Good day, everyone, and thank you for joining the conference call and webcast covering i-80 Gold's results for the second quarter of 2026. Right now, every line has been placed in listen-only mode. After the presentation, there will be a question-and-answer session. Should you require immediate assistance at any point during the conference, just press *0 to reach the operator. Today is Tuesday, August 11, 2026, and this call is being recorded. I'll now hand things over to Katarina Rosa, Vice President, Investor Relations at i-80 Gold.

Caterina De Rosa executive
#2

Thanks, Operator, and good day to all of you. We appreciate you being here for our look at i-80 Gold's results for the second quarter. The presenters from the company with us today are Richard Young, our President and CEO, Paul Chawrun, our COO, and Ryan Snow, our CFO. Before we get started, we want to point out that certain remarks made today might include forward-looking statements, and those carry risk factors and uncertainties that may lead actual outcomes to differ materially. Kindly see yesterday's press release for the cautionary language about such forward-looking statements and the risks connected to them. What we say today ought to be considered alongside the company's Form 10-Q covering the quarter that ended June 30th, 2026, and you can find that document on i80gold.com, SEDAR+, and EDGAR. I'll now turn things over to Richard.

Richard Young executive
#3

Caterina, thanks. Appreciate everyone being with us today; let's begin on slide 3. For i-80 Gold, the first half of 2026 represented a significant inflection point, coming after the recapitalization we successfully finished during the first quarter. Now that the recapitalization is behind us, our attention is on delivering the development plan, and the progress achieved as we head into the second half of this year gives us encouragement. Our balance sheet has been strengthened, our key development projects have moved forward, we've produced encouraging results from the drill bit, and demolition has begun at the Lone Tree autoclave and CIL processing plant ahead of construction in the fourth quarter. Moving from toll milling to owner processing in 2028 will lift our cash margins by $1,000 to $1,500 per ounce. The technical work now under way across the portfolio is considerable in scale, and we keep adding technical, operating, and financial depth to our team so that multiple projects can advance at the same time. Permitting remains on track as well, and what we achieved in the second quarter continues to reduce risk in our development plan and keeps our Phase 1 projects on schedule, with the goal of raising annual gold output from roughly 50,000 ounces this year to 150 to 200,000 ounces in 2028.

Richard Young executive
#4

Simultaneously, we keep moving our project pipeline forward, which gives us a route toward organic growth reaching more than 600,000 ounces of gold by the early 2030s. With that said, I'll hand the call to Paul so he can give the project updates.

Paul Chawrun executive
#5

Thanks, Richard. To begin on slide 4 with Granite Creek Underground — the first project where we've generated gold. Development kept moving forward nicely over the quarter as the mine ramps up, pushing year-to-date advance to roughly 750 meters, which is over twice what we accomplished in the first half of last year. The main decline and the lateral work are both tracking ahead of the mine plan, which opens up more access to high-grade zones and helps the production ramp-up that's underway. At this point Granite Creek is far enough ahead on development to cover the rest of the year and beyond. Ground conditions in two of our highest-grade areas temporarily got in the way of mining, limiting access and pushing some high-grade tonnes into later during Q2. Access to those areas has since been restored, and they're now feeding into third quarter production. We typically have around 15 headings available at any given time, which is more than enough to support ramping production. Because of that, we look for grades and tonnes to be better in the third quarter. Roughly 72,000 tonnes were mined in total, including about 13,600 tonnes of sulfide material grading 6.5 grams per tonne and 12,000 tonnes of oxide material at 7.4 grams per tonne gold.

Paul Chawrun executive
#6

During the second quarter, output rose compared with a year earlier, reaching roughly 8,600 ounces of gold. On a year-to-date basis through Q2, we've produced about 17,500 ounces, which keeps us on pace to hit our 2026 guidance of 30,000 to 40,000 ounces. Turning to processing, we put through approximately 9,100 tonnes of sulfide material in the quarter. Tonnes processed came in below tonnes mined because of availability constraints at the third-party processing facility, and that led to a build-up in several inventories at quarter-end — including 5,300 recoverable ounces of gold that were in process at the third-party facility, plus another 1,800 ounces of recoverable gold sitting in inventory at Granite Creek. Mining unit costs came in at about $178 per tonne, consistent with plan. Finally, water management is staying well under control. Underground pumping capacity keeps exceeding inflow rates, and our second, larger water treatment plant along with two new dewatering wells are in commissioning right now; these will support the site's long-term water management capability and will ultimately draw the water table down beneath the underground workings. Moving to slide 5. The updated mineral resource estimate for Granite Creek Underground is now finished and will underpin the feasibility study that's scheduled for completion in the third quarter of 2026. Although the cutoff grade has come down relative to the PEA, allowing the economic areas to be mined to expand, we anticipate the reserves grade will line up with the average mined grades seen over the last several quarters.

