Home / Transcripts / Standard Lithium Ltd. (SLI) · March 30, 2026

Standard Lithium Ltd. (SLI) Earnings Call Transcript & Summary

March 30, 2026

TSX Venture Exchange CA Materials Metals and Mining earnings 44 min

What were the key takeaways from Standard Lithium Ltd.'s March 30, 2026 earnings call?

In the fourth quarter of 2025, Standard Lithium Ltd. reported a net loss of $35.7 million, a significant increase from a $24.7 million loss in the same quarter of 2024. The company highlighted the completion of a definitive feasibility study (DFS) for its SWA project, which is projected to have an initial production capacity of 22,500 tonnes per year of battery-quality lithium carbonate. Management signaled a strong outlook for 2026, with plans to finalize key agreements and reach a final investment decision (FID) for the SWA project, targeting construction to begin this year and commercial production by 2029.

What topics did Standard Lithium Ltd. cover?

What were Standard Lithium Ltd.'s March 30, 2026 results?

Standard Lithium's strong cash position and completed DFS for the SWA project position it well for future growth. However, the increased net loss and reliance on securing offtake agreements present risks. Investors should monitor the progress of these agreements and regulatory approvals as key catalysts for stock performance.

Earnings Call Speaker Segments

Operator operator
#1

Hi, everyone. Thanks for being here, and welcome to Standard Lithium's Fourth Quarter 2025 Earnings Call. <<operator_script>> At this point I'll turn things over to Daniel Rosen, Vice President of Investor Relations and Strategy at Standard Lithium. Please go ahead.

Daniel Rosen executive
#2

Thanks, and hello everyone, and welcome. With me on the call today are David Park, our CEO and Director; Andy Robinson, President, COO and Director; Salah Gamoudi, Chief Financial Officer; and Mike Barman, Chief Development Officer. Before we get started, I'd like to begin by reminding you that certain statements we make on today's call, including anything related to company performance, expectations and timing of projects, may be forward-looking statements. Please take note of the cautionary language regarding forward-looking statements that's in our press release, and that also applies to this call. I'll now hand the call over to David.

David Park executive
#3

Thanks, Dan, and I appreciate everyone joining us today. The fourth quarter was busy and productive for us, as we moved forward on and finished several key milestones and deliverables for the company. We filed a positive definitive feasibility study for the SWA project, along with a maiden inferred resource report for our first project in East Texas, the Franklin project. The DFS for SWA shows how attractive and cost competitive our first commercial project is, being developed alongside our SMAC over lithium JV partner, Equinor, which is expected to have production capacity of 22,500 tonnes per year of battery-quality lithium carbonate in its initial phase. The maiden resource estimate for the JV's Franklin project in East Texas highlights the size and quality of its brine position, with some of the highest reported lithium in brine grades in all of North America. It provides a strong foundation for future scalable production and is a key step towards the ultimate goal of reaching production of over 100,000 tonnes of lithium chemicals per year in Texas through multiple projects. We obtained the final regulatory approval required for SWA from the Arkansas Oil and Gas Commission for integration, receiving unanimous support for our application for the Reynolds Brine unit, where the initial phase of the project is planned to be developed.

David Park executive
#4

And we kept making our balance sheet stronger, while also moving forward with the export credit agency led project financing for the SWA project. In October, Standard Lithium closed and upsized a $130 million underwritten public offering. Institutional investors showed strong support, and the order book was oversubscribed — which underscores confidence in our strategy and in the quality of our assets. On top of that, Smackover lithium received indications of interest for more than $1 billion in project financing for the SWA project, led by 3 major export credit agencies, including the Export-Import Bank of the United States and Export Finance Norway, and backed by a strong group of commercial banks. The interest came in on competitive indicative terms and exceeds the targeted debt alone. As we begin 2026, we've been working diligently to advance the remaining work streams required to reach a final investment decision for the SWA project. We've made meaningful progress on all fronts, including signing our first binding commercial offtake agreement with Trafigura, a global commodities market leader with an established presence across battery metals, including lithium. Spec over lithium will supply Trafigura with 8,000 metric tons per year of battery quality lithium carbonate for over a 10-year period beginning at the start of commercial production.

