National Aluminium Company Limited (NATIONALUM) Earnings Call Transcript
August 3, 2026
Earnings Call Speaker Segments
Good day, ladies and gentlemen, and welcome to the Q1 FY27 earnings call of National Aluminium Co. Ltd., NALCO, a conference call hosted by Systematix Group. <<operator_script>> Please be reminded that every participant line will remain in listen-only mode, and after the presentation wraps up there will be a chance for you to pose questions. If you require assistance at any point during this conference call, kindly alert an operator by pressing star followed by zero on your touchtone phone. I'll now turn the conference over to Ms. Shweta Dikshit of Systematix Group. Thank you, and the floor is yours.
Thanks, Sharif. Good morning to all of you. Speaking for Systematix, we're glad to have you join us for NALCO Limited's Q1 FY27 earnings conference call. We appreciate the management letting us host this call, and at this point I'll pass things along to Mr. Bharat Sahu, the Company Secretary at NALCO, who will walk everyone through the company's financial and operational performance. The floor is yours, sir.
Good morning and a warm Namaste from NALCO, a Navratna CPSE that operates under the Ministry of Mines. Before we go further, allow me to introduce the functional directors who are with us on this earnings call. Seated at the center is our CMD, Shri Brijendra Pratap Singh.
Morning, everyone.
Beside him is the Director of Finance, Shri Abhay Kumar Behuria.
Hello.
Beside him is our Director HR, Dr. Tapas Kumar Pattanayak.
Good morning, everyone.
Beside me sits our Director of Production, Shri Pankaj Kumar Sharma, sir. I'm Bharat Sahu, the Company Secretary and Compliance Officer. On the evening of 31st July, the NALCO Board took up and cleared the financial results covering the first quarter of FY27. NALCO has already posted a strong showing in Q1, and a presentation is already up on the stock exchange's website as well as on the company's own site. Performance has been strong, and I'd ask our CMD sir to just walk through a few of the key financials from this Q1, and after that we'll begin accepting the calls, the questions from your end, please.
Good morning. Right from the start, our Q1 results—the presentation is already loaded. But I'd like to highlight a few things about how Q1 went. In Q1, total income overall rose, comparing with the same quarter last year, from INR 3,930 crores to INR 5,400 crores—roughly 39% growth, Q1 to Q1. The same holds if you look at CPLY. On earnings, PBT was up about 88%, and EBITDA up about 78%. So we've seen substantial growth both in revenue collection and in the company's profitability. Looking at the performance highlights, physical performance has also been very good. Nearly all the targets we set at the start of the year have been achieved. We posted our best-ever production in bauxite, in hydrate production, and in power generation. For quarter one progress, this is the best quarter one across all these areas. On the financial side, this is the best quarter we've delivered as far as revenue generation goes—the ever-best quarter we've done. On profitability, we achieved our best Q1 profitability. And the major contributors have been, of course, internally—if you look at the improvement in production volumes, we've nearly reached the peak of volume in all the areas against the targets we took.
Looking at the refinery and our metal output across all areas, we've set a target of at least 5% to 10% above capacity utilization in whatever we undertake. Beyond the rated capacity is what we're aiming for this year. On other fronts, we're also targeting cost reduction and efficiency gains — those are within our control, meaning raising volumes while lowering costs. We're additionally pursuing some value-added products for the future, for upcoming expansions. Turning to expansion, the fifth stream refinery is due to come this year, and we're also aiming to grow our smelter capacity, for which we're going for <<inaudible>>, moving ahead with the various milestones that we'll be discussing in the presentation. So once again, thank you, Systematix Group, for organizing this conference call.
Ma'am, the floor is yours. At this point we'd like to invite all of our distinguished participants to step forward and ask their questions.
Thanks a lot. We’re moving on to the Q&A portion now. <<operator_script>> If you’d like to ask a question, you can press star and one <<inaudible>>. We ask that participants use their handsets when asking a question. We’ll pause briefly while the question queue <<inaudible>>. Our first question comes from Mr. Amit Lahoti at Aditya Birla Capital. Please go ahead.
On the refinery, <<inaudible>>, how is that commissioning effort progressing, and are we still able to hit 300,000 tonnes in the current fiscal?
On our fifth stream refinery, we've begun the decommissioning work as of June. There are quite a few packages — in fact, more than 50 of them. Mechanical completion has already been achieved on a handful of these packages, and trials on those are currently underway. Some packages still remain. Our goal is to have mechanical completion finished on all of them by the end of September, then carry out the integrated trial first — that is, the water run within the packages. Following that, we'll move into actual production, which should take roughly three to four months to stabilize and get up to the 60%–70% level. Our target for this year was to produce approximately 2 lakh tonnes of alumina from this refinery. So even if actual production begins from November–December onward, we will still be able to hit those kinds of numbers from the fifth stream refinery — around 2 lakh tonnes of alumina production.
Okay, so what's behind the delay? The thing is, we'd previously been aiming to kick off production starting in June. Given that we're now looking at roughly a six-month slip, is there any reason for that?
Our plan had been to kick off commissioning work beginning in June, then wrap it up over the following three to four months. Naturally, the mechanical completion that was meant to be finished around June-July could slip by two or three months. So this is a large project. Pinpointing the exact commissioning date and so on is really tough, especially since it's a chemical process plant. As things stand, we're now aiming for mechanical completion around the end of September, and we'll get started then. There's roughly a two-to-three-month delay, so the slippage isn't especially large.