Paul Chawrun executive
#7

During the quarter, infill and step-out drilling carried on across the OG, Range Front, and Adam Peak zones, with the focus on resource conversion and infill work to help with mine planning. Opportunities to grow mineralization in these areas and elsewhere are still coming into view. For the rest of the year, drilling kept its focus on delineation and resource expansion. Given the considerable potential at Granite Creek, evaluations of additional expansion campaigns are in progress for 2027 and beyond. Moving to slide 6. Underground development at Archimedes is still moving forward on schedule and mostly on budget. Underground operating costs align with the PEA, though we anticipate somewhat higher capital tied to surface infrastructure as we construct the Ruby site for the long term. Development productivity keeps gaining from favorable ground conditions and contractor productivity. In the second quarter, the main decline went on advancing faster than planned rates, and the exploration drift was finished ahead of schedule, putting in place the underground drill platforms needed to support definition drilling at depth. We are still on track for first gold mined from the Upper 426 zone in the fourth quarter of this year. Moving to slide 7. At Archimedes, we continue to see substantial potential for resource expansion.

Paul Chawrun executive
#8

At the start of the quarter, we finished infill drilling within the Upper 426 zone. We reported those results in June, and they confirmed solid grades and continuity across the planned mining areas, while also pushing mineralization past the existing resource boundaries. The drilling cut significant high-grade oxide mineralization that wasn't part of the mineral resource estimate behind the 2025 PEA, which gives us potential upside in the near-term mine plan. We think this emerging oxide opportunity at Archimedes could deliver meaningful, low-cost near-term ounces. We're continuing to move metallurgical test work and geological modeling forward, while the Archimedes feasibility study and the supporting tradeoff work will assess processing options for this oxide material, including the existing heap leach pad at Ruby and the CIL circuit at the Lone Tree plant. The 2026 infill drilling campaign began during the quarter from the exploration drift for the Lower 426 and Ruby Deeps zones, supporting an updated resources model and mine plan. So far, this campaign has moved a little slower than planned because of drill rig availability and contractor staffing constraints. Because of that, we expect the current campaign to run into early next year. Now, these are moderate delays. We have 7 rigs underground, and we're not able to run all of them 24/7.

Paul Chawrun executive
#9

But we are exploring options to finish that work, and it simply means the technical report will be pushed back a little so the drilling can be completed. As a result, the 2026 exploration guidance for Archimedes has been revised, and completion of the feasibility study is now anticipated around mid-2027. These findings, along with the encouraging drilling results already announced at Granite Creek Underground, keep underscoring the growth potential at both underground mines, which are now anticipated to supply the Lone Tree plant through the mid-2030s and perhaps beyond. Turning to slide 8. At Cove Underground, technical and economic studies carried on through the second quarter to further refine work supporting the feasibility study, which is expected late in the third quarter of 2026. Permitting work likewise progressed on schedule, encompassing baseline studies and technical reviews. At Granite Creek Open Pit, planning for a pre-feasibility study has begun, with technical tradeoff studies under way to refine the project design and economics. Early-stage pre-permitting work is also in progress, with baseline field studies set to begin in 2027 in support of an anticipated NEPA permitting process. On to slide 9. Mineral Point Open Pit falls within Phase 3 of the present development plan and ranks as the company's most valuable asset.

Paul Chawrun executive
#10

With the value proposition in mind, we keep evaluating ways to optimize how Phase 2 and Phase 3 of the development plan are sequenced. Late in the first quarter, a surface drilling campaign got underway, and roughly 15,800 meters of core and RC drilling were finished in the first 6 months of the year, with as many as 5 RC rigs and 2 diamond rigs deployed. The program has concentrated mostly on infill drilling to support classified inferred resources. Progress during the quarter also came in slower than planned because of drill rig and contractor staffing availability, along with drilling rates that were slower than anticipated through the softer Sandra dolomite. Management expects to raise the overall drilling rate over the rest of the year, and completion of this program is now anticipated late in the first quarter of '27. I want to stress that this is a large program, targeting approximately 300 drill holes across 131,000 meters, and it is designed to infill the inferred resources, to test opportunities for adding resources via step-out drilling beneath the existing heap leach pad, and to support geotechnical and metallurgical studies for the Mineral Point pre-feasibility, which is now expected approximately mid-2027, pending how this drilling campaign progresses.