David Park executive
#5

We will go over where each of the remaining work streams stands and how that backs our plan for taking FID and starting construction in 2026. To give an update on the main project-related developments and the deliverables coming up, I'll hand things over to Andy.

J. Robinson executive
#6

Thanks, David. Before we reach FID and execute contracts, there are 4 primary deliverables to complete: key construction vendors securing National Environmental Policy Act, or NEPA, approval from the federal regulators; finalizing customer offtake agreements; and closing the project financing. For the downstream portion of the project, which contains a central processing facility and includes a direct lithium extraction and battery-quality lithium carbonate conversion process, we're pursuing an engineering, procurement, construction and commissioning, or EPCC, model. For the upstream portion — the well field and pipeline — we're pursuing an engineering, procurement and construction management, or EPCM, model. Agreements with our preferred partners in these roles are close to finalization, and we expect both to be completed in the second quarter. Upon signing, each contract will contain a limited notice to proceed so that key work items can immediately progress and the construction schedule can be optimized. A positive final investment decision will be followed immediately by the full notice to proceed. Turning to the regulatory front: our $225 million grant from the Department of Energy triggers a requirement for the project to undergo an environmental assessment under NEPA. The DOE is leading that environmental assessment process, and it is progressing well.

J. Robinson executive
#7

In 2025, the project wrapped up every required field work item and all baseline environmental studies needed as inputs for the EA. DOE has finished all required consultation with the other federal agencies and with travel nations, and the draft EA report for public comment is now complete. We anticipate the NEPA process will conclude in the second quarter, in line with the Federal Permitting dashboard. All in all, government support for our project has been strong throughout this process, and it received a fast 41 transparency project designation. Now turning to our dual track customer offtake and project financing processes, Smackover lithium, working with our experienced financial advisers, keeps making progress, as shown by our first binding commercial offtake agreement and the indications of interest we've received in support of the project debt, which Salah will discuss in more detail. Out of our planned 22,500 tonnes of annual nameplate lithium carbonate capacity, we are aiming for roughly 80% of that production to sit under long-term offtake contracts. Our first offtake agreement, with Trafigura for 8,000 tonnes, accounts for more than 40% of the targeted offtake for the initial phase of the SWA project. The joint venture is in advanced commercial negotiations with multiple additional parties, with the goal of completing this process as soon as practical. We stay focused on securing the best possible terms under these agreements so as to support our project financing efforts and to help mitigate risk from negative price fluctuations while maintaining attractive price upside for our stakeholders.

J. Robinson executive
#8

Among the pre-FID items still outstanding, we think finishing the customer offtakes carries the greatest chance of timing slippage, simply because of how these negotiations tend to work. Before the final size and structure of the project finance package can be set, every material offtake term has to be agreed. That said, we keep pushing forward on project financing due diligence, documentation, credit and other approvals concurrently, so that we can get to financial close and draw down soon after. The joint venture is still confident it can land a satisfactory result in these customer offtake talks, and therefore the land for FID to be taken and for construction to start in 2026. If construction gets underway on that schedule, we would expect first commercial production in 2029. We also want to touch on our priorities for East Texas in 2026 for the Franklin project and for the region more broadly: we intend to keep sharpening the definition of our resource positions through additional drilling and process test work. Our aim is to release a preliminary feasibility study for the Franklin project within the next 12 months, showing the project economics of that world-class resource and hopefully bringing further recognition to this important and underappreciated part of our asset portfolio.

J. Robinson executive
#9

We are going to keep working on reports covering made and inferred resources for the 2 additional prospective projects we have in that area, and at the same time we will keep growing our leasehold position across East Texas. At this point I will hand things over to Salah, who will walk through our financial results.

Salah Gamoudi executive
#10

Thank you, Andy. Just so everyone's clear, every figure I cite today is denominated in U.S. dollars. Turning to the fourth quarter, which closed on December 31, 2025, we recorded a net loss of $35.7 million, versus a loss of $24.7 million in the quarter that ended December 31, 2024. What mainly explains that year-over-year widening of our net loss are items that are onetime in nature and don't reflect underlying business trends — specifically, a $6.8 million rise in impairment expense, a noncash charge tied to the LANXESS property project, along with a noncash $3.4 million increase in foreign exchange loss. The impairment on the LANXESS property project stems from several things: we terminated our prior memorandum of understanding with LANXESS, we stopped discussions with LANXESS about taking the project further, we executed a new site services agreement that sets out our go-forward relationship with LANXESS concerning our demonstration facility but does not contemplate further commercial development. And lastly, we refocused our efforts and capital allocation toward our Southwest Arkansas and East Texas projects. Consequently, in the fourth quarter we recognized a full $26.5 million impairment expense on our exploration and evaluation assets associated with the LANXESS property project.

