Lundin Mining Corporation (LUN) Earnings Call Transcript

August 6, 2026

Toronto Stock Exchange CA Materials Metals and Mining earnings 48 min

Earnings Call Speaker Segments

Operator operator
#1

Good morning, everyone, and thanks for joining us today. I'd like to welcome you to the call covering Lundin Mining's financial results for the second quarter of 2026. Right now, everyone has been placed in a listen-only mode. Following the speakers' presentation, we'll open things up for a question-and-answer session. If you'd like to ask a question during that session, simply press *11 on your phone. An automated message will then confirm that your hand has been raised. Should you wish to withdraw your question, just press *11 once more. Please note that this conference is being recorded today. At this point, I'll hand the call over to Jack Lundin, our President and Chief Executive Officer. Jack, please go ahead.

Jack Lundin executive
#2

Good morning, and welcome to Lundin Mining's conference call for the second quarter of 2026. We appreciate you being with us today. A press release and a presentation that summarize the results for the quarter can be found on our website, and a replay of this call will be posted there as well. Before we get started, I want to remind everyone that today's presentation and some of the remarks made during the call, including in our Q&A, will contain forward-looking information that carries risks and uncertainties. Please note the cautionary statements on slide 2, and I encourage you to review our MD&A and related filings on SEDAR for a complete description of the relevant risk factors. As a reminder, unless otherwise noted, all amounts discussed on today's call are in US dollars. With me on the call today are Juan Andrés Morel, our Chief Operating Officer, and Teitur Poulsen, our Chief Financial Officer. If you turn to slide 4, the second quarter was another productive period for the company operationally, financially, and strategically. In line with our corporate vision, we completed the acquisition of an additional 5% interest in Caserones from our partner, JX Advanced Metals, bringing our total ownership to 75%. We also acquired a 31% interest in the Los Helados project, all for total consideration of $215 million.

Jack Lundin executive
#3

Los Helados is a sizable copper-gold deposit situated roughly 17 km to the south of Caserones. By completing this deal, we bolster the foundation of our mineral resources and gain attractive long-term growth optionality within a district we understand well. Our second annual Capital Markets Day took place on June 17th, and there we expanded upon last year's strategic vision and refreshed our financial outlook covering the coming 5 and 10 years. We drew attention to several low-capital-intensive brownfield expansion possibilities across our three existing operations — Candelaria, Caserones, and Chapada — as well as the transformational long-term growth potential of the Vicuña project. Together, these opportunities support our journey toward ranking among the top 10 global copper producers. During the CMD, we gave the green light to building an extra ball mill at Chapada, which will deliver better recoveries at that operation in anticipation of the Saúva growth project — one more concrete step in turning our brownfield pipeline into production. We expect construction to begin by year-end, with commissioning targeted for late 2027. At Vicuña, the quarter brought a significant milestone: approval of the inclusion of the Josemaria and Filo del Sol deposits under Argentina's RIGI regime program. Vicuña becomes the first copper mining project in Argentina to earn this more favorable designation.

Jack Lundin executive
#4

This approval gives us fiscal stability over the long term and certainty for investment, and it represents a meaningful move ahead as we move toward a Stage 1 sanctioning decision. After the quarter ended, Vicuña announced a long-term agreement with the San Juan province covering royalties and an infrastructure trust for the life of mine, which brings together the provincial royalties that already existed on the Filo del Sol and Josemaria deposits under a single framework. That framework includes a 3% mining royalty and a 1.5% gross revenue royalty that together form a provincial infrastructure trust. The agreement delivers economic certainty over the long term and improves how stable our operating framework is as we keep moving toward a sanctioning decision. Last item on this slide: we bought back roughly 2.2 million shares in the quarter, taking our year to date total to 6.1 million, which reflects our confidence in the intrinsic value of the company and the strength of our balance sheet. Since 2017, we have returned more than $1.8 billion to shareholders via dividends and buybacks. On the operational side, the quarter was highly consistent, helped by disciplined execution throughout our operations and a copper price environment that was supportive. Copper production came in at about 76,900 tonnes, and with a consolidated cash cost of $2.11 per pound that translated into $1.2 billion in revenue and $360 million of free cash flow from operations, which further strengthens our balance sheet and gives us the financial flexibility to keep investing in our growth pipeline while returning capital to shareholders.