Alright, so my next question concerns employee cost, and if we annualize the Q1 figure of INR 395 crores, that has dropped under INR 1,600 crore. Now, is this tied to the superannuation plan you spoke about in Q3 FY26, where roughly 200 to 250 senior people were going to be affected with a cost saving of INR 70 to 80 crore? So is that the same thing showing up now?
Good morning, this is Abhay Behuria, Director of Finance. You're right to ask why our employee cost is declining. If you look at our CTC for last year, 2025 to 26, the average CTC stood at roughly INR 36 lakhs, while this quarter it comes in at about INR 33 lakhs. That works out to a drop of nearly INR 3 lakhs. As you correctly pointed out, one reason is the superannuation of highly paid employees along with the induction of entry-level staff. That's the first reason. The second reason is that last year we made certain provisions toward retirement benefits — provisions for the actual valuation of leave, gratuity — and those were on the higher side. This quarter we need to provide for that. Another area is ERP. For ERP, we made a provision last year that does not need to be provided this year in that ratio. That has brought our cost down, and we expect this trend to carry on through the next three quarters as well.
So for the whole year, we can still expect that figure to be around INR 1,600 crore — is that correct?
Okay. So in the later portion of the year, during the final quarter — quarter four — pay revision could have some effect, since a pay revision is scheduled for 1st January 2027. So in that last quarter, there might be some increase, an additional 15%. Apart from that, for the two quarters, the second and the third, the cost will stay in this line.
Got it. Thanks a lot.
Thanks, sir. The next question comes from Mr. Aditya Welekar at Axis Securities. You have the floor.
My question concerns the volume of alumina we sell. For FY27, you've given guidance of 25 lakh tonnes for alumina production, but what about sales volume? That figure moves around quite a bit. So could you provide guidance on the volumes for the full year for FY27?
During this financial year — well, last year, we sold roughly 14 lakh tonnes of alumina. This year our target is 16 lakhs. Any additional 2 lakhs of alumina that this team manages to produce will go into our sales value. So an extra 2 lakhs will be sold this year.
Okay, got it. And the second part is, we've now seen aluminium prices come down. So looking ahead to Q2, do you expect any raw material cost pressure that will stick around? Because in the earlier quarter, as we saw, you guided that there's some cost inflation on CP Coke, cold cartridge, and other raw materials. So will that affect our margins going forward, given that aluminum prices have cooled off?
Looking at aluminum prices, in the first quarter the average LME was roughly 3,500 to 3,600 or 3,700. It's now down to about 3,200. Raw metal prices have of course gone up. Caustic soda last year averaged around 42,000. Our Q1 spend was about 45,000 per ton, and in Q2 that will be roughly 49,000. Naturally, caustic soda is set to rise by about 3,000 to 4,000 versus Q1. CP Coke has also climbed — INR 44,000 last year, now INR 66,000 to INR 70,000. Those are the two main areas. Then there's HFO, at INR 46,000 last year, which has risen to INR 75,000. All this has pushed up our total production cost by roughly INR 15,000 to INR 16,000 per ton of metal. So those three — caustic soda, CP Coke and HFO. Those are the three areas, plus aluminum fluoride to some degree. So yes, raw material prices are up about 10% to 15%, which is adding around INR 15,000 to INR 16,000 to metal prices.
So anything that can offset that — I mean, we’ve just recently seen alumina prices climb to $350 per ton — and then, is there any room to offset that through lower pool power costs, or do you think the margins might take a slight hit?
For alumina, our initial expectation for this year was roughly $310 to $320, though lately we've been seeing prices near $370. The reason is that in Russia as well, RUSAL and China—two of the refineries—cut output because of red mud problems. Bauxite prices in New Guinea have risen somewhat. That's why alumina, which we thought would land near $320, is now coming in around $370. So that should offset part of the raw metal cost increase, since raw metal added an expense burden of about INR 230 crores extra in Q1 because of higher raw material prices. So if alumina stays at the 370 level, that is the price we expect will offset the input raw material cost.
Got it, sir. That’s all from our side.
Thanks. Our following question comes from Pinakin at HSBC. Go right ahead.
Thanks a lot, sir, for giving me this chance. Sir, I have a few questions. First, you mentioned that $370 per ton is the alumina realization you're currently receiving. And what alumina realization did we get in Q1, sir?
Could you say the question again — only that final sentence?
Alumina realization comes in Q1.
In Q1, our average realization came in at roughly 323 for alumina.
For Q1, what about alumina cost — will Q2 be higher or flat?
Could you speak up a bit? We can't really hear you — the audio keeps breaking and it isn't very clear.
Just a moment, sir. Regarding Lumina’s cost of production, sir, will that be higher in quarter two compared with quarter one?
For the first quarter, when you look at our cost of production, are you referring to alumina or to metal?
Alumina.
Alumina costs typically fall in the INR 21,000 to INR 22,000 range. In the last quarter, it stayed inside that band. As for the second quarter, since all the input cost increases were seen in the first quarter, a similar cost pattern will carry into the next quarter. We don’t expect our costs to rise. Instead, they’ll stay within that band, roughly INR 21,000 to INR 22,000 per ton of alumina. And we’ll actually gain on price, because CMD sir already explained that in the next quarter we’ll get an incremental price of about $50 from alumina.
Understood sir. For my second question: sir, you mentioned an increase in metal cost of production of INR 15,000 to INR 16,000 per ton. Had that rise in production cost already shown up in quarter one, or will it arrive in quarter two relative to quarter one?
No, we already anticipated that, since we knew raw metal prices would rise. Those three raw materials — caustic soda, HFO, and CP Coke — so that was pretty much expected, and costs of a similar kind will carry on in Q2 as well.
