Ivanhoe Mines Ltd. (IVN) Earnings Call Transcript
October 30, 2025
Earnings Call Speaker Segments
Thank you so much, Operator, and good day to all of you. First and foremost, I want to express our appreciation to each of you for being here today. It's a pleasure to have you with us for Ivanhoe Mines' conference call on the financial results for the third quarter of 2025. As the operator noted, my name is Matthew Keevil, and I serve as Director of Investor Relations and Corporate Communications. Joining us on the line today from Ivanhoe Mines are Founder and Executive Co-Chair Robert Friedland, President and Chief Executive Officer Marna Cloete, Chief Financial Officer David van Heerden, Chief Operating Officer Mark Farren, Executive Vice President, Corporate Development and Investor Relations Alex Pickard, and Executive Vice President, Projects Steve Amos. Today's event will conclude with a question and answer session. Questions can be submitted through the Q&A box on the webcast or via the conference operator on your phone line. For any follow-up questions that don't get addressed during the call, please reach out to our investor relations team directly. Before we get started, I want to remind everyone that forward-looking statements will be part of today's event, and these involve risks and uncertainties that could cause actual results to differ materially from those in the forward-looking statements. You can find details of the forward-looking statements in our October 29th news release, as well as on SEDAR+ and at www.ivanhoemines.com.
At this point I'm happy to hand things over to Robert Friedland, the founder and executive co-chair of Ivanhoe Mines, who'll make a few opening comments. Robert, the floor is yours.
Thanks to all of you — every one of our stakeholders around the globe. I'm speaking to you from Riyadh, Saudi Arabia, where the Future Investment Initiative, held here in Saudi Arabia each year, has just wrapped up. For those interested in the materials that make up our supply chain and in countries' national security as it relates to critical raw materials, this event has become the world's premier investment destination. It feels especially fitting that we welcome the Qatar Investment Authority, whose $500 million equity investment in Ivanhoe Mines makes them a leading institutional shareholder in a country with superb relations throughout the Islamic world — which I believe is the least explored part of this planet's mineral endowment. We welcome Qatar Investment Authority as a long-term shareholder, and we'll be talking more about our excellent relations and future together in the near future. It's also a very good day today to have to tell you that yesterday we fed the first ore to the concentrator at what will become the largest precious metals development in our industry. It was in the 1980s that we began working in Limpopo Province in the northern part of South Africa to find a giant deposit on the northern limb of the Bushveld, which is quite different than the rest of the Bushveld.
We’ve found what amounts to a super monster — a Tier One polymetallic mine with an extremely long life and enormous importance. Yesterday the ore went into the phase I concentrator, and that begins a period of at least 100 years for a highly significant developer of gold, platinum, palladium, rhodium, nickel, and copper. Among all metals, rhodium ranks as one of the most strategic. Platinum and palladium are also used in data centers and are essential to every server in nearly every data center across the globe. So with that, I welcome everyone. I want to express thanks to all our people who have been working on the recovery program following the seismic event we had in May. Our progress and our people’s efforts make us very pleased. Now I’ll hand things to Marna so she can begin telling you the story. Thank you very much.
Thanks, Robert, for those opening remarks, and good morning. Good evening, everyone, and thank you for being with us on this quarterly call. These are genuinely exciting days in South Africa. We're getting ready for the G20 summit taking place later this month, and I believe the timing of Platreef's startup could hardly be better, lining up with this significant event in South Africa. On the screen you can see a photo of our management team standing in front of a discharge and settling pond that forms part of the stage two dewatering. I'll briefly walk you through our quarter three turnaround strategy and a few highlights at Kipushi. We truly stand at the edge of a new horizon. New Horizons was a tagline we used before, and I'm reviving it today because our plans at Kamoa-Kakula are coming together in a way that has us very excited. Let's move to the next slide. The third quarter was always anticipated to come in somewhat softer, but we were thinking about what we've accomplished physically on site, and considering the team and the enormous effort that went into our dewatering, it is going exceptionally well. The pumps we flew in from China made a difference.
We are witnessing unprecedented pace in project construction, and Mark will walk you through that during the presentation later today. Getting the mine rewatered as fast as possible has been a major accomplishment by the team. There's a group of technical specialists we have. We assembled them. Work is underway on our new life of mine plan, which we intend to release around the first quarter of next year. At present, we expect to restore Kamoa-Kakula to copper output above 550,000 tonnes down the road. We had hoped to be ready to issue guidance for 2026 and 2027 somewhat earlier, yet we discovered there are numerous moving parts. Dewatering is happening in real time. We have technical specialists who must all come to agreement. We're pretty enthusiastic about what these numbers are revealing, and we'd prefer to invest the time to make everything accurate before releasing it to the market. At the latest, those figures will likely come out in early January, though possibly sooner. That's our plan for the coming couple of months. Turning briefly to Kamoa-Kakula and stepping somewhat away from our turnaround strategy, this smelter has been a really thrilling area.