Paul Chawrun executive
#11

Now moving to slide 10 and the Lone Tree processing plant. We put out a press release not long ago that highlighted how the refurbishment is coming along. The project is still moving forward on schedule, with first gold targeted for the end of 2027, and estimated project capital is still within budget — roughly 40% of capital had been committed as of mid-July. Demolition work on existing plant components that need replacing got underway in June and is continuing to track the engineering study schedule. Procurement packages that support the critical path are still on schedule, and about 50% of those packages, measured by value, had been awarded as of mid-July. Detailed engineering is advancing as planned, and the Hatch construction team was fully mobilized in the second quarter. Priorities for the third quarter include pushing detailed engineering to approximately 60%, substantially finishing the primary demolition, and awarding the key civil and concrete contracts. Permitting is still aligned with the construction schedule, with several permits received so far and others still pending. With that, I'll turn the call over to Ryan for the financial review.

Ryan Snow executive
#12

Thanks, Paul. If we move to slide 11, our balance sheet is still in a strong position. That's underpinned by the recapitalization we finished in the first quarter, better operations, roughly $17 million of restricted cash being released, and higher realized gold prices. We closed the quarter with a substantial cash balance of about $465 million. That's down from roughly $514 million at the end of the first quarter, and it's consistent with what we expected. We keep getting some of the proceeds we anticipated from the warrants tied to the November 2027 maturity date, and 8.5 million warrants were exercised in the quarter. At quarter-end, 152 million warrants remained outstanding out of the original 186 million. On top of that, we signed a termination and settlement agreement with Vox Royalty covering a gold offtake agreement. That gives the company more flexibility to manage future gold sales and stockpiling opportunities as we prepare for commissioning of the Lone Tree plant. The company believes that removing the offtake also delivers meaningful cash flow savings over the next 30 months. In March, we closed several financing transactions supporting the recapitalization plan, which brought total proceeds funded and committed to over $1 billion since May of 2025.

Ryan Snow executive
#13

Q2 marked the initial complete quarter in which these new financial instruments appeared on our balance sheet. I'd like to use this moment to stress that such instruments are recorded at fair value and get refreshed every reporting period to capture movements in metals prices as well as discount rates. Consequently, those revaluations are going to produce non-cash effects on our income statement moving forward. I'd also like to remind everybody that the $100 million accordion remains accessible to us under the gold prepay facility with National Bank and Macquarie Bank, plus a further $25 million is available from Franco-Nevada once we have spent the initial $25 million toward advancing Mineral Point. Turning to slide 12. For the quarter, company-wide gold production and sales came in at roughly 11,100 ounces and 5,300 ounces, respectively, versus 4,200 ounces and 8,400 ounces during the prior-year period. Across the 6-month period, gold production and sales reached approximately 22,000 ounces and 16,000 ounces, respectively, compared with about 14,300 and 13,400 ounces in the prior-year period. The gap between gold produced and gold sold comes down to the timing and availability of third-party processing. As Paul noted, work-in-process inventory presently stands at more than 5,300 recoverable ounces of gold.

Ryan Snow executive
#14

For the quarter, total revenue came in at a bit above $24 million, which brought our year-to-date revenue to slightly below $77 million. Those figures compare with $28 million and $42 million in the same periods a year earlier. The rise in 6-month revenue stems mainly from over 2,500 additional gold ounces sold thanks to the ramp-up at Granite Creek, along with the realized gold price climbing to almost $4,800 per ounce. That revenue pushed gross profit to $9 million for the quarter and $25 million year-to-date, and both are up substantially from the prior year. We recorded a net loss of $53 million, or 6 cents per share, for the quarter, and $131 million, or 15 cents per share, year-to-date, versus a net loss of $30 million, or 5 cents per share, and $71 million, or 14 cents per share, in the prior-year periods. The net loss stemmed chiefly from larger non-cash accounting effects related to revaluing our financial instruments, as we covered earlier, financing costs connected to the recapitalization, and higher pre-development expenses as we move the development plan forward, which we will start capitalizing once we publish feasibility studies and declare commercial production, with all of that partly offset by greater gross profit. Adjusted net loss rose to $41 million and $70 million for the quarter and year-to-date, respectively, against $27 million and $50 million in the prior-year periods.

