Home / Transcripts / Cipher Digital Inc. (CIFR) · August 4, 2026

Cipher Digital Inc. (CIFR) Earnings Call Transcript

August 4, 2026

NASDAQ US Information Technology Software earnings 65 min

Earnings Call Speaker Segments

Courtney Knight executive
#1

Hello, everyone, and welcome to the call where we'll be discussing Cipher Digital's business update covering Q2 of 2026. With me today are Tyler Page, our Chief Executive Officer, and Greg Mumford, our Chief Financial Officer. Our press release and presentation are available in the investor relations portion of the company's website, and a simultaneous webcast of this call is being provided there as well. I'd also like to point out that this call belongs to Cipher Digital. Recording it or reproducing it in any form is strictly forbidden unless we've given prior approval. Before we proceed, let me remind everyone that forward-looking statements are included in the discussion that follows, as well as in our press release and presentation. Cipher's financial outlook, business plans and objectives, other future events and developments, including statements regarding the market potential of our business operations, potential competition, and our goals and strategies, are among these statements, though not the only ones. The forward-looking statements and risks discussed on this call, including in response to your questions, reflect expectations held as of today. Unless the law requires it, Cipher undertakes no duty to update or revise them, whether because of new developments or any other reason. In addition, non-GAAP financial measures may come up in the following discussion; such measures might be used by us to explain how our business is managed and operated. Reconciliations of non-GAAP measures to the most directly comparable GAAP measures are provided. We encourage you to review those reconciliations, which appear at the end of the earnings release we issued earlier this morning. At this point, I'll hand things over to Tyler Page, our CEO. Tyler?

Tyler Page executive
#2

Appreciate that, Courtney. Good morning to all of you, and thanks for being with us today. My name is Tyler Page, and I serve as CEO of Cipher Digital — it's a pleasure to have you on our second quarter 2026 business update call. This quarter, execution throughout the organization has been outstanding, and we keep constructing in accordance with our transformational strategy. Over the last several months, one thing has grown ever more evident: every advance in our flywheel now strengthens the one that follows. Thanks to the leases we've executed, prospective tenants feel greater confidence about engaging with us. The financings we've closed bolster our position with capital markets and confirm the co-location approach we've set forth. Since we continue hitting construction milestones either on schedule or ahead of time, the big cloud providers are gaining trust in us as their partner of choice for the data center campuses they have coming up. Simply put, this operation grows by building on its own momentum, and those outcomes are starting to show, handing us an ever-clearer path toward expanding on a much bigger scale. For anyone just getting acquainted with our company, let me take a moment to explain what Cipher Digital looks like right now. We control every link in the chain for creating and providing fully turnkey data centers to hyperscalers — from securing land and power all the way through engineering, building, and running them — and that is exactly what allows us to move with the speed and accuracy these hyperscalers require. The result of all that work is a business that's steady, reliable, and built to last. We have three data center campuses under lease to a group of the most advanced technology firms anywhere, and that adds up to billions of dollars of contracted revenue locked in for more than the coming ten years. Beyond those first campuses, our pipeline keeps expanding — about 4.4 GW of developments we expect to pursue in the future — and that hands us years of forward visibility into growth well past what we've already signed. Now let's zoom out and take in everything we've assembled. When you put together what's operating, what's contracted, and what's in the future pipeline, the portfolio comes to roughly 5.3 GW of capacity spread over 11 sites. The bulk of that sits in our pipeline, and it represents substantial growth on top of the contracts we already hold. The remainder consists of the HPC capacity we've already got under contract, plus the older Bitcoin mining operations we run in Odessa. This portfolio is deliberately anchored in Texas, which remains its heaviest concentration. We recognized quite early that Texas was going to become one of the country's most attractive areas for AI infrastructure built at scale, and that view has since proven correct; over this quarter, we added as much as 1.1 GW of prospective future capacity in the state, coming from a newly secured 900 MW location called Apollo and a 200 MW expansion we have planned at Stingray, where we currently operate. Our future growth comes from several places, and we're in a really strong spot for all of them: we'll keep buying new sites, we'll expand the ones we already have, and we'll add behind-the-meter generation. That last one fits our sites especially well, and it isn't part of this pipeline yet. Now, let's look at the cash flow profile underpinning the contracted leases, which you'll find on slide five. Three data center campus leases are now signed, and from October 2026 through September 2036, those are expected to generate about $793 million in average annualized net operating income. This slide shows where our revenue model is headed — net operating income that is steady, predictable, and contracted, coming from long-term deals with counterparties that carry investment-grade ratings. As we enter the back portion of 2026, those projected cash flows are becoming real, with our first rental payments kicking off at Barber Lake and Black Pearl. And I'm happy to share that at Black Pearl, things are happening even faster than we had anticipated. Key second-quarter developments are laid out on slide six — these have created momentum and put Cipher in a strong position for the latter part of 2026 and going forward. To start, and this is the biggest item, I'm proud to share that we've delivered data center capacity early at Black Pearl, coming in 2 months before the planned date. Our tenant asked us to speed things up, so we amended the lease to accelerate the timeline for developing initial capacity. I'm glad to say that capacity has been delivered and rent has begun at that location. Let me take a moment to explain why this is significant beyond the headline. Signing a lease is something any developer can do. But delivering early — when a tenant requests a quicker schedule, and doing it without cutting corners or sacrificing quality — that's something far fewer can pull off. What we've now demonstrated is that across all our teams, Cipher possesses the operational depth to compress a delivery timeline whenever needed, with no compromise. There are a couple of ways that getting this done ahead of schedule helps us. For one thing, it strengthens how credible we look in the eyes of tenants — those we already have as well as those we might sign — so they feel more comfortable working with us at additional sites across our 4.4 GW pipeline. For another, it gives us an early demonstration of how well we execute on construction, which will help down the road when we seek financing, since we can now show a proven record of finishing on schedule. As we wrap up the remaining projects in our current slate and execute additional leases moving forward, we'll continue demonstrating what sets us apart in construction and execution, and every step will build on the one before it. Our landmark financing for the Stingray data center is the second highlight. We issued an $810 million bond offering, priced with a 6% coupon, and that money covers Stingray completely all the way to substantial completion. Greg is going to go into more depth about the financing when he speaks, but I want to point out that this third bond issuance at the project level came in tighter than our earlier bonds, and that happened even while credit market spreads were widening — which shows people keep having faith in what we're doing. Also, I'm happy to report we've picked up an option on a new site, and we're calling it Apollo. Since it's our 11th site, that name works nicely as a nod to Apollo 11 and to that same spirit of reaching for what seems impossible, the one that left footprints on the moon. By 2031, this location will deliver as much as 900 MW, and it sits fewer than 25 mi from San Antonio, Texas. Under ERCOT's updated interconnection process, we've submitted a studied load request for the site in Batch Zero, and given that the terrain is flat, ready for construction, and close to San Antonio, it suits a large-scale data center extremely well. Beyond that, we continue investing in our team. This quarter, Bill Blevins joined us as Head of Grid Strategies; previously he served as director of grid coordination at ERCOT, overseeing interconnections for large loads — experience that directly reflects how we approach interconnection across our entire pipeline. Mohamed Abouelella also joined us, arriving from Google, where his duties covered technical due diligence, design, and delivery for over 5 GW of data center capacity around the world. For 11 years he worked on designing Google's build-to-suit and colocation data center campuses, and we could not be happier to have that expertise on hand as we keep constructing and signing additional leases. Those are merely two among the numerous people we have brought in during this quarter, and they show how we are assembling the organization required to carry out gigawatts of HPC development in the years to come. We moved faster on delivery, got financing at a sharp price, locked in a new location under favorable conditions, and our team continues to improve — that combination is genuine compounding momentum in action. Now let's take a closer look at the development portfolio we hold today.

