Home / Transcripts / i-80 Gold Corp. (IAU) · November 3, 2026

i-80 Gold Corp. (IAU) Earnings Call Transcript

November 3, 2026

Toronto Stock Exchange CA Materials Metals and Mining earnings 49 min

Earnings Call Speaker Segments

Operator operator
#1

Good day, and thank you for joining the conference call and webcast covering i-80 Gold's results for the third quarter of 2026. <<operator_script>> At this point, I'll hand things over to Caterina De Rosa, who serves as Vice President, Investor Relations with i-80 Gold.

Caterina De Rosa executive
#2

Thanks, operator, and good day to all of you. We appreciate your presence as we walk through the third quarter results for i-80 Gold. The presenters from the company today are Richard Young, our President and CEO; Paul Chawrun, our COO; and Ryan Snow, our CFO. Before we get started, please be aware that this discussion will contain forward-looking statements, which carry risks and uncertainties that might make actual outcomes differ materially. We therefore encourage you to consult the cautionary notes about those forward-looking statements found in yesterday's press release and in the company filings. Remarks made today ought to be considered alongside the Form 10-Q covering the quarter that ended on September 30, which you can find on our website, SEDAR+ and EDGAR. I'll now hand things over to Richard.

Richard Young executive
#3

Caterina, thanks, and hi everyone. If we look at Slide 3. This quarter we moved further ahead on our aim of becoming a multi-asset, mid-tier gold producer in Nevada. Every milestone we hit reinforces our record of execution and takes us one step nearer to unlocking the value in our portfolio. In the third quarter, we released the Granite Creek underground feasibility study. That study sets out maiden mineral reserves and lays out solid project economics, a higher production rate and a longer mine life than the March 25 preliminary economic assessment. Paul will walk through the drilling campaign now under way across the property, which is intended to underpin additional resource growth and reserve conversion so that the mine life at Granite Creek can be extended further. At our committees underground, development is still on track for first gold mining by year-end, which would bring our second high-grade underground project into production. Metallurgical test work finished in the quarter confirmed strong heap leach recoveries for the greater-than-anticipated oxide material that infill drilling in the upper 426 identified earlier this year. Putting that material on the existing heap leach pad should cut processing costs substantially over the next few years of oxide mining relative to the committees PA mine plan. At the laundry plant, refurbishment is moving ahead on schedule and largely on budget, with first gold pour targeted for the fourth quarter of next year.

Richard Young executive
#4

Loan Tree is the place where our production platform comes together, and it unlocks operating efficiencies from our 2 underground projects, producing stronger margins that should transform our cash flow profile. Across our 2 underground projects and Mineral Point Open Pit, the 2026 drill programs have delivered strong results, underscoring the potential to expand memory resources beyond what was outlined in the 2025 PAs. Permitting work across the portfolio also moved forward in line with our development plans. We also kept up discussions with our key stakeholders, especially in Eureka, the community neighboring our Ruby Hill property, to move long-term planning forward for our workforce housing and infrastructure buildup supporting planned project growth at our committees in the short term and mineral point in the medium term. Our team is advancing a clearly defined development plan aimed at increasing production and generating stronger free cash flows. Moving now to Slide 4. We updated our development plan after quarter end. Our near-term plans remain unchanged. That includes establishing our hub-and-spoke mining and processing platform, with Granite Creek and our committees feeding through the Loan Tree process land. 2027 will be a transition year for the company. We intend to keep ramping up mining at our 2 underground mines and finish the plant refurbishment to position i-80 to grow from a higher cost 400,000 ounce per year producer into a lower cost, 150,000 to 200,000 ounce per year producer beginning in 2028.

Richard Young executive
#5

Before Lone Tree is commissioned, we intend to accumulate refractory and oxide stockpiles over the course of 2027 to help the plants ramp up. At present, we are assessing when stockpiling should start, as well as the schedule and anticipated throughput for commissioning next fall. Exploration potential at both Granite Creek and our committees underpins the possibility of a longer-term fee base for Lone Tree. As a result, Cove underground has been moved later in the development sequence, positioned as a significant future source of refractory feed, probably in the latter half of the 2030s or beyond. Our Mineral Point open pit oxide project is the next major development project, and it supports our medium-term goal of 400,000 to 500,000 ounces of gold equivalent production by the early 2030s. Once Mineral Point is operating, we intend to develop the Granite Creek open pit oxide project, which supports our longer-term objective of 500,000 to 600,000 ounces of annual gold production by the mid-2030s. This growth is planned around assets we already own, in the top mining jurisdiction we know well. Our expanding team brings demonstrated mine building and operating experience and is focused on continuing to deliver consistent execution quarter after quarter as we build i-80 into a Nevada-focused mid-tier gold producer.

