Hello, and thanks for being with us today. Welcome to the Lundin Mining conference call covering first quarter 2026 financial results. Right now everyone is in a listen-only mode. Following the speakers' presentation, we'll hold a question-and-answer session. If you'd like to ask something during that session, press *11 on your phone. An automated message will then confirm that your hand is raised. Should you wish to withdraw your question, just press *11 once more. Please note that this conference is being recorded today. I'll now hand the conference over to today's speaker, Jack Lundin, President and CEO. Go ahead, please. It seems your line may be muted. Please unmute it.
Good morning, everyone, and thank you for joining us for Lundin Mining's Q1 2026 financial results. We released our financial and operating results for the first quarter last night. We're grateful for your ongoing interest as we walk through our performance and the key developments during the period. The presentation can be found on our website, and a replay is available there as well. Unless otherwise noted, all figures we present are in US dollars from continuing operations. Before we begin the call, I'd ask everyone to review the cautionary statements on this page. Please be aware that certain remarks today will include forward-looking information and are subject to risks and uncertainties. For further details, please see the cautionary statements on slide 2 and our latest filings on SEDAR. Thank you for your attention as we proceed. With me on today's call are Juan Andrés Morel, our Chief Operating Officer, and Teitur Poulsen, our Chief Financial Officer. I'm happy to report that we got off to a solid start in the 2026 calendar year, as reflected in these first-quarter results. On the operational side, we produced roughly 79,900 tonnes of copper and 31,500 500 ounces of gold at a consolidated C1 cash cost of $1.66 per pound, which keeps us on track with our annual guidance.
For the quarter, our operations brought in more than $1.1 billion in revenue, $627 million in adjusted EBITDA, and $380 million in free cash flow from operations, which shows how consistent and stable our asset base is. Those results bolstered our net cash position, and as of quarter-end we held roughly $250 million in cash, net of debt, and excluding lease liabilities. Several corporate events took place during the quarter, and this slide presents the main highlights. One notable milestone, which most people on this call will already know about, was the results and subsequent filing of the integrated technical study on the Vicuña Project, which underscores a Tier 1 asset able to produce more than 500,000 tonnes of copper and 800,000 ounces of gold at a first-quartile C1 cash cost. In March, we hosted a group of analysts and investors for a visit, touring both the Vicuña Project and the Caserones operation. That visit showcased the district's outstanding potential, anchored by the stable, high-margin Caserones asset and complemented by the substantial long-term growth opportunity throughout the wider Vicuña district with the Josemaria and Filo del Sol deposits. While there, we announced the acquisition of an extra 5% interest in Caserones, together with a 31% interest in the neighboring Los Helados project, acquired from our partners at JX Advanced Metals.
At this point, our stake in the Caserones mine stands at 75%. At Los Helados, we anticipate substantial synergies as well as strategic optionality going forward, and we'll keep assessing that project while giving the market updates across the year. Later in this presentation, I'll address how the region is developing. Measured on an attributable basis, our company's copper mineral resources rose by roughly 115% year-over-year, reaching more than 39 million tonnes. That figure takes in the 31% interest held in the Los Helados project. With growth opportunities across our portfolio advancing quickly, we hold strong conviction about turning these resources into reserves, consistent with our strategy of feeding a pipeline of growth opportunities. One major factor behind this sizable gain was the maiden resource estimate produced at Vicuña last year, which brought in the Filo del Sol deposit and brought to light what is today viewed as the biggest copper discovery of the past 30 years. Within the Vicuña Project sit 40 46 million tonnes of copper, 97 million ounces of gold, and 1.8 billion ounces of silver, and it keeps expanding through the drill bit. In the quarter, we completed enlarging our revolving credit facility from $1.75 billion up to $4.5 billion, which ensures full financing for stage one of the Vicuña Project.
Our balance sheet is in excellent condition, and with a larger credit facility, we're well placed to cover our share of the project. Consistent with our policy on shareholder distributions, we bought 1.4 million shares this quarter for $40 million US dollars under our share buyback program, and we also declared our Q1 dividend. Since 2017, dividends and share buybacks have delivered more than $1.6 billion back to shareholders. Lastly, we submitted our first CSRD report under the EU Corporate Sustainability Reporting Directive, which offers stronger disclosure and more rigor regarding our key environmental, health and safety, governance, and social commitments, and this underscores our commitment to responsible mining practices. I'll now turn the call over to Juan Andres, Chief Operating Officer, to discuss our production results.