Tyler Page executive
#3

Beginning with Black Pearl, as we noted earlier, we signed a lease amendment with the tenant so that the timeline for developing the initial capacity there could be sped up, which the tenant had asked for. Our team, I'm glad to report, came through on that pledge. Capacity for the first data center at Black Pearl came online in August — a full 2 months sooner than the schedule we'd originally set — and rent at the site has now begun. Past that initial handover, the balance of the site keeps advancing nicely toward the very same deadlines and milestones we'd agreed to before. Mechanical, electrical, and plumbing fit-out is underway for the remaining data halls in phase I, and in parallel phase II is moving forward, with concrete foundations, structural steel, and underground electrical work all in progress. When it comes to procurement, we've locked in roughly 96% of the equipment needed for phase I and phase II combined, which gives us solid visibility into finishing out the rest of the site. Shifting to Barber Lake, we're happy to report that phase I — about 168 critical IT megawatts — is still on track, with rental payments anticipated to start in October. Beneficial use of the facility has begun for our tenant, including occupying part of the building and deploying network racks. We've also now locked in 100% of the equipment needed to finish the project, which gives us solid visibility of our path to completion. What a few months back was steel and open ground is today a data center campus moving toward completion. We look forward to sharing more updates on how Barber Lake is progressing in the months ahead as we work to deliver the first phase of data center capacity in September. Next we turn to Stingray, which keeps advancing through its early construction stages. Earthwork, grading, and pad preparation are all proceeding on schedule, and underground electrical work is now underway at the site. We expect concrete foundations and steel erection to get started in the third quarter. With the project now fully financed through substantial completion, and roughly 75% of the equipment secured, we're well-positioned to keep construction progress moving efficiently toward our expected delivery in the first half of 2027. We look forward to sharing updates on how Stingray is progressing as construction ramps over the quarters ahead. Odessa, the last Bitcoin mining site we operate, turned in a good performance in the second quarter. As of today, we're running 207 MW of capacity, producing roughly 11.6 exahash per second of total hash rate at a fleet efficiency of about 17.2 joules per terahash. During the second quarter, we mined approximately 346 Bitcoin at Odessa. Importantly, we don't expect further capital investment in this part of the business as we keep prioritizing HPC, and the level of interest we're seeing in converting Odessa to an HPC site is encouraging. We're in early-stage discussions with multiple prospective tenants, and while it's too early to share specifics, we look forward to providing updates as these conversations progress. Let's now shift to an update on our development pipeline. Let's begin with Odessa — that 207 MW location has been powered up and is running right now under a fixed-price PPA with Vistra Luminant. HPC tenant demand here has us excited, and talks are underway at an early stage with several possible tenants. The pitch is simple: because power is already flowing at this site, turning it into an HPC data center means a considerably faster route to power than what you'd see in a standard greenfield build. As for Reveille and Ulysses, both have full interconnection approval and sit outside ERCOT's batch process; at these locations we're in HPC hosting lease negotiations with a wide array of tenants, and our priority stays on landing the correct deal for Cipher rather than simply the first one on the table. Turning to the longer horizon, Colchis, Mikeska, and McLennan — which could total as much as 2 GW of gross capacity — are still progressing through ERCOT's interconnection queue. Since ERCOT should wrap up its batch process decision shortly, everything we're sharing reflects what we know as of today. At all three sites, the required deposits are in place, land is locked down, and the needed studies along with executed FEAs went to ERCOT before the deadline; we hold firm conviction that these three sites will make it into Batch Zero, and we can't wait to bring the market an update. Now let's step back and look at the whole portfolio as it stands today, plus what came in last quarter. On the operating and contracted side, the figure holds at 907 MW. From Reveille and Ulysses, we anticipate 270 gross megawatts arriving in 2027. Colchis, Mikeska, and McLennan should contribute a further 2 GW across 2028 and 2029. Then for 2030 and afterward, we anticipate energization at Milsing and at Apollo, our newest site, together with expansions at Barber Lake and Stingray, to bring as much as another 2.1 GW. Apollo and the Stingray expansion were both filed as studied loads in Batch Zero. The 500 MW Barber Lake expansion should land in Batch Zero, while Milsing should fall in Batch 1, since its studies are still being wrapped up. Cipher's portfolio as a whole now covers roughly 5.3 GW over 11 sites. We rank among the biggest hyperscale infrastructure developers in the nation, backed by a contracted revenue base in the billions, a pipeline measured in gigawatts, and a team that has demonstrated time and again, quarter after quarter, that it can transform opportunity into reality. That's the platform we've assembled, and in our view it's one that will shape the coming chapter of AI infrastructure growth in this country. With that, I'll hand things over to Greg Mumford, our CFO, to take you through financing activities, the capital structure, and second quarter financial results. Greg?