Right, so a similar sort of cost will carry on. Understood, sir. Then for my third question — you pointed out that LME prices have shifted. So what's the situation with domestic aluminum premiums? Earlier you noted that they adjust with a delay. Have they gone up lately, or do you expect those premiums to rise on domestic sales?
The premium has gone up. Previously, it was roughly $60. Now it's risen to about — we ran the tender at approximately $110. So the premium is up by roughly $50.
Understood. And do you anticipate that going up even more, sir?
No, that premium bump came from the war situation over in the Middle East. And now that the war situation is easing, we expect it might stay the same, or it could even come down.
Understood. So my final question: given the conflict in the Middle East, did any of your export shipments get affected — whether alumina or aluminum — that would now return to normal?
Yeah, a few shipments. For instance, one shipment had been ordered earlier — that was before the war, of course — and it was ordered at $390 as well, and that one has materialized. So we're getting a better relationship there. As for the other shipments, whatever is being ordered on the other shipments is going out. There are no other pending shipments.
Understood. Thank you so much, sir.
I appreciate that.
I appreciate it.
Our following question comes from Vikash Singh with ICICI Securities. Vikash, the floor is yours.
Morning, sir, and thanks for giving me the chance to ask. Normally the second quarter falls in monsoon season and has historically been softer, particularly where coal input is concerned. So I just wanted to get a sense of whether we had enough coal inventory this time, captive coal included, and whether any one-off cost escalation or disruption has come up so far?
Regarding our power plant, <<inaudible>> that serves our smelters, we do have enough coal there, since roughly 60%-70% of that coal comes from our captive source. So there aren't issues on that front. Naturally, at our refineries the coal stock sits on the lower side. We need to keep coal inventory at a level of perhaps 10 to 15 days. Right now it's about two to three days. That's owing to the restriction imposed by the government, the priority for rakes. We depend heavily on rakes supplied by the railways, and priority goes to the power plant. So some issues exist there. We are pursuing it very aggressively with the Indian Railways and our ministry, and there has been some improvement. And since summer has now ended, the restrictions will ease. So we expect these stocks will improve as well in the days ahead.
On the rake availability side for the shipment, so far there’s no issue, right?
No, for that shipment we handle dispatching the calcined alumina using our own rakes. There aren't any problems there. We have our own BTAP rakes. No issues on that front.
Understood, sir. Sir, for my second question, is the company {indecipherable} starting work on an aluminum plant with a capacity of 500,000 tons?
Vikash Singh, sir — your voice is breaking up.
Is it better?
Yes, that's an improvement. Please.
Right, this is the second question about the case concerning the CapEx for our 500,000-ton aluminum plant. Could you share a few highlights on where those plants stand in terms of board approval, when we'll get started on this, and what the CapEx looks like?
Regarding this 0.5 million ton smelter plant development, as of today, we have already finalized a technology supplier — that's EGA. We will sign the technology license with them, perhaps this month, by the 10th or 15th. So the DPR is being prepared. The consultant is working on the DPR. Our target is that in the next three to four months we will have the DPR ready. And obtain board approval, maybe in October or November, for the DPR for setting up this 0.5 million ton smelter and also a 1,000 megawatt power plant. After that, it may take us eight to nine months to order the packages. By next year, August or September, we should have ordered all the packages and begin the groundwork, maybe next year in October or November. And from that point, setting up this plant will take three to three and half years. So the timelines we have given to the ministry, and our internal timeline, are that by December 2030 we must complete this plant along with the power plant. As for the power plant, we have done one JV agreement with Neyveli Lignite for setting up this power plant, so as to reduce our CapEx and to have raw material security, that is the coal.
NLC itself owns the coal mines located in the Talcher district. That means coal will be supplied from right there, which is a positive for this power plant. The DPR for this power plant is likewise in progress. So both will be ordered together and commissioned around the end of 2030 or the first half of ’31. On CapEx, total capital expenditure should come to roughly INR 25,000 crores, and it begins in financial year ’27-’28. The peak arrives in ’28-’29, ’29-’30, and ’30-’31. Those two to three years are when this CapEx spending will be distributed. In this year, no major CapEx is planned for that project. Naturally, for technology licenses we must pay something, perhaps 300 to 400 crores, but the bulk of the CapEx comes starting the next financial year.
Understood, sir. One point I’d like clarified, sir. As for those shipments—or the exports we make to Russia—are they priced in dollars, or in the Russian currency? And for any dollar-denominated sales we make in the export market, we convert the dollars into rupees at the time of shipment, correct?
No, whenever our export shipments go out, the price is set in dollar terms at the moment the order is placed. When we float a tender, we run the spot tenders, and the dollar rate used is the one in effect on that particular day.
Right, but the booking itself, or the sale getting recorded, occurs when the shipment takes place, correct?
On the booking side, we handle spot tenders, and when a spot tender is opened, the dollar prices in effect on that date are the ones that get locked in.
Got it — I understand. Thanks very much, sir, and best wishes going forward.
Thanks.
Thanks. Our following question comes from Mr. Manav Gogia at YES Securities Limited. The floor is yours.
Yeah, hi, good morning. Thanks a lot for giving me the chance to ask. So my first question is about the captive coal mines. We had a target of 4.8 million ton production for FY27. Could you just go into more detail on where things stand in the EC process for expanding the mine?
We've already completed the mining plan approval. For the mining plan, approval has to come from the board. This board has granted the mining plan approval, and now we're applying for the EC. In the next two to three months, we should be getting the EC. So we've already begun production, and 4.8 million tons we're confident about — we're proceeding at a rate of 4.8 million tons, or whatever monthly breakup we've worked out. Within the next two to three months, we'll receive the EC from MOEFCC. So there aren't any major issues there.