Thanks, Jack, and good morning to everyone. We're happy to say that this quarter we achieved one of our best safety results ever, with a TRIF of 0.03, and that went hand in hand with solid operating performance from our assets. Company copper output came to 79,900 tonnes in the quarter, which matches guidance. Gold output for the quarter was 31,500 ounces in total. We anticipate that gold-grade profiles at Candelaria and Chapada will help deliver a stronger second half for gold production, and we remain on track with guidance. At Candelaria, we produced 30,800 tonnes of copper and 17,700 ounces of gold. Lower grades resulting from mine sequencing in the first quarter, together with roughly 3 days of unscheduled downtime to finish preventive maintenance on the mill, weighed on production. While the mill was down, we seized the opportunity and brought forward scheduled maintenances that will boost runtime hours in the second half of the year. Candelaria will be weighted toward the second half, with approximately 55% of production expected in Q3 and Q4. Candelaria's production is tracking to plan and on target to meet guidance for the year. Caserones had a strong quarter and produced 38,600 tonnes of copper.
Improved grades from ore that came out of Phase 6 helped drive output higher, together with strong cathode production. Cathode output remains robust thanks to increased irrigation rates, better irrigation patterns, and additional material being stacked on the dump leach pad. At Caserones, we anticipate a first-half-weighted year, with grades declining in the second half. Caserones is likewise on track to meet guidance for the year. Chapada's mill throughput was elevated this quarter due to greater mechanical availability and softer ore, which compensated for lower grades. Chapada turned out 10,600 tonnes of copper and 13,800 ounces of gold during the quarter. Output will also lean somewhat toward the second half of the year, reflecting the mine's grades profile. I'll now hand the call over to Teitur for a summary of the financial results.
Thanks, Juan Andres, and good morning, everyone. On the financial side, we delivered another exceptionally strong quarter, supported by steady operations and stronger commodity prices. Revenue came in at just about $1.2 billion. During the earlier part of the quarter, we closed the sale of Eagle Mine to Talon Metals, a step that cements our standing as a company that is now predominantly a pure-play copper producer, with roughly 85% of revenue coming from copper and about 10% from gold. Caserones ranked as our biggest revenue contributor for a second quarter in a row, representing 44% of the company's total revenue. Turning to the next slide, on volumes sold and realized pricing: over the quarter we sold 77,700 tonnes of copper at a realized price of $5.70 per pound, along with 29,900 ounces of gold at $5,120 per ounce. The LME copper price was quite stable during the quarter and moved relatively in line with where the LME copper price stood at the end of 2025, and that consequently produced a realized price of $5.70 per pound in the first quarter, which reflects provisional adjustments relating to sales from prior periods and sits closer to the LME average copper price for that same period. Every shipment planned for the close of the first quarter was completed successfully, and as a result our concentrate inventory levels stayed comparatively low at the end of the first quarter, at roughly 29,000 tonnes of concentrate inventory.
Closing out Q1, roughly 67,100 tonnes of copper carried provisional pricing at $5.54 per pound and stayed open for final pricing adjustments; likewise, 27,900 ounces of gold were open at $4,540 per ounce. Slide 12 summarizes the breakdown of our operating costs. Following the outbreak of war in the Middle East, attention on input costs across the mining sector has intensified. As this slide shows, the majority of our costs divide among labor, consumables, and energy. Taken together, those input costs represent about two-thirds of our overall cost structure. Diesel made up roughly 7% of total operating costs in Q1, and because diesel prices climbed only near the end of the quarter, the effect on the quarter overall was limited. Our present guidance assumes a diesel price of about 60 cents per liter based on the New York Harbor index. The New York Harbor price currently sits near $1 per liter, and combined with the partial removal of Chile's specific diesel tax credit for mine diesel use, that increase is projected to raise C1 cash cost by roughly 8 cents per copper on a consolidated basis for the year — meaning the company stays on track to hit full-year C1 cash cost guidance even should today's diesel prices hold through the remainder of the year.