We will begin the heat-up shortly. Our first concentrate will be fed into the smelter in early December, and the technical experts on this call will walk you through what that involves and how we plan to go about feeding the smelter in early December. Turbine 5 at Inga II has also been completed — another major project the team finished very successfully. Power is beginning to flow through the grid, and we expect to receive an additional 50 MW through the grid in November. As Robert said, these are exciting times at Platreef, and Kipushi is something of a rising star that we shouldn't lose track of. The debottlenecking program is complete, and we remain on track to meet our production and cash cost guidance at Kipushi. The same applies to Kamoa-Kakula. We are likewise on track to meet our revised production guidance and cash cost guidance at Kamoa-Kakula. One number I want to address directly is the cash cost shown at the bottom of your screen. That is the quarterly cash cost at Kamoa-Kakula. It does appear higher than the figures you typically see. That is simply due to the base used to calculate this cash cost for the quarter.
Production came in lower, and we had some G&A sitting in that figure; on top of that, we were feeding somewhat lower-grade material into the plant. That explains the variance you're seeing there. Moving to the next slide on health and safety — that remains our top priority. These statistics, I believe, speak for themselves, particularly for a company that is executing projects right now and running major turnaround strategies. There have been no LTIs of late at the Kamoa-Kakula site, and construction of the smelter was finished with zero lost time injuries recorded, which is a meaningful accomplishment. I think that stands as real testimony to our project team and our construction crews. In the same way, building the Kipushi concentrator plant, which began in September of 2022, along with the debottlenecking completed recently, were all done with not one lost time injury. A big shout out, I think, goes to our operational teams on the ground — they are performing exceptionally well. With that by way of introduction, we'll now go into the details, and I'll ask David to walk you through the financials for the quarter.
Thanks, Marna, and good morning — good day to everyone who's on the call with us today. Let's go right ahead to the following slide. During the third quarter, Kamoa-Kakula sold just under 62,000 tonnes of payable copper. Output in that quarter exceeded the tonnes sold, which pushed up contained copper and concentrate inventory on hand. By quarter-end, that figure had risen to 59,000 tonnes. It was up from just under 54,000 tonnes on hand when Q2 closed. At the Lualaba copper smelter near Kolwezi, inventory stood at roughly 7,000 tonnes at the close of Q3, which is down from the nearly 19,000 tonnes present there when Q2 ended. Most of that inventory is essentially sitting there, ready for smelting. Between Kamoa-Kakula and the copper smelter, it's really a supersized piggy bank. With the copper price where it is now — just waiting to be broken — we expect the unsold inventory to come down gradually. We've mentioned this before, but we kind of hold to the view that it should fall to about 17,000 tonnes as the smelter ramps up. Kamoa brought in revenue of $566 million in the third quarter, at a realized copper price of $4.42 per pound of payable copper.
Turning to the following slide, Kamoa-Kakula posted EBITDA of $196 million in Q3. Lower tonnes sold and reduced ore grade processed as the recovery plan moves forward both weighed on that figure. Given that this is, at least in our view, the lowest point of Kamoa-Kakula's turnaround, a 35% margin looks pretty good. Cash cost for Q3 2025 came in at $2.62 per pound of payable copper. Year-to-date cash cost stands at $1.97 per pound, still comfortably inside our full-year guidance of $1.90-$2.20 per pound of payable copper. Mined grade at Kakula was approximately 5% in Q1, 4% in Q2, and fell to 2.5% during the third quarter, which was broadly consistent with the grade processed overall from Phase I and Phase III as well as from surface stockpiles. During Q3, we do anticipate that mining of the higher-grade zones on Kakula's western side will begin in November. As Marna noted, Q3 was truly an unusual quarter where cash costs are concerned — not just owing to the effect of lower grade, but also because of additional factors that will be tackled as the turnaround advances.
Right now, the mining teams are largely focused on development tonnes as part of the re-establishment work, and that carries a higher cost than stoping does. The crews are also still adjusting to the smaller heading sizes, and we expect efficiencies to get better going forward. As we've said before, we'll see meaningful cash cost reduction benefits from the smelter starting early next year as it ramps up. Moving to the next slide, this shows the typical Kamoa-Kakula EBITDA waterfall. The EBITDA waterfall lays out what drove the quarter-on-quarter EBITDA change for Kamoa-Kakula. Although we recognized $90 million of abnormal cost in Q2 tied to the seismic event in May 2025, that fell to $9 million in the third quarter, giving a delta of $81 million. Shown as the green bar on the left in Q3, only costs directly related to the dewatering effort were classified as abnormal. In Q3, that was mainly the cost of diesel to run the generators powering the dewatering pumps, since the mining crews were no longer idle. The other major driver of our lower EBITDA was the impact of lower tonnes sold, which was almost $300 million.