Oh, alright, that's nice to know. And would you be able to tell me what our total coal production from our captive mines came to in Q1?
For Q1, the figure was 11.04 lakhs. The reason is that at the very start — during the first four or five days of Q1, five days — there was no production coming from the mines. Some technical issues had come up. At this point we've ramped production up, and in the quarters that follow we'll be making up for whichever shortfalls existed.
Okay. Could you say that figure one more time, sir?
11.04 lakh tonnes.
11.04. Okay, sure. So my second question now concerns the Pottangi mines — we've already appointed an MDO. At what point do we see production happening, or has it begun already?
On Pottangi mines, first, the MDO has already been ordered. To reach the mines and begin production, a road needs to be built — an eight-kilometer road. Tree cutting has to happen for that road to be made. Working with the district authorities, we're encountering some resistance there. Some activists and some opposition are showing up. Together with the state government, the police force, and all of that, we have tried two or three times with the district authorities. Along with the MDO, we are trying to mobilize the locals there. And I think this very month itself — that is, in August — we will go there again with the authorities to make the road. Road construction will take perhaps 15 to 20 days, and after that we are targeting maybe September, October onwards. From October onwards, we'll start production.
Okay, sure, that helps a lot, sir. So just one final question from me: as of March 2026, our total headcount stood at roughly 4,880. What would that number be right now, or at the end of Q1?
4848.
Right now, that figure stands at 4848.
So is it fair to say there might be an additional 150 to 170 employees reduced by year end?
Yes, each year you'll see a reduction of roughly 170 to 200, and that will continue over the next three to four years.
Absolutely, sir. That is really useful. Wishing you all the best.
Thank you.
Much appreciated, sir. We now move to the next question, which comes from Amit Murarka of Axis Capital. The line is yours — please proceed.
Hello there, and thanks for giving me the chance to speak. You brought up the alumina plant reaching mechanical completion in September, along with an extra 200 KT of production, roughly speaking — is that correct? So then, for next year, would it be fair for us to expect that this capacity will be running at its full rate?
Yes, starting next year we need to make that move. From that point we'll be pushing toward 1 million tons of production, and we're already at 2.2, 2.3 from what we have now. Perhaps we'll reach 3.1, 3.2 beginning next year.
Sure. And about this premium in the local aluminum market — how does it actually function? Do you sign certain contracts once that premium gets locked in, or does it simply track the spot market itself?
We do actually have an export tender. There’s a premium from that export tender — <<inaudible>> — that gets added onto domestic prices <<inaudible>>. It’s applied to the domestic pricing, which is LME-based; domestic pricing is set off the LME.
No. The premium isn't what I'm referring to. So in the local market, when you make a sale, the premium you record or bill customers for there is likewise tied to some benchmark — say the MJP benchmark, or something along those lines — or do you fix it?
Regarding MJP, we don't <<inaudible>>. Our process involves a single export tender. Whatever premium we secure through that export tender stays locked in for the following three to four months, until we conduct the next export tender. For instance, if we ran an export tender last month and obtained a premium of $110, that premium gets applied to domestic pricing over the next three to four months, until we hold the next export tender and establish the premium anew.
Alright.
Is your point about the metal price or about alumina?
On aluminium, the sales you generate within the local market.
That's the policy we follow. As CMD sir explained, we have a structured approach to setting the aluminium price, and other factors come into play as well. Premium is one such factor. Whatever premium comes out of tendering — export tendering — gets added to our aluminium price for domestic supply. Okay.
Okay, understood. And is it updated for each tender you conduct?
Yes, every single tender. How often a tender comes up varies — it's usually every 3 to 4 months. So that's what we typically do.
Right? And what's the CapEx outlook at this point for FY27 to 28, if you could give us those numbers?
We're aiming for INR 1,500 crore. We may go beyond that — by around '26-'27, we'd be landing somewhere in that vicinity, wouldn't you say?
Yes, both this year and next year.
For this year, we're aiming at roughly 1,500, since most of the fifth stream payments have already been made, so there isn't major capital expenditure. Even so, we'll still be spending somewhere in the range of 1,500 to 1,700 or 1,800 crores. Starting next year, that figure will go up, because we'll have the smelter expansion underway. So for next year, how much have we planned?
For the coming year, we've got plans in place for roughly 2,500,
Perhaps 2,500 in ’27-’28. Following that, it could reach maybe 4,000 to 5,000 crore. After the next stage, perhaps 6,000 to 7,000 crore. The phasing has been completed by us, and the bulk of the spending will stem from expanding the smelters and the power plant.
Okay, understood. And on captive coal as well — I believe you said earlier it would be around 4.6-odd million tonnes of production this year. So it looks like you're on track for that?
Yes. On captive coal, we did 4 million tonnes last year. This year our target is 4.8 million tonnes, since a 20% increase is permitted. For that, all the permissions and so on are in process. And on a monthly basis, we're producing at a rate of 4.8 million tonnes, and we'll hit that by the end of the year.
Sure. That’s all I have. Thanks.
Thanks. Our next question comes from Sumangal Nevathia at Kotak Securities. Please go ahead.
Good morning, and thanks. To follow up on the earlier question, on CapEx, could you tell us how much we spent in Q1? Then, regarding the expansion, I'd just like to know whether the power CapEx will occur in the JV, meaning we'd contribute only the equity portion, which might be roughly 20% to 30%. So if you could explain how the power expansion CapEx will be handled?