We’ve taken steps in advance to raise the amount of physical diesel storage we have in Chile at our two mines, going from roughly one week of consumption to one month of consumption. With this added storage capacity, we can reduce exposure to supply risks and keep operations running in the short term if diesel supply restrictions come up down the road. On the whole, consolidated production costs are lower than in the prior quarter and have stayed in line with earlier periods, coming in at slightly less than $500 million, while the adjusted EBITDA margin was 54%. In the last quarter, the higher costs resulted from greater sales volumes. At Candelaria, during the fourth quarter of last year, the company completed early renewals of labor agreements, and that produced a one-time cost increase because of signing payments. Total costs for the first quarter were $202 million, versus $227 million in the preceding quarter. At Caserones, costs are down quarter-over-quarter, which mirrors the smaller volume sold. Stronger cost control and greater by-product credits, partly offset by a stronger Chilean peso, have helped bring C1 cash cost down to $1.58 per pound — the lowest level Caserones has recorded since we acquired the asset. Unfavorable foreign exchange rates affected both Candelaria and Caserones. Against the US dollar, the Chilean peso appreciated by roughly 5% relative to the previous quarter.
Over at Chapada, expenses held steady, and thanks to a stronger gold price, the C1 cash cost came in at 45 cents per pound, which is consistent with what we saw in the prior quarter. Looking at the consolidated figures, C1 cash cost for the quarter was $1.66 per pound, and that sits under our full-year guidance range of $1.90 to $2.10 per pound, largely because of higher by-product credits. Slide 14 lays out our key financial metrics for the first quarter. Solid operational performance drove adjusted EBITDA of $627 million along with adjusted operating cash flow of $450 million for the quarter. That adjusted quarterly EBITDA number was once again close to a record for the company, and it reflects the ongoing benefit of higher commodity prices and strong production across our assets. Moving on with the financial results, free cash flow from operations came to $380 million, and adjusted earnings were $265 million, giving us adjusted earnings per share of 31 cents attributable to our shareholders. Sustaining capital expenditure for the period was $126 million in total, and expansionary capital expenditure totaled $54 million, with $52 million of that spent at Vicuña. Most of the sustaining capex went toward open pit waste stripping, underground mine development, and tailings storage development.
Sustaining capex came in a bit below what we'd expected, and that's because of project delays at Caserones and Candelaria. Looking ahead, we expect the pace of capital spending to pick up across the rest of the year, and our guidance for full-year sustaining capex across all assets hasn't changed. We also had an underspend at Vicuña in Q1 tied to the phasing of expenditure, so our full-year guidance for Vicuña spend stays at $395 million for our 50% interest. On slide 17 you can see a more detailed breakdown of where cash came from and where it went in the first quarter. Continuing operations brought in just under $500 million of operating cash flow, after we paid $95 million in cash taxes. Following $126 million of sustaining capital spend, the company produced free cash flow from continuing operations of $380 million. During Q1 the company declared a dividend that will be paid out in Q2, and it also bought back $40 million in shares under its share buyback program. Dividends paid to non-controlling interest at Caserones came to $60 million, and on a consolidated basis the company finished the quarter with $565 million in cash. Excluding capital leases, we closed the first quarter with a net cash position of roughly $250 million, versus a net cash position of $77 million at the end of last year.
After the quarter ended, we completed the purchase of an extra 5% stake in Caserones along with a 31% interest in Los Helados, and that generated a cash outflow of $250 million when the deal closed, which leaves the company sitting at a current net cash position of $51 million. In the first quarter, the company wrapped up the expansion of its revolving credit facility up to $4.5 billion. At present, $2.25 billion is available to draw under that facility, and it will grow to $3.5 billion once certain conditions are met, then rise further to the entire $4.5 billion following approval of Stage 1 of the Vicuña Project. To wrap up, from a financial standpoint the company remains in excellent shape, thanks to producing assets that are highly cash-generative, net cash on the balance sheet, and plenty of liquidity on hand to fund its exciting growth plans, all while keeping an annual shareholder distribution of roughly $250 million. With that said, I'll turn the call back over to Jack.