Salah Gamoudi executive
#11

Separately from that, Standard Lithium will keep running and operating the industrial-scale DLE and carbonation demonstration plant located at LANXESS's existing bromine site, just as it has done successfully for about the past six years. The foreign exchange loss stemmed from holding considerably higher average cash balances in the fourth quarter, which came about because of our $130 million follow-on offering in October, along with the resulting noncash accounting effect of exchange rate movements on those balances. For the quarter, compared with the quarter ended December 31, 2024, G&A of $2.9 million rose by $0.2 million, mainly because of higher employee-related expenses tied to growing our team as we keep maturing and shift from early-stage project development toward construction and, eventually, production. Demonstration plant costs of $1.4 million were up by $0.6 million, reflecting greater personnel costs and indirect allocations related to process refinement and testing, as well as operator training and support for potential future commercial production. Share-based compensation expense of $1.5 million grew by $0.3 million, owing to more long-term incentive compensation for our management employees as we expanded our team as noted above and to better align compensation with shareholder value creation.

Salah Gamoudi executive
#12

Further down the income statement, below operating expenses, we posted a larger loss from joint ventures — $3.2 million for the quarter, compared with $0.3 million in the prior period. That rise comes from greater operational activity and the associated costs at the Smackover lithium JV level in 2025, along with our progress toward issuing our 2 technical reports at SWA and East Texas. In addition, we booked a $0.4 million gain on the fair value of our contingent FID payments, which Standard Lithium would receive from our JV partner, Equinor, if we hit a positive FID at our SWA and/or East Texas projects by certain dates. As we keep reaching milestones and get closer, the value of those contingent FID payment assets has gone up, which is what the gain reflects. We also recognized $0.9 million of additional interest income for the quarter, driven by higher average cash balances during part of the period. For the full year 2025, the company reported a net loss of $48.4 million. Full year results are compared to our last audited period, a shorter 6-month fiscal stub period ended December 31, 2024, in our reported financials. The reason is that we changed the company's fiscal year-end from a June 30 fiscal year-end to a December 31 calendar year-end in the fourth quarter of 2024, to better align our reporting cycle with how we manage the business and with our peers.

Salah Gamoudi executive
#13

So because of that, our focus today has stayed on the fourth quarter comparables rather than the full year 2025. Now turning to the balance sheet. We closed the quarter in a strong position on cash and working capital, at $152.3 million and $147.6 million, respectively, versus cash and working capital of $31.2 million and $27.5 million, respectively, in the prior year. That higher cash balance mainly reflects the follow-on offering we finished in October, which brought in net proceeds of $122.2 million, along with our continued use of the ATM facility, partly offset by the capital contributions we made to the SWA and East Texas projects and by general operating expenses. The follow-on offering will help support the equity contribution we expect to be required into the SWA project at FID, as well as continued progress on development work in East Texas. As part of the original agreement, Equinor's sole project funding requirements into the JVs were exhausted during the second quarter of 2025, with standard lithium and Equinor then each making their own respective capital contributions under a 55%, 45% ownership split. Standard Lithium contributed $9.6 million of JV capital during the fourth quarter, which brings the 2025 total to $29.1 million as reflected on our cash flow statement.

Salah Gamoudi executive
#14

For the entire year, $16.1 million was allocated to SWA and $12.9 million to East Texas. A key element of the final investment decision for SWA is locking in an attractive and comprehensive project finance package. The roughly $1.5 billion of base project CapEx according to our DFS, along with potential cost overrun facilities, reserve accounts, or other incremental capital needs, is anticipated to be funded through a mix of senior secured project debt, our $225 million grant from the DOE, and respective funding contributions from Standard Lithium and Equinor. The joint venture aims for approximately $1.1 billion in total senior secured limited recourse project debt, backed by leading export credit agencies and commercial banks. Last year, we carried out a market sounding of global commercial banks active in the project financing debt market. Their response is reflected in indicative terms that aligned with the JV's expectations and validated certain assumptions about the cost, term, structure, and conditions customary for project debt facilities of this nature. The commercial bank expressions of interest, together with those of the exceeded our total targeted project debt. The remaining 55% pro rata equity contribution required from Standard Lithium will be funded by proceeds from our recent equity raise.