Richard Young executive
#6

Having said that, I'll hand things over to Paul, who will go through the projects one by one.

W. Chawrun executive
#7

Thanks, Richard. Moving to Slide 5 and Granite Creek underground: development underground remains on schedule, with close to 900 meters finished so far this year in the main decline plus lateral work needed to reach the ore. That gives us steady availability of roughly 12 to 15 headings, whether ore or waste, at any single time, which carries the mine plan through the end of the year and past it. Per the feasibility study, a main ventilation raise is slated to start late in 2026 and continue into 2027, forming part of our life-of-mine optimization. Mining carried on in the OG upper South Pacific and AutoZones across the period — although total ore tonnes of material mined came in below plan. The cause was heavy turnover among contract workers during the quarter, driven by tougher competition for experienced underground labor in the region. Material movement therefore dropped, which held back access to certain high-grade headings. Since then we've put in place a competitive retention incentive program, and contractor staffing has returned to a steady state that supports planned mining rates for the rest of 2026. Because of that, we anticipate both mine grades and tons rising in the fourth quarter. Tonnes mined totaled about 86,000, comprising 22,000 tons of sulfide ore grading above 8 grams per tonne along with 12,400 tonnes of oxide ore grading above 9 grams per tonne.

W. Chawrun executive
#8

During the quarter, we processed roughly 18,400 tonnes of sulfide ore. Processing fell behind mining because of constrained availability at the third-party facility, which pushed quarter-end inventories higher. At quarter-end, about 6,200 recoverable ounces are still in process at that third party, plus another 3,000 ounces sitting in finished goods inventory at the facility. Gold production for the quarter came to roughly 9,100 ounces, comparable to the prior year period and above the ounces mined year-to-date. For the full year, we anticipate landing in the lower half of our production guidance range of 30,000 to 40,000 ounces. Unit mining costs rose year-over-year, driven by higher contractor and labor costs along with lower mining rates. Even so, we expect to stay on budget for the year. Water management is still under control, since the existing pumping infrastructure can keep up with inflow rates, which remain at approximately 1,300 to 1,400 gallons per minute. We finished construction of the second water treatment during the quarter, and it is now being commissioned for water placement into the ribs. With 2 new dewatering wells completed this quarter, we expect treatment levels of up to 3,500 gallons per minute, which should begin lowering the groundwater table and ultimately enhance the long-term mining conditions of the life of mine plan.

W. Chawrun executive
#9

Now on Slide 6. Underground infill and step-out drilling at Granite Creek moved forward in order to aid resource conversion, mine planning, and ongoing resource expansion. Ever since mining started, delineation drilling performed ahead of mining — targeting roughly 40 feet of spacing — has repeatedly outlined mineralization beyond what the block model shows on each individual mining level. A multiyear drilling program that is expected to kick off in 2027 will involve additional drilling across 5 focus areas with strong prospectivity for evaluation: the South Pacific, Range Front, auto, and Ology zones, plus the high-grade CX zone located beneath the historic pit. In our view, these programs will grow the mineral resource we already have and extend the life of the mine. The Granite Creek feasibility study, released in September, made the mine plan stronger by way of improved geological definition, an optimized mine design, and higher mining rates stemming from changes to the ore access plan. Infill drilling enhanced continuity within the South Pacific zone and moved a substantial share of resources into categories of greater confidence. That underpinned a bigger mineable inventory and an 8.5-year mine life once more than a year of depletion since the PEA is taken into account. The revised plan allows for greater planned production with less waste development, supported by upgrades to dewatering and water treatment systems as well as less restricted ventilation.

