#1

Good day, ladies and gentlemen, and welcome to the Q4 and Financial Year 2026 earnings conference call for Ceigall India Limited. Please be reminded that every participant line will remain in listen-only mode, and once the presentation wraps up there will be a chance for you to pose questions. Should you require any assistance during this call, just signal an operator by pressing Star followed by zero on your touch-tone phone. Kindly note that this conference is being recorded. I'll now turn the conference over to Mr. Arun Prakash of Edfactor PR. Thank you, and the floor is yours.

Arun Prakash analyst
#2

Today, joining us are Mr. Ramnik Sehgal, Chairperson and Managing Director of CGR India; Mr. A Sarvanan, CEO; Mr. Kapil Agarwal, the CFO; and Mr. Akshay Jain, VP Strategy and Planning. I should note that this conference could contain forward-looking statements regarding the company, and those are grounded in the beliefs, opinions, and expectations held by the company as of the date of this call. Such statements do not guarantee future performance and carry risks and uncertainties that are hard to foresee. We'll start the call with opening remarks from management, and after that we'll open the forum for the interactive Q and A session. I'll now hand the conference over to Mr. Ameek Sehgal for the opening remarks. Thank you, and over to you, sir.

Ramneek Sehgal executive
#3

Good evening, everyone. I'm glad to welcome all of you to the quarter four financial year 26 earnings call for Seagull India Ltd. Our financial results, investor presentation and press release have been posted on the stock exchanges and on the company's website, and we hope you've had a chance to go through them. The worldwide macroeconomic climate remains difficult: geopolitical ambiguity, inflationary pressure and supply chain uncertainties persist. Yet India needs to build, modern infrastructure keeps strengthening, and the growth story in this sector stays compelling. The tightening of technical and financial eligibility norms in the bidding process, a higher net worth requirement, additional performance securities and greater emphasis on PPP projects all continue to favor established players that have proven execution capabilities and credentials. These developments are a good sign for a company like Seagull, and we believe we are well positioned to capture a meaningful share of the upcoming wave of projects. At the macro level, India remains one of the fastest growing major economies, and the government's sustained infrastructure push, combined with the nation's energy agenda, provides a promising backdrop for the kind of diversified EPC and developer platform we are building at Seagull. Financial year 26 has been a strong year of growth for Seagull, driven by consistent execution across our core EPC business and robust order inflows across highways and urban mobility. The fourth quarter has been a strong execution quarter, and we are pleased with the way our projects have progressed throughout the year.

Ramneek Sehgal executive
#4

As of March 31, 2026, our total order book was at 18,554 crores. Order inflow for the year came in at 11,332 crores, well above the annual guidance of 5,000 crores for financial year 26, and roughly 35.02% of that inflow came from the renewable sector. We entered five new verticals during the year and expanded into three new states. That gives us strong revenue visibility over multiple years. In quarter four of financial year 26, we saw a high, healthy order inflow of Rupees 6,014 crores, spread across the renewable sector and the road sector. We remain confident about the inflow pipeline as we head into financial year 27 as well. The book to bill ratio stands comfortably at 4.8x. Across our verticals, we see no shortage of bidding opportunities. One of the key highlights for the year was the LOA for the Sahibganj Arira Bhatia corridor, which remains the biggest project — the single biggest project CECL has received till date. The total project cost is 21,160 crores. Quarter four of financial year 26 was a strong quarter for order awards. With meaningful inflow across our renewable and power transmission segment, we secured multiple solar and battery energy storage projects, further strengthening our presence in the energy transition space. I would like to highlight this strategic milestone, as it reflects a successful diversification into the high growth energy link sector.