Jack Lundin executive
#5

Even with the storm that hit following the quarter — and Juan Andres will get into that further during the operations portion — we're still, halfway through the year, on course to hit our annual production guidance range. Our operations have done well, and that gives us confidence in our capacity to meet our full-year objectives. Operational costs in the quarter took a hit from higher diesel prices. If pricing stays where it is now for the rest of the year, we still anticipate landing inside our guided cost outlook. Going forward, we remain focused on safety performance, on delivering operational excellence, on moving our pipeline of organic growth opportunities forward, and on driving the Vicuña project toward a sanctioning decision. Backed by high-margin, long-life assets, a disciplined approach to capital allocation, and one of the strongest copper growth profiles in the industry, we believe Lundin Mining is well positioned to deliver sustainable, long-term value for our shareholders. I'll now pass things to Juan Andres, who will walk through the operational results in more detail.

Juan Andrés Morel executive
#6

Thank you, Jack, and good morning to everyone. During the second quarter our operations delivered consistent performance, and we continue to expect to hit the annual production guidance we have set for both copper and gold. After the quarter had ended, the storm in Chile affected operations at Caserones, and later in this presentation I will give you more detail on that. As was mentioned earlier, copper production from our three operations came to 76,900 tonnes for the quarter. In the first half of the year, we produced roughly 157,000 tonnes of copper. Gold production in the quarter was 33,000 oz, which takes our year-to-date gold output to approximately 65,000 oz. If we compare our first-half copper production against our full-year guidance range of 310,000 to 335,000 tonnes, we are on track toward guidance despite the weather-related events I mentioned earlier, and that aligns with our expectation that production will be weighted toward the second half, particularly at Candelaria. On gold, we are likewise well positioned to reach our full-year guidance of 134,000 to 149,000 oz. Broadly, the portfolio is performing in line with the planning assumptions we have made, and our operations are delivering the consistency required to meet our targets. Turning to each operation individually, at Caserones copper production for the quarter was approximately 34,000 tonnes, with higher grades from Phase 6 and strong throughput still benefiting from the initiatives of our Full Potential program.

Juan Andrés Morel executive
#7

So far this year, we've produced 73,000 tonnes. At Candelaria, copper output for the quarter came in at roughly 31,000 tonnes, and mining grades were a bit lower than in the first quarter — that reflects extra shovel maintenance and ramp work in Phase 11 of the open pit. We're still confident Candelaria will hit its full-year guidance. The production profile at Candelaria stays second-half weighted, and we expect better grades in the third and fourth quarters as we keep moving forward with Phase 12. Gold output for the quarter was around 18,000 oz, which is in line with what we expected. Over at Chapada, we had a good quarter — strong throughput, and copper grades slightly better than in recent periods as we access higher-grade portions in the South Pit. Copper production for the quarter was about 12,000 tonnes, and gold production was 16,000 oz. We expect output levels to stay consistent with Q2 through the second half of the year. After the quarter ended, Chile's Atacama region was hit by severe winter storms that caused flooding across the region and significant snowfall. Candelaria saw over 35 of rain, and Caserones had 3.4 m of snow. The country reported 13 fatalities and over 2,200 injuries tied to the storm — a truly tragic event that affected several regions in Chile. I want to recognize the Caserones and Candelaria teams for all their hard work and for proactively taking precautionary measures to protect employees, and a special thank you to the crew at Caserones who were isolated at the site during the storm for their dedication.

Juan Andrés Morel executive
#8

We’re grateful that everybody stayed safe and that no injuries were reported across our operations. Heavy rainfall briefly affected mining activities at Candelaria. Even so, the mill kept running by drawing on ore stockpiles already on hand. Mining has since come back to full capacity, and the company is still on course to achieve its production guidance for the full year. At Caserones, heavy snowfall and strong winds disrupted operations, restricting access to the site and cutting power for 12 days. Backup generators carried critical activities through that period. Wind speeds exceeded 125 km/h, and ice accumulation caused damage to two power line towers that need repairs. Crews spent all of last week taking down the damaged structure and putting up a replacement. The photo on the right shows the harm done to the upper tower and cross arm of one of those towers. Electricity has been restored at the site, and operations at Caserones are now in the process of restarting. The first concentrate output is anticipated by the end of this week, with full capacity early next week. Before the storm, Caserones had been trending toward the upper end of its copper guidance, having produced 73,000 tonnes in the first half of the year versus the 130,000-tonne to 140,000-tonne range.