A better copper price versus the prior quarter gave us a $25 million lift. Logistics came in slightly under the previous quarter, and other costs declined too, compared with the elevated levels seen in Q2. Let's move to Kipushi on the following slide. After Kipushi's record output in Q3, it sold nearly 50,000 tons of payable zinc and posted record quarterly revenue of $129 million. For the quarter, Kipushi added $27 million to Ivanhoe's EBITDA. That strikes me as a pretty solid outcome given that Kipushi lost a number of days of uptime while the teams finished the second phase of debottlenecking. Later in the presentation, Mark will walk you through how the debottlenecking succeeded, and we anticipate Q4 results improving further once the production gains come through. Cash cost is holding nicely steady, right at the midpoint of our guidance. From the fourth quarter onward, we expect to see the advantages of the higher production. Now to Ivanhoe Mines Consolidated Profit and EBITDA on the next slide: Ivanhoe posted quarterly Adjusted EBITDA of $87 million. In Q3, what really drove the weaker Adjusted EBITDA was the lower sales at Kamoa-Kakula, as I explained earlier, together with the effect on Ivanhoe's share of Kamoa-Kakula's EBITDA.
Part of that was offset by Kipushi's EBITDA rising, since exploration spending and overhead costs stayed mostly flat. For the third quarter, Ivanhoe posted a profit of $31 million, versus $35 million in Q2 2025. Moving to the liquidity snapshot on the following slide, Ivanhoe held $1 billion in cash and cash equivalents at the close of September, while Kamoa's cash on hand stood at $125 million. As Robert noted earlier, we closed the Qatar Investment Authority investment in September, bringing in gross proceeds of $500 million, and we received another $70 million from Zijin through their exercise of anti-dilution rights; separately, Kamoa Copper wrapped up a $500 million two-year term facility during the quarter and drew down $370 million in early October. Ivanhoe Mines and Zijin each also covered our proportionate share of a $135 million cash call from Kamoa-Kakula in September. Now turning to the CapEx spending plans on the next slide, we cut $100 million from both the top and bottom end of Kamoa-Kakula's 2025 capital expenditure and simply moved that amount into 2026. Work on the updated Life of Mine Integrated Development Plan for Kamoa-Kakula is progressing well, and once that is finished and folded into the guidance, the 2026 CapEx will be narrowed down and more clearly defined.
Spending at Platreef is coming in toward the bottom of the 2025 guidance, and our capital expenditure guidance range for 2025 to 26 remains as it was. The first ore was fed into the phase I concentrator, as Robert noted recently, and the phase II expansion is moving forward in line with what the feasibility study sets out and was finished earlier this year, which then schedules the phase II concentrator module to start up in Q4 2027. We're also pursuing a senior project finance facility for Platreef's phase II totaling $700 million, and that is going quite well and should close in Q1 of next year. Kipushi's debottlenecking program wrapped up in August, ahead of schedule and under budget, and as I said Mark will walk you through that, and we've nudged CapEx for Kipushi up a bit simply to accommodate faster construction of the second tailings facility paddock as we get ready for higher output after that debottlenecking. Moving to the next slide, it presents our consolidated pro rata financial ratios, which are better than where they stood at the close of last quarter. The main reason is the cash from the September private placement by Qatar Investment Authority, and we sit in a very strong pro rata cash position, with more than $1 billion of cash on hand.
At Kamoa-Kakula, we're adding somewhat more debt, though EBITDA—and hence the net debt ratio—will get better as we keep carrying out the turnaround plans there, and as EBITDA from Kipushi rises and Platreef's EBITDA joins in later on. Our goal for net leverage stays at one times across the cycle, and we continue to expect it to decline soon as our plans move forward. I'll now pass things to Mark Farren, our Chief Operating Officer, who will begin the operations update part of today's presentation.
Thanks, David. Please move to the following slide. Appreciate it. All right, we've discussed this before, and our view is that this was the bottom. Milling wasn't really the main factor. To be clear, we milled 3.4 million tons, but the grade is the issue. The grade is truly the key. If I can walk the listeners through it, there are really two things involved. Primarily, it's about accessing the higher grade zones at the Kakula mine, which are all located in the lower portion of the mine, obviously where the water problem sits. As we advance and build out the footprint at Kamoa 1 and Kamoa 2, the grade gets better. You're going to see a number of factors that will affect the grade in the immediate near term and then over the longer term. That's why we're quite confident that we've reached the bottom, hopefully the bottom of everything, and we'll see a significant turnaround from here going forward. What's encouraging is that the phase III concentrator is operating sustainably at roughly 30% above its design capacity. When we discuss the long term, you'll notice the reference is always to 17 million tonnes. Building out this infrastructure that we have in order to reach the 17 odd million tons and then to raise the grade across all the different areas to achieve that target, the short term target I believe of exceeding 550,000 tons of copper, which will be in all the project plans and all the long term plans that you see coming forward.
I think there will be additional increases beyond that over the longer term. David, could we go to the next slide, please? Let's discuss water. That blue shape resembles a fish. We refer to it as a whale. It genuinely does look like a whale. You can see that the west and the east have been connected between the two. There was, in a sense, flooding between the two. In the lower portions of both, mining was in fact occurring in the upper portions of the west and, to some degree, the upper portions of the east. Those regions are in fact the lower-grade regions. The 2% grade regions, the light blue on the western side, will be the first target area we dewater, and we have carried this out in stages. Stage one involved installing temporary pumping capacity and stabilizing water levels at levels far above where they stand today. Stage two involved placing these high-capacity centrifugal pumps down these vertical shafts and then pumping out at 2,600 liters per second. Those pumps were imported; they were installed within six weeks. I believe the team on site has done an absolutely fantastic job getting all of that pumping infrastructure working.