Ramneek Sehgal executive
#5

These contract wins put us in a strong spot to take part in India’s growing clean energy push, giving us long-term revenue visibility. I’d also like to discuss a strategic diversification that stood out as a key feature of 26 financial air. We have achieved meaningful progress in renewable energy power transition, wind and turbine generator, and industrial infrastructure. Over the year, we won various awards for a solar Basin transmission project. These put the company in a position to gain from India’s energy transition and the expanding opportunity in entity based infrastructure assets. In addition, the Deni Amritsar Katra Expressway project reached COD successfully during the year, an important milestone in our project lifestyle. On the ham monetization side, I’m pleased to report that French and layer 26 was a defining year for US capital recycling strategy. We have entered into a binding document for Malodhobor Sadhu Vali as is with Neo Asset Management. This marks the first transaction of its kind for Segal. It validates our execute monetize recycle framework for Brinder Dhapani Jalbira Shah project. We have signed non binding offer and These are currently under due diligence. That said, we have a clear pipeline of HAM assets mortgages ahead of us on the renewable energy and power transition.

Ramneek Sehgal executive
#6

We've gotten the LOA for the solar park projects in Maharashtra and Madhya Pradesh; the Marina Solar Park Beds project in Madhya Pradesh is now included in our order book. PPAs have been executed for the Maharashtra and Madhya Pradesh solar projects, and work has begun. Progress is also being made on the 400kV substation in Maharashtra. Regarding the balance sheet, the company keeps up a disciplined approach to deleveraging. As of 3/31/2026, our standalone debt to equity was 0.2x. Consolidated, it was 0.6. We stay committed to optimizing our capital structure through standalone debt and deploying HAM onto the proceeds toward both growth and deleveraging. For financial year 27, we are guiding to a minimum of 15% revenue growth, with the renewables sector accounting for close to 20 to 25% of total revenue. Furthermore, as we build up diversification, EBITDA margin is expected to hold between 11 to 12.5%, and order inflow guidance is a minimum of 5,500 crores. Looking ahead, we remain focused on strengthening execution, expanding our order book, and building a diversified asset portfolio with long-term revenue visibility, while maintaining financial discipline and creating sustainable value for our stakeholders. We are confident about the momentum heading into financial day 27.

Ramneek Sehgal executive
#7

We feel that the mix of a robust order book, a better execution landscape, and our growing presence across sectors gives us an encouraging view of the coming year. I’ll now pass the call to our CFO, Mr. Kapil Agarwal, who will walk everyone through the financial performance in detail. Thank you very much, everyone.

Kapil Aggarwal analyst
#8

Thank you, Ramnik sir, and a warm welcome to everyone who has joined us today. It's a pleasure to talk through how we performed as we wrap up the fourth quarter and FY26. The fourth quarter has been a stretch of considerable execution momentum, as we capitalized on the strong contribution window, which allowed us to post our strongest quarterly showing of the year. In Q4FY26, our standalone revenue from operations came to INR1294 crores, compared with revenue from operations of 992 crores in Q4FY25, which works out to 30.5% YoY growth and demonstrates our capacity to scale operations efficiently through the peak construction seasons. That takes our total standalone revenue for the year to INR3869 crores, a healthy rise of 14.3% year on year. Turning to profitability, standalone EBITDA for Q4FY26 was INR183 crore, versus INR109 crore in the same quarter a year earlier, giving us a margin of 14.1% in Q4FY26. Our PAT for Q4FY26 came in at INR119 crore, a margin of 9.2%; for the full year FY26, our standalone EBITDA was INR487 crores, against INR432 crores in FY25, which yields a margin of 12.6% in FY26 versus 12.8 in FY25. Standalone PAT for FY26 stood at INR305 crores, with a PAT margin of 7.9%. Let me move to our consolidated results, which give a more holistic picture of the growing portfolio and SPV performance.

Kapil Aggarwal analyst
#9

Turning to Q4 of FY26, our consolidated revenue from operations came in at INR1386 crores, compared with INR1012 crores in Q4 of FY25, which works out to growth of 37.1% quarter on quarter. Across FY26, consolidated revenue rose 70.1%, reaching 4022 crores, versus 3437 crores of revenue in FY25. Consolidated EBITDA for FY26 came to 585 crores, giving an EBITDA margin of 14.6%. Consolidated PAD for FY26 was 309 crores, which translates into a PAT margin of 7.7%. On the operational front, our execution engine stayed robust, with 37 ongoing projects at present in various stages of completion. Our order book has now grown to 18,554 crores, which gives us multi year revenue visibility and makes this order book especially strong in how diversified it is. It is no longer only about routes and IBAs. We now handle a broad mix of projects made up of 19 EPC projects, Tan Ham projects, one DBFOT projects and seven Sarif base projects. Our footprint now covers critical segments such as tunnel, railways, metros, transmission distributions and renewables, which effectively removes our business's dependence on any single segment, with renewable accounting for 19% of the total order book. That brings me to the end of my opening remarks, and I would ask the moderator to open the floor for the QA session.