Juan Andrés Morel executive
#9

Our planning does take into account certain disruptions caused by weather, though not of this size. Having gone back over the mine plan for the rest of the year and made a few adjustments, we now expect to land in the lower half of the guidance range at Caserones. That assumes weather stays on our side for the remainder of the year and that operations run well in the third and fourth quarter. Cash cost guidance at Caserones is unchanged. So far this year we are running below the guidance range at $1.85 per pound, and we now expect to be inside Caserones' cost guidance range of $2.05 per pound to $2.25 per pound. Candelaria and Chapada keep performing well, and we reiterate our consolidated full-year production guidance range of 310,000 to 335,000 tonnes of copper and 134,000 to 149,000 oz of gold for the year. I will now hand the call over to Teitur to give a summary of our financial results.

Teitur Poulsen executive
#10

Thanks, Juan Andres, and good morning, everyone. As I noted earlier, we delivered yet another quarter of steady operational results, and that has carried through to outstanding financial performance. Operating revenue for the quarter came in above $1.2 billion, which is close to a record, supported by robust copper and gold prices together with steady output volumes at all three of our operations. Our revenue mix stayed weighted heavily to copper, which made up roughly 88% of total revenue for the quarter, giving us one of the strongest copper leverages among our peers. Gold accounted for about 8% and moly about 2%, and the balance came from silver and other metals. Looking at each operation, Caserones was the biggest revenue contributor at around $518 million, then Candelaria at roughly $476 million, and Chapada at $219 million. For the year to date, revenue reached $2.4 billion, which reflects the substantial increase in realized prices for both copper and gold versus the comparable period a year earlier. Moving now to volumes sold and realized prices: during the quarter we produced 77,000 tonnes of copper and sold about 74,000 tonnes, making this one of the weaker quarters recently in terms of copper sales volumes. That comparatively low sales volume was more than offset by a record realized copper price of $6.51 per pound and a significant improvement over the $4.40 per pound realized in the same quarter last year.

Teitur Poulsen executive
#11

Gold was sold at a realized price of $4,385 per ounce. At quarter-end, roughly 47,600 tonnes of copper were still provisionally priced at $6.07 per pound, and final pricing will be settled over the upcoming quarters, with most of that settling during the third quarter. Turning to production costs, our underlying cost structure stayed stable across operations this quarter, with total production costs of about $513 million. The main source of modest cost pressure this quarter was higher diesel prices, which affected all three operations to differing degrees. As Jack noted, if diesel pricing stays at current levels for the rest of the year, we still expect to meet consolidated cash cost guidance of $1.90 to $2.10 per pound copper. Apart from this fuel-driven impact, the underlying operational cost base continues to perform in line with our expectations. Higher diesel prices raised costs by roughly $15 million in the second quarter versus the first quarter, equivalent to approximately 8 to 10 cents per pound copper on a consolidated basis. Our consolidated cash costs came in at $2.11 per pound of copper for the quarter, showing disciplined cost management despite higher diesel prices.

Teitur Poulsen executive
#12

While that came in a bit above the $1.90 to $2.10 per pound range we guided for 2026, we're still on course to hit our full-year guidance. Cash costs so far this year sit at $1.88 per pound, which is under the bottom of the full-year guidance range. At Caserones, cash costs stayed broadly in line with expectations at $2.14 per pound. Those cash costs keep benefiting from strong cathode production and favorable TC/RC terms, partly offset by higher diesel costs this quarter. At Candelaria, cash costs came in somewhat higher this quarter at $2.65 per pound, reflecting lower byproduct credits driven by a lower realized gold price versus recent periods, along with slightly higher stripping costs and lower sold volumes than the prior quarter. On top of that, Candelaria consumes more diesel than our other assets, so the rise in diesel prices hits Candelaria harder than it does our other assets. At Chapada, absolute costs for the quarter were $84 million, in line with the prior quarter. The cash costs recorded were 62 cents per pound, below the bottom end of full-year guidance at Chapada of 75 cents to 95 cents per pound, with that outperformance mainly tied to higher byproduct credits from a higher realized gold price as well as higher gold volume sold.