W. Chawrun executive
#10

The study additionally factors in building up sulfide and oxide ore stockpiles during 2027, prior to lone trees being commissioned, which lets more material from Granite Creek take advantage of expected lower processing expenses and less dependence on processing by third parties. Moving to Slide 7. Work at our committees underground keeps showing solid execution, with unit costs mostly in line with budget and the first gold mine anticipated in Q4 of this year. That milestone is eagerly awaited and marks our second underground project entering operation. Underground operating costs stay consistent with the PEA, though capital costs are projected to come in somewhat above that, mirroring spending on surface and underground infrastructure needed to underpin long-term operations at the Ruby Hill property. Favorable ground conditions and contractor productivity enabled roughly 2,300 meters of development across the 9-month period, considerably ahead of the plan. Development in the quarter centered on pushing the main ramp forward, finishing lateral access for drilling platforms, and getting ready for ore mining this quarter. Beyond the waste development, drilling, and the exploration drift, the quarter's focus included installing key infrastructure like the completed backfill plant, ventilation raises, and the surface infrastructure. Infrastructure work will need to stay a priority in Q4 to prepare for the heap leach, further ventilation raises, advancement at the main dry facility, and planning and engineering for installation of the domain fan assembly area.

W. Chawrun executive
#11

The permitting work for our committees is moving forward as scheduled. Just to remind everyone, the project has its permits in place above the 5,100-foot level at our committees for starting production mining, which is roughly several years before mining begins. Under our revised stockpiling approach, refractory material from our committees is now planned to be stockpiled in 2027 so it can be processed at our wholly owned Lone Tree plant once that facility is commissioned, instead of being processed through a third-party facility, and mine plan optimization for 2027 is underway to account for this larger oxide resource in the upper zone. As Richard mentioned, we expect to start placing the oxide material on the existing leach pad at the Ruby Hill property by year-end. The oxide opportunity emerging at Archimedes could deliver meaningful low-cost near-term ounces. Metallurgical test work on the oxide material is complete, showing excellent leach kinetics and gold recovery at a sizing suited to the underground run-of-mine feed. We're pleased with how this project has advanced from a construction decision in September of '25 to expected first gold in just 15 months. Moving to Slide 8. Recent drilling at our committees has confirmed the grades and continuity within the planned mining areas from the PEA and has extended mineralization past the previous resource boundaries.

W. Chawrun executive
#12

During Q2, we kicked off the 2026 infill drilling campaign targeting the Lower 426 and Ruby deep zones, and we expect it to cover roughly 55,000 meters over 140 holes. Data from this program will feed into a revised resource estimate supporting a feasibility study that we anticipate in the second half of 2027. Right now, 7 rigs are drilling underground, and we expect to wrap up drilling in the second half of 2027. As the campaign moves forward, the company plans to publish results on an ongoing basis. Turning to Slide 9 for an update on the Lone Tree plan: we're happy with how the Lone Tree plant refurbishment is progressing, and it stays on schedule for first gold pour in Q4 27, in line with the execution plan set out in the December 2025 engineering study. Bulk demolition has finished, contractors are mobilizing for initial construction, and we're starting civil and concrete work. Engineering and procurement keep moving forward consistent with the project schedule. Management is likewise getting ready for operational readiness, the commissioning schedule, and the initial placement of operating personnel over the course of 2027. We continue to receive construction permits ahead of schedule, and the remaining routine operating permits keep advancing in line with the construction schedule.

W. Chawrun executive
#13

The total project cost is still pretty much in line with the $430 million capital estimate. By the end of September, 74% of procurement packages by value had been awarded, and 44% of total project capital was committed. Although 2026 cash expenditures are now expected to come in below the original guidance, we still expect refurbishment capital to be near fully committed by the end of the year, as we work towards securing a general contractor in December. Labor costs are running approximately 5% to 10% above the original estimates. However, those increases remain within contingency at present. Approximately 20% of total contingency has been used at quarter end, which places us in a great position as we head into the critical phases of the project. Turning to Slide 10. As Richard discussed, the Mineral Point open pit oxide project is our next major development priority. During the quarter, we completed approximately 26,000 meters of core and reverse circulation drilling focused on converting inferred mineral resources into the indicated category in preparation for a prefeasibility study. Drilling rates reached steady state during the quarter, with productivity improving significantly as additional rigs arrived. 9 drill rigs are currently active at Mineral Point, bringing the total across the Ruby Hill property, including our committees underground to 16.