Yes, regarding our CapEx plan, as CMD sir already explained, for the smelter we're going with EPC mode, and for the power plant we have a JV with NSE, and we'll be doing both. Okay, so the contribution toward total expenditure for our CapEx up to 2030 to 31 will be around INR 24,000 crore — INR 17,000 to 18,000 crore on the smelter, and INR 6,000 crore as contribution toward this power plant, a 1,080 megawatt power plant through <<inaudible>>. The cost — total cost — will be around INR 12,000 crores, with INR 6,000 crores from our side and INR 6,000 crores from NLC, because it's 50 to 50 there. In the power plant, we have a debt-equity ratio of 30 to 70. So if you follow that, our equity contribution will be lower. It's around 3,500. Our share will be 1,766, and the balance will be financed through the bank, with our NALCO and NLC as guarantor — since this is the new JV, they will be the guarantor, and the money will be taken from the bank. So if you see otherwise, if you look at our fund base, if you look at our balance sheet as on date, we have a fund base of around 10,500 crores <<inaudible>>.
Each year, then, we're putting in 3,500 after the dividend is paid and after all our regular CapEx spending. So in that area, look, we don't have to bring in money from outside, because our balance is enough. Since we've signed the JV agreement for the power plant, that plant is going to be financed by that company — which is a company. Equity participation will be 30%, and 70% will come from the bank. So the remaining money we hold, we'll use it for our smelter expansion project and other projects we're also looking at. That will be entirely through equity, because we have sufficient balance. So the power plant will be 70 to 30 — 30 equity-based, debt-equity — 30 to 70. So that is the current proposal, and we're going to proceed on this basis <<inaudible>>
Got it. So on the power plant — INR 12,000 crores for 1,000 megawatt — I mean, as a rule of thumb it's usually INR 7 to 8 crore per megawatt. So why does the cost come out so much higher?
Apologies. I believe that's 10 crore per megawatt, so the figure comes to between INR 10,000 and INR 11,000 crores. The reason it isn't larger is that what we'll be building is a power plant of 1,080 megawatts.
Got it. And sir, regarding what you mentioned, the cash balance as of 1Q — net cash — is that 10,500?
Right, so as of 30th June 2026 — as of today — that figure stands at more than 10,500.
Got it. And for the first quarter, what was your CapEx spend?
Are you referring to this year, or do you mean the subsidiary?
Just in Q1.
My guess would be 350.
Got it. Sir, I'd like to clarify something regarding the earlier question about metal sales. You mentioned that the premium gets set according to the export tender. So for the domestic price, just to be clear, is it LME plus the customs duty plus whatever premium we receive on exports? Are those the three components involved?
Some handling fees and stockyard fees get added onto that as well. So with that included, the freight costs…
The port-to-E-point and port-to-customer-point transportation charges, since there's a calculation module for that. The factor is right there. As you correctly pointed out, it's the export-import duty plus premium plus handling charges and plus freight equalization. What freight the customer would have paid to get to their location, what they'll be paying from our location to theirs.
Got it, sir. Could you break down those 3 components for 1Q? We're familiar with LME, but what's the split on the realization side?
That's available in our domain. You can get it from our website. I think the pricing policy is there. So that policy, we need to see whether it's a classified one or not. We can share or not.
All right, that works. And then one final point regarding the aluminium metal. You mentioned a cost increase of INR 15,000 to INR 16,000…
Between INR 15,000 and INR 16,000.
Yeah, 15,000 to 16,000. So is that figure for the fourth quarter, or is it an average compared with last year?
The average for last year came in at 1,56,000 or 1,57,000. In Q1 of this year, the average is roughly 1,70,000.
So given how things are trending today, what should we expect for 2Q, sir?
In Q2, things will edge up a bit, since CP Coke and caustic soda prices are set to be somewhat higher in Q2. Not by much, though — perhaps it moves to 172, or 171 to 172. How much efficiency we manage to achieve will determine that.
Got it. One final question, sir. When we bring in just under 1 million tonnes of captive coal this year, what savings does that create? How much cheaper is captive coal compared with what it replaces — linkage coal or auction coal?
For captive coal that we source from mines we own, the landed cost comes to roughly 1,600. When you compare that with the coal we take from The Coal India, we use two types. One comes under the agreement, the FSA linkage, the fuel supply agreement. The other is bought through auction. FSA coal lands at nearly the same figure, 1,600 to 1,700. As for the auction coal, that ranges between 3,500 and 3,600. So a gap exists on the auction coal. Looking at the FSA coal, we don't receive it on a regular basis, since rack supply is the issue. That makes auction coal far more expensive than our captive coal. So a big advantage exists between auction coal and the captive coal we produce. Okay, that works out to almost 1,500.
Okay, and sir, for last year, what's the split on coal? How much came from linkage and how much from e-auction?
If you look at linkage and E-auction last year,
Roughly 55 to 45.
What about linkage and e-auction?
Yes, linkage plus e-auction,
Out of the total 7.2 million, 4 million comes from us. The remaining 3.2 we source from Coal India. Within that 3.2, linkage and E-auction <<inaudible>>
Linkage came in at roughly 34 million. From our CPP, we saw INR 30 lakhs, and refinery linkage contributed INR 10 lakhs. As for the auction pool, that stood at about INR 1 million.
We’ll just verify that data and get back to you with the answer.
Understood, sir. That was my final question. I’ll wait for the response and rejoin the queue afterward. Thank you, sir.
Thanks. Our next question comes from Digant Haria at GreenEdge Wealth. Please go ahead.