Teitur Poulsen executive
#13

For the year, our consolidated cash cost guidance for copper is still $1.90 to $2.10 per pound. Moving on to capex, sustaining capital expenditure came in at $111 million for the quarter, and across all three operations that spending went mainly toward open-pit waste stripping, underground mine development, upgrades to tailings storage facilities, and investment in new mining equipment. Expansionary capital expenditure totaled $83 million in the quarter, which puts year-to-date expansionary spend at $137 million. Most of that quarterly expansionary capital came from the Vicuña project, where spending reached $74 million as activity kept ramping up, including engineering, training, and early earthworks. As we previously announced at Chapada, sanctioning the additional ball mill under the Saúva growth project has raised our full-year expansionary capital guidance from $50 million to $85 million, with construction expected to begin before year-end and commissioning targeted for late 2027. Full-year sustaining capital guidance is still unchanged at $550 million, and we continue to reaffirm total 2027 capital expenditure guidance of $1 billion and $30 million for the full year, which implies a higher spend rate in the second half of the year to meet that guidance. Our key financial metrics for the second quarter appear on slides 16 and 17.

Teitur Poulsen executive
#14

For the quarter, we produced adjusted EBITDA of $658 million and adjusted operating cash flow of $495 million. Year to date, adjusted EBITDA is now roughly $1.3 billion, with adjusted operating cash flow at $945 million, and both figures are running ahead of the full-year guidance we gave at our Capital Markets Day event in June. Free cash flow from operations this quarter came in at 600 — sorry, at $360 million, reflecting a working capital build of $36 million, sustaining capital investment of $111 million, and cash taxes paid of $139 million. Adjusted earnings attributable to Lundin Mining shareholders were $257 million, or 30 cents per share for the quarter. Slide 18 lays out in more detail where cash came from and where it went in the second quarter. Our balance sheet is still strong, and we continue to carry a net cash position. As I noted earlier, the company brought in adjusted operating cash flow of $495 million in the quarter, and once you account for the working capital build and capital investments, free cash flow for the quarter totaled $265 million. During the quarter we closed the $215 million purchase of an extra 5% interest in Caserones, together with a 31% interest in Los Helados.

Teitur Poulsen executive
#15

We paid for this acquisition completely out of our balance sheet. In the quarter, two regular quarterly dividends went out — one in April, the other in June — totaling $34 million. On top of that, we finished roughly $56 million in share buybacks during the quarter under our normal course issuer bid. Once we distributed $82 million to the minority shareholder in Caserones and made certain other smaller cash outlays, the net outcome is a balance sheet still sitting in a net cash position of $79 million — even though we returned $90 million to shareholders in the quarter, on top of the significant investments in the Vicuña district via the purchase of an additional equity stake in Caserones mine, plus a meaningful stake in the Los Helados project, alongside continued capital investments into the Vicuña projects. Also, having returned $90 million in shareholder distributions. Beyond the net cash on the balance sheet, the company still has $2.5 billion of liquidity available through its corporate revolving credit facility. That facility will grow to $4.5 billion once Stage 1 of Vicuña has been sanctioned, which leaves the company fully funded for Stage 1 constructions at the Vicuña project.

Teitur Poulsen executive
#16

I'll hand things back over to Jack now, and he'll give you an update on the Vicuña project along with some closing remarks from us.

Jack Lundin executive
#17

Thank you, Teitur. Vicuña keeps moving meaningfully toward what could become a sanction decision, and work on the project is already in motion, with a solid base being put in place for what comes next. We're happy to report that as of yesterday, we closed a long-term royalty deal with San Juan province, which secures fiscal stability across the mine's entire life. This provincial royalty arrangement represents one more key milestone in moving the project forward, and it further strengthens the close working relationship we've built with the province of San Juan. Two existing provincial royalties apply to Vicuña: a 3% mining royalty and a 1.5% provincial infrastructure trust. The economics of the PEA accounted for both of those royalties. Under the provincial agreement, infrastructure obligations tied to both deposits are consolidated into one 1.5% gross revenue infrastructure trust, and the provincial mining royalty is capped at 3% of gross revenue, with both held fixed for the life of the mine. As part of this deal, the province will get an upfront $250 million infrastructure trust contribution, $125 million net to Lundin Mining, which will supply funds to the San Juan province for local infrastructure and community initiatives. The advance will help bring near-term tangible benefits to stakeholders while also supporting the project's broader development.