W. Chawrun executive
#14

The first infill and step drill results from the East and North look encouraging—they point to possible extensions of mineralization past the 2025 PEA pit shell. Out of the initial 35 holes reported, 19 were drilled beyond the existing mineral resource, every one of them hit mineralization, and over half returned gold and silver intercepts greater than 150 meters. Of those, 15 tested the Eastern extension, 3 were to the north, and 1 was to the west. The eastern area offers the biggest expansion upside and has only seen Spire's historical drilling. Geotechnical drilling in support of the pre-feasibility study is finished. That study is expected in the second half of 2027, contingent on completing the wider drilling program. Early-stage pre-permitting work at Mineral Point kept moving forward. Formal permitting has not started yet. Moving to Slide 11. At Granite Creek open pit, preparation for a pre-feasibility study has begun, and early-stage pre-permitting activities are underway. Technical site investigation and baseline environmental work are expected to start in the first quarter of 2027, with engineering trade-off optimization studies to follow, and then completion of a pre-feasibility study technical report anticipated in the second half of 2027. We are presently working through operational and permitting requirements, followed by an expected EIS, which is currently projected to begin in 2027.

W. Chawrun executive
#15

Turning to Cove, over the quarter we kept moving forward on technical and economic studies for that underground project, optimizing the dewatering capital as well as a revised mine plan. Permitting approvals at both the federal and state levels in Nevada keep advancing. We expect the Cove feasibility study to wrap up in Q4 of 2026. As noted, the recent success at Granite Creek across our Communities underground mines has let us move Cove later in the development sequence, likely into the 2030s. With that, I'll pass it to Ryan.

Ryan Snow executive
#16

Thanks, Paul. Turning to Slide 12. Our balance sheet is still solid, helped by finishing the recapitalization during the first quarter, improved operations, and higher realized gold prices. We closed the quarter with roughly $411 million in cash. That's down from about $465 million at the close of the second quarter. Cash on hand is still consistent with what we expected, perhaps a touch better. We anticipate further funds from the gold prepay with the banks, the Franco-Nevada NSR, expected warrant exercises, and stockpile facilities. Combined, those sources could deliver as much as approximately $350 million in extra liquidity across the coming 18 months, which would help finance completion of the hub-and-spoke strategy and move the other pipeline projects forward through permitting and technical studies. Apart from the NSR, every one of those sources depends on lender approval, definitive agreements, or outstanding warrants being exercised. The company is also pushing ahead with talks on a corporate credit facility that could supply added liquidity, should it be needed, for developing mineral point. That will largely depend on gold price and other market factors, but we want to make sure we can fund mineral point without any further equity dilution.

Ryan Snow executive
#17

Turning now to Slide 13. Across the whole company, gold output and sales during the quarter came in at roughly 11,700 ounces and 7,750 ounces, respectively, versus 12,430 and 9,370 ounces a year earlier. Over the 9-month period, gold production and sales stood at approximately 33,650 ounces and 23,670 ounces, respectively, against about 26,250 and 22,720 ounces in the same stretch of the prior year. The gap between what we produced and what we sold comes down to the timing and availability of third-party processing. As Paul mentioned, work in process inventory right now holds more than 6,200 recoverable ounces of gold, plus another 3,000 ounces sitting in finished goods inventory. That puts total gold inventory held with our third-party processing partner at just over 9,000 ounces. Total revenue rose for the quarter, driven mainly by a higher average realized gold price, and for the year-to-date thanks to both that higher average realized gold price and more ounces sold. Those revenues produced a substantial lift in gross profit for the quarter and year-to-date. Net loss grew for the quarter and the 9 months, chiefly because of higher predevelopment expenses as we push the development plan forward, which we will start to capitalize once we publish feasibility studies and declare commercial production.

Ryan Snow executive
#18

Noncash accounting effects from revaluing our financial instruments, plus financing costs tied to the recapitalization, were partly offset by greater gross profit. Adjusted net loss rose for both the quarter and year-to-date compared with the same periods a year earlier. That matched what we had expected, mirroring the ongoing scale-up of our predevelopment evaluation and exploration work as we move several development projects forward, and it will keep going until we declare reserves at each project. We declared our first mineral reserves at Granite Creek underground, so starting in Q4 of this year we will capitalize qualifying costs tied to predevelopment, evaluation and exploration. As a reminder, under U.S. GAAP, which we transitioned to in 2024, predevelopment evaluation and exploration costs get expensed until we declare mineral reserves. Because of that, predevelopment evaluation and exploration costs for our other projects will keep being expensed until their respective technical reports are finished. Cash used in operating activities grew for the quarter and year-to-date, mainly from larger development, evaluation and exploration outflows as activities ramp up, along with interest paid on repayment of legacy debt, all partly offset by our higher gross profit. Turning to -- sorry, looking at 2026 guidance on Slide 14.