Greg Mumford executive
#4

Thanks, Tyler, and good morning to all of you. Tyler walked through the exciting momentum we're seeing across our development platform. What I'd like to do is call attention to the disciplined capital model that underpins that growth, along with the progress achieved during this quarter. As we've said on earlier calls, our approach involves financing contracted projects at the project level, keeping flexibility in reserve at the parent, and optimizing the capital structure once assets stabilize. Barber Lake proved that these projects could be financed. Black Pearl showed this could be repeated. Stingray — our third successful project financing and the lowest coupon we've achieved so far — showed scalability along with improving capital efficiency. That trajectory leaves us more confident in our capacity to finance contracted growth and to fund investment in our development assets. Now let's look at where our capital structure and liquidity stand today. During June, we closed an $810 million offering of project-level senior secured notes, which funds development through substantial completion. That transaction covered roughly 98% of project costs and reimbursed Cipher for $56.7 million in project expenditures funded earlier. As with our previous transactions, the five non-call two structure keeps flexibility intact so we can optimize the capital structure once the asset stabilizes. The financing drew demand that was approximately 8x oversubscribed and came with a 6% coupon — our lowest so far; we've now closed three project-level financings that fully fund our contracted obligations through completion. Our notes are designed to amortize across the base lease terms, matching debt service with the cash flow the leases produce. At the corporate level, we hold a four-year committed revolving credit facility of $200 million, plus a $50 million accordion feature that supports working capital and LC issuance; we also have two unsecured convertible notes totaling $1.47 billion. As of June 30th, 2026, the aggregate principal amount of corporate and project debt outstanding came to just over $6 billion, and there were no cash borrowings on our revolver. Let's move on now to a review of our financial results for the second quarter of 2026. Revenue in the second quarter reached $25 million, a decline from $35 million in Q1, which reflects the decommissioning of Bitcoin mining at Black Pearl, consistent with our shift toward contracted data center revenue; during the quarter, we reported a GAAP net loss of $268 million, or $0.65 per diluted share, versus a GAAP net loss of $114 million, or $0.28 per diluted share in the prior quarter. The sequential rise in net loss was mainly attributable to a $150.5 million non-cash warrant remeasurement loss, against a $43.6 million non-cash gain in the quarter before. Compensation and benefits climbed $7.4 million quarter over quarter, largely reflecting greater stock-based compensation, related employer payroll taxes set off by equity vesting, and ongoing investment in the team needed to execute on our contracted portfolio and development assets. As Tyler noted, these hires were essential additions, bringing expertise that will prove instrumental as we keep executing and scaling as a best-in-class HPC developer. General and administrative expense grew mainly because of higher legal, insurance, and other costs tied to the continued build-out of the platform. Turning now to items beneath the operating line: during the quarter, interest income came in at $36 million, which mirrors larger average cash balances after the Black Pearl and Stingray financings. Interest expense reached $67 million, compared with $59 million in the prior quarter, driven by a full quarter of interest on the Black Pearl Compute notes. Let's now move to our balance sheet dated June 30th, 2026. We ended the second quarter with total assets of $7.5 billion, an increase of $3.2 billion, or about 75%, versus $4.3 billion on December 31st. That growth largely tells the tale of capital raised and capital deployed. First, let's examine the financing proceeds. We closed the Black Pearl Compute notes in February, and we closed Stingray in June. Combined, those transactions pushed restricted cash to a total increase of $1.7 billion. After accounting for cash deployed during the year, that amounts to $1.4 billion in current restricted cash and $264 million in non-current debt service reserve funding. As of quarter end, restricted project cash came to roughly $3.7 billion, which includes approximately $3.2 billion set aside for construction and approximately $526 million for DSRA and interest during construction funding. Unrestricted cash rose by another $204 million, reaching $832 million, aided by $289 million of CapEx reimbursements tied to the Black Pearl and Stingray financings. Our total unrestricted liquidity position was $870 million, made up of $832 million of unrestricted cash and cash equivalents plus $38 million of Bitcoin. This does not include undrawn revolver availability. We stay well capitalized to meet our near-term commitments, and given current forecasts, we do not anticipate needing additional equity. Second, let's examine the build, where we are solidly in execution mode. Property and equipment increased $1.5 billion- $2.13 billion. Construction in progress rose $1.4 billion- $1.68 billion, which reflects the concurrent construction ramp at Barber Lake, Black Pearl and Stingray. On the liability side, accounts payable climbed to $289 million at quarter end, versus $40 million at year end, while accrued expenses and other current liabilities grew similarly, to $357 million from $90 million. Both changes reflect the same story. The concurrent construction ramp across Barber Lake, Black Pearl and Stingray, together with the timing of project billings, accruals, and vendor payments. Simply put, these are the balance sheet dynamics you would anticipate from a company in active construction mode. The company keeps making strong progress across the development platform, and from a liquidity standpoint we remain well-positioned to keep executing and invest in future growth. Before we open the call for questions, I want to restate our commitment to disciplined execution, capital allocation, and delivering long-term value for our shareholders. To put the quarter in context, we now have a 4.4 GW pipeline, a financing model that has proven itself 3x over, and the liquidity to remain agile. We look forward to updating you on our progress in the quarters ahead. Thank you for your continued support. Tyler and I would be pleased to take your questions.