Thank you, Teitur. Back in February, we shared the findings from the integrated technical study on the Vicuña Project, which verified its Tier 1 designation and laid out a thorough plan for staged development. That study underscores what the project can deliver — substantial returns driven by large-scale output of copper, gold, and silver, with an operating cost profile in the first quartile or better. You can find the technical report filed on SEDAR, where it is available to download. Under the project governance framework, the technical assurance and peer review work done for the PEA phase surfaced chances to build value and move closer to sanction readiness by way of focused de-risking efforts spanning every stage of development. The Vicuña team is pushing these efforts forward actively, and detailed design and engineering kept advancing on schedule in line with the 2026 work plan. Out at the site, things are moving along nicely as project readiness builds. More than 100 people were hired by the project during the first quarter, lifting the full-time Vicuña Corp workforce by roughly 25%, contractors not included. Preparation for early works is in progress, which includes continuing training for equipment operators, and the first deliveries for the earthworks fleet have started to arrive. Site development should get underway over the next few months, backed by the arrival of the 40-tonne trucking fleet along with other auxiliary equipment.
That construction camp with 1,500 people is still where we run things from. Right now the work is mainly early earthworks, getting ready for the bigger bulk earthmoving, and the plan is for us to self-perform that as part of how we start construction. On top of that, our RIGI application — we filed it back in December under the Long-Term Strategic Export Project category — is still moving through review, and we've gotten through several rounds of questions, the latest one at the end of April. We expect approval soon, and that will back our final investment decision on Stage 1, which we're aiming for as soon as before the end of this year. Another exciting development opportunity for the company was the transaction we announced recently with our partners JX Advanced Metals, which Teitur mentioned. Through our additional ownership in Caserones, we picked up a 31% stake in the Los Helados project. Los Helados sits about 17 km south of our Caserones mine, roughly halfway between Caserones and the Vicuña Project on the Chilean side of the district. As you can see in the center of this slide, the NGEx exploration team drilled the initial discovery hole in 2011, and since then more than 100 km of drilling has defined a significant resource.
There’s substantial synergy potential and long-term optionality, in our view, between Los Helados and Caserones. We’re actively assessing ways to realize those synergies—among them hauling mined ore over to Caserones—plus a scenario in which Los Helados is developed on a stand-alone basis. Throughout the year, that effort will keep moving forward together with our partners at NGEx. Los Helados is an advanced copper-gold development asset, and to date over 100 drill holes have been completed there. That drilling has produced a resource estimate, on a 100% basis, of 12 million tonnes of copper and 14 million ounces of gold, together with a higher-grade core of 2.9 million tonnes at 0.72% copper equivalent—giving us a solid foundation for continuing to move the project ahead and analyze it alongside our partners. We’re eager to share an update on how we see Los Helados at the Capital Markets Day we’ll hold in June. We’re highly encouraged by how strong the start to 2026 has been. Solid operating performance has fed through into robust cash flow, which lets us keep building on our net cash position. We stay firmly on course to meet full-year guidance, while keeping cost and capital management disciplined. With liquidity now stronger, we’re well placed to move Vicuña forward as well as other growth opportunities, and at the same time to keep returning capital to shareholders via our dividend and buyback program.
At Lundin Mining, our results are built on running high-margin, stable operations with discipline. Backed by a growth strategy that has no equal and a balance sheet that remains strong, we're set to create substantial value for our stakeholders in the years to come. With that said, I'd like to turn the call over to questions now. Thank you, operator.
Thank you. Just a reminder that if you'd like to pose a question, press *11 on your phone. An automated message will confirm that your hand is raised. We also ask that you hold off until your name and company have been announced before you go ahead with the question. One moment while we take the first question. The first question comes from Orest Wowkodaw at Scotiabank. Please go ahead.
Hello, and good morning. I appreciate the sensitivity you provided regarding diesel prices in opex. With the current environment, I'm wondering whether you could also share the potential impact on Phase 1 capex at Vicuña. I'm curious what diesel price was assumed for Phase 1 compared with where spot stands today. In addition, I'm wondering whether you're beginning to see any inflationary pressures as you obtain, I assume, firm contracts for portions of Phase 1?