Ryan Snow executive
#19

We anticipate output landing in the bottom half of the range we guided, in part because of our choice to leach the oxide material from our committee on the leach pad we already have, instead of selling that material under the ore purchase agreement. Consequently, material put on the pad during Q4 of this year should have its production booked in Q1 of 2027. Given output in the bottom half of the guided range and a greater volume of lower-cost oxide material from Granite Creek than we had planned, we anticipate operating costs sitting at or under the bottom of the guided range. On the whole, sustaining capital, growth capital, and predevelopment expense should come in at the bottom of the guided range. Although the lone tree plant refurbishment remains on schedule, we are encountering a lag of roughly 4 months between commitment and invoicing or payment, instead of the 30 days assumed in the budgeting process. Exploration expenses should land under the guided range, largely because fewer feet were drilled than planned, stemming from rigs arriving late at the Ruby Hill property and from contractor personnel shortages that we discussed last quarter. These revisions largely reflect the timing of spend, since the company is still on track toward our development objectives.

Ryan Snow executive
#20

Richard, over to you now for the rest of the call.

Richard Young executive
#21

Well, thanks, Ryan. At this point, Joel, we'll turn the call over to questions.

Operator operator
#22

<<operator_script>> Our first question is from Justin Chan at SCP Resource Finance.

Justin Chan analyst
#23

First, just to clarify on our committees. Heap leach ounces will begin coming online, and some tons will be placed in Q4. I'm curious to get a clearer picture of the mining ramp-up, right? Will you be stoping in Q4? Or is it largely orphan development, and could you give us an early preview of how next year shapes up in terms of how much stoping ramps up versus mostly from development, and then the split you're expecting between oxides and sulfides, stockpile sulphides and oxides.

Richard Young executive
#24

Yes, absolutely. So to begin with, there's essentially no ore being produced from development, and we're already able to access it as of today—we can actually touch the ore. What we're doing, then, is carefully putting it onto the pad; as I said, it will be run of mine, and we've put substantial effort into the heap leaching to confirm we achieve solid recovery, since this material is great stuff. Regarding the sulfide-to-oxide ratio, our emphasis is on the oxide, though simply because of how the ore body behaves, we'll be mining through a portion of the sulfide, which will go into stockpile, and then around midyear we'll begin trucking that to Lone Tree, based on our stockpile capacity in 2027. As for mining rates, we'll be ramping up toward the end of the year, targeting roughly 1,500 tonnes per day—that's the aim. We'll keep pushing that higher into 2028. We simply need to stay prudent in our expectations regarding mining rates as we begin building up the contractor workforce; we also have, as we've described, certain challenges with the Eureka town, ensuring we have the right combination.

Richard Young executive
#25

So we don’t want to set our expectations too high there. But hopefully that addresses your questions.

Justin Chan analyst
#26

No, that’s excellent. And perhaps one quick follow-up regarding the rates. 1,500 by the end of ’27. What would be a reasonable kind of entry-level rate for going into ’27?

Richard Young executive
#27

Yeah. Right now we're probably sitting in that 700 to 800 range. We won't truly have a handle on it until we get started, since development is also a big focus for us. So I'm just attempting to give you an approximate idea of how much is going to be in the ore.

Justin Chan analyst
#28

Thanks. My second question is probably more for Ryan. On the CapEx timing, though — cash versus accrual for Q4 — will you still be accruing more than what goes out in cash? Or does that lag start to mean the two figures are equal, even with a delay? I'm just trying to get a sense of when those two will line up better. Is that Q4, or is it sometime next year?

Ryan Snow executive
#29

Justin, that’s going to happen at some point next year. We will certainly keep seeing the delay in Q4. We expect it will run through most of ’27. So in the end, we do anticipate that some cash outflows tied to the refurbishment will extend into 2028 as we make up for that timing gap.

Operator operator
#30

Don DeMarco from National Bank has the next question.