Stephen Byrd analyst
#5

Oh, hi there, and good morning. This is Stephen Byrd here, in fact. I really appreciate it. Nice work on what is genuinely a positive set of developments. Am I coming through clearly?

Tyler Page executive
#6

Yep, I can hear you, Stephen.

Stephen Byrd analyst
#7

All right, great. First off, I'd like to hear what your first take is. None of us has really had much opportunity to digest the letter Greg Abbott put out yesterday, I realize that, but I was hoping you could share your early thoughts and what they mean for Cipher. Clearly, you hold a number of assets spanning from ones that face zero effect and so could appreciate in value, all the way to ones sitting squarely in the middle of the process. Just wondering what your first impressions might be.

Tyler Page executive
#8

Yes, absolutely. Look, similar to many others, yesterday's letter from the Governor caught us somewhat off guard, yet I'd say it didn't catch us off guard given that the underlying theme aligns closely with the batch process and every difficulty Texas is currently grappling with. To be specific, Texas right now is the number one destination for data centers since it offers the finest conditions. Its framework is the best available. They've become somewhat a casualty of their own achievement as they work to trim the queue alongside the pure scale of development being pursued there. What I'd say is this amounts to yet another strengthening of the rationale behind the batch process, meaning that Texans, the Texas legislature, the Texas Governor, and the state's residents require a mechanism to figure out who is genuine and who will be a welcomed addition to the grid, to the neighborhood, and so on, versus who is less genuine and won't be, in a sense, meeting their duties as a good neighbor and a good grid citizen. The batch process had already been in motion. One unfortunate aspect, I believe, is that this Friday we won't receive the answers we'd been anticipating. The Governor's points strike me as truly significant ones, bringing attention to items such as auditing the attestations everyone has turned in to confirm they're legitimate and making sure people act properly by taking part in efforts like the water surveys he called out. For Cipher, let me point out, we've completed all of that. Water surveys have already been turned in by us, and we back every attestation we provided during the process. I think it's premature to say what the precise effect will be, beyond noting that I see three key points I consider regarding how Cipher could be affected. The first and biggest one is that no matter what the final process and timeline end up being, Cipher will be positioned at the front of it. Fine. Our team has outstanding individuals keeping watch on these developments. We aim to be extremely good neighbors, we aim to stay ahead of precisely the sorts of matters the Governor is calling out; generally we're in favor of any steps that help distinguish the genuine from the less genuine, since Cipher is genuine. Regardless of how the process wraps up, the sites we believe sit at the head of the queue are going to stay there as time goes on. We'll make every effort to guarantee that outcome. Another point worth mentioning, I think, is that we're already seeing client interest at locations where the Batch Zero process hasn't even been completed, and the demand backdrop is extremely robust and still growing. We won't receive the answer on Friday that we were hoping for, but whenever that answer arrives, the demand curve keeps stretching out further on improved terms, and our sites will be positioned at the head of that process. So in that regard, we're disappointed not to have an answer on Friday. Other than that, I believe we remain very strongly positioned in the process. The second takeaway, I'd say, is that the letter and the timeline now suggest that the worth of any near-term megawatts sitting outside that process has just increased. When it comes to how lease terms are developing — with rents rising, longer durations, triple net structures, et cetera — I've never witnessed a stronger environment for us. Remember, Cipher has 477 MW potentially available in 2027 outside of this process, and we're quite engaged in conversations with multiple tenants — potential tenants, I should say — at those sites, and logically the terms ought to get better if there's an uncertain timeline for going through the batch process; that's wonderful for our portfolio, to your point, Stephen. Finally, I'd mention sites where we plan to bring our own generation. Some folks would call that behind the meter, but any locations where we generate our own power, whatever we can accomplish on that front is likewise more valuable now. I'll repeat what I've said previously: all of our sites have the potential ingredients for that to be an enormous success; we have some of our finest people at Cipher working daily on the bring your own generation solutions. We have access to natural gas and very enthusiastic potential tenants for that. Stay tuned, because I think that is more valuable as well. Most of those structures envision setups where ultimately some of that generation can be exported to the grid. I think it aligns with the challenges Texas is attempting to address and certainly what the Governor's letter is attempting to address. The long answer is, it actually doesn't change anything about how bullish I am for Cipher. The short-term frustration is that we won't hear on Friday.

Stephen Byrd analyst
#9

Got it, that's really clear and well reasoned. Perhaps only a single follow-up regarding that final item you brought up, Tyler, concerning generation located behind the meter. I was hoping to get something like a temperature read from you on how significant that is for customers, in the sense of offering a location that is far larger than grid access by itself. There are additional benefits too. Basically, how enthusiastic are you about it as a tool that your customers are asking you to deploy, and how substantial might it prove as we consider your expansion?