Hi, Orest. Teitur speaking. The capex figures we published in the PEA rested on input factors that were, in effect, tied to spot prices as they stood at that moment. Diesel would have been nearer to the assumption behind our C1 cost guidance for the company — roughly 60 cents per liter. We are still working through bottom-up cost estimates for Phase 1, though we don't expect much movement there. Clearly, this is a development phase spanning 3 or 4 years, so let's see how it plays out. We're also working to map the volume of every input cost, and then to make a call later alongside BHP, our partner on Vicuña, on whether we ought to lock in hedging for any of those input costs. That is still being evaluated, and nothing has been decided yet. As for our operating assets, I believe we're well placed, as I mentioned on the call. Should today's diesel prices hold for the rest of the year, we will remain inside guidance. In fact, we ran a sensitivity: even if diesel prices were to double from where they are now, we still expect to land within the upper end of our C1 cost guidance of $2.10.
From an input-cost standpoint, I'd say we're positioned well, even though we've recently been seeing some pressure from rising input costs.
Thanks. To build on that, could you speak to the sulfuric acid expense at Caserones? What sensitivities could you share around that?
Hey Orest, Juan Andres here. At Caserones, sulfuric acid usage is pretty modest — 45,000 tonnes annually. We haven't seen any signs that our suppliers are short on supply. Costs have risen slightly. We're now above $300 per tonne for sulfuric acid, but up to this point supply keeps coming without any interruptions.
All right. Does that price stay locked in for a set period, or is the acid entirely exposed to the market?
Actually, there are a few modifications we're making to the spot price.
All right, thanks.
We'll take a brief pause before taking the following question. The next caller is Matt Greene from Goldman Sachs. Your line is open — go ahead.
Hello there. Good morning, everyone. Teitur, perhaps I could put the diesel question in a different way. That reflects strong cost performance, though a significant portion of your capex involves earthworks, which are clearly far more diesel-heavy than the wider cost base, presumably. Could you tell us, based on that 400 million for Vicuña, what share of it relates to earthworks? And then, I suppose, for each dollar allocated to earthworks, could you indicate how much of that connects to fuel?
No, I don’t have that granular a level of information. Of course, diesel, steel, and cement — every one of those input costs matters when it comes to capex for Vicuña, so, like I said, that’s something we’re mapping out as we proceed from the more detailed engineering work on the project and the bottom-up capex estimates. I think it would be prudent for us to examine those volumes and how they are phased across the next 3, 4 years, and then determine whether we ought to lock anything in. Given where diesel prices are trading right now, I’m not sure I would recommend locking anything in at these levels, but I think, assuming things normalize in the Middle East later in the year, it would be prudent to perhaps consider locking in certain of those costs.
Understood, that's excellent, thank you. So, staying on Vicuña, the remarks included there regarding the power situation with ENRE — could you expand on just what is happening there? Because my understanding is that you are financing a transmission line, and you receive roughly 90% of the capacity that you're building out. Some of your peers in the region, I believe, are resisting parts of this, and a hearing is scheduled next month. Could you elaborate on just what's happening there, and, I suppose, if the outcome of that hearing were negative, would that have any effect on the sanctioning or the development timeline?
Hey Matt. On the specifics there, we’ll need to circle back to you, but from where we stand today, the transmission line and what we’re doing under our off-site infrastructure planning remain on schedule. Our plan is to hook up to the national grid via Rodeo and San Juan so that 260 to 290 megawatts can be delivered to the project. That hearing you’re probably thinking of is a standard step in linking power into Argentina’s national grid — yes, we monitor it closely, but as things stand right now, we haven’t observed any material effects that might negatively affect our planning.
Excellent. Everyone, thank you so much.
Thank you. Just a reminder — if you'd like to pose a question, dial *11 on your phone. We'll take a brief pause before the next question. One moment. Our next question comes from Craig Hutchison at TD. Please go ahead.
Morning, everyone. In your opening comments, you mentioned some of the efforts your team is making at Los Helados. Given that you hold a 31% interest, do you intend to collaborate with NGEx and release some form of scoping-level study later this year or early next year? I'm just curious about how you plan to crystallize value there, and what that might look like. Thanks.