Ryan Snow executive
#15

That matched what we had anticipated, and it shows pre-development, evaluation, and exploration work continuing to ramp up as we move several development projects forward. As a reminder, under US GAAP, which we transitioned to in 2024, pre-development, evaluation, and exploration costs are expensed until we declare mineral reserves. Cash used in operating activities rose to $50 million for the quarter and $95 million year-to-date, compared with $11 million and $34 million in the prior-year periods, mainly due to a comparative inventory build-up from third-party processing delays, increased pre-development, evaluation, and exploration outflows as we ramp up activities, and interest paid on the repayment of legacy debt, all partially offset by increased gross profit. Moving to slide 13. Looking ahead, we continue to see results from across the business trend in line with our expectations for the year, and we remain on track to achieve our 2026 guidance, subject to the following changes. Overall, growth capital expenditures are expected to be in line with the $150 to $175 million guidance range on an accrual basis. The Lone Tree refurbishment growth capital is expected at the bottom end of guidance on an accrual basis. However, we anticipate approximately $30 million in accruals, resulting in the cash expenditure being below the guidance range.

Ryan Snow executive
#16

When we went through the recapitalization planning earlier this year, management took a cautious approach to projecting what the refurbishment would cost in 2026, and that was to make sure the company brought in enough capital. For Archimedes underground growth, capital expenditures should now come in roughly $10 to $15 million above that figure, which reflects a shift in how we're approaching long-term surface infrastructure. On top of that, exploration expenses in 2026 are now anticipated to be about $10 million less, largely because drill rigs arrived late at the Ruby Hill property and contractors are short on personnel. Taking it all together, we still feel good about our 2026 outlook. What's driving these adjustments is mostly timing and where capital is being allocated, not any revision to our development objectives. With that, I'll turn the call back over to Richard, who will walk through the catalysts coming up.

Richard Young executive
#17

Thanks, Ryan. Wrapping up on slide 14. We've got distinct near-term catalysts inside the development plan that we expect to deliver over the coming 12 months. Among them: getting Archimedes, our second mine, into production; moving the plant refurbishment along toward commissioning; finishing feasibility studies across all three of our underground projects; and a pre-feasibility study for Mineral Point, our largest and most valuable oxide open-pit project. As those milestones are delivered, we think the gap will close between what the market currently values us at and the underlying worth of our asset base. Gold has traded with volatility this year, yet the longer-term picture for the metal stays constructive, and we keep our attention on what we can control: execution. We're really pleased with how the first half of the year has gone, and we stay focused on carrying that momentum forward. Thanks once more for your continued support. Joelle will now open the call for questions.

Operator operator
#18

Thank you. Ladies and gentlemen, the question-and-answer portion of today's call starts now. If you'd like to ask something, hit * and then 1 on your touchtone phone. A prompt will confirm that your hand has been raised. If you'd prefer to drop out of the polling process, hit * and then 2. When you're on a speakerphone, please pick up the handset before you press any keys. Our first question is from Justin Chan at SCP Resource Finance. Your line is open.

Justin Chan analyst
#19

Hello, Richard and the team. I appreciate you holding this call. To start with Granite Creek, it seems you've made solid strides on development. Is that tied to having more levels? Perhaps you could give a little more detail on the spots where ground control issues arose, how you subsequently rehabilitated them, and the access to your high-grade stopes? Was all of that within the South Pacific Zone? Maybe just to describe it, are you now fairly pleased with how the level development on the ramp is going and the access you'll have as you head into Q3 and the second half?

Paul Chawrun executive
#20

Yes, I'll address that question. The ground conditions were mainly driven by the fact that it took us some time to install a vent raise, and once that was done, it gave us access to a high-grade zone we had expected to reach during Q2. As it turns out, we're mining that area at present. It was simply a matter of completing a vent raise. Was that located in the South Pacific Zone? Actually no — it was in the OG Zone, though certain portions of the South Pacific also contain more challenging ground. In addition, for roughly two months, we experienced a minor rib failure, which is essentially the side of the drift. We then had to bring MSHA in, which we did, and obtaining clearance to mine that area took us a bit of time. Those areas are now being mined. As for all the development we've managed to accomplish, our real target is to reach a range of 10 to 12 headings, and at the moment we're at about 15 or 16, which will give us considerable flexibility in the mine plan.