Jack Lundin executive
#18

Vicuña gets a five-year holiday on infrastructure trust payments starting from first production. Provincial sign-off is required for the agreement, and closing of the advance payment is anticipated in Q4 of 2026. Also, in the past week, the National Gas and Electric Regulatory Entity granted us approval to construct the high-voltage power line plus the electrical infrastructure needed for the project. When finished, it will connect into the Argentine interconnection system. As part of San Juan's future electrical infrastructure, Vicuña will develop the Rodeo-Chaparro corridor, and that will help the province grow in the decades ahead. With this approval, the path is now clear, and by funding the infrastructure, Vicuña can access most of the capacity, while the rest stays open for public use. Alongside the recent RIGI regime approval and the provincial agreements, this makes the foundation for Vicuña stronger and backs our goal of responsibly unlocking the project's full potential for the benefit of all stakeholders. In the near term, our priorities are advancing project and operational readiness, delivering the Stage 1 estimate update, unlocking additional value across Stages 2 and 3 via trade-offs and engineering, and positioning Vicuña for a successful sanction decision as early as before the end of this year.

Jack Lundin executive
#19

Thanks to backing from Lundin Mining and our partners at BHP, along with the advantages that come through RIGI, we're laying the groundwork for something that could grow into one of the most important copper-gold-silver districts anywhere in the world. To wrap up, this quarter showed how consistently our business operates, delivering high-margin output from three long-life assets while copper and gold prices were strong, and that turned into $1.2 billion in revenue, $658 million of adjusted EBITDA, and $360 million of free cash flow from operations. Halfway through this year, we're still on course to hit our consolidated production guidance range for the full year. Even though the storm hit operations at Caserones after the second quarter, we still expect to meet guidance at Caserones, since we were tracking toward the upper end of the guidance range before this shutdown. We are seeing modest cost pressures from higher diesel prices, but we expect to stay within cost guidance for the year. On the strategic side, this quarter mattered a great deal: the RIGI approval, the royalty agreement, and the power line approval at Vicuña, the sanctioning of the Chapada ball mill, the closing of the transaction to raise our ownership in Caserones, and the addition of the Los Helados interest all show disciplined execution of a clear, well-funded growth strategy.

Jack Lundin executive
#20

Every one of these actions brings us substantially nearer to our aim of ranking among the world's 10 largest copper producers. Operator, at this point I'll turn the call over for questions. Thanks.

Operator operator
#21

Thanks. Just a quick reminder—if you'd like to ask a question, hit *11 on your phone and hang tight until your name gets called. And if you want to pull your question, just press *11 once more. Our first question is coming from Orest Wowkodaw at Scotiabank. Your line's open.

Orest Wowkodaw analyst
#22

Hello, good morning. I have a question regarding the announced increase — the $100 million, or up to $100 million, raise in the NCIB. I'm curious whether you could comment or offer us some color on that. It's very encouraging to see something like that as you're about to embark on a major project build. I'm just wondering if there's any read-through there with respect to where you see your balance sheet, and also whether we might see comparable increases to the NCIB going forward, say for next year.

Jack Lundin executive
#23

Hi Orest, thanks for asking. As we said in the press release and on this call, we've raised it by a one-time amount of up to $100 million, on top of the original $150 million in buyback approvals. From our standpoint, we're basing this on the valuation we have this year, on the financial performance we've delivered, and on the favorable tailwinds we're seeing in commodity prices, so I think we're acting opportunistically, and the board was in a position to approve it. Looking ahead, it's too early to say whether we'll seek to increase it further. As you noted, we're heading into a fairly capital-intensive stretch with Vicuña and our other brownfield expansion opportunities. We'll revisit that later on, but for now, I think in terms of keeping our absolute shareholder distribution program of $220 million a year in dividends and buybacks, we'll be looking for that to be maintained over the long term, and this is more of a one-off opportunity.

Orest Wowkodaw analyst
#24

Thanks for that context. Let me turn to Vicuña for a moment. You said work is underway on the Stage 1 update. Could you take us through the milestones still outstanding before a sanctioning decision, presumably later this fall?