At stage three, we're truly focused on managing the declines and expanding within the infrastructure that already exists — the pumping infrastructure — and rehabilitating what's underground, then dewatering the west first and the east afterward. Our belief is that during November, the west will be fully dewatered, and after that we'll turn our attention to the east. I think by early next year, the entire east will be dewatered and, as you can imagine, every crew is eager to get back into that higher grade western section. Everything has been scheduled, and I'll also cover life of mine planning in the next couple of slides. There is a solid, proper pumping plan in place to bring the infrastructure back on track and get the crews back into higher grade mining. Thank you. Next slide. This is simply a picture of what we've had to do. We had to descend through ventilation shafts roughly 300 meters deep and install very high capacity pumping systems. I thought that idea was very clever, and it has worked extremely well. It's likely to be used over the longer term as well, because these pumps are performing really well as long as the water stays clean.
So I suppose from here on out, those high-capacity pumps are going to be deployed in various sections of the mine. Thanks. On to the next slide. What you're seeing here is simply an image illustrating the kind of situation we face when rehabilitation comes up. You can notice spalling on the sidewall. That was essentially the entire cause of that incident. The seismic activity we mentioned consists primarily of sidewall spalling. Pillars spalling, and that has to be rehabilitated as you move downward, and then the pumping infrastructure must be recapacitated as you move downward. The following slide will simply show you how it appears once rehabilitated. Next slide, please. Taking a look at this, the sidewalls and the hanging walls have been resupported, and it resembles a new mine, and it happens fairly quickly. In my view, we've achieved very solid progress with the rehabilitation. As I mentioned, I believe that in November we ought to open up the entire western front, which amounts to roughly 30 new faces for the teams to mine. Next slide. Yes. A different planning approach. This is merely one of the images, but it's complete. Those same principles get applied to the new mines. The Kamoa 1 and 2 mines have those same principles applied.
You have a truly strong and capable team—Marna mentioned this too—and they're focused on designing the mine of tomorrow. Our belief is that this work will wrap up in Q1 2026, and we'll move as quickly as possible to provide near-term production guidance, targeting the coming 3 years and the longer horizon after that. We're confident the engineering is being handled by the industry's top specialists, ensuring we recover and avoid any recurrence of these issues. In my view, the near-term plan is to return to 17 million tons at the best grades achievable. That small green block you see indicates we'll surpass 550,000 tons per annum over the medium term. To me, medium term means the next 2 to 3 years, and from there we'll continue growing the business. Next slide, please. The smelter. We did discuss the smelter. It's arriving at just the right moment for us, for a couple of reasons. First is obviously what we've consistently talked about—our logistics costs.
At this point, logistics represent roughly 50% of our costs. I believe we've brought that down below half, since our plan is now to export 99.7% blister copper — anode copper, really. Another factor that's about to arrive and should give us a meaningful boost is the acid credits. As you're able to see, we anticipate prices of approximately $500 per ton, which stands quite high for the industry. Export bans have been put in place in Zambia, and that means bringing acid in from other nations will cost considerably more. We happen to be located right in the DRC, where the acid is needed by all the other mines. I believe this will prove extremely helpful to us. Naturally, David's small piggy bank has to be cracked open. Those 59,000 tons of unsold copper must be fed into our smelter. Because of the SNEL interruptions, we've had to take certain measures — SNEL is still not flawless. We're also putting substantial effort into stabilizing the infrastructure. We did mention that Inga II would be commissioned, and that was carried out extremely well. There are additional steps we're taking on that network to fully stabilize it, and those will require somewhat more time, but we've installed an uninterrupted power supply of 60 MW.
This is a massive undertaking in its own right, and it's being commissioned right now — which means we're able to begin feeding our direct to blister smelter. That's a project north of $1 billion, and in my view it was executed exceptionally well. I'd call it one of the finest installations in that country, or the finest that nation has ever had. I'm extremely proud of what's been accomplished, and it will be heated up during November, with first feed in December. Those are the reasons we're so excited. We'll generate profit from the asset, and we'll cut transport costs substantially. Thank you. On the next slide — the turbine at Inga II is finished. It's online right now. That's a massive undertaking in itself. It's been carried out very, very well, and we'll get the first 50 MW of power in November, and then it ramps up, if you recall how things stood before. That turbine produces 180-odd megawatts of power, and of that we'll be able to receive 150 MW as we fix things. As I mentioned earlier, we're strengthening the transmission. There are upgrades we're working on, including these resistor banks that we'll finish in Quarter 2, 2025, 2026, to boost and enhance stability across the entire infrastructure.