Tyler Page executive
#10

It could be remarkably substantial. I say that since the basic components exist. What do I mean by the basic components? We have the highest-rated companies anywhere in the world, extremely keen on obtaining, I don't want to claim the maximum feasible, but very sizable data center capacity. We have locations with, say, easily obtainable access to remarkably vast amounts of natural gas. We are putting enormous effort into resolving every engineering hurdle, supply chain hurdle, financing hurdle that arises from combining, in a sense, generation building and data center building. In my view, the opportunity exceeds everything else in our portfolio. The way it ultimately materializes will hinge on numerous factors such as supply chain, financing, and engineering; giving precise projections on scale is premature for me, yet it could be gigantic.

Stephen Byrd analyst
#11

That's really useful. Thanks a lot.

Tyler Page executive
#12

Thanks, Stephen.

Paul Golding analyst
#13

Many thanks. Tyler and Greg, congratulations on the momentum and the impressive execution. My first question concerns Reveille and Ulysses. The 2027 energization goal remains on schedule. What's the status of talks with potential tenants at those two locations? You provided specifics about Odessa as a possible conversion site, and because the other two sites are not yet interconnect-energized — they are interconnect-approved, though — and have near-term energization targets, I'm curious how those discussions are progressing and how much you could begin construction ahead of energization in the event a deal were reached. I have a follow-up regarding Apollo. Thank you.

Tyler Page executive
#14

Certainly. I would say demand has never been more intense; we have several parties expressing interest in each site. As we noted, with demand rising like this and against the backdrop of, honestly, a fresh scarcity factor stemming from certain developments in the Texas approval process, we intend to secure the most favorable arrangement we can. The most favorable arrangement covers excellent structures, excellent terms, long-term leases, triple net structures, high rental rates; in addition, we are watching credit markets and what they imply for counterparty credit quality. Careful structuring to achieve the best lowest risk returns for Cipher is basically foremost in our thinking, demand is strong; it simply comes down to reaching a point where we choose our dance partner. I anticipate every one of those available megawatts will ultimately be leased.

Paul Golding analyst
#15

Excellent. Regarding Apollo, it's wonderful to see it made it into Batch Zero. Can you provide some background on how that possibility arose, and how you managed to pull off what appears to be its addition to the Batch Zero process while simultaneously working out that option?

Tyler Page executive
#16

Absolutely. I believe this genuinely demonstrates how strong our deal team is; they've been incredibly occupied as events have unfolded in Texas since we've witnessed — as I think we noted on an earlier call — every sort of opportunity emerging from the batch process. Once more, stepping back, the rationale behind this process involves figuring out who qualifies as a genuine developer, and one of the indicators employed for that purpose is whether they can put up the required collateral deposits, doing so promptly. The team has been incredibly occupied; we turned down a huge number of deals that we spent considerable effort examining. This specific deal satisfied our examination standards and happened to match a very distinctive scenario that nobody but Cipher could carry out. This is a development site where a fairly substantial deposit needed to be submitted within an extremely brief window. Our team managed to conduct rapid examination, evaluate how likely the site was to land in Batch Zero, and could subsequently arrange a remarkably low price for the site, since we needed to assemble a sizable sum to submit the deposit quickly. We arranged it as an option. What's fascinating regarding the events tied to yesterday's letter and so on is that no money of ours is exposed. Should there somehow be a strange deviation or shift in how things unfold in Texas, we recover the entirety of our funds, the deposit we submitted, and so on. Exercising the option isn't required of us. Conversely, should matters advance as we anticipate they will at a reasonable pace, we consider this an utterly superb site obtained at an amazing price. I want to emphasize that it hinges somewhat on what ultimately emerges regarding the broader advancement of the Texas process. I believe the more significant takeaway — something I frequently attempt to convey to our stockholders — is that we aren't a closed-end fund holding just a few development sites. We possess a genuine growth equity narrative. Our team will keep sourcing top-tier deals in which we manage downside exposure and generate an exceptional ROI, and this deal exemplifies exactly that. This site excites me. I'm hopeful we receive more definitive guidance concerning Texas soon. Should that not happen for whatever reason, one key point shareholders ought to carry away is that Cipher is capable of putting together highly advantageous arrangements regardless of market conditions, and it confirms the position we hold within the sector as a collaborator others are eager to engage with — an entity able to act fast, operate with sophistication, command access to capital, and so forth. Enthusiastic about Apollo. Eager to see where matters head.

Paul Golding analyst
#17

Thanks, Tyler. Congrats again.

Tyler Page executive
#18

Thank you.

Bill Papanastasiou analyst
#19

Bill, thanks for the kind words about how we performed at Black Pearl and our willingness to accommodate what our tenants asked for. It's also nice to be participating in this call again. Tyler, since you're the one actually on the ground, I'd love to hear your take on what demand looks like right now and how the pipeline has been developing lately. In deciding which tenant to bring in next as a partner, what factors is the team weighing? Is the vision to serve primarily as a launching point for a single anchor tenant, or does spreading risk across multiple tenants come first? What's your approach there? Thanks.