Hello, and thanks for the chance to speak. I had just a couple of questions. First, regarding the outlook for aluminium metal prices — since the Middle East war wiped out one or two major production plants, what happens when those facilities come back online? What's your view on where aluminium metal prices go? That's the first one. Second, India is also seeing a lot of investment in recycled aluminium. Does NALCO have any plans in that area? And could that affect our sales two or three years down the road? Yeah, those are my two questions.
Right now, metal prices stand at $3,200. LME is at 32. So the forecasts coming from CRU, Platts and the rest indicate that for the balance of the year, it will stay somewhere near 31 to 32. We also anticipate the LME will land somewhere between 3,000 and 3,200 over the remainder of the year, because the smelters that are meant to come onstream in the Middle East probably won't arrive until around the end of Q4 of this financial year, since those smelters need additional time — six, seven months, eight months more. So supply constraints and projections are out there, and there will be a deficit of roughly 0.88 million tons of metal in the international market. If you look at the production and consumption pattern, the deficit comes to around 0.88 million tons. So LME should sit somewhere around 32,00.
Understood, sir.
And the concern is that we’re discussing recycling. Where NALCO is concerned, recycling is basically carried out by secondary producers who turn out small volumes, and because we’re a major producer, we don’t get into recycling, since doing so also disrupts the quality of the metal we make. In the aluminium sector, metal quality matters a great deal — the purity of the aluminium. Whenever recycling takes place, there’s no quality assurance. So we have no plans for recycling.
Alright, sir. Thanks a lot.
Thank you.
Thanks. Our next question comes from Mr. Akhilesh Kumar at MK. Please go ahead.
Hello, hello sir, and thank you for taking my question. First off, I'd like to ask whether we had any contracts for alumina tied to the LME during this quarter. If the answer is yes, then how are we positioned for the quarters that lie ahead of us?
Yes, we weren't able to hear you. Could you say your question again?
Yes, sir. My question is whether we had any contracts linked to LME for alumina in 1Q of ’27. And if so, how are we positioned for the quarters ahead?
In Q1, we had a term contract, and I believe there were one or two shipments at the start. However, at present, for the last two months, we haven't had any of what we refer to as a term contract tied to the LME. That's absent because we had a few tenders where the percentage came in quite low—around 10% of the LME. So we cancelled that tender, since the spot prices we're getting are better.
So would it be fair to say that in FY27 as well, for the rest of the year, we won't have any term contracts?
Actually, we do pursue tenders. We'll be participating in some tendering. Only if improved pricing comes through will we proceed. Because right now, if we're receiving $370 and percentage-wise we get just 10%, 11%, that works out to roughly 3,200 LME, which would come to about $320. So we don't place that order. So it all hinges on us running a tender—if we secure better prices, around 12%, 13%, 14%, only then will we book the order.
Could you also walk us through how we end up at that $50 premium compared with the 1Q average you cited at roughly $320 for alumina? And for this quarter, you're now expecting $370. So what's behind that difference?
Look, regarding the premium I mentioned, that applies to metal — aluminum. As for alumina, or whatever product we're selling there, it goes through a spot tender at a fixed price. Say we run a spot tender and on it we receive $370 per ton, or $350, whatever the figure, that price is fixed for the tender and for the shipment. But the premium I referred to earlier relates to the metal, to aluminium. On whatever aluminium we sell in the domestic market, we add a certain premium. That depends on the exports we handle — we also export some aluminium. We ship some metal abroad as well, 500,000 tonnes each month. So whatever premium comes to us in that export tender gets passed on and loaded onto the domestic customers.
Okay, so would it be reasonable to expect that in the second quarter, NALCO's aluminium realizations might come in around $360 to $370?
Right, so this month — July — we've already had spot tenders. In August, there's another spot tender coming in at roughly $370, which is what we're getting. The most recent spot tender, we did two or three back, on that one too we got $380. So for Q2, an average of $370 is what I think we'll be getting. Q2.
Alright.
As we noted, the first quarter came in at roughly $323, and for the following quarter we expect an additional $50. Whether that comes through first spot tendering or a term contract, it doesn't matter. Our expectation is based on the fact that pricing at current levels will deliver $50 more than what we realized previously. Okay.
Understood. My second question concerns the conversion of bauxite into alumina. In this quarter, we utilized roughly 3.2 tonnes of bauxite per 1 ton of alumina, which is efficient when compared with the preceding few quarters, where the figure stood at approximately 3.5 tons of bauxite. So is there any specific cause behind this improvement, and can we expect it to continue going forward as well?
It really hinges on the bauxite quality coming out of the mines. And essentially, we've kicked off a few new phases at our mines. So whenever bauxite quality is good, consumption of bauxite per ton comes down. Going forward, since we're also going to begin South Block 2, we'll be getting better-quality bauxite there. Now our North Block, the very old block, is nearly exhausted. So we're starting some new phases where bauxite quality will be better. As a result, average specific consumption of bauxite will improve.
Yes, sir — many thanks. That’s all from my side.
I appreciate that.
There was only a single question regarding linkage coal and that sort of thing. Our Director of Production is present, and he will respond to it.
So essentially, for our CPP, the coal we're using comes from linkage coal and Utkal D&E coal. In the last year, we used 47.16 lakh coal from linkage through NCL, along with 40 lakh from Utkal D&E. For our alumina refinery, we're obtaining coal via E auction. And through linkage, we purchased 11.24 lakh last year through linkage, plus roughly 7 lakh in E-auction coal. So about 40% of the total coal used at the refinery is bought through E-auction, and the rest comes via linkage. Thank you.