Salah Gamoudi executive
#15

Should there be any facilities for cost overruns or reserve accounts beyond what the base project CapEx requires, those are still open to discussion with the lenders, and the quantums have yet to be determined. At this point I'll hand things back to David, who has some closing remarks.

David Park executive
#16

Thank you, Salah. Standard Lithium remains in a very strong position, thanks to a portfolio of scalable, high-quality assets, and as a domestic champion for securing critical minerals production in the United States. Our SWA project is well engineered and well defined, and we have an exciting and important year ahead of us as we approach a final investment decision. We delivered critical project milestones in the fourth quarter and to begin this year, and we intend to provide multiple updates in the coming weeks and months as we conclude our pre-FID work streams and push to approve FID at SWA before moving quickly to construction in 2026. Thanks again for joining us today. Operator, I'll turn it back to you.

Operator operator
#17

<<operator_script>> The initial question will be taken from Anthony Taglieri of Canaccord Genuity.

Anthony Taglieri analyst
#18

David and team, I’m curious about the offtake discussions and how those may have shifted over the past 6 to 12 months, given the rising price environment we’ve seen. Has the number of parties and the level of interest changed? Is there more caution because of price volatility? Have pricing mechanisms changed at all? Some color there would be great.

David Park executive
#19

Yes, great. Thanks for the question. I'll take this one. I would say that over the past 6 months, the market has clearly moved in a positive direction. Lithium pricing has reached levels that are more consistent with reinvestment support. As a result, I think it's fair to say that more counterparties have reemerged as interested parties in discussions who are willing to enter into agreements with us that would be supportive of the financing that we're looking to put in place. So I would say that the last 6 months have been positive and have helped us move forward. That said, as you'll note, these agreements have taken longer to put in place than we would have thought. They're quite complex agreements that need to survive through multiple cycles. They're multiyear agreements, multi-hundred million dollar agreements. So making sure that these transactions work for not just us, but our lenders, our shareholders and our partners is extremely important. So long story short, we're moving in the right direction. The market environment is supportive of what we're trying to do. And if anything, it's brought more potential counterparties to the table.

Anthony Taglieri analyst
#20

Thanks, that's useful. Perhaps just to follow up: should we anticipate seeing one more offtake agreement, say, before the financing wraps up? Or should we expect something like the next batch of offtake agreements to come about around the same time?

David Park executive
#21

No. From the very beginning, our intention has been to secure contracts for more than 80% of volumes ahead of FID, spread across several counterparties — so I'd say you can count on seeing a few announcements regarding 1 or 2 possible counterparties during the next quarter, and those ought to help support the financings we're aiming to arrange.

Operator operator
#22

The next person to ask a question is Max Yerrill with BMO Capital Markets.

Max Yerrill analyst
#23

So my understanding is that the project debt seems to hinge on getting the offtake agreements finalized. Are there particular clauses or conditions that the lenders on that project debt want to see included in those offtake contracts? And then, as a follow-up, is that 80% target something set internally as a strategic decision, or is it a requirement coming from the project debt lenders?

David Park executive
#24

Thanks, Max. What I'd say is that 80% is a target we set internally. But overall, the percentage we end up contracting will depend on the terms we have in place across a portfolio of different agreements. So in short, we're seeking take-or-pay contracts with creditworthy counterparties that, as a portfolio, offer enough price support for our lenders to feel comfortable with the amount of debt we're looking at putting in place. So it really is a portfolio approach. It isn't the case that any 1 specific deal has to meet certain specific terms.

Max Yerrill analyst
#25

Understood — that clarifies things. So should we still expect construction to take around two years, and am I right in assuming that, provided everything this year goes according to plan, most of the CapEx for Phase 1 will still fall in 2027 and 2028?