Tyler Page executive
#20

Bill, I'll respond first, and after that I might turn things over to Greg so he can add some perspective regarding the financing markets, since those keep shifting and play a significant role in shaping our thinking here. To start, I want to draw attention to a point from my prepared comments earlier on this call: there's something of a flywheel effect emerging in our business, in which one win leads to another, which leads to stronger financing, which leads to additional transactions, and so on. For one thing, at our campuses we're partnering with the absolute top-tier tenants globally; meanwhile, the industry is flooded with accounts of projects running late, while we're finishing ahead of schedule. That makes us stand out. I can't stress this enough — I know there have been doubts about our schedules and whether they're too ambitious, yet despite those ambitious schedules, we've already completed ahead of time for a tenant that ranks among the most demanding anywhere. Naturally, achieving that calls for extensive, ongoing coordination with that tenant, including their engineers and ours, and it follows quite naturally that when we've had so much success and such a strong working relationship, our hope and aim is to conduct additional repeat business with those tenants, and I believe that will probably occur going forward. That being said, we have a strong reputation in this industry. Word gets around; we've witnessed a tremendous surge in incoming demand. You've all observed the signals from rising CapEx budgets among the hyperscalers. That lines up perfectly with what we're witnessing internally. Let me state this plainly: never before has the demand environment been this favorable. For developers, terms keep getting better. We need to set those improving terms alongside the way our model functions, which involves securing financing at the project level. In my view, today's demand conditions strongly confirm that we were right to concentrate on co-location and constructing fully turnkey data centers for the world's finest tenants, since those terms are now becoming even more favorable than what we were already receiving. Given the questions surrounding financing, and with growing amounts of debt entering the market in this sector, the co-location model remains extremely sound. So Greg, perhaps I'll turn it over to you just to give a bit of color based on what you're observing in the financing markets going forward, and perhaps how we're considering positioning ourselves.

Greg Mumford executive
#21

Absolutely. Tyler, thank you, and Bill, it's wonderful to have you joining us again; hearing from you is a pleasure. To build on that point, without question we're keeping a close eye on developments in the credit markets. Being able to go out and secure financing for these transactions is an essential element of what we do. Treasury yields are climbing; spreads are getting wider. There's definitely a substantial amount of supply when it comes to debt tied to AI infrastructure hitting the market. When supply grows, the natural expectation is that eventually investors become more selective about where their money goes. I believe this situation actually aligns well with our strengths and suits our model. To start, let me point out that the committed funding already secured for our current projects carries a fixed rate and is roughly medium term in nature. It's debt at a fixed rate over five years. Neither present rates nor today's market conditions have an impact on that. When we look ahead, in terms of how we genuinely approach analyzing a deal — you raised the question of whether we'd prefer to serve as a launch platform for a single tenant or instead consider some level of diversification — we assess every deal based on that particular deal and based on whatever market conditions exist at that moment. What I'm getting at is that we'll examine, above all else, how strong the counterparty is. That's essential. It also boils down to factors such as the development parameters. How complex is the design they're asking us to go out and construct, and what impact does that have on the supply chain? Does our team believe we can deliver according to the schedule we've proposed? Then there's the risk profile associated with the actual contract. We review every contract individually, and no two contracts are identical. There are various termination rights, various milestones, that sort of thing. When we finance each project, we want it to stand independently. That's the reason, up to now, we've completed all project-level financing on a non-recourse basis, and every one of them is structured so they amortize over the base term of the lease. Each project has to stand on its own, and it must produce appealing risk-adjusted returns. We'll keep evaluating tenants within that framework whenever we consider a deal.

Bill Papanastasiou analyst
#22

Thanks for those details, Tyler and Greg. At a broad level, what approach are you taking right now when it comes to chances in other states? That Ulysses project was acquired not too long ago. Does the power group see anything significant in Ohio, or in states besides Texas? Thank you.

Tyler Page executive
#23

Part of what makes this difficult is that rules keep shifting from one place to another. Ulysses was a facility located within PJM, yet it received grandfathering ahead of the new collateral deposit mandates there. Anything that lands on our desk gets reviewed. Without a doubt, the bulk of the team's attention during the latest quarter went to Texas, since everyone is preparing for the batch process, and some people might hold an excellent site yet lack the money to put up the required deposits. Sites everywhere get evaluated by us. Still, I would say Texas continues to be the overwhelming priority. As for the remaining sites we review, they tend to be spread fairly evenly among a small number of areas throughout the South and the West.

Bill Papanastasiou analyst
#24

Thanks, I appreciate that.

Richard Choe analyst
#25

Hello. I was hoping to hear a bit more about the way you managed to finish 2 months ahead of schedule. If a customer truly wants that, is it something achievable? Delivering that quickly generally seems quite difficult. I'd just like additional specifics on that; and after that, could you share any updates regarding how equipment is procured? Thanks.

Tyler Page executive
#26

Yes. At a high level, I want to praise the fantastic construction, engineering, and procurement operations group we have internally. Most of them came from hyperscaler backgrounds. They've been employed at those companies. They collaborate extremely effectively with the kinds of tenants we have. The actual key here involves roughly 2 factors. First, your team needs the ability to anticipate what's coming and to collaborate effectively with those kinds of tenants. We definitely possess that. I'd also point out that at that specific location, our arrangement includes a cap on expenses. Part of it is asking whether we could bring in additional burst labor to accomplish certain tasks more quickly. Clearly, we're willing to do so provided we can find a way to cover the cost, and usually that burden isn't ours. Past that, there are approaches such as using supply chain partnerships. The reality that procurement happens in-house and that we then have that group refining the design daily genuinely lets us collaborate with tenants. Can it be repeated? Yes, in the sense that the necessary ingredients exist — a team plus a tenant willing to pursue accelerated schedules — though there is a cost attached, and we would need to negotiate it. Another point as well: I don't believe you're necessarily pulling forward a whole data center build. All of these builds turn somewhat iterative as you move through the process. Change orders may come up. People may want to alter the scheduling of when items get delivered, which might not involve the whole data center. I do believe that, opportunistically, broadly speaking, it simply demonstrates what the team here can do, given that we managed it despite a backdrop of delays.

Richard Choe analyst
#27

No, that's fantastic detail and fantastic execution. Thank you.

Tyler Page executive
#28

Thank you.

Jon Petersen analyst
#29

Great, thanks. Perhaps picking up where we left off there. If things are moving faster than planned at Black Pearl, I mean phase I, does that mean phase II will also come in early? What's the right way to look at this?