We're also putting in capacitors as extra projects. Broadly speaking, we're reinforcing the grid nationwide, so that entire DC line and its conversion over to AC is being reinforced right now. Thank you. On the next slide, green power. We're currently carrying out construction of two on-site solar installations of 30 MW each, paired with battery storage. In my view these are two excellent projects that also reduce our operating cost — our power cost — relative to diesel. Massively so: it comes in at under half what diesel costs. Our first two will be up and running in Quarter 2, 2026. These are large installations, excellent installations, and we're doing work to grow that on-site solar facility to 120 MW. The first two will supply roughly 20%-25% of the energy we require, and you can figure out what the remainder will do. I believe it's expandable. It's something we'd like to carry forward and grow in increments as our business grows and as we move into the Western Forelands. It carries a very strong advantage of being clean and inexpensive, and it pairs very well with hydropower. I think going forward, we'll be focused on clean hydropower and clean solar power to grow our business.
Thanks. Moving to the next slide — Kipushi. We've talked about Kipushi, I believe, on a couple of occasions when we were working through the debottlenecking projects. Both of those are now finished. It was divided into two parts, essentially a shutdown in June and another shutdown in August. Both are done. There's still a small amount of work under way to install energy backup — diesel backup, basically, serving as contingency backup — and that should be finished in November. We're taking Kipushi to roughly just over 250,000 tons — 250,000 to 300,000-odd tons of zinc. That comes starting next year, and there will be a strong quarter in this last quarter. Quarter four will be stronger than quarter three, which represented quite a significant improvement over quarter two. We're setting Kipushi up to produce around 250,000 to 300,000 tons of zinc starting next year, which places it on the next slide, I think. Next slide, yes. That makes it number three in the world. It's a small mine, but it's very high grade, and you can just take a look at that grade. It's above 30%, that little red dot, and it takes us to essentially the third biggest in the world.
And I should also mention that zinc prices have risen fairly substantially. The operational team has kept our C1 cash cost very well in check, and I believe the project was completed competitively — competitively in terms of schedule and within budget; it has gone really well, and we are eager to see what Kipushi delivers over the coming couple of years. Thank you. I think. Alex, will you handle Plat?
Mark, I'll take this one. Thanks. Yes, I'll handle it. Platreef had a major day yesterday. First ore went into the mill, and we operated it for four hours at a 30% ball load, consistent with the hot commissioning ramp-up curve for the mill. Since then, the mills have been halted. We'll bring the ball charge up the rest of the way to 100%. That should take about a day, maybe a day and a half, after which we'll restart the plant and begin ramping up. My expectation is roughly a week or so from the mill restart — hopefully tomorrow — until we produce the first concentrate. That will be an exciting moment for Platreef. Next slide, please. Let me say a few words about Shaft 3. Shaft 3 is a 4 million tonne per annum rock hoisting shaft. It's the image in the center. You can see the sinking headgear — the brown construction there — which is truly essential for phase I to sustain phase I, and also very important for phase II, to ramp production up to 4+ million tonnes and to build a nice big stockpile before we start the phase II plant with this shaft and with Shaft 1. Shaft 1 is the shaft on the left-hand side in the background.
Altogether, hoisting capacity will come to 5 million tonnes. Shaft 1 is going to serve mostly for personnel and supplies, while rock hoisting will happen through Shaft 3. Up front, there's a great deal of steelwork visible. That's the permanent headgear for phase III, and we'll set it into position. The plan — and we remain on schedule — calls for starting to hoist rock from that shaft at the end of March 2026. That covers underground rock handling too: a crusher, two conveyors, and a tip, plus of course the hoisting up through the shaft. Let's move to the next slide, please. I'll spend a moment on phase II and Shaft 2. For anyone unfamiliar with it, phase II is a mine and concentrator rated at 4 million tonnes, turning out roughly 450,000 ounces of platinum, palladium, rhodium, and gold, around 10,000 tons of nickel, and approximately 5,000 tons of copper. The EPCM contracts have gone to DRA, which is based in South Africa. They are the very contractors who carried out the phase I work. Early procurement is already underway. Earthworks are slated to break ground in Q1 of next year. In Q3 and Q4 of 2027, we begin work on the big plant. All told, that gives Shaft 2 hoisting capacity of 4 million tonnes, which phase II needs.
That also gives us the start of phase III. We have just handed out the contract we refer to as the slip and line contract. As for what is on site right now, you can see the headgear finished. There is a raised bore of 3.1 meters in diameter going all the way down to 950 meters. The slip and line contract works by slipping that 3.1 meter diameter shaft out to a shaft of 10 meters in diameter. After that we line the barrel and equip the barrel, and come Q4, 2028, we intend to use that shaft for mana material at a later stage. We equip that shaft for hoisting rock, and in time that shaft is going to be a rock hoisting shaft of 8 million tons per annum, which will underpin phase III of the project. Very exciting. The crew mobilizes for the slip and line in Q1 of next year, and that is roughly an 18, 18 to a 24 to 30 month project. Next slide, please. Do you want to take that, Alex?