David Park executive
#26

Absolutely. I'll hand things off to Andy for that.

J. Robinson executive
#27

Yes. So, thank you, Max. Yes, regarding the construction period, I believe our guidance points toward commercial production in '29. We're in the final stages of talks with the contracting counterparties. We're fine-tuning the construction schedule. And crucially, Max, the precommissioning, commissioning, and start-up schedules as well, so that we're positioning ourselves to succeed through the commissioning and startup process, enabling us to reach commercial operation in good alignment with the offtake contracts David just mentioned. So this is a fully integrated process, meaning that not just the construction but the entire commissioning and start-up period is fully aligned with those offtake contracts we are currently negotiating and signing. So yes, we're aiming for commercial production in 2029, assuming FID and construction happen this year.

Operator operator
#28

Theo Genzebu has the next question, and that's great.

Theophilos Genzebu analyst
#29

Thanks, everyone. I appreciate the detail on the route to FID — but among everything you disclosed in the press release, is there any single gating item for FID that stands out above the rest in your view?

David Park executive
#30

I'll start, and then Andy, perhaps you can finish up. Several items need to be completed before FID. Andy already mentioned finalizing the EPC agreements, completing the NEPA process, finalizing the offtake agreement, and then closing the project debt financing. I'd say that in all likelihood, the offtake agreements are the toughest to pin down in terms of exactly when they'll be in place and finalized. But everything — we're pursuing all these tracks simultaneously, though they all must align with one another. Andy, I don't know if there's anything else you'd like to add there.

J. Robinson executive
#31

Not really, Theo. There are a number of items that sit firmly within our own hands, and we're pushing each of them ahead as fast as we can. As we said, we set guidance to wrap up the NEPA process — that federal permitting track — during this Q2 period. In the same way, the EPCM and EPCC contracts are clearly things we hold a tight grip on, and we're working to bring them to conclusion. We've discussed the offtake process, and that one is somewhat less within our immediate control when it comes to fully and tightly directing the timelines. But as I said earlier, it's going extremely well. And all of it finishes with the debt component at the final stage. So we have a full team. I think, as we mentioned previously, Theo, we have a fully integrated team spanning Standard Lithium and the Equinor partners, driving us toward an FID conclusion this year. And yes, we're excited to get this one into construction and move it forward as quickly as we can.

David Park executive
#32

Absolutely. I’ll just add that a robust domestic lithium market exists for 2029 and later. We are — and will continue to be — in advanced commercial talks with several parties. And we’re dedicated to giving you updates over time regarding the progress we’re making on these efforts.

Theophilos Genzebu analyst
#33

Thanks. And I suppose, just following up on the off-taker discussion, are there particular counterparty sectors where discussions are proving most constructive, or perhaps further along at the moment?

David Park executive
#34

From the very beginning, we've been evaluating several counterparties spanning trading houses, battery makers, and automotive OEMs, and conversations continue with all 3 of those groups. Putting everything into a single basket wasn't our aim. Our goal was a varied customer portfolio, and that remains the direction we're moving in.

Theophilos Genzebu analyst
#35

Understood. Alright, and perhaps just one final question from me. Regarding the ATM program, how are you viewing its usage going forward? My assumption is that it remains genuinely opportunistic — or might it be deployed more actively should the stock continue to hold up well prior to FID?

David Park executive
#36

Salah, shall I hand that question over to you?

Salah Gamoudi executive
#37

Thanks, David. Yeah, so on that point, we still have roughly $25.5 million remaining under our current ATM program. Going forward, we intend to deploy that carefully and at a measured pace. It's among the tools available to us for financing our East Texas expansion, and it can also cover part of what we need at Southwest Arkansas, particularly ahead of FID. On top of that, it helps us handle corporate overhead costs as we move forward. So I'd say the ATM will keep being used as a prudent tool, though in all likelihood it won't be used in a manner where it becomes our main source of funding for future projects.

Operator operator
#38

Our following question is from Joseph Reagor, who is with ROTH Capital Partners.

Joseph Reagor analyst
#39

And I have a follow-up, plus another separate question. So, regarding FID — you've already discussed it quite a bit — but given that your balance sheet is in decent shape at the moment, is there any chance to begin some early earthwork activities, perhaps to even move up the timeline toward price reduction? Or are there permitting matters and other issues underway that stop you from truly getting started, or has the capital simply accomplished enough, or anything along those lines?