Kapil Aggarwal analyst
#10

I appreciate it, everyone.

Operator operator
#11

Thanks a lot, sir. Ladies and gentlemen, we're starting the question-and-answer portion now. If you'd like to ask something, just press Star and one on your touchtone phone. Should you want to drop out of the queue, press Star and two. Ladies and gentlemen, we'll hold for a moment while the queue lines up. Our first question is from Vaibhav Shah of JM Financial. Please go ahead.

Vaibhav Shah analyst
#12

Okay, starting with the international expansion. First off, what pipeline do we have in the domestic market as well as internationally? And what's your goal for the international business, let's say over the next 1 to 3 years?

Ramneek Sehgal executive
#13

Weber, that's a solid question. An office has already been launched by us in Singapore as well as Dubai. One CEO international has already been appointed by us, and that only drives the war position. We were somewhat slow, and we're holding until things calm down. And observe, since a renewable vertical has been entered into by us. So I think there are no dots of the what? Roughly 11 verticals already exist in Seagull at this point. So, you know, what counts is our beta margins and IRR at a concession level. So should that be achieved by us, then definitely we'll bid outside India as well.

Vaibhav Shah analyst
#14

Thanks. How big is our bid pipeline, split between domestic and international markets?

Ramneek Sehgal executive
#15

At the moment, the tenders we've quoted that are still under evaluation total what — 13,000 crore, plus the international ones. There was just a single tender internationally, and that was Shobha in Dubai, and one EU tender — Shobha's was roughly Dh250 million. And in the EU, it came to close to about 13,000 crore, which again is undervaluation, and that one is in Romania.

Vaibhav Shah analyst
#16

So these are part of this segment. That’s

Ramneek Sehgal executive
#17

It's one highway. So that's just one highway project, and it includes a highway, a tunnel, and bridges. One project. 17km 15,000.

Vaibhav Shah analyst
#18

Just one project?

Ramneek Sehgal executive
#19

Yeah, yeah, just one project.

Vaibhav Shah analyst
#20

Okay, so you need a bed, with — I think there should be a partner, right?

Ramneek Sehgal executive
#21

No, no, no, no. We have qualified the loan. Among the 12 bidders, ours was the sole qualifying bid. We stood as the only qualifying single company; the rest quoted as a consortium or something similar. If I'm not mistaken, that's the story. Okay,

Vaibhav Shah analyst
#22

It's not 13,000. So earlier, as was mentioned on the last call, we were considering growing the business gradually. That's on the international side. So if we win this order, it will be a very, very large order, a very large expansion in the international market — to almost 65% of the current book. 65, 70%. So how do you view that, or any risk? How do you foresee that?

Ramneek Sehgal executive
#23

Okay, so to start with, that piece is quite a conservative one. Securing L1 is really tough. And second, even if it happens, it's merely a 17 kilometer project for 30,000 crore. Whereas back in India, were I to take on a job like that, 17 kilometer would run to only about 6, 7, 800 crores, let's say. It's simply down to, you know, the EU, since costs there run high. Apart from that, we've carried out work far, far bigger than this one. And in terms of land size, linear land.

Vaibhav Shah analyst
#24

All right. So when I think about what's likely to open,

Ramneek Sehgal executive
#25

My sense is that they’re going to take a while. What I’ve been hearing is that it’s already been five months. And I believe in a month, the midwent will be done as well. So they do take quite a bit of time. There are about 12 bids.

Vaibhav Shah analyst
#26

All right, all right, all right. Turning then to the equity investment — which investments are we actually aiming at? What's the pending investment on both the highway side and the non-highway side? And how does the timeline break down year by year for that investment?