Thanks, sir. Our next question comes from Pathanjali Srinivasan at Sundaram Mutual. The line is yours — please go ahead.
Hello, and thanks for giving me the chance to ask. I was hoping to get some clarity regarding one of the…
Could you speak up just a bit, sir? Thanks.
Okay, can you hear me at this point? Does that sound any clearer?
It's an improvement. Good morning.
Good morning, sir. You mentioned metal premiums sitting at roughly $110 right now. Could you tell us what the figure stood at the last time you revised them, and what the impact has been from that point to the present?
The previous occasion was roughly 5 to 6 months ago. Back then, the premium we received came in at about $60, close to $60.
All right, but from what you're describing, the premium has done nothing but go up. Yet I believe during your presentation you said something along the lines of premiums coming down, or that they're expected to fall. The war risk premium. Could you explain how those two things differ?
The premium is entirely a function of supply and demand. When demand outpaces supply, we command a better premium. In the last tender we ran, supply constraints existed because of the war situation. As those war conditions are easing, smelters in the Middle East are also working to raise output. Once things loosen up over the coming months, the premium will come down.
Understood, sir. And here's one more question. That new alumina refinery you're bringing online — how will its production cost differ from what your existing plants achieve? After all, the ones running now are considerably older, correct?
What's the production cost at the expansion unit you're referring to?
That's right.
For the expansion unit's fifth stream, we've worked out that production costs won't be significantly higher, since our average — if you look at what we currently spend to produce alumina, last year it came in at roughly 20,000, while in this year's first quarter we recorded about 22,766, driven by rises in caustic soda and fuel oil, meaning HFO. Those are the two main factors behind the increase. With our new refineries — the fifth stream refinery — the benefit we'll gain comes from pressurization, which will keep caustic soda usage on the lower side. In our existing refinery, caustic soda consumption stands at approximately 103 kg to 105 kg for each ton of alumina produced. That figure ought to fall to somewhere around 85 to 90 kg per ton of alumina consumption, and as far as alumina cost goes, that should bring our cost down by perhaps INR 1,000 or INR 1,500 per ton. As for other areas, such as manpower cost and so on, this is a large unit — a single line turning out about one million tons. At present, with four lines at the existing refinery, those four lines give us 2.1 million tonnes.
The fixed cost — meaning the manpower cost — will likewise be somewhat lower. Sure, interest isn't there, but depreciation gets added in; some depreciation will be charged to the cost. Still, based on what we've worked out, the total cost for the existing refinery and the new one will come out nearly identical. For the new refinery too, the cost arriving will be roughly 22,000 to 23,000.
Understood, sir. Thanks.
Thanks.
Thanks. Our following question comes from <<inaudible>> Dutta. You have the floor.
Sir, I just need one clarification. Our alumina capacity right now stands at 2.1 million tonnes, correct?
Yes.
And sir, once it’s expanded, what is that going to amount to?
Look, right now we're sitting at 2.1 in terms of capacity, yet we turned out roughly 2.3 last year. That means we ran 0.2 beyond what our capacity allows. Once the expansion is done, an extra one million tons comes on stream. So post-expansion, the rated capacity we're aiming at will be 3.1 million tons, though we'll actually be shooting for something like 3.2 or 3.3 million tonnes.
And sir, when does that additional one million ton capacity come up?
A single million tons — this year, just 0.2 million tons gets added. Starting next year, that means ’27-’28.
By '27-'28, we'll be at a full 3.1 million tonnes.
Yes.
So at this point, we're moving what—near 1 million, correct?
Last year our sales came to roughly 1.4 million tonnes, or 14 lakh tonnes. For this year, the plan is 1.6. So once this reaches full capacity — because our smelter needs only 0.9 to 0.95 million tonnes — the remainder will have to be sold on the open market.
So the following year, we’ll receive an additional 1 million tons — does that mean full?
Yeah, that’s something that has to be sold.
All right, thank you, sir. That's everything from me. And sir, just one more thing.
Yes.
Ma'am, kindly press star and one. In the meantime, we'll go to Mr. Rajesh Mazumdar of 361 Capital. Yes, Falguni <<inaudible>> ma'am has returned. Please proceed.
How much did that new refinery, with its 1 million ton capacity, cost?
Roughly 5,600 crores.
All right, sir, thank you. That covers everything on my end. Just one more item, sir — this is entirely from internal accrual, correct?
Yeah, that came from internal accrual. There won't be any interest loaded onto it. Depreciation is the only thing that'll be there.
Alright, thanks a lot.
I appreciate that.
Thanks. Our following question comes from Rajesh Majumdar. You have the floor.
Yes, sir. Good morning, and thank you for the chance to ask. I have a few questions about the bauxite-alumina segment. First, regarding the bauxite mines already operating at Panchpatmali, how many years of life remain for those mines, and what reserves does Panchpatmali hold? As for Pottangi, what output are you achieving at present, and what capacity could you reach in the coming year?
So essentially, our Panchpatmali bauxite mine holds reserves of roughly 110 million tons. And beyond that, we've acquired a new mine that also contains somewhere around 110 to 120 million tonnes. So at the current rate — roughly 8 million tonnes per year, if we go by that — we could say the remaining life of our Pachapattamalai bauxite mine comes to approximately 15 to 20 years.
Right, and I get that the bauxite from the Pottangi mines is of better quality, and because of that, production costs for the new alumina expansion will come down. Is that right?
Could you say that again?
So what I'm getting at is this: the bauxite quality that will come out of the Pottangi mine is going to be incrementally favorable for alumina production costs as we move forward. Is that right?