Tyler Page executive
#30

No, I'd say it's reasonable to say that the remaining handover dates at Black Pearl are still unchanged for now. What happened here was getting one portion finished ahead of time so the tenant could be brought in and begin working on parts of it. As for the remaining handover timetable, our expectation is that it will come online on the very same schedule.

Jon Petersen analyst
#31

Okay. Regarding ERCOT's batch approval process, I realize much of it remains uncertain, but could you perhaps outline a base case expectation? What might a best case scenario look like for the news we could receive, I suppose, given delays stemming from the Governor's letter? What would the base case be, and what's the upside for you folks?

Tyler Page executive
#32

Look, predicting that is genuinely difficult, since over time that process has mattered enough to every interested party in Texas that it has typically been stretched out. Look, we had anticipated this Friday as the deadline for receiving results, which would have cleared a quicker route forward at the sites we believe are well positioned for baseload in Batch Zero. It's quite hard to say — this is pretty fresh, right? That letter appeared yesterday afternoon; we've definitely reached out to all our contacts in Texas attempting to get some read beyond the fact that it's clearly very serious, given the attention it's drawing. Making precise forecasts about the timing of what that implies is difficult. I'm somewhat repeating myself, but regardless of what that timing turns out to be, I expect Cipher to be extremely buttoned up about it and positioned at the front of the line. Right now, it's simply a bit too fresh for a serious forecast regarding timing. I just don't know whether it's like the Governor has asked for an audit of those waiting in the interconnection queue. How long such an audit takes, or whether we learn more about how significant and substantial it will be, might provide some signal on timing — yet it's too hard for us to forecast the precise timing. What I do believe will occur, though, is that logically such an audit would reduce the quantity of load in Batch Zero. Certainly the baseload portion. I think it will make it even more crucial that you're a development team that is extremely buttoned up and has dotted your I's and crossed your T's and paid your deposits. Again, that ought to strengthen our relative position. I simply can't forecast the precise timing since everything remains pretty fresh.

Jon Petersen analyst
#33

All right. Let me slip in a question about the balance sheet if I can. In your prepared remarks, I believe you mentioned that new equity wasn't part of your business plan. Was that referring to a shorter timeframe, or is the revenue you're bringing in now — with these projects starting to come online — enough that you can fund upcoming deals organically through recurring cash flow?

Greg Mumford executive
#34

Yeah. Hey, this is Greg. I'll take that one. I think it really depends on the moment and on what plays out in our development platform. Looking at the prior quarter, during Q2, we spent roughly $400 million on CapEx. Around $50 million of that went toward the development pipeline. That covers things like buying land, putting in electrical infrastructure, certain grade sites — essentially preparing everything to the point where it would be just as appealing to any tenant. Those CapEx outlays can go up or come down, and that figure doesn't include the equity down stroke you'd actually require if you went out and signed a really big deal, whether that's several hundred megawatts, all the way up to a gigawatt. Depending on what happens with the development pipeline and how leases come together, there could be a scenario later on where equity is needed. As for where we stand right now, we have $870 million of liquidity on the balance sheet. Our revolver is undrawn; to date there have been no cash draws on it. We feel really good about our position. We believe we could manage the sites directly ahead of us without having to access the equity market.

Jon Petersen analyst
#35

Great, thank you.

Mike Colonnese analyst
#36

Morning, everyone, and congratulations on the progress. My first question concerns the development pipeline. You've clearly assembled a very strong one. Based on your talks with prospective tenants for that future capacity, what key development milestones do you think must be hit before they feel comfortable signing a lease at a particular campus? And then it would help to know what share of the sites in your pipeline has gotten to a point where, as things stand, you believe they could be ready for lease execution.

Tyler Page executive
#37

Yeah, thanks, Mike. I'd say that historically, generally speaking, the dividing line has come down to whether the final interconnection approval is in hand. If not, you're still waiting on that key input. Looking at what we have available right now, again, that's Odessa, Reveille, Ulysses, 477 MW. Every one of those has cleared whatever milestones would be required to get a lease. What's left is whether we like the terms and the tenant, and whether we can work through the legal documents. My expectation is that all of them will be signed. On top of that, there's a newer development, and I think it says something about the demand environment. In the past, again, tenants weren't interested in discussing a site before interconnection approval. We've had tenants who are interested in sites awaiting Batch Zero. I think Colchis in particular is pretty juicy as a 1 GW site. We've already held lease discussions on that site with interested parties. We'll need to see how things unfold around the batch process. It's not inconceivable that we come up with some kind of condition precedent structure or something that lets us move forward, given that it's a 1 GW site; that said, this is all new territory and it speaks to just how serious the demand environment is. It kind of remains to be seen. The short, punchy answer is that the three sites with 477 MW available are all very leasable. It just depends on when we reach a deal we like. Beyond that, there's some upside as we wait on the process in Texas, and that's separate from any bring your own generation sites, which again carry some deal complexity. In general, the tenant's driving desire behind those structures is to get a more accelerated timeline. If we pull that together, the types of discussions we're having are: are there ways to get my first megawatts online in calendar year 2027? To do that, we'd have to make quick progress on a lease, just given building timelines. Again, kind of remains to be seen what the overall scope of that opportunity is, but it's very, very real.

Mike Colonnese analyst
#38

That's useful detail, Tyler — thanks for that. I've got one more question. It seems like there's a lot of solid interest coming your way regarding Odessa. I'm wondering how the timeline for delivering a data center might shape up if a lease were signed and that site were switched from Bitcoin mining to an HPC campus.