Ramneek Sehgal executive
#27

So over the next three years, we need to put in close to 2000 crore — 1937 crore. Since the IPO, we've put in more than 400 crore. And as I said, we've already sold three assets to NIO. Of those, we expect the first asset to be executed this very month. So more than 400 crore will come from NIO, which is additional cash. We have unencumbered cash sitting in our bank as of 31st March at just about 66 crore. An unencumbered FDR of close to 146 crore. So equity isn't an issue for Seagull. We have amazing cash flow available to us. And apart from that, we also have our cash pools.

Vaibhav Shah analyst
#28

So from 1937, what would we be left with? And

Ramneek Sehgal executive
#29

So I think the distinction with The One second — this is the hemp, just coming from these two. So almost 800cr is renewable. The rest is all ham road.

Vaibhav Shah analyst
#30

And both of them need to be in place for the next 3 years.

Ramneek Sehgal executive
#31

Over the coming 3 years — that's right.

Vaibhav Shah analyst
#32

Alright. Alright. And finally, on the revenue guidance you've provided of roughly 15% or more — that seems rather conservative considering how strong our bookings are. So what would we be aiming for internally?

Ramneek Sehgal executive
#33

That's a fair question. We tend to be somewhat cautious when it comes to the figures. That's why, on every occasion, you'd have heard me keep it in the 10% to 15% range. This time around, I've stated 15% at minimum. So we're anticipating strong results.

Vaibhav Shah analyst
#34

Thanks, sir.

Operator operator
#35

Thanks. Our following question is from Tej Pal Singh at Monthan Capital. You have the floor.

Tejpal Singh analyst
#36

Hi there. Can you hear me okay? Sir.

Ramneek Sehgal executive
#37

Yes. Hello. Yes, sir.

Tejpal Singh analyst
#38

Hello sir, and congratulations on those strong setup figures. First off, sir, my question is this: your bidding pipeline seems a bit on the aggressive side. Your order book is also expanding quite quickly. Yet when it comes to guidance, you're only indicating 15 to 20 — 15% growth. So those things don't quite line up. Could you shed some light on that?

Ramneek Sehgal executive
#39

If you look at our previous investor calls, conservative guidance was in the 10 to 15% range, and we've already hit that. So this time around, we've set guidance at a minimum of 15%. To stay on the conservative side, we're saying we'll easily reach 15%. But we have — I mean, this is the conservative side of our, you know.

Tejpal Singh analyst
#40

Alright. Alright. And sir, one more thing — even though we're well diversified across the segments, our order book is huge. So how do you intend to handle receivables and. Receivables and working capital days so that we can. We don't get stuck in the payment cycle. So that's how we can execute easily and comfortably.

Ramneek Sehgal executive
#41

That's a fair question. When the war broke out, our department, Morth, issued a notification — actually, they've now issued three separate notifications — and they've loosened up our billing plan. Previously, we had to hit the milestone before receiving payment. Under this, we can also receive multi payments. That should ease our cash flow as well. Beyond that, we've sold three assets. So over 400 crore will also come in from NIO once those assets are sold. Cash flow therefore won't be a challenge for single. We have very clear cash flow on our side.

Tejpal Singh analyst
#42

And sir, looking at it from a margin standpoint, which segments in our order book are accretive to margin?

Ramneek Sehgal executive
#43

Our guidance is for a double-digit margin in the 11% to 12.5% range. On top of that, we also generate earnings from other income.

Tejpal Singh analyst
#44

Our order book is broken into segments — there are several different ones. So which of these segments add to margin? If you could break out the margins for us.

Ramneek Sehgal executive
#45

No, no. Look, we always take a cautious approach when we guide. So what we'd tell the investor is somewhere in the range of 11 to 12.5%, plus other income — and that will come from, you know, selling these assets, like what we did with Neo, or some bonus, or money earned from FDR, or some royalties. So plain vanilla EPC would be at minimum between 11 and 12.5%.

Tejpal Singh analyst
#46

Okay. Okay. And sir, what portion of the order book comes from state governments and the central government?

