanks very much for the chance to ask. Sir, regarding the HAM project, the equity funding comes to roughly INR 870 crores of infusion across the coming 2 and a half years. Is that infusion to be met through accruals, and what roadmap exists for these infusions, and what amount of annual operating cash flows do we expect will be available for this?

Speaker unknown
#74

That's a solid question. There's still INR 788 crores left to be infused. What exactly is a HAM project? Sorry—could you folks mute yourselves? Apologies, go ahead. Right, so we need to put in INR 788 crores, and our aim is to infuse roughly INR 297 crores over the coming 3 months. Cash accrual is one route. The other is that by finishing the HAM projects, we can also secure refinancing. We face no shortage of ways to raise this money, since everything is already arranged internally. I don't see anything of that sort arising, because that INR 788 has to go in over the next 2 and a half years.

Speaker unknown
#75

Alright, sir. Sir, my understanding is that bids on tenders came to roughly INR 16,000 crores. Would you be able to provide that breakup by segment so we can see how it fits the inflow target of about INR 5,000 crores? The main emphasis is on the quality of inflows, which leads us to walk away from low-margin bids. If you could give some clarity on that.

Speaker unknown
#76

It falls across the road segment, the railway segment, and the renewable segment. On the road side, that could involve elevated work as well as bridges. Most of these projects would be HAM.

Speaker unknown
#77

Okay, sir. Sir, I believe net working capital days rose to 70 days in H1, versus 45 days in FY 2025. What's driving that mainly — specifically, are clients paying receivables more slowly, are we making advance payments to suppliers, or is inventory building up? And what's the target by the end of this year?

Speaker unknown
#78

Right. The working capital increase is mainly down to the scheme. Before 31st March 2024, there was a scheme where payment wasn't tied to milestone payments. After 1st April 2024, the government withdrew that scheme. Payments are now linked to milestone payments, and your average billing cycle has gone up. Beyond that, if you look, there's a 6% retention that NHAI has deducted from each bill, and that's adding to the working capital cycle.

Speaker unknown
#79

Alright, sir. Sir, this is my final question. Package 2 of the Jammu Kashmir Tunnel project is roughly 80% finished. Some challenges do remain, though. What are the main lessons learned, and how will you mitigate them for future complex projects?

Speaker unknown
#80

Working on that project taught us a great deal. The civil work on the project is already finished, and only the MEP work is now being completed. I believe it should be done within the next three months. We have also built a road inside. The tunnel is finished as well. Only the MEP work remains. Executing the project there gave us great exposure and was a great learning experience. The terrain was very tough. In fact, there is another package right next to ours that is not even 30% complete. We genuinely feel our teams have done an amazing job delivering this project.

Speaker unknown
#81

Understood, sir. Thanks.

Speaker unknown
#82

Thanks. Our next question comes from Vaibhav Shah at JM Financial. Vaibhav, the line is yours — please go ahead.

Speaker unknown
#83

Thanks for the follow-up. Sir, I wanted to ask about a couple of data points. Of that INR 1,000 crores in total receivables, what would our HAM receivables be?

Speaker unknown
#84

HAM receivables are sitting at just about INR 686 million.

Speaker unknown
#85

618 crore Indian rupees.

Speaker unknown
#86

Yes, that comes to INR 618 crores.

Speaker unknown
#87

All right. Sir, turning to the second point — when I examine the order book project by project, it's clear that work on Ramban Banihal has been moving at a notably slower pace, package 3 in particular. Going forward, how do you expect execution to unfold on these projects? Both packages of Ramban Banihal.

Speaker unknown
#88

That's a great question. At Ramban Banihal, the project was stalled for nearly 2 and a half months when a flood and a landslide hit. Our vehicles actually couldn't reach the site either. On top of that, during Operation Sindoor, the work came to a halt. It was disrupted for 4 to 5 months, because the people who had left the site — it was really hard to persuade them, those young boys, to bring them back, since they had been through a rough time. Even so, we've been quite fortunate here that we're in a position to finish our tunnel work over the next 3 months. As for the viaduct, that's genuinely a very challenging and tough job. Under the original tender, we were meant to build it using PSC girders. Carrying out PSC girders has become extremely difficult, since there's barely any room to launch them or cast them. So what we've done is switch to steel girders. With steel girders, what we've done is fabricate them in Samba and Punjab, then transport them to the site and launch them there. At this point things are very much under control, and we're aiming to wrap this up by March 2027.

Speaker unknown
#89

We're finishing that tunnel within the next 3 months.

Speaker unknown
#90

Sir, so the balance work comes to INR 385 crores across both projects. All of it will be finished by March 2027?