Paul Chawrun executive
#21

To achieve that, we had to make progress on both lateral development and the main decline, and we've now caught up on those. As a matter of fact, we're caught up for the remainder of the year, and we'll continue doing some lateral development so that we're always staying ahead.

Justin Chan analyst
#22

Understood. Perhaps a quick follow-up regarding that idea. At any one moment, across the different stages of mucking and blasting, how many stopes would you be pulling from, relative to the figure of 15 available that you cited? And then, for the study itself, you gave a hint that the plan is to lower the cutoff grades, with grades sitting closer to what you have been mining. Does that match the high-grade ore you have been extracting? Since in your reporting you somewhat separate high grade from low grade, or ought we to model closer to the overall ore grades?

Paul Chawrun executive
#23

What I'm referring to is the high grade. It will be more in line with what we've seen over the last three to four quarters. The reserves estimate will roughly correspond to that, since in reality we're mining at about that cutoff grade. The PEA used a lower gold price and a higher cutoff grade. We simply want to give notice that the grade in the upcoming feas will align with that. Now, you brought up the 15 headings. When we shoot our rounds, cleanup typically takes about a day. We don't need to shoot 15 rounds at any given time, and that gives us plenty of flexibility to mine the given areas, depending on where we are in the mine plan. I hope that helps.

Richard Young executive
#24

Usually 10 to 12 headings would do the job, but at the moment we're sitting at 15 or 16, correct?

Paul Chawrun executive
#25

So 10 to 12 gives us plenty of flexibility. That's not something you need either. In the past, it was 5 or 6, right? That caused a lot of challenges and quite a few delays in the mining. Now we're well above that.

Justin Chan analyst
#26

Perfect, that’s really good to hear. Perhaps just one final question about Granite Creek, and after that I’ll hand the line over and come back on. I suppose what I’m asking is whether you’re considering a lower cutoff — say, more tonnes at the grades you’ve been mining recently — or tonne levels similar to those in the PEA on either a daily or an annual basis?

Paul Chawrun executive
#27

Comparable tonnage, I believe I'm permitted to state that.

Richard Young executive
#28

Nope — we'll see more tonnage at a reduced grade, with ounces coming out about the same.

Paul Chawrun executive
#29

All right.

Richard Young executive
#30

That's the destination we're heading toward, Justin. Both infill drill campaigns have largely validated—for Cove as well as Granite Creek, I believe—the ounce figures in the PA, more or less. With certain adjustments to modeled grades and reduced cutoff grades, the grades will come in somewhat lower.

Operator operator
#31

Don DeMarco from National Bank Financial has the next question — your line is open now.

Don DeMarco analyst
#32

Thanks, Operator, and good morning, Richard and team. Starting with Archimedes, I notice the FS timeline has moved to mid-'27 because of some contractor staffing constraints. Will this later study affect the mine ramp-up schedule at all, or the Lone Tree feed assumptions?

Paul Chawrun executive
#33

No. Really, it's just about completing all the technical work in time for feasibility status, but at the same time, we're stepping up the mine plans on execution and examining opportunities for 2027 to recover some of the oxide at site, as well as building up an inventory over at Lone Tree.

Don DeMarco analyst
#34

All right, thank you.

Richard Young executive
#35

Apologies, Don. I should also mention that the Upper 426 zone drill program finished earlier this year — regardless, it’ll supply feed for multiple years.

Paul Chawrun executive
#36

You've got it right.

Don DeMarco analyst
#37

Alright, so obviously at Mineral Point the recapitalization set aside certain capital for permitting and technical efforts. Could you sketch out which particular de-risking milestones investors should look for ahead of the upcoming study? I know there have been a few difficulties when it comes to drilling and that sort of thing. Just wondering whether you could map out those kinds of milestones prior to the next study. Thanks.

Paul Chawrun executive
#38

Prior to the study? The primary element is that we will keep this campaign going, and it covers roughly 430,000 feet. We'll put out results from that from time to time. After that, the key piece will be assembling that into a pre-feasibility so we could declare reserves at around mid next year. That depends on this program being completed. We have 5 RC rigs and 2 diamond rigs, and that ratio will shift over time. We're also looking at drilling at depth beneath the heap leach pad, attempting to get a handle on that, and likewise at possible expansion areas. Then in addition, making certain we are extremely thorough on the geotech so we don't need to return to the well. Really, from this point until the pre-feasibility study comes out, it's essentially drilling results and then maybe getting permitting underway.

Richard Young executive
#39

Work on the Met has begun.