Alright. Thanks, Steve, and hello everyone joining the call. This is Alex Pickard speaking. We put this slide in mainly to pat ourselves on the back, I suppose, for the perfect timing of first production at Platreef following, without question, over 25 years of work. We are just beyond LME week here in London, and clearly the market has placed a great deal of focus on the gold price as well as the copper price. As a matter of fact, the PGMs — the platinum group metals — have delivered the strongest performance of any metal so far this year. Platinum has risen roughly 78%, and palladium has gained 56% since January. What that means is Platreef will generate even healthier margins. Bearing in mind, naturally, that as we ramp up toward phase II, we anticipate ranking among the lowest cash cost producers across the entire industry, thanks to the large scale mechanized underground mining and the byproduct credits we get from nickel and copper. On the right-hand chart, you can see that the spot basket price for Platreef today, covering platinum, palladium, rhodium and gold, stands at $1,900 per ounce. Once phase II is operating, the target cash cost is $600 per ounce.
Once fully ramped up, phase I is definitely below $1,000. Also, if you check the sensitivity analysis included in the feasibility study we released earlier this year, the NPV at spot prices comes in 40%-45% above the base case we showed. We hold the view quite firmly that the NPVs shown on the bottom left are not truly reflected in the Ivanhoe Mines share price as of today. Hopefully that begins to shift, since we'll be reporting revenue and earnings from Platreef starting next quarter, which is quite exciting. Turning to the following slide and to exploration, beginning as always with the Western Forelands: throughout this year we have drilled more than 40,000 meters of diamond drilling across the Western Forelands. That takes in a great deal of work we have been carrying out around the Makoko District, which appears here. I'd like those listening to examine this graphic quite closely, as it displays the 18 km long strike length. You can see the outline of the Makoko, Makoko West and Kitoko ore bodies, where we announced the upgraded resource in May of this year, along with over 9 million tons of contained copper across those three ore bodies.
Looking eastward, you'll also notice how close Kakula West sits — just 8 km from here. On the chart before you, the bigger colored circles represent the holes drilled during this year, after the new resource came out. You can compare each hole's grade against the scale provided in the key. As you'll see, we've been infilling the zone between Makoko West and Kitoko quite productively, turning up some solid-grade intersections. Beyond that, we've also been stepping out south of Kitoko and east of Makoko, and both have met with success. Honestly, what we hold in the Western Forelands may well be among the finest value-for-money copper drilling to be found anywhere on earth. Across the Western Forelands, our discovery cost comes in at under $10 per ton of copper. The wet season is upon us now — it tends to begin in November and definitely by December. Once again we've made our preparations. This marks, I believe, the third consecutive year in which we'll keep drilling right through the wet season. Keep watching this space — both at the Makoko District and elsewhere across the Western Forelands license package on the following slide.
Honestly, what we're doing in neighboring Zambia and Angola is really just an extension of the approach we've taken at the Western Forelands. Let's begin with Angola, where we hold a massive license package spanning more than 22,000 sq km — that's several times larger than the Western Forelands. Baseline geochem and geophysics have been underway and are now finished, and we're on the verge of kicking off our very first drilling on this land package in the fourth quarter. That's pretty exciting. We've got two drill rigs mobilized to carry out more than 6,000 meters of drilling. Zambia isn't quite as far along. That large land package was only acquired by us recently, and honestly what we're doing is the foundational work needed to get set up so that drilling can begin in Zambia in Q2 of 2026. Keep an eye on both of those fronts. On the final slide, looking even further afield, I believe Marna brought up New Horizons, and Kazakhstan is definitely a new horizon, where we established an exploration joint venture allowing us to earn up to 80% over time, covering more than 16,800 square km. Once again, that's roughly seven times the size of what we're looking at in the Western Forelands. Given that this joint venture was only signed by us in the first quarter and the licenses were really staked by us in Q2.
The joint venture crew has accomplished an excellent job of getting mobilized very fast, and drilling is already underway. A 17,500 meter diamond drilling campaign has already begun, and some quite encouraging initial news is that visible copper mineralization has been seen in the first drill hole on that license package. We are very excited about what lies ahead in Kazakhstan and looking to leverage from that. That brings the presentation to a close, and I will hand things back to Matthew Keevil to chair the Q&A.
Much appreciated, Alex, and thank you all. We'll move on now to the Q&A portion. First off, we're going to clear the phone lines of any questions that our analysts are sending in over the phones. Operator, please go ahead and proceed with the Q&A period.
Thank you, and thank you, sir. Ladies and gentlemen, should you wish to ask a question right now, kindly press Star and then one on your touchtone phone. A prompt will tell you that your hand has been raised. If you would prefer to withdraw from the polling process, you will need to press Star and then two. When using a speakerphone, please pick up the handset before you press any keys. As was noted, questions may also be submitted through the webcast platform. Thank you. Thank you. Your first phone question comes from Ralph Profiti at Stifel Financial. Please go ahead.
Thanks, operator. Good morning, Marna, and good morning to the team. It's really good to see the recovery plan at Kamoa-Kakula progressing as planned. Marna, congratulations on that landmark investment from Qatar Investment Authority. Now that the mine has been dewatering and continues to do so, have you observed, or do you anticipate, higher inflow rates, essentially as a result of the pressure — the differential between external and in-situ pressures on the dewatered workings? From the progress, it sounds like inflow rates have at minimum stayed fairly steady. As I recall, the figure was around 3,800 liters a second. Does that remain the case?