Speaker unknown
#91

About 20% of the tunnel work — roughly INR 180 crores — should be finished ahead of this March, and our aim is to wrap up all of it by February. Payment is expected to go out by March. As for the other project, whose total is INR 369 crores, I believe close to 54% of it is done, with 45% complete on the financial side. That one will run until March 2027.

Speaker unknown
#92

Alright. And second, sir, you said the equity that's still pending comes to about INR 788 crores. That applies just to the HAM projects, correct?

Speaker unknown
#93

Yes.

Speaker unknown
#94

What amount will you be putting in during 2026, 2025, and 2028? Could you give us annual guidance on that?

Speaker unknown
#95

When you consider how long these projects run, it's between 2 years and 2.5 years. In the coming 3 months, we plan to put in nearly INR 200 crores across VRK, Ludhiana-Bathinda, and Northern-Southern — those projects. How much will we be infusing in the next financial year? Second, we have a refinance opportunity on the completed HAM projects. 2 projects are already done. The third one will be covered next month. Through refinance, we can get to roughly INR 450 crore. That too — we'll only go for refinance once we're nearer to deploying the equity, since we're getting an attractive equity IRR. If we did it now, we'd have to park it in FDRs or similar. We'll take it at the point when the equity has to go in.

Speaker unknown
#96

Alright, then — sir, how much equity would the T&D projects need?

Speaker unknown
#97

It's nearer to — no, wait. The total would come to roughly INR 550 to 600 crores, right? We can share the exact figure with you. It's nearer to just under INR 600 crores.

Speaker unknown
#98

Over what time period do you need to put that amount to work?

Speaker unknown
#99

Two and a half years — that's the timeframe. This is going to take a while. With solar projects, getting the PPA signed is a lengthy process. For example, this work was allotted to us 3 months ago. Typically, a PPA takes 7 or 8 months to sign. After that, the project itself would run for another 24 months. So it will take considerable time. I mean, on project financing, we've already tied up with the banks, but we're just waiting on the PPA. Only once that PPA is signed will we move forward with it. Secondly,

Speaker unknown
#100

The figure covers,

Speaker unknown
#101

We also have 1.5 years in which to dilute another 8%.

Speaker unknown
#102

I didn’t catch that, sir. I also missed another 8%.

Speaker unknown
#103

We’ve diluted-

Speaker unknown
#104

Regarding the shareholding.

Speaker unknown
#105

Yeah.

Speaker unknown
#106

Right, got it. And sir, regarding that figure you brought up — INR 600 crore — is that meant to cover solar and T&D together?

Speaker unknown
#107

Correct.

Speaker unknown
#108

All right. And finally, sir, you said you're also open to certain opportunities abroad. Which verticals would we be looking at, and which geographies?

Speaker unknown
#109

Our geography is the GCC, and we're looking at opportunities in the EU and even Singapore. At the moment we're examining a civil infrastructure project that includes metro, railway, elevated highway, bridges — everything.

Speaker unknown
#110

Sir, considering how much opportunity exists within the country at present, what is driving our pursuit of international markets right now?

Speaker unknown
#111

Our plan was to begin with small steps—we’re not looking to buy up a great deal of business over there. Setting up a company simply takes time—considerable time—and we need to establish ourselves. Whenever the need arises, we wanted to bid on a very large project in the EU. But they made it very clear that, because of the legislation, Indian companies are unable to build there. We want to set up our company abroad as a footprint so that whenever it’s needed, by taking a PQ original company, they can also bid across other continents. And we want to de-risk and de-leverage ourselves, so that if at times there is less work or fewer opportunities in the country, we have an arm through which we can go and build there as well.

Speaker unknown
#112

Alright. And finally, sir, how is execution progressing on the metro projects? Are we bidding on additional metro projects, both underground and?

Speaker unknown
#113

Yes, we'll be putting in bids for additional underground and elevated work. We have been bidding as well. Both of those projects are performing very well. On one of them, we've already completed close to 45%; the other is at close to 35%. As you can imagine, operating in urban areas is always difficult. Securing land, and station land in particular, is always difficult. But yes, it's going well.

Speaker unknown
#114

And sir, you said you've put in bids totaling INR 14,000 crores, correct? None of those bids have been opened yet, right?

Speaker unknown
#115

This process isn’t quick. We recently submitted a bid with NHAI the day before, and then again last week — in fact, it was only Monday when we filed it. There are several bids pending with NHIDCL, roughly INR 2,400 crores and INR 1,200 crores. Their bid is between INR 300 crores and INR 700 crores, and that’s the sole highway project we currently hold. We keep submitting bids regularly. True, certain departments are slower to move.

Speaker unknown
#116

Sir, how did those INR 14,000 crores of bids you placed break down by segment?