Paul Chawrun executive
#40

The work on Met is now in progress. A number of composites have already been gathered by us, and we're going to be very thorough on that front. Those results will be released as they come in.

Richard Young executive
#41

Right. We’ve been collaborating with the community regarding the mine’s layout, and through those discussions we secured their approval on the placement of various facilities—waste dumps, leach pads, and similar infrastructure. Our progress with the community has been substantial, and it keeps advancing, since between Archimedes and Ruby Hill this will be the portfolio’s most valuable asset. Eureka is a small mining town, yet we intend to reinvest there and make it a highly appealing place for people to work.

Don DeMarco analyst
#42

That’s really good to hear.

Paul Chawrun executive
#43

Pre-feasibility is also going to assess several opportunities through tradeoff studies. For instance, possible improvements in silver recovery, and maybe gold recovery more broadly, examining crushing alternatives, and the chance for some optimization of the pit design. A range of tradeoff studies will form part of the pre-feasibility.

Richard Young executive
#44

To give you some context, that asset was originally Barrick's, and they carried out extensive technical work, so the project was already fairly far along by the time we took over that PEA. Steve Yopps, one of our board members, actually served as General Manager of Ruby from 2010 to 2014, during the period when all of that work took place. They ran into some of the same drilling problems with the Sandra dolomite that we're encountering today, but I believe Tyler has come up with a way to handle it.

Don DeMarco analyst
#45

All right, that's wonderful to hear. I'm eager to see all of that progress pay off. That's everything from my side. Thanks once more for answering my questions.

Richard Young executive
#46

Appreciate it, Don.

Operator operator
#47

At this point, I'll pass things over to Caterina so she can take the web questions.

Caterina De Rosa executive
#48

Thanks, Operator. There's a question that came in online, and it asks: 'Do you intend to stockpile sulfide material during 2027 so that there's sufficient ore available for Lone Tree in 2028?'

Paul Chawrun executive
#49

Yes. There are a number of distinct opportunities here. During 2027, we'll be accumulating sulfide from both Granite Creek and Archimedes, so that by the time the plant starts up at the end of 2027, we have enough feed for it. The second thing is that operating Lone Tree ourselves should deliver significantly better margins than the arrangement we have now. Assuming we can afford it — and we believe we can — that will be a big help. Then on the oxide side, yes, the high-grade oxide can be fed through the CIL. We're evaluating that. We're also looking at leaching at the Ruby pad, and there may be an opportunity there that could prove more economically beneficial than hauling it to Lone Tree. Either way, we'll be building up the high-grade oxide as well.

Caterina De Rosa executive
#50

Thanks. There's another question from the web. "Would September or October 2027 be a sensible assumption for when we'd begin running the high-grade oxides through the CIL plant at Lone Tree in order to confirm" — we actually just addressed that one. Sorry. Let me move to the second part of the question. "Has the availability of drilling contractors gotten better? Is there any risk to the Mineral Point schedule tied to hydrogeological drilling or geotech work for permit submissions, or is that for now more just a push within the pre-feasibility study?" Once again, it seems we've already covered it, but if you'd like to add anything further.

Paul Chawrun executive
#51

Turning to the geotechnical piece. Any extra drilling we might have to carry out would be from underground, and the reason is simply to let us assess a few alternative mining approaches. We haven't fully settled yet on whether that work is required. As for contractor availability, we're exploring options, though building up the crew will be difficult, since Mineral Point and Archimedes Underground together come to 14 rigs. That's a lot, and the work has to be done safely and effectively.

Caterina De Rosa executive
#52

Perfect. That covers all the questions submitted online, so I'll now return the call to the operator.

Operator operator
#53

That brings us to the end of the question-and-answer session. At this point, I'll hand things back to management for some closing comments.

Richard Young executive
#54

I appreciate everyone taking the time to be with us today. We're genuinely enthusiastic about how far we've come. With the recapitalization in place, we can now concentrate on execution. Those oxide drill results at Archimedes could meaningfully affect our production cash flows as early as next year. We're happy with how the team is performing, and with our capacity to keep hiring and keeping really strong people in Nevada. Thanks again to all of you for being here today, and should you have any follow-up questions, don't hesitate to contact Cat Whaley or Candeda, who joined us quite recently. Thank you for your time today.

Operator operator
#55

That brings today’s conference call to a close, everyone. We appreciate your taking part, and we ask that you disconnect your lines at this time.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete i-80 Gold Corp. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to i-80 Gold Corp. earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.