Jack Lundin executive
#25

Certainly. What we're primarily focused on is the bottom-up estimate for Stage 1, refining how we'll execute the plan, and collaborating with our contractors so we're positioned to execute Stage 1 successfully. As you've seen, the long-term stability agreement with the province of San Juan is now in place. That followed the RIGI approval we secured back in June, so from a permitting approval standpoint, we're essentially there. There are various sectoral permits we're still going to obtain, and those wouldn't be required for a sanction decision, but our real focus right now is completing those bottom-up estimates, having the technical independent peer review teams at BHP and Lundin Mining review them, and then pursuing a favorable sanction approval potentially before the end of this year. Yeah.

Orest Wowkodaw analyst
#26

That context is helpful. Thanks a lot.

Operator operator
#27

Thanks. We'll take our next question from Matt Greene at Goldman Sachs. Your line is open.

Matt Greene analyst
#28

Morning, Jack and everyone. Appreciate you taking the question. Juan Andres, this one might be for you. I understand you're dealing with some pretty severe outside forces here with the weather, but specifically at Candelaria with the rain, far past what you'd normally assume for operations. How do regulators handle it when you may need to release water temporarily? Maybe you could walk us through how you deal with all that surplus water. Was it necessary to send it into the pit? I know you're back at production now, but just thinking about how you were able to handle that and whether anything on the environmental side might come back at you. Yeah.

Juan Andrés Morel executive
#29

Appreciate that, Matt. It's an interesting way to look at the event. Since we're out in the middle of the desert, the pit and the waste dump take up most of the water. There isn't any contact water on our hands that would need to go out to a river or another body of water nearby. This is how we normally operate. Sernageomin, the agency overseeing mining in Chile, did come out for an inspection, and they toured every one of our facilities at Candelaria and concluded that operations and management were proceeding as expected.

Matt Greene analyst
#30

That's good to hear. Then, regarding Caserones—in your opening comments, you mentioned that you've gone over the mine plan and are making certain adjustments, and that you feel at ease with the guidance range. Could you elaborate on which adjustments you're making to the mine plan in the second half?

Juan Andrés Morel executive
#31

Right. We identified a few opportunities — essentially, by shifting where some loading equipment sits, we can guarantee the high grades we saw in Q4 are going to be mined over the course of the year, which basically keeps those high grades inside the 2026 mine plan. We also spotted a chance to push back one mill shutdown, since we'll essentially be idle for several weeks. In our view, the mill liners can be deferred until the first week of January.

Matt Greene analyst
#32

Understood — that's excellent. If I may fit in just one more question, mainly by way of clarification: Teitur, congratulations on the agreement with the San Juan government province. For clarity's sake, that payment in the December quarter — is it already included in your CapEx guidance? Apologies if I missed that.

Teitur Poulsen executive
#33

No, that isn’t in the budget, and honestly we don’t view it as a CapEx line. What it is, is an upfront payment made in exchange for a 5-year royalty holiday once production begins. We’ve paid $250 million in advance, and when you factor in avoiding royalties across the first 5 years of production, that comes out roughly NPV neutral.

Matt Greene analyst
#34

Alright, I understand. Thanks very much.

Operator operator
#35

Thanks. Our following question comes from Ioannis Masvoulas at Morgan Stanley. Your line is open.

Ioannis Masvoulas analyst
#36

Hi there, and thanks a lot for the presentation. My first question is about Vicuña. I suppose we'll need to wait for the FID decision as well as the results of the CapEx review for Stage 1 at some point near the end of the year. I'd also like to ask about Stages 2 and 3, since you intend to publish a PFS in the second half of next year. Could you share your current thinking on potential modifications to the flow sheet and mine planning, and on whether a comparable bottom-up CapEx review is likely, similar to what we've seen with Stage 1? Thank you.

Jack Lundin executive
#37

Hi Ioannis, appreciate the question. For sure, before we'd consider sanctioning the future stages at Vicuña, we would complete a bottom-up estimate covering both Stage 2 and Stage 3. As things stand, per the guidance we gave at our Capital Markets Day, we expect an updated study for Stages 2 and 3 around the second half of next year. What we're doing is examining how to simplify the flow sheet for Stage 2, which was somewhat complex in what we presented in the PEA. The team is currently developing a simplified flow sheet, and that will likely serve as the foundation for the PFS. Moving to Stage 3, much of the information is arriving via the updated drill program we have underway. We keep drilling out the deposit, examining the lateral extensions east and west within the Aurora zone. We're additionally finding some mineralization to the north and south. The deposit keeps growing in every direction. All of that will feed into our optimized mine plan. Some changes and some improvements are going to be presented in the second half of next year, but there's nothing substantive we could report on apart from that flow sheet optimization I mentioned for Stage 2.