Ramneek Sehgal executive
#47

Yeah. Yeah. When it comes to ham alone, there's just a single project, which is NPRDC. Every other project comes from nhi.

Tejpal Singh analyst
#48

Alright. Alright. Thank you very much, sir, for that brief reply of yours. And I wish you all the best going forward.

Ramneek Sehgal executive
#49

Thanks.

Operator operator
#50

Thank you very much. Ladies and gentlemen, if you’d like to ask a question, please press star and one. Thank you. Our next question is from Ishita Lodha of Swan Investments. Please go ahead.

Ishita Lodha analyst
#51

Hello sir, and thanks for the chance to speak — also, congratulations on a really strong quarter. To follow up on the earlier question: the 400 crores we're expecting from NIO, which quarter should we look for that in, and will it show up in our standalone books?

Ramneek Sehgal executive
#52

Regarding what we refer to as the first project, Malotwali, we anticipate it this month. So that one is going to land in this quarter. We're looking at the second quarter for it. As for Jalbeda Shabaz, that's expected during the third quarter. So each quarter, we receive an inflow.

Ishita Lodha analyst
#53

And that’s going to sit right upstream of the standalone books.

Ramneek Sehgal executive
#54

Yeah, that's right. That's right. That's right. That's right.

Ishita Lodha analyst
#55

Also, regarding this trade — the tables I've looked at show a sharp jump from 79 days to 1:38 days. So what's causing that?

Kapil Aggarwal analyst
#56

Yes, a couple of people will respond to that. Yeah. Essentially, if you look at just March—whatever we had built up, those payments get released by the department in April in the same manner. So the payments that are to be made to the creditors are tied only to the receivables. So accordingly, payment was made to the creditors in April as well.

Ishita Lodha analyst
#57

So how much had actually gone out to those creditors by April?

Kapil Aggarwal analyst
#58

Roughly 300 crores.

Ishita Lodha analyst
#59

And in the same way, revenue has also jumped sharply, going from 94 days to 133 days.

Kapil Aggarwal analyst
#60

The main reason for this was the withdrawal of that notification by the government in April 24. So what happened previously was that we were billing monthly, starting from first April. So. So it has now been tied to milestones. So since most of the projects Seagull is executing are in the range of more than thousand crores. So each project has a billing cycle of 10%. If you look at billing cycles above 100 crore. So that's why, since the number of projects being executed is greater in number. That's why the unbilled revenue has gone up.

Ramneek Sehgal executive
#61

However, this is going to get better, since monthly bills have already begun going out with a new notification. Things will pick up now. You will see that improvement in the quarter ahead.

Ishita Lodha analyst
#62

Thanks.

Operator operator
#63

Thanks. Our following question is from Dheeraj Kriplani at Avidis Park, on the line. Go right ahead.

Dheeraj Kripalani analyst
#64

Hi, I’m audible.

Ramneek Sehgal executive
#65

Alright, Ajik, go ahead — it's your turn.

Dheeraj Kripalani analyst
#66

Appreciate the chance to ask, and congratulations on the strong results. I have one question that's specific to the industry. So in SR26, how is NHA progressing when measured in kilometers and in value terms, and how do you see it developing from here?

Ramneek Sehgal executive
#67

When you look at NHI — starting this year, we began — there were plenty of strong projects that were out there, but everything was still working through cabinet approval. This quarter as well, we expect a solid volume of tenders. On top of that, we're bidding in renewables too, solar included. So NHI orders aren't the only thing we rely on. If you look at last year as well, the order book that came to us from renewables was supposed to. And the overall NHI pipeline stands at close to 2 lakh crore.

Dheeraj Kripalani analyst
#68

All right, so what was the volume, just like any other number?

Ramneek Sehgal executive
#69

So these are the numbers NH has posted on its own site, you know? And these—sorry for cutting in.

Operator operator
#70

You, sir — though something troubling is emanating from your mind.

Dheeraj Kripalani analyst
#71

Hi there, and thanks very much.

Operator operator
#72

Thanks. Ladies and gentlemen, if you'd like to pose a question, you can press star and 1. Mahesh Patil from ICIC Securities is up next with a question. Go right ahead.