Don DeMarco analyst
#31

Thanks, operator, and good morning, Richard and team. So over at Granite Creek, it looks to me like horizontal development is still on track. The ventilation raise has just been moved into early '27, or possibly even late this year. Will that change in timing for the ventilation raise have an impact on production flexibility? And on the contractor turnover as well, should we treat that as fully resolved now?

Richard Young executive
#32

Yeah. Okay. So first, about ventilation. No, the mine plan won’t be impacted. What the team did is we had several options for the feasibility study; one option we had to stick with because we needed to get the report out was going straight to surface through the alluvial, but to avoid that, we needed to do a bit more work and then install the main ventilation rates going close to surface, and then the outlet is through one of the assets. It’s significantly cheaper. And no, we’ve done all events and models, and ventilation won’t affect us. And then the other question is about the contractor workforce. We’re at steady state now. And in fact, we’re ramping up for production rates into 2027. That was a relatively short-term impact, but it is also why we were lower on our material movement for Q3.

Don DeMarco analyst
#33

All right, that’s helpful. As you think forward to the 2027 guidance, what are you intending to put into that release? Is it going to be just production and costs — and costs could be a new item to add? Or would you also include items such as ounce of mine process and similar metrics?

Richard Young executive
#34

So Don, we are in the middle of working through that, and we'll provide as much guidance as we can. We will definitely provide the tonnage of tonnes grade and the ounces mined from both properties. And also what the stockpiling strategy is and how we think the production profile looks for both our committees, heap leaching, what gets sent to third-party processing and then ultimately, what we believe will be processed at our own facility Lone Tree in Q4. But it is going to be a complex year. We're working through all of that, and we will provide guidance on all those aspects along with our year-end reporting in February.

Don DeMarco analyst
#35

All right, and for my last question, regarding the Mineral Point PFS — I heard the target is the second half of next year, contingent on drilling. So is what we should expect basically a de-risked version of the 2025 PA mine plan? Or do you foresee any meaningful changes, such as a bigger production profile with staged construction, perhaps reduced initial CapEx, or anything along those lines?

Richard Young executive
#36

What I'd say is that, by and large, we're in the process of confirming many of the assumptions contained in the PEA. That said, there are certain elements we're dealing with internally. As we've noted, there's potential to expand the pit toward the east and toward the north. There might be some thinking that we'd spend somewhat more time drilling that out and afterward incorporate an expanded pit, but that would then alter part of the material balance. So we're working through that internally. For the time being, though, I'd say it's more or less in line with what the PEA contains.

Ryan Snow executive
#37

I mean, John, the main thing we're concentrating on there is nailing down what the project's parameters are, so we can file what in Canada—and in the States too—we refer to as the project description. That's an operations effort so the permitting work can get underway as early as possible next year. So that will really be a central focus for the team.

Operator operator
#38

Harrison Reynolds of RBC has the next question.

Harrison Reynolds analyst
#39

Thanks very much, team, and well done on the steady advances made this quarter. Looking at our committees, it is encouraging that the various developments remain on schedule. I had a question regarding the feasibility work coming up in 2027. Could you share what you are observing with respect to the drilling oxide currently under way, and what ground conditions look like in the underground development? Also, what are your expectations for the feasibility study, and how do you think it will stack up against the earlier technical report?

W. Chawrun executive
#40

Yes. Excellent question, Harrison. All right. So regarding the Upper Zone at the 426, the portion that was heap leaching, we don’t anticipate that continuing much past what we’ve already drilled, perhaps slightly. And then as for the Ruby deeps, where most of the remaining drilling is focused, we’re only now receiving some of those assay results. So at this point, we can simply say that we expect to convert what is inferred in the PEA to indicated for the feasibility plan. On the technical side, we substantially increased the number of geotechnical holes. The primary reason is that we want to investigate, and we believe there is reasonable potential for long-haul mining, which is considerably cheaper and more productive than underhand cut and fill, in the Ruby Deep zone. And so that has taken more time. Additionally, we encountered some difficulties with certain contractor production rates for the drilling production rates. So we are looking at the back half of 2027 to deliver this feasibility, and I’d say stay tuned for us to demonstrate potential with the Ruby deeps in some of those results.

W. Chawrun executive
#41

Those are only now beginning to come back to us as well.