Thanks, Ralph. I’ll have Mark take that one. The setup is fairly complex, since you have both horizontal and vertical pumping. Naturally, as dewatering proceeds, infrastructure has to be relocated. Some installations are temporary and some are permanent. You don’t really track it meter by meter, day by day. We have not observed higher inflow rates — that’s fair to say. Morgan, perhaps you can walk through how the dewatering metrics we use shift from day to day because of the various pumping installations we’re working on.
No thanks, Marna. No, that's correct. You're actually not mistaken. You're quite right. We pump approximately 4,000 liters every second. That figure hasn't changed so far. We're attempting to bring this down — the entire system, let's refer to it as the system that depends on the vertical pumping setup, but also the horizontal one, let's call it the horizontal or the decline. Your rehabilitation and your decline system must also decrease at an equivalent rate. On the vertical side, we lower it by roughly a meter each day. We haven't truly raised anything in a meaningful way. Right now we're operating at roughly 4,000 liters per second. We've refreshed our hydrological model, which indicates what lies ahead. Going forward, as mining continues, especially in the direction of the west, our pumping rate will rise. Put differently, we'll run into additional water. We're aware of this as we advance farther west while mining. That will all be managed provided you factor in the pumping capacity we possess. At present we have a bit more than 10, around 11,000 liters — let's say 10,000 liters per second of pumping capacity, with an inflow of 4,000. As things grow hydrologically, as the water rises while we move west, we boost that vertical and horizontal pumping capacity in the places where it's required.
There's nothing unusual here, and it's fully in line with what we anticipated. Thank you.
Got it, and thanks for that. If I may pivot to something else entirely — and it's encouraging to see — the progress at Platreef. Could you bring me up to speed on the offtake agreements and the negotiations with the various parties and counterparties? I'd simply like to know which milestones we ought to watch for as those get secured going forward.
I'm glad to handle that one. Alex, perhaps you could add a bit as well. The phase I concentrates are now placed with Northern, and that arrangement is essentially finalized and in position. Part of our second phase concentrate has been placed with Sabanier. We actually met with SFA this morning, and they are right now touring South Africa and capacity. Our understanding is that capacity likely exists for the rest of our concentrate. Those portions still have to be tied in as we bring phase II online. We feel quite confident we'll find a home for what remains. There is also expansion capacity at certain existing fully integrated producers, where one can join forces on capital expansions if needed, though we don't even believe that would necessarily be required.
Oh, wonderful. I appreciate the positive news. That's excellent.
Once again, ladies and gentlemen, a reminder that if you have any questions, please press star one on your telephone keypad. We will now hear from Andrew Mikitchook at BMO Capital Markets. Please go ahead, Andrew.
Yeah, several good questions have already come up and been addressed, but perhaps I could just get a few additional comments from Mark, maybe based on slides 20 and 21, where you presented the before and after of the rehabilitation work at Kakula. Does that reflect what you're actually observing, or what's the range of impact you're seeing as dewatering proceeds and your crews move in to rehabilitate? Generally speaking, I don't personally regard myself as an expert in rehabilitation. Is what those pictures show extensive, expensive, or time consuming to rehabilitate?
That's a fair question, and it reflects what we're seeing. Certain areas perform considerably better than that, while one or two spots over on the eastern side come in worse, and those are the ones we're actively working on — though nothing has come up that we can't handle. As we bring the pumps down, we're seeing the pillars sprawl, and we restore them using crews trained for that work. I believe there are seven separate crews covering different zones, and together they've completed more than 10 km of this. They know pretty well what needs doing. Progress is happening, and they're keeping us on schedule. As I mentioned, we ought to have the west side open and dewatered during this month — November — and that's a major breakthrough for us. After that, we can commit the resources and ensure the eastern side gets re-established with its pumping systems and so on. I genuinely think they've delivered the progress we required. My concern was installing those large pumps we had no prior knowledge of. We hadn't used them before, so we didn't know whether it would succeed — and it succeeded remarkably well.
The progress we set out to achieve has been achieved, and we're still moving forward nicely. Should any issue arise, we'll let you know — we'll tell the market, look, we ran into this problem or that one — but up to now, in my view, things are going quite well. Thank you.
To return to the other project that's front of mind right now, Platreef — let's go back to Shaft 1 and Shaft 3 and how those have been doing up to now when it comes to ramping up phase I, since they're the linchpin holding together both that ramp-up and the expansion into phase II. How has performance been to this point?