David Park executive
#40

That’s a great question. Andy...

J. Robinson executive
#41

Yes. I'll start things off and then pass it back. Thank you, Joe. Yeah, so, we have a construction schedule that is currently being integrated with both of our main contracting partners. As I mentioned, there's the EPCM and the PCC. We were examining the schedule to optimize it as much as possible. I think the greatest time savings—what we're concentrating on at the moment, Joe—is that we aren't really limited by earthmoving, earthworks, or enabling-works-style activities. What's genuinely on the critical path for us is, frankly, additional engineering, early vendor outreach, and procurement-type activities. Those are the items, and that's really why we're going to issue a limited notice to proceed to the main contracting team—so that we can preserve that construction schedule by carrying out that early-stage work, the more EP portions of the various packages, to keep the schedule advancing. That's genuinely where our attention is, rather than earthworks, since the volume of earthworks we have is fairly minimal and doesn't sit on the construction schedule's critical path.

Joseph Reagor analyst
#42

All right, that's useful. And I don't believe anyone has brought it up. Yes. So regarding the LANXESS write-off — should we view that as the company concentrating on the JV, the specular lithium JV, and simply that the grade is better across all those areas? So there's no sensible reason to go back to the LANXESS project? Or is there something else we should read into that?

David Park executive
#43

No, Joe, I think you got it exactly right. It all comes down to setting priorities, staying focused, and executing — and putting our effort where the best grade is. So Southwest Arkansas is where our future lies, and from there we expand into East Texas. Andy, I’m not sure whether you’d like to say something about the quarter..

J. Robinson executive
#44

Yes. No, I mean, you've got it exactly right. And Joe, like our future, we want to build bigger projects. That's this first one, the 22,500 at Southwest Arkansas Phase 1—it's the right-sized project for us in the JV to build the first one. But really, the true scale comes in East Texas, where we can build some really pretty sizable projects given the extent of the resource, the grade the grade of the resource and then our continued understanding as we move through engineering and construction of this first one making the subsequent projects, larger, cheaper to build, et cetera. So we're looking to grow out into the much larger project portfolio in East Texas where we can see some really substantial scale.

Operator operator
#45

Noel Parks with Tuohy Brothers Investment Research has the next question.

Noel Parks analyst
#46

I only have a few. Earlier, when expenses came up, it was noted that refining processes and testing formed part of the increase in expenses. I was just curious whether that kind of work is more or less specific to Southwest Arkansas, or whether, once it's finished and you need to shift focus more toward East Texas, it will be roughly repeatable, so that work is essentially a one-time effort more or less.

Salah Gamoudi executive
#47

Andy, would you like to field that question?

J. Robinson executive
#48

Yeah, absolutely. I mean, look, these are lessons straight from the project that we can take and apply right across the entire project portfolio. We're in a pretty unique spot in that the demo plant is up and running right now and, as Solar mentioned, it's been operating for 6 years at this point — and it's certainly among the biggest fully continuous DLE demo plants anywhere in North America today, and we keep getting just outstanding data from it. We keep — so it's not just process learnings we're getting, and optimizations around how to make the process simpler to operate, potentially less expensive to construct. But on top of that, that plant right now serves a really critical role as we're effectively building out the core operator team who, during that commissioning process I touched on a bit earlier, will ultimately take over from the contractor's commissioning team and run the plant. And so the demo plant keeps being this genuinely unique kind of training tool for getting the core operator team fully comfortable with turning Smackover brine into battery-quality lithium carbonate material — that's what we do every day at the demo plant, and it's a genuinely unique opportunity.

J. Robinson executive
#49

From what we observe, the broader industry has had a tough time, I’d say, somewhat with commissioning and start-up work on numerous projects spanning a wide range of asset and processing types, since the activities we carry out at the demo plant serve as such a strong kind of small-scale parallel to what happens at the first commercial plant — it truly is this sort of one-of-a-kind — this one-of-a-kind training instrument. So yes, we remain fairly at ease kind of bearing costs in that area, because it will deliver returns sort of at a large scale across the coming series of projects.