Appreciate that question, Craig. For sure. So at this point we hold a 31% interest in Los Helados, and we're collaborating with our partners at NGEx — who are now our partners — to figure out which development paths are available, and we sit roughly 17 km from Caserones. What we're examining is where synergies could arise from what we might build out via Los Helados and from moving material over to Caserones. We're also asking whether additional exploratory drilling is needed, and reviewing various development concepts — for instance, possibly constructing a brand-new concentrator near Los Helados. Every bit of that is effort we'd carry out alongside our partners at NGEx, and in the end plenty of work remains, since we've only just earned into this deposit, though it's a highly attractive one. The exploration upside and the prospective ground are still there, so we intend to provide a fuller update on the work completed and the work ongoing at our Capital Markets Day, which comes in just over a month. It's very exciting for us, because we view this as sitting right in the middle of the Vicuña district, where we already have substantial investments and know the region very well, and we're eager to watch this growth opportunity develop.
Alright, so if we just stay with Caserones for a moment — you folks posted really strong cathode production figures this quarter. Do you see chances to remain around those levels, and possibly land at the upper end of your guidance there? I'm aware you're doing quite a lot of work in that area. Thanks.
Thanks. Just a moment while we move to the next one.
Craig, you have a question?
We remain on the line.
Appreciate the question. Juan Andres here. Of course, we see opportunities to get sustaining capex stabilized across all of our assets. We keep examining that through our full potential initiative, and we'll probably update the market at the next Capital Markets Day.
Excellent. Appreciate it, everyone.
Thanks — please hold a moment while we take the next question. That question comes from Stefan Ioannou at ATB Cormark Capital Markets. Go ahead.
Appreciate you taking the question. Perhaps just as a follow-up to what Craig said about Los Helados — and maybe this is something that comes up at the Capital Markets Day — but I just recall that there's also quite a lot of compelling exploration, not only at Los Helados but also between Caserones and Los Helados beyond Angelica. Going forward, is the plan to do a fulsome, deeper dive on that exploration potential as well, and how that might tie into a Los Helados strategy? Or is the current thinking to focus on Los Helados and how it fits into Caserones on its own?
Hi Stefan, appreciate the question. You've got it exactly right. At the time we bought Caserones, we picked up a sizable land position — roughly 58,000 hectares of territory in the Vicuña district that hadn't seen much exploration. Together with our exploration group, which Tim Walmsley, our VP of Exploration, heads up, plus the Caserones team of course, we've been working out how to phase that work. Our attention has been on the deep sulfide zone at Caserones. As you know, we've also been focused on Angelica. There's an oxide overburden there, and below it we've been probing for sulfide breccias, trying to determine whether that material might potentially work its way into the mine plan, provided we can establish a meaningful volume at grades that are attractive enough. That near-mine exploration is ongoing. In addition, we're examining two targets that we're drilling out at present, situated somewhat farther from Caserones, and we'll keep advancing those opportunities while simultaneously assessing this new development opportunity at Los Helados. All of it feeds into our capital allocation framework, and we consider where the highest-impact investments might lie — though in the end, exploration in this region will be prioritized based on where we think we can swiftly convert a discovery into a resource, then into a reserve, and finally fold it into the Caserones mine plan.
Given that we possess such a clearly defined resource at Los Helados, or a partnership stake of this kind, or equity in this Los Helados deposit, it is now moving onto the horizon of development-type opportunities.
Excellent. Understood. Thank you so much.
Thanks. Right now the queue has no further questions, so I'd like to hand the call back to Jack for his closing remarks. Jack, please go ahead.
Thanks, everyone, for being on the call. At Lundin Mining, we keep seeing excellent headway across every one of our initiatives, along with another strong quarter. We'll keep moving forward with discipline on capital, disciplined operational execution, and the pursuit of our highly exciting growth opportunities, and we look forward to giving the market a more detailed update at our upcoming Capital Markets Day on June 17th. Thank you.
We appreciate everyone being part of today's program. You can go ahead and disconnect at this point.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Lundin Mining Corporation transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Lundin Mining Corporation earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.