Ioannis Masvoulas analyst
#38

Appreciate that, Jack. Moving to my second question about Caserones and moly output, which came in fairly soft versus what was expected, because recoveries have dropped to 27%. Could you give us some sense of what to anticipate in the second half of this year, and when exactly do you expect those recoveries to climb back toward historical levels?

Juan Andrés Morel executive
#39

Hi Ioannis, thanks for asking. We've run into a few metallurgical issues at the moly plant. As we transition from the secondary section of the deposit over to the primary section, a new mineralogic species is showing up alongside the moly, and that's been creating some recovery problems at the plant. We're on it. We're looking into various reagents as well as modifications to the flow sheet, but for this year, without question, we don't anticipate hitting the target we'd set for moly, and we expect to get back to that level of recoveries and performance next year. Naturally, once we move out of that zone in the pit, recoveries should get better, but while we remain in that portion of the deposit, these challenges will persist.

Ioannis Masvoulas analyst
#40

That's extremely clear, thanks a lot. Perhaps one final question for Teitur regarding that $250 million upfront payment on a 100% basis tied to the infrastructure trust. If I put everything on the spot, it would appear that this could actually be NPV positive for Lundin Mining. Would that be fair to say, and was your NPV-neutral comment based on a more conservative price deck, or would you reach a different conclusion given what you have on your production profile?

Teitur Poulsen executive
#41

I suppose everything really hinges on where you see copper prices when we begin operations, and clearly it will also hinge on how the ramp-up unfolds during that first period, since the term is fixed for 5 years. Whether the outcome turns out neutral, somewhat positive, or negative will be determined by the total production volume accumulated across those 5 years, but my sense is that every stakeholder involved — ourselves, BHP, and the province — has viewed this as a deal that is more or less neutral for all parties.

Ioannis Masvoulas analyst
#42

That’s very clear. Thank you very much, and I wish you the best of luck.

Teitur Poulsen executive
#43

Yeah. That's right.

Operator operator
#44

Thanks. We'll now take the following question from Matthew Murphy at BMO Capital Markets. Your line is open.

Matthew Murphy analyst
#45

Hi there. I’ve got one more question about the weather. How did things turn out at Vicuña during this winter storm? You mentioned that Caserones, I believe, received 3.5 m of snow. Was the situation the same on the Argentina side of the border?

Jack Lundin executive
#46

Hey Matt, thanks for the question. On the Argentinian side of the border, where the Batidero camp sits roughly 40 km or 50 km from Caserones, Batidero and the upper part of San Juan province experienced an extreme weather event. Thankfully there were no major safety incidents, and the recovery effort is less extensive since we aren't in project development mode or in operations. Some early work activities had to be paused, and winter drilling in the Vicuña district is always tightened up to ensure rigs aren't exposed in far-to-reach areas. I think they were well prepared, but it was undoubtedly a significant severe weather event that hit both sides of that mountain range.

Matthew Murphy analyst
#47

Can you recall the last time Caserones went through anything comparable to this?

Juan Andrés Morel executive
#48

Yes. Hi, Matt — Juan Andres here. Back in 2017, the prior operator went through a comparable situation. At that point, they had 320 cm of snow, and a shutdown happened for them as well. You could say the team probably has some experience handling a situation of this kind.

Matthew Murphy analyst
#49

Understood. I’m asking because people tend to focus on high altitude and the associated risk, and then a major event occurs and guidance isn’t reduced, which is encouraging. On the wording about sanctioning, where it says as early as year-end, is it still fair to interpret that as probably before year-end for Vicuña?

Jack Lundin executive
#50

Matt, this is Jack. Yes, absolutely — that's the goal we've been aiming at since the start of this year, and it hasn't changed. As you can see, we've made considerable headway in securing the different stability agreements, and at this point we're focused on the estimate as well as the execution plan for Stage 1. We're still on track for the end of this year.

Matthew Murphy analyst
#51

Alright. Then one more thing about the CapEx cadence. Relative to guidance, you're tracking fairly low really across the board, but especially on the expansionary CapEx items. Any thoughts on how we might see that ramp?