Happy to cover that one too. With phase I, we essentially deferred the commissioning of that plant so we could concentrate on the critical infrastructure needed to get phase II up and running. Phase II genuinely had to be completed via shaft number three. Three. As Steve Amos noted, shaft number three is a 4 million ton wasting shaft. That shaft will be commissioned and operating in quarter one, essentially by March next year. Keep in mind, phase I is roughly 700,000 or 800,000 tons a year. It's a tiny little mine. It's a small little mine. We have moved very quickly. We were executing phase II in parallel. That shaft, shaft number three, is what we needed. That, I'm telling you now, will be running at the end of quarter one next year, which completely de-risks phase I hoisting. In other words, the longer open stoping that you need to do in phase I is completely de-risked. You can put material down, you can blast, you can hoist, you can do everything else you need. It accelerates the development towards the footprint of phase II. We can increase the development as much as we need to. We can open up the long haul stoping faces for ourselves while Steve Amos is busy building the concentrator.
In my view, going ahead with shaft number three was a sound call. He mentioned shaft number two as well, and we're pursuing that too alongside phase II, even though it serves phase III. By completing shaft number three, we're sort of de-risking phase I, preparing phase II ahead of schedule, and over the longer term paving the way for phase III through shaft number two. That sequencing is paying off. As I see it, the risk now is far smaller than it otherwise would have been, and I believe we've handled that well. It's going to work. Thank you.
Alright, that clears up what I needed to know. I'll hand over the mic now. Thanks so much, everyone, for spending your time with us.
Thanks. And just to repeat, everyone—if you’ve got questions while you’re on the line, hit star and then one. We’ll take the next one from Alon Olsha at Bloomberg Intelligence. Go right ahead.
Hello, and thank you so much for the question. I actually have three, if that's alright. First, on recoveries, you said you're targeting 90%. Clearly, given the grades you've been processing, recoveries have come in below that. Then, of course, once things are fully recovered, you'll move up to that 95% later on. On that roughly 90% figure — I believe it was around 82% in the quarter — when should we expect that 90% to apply? Could that potentially arrive as early as Q1 next year, or is it a bit later than that?
I can take that question. There are two reasons behind the low recovery — that 82% figure. First, low grade, which accounts for a couple of percent; second, low feed grade, which accounts for another couple of percent reduction in recovery. On top of that, some oxidized copper has been sitting on the stockpiles. Those stockpiles have been there for a number of years, and that material isn't recoverable. Since the sulfide is oxidized, flotation can't recover it. I think once the stockpiles are depleted by the end of the year and we begin mining fresh rock, we'll get back to close to 90% recovery, which is roughly what we were achieving before we had the issues. I'm not sure whether we mentioned this. We're busy with a project called Project 95 at Kamoa, phase I and phase II — basically it involves installing a whole lot of regrind capacity. We call it Project 95 because we're going to take that 90% odd recovery up to 95% recovery, and it will be commissioned in Q2 next year. In Q2 next year we'll be mining fresh rock, the grade will be better, and the plant will be achieving 95% recovery on phase I and phase II.
So next year from Q2 onward, phase I and phase II sit at 95%, and Q1 could potentially be 90% — is that right?
Yes, that's right.
Alright, understood, and thanks a lot for that. I have one more question about the stockpiles you're drawing down, which have been helping supply the concentrators while the mine is being restored. The expectation is that those stockpiles will be used up by the close of Q1, though I might have heard incorrectly — you may have said they could be gone by the end of this year. I'd just like to get a clearer picture of the shift from stockpiled material feeding the concentrators to ore that's been mined. With run of mine feed coming in, is there a risk in how that transition is being handled? Could there be a risk that you exhaust some of your inventories — your stockpiles, your surface stockpiles — before you have enough run of mine ore available to supply the concentrators?
Yeah, I believe throughput through the concentrators is going to drop, especially at Kakula. The extra tons we pull from Kamoa will be trammed over to Kakula to help out there too. I think there's some upside from the material being fresh, when it comes to recovery and processing. Output at Kakula phase I and phase II will come down a bit, purely because there isn't sufficient fresh run of mine to fill those plants — to fill the 10.5 million tons of capacity we have installed there.
Alright, thank you. Got it. Last question regarding the stockpiles — the copper and concentrate inventories sitting at 59,000 tonnes — how should we view the way those get reduced across 2026? What level is the optimal one it reaches, and by what point in time?
From what I can recall, the optimal level is roughly 19,000 tons. That figure refers to the inventory and stocks sitting ahead of the smelter. They have a ramp-up plan that wraps up around Q3 2026. By Q3 2026 for sure, that 59,000 tonnes will come down to 19,000 tonnes.
All right, that’s very clear. Thank you so much.
Thanks. At this point, I’d like to hand the conference back to Matthew Keevil.
Much appreciated, Operator. It's now the top of the hour, and nothing is waiting for us in the webcast queue. So with that, we'll bring things to a close today. Thanks once more to all of you for being with us. We're eagerly anticipating plenty of good developments from the recovery program and the Platreef ramp-up in the months ahead. We look forward to speaking with you again, and have a wonderful day. That being said, please wrap up.
Much appreciated, sir. Everyone, that really does bring today's conference call to an end. Thanks again for joining us, and right now we'd ask that you kindly disconnect your lines.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Ivanhoe Mines Ltd. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Ivanhoe Mines Ltd. earnings transcripts and 132,000+ others is available through the