Noel Parks analyst
#50

Thanks. And just at a high level, over the coming few years, do you have any sense of roughly where that export category might top out and then level off?

J. Robinson executive
#51

On actual cost, I'll let Salah address that. Noel, my sense is we plan to keep that demo plant operating for roughly the foreseeable future — up until the point when team members have been fully transferred. It has served its purpose. There could also be some other use for it somewhere else at some point down the road, though nothing has been decided on that so far; the real intent is to keep it running for certainly the foreseeable future as this critical training tool that lets us move into a smooth commissioning and ramp-up, as we can expect to achieve.

Noel Parks analyst
#52

Understood. And it would be great to hear any thoughts on, sort of, the cost?

Salah Gamoudi executive
#53

Sure, Noel, I’m glad to share my view on that. So going forward, I’d anticipate that what we spend on demo plan costs will line up quite closely with the costs that showed up in Q4 of last year.

Noel Parks analyst
#54

Great. Okay. That's definitely helpful. And I suppose the only other thing for a pump was maybe just again, thinking about East Texas, could you just sort of maybe describe where you stand in the process of the drilling that's required to gather data in East Texas, I'm assuming the focus is still very much on delineation. And so I just kind of wondered maybe what inning you think you're in for establishing, I guess, the baseline for, say, a PFS going forward?

David Park executive
#55

Andy, would you mind handling that one?

J. Robinson executive
#56

Yes, absolutely. So Noel, we have a number of project areas over in East Texas. The sole one that's, say, public is the Franklin project, which is roughly focused around Franklin County. That makes it the most clearly defined asset among our East Texas portfolio as of today, and it's the one on which we published a maiden inferred resource. So with that project, Franklin, where things stand at the moment is that we've been carrying out well reentry work — for roughly the past quarter, or really 2 quarters by now — all of it aimed at gathering different reservoir data, resampling those wells, retesting them, and beginning to build a far more complete picture of the subsurface. Concurrently, we've been running some further process testing on the East Texas brands. That effort is certainly going to carry on through the coming quarter or 2. Some extra drilling is scheduled inside the Franklin project area — presently aimed at later in this year. And we intend to combine that further process testing with more subsurface exploration and delineation, together with a substantial amount of extra leasing across the Franklin project area, with the goal of delivering what would essentially be the first economic study, meaning a PFS.

J. Robinson executive
#57

My view is that our guidance points to something within the next 12 months, Noel — we wanted it to happen as soon as it's feasible. In our opinion this report will matter a great deal for the investors in standard to genuinely grasp the true value that exists in our East Texas portfolio; a number is just one of the projects. Yet there is a great deal of enormous unrealized value sitting in the portfolio we already hold, and we truly want to bring that out and show it to the market.

Noel Parks analyst
#58

Thanks. And on that leasing point you brought up — is anyone new showing up in East Texas?

J. Robinson executive
#59

My sense is that it's pretty much the same group of other companies operating around Texas. No, nothing has really shifted in a meaningful way over roughly the past 3 to 6 months. So overall, I'd describe leasing activity as proceeding at a quick clip. There's competition in the region. Still, I'd say it's holding steady — fairly stable, from what we're seeing right now.

Operator operator
#60

Eric Boyes with Evercore has our next question, which will also be the last one.

Eric Boyes analyst
#61

I have just one question as well. Could you talk about where you might be encountering inflationary pressures on Southwest Arkansas CapEx items, and what approach you're taking to mitigate them?

David Park executive
#62

That one is also directed at you, Andy.

J. Robinson executive
#63

Eric, yes — look, the FEED study is clearly still quite recent. And we feel fairly comfortable with where vendor pricing stands relative to what we built into that FEED study as we wrap up the EPCC and EPCM contracts; obviously, we've accounted for some price escalation and inflationary impacts in the final contract amounts. So you'll see some of that once those are finally announced. But since we conducted a very broad and extensive vendor outreach against a very conservative set of engineering assumptions when we carried out the FEED work, we aren't seeing much actual real price growth in the key vendor packages to date.

Operator operator
#64

That brings us to the end of the question-and-answer portion. Today's call is now finished. We appreciate everyone joining us, and you're free to hang up at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Standard Lithium Ltd. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Standard Lithium Ltd. earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.