Teitur Poulsen executive
#52

No, I think that's simply how it goes with a major undertaking such as Vicuña. Ramp-up is happening all the time, and activity levels near year-end will invariably exceed those seen at the start, so at present that isn't really deviating from our forecast. Regarding sustaining CapEx, I'd say Caserones in particular is trailing our guidance somewhat, and again that ties to the timing of particular equipment purchases plus certain other projects slated for the second half, especially IT upgrades, telecom upgrades, and so on. The Caserones team is confident that they can make up ground during the second half on a number of these projects. As a result, we are keeping full-year guidance across the board.

Jack Lundin executive
#53

Adding to Teitur's comments, keep in mind as well that the extra ball mill at Chapada was approved by us around the middle of this year, so that growth capital spending would only have shown up by this point.

Teitur Poulsen executive
#54

Yes. Precisely.

Matthew Murphy analyst
#55

Alright, thanks.

Operator operator
#56

Thanks. Just a quick reminder — if you'd like to ask a question, hit *11 on your phone. Lawson Winder from Bank of America is up next. Your line is open.

Adam Smiarowski analyst
#57

Hello, Adam Smiarowski here, and I'm calling for Lawson. I just wanted to follow up regarding Chapada — how ought we to think about the growth CapEx at that asset in 2027? Is a level comparable to 2026 what we should anticipate? We'd appreciate any specifics you can offer there.

Teitur Poulsen executive
#58

On the ball mill side, that project comes to roughly $65 million all-in, and we're putting $35 million of that into this year — it's about a 50/50 split between this year and next. And then, if you add in Phase 1 of Saúva, we've guided to $110 million all-in CapEx for that project, ball mill included. Of that $110 million, the ball mill accounts for $65 million, and the remainder gets allocated to Saúva as and when our board gives final sanction.

Adam Smiarowski analyst
#59

Great, thanks. I was hoping you could discuss your M&A approach after this quarter's activity — the bigger stake in Caserones and the interest you picked up at Los Helados. Do you have an appetite for additional deals, or for bigger acquisitions?

Jack Lundin executive
#60

Appreciate the question. Lundin Mining, as a Lundin Group company, has always kept an opportunistic stance when it comes to expanding the portfolio via M&A. Our asset base today is quite solid. We intend to increase output at every one of our operations, and with Vicuña—our major development project—I'd say the current portfolio offers us a solid set of opportunities. That said, given the financial position we hold and how we're reading the market right now, there are always things to examine, yet at present we aren't actively chasing anything of scale, and our real focus is on the assets already in our portfolio.

Adam Smiarowski analyst
#61

I appreciate that.

Operator operator
#62

Thanks. We’ll take our next question from Stefan Ioannou at ATB. Your line is open now.

Stefan Ioannou analyst
#63

Thanks a lot. That’s helpful. I just wanted to ask—you said the Stage 2 update study is expected at some point later next year and would examine a more simplified flowsheet or operation. Is that mainly focused on the gold and copper components coming out of Filo, or should we interpret that as meaning you might also be looking at other possible strategic feed sources for Stage 2?

Jack Lundin executive
#64

Appreciate the question. No, honestly, what we're doing is simply optimizing around the ore body at the Filo del Sol deposit and the oxide zone at Filo. We're still very much focused on building off what we designed for Stage 2, but really just aiming to optimize and potentially simplify that flow sheet.

Stefan Ioannou analyst
#65

Excellent. I really appreciate it, everyone.

Operator operator
#66

Thanks. We’ll take our next question from Matt Greene at Goldman Sachs. Your line is open.

Matt Greene analyst
#67

Hey Jack, thanks for taking the follow-up. Really it's just a follow-on from that Phase 2 streamlining. As much as you're able, are you considering things like new technologies, novel technologies? Does that factor into your thinking?

Jack Lundin executive
#68

Yes, Matt, that's a good question too. We are certainly examining various kinds of leaching technologies and figuring out how those could be worked into the Stage 2 design. It's too early to say exactly what that will be and how we'll build on it, but absolutely, we're seeing some very promising technologies coming out today for leaching, and that's something we would love to incorporate, and we'll look to include it in the updated study for Stage 2.

Matt Greene analyst
#69

That's excellent. I appreciate it.

Operator operator
#70

Thanks. That brings today's Q&A portion to a close, and it also wraps up today's conference call. We appreciate everyone joining us, and you're free to disconnect at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Lundin Mining Corporation transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Lundin Mining Corporation earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.