Harrison Reynolds analyst
#42

Thanks for those specifics, Paul — that's really helpful. And then, second, even though we're still in the early stages, how much material would you want to build up in advance of Lone Tree commissioning, connecting Granite Creek with our communities? And given the economic uplift you get after Lone Tree, does it make sense to stockpile as much as you can? Or what trade-offs are you weighing when it comes to the timing and size of that stockpile?

Richard Young executive
#43

Ideally, we'd build up a stockpile of no less than 200,000 tons of material ahead of Lone Tree's commissioning, since we do have spare capacity at Lone Tree in '28 with both our committees and the Granite Creek ramp-up. And there's simply the cost advantage: right now we're paying roughly $350 a ton for that sulphide material via a third party. That figure falls to approximately $100 a ton. So we're plainly motivated to stockpile, especially given the working capital facility that Ryan and the team have managed to negotiate for the stockpile. That lets us get all of it started and run it through our own facilities.

Operator operator
#44

<<operator_script>> Our following question is from John Tumazos of John Tumazos Very Independent Research.

John Tumazos analyst
#45

Thanks, Rich. I’d like a bit more detail on those really strong oxide grades — both at Granite Creek and in our commutes during the quarter. A portion of the drilling for the resources was more widely spaced. Are you able to identify and plan ahead for all of these straightforward metallurgy oxide extractions? Or do they come as favorable surprises? Will they be higher next quarter, and so on.

W. Chawrun executive
#46

Alright, John — I’ll need to break that down a bit. At our committees, the oxide material came directly from drilling, so it isn’t mining. While we were drilling prudently, we carried out thorough legal test work, so with each drill hole and once we receive the assays, we can tell with good confidence what is oxide and what is sulfide. At Granite Creek, though, much of that drilling did not include enough comprehensive legal testing. That is why we are now doing it through our delineation drilling. As you said, that could turn out to be a somewhat pleasant surprise given how much oxide there is. That is also why you do not see much oxide in the feasibility study: the legal test work was not done sufficiently to model it for QP. So Granite will likely contain more oxide than what appears in the mine plan. As we have said before, processing that costs less, whether through heap leach at Lone — sorry, at Ruby — or by sending it past the autoclave, as we mentioned on earlier calls while stockpiling it at Lone Tree.

W. Chawrun executive
#47

So our economics aren't affected by it. As a matter of fact, it works in our favor, though technical work remains ahead at Granite before we can determine where those oxide boundaries sit. So it essentially runs through the structures, and then you wind up with the media order of water, after which oxidation occurs, and that's how the oxides zone gets created. And that is basically the same mineralogy. It has simply had the time to oxidize. So when it comes to whether it's higher or lower grade, there's no difference from the sulfide.

John Tumazos analyst
#48

Let me ask one more. On the timing of those big CapEx outlays and cash draws — basically, when do you actually have to write the large checks?

W. Chawrun executive
#49

Right. Construction is picking up pace as we speak. Our aim is to hand the general contractor the award at some point in December. After mobilization kicks off and we move forward with the build — steel, concrete, plus a few other refurbishment items — our onsite headcount will climb toward 300 people. So, as you put it, those larger payments will most likely land in Q2 and Q3 of '27.

John Tumazos analyst
#50

Seeing that much cash on the books was great, given how much work lies ahead.

Operator operator
#51

That brings us to the end of the phone questions. At this point, I'll hand things over to Caterina De Rosa for the webcast questions.

Caterina De Rosa executive
#52

The opening question is about Line states. Is the tender for loan tree completion about to happen? If it isn't, at what point during the fourth quarter will it be signed? And to be specific, when is construction scheduled to begin?

W. Chawrun executive
#53

Granite Creek remains a highly valuable asset for us, though honestly it's not really somewhere we want to be.

Richard Young executive
#54

All right, this is optional. It's just a standard agreement.

W. Chawrun executive
#55

My apologies. All right. So that award should go out in December, and after that our hope is to get mobilization going early in the new year.

Richard Young executive
#56

To give everyone a sense of scale, this construction effort calls for roughly 600 man hours, which is on the low side. Contracts are already in place covering the first 300,000. The balance — about 300,000 hours — sits with the general contractor, and that represents the largest contract. Eight groups took part in the tender process. We anticipate working through that in December. By the time the year closes, we'll have a solid read on where our commitment stands; as we head into 2027, we should be largely committed, with procurement essentially finished and all the major contracts in place.