Speaker unknown
#117

Roads account for nearly INR 8,886 crores. The remaining portion comes from railway, which is roughly INR 4,896 crores. What's left is the renewable segment, at approximately INR 600 crores.

Speaker unknown
#118

Alright, thank you, sir. That covers everything I wanted to ask.

Speaker unknown
#119

Happy to take that.

Speaker unknown
#120

Thanks. Just a reminder for everyone: to ask a question, press star and one. Our next question comes from Priyam Shah at Value Equity. Go ahead, please.

Speaker unknown
#121

Good evening, sir. I appreciate the chance to speak.

Speaker unknown
#122

Hello there, and thanks for joining us tonight.

Speaker unknown
#123

This relates to the new businesses we're planning, like renewables and T&D. If you could shed some light on that, are these more margin accretive than the businesses we have now?

Speaker unknown
#124

At first, I'd say yes. Let's carry it out on site, but our guidance to investors has always been that we aim to hold our EPC margin at 11.5%. We're being somewhat conservative in how we pursue additional margin. Sure, if that margin is there, it benefits both investors and us.

Speaker unknown
#125

Okay, so do we anticipate any kind of ramp-up in these new businesses? And going forward, are we planning to take on more businesses like these?

Speaker unknown
#126

Our bids will follow the EPC margins and return on equity IRR we require. Should those rates come through, then naturally we will bid for sure, but in the event they don't, we'll keep on bidding regardless. Yes, more projects are on our bidding list.

Speaker unknown
#127

No, that is a solid approach, sir. That is exactly the clarity we were after. Second, turning to our core business. Given the nice expected bidding and order expectations on this front, how much should we expect to win, and what would the likely success ratio be?

Speaker unknown
#128

NHAI has already posted data on its website regarding the new bids it plans to call before March 31. Approvals have already been secured for roughly INR 60,000 crore to INR 70,000 crore. Just yesterday, a list came out with three projects approved under the PPP business. It's the same situation. Until it's out, it's out. The tenders are out, and we've been bidding as well. On the probability of winning those tenders, I'd say that with the new circular now in place and the new net worth criteria, our chances are higher, since we rank among the top 10 companies, and if you compare us with them, we always stand a better chance of securing the tenders. We are considerably stronger and better positioned than our competitors.

Speaker unknown
#129

Alright, is there anything on the numbers you'd like us to highlight, or should we just hold off until we hear back from you?

Speaker unknown
#130

Yeah. Updates are something you'll want to hold out for.

Speaker unknown
#131

Alright.

Speaker unknown
#132

I really appreciate it.

Speaker unknown
#133

Alright, and finally, this concerns how our revenue is split. So we have one project segment made up of EPC, HAM, and BOT. And then the other segments are roadways, highways, metros, and T&D. Could you tell us what revenue mix you're aiming for over the next 2 to 3 years?

Speaker unknown
#134

At present, road and highway accounts for 64% of the revenue mix. Renewable sits at roughly 21%. Industrial infrastructure comes in at nearly 5%. Metros is 3.5%. Transmission distribution is 3%. Tunnel stands at 1.3%. Bus terminal is 1.1%. When you look at HAM, EPC, tariff-based, that's a separate one. HAM is close to 45%. EPC is nearly 25%. Tariff-based is around 24%. DBFOT is 1%.

Speaker unknown
#135

Yeah. How do you see that mix shaping up as we move through the coming 2 to 3 years?

Speaker unknown
#136

Looking forward, the response stays the same. Our bids will follow our EPC margins along with the equity IRR. That's what counts. We operate 11 verticals. Whichever segment we take on, we want our margins to remain intact. We have expanded to as many as 12 states. As a company, we're quite diversified. In terms of geography, we're very well positioned, and on the vertical side too, among companies of this size, we're one of those with the most verticals in which to carry out work.

Speaker unknown
#137

That's all from me. I appreciate you making the time to answer my questions so thoroughly. Many thanks.

Speaker unknown
#138

Thanks. I really appreciate that.

Speaker unknown
#139

Much appreciated. Since participants have no more questions, I’ll now pass the conference to Mr. Ramneek Sehgal for his closing remarks. Thanks, and the floor is yours, sir.

Speaker unknown
#140

Thank you very much, everyone. Once more, I want to express my appreciation to all the participants for being on today's earning calls and for making this such an engaging discussion. We stay committed to pursuing our business strategies, doing everything that is right, and continuing to deliver positive results. We hope all your queries have been answered well. If you have any other further queries, please feel free to reach out to the investor relation team at EY LLP. Thank you so much once again. Have a great day.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ceigall India Limited transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Ceigall India Limited earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.