Tyler Page executive
#39

Right. A lot of it hinges on precisely when we'd reach a finalized deal. Clearly, at that location we already have a facility built — a containerized data center used for Bitcoin mining. Taking that site out of service ought to be fairly straightforward. If terms were settled shortly, we'd definitely be aiming to bring our first megawatts online during calendar year 2027. Whether that happens depends on completing a lease within the next couple of months, so we don't end up too far along — or rather, too near — on the construction schedule to have things ready. The target would be right at the end of 2027.

Mike Colonnese analyst
#40

Understood. I appreciate you answering my questions, and I wish you the best with those upcoming deployments.

Tyler Page executive
#41

Thank you, Mike.

Chris Brendler analyst
#42

Hi there, and thank you. Morning to everyone. Congratulations on everything that's been accomplished. The execution has been fantastic. About the specifics on equipment procurement that you're providing per site — those percentages are quite striking, and the disclosure itself is quite striking too. Could you offer us more of a qualitative picture of how that process is going? My guess is it's becoming increasingly challenging with all the construction demand that exists and for data centers. Would you share some qualitative remarks regarding the equipment procurement side?

Tyler Page executive
#43

Sure. First off, let me say that a major emphasis in certain hiring we did during the past quarter has involved building greater depth on our team around procurement work done internally. This differs from how our setup compares with most competitors. Procurement is outsourced by most of our competitors. That supply chain is still handled by us internally. Chris, one factor behind the greater transparency you receive from us is that we truly understand our procurement position at the sites. We aren't really at the mercy of market fluctuations, waiting and hoping for good news from whoever we've outsourced to. We've brought considerable depth into that team, since managing it is such a crucial activity for us. I should offer a general observation that demand appears elevated for basically everything. Without a doubt, occasionally something will prove tougher to obtain, and we'll encounter reasonable levels of inflation and cost. Broadly speaking, whenever we put together a construction timeline, we begin at the back and work forward from the items with the longest lead times, and typically those are settled and we understand our position prior to committing to a schedule with a tenant. So once more, speaking in broad terms, while we move through a building process, should some specific piece of equipment turn extremely sought-after and tougher to source, we can more or less navigate those difficulties.

Chris Brendler analyst
#44

That tracks. As a quick follow-up, assuming things move forward and we hopefully get more HPC agreements signed for these extra sites, should we anticipate a meaningful jump in power CapEx per critical IT? Does it stay near $10 million a megawatt, or does that figure climb from here?

Tyler Page executive
#45

Honestly, that hinges on what the tenant wants built. I've pointed this out occasionally when talking with investors — we go back and forth so many times regarding what a given tenant requires and how they view a specific site, and that's the real driver. We're also great at sourcing and nurturing our relationships, yet it isn't as though we're inherently far superior at securing a bargain on transformers; rather, we can sit down with tenants and say something like, "Hey, considering how reliable this site has been historically, do you truly need backup gens in the quantity your standard basis of design would specify?" Perhaps the response is no, and perhaps that results in a reduced price. What I can say broadly is that we're clearly seeing cost increases on labor and equipment everywhere. When we put together budgets for the upcoming build, I'd anticipate our budgeting to rise, and that likely means a greater cost per megawatt, at minimum to offset inflation. Any given site might land toward the lower end or the higher end of the cost curve.

Chris Brendler analyst
#46

Naturally, everything hinges on pricing—

Tyler Page executive
#47

We take that into account whenever we draft a lease proposal.

Chris Brendler analyst
#48

Right. Typically, you recover those expenses. All right, excellent. Many thanks. Impressive execution.

Tyler Page executive
#49

Thanks.

Analyst analyst
#50

Hello, and thank you for allowing me to ask. This is Michael Chen, filling in for John Todaro. Right. To follow up on what was said about procurement, in the past you have given CapEx figures in the $9 million-$11 million per megawatt range, and I realize much of the equipment is already locked in, while across the industry we have witnessed rising pricing pressure along with tighter supply. I'm wondering, as you evaluate upcoming leases and determine what equipment remains to be purchased, whether those costs are trending upward, and how much confidence you have that the band can still be met later on?

Tyler Page executive
#51

Yes. Well, when it comes to the builds we have underway, our budget includes contingency provisions for exactly this kind of situation, and given the inflation, I'd tell you we are currently at that contingency level. As we move forward, we are factoring in still more, since, like I mentioned, inflation is showing up everywhere for both labor and equipment. My expectation is that those figures will continue to rise. That said, for any given build spec, it's difficult to make broad statements, since the tenant's requirements are what drive it.

Analyst analyst
#52

Understood.

Tyler Page executive
#53

One more point I want to raise as well: bear in mind that at a number of our locations, we handle this by capping the CapEx to which we're exposed. Naturally, that isn't truly the case — what we're after is running things as efficiently as we can — and in certain structures, we also shift that risk over to the tenant.

Analyst analyst
#54

I see. That makes sense. Regarding Odessa, unless I've got this wrong, the PPA at that location was scheduled to run out. Do you have a deadline by which a lease has to be finalized, or did they sign the PPA again?

Tyler Page executive
#55

No; that PPA remains in effect until the close of July next year, meaning 2027. The appeal of that location, you see, lies in being able to convert it into an HPC site prior to the close of calendar year 2027. For any HPC lease at that location, a renegotiated PPA would be needed with Vistra Luminant, which sits alongside the site and supplies it with power. All of that would move forward alongside the lease negotiations that are required there.

Analyst analyst
#56

Alright, understood. Thanks.

Tyler Page executive
#57

Thanks to all of you for joining our call about the business update. At Cipher, what lies ahead looks incredibly promising, and we can’t wait to speak with you again before long. Cheers.

Operator operator
#58

This concludes today's conference call. Thank you for participating, and you may now disconnect.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Cipher Digital Inc. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Cipher Digital Inc. earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.