Mahesh Patil analyst
#73

Yeah. Hi. So, congress on the various. First question is just on margins. So if you look at Q4, the last Q4 there was a significant increase. So is there any one-off, or is it just because of the execution that we have? And going forward, obviously you've added probably 11 to 10 and a half percent range, but are you seeing any intact, you know, RM cost, inflation, etc.? You can just do some detail.

Kapil Aggarwal analyst
#74

Looking back at last year — and actually, if you look at last year — we launched four HAM projects, and those have been a major contributor to the PAD margins. And obviously, the higher turnover is also one of the factors behind the rise in PAT — the company's overall PAT. So going forward, we're guiding our investors to a range of 11 to 12.5. We're deliberately staying on the conservative side. So we will definitely try to match those numbers in the quarters ahead as well.

Mahesh Patil analyst
#75

All right. So as of right now, we aren't seeing any effect on the quarters ahead. And when it comes to RM cost, inflation and so on — no further near-term challenges.

Kapil Aggarwal analyst
#76

The higher cost has already been offset by the department. They've already issued the circular for covering the escalation portion, and whereas previously it was tied to three months, it's now been put on a monthly basis. So whatever cost increase we can — that will ultimately be paid by the authority to the EPC contractor.

Mahesh Patil analyst
#77

Alright, sir, thank you. So my second question concerns the order book. If you look at the portion of the total order book for which the exhibition has not yet begun on those projects, how much of that order book can be expected to—you know, fresh projects that we can expect to kick off over the next, let's say, couple of quarters—do you have any figure for that?

Ramneek Sehgal executive
#78

As you’re aware, apart from the HAM project and efforts like Marina, work won’t begin until the transmission line is finished—and for HAMP, it won’t kick off until 80% of the land has been cleared for us. Still, the visibility we’ve provided as a minimum figure is already with us as revenue. And naturally, the more projects that get underway, the better those numbers will be.

Mahesh Patil analyst
#79

Alright, thanks.

Operator operator
#80

Thank you. A reminder has been given to everyone on the line. Should you want to pose a question, just press star and one. Maitricha from Sapphire Capital is our next questioner. Please go ahead.

Maitri Shah analyst
#81

Hi everyone, this is Audible.

Operator operator
#82

Yes, that's right.

Ramneek Sehgal executive
#83

Hello there, please proceed. Hi.

Maitri Shah analyst
#84

Hello there, and good evening. I have just one question, once more, regarding the margin. Over the last three years, both our gross margin and our EBITDA margin have been declining, and once again you have guided toward a significantly lower margin for FY27. Is any kind of competitive pressure behind this — why do you expect these margins to fall? And is that perhaps a little too cautious, or is this simply how our order book stands at present?

Kapil Aggarwal analyst
#85

So, ma’am, if you look at the prior year, there was income from bonus and royalty as well. So your comparison must take into account the bonus and royalty income too. Our beta from pure operations falls in the 11.12.5 range, which we have been consistently maintaining for the last three years. The other income always depends on execution and also on the royalty, which depends on the contract itself that we are going to the subcontract. So those two are not directly tied to operations and are uncertain in nature. So if you complete any project during the year and you receive an early bonus, that will raise your overall margins. But if you look at the margin from operations, it is more or less stable across the last three years.

Maitri Shah analyst
#86

I was actually talking about slide 41 in the presentation. So the royalty income will probably go into other income. But the EBITDA margins above those are also declining year on year. So I was just wondering, is royalty income being added to revenue from operations? That's what I was wondering.

Kapil Aggarwal analyst
#87

No, no—Beta Martin is holding steady. It isn't going down. And when you look at this year's figures too, our EBITDA margins have risen relative to last year.

Maitri Shah analyst
#88

Could you turn to slide 41 for a moment? Perhaps I'm reading it incorrectly. From where we sit on the consolidated side, margins are indeed declining. So

Kapil Aggarwal analyst
#89

Your FY24 margins include bonus as well, and FY25 also includes bonus.

Maitri Shah analyst
#90

So these bonuses get added to the revenue from operations?