Caterina De Rosa executive
#57

Alright. The next question from online asks whether $411 million is enough to bring the Lone Tree commissions online without an equity raise. And how confident are we that production mining at our communities will start before 2027 — we've adjusted some of these items, but.

Richard Young executive
#58

Yes. Perhaps I'll begin, and Ryan, feel free to chime in. With the recap, we took a conservative approach. Every one of our projects remains on schedule and within budget. And we think we have substantial liquidity as we move through 2027. So no equity raise will be needed. And the one point I'd like to underscore, echoing Ryan's comment: originally, with the recap, we were aiming for payments within 30 days after commitment. What we're actually seeing is roughly a 4-month lag, which means that even though we'd expect to commission late in Q4 of next year, we likely won't finish paying for that project until 2028. Ryan. I'm not sure whether you have something.

Ryan Snow executive
#59

Richard, the one thing I would tack onto that is this: besides the $411 million of cash sitting on the balance sheet, we can reach roughly another $350 million via the accordion feature attached to the gold prepay instrument, along with the warrants we anticipate being exercised from now until November of next year. Then there is the extra funding we have set aside under the stockpile finance facilities that came up during the call. So the $411 million on the balance sheet comes on top of the $350 million we have available, and that ought to be enough to carry us through everything we expect to do.

Caterina De Rosa executive
#60

All right, the following question comes from Adela Harding of ElcoDaily-Free press. Who owns the BrubyHill mine that produces leached ore?

Richard Young executive
#61

Yes. The answer is yes. So our communities — our committee oxides will be placed on the existing Ruby Hill path — that's Yes.

Caterina De Rosa executive
#62

We've touched on a few of those items already. And the last question from the web is this: could you give us a bit more detail about the shift in timing for the upcoming technical studies — in particular, our communities, Mineral Point, and then the Granite Creek open pit, which had been under review. What was different there?

W. Chawrun executive
#63

All right, one at a time then. We’ve touched on this a bit already. The drilling over at Mineral Point is simply running a bit longer. There are also some expanded areas, plus we had a little additional geotechnical work that needed finishing. So that carries us into — and it takes roughly 2 months for us to get the — so if you work that backward, we land in the second half of 2027. That’s really only so we can obtain the technical data required for a pre-feasibility study on minimal play. Our committee is in a very comparable position. At present we have 7 rigs operating, but we couldn’t staff all 7 rigs around the clock, 24/7, and these are now reaching longer holes. As a result, the drills’ production rate came in somewhat below plan. So at this point we don’t anticipate finishing that until roughly Q2, after which, once again, we must await assays and complete the technical work so a feasibility study can be done. So that too pushes into the second half of ’27. Then for Granite Creek, there’s considerably more happening. We’ve been carrying out a fair number of trade-off studies, and a fair amount of work involving the existing resource estimate.

W. Chawrun executive
#64

A lot of that has already been covered. We do still need some infill drilling. What we’ve done internally, though, is invest a good amount of time reviewing the full scope of work required for all the proper trade-off studies involving heap leach, CIL, where the TMF would eventually sit, every component of the surface infrastructure, the geotech site investigation effort, and so forth. So we have a comprehensive scope that we hope to kick off in Q1, and then to get all of that work assembled so we can then put together the detailed work needed for a project description to begin an EIS process. And finally, as noted — as Richard noted, we hope to place that construction as we keep advancing the technical work at the back end of Mineral Point.

Caterina De Rosa executive
#65

All right, thank you, Paul. We have no more questions on the line.

Richard Young executive
#66

Thank you all for being with us today. To sum things up, we released results for the first quarter of 2025, and apart from cove dewatering, which is running above the amount the PEA set aside, nothing has caught us off guard. What we are seeing, however, is that Granite Creek underground, our committees, and Mineral Point are each likely to come in bigger than the PEAs assumed. As we go forward, quarter after quarter, in terms of execution, we believe we will begin moving toward fair value. In our view this portfolio is extremely valuable, located in the #1 mining jurisdiction worldwide. It will take time, but we anticipate reaching fair value as we keep executing. So I am glad to take any additional calls as people go through the materials published overnight. Thank you for attending the call today.

Operator operator
#67

That brings us to the end of today's call, everyone. We appreciate your joining us, and please go ahead and hang up your lines.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete i-80 Gold Corp. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to i-80 Gold Corp. earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.