To put it plainly, the grade of bauxite at the Pottangi mine is something we'll only learn once thorough exploration is done and the mine has been developed. So right now, we can't say with 100% certainty that this benefit will materialize.
So then, on what basis are you assuming that the caustic soda needed for the new expansion will be lower — is that because of the plant specification rather than the bauxite?
So essentially, this year we’ll be feeding bauxite from our existing mine into the new fifth stream. And only when production at the Pottangi bauxite mine begins will we then be using bauxite from Pottangi. Both of these bauxites will be mixed and used proportionately in our fifth stream as well as in the old stream.
Then, with the Pottangi mines running at full capacity, production costs should drop even more — is that right?
My sense is that it'll be pretty much the same.
Right, because what happens is that once those new mines are running, the quality comes out better. And as mines age and we go deeper, quality gets worse. So this one will be a new mine, so quality is going to improve. And at our new refinery, which is being built with pressurization using the new technology, the caustic soda consumption benefit will come about thanks to that new technology in the refinery.
Okay, thanks. I’ve got one question about alumina realization. We follow the LME, and that figure differs from what you’re reporting at $370 — the LME average for the last quarter was $323, $325, yet you show $370. Could you give us the rough country-by-country split of those exports, and explain why your realization and the LME don’t match?
You mean alumina?
Yes.
Alumina isn’t tied directly to the LME. It’s entirely a matter of alumina’s own demand and supply. Earlier, when you compared it with LME, we were getting roughly 14%-15%. Now that has fallen to 10%-11%. Even at present, most of our alumina goes to the Middle East. Somewhere around 60%-70% of the alumina is shipped to the Middle East through one route or another. A small portion of the alumina is also headed perhaps to Europe and China—some shipments are moving there. So what’s really happening is that bauxite prices have also risen somewhat; in New Guinea, because of rain and so on. At RUSAL in Russia, and also in China, two major refineries have cut alumina output owing to red mud problems there. So there are some temporary supply constraints, and that has pushed alumina spot prices up to the $370-$380 level. Which we are seeing, as this war situation eases and as the Middle East’s alumina requirement continues. It will stay at that same level,
Okay, so over the long term, alumina prices are going to trend toward 14% to 15% of NSE. Is that a fair assumption once aluminum production comes back?
It's not 14%-15%, it's perhaps 11%-12%, entirely because LME is on the higher side — LME is around 3,200 to 3,300. So for alumina, in percentage terms, it shouldn't go above 11% to 12%.
Okay, so my final question was about net debt. Did you say that net debt now stands at 10,000 crores?
Net debt.
Net cash.
That's a cash reserve, and we’re a company with zero debt.
No — what's the net cash figure shown on the balance sheet at the end of the first quarter? That's cash minus net debt.
That comes to roughly 10,500.
So that means by the end of the year, even after paying your dividends, you'd still have roughly 15,000 crore in cash. Is that the right figure? If it's a balanced cash flow and the CapEx <<inaudible>> balanced cash flow for FY27.
Our Director of Finance will walk you through, each year, exactly how much cash we’re going to add.
Right now we're sitting at a balance of 10,500. Each year, given our profitability and the PAT, we're adding 3,500 plus, because we expect to earn a PAT of 6,000 plus. This year too we're projecting 6,000 plus, and from next year onward as well. So after we pay our dividend and cover our normal CapEx expense of around 1,500 crores, and once the non-cash item gets added to that PAT, we'll be adding 3,500 plus annually. So when the time comes to fund our CapEx, we'll have enough cash reserve on hand, which means we can easily finance what we need through our internal accruals. Okay. And,
And approximately what would that smelter CapEx come to — around 4,000 to 5,000 crores each year?
As we’ve already said, for the power plant we opted for a JV, so the funding need there will be smaller, since that will be financed through a debt-equity ratio, with debt at 70 to 30. In our case, then, the remaining portion — the smelter part — will be funded solely from our internal accruals. So given our cash reserves and the earnings potential we expect going forward, there’s no need for us to go to the market to borrow for the smelter expansion.
And so, if I could just slip in one final question. At present, with the 950 pots we're running, aluminum capacity stands at 4.6 lakh tonnes. So could there be some sort of brownfield expansion there, or will it stay capped at 4 lakh 60 only? As with alumina, where you're going from 2.1 to 2.3?.
Even though our capacity stands at 4.6 lakh tonnes, we produced roughly 4.72 last year, and for this year we expect output of about 4.76 to 4.77 lakh tonnes.
We're actually a bit above that, if anything.
And as of right now, we're running at roughly 958 to 959 pots.
So realistically, you could get to a number like 4.75, entirely in aluminum?
Affirmative — 4.75.
I really appreciate it.
Thank you, sir. Since participants have no more questions, I'll now pass the conference to Mr. Bharat Kumar Shah for his closing remarks. Please go ahead, sir.
Thank you, Mr. Kalender<<inaudible>>. I want to express gratitude on behalf of NALCO and every respected participant who gave their valuable time to join this earnings call for NALCO. That demonstrates the keen interest you hold in NALCO's business activities, and going forward we hope for the same kind of cooperation from all of you. Thank you, Chorus team, for making this post-earning call possible for NALCO's Q1 results. My thanks also go to Systematix Group for consistently hosting this post-earning call for NALCO each quarter, and we seek the same cooperation in the future as well. Thanks. Thank you all.
I appreciate that.
Thanks. That brings NALCO Limited's conference to a close. We appreciate your participation. <<operator_script>> Your lines can be disconnected at this point. Thank you.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete National Aluminium Company Limited transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to National Aluminium Company Limited earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.