Kapil Aggarwal analyst
#91

Regarding the revenue that comes from operations — yes.

Maitri Shah analyst
#92

All right,

Kapil Aggarwal analyst
#93

So in FY25, we had 20 crore in royalty and bonus, and even in FY24 there was a bonus for Kanal Pava that was—that was included as part of your EBITDA only.

Ramneek Sehgal executive
#94

And just to add, we also have certain awards in place. Yeah. Whenever we get that, it will also come straight to the bottom line.

Maitri Shah analyst
#95

I really appreciate it.

Operator operator
#96

Thanks. A quick reminder for everyone: to ask a question, press star and one. Our next question is from Modi Bhandari at IFL Capital. Please go ahead.

Mudit Bhandari analyst
#97

Hello, sir, and congratulations on the excellent 4k results. My first question concerns solar and the projects. As I understand it, we've already signed the PPA and TSA for these projects. So I'd like to know whether execution has begun, or whether any land acquisition or approvals are still pending for those projects.

Ramneek Sehgal executive
#98

That's a fair question. Solar Maharashtra has already begun — we've completed a lease for a project exceeding 50 megawatts. And we expect to secure more than 75 megawatts this month, and that project is already underway. Land development, fencing, and piling have all started. We anticipate delivering solid results to you within the next three months.

Mudit Bhandari analyst
#99

This figure applies to a single solar project, and separately to the two solar projects that are left.

Ramneek Sehgal executive
#100

We’ve got two projects here. One is a solar project in Maharashtra, and the other is in — there are actually two in Maharashtra, sorry, and one in Madhya Pradesh. Maharashtra — both of the solar-grade projects have kicked off, and in Madhya Pradesh the land leaching is underway. I believe that one will also be wrapped up within the next 10 days. Execution will get going there as well. And when it comes to tnd, TND is already — construction is currently in progress. We’ve already acquired the land; we purchased that land. Since, in solar, the land has to be bought by us, we have to clear the land, and site development fencing has already begun. We’ve already placed the order for the transmissions and GIS.

Mudit Bhandari analyst
#101

Understood. And regarding BS's Monera project, has that acquisition kicked off yet?

Ramneek Sehgal executive
#102

No, that project is going to take a while. Because the government — the tender was quite clear. The government has to give us the land, the transmission, connectivity and the PPA. So far only the LO has come in. The PP still hasn't been signed. And the transmission line tender hasn't even been received yet. So once that's finished, once the transmission line is done, that's the only point when the product will start.

Mudit Bhandari analyst
#103

Got it, sir. One question about the industry side of things. I realize we're not paying much attention to NHI road projects at the moment. Still, if you do bid, how do you view order awarding from NHI — both on timelines and from a competition standpoint?

Ramneek Sehgal executive
#104

As you know, we operate in a higher sector where we're building projects. Most of them exceed 2,000 crore. And we already have one 2,160 crore project and one 600 crore project of ZX crore Maibas, so we have a notch buff there and better because of the higher network. As a group, we have a very good network, and as a listed company this is on a better side. And going forward also, we're expecting a lot of good bids from NHI and we're looking forward to it.

Mudit Bhandari analyst
#105

I really appreciate it.

Operator operator
#106

Thanks, ladies and gentlemen — that wraps up the questions for today. At this point I'll pass the conference to Mr. Ramnik Sehgal for some closing remarks. Thank you. Sir, the floor is yours.

Ramneek Sehgal executive
#107

Many thanks to each of you. Once more, I want to express appreciation to everyone who took part in today’s earning calls, as you made this an engaging discussion. We stay dedicated to carrying out our business strategies and to continuing to produce positive results for our stakeholders. We hope every one of your questions has been answered. Should you have any additional questions, please reach out to the investor relations team at Ad Factor whenever convenient. Thanks again. Good evening.

Operator operator
#108

Thank you very much, sir. Ladies and gentlemen, that brings this conference to a close on behalf of Segal India Limited. We appreciate your participation, and you are now free to disconnect.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Ceigall India Limited transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Ceigall India Limited earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.