Standard Lithium Ltd. (SLI) Earnings Call Transcript
November 16, 2026
Earnings Call Speaker Segments
Thanks, and good day to everyone. With me today are David Park, our CEO and a director; Andy Robinson, President, COO, and director; Salah Gamoudi, Chief Financial Officer; and Mike Barman, Chief Development Officer. Before we get started, I want to remind you that certain statements we make on today's call, including anything tied to company performance, expectations, and project timing, could be forward-looking statements. Please take note of the cautionary language regarding forward-looking statements that appears in our press release, and that language applies to this call as well. I'll now hand the call over to David.
Thanks, Dan. And thank you all for being with us today. As we entered this year, we identified four main deliverables that had to be finished before we could take FID at our SWA project: signing the key construction contracts, finishing a federal environmental review under the National Environmental Policy Act, or NEPA, wrapping up our customer offtake agreements, and locking in project financing. Once we had the first two of those done in the second quarter, we were able to close out the customer offtake process during the third quarter, and at the same time we made meaningful headway on advancing project financing, which is now the main workstream left before we reach FID. These are significant accomplishments, and they represent the culmination of years of effort from our team and our partners. We signed long-term commercial agreements with LG Energy Solution, one of the world's leading battery producers, and with Trafigura, one of the largest global commodity traders. This workstream has been among the most important and most time-intensive, and we now hold the volume commitments required to support finalizing the project debt financing; we keep moving the project financing process forward and have worked closely with the export credit agencies, and each of them remains focused on supporting the strategic SWA project. Their comprehensive due diligence review is now substantially complete, and no material concerns have been raised, and we are now targeting more than $1.2 billion in total senior secured project debt, which exceeds our initial expectations of up to $1.1 billion. The ECA-led financing process has taken longer than we first anticipated. Even so, we have not lost sight of the tremendous opportunity to put a highly attractive financing package in place that will fund a substantial portion of the project's capital requirements. The effort has been worth it, and it matters to take the time needed to structure it optimally so that success is ensured for all parties. Given the latest financing timeline, we expect to take FID by the end of the first quarter of 2027, with construction starting shortly after that on a two- to three-year timeline. Lastly, during the third quarter, we released a preliminary economic assessment for the Franklin Project in East Texas, the first of several projects we have planned, which highlights the strength of one of the biggest and highest quality lithium brine resources in North America. It could produce up to 70,000 tons of battery quality lithium carbonate annually, and it is a key part of our plans to build a world-class portfolio of lithium projects. I will now hand the call over to Andy.
Thank you, David. Getting the commercial offtakes finished last quarter marked a major milestone for the SWA project. This past August we executed our second binding take-or-pay contract, this time with LG Energy Solution, which ranks among the top lithium-ion battery manufacturers globally and is the biggest one headquartered outside China. Under that deal, the project will deliver to LGES 8,000 tons annually of battery-grade lithium carbonate across a 10-year span once commercial production begins. Confidentiality applies to pricing and the rest of the key commercial terms, though they were designed in a way that supports the project financing. Then in September we revised our binding contract with Trafigura, among the biggest commodity traders worldwide, whose involvement gives us useful entry into numerous industry supply chains dependent on lithium chemicals as well as a wide customer base. As with LGES, that original contract covered 8,000 tons per year of battery-grade lithium carbonate on a take-or-pay basis across a 10-year span. Through the amendment, the joint venture we hold with Equinor can now choose, entirely at its own discretion, to deliver as much as an extra 4,000 tons of battery-grade lithium carbonate in every year of that agreement. Adding the initial commitment, the ceiling for volumes possible to Trafigura on a take-or-pay basis has risen to 12,000 tons annually. Another benefit of the amendment is useful production flexibility, since the extra volume can be delivered solely when we elect to do so, and we keep the right to direct that volume toward other strategic customers later should a better commercial or strategic opportunity arise. For the SWA project, the financing-driven goal was to lock in binding customer offtake agreements covering approximately 80%, or 18,000 tons, of the 22,500 tons of annual nameplate lithium carbonate capacity in the initial phase. Across our two customers, commitments now total 16,000 tons of battery-grade lithium carbonate yearly, and with the extra 4,000 tons that may be sold at our discretion either to Trafigura or to another party, contracted volumes of 20,000 tons altogether surpass our financing thresholds. These contracts give us long-term commitments from two counterparties that are global leaders, and the partnerships we are growing demonstrate both the strong quality of the SWA project and how important our role is in building a scalable, competitive domestic lithium supply chain. Above all, now that the customer offtake process is finished, we have turned to finalizing and closing the SWA project financing as fast as we can ahead of taking FID and starting construction. In the interim, we have kept making meaningful headway with our EPCM, Wood, which oversees the upstream wellfield, and with our EPCC, S&B, backed by Hatch, which handles the central processing facility. For the past six months they have worked under a limited notice to proceed, concentrating on key activities meant to de-risk the SWA project and optimize the construction schedule. That covers detailed engineering, pinpointing long-lead-time items together with vendors, completing the relevant construction permitting, building out the team, and engaging with the community. They should move to the complete, final EPCC and EPCM contracts after the JV reaches a positive FID. In the weeks ahead, we'll also finish some key pre-FID work, such as tree clearing at important sites, to help us meet the planned construction timetable. Standard Lithium hit a significant technical milestone too, together with one of its collaborators, Nano One. At our South West Arkansas pilot plant, lithium carbonate was used by Nano One to make lithium iron phosphate cathode material and battery cells in North America. That outcome further confirms the SWA project's process flowsheet and how well our material suits downstream battery uses. It likewise reflects our dedication to technological innovation and to helping build a domestic, fully integrated energy storage supply chain. On a separate note, in September we announced a preliminary economic assessment for the Franklin Project in East Texas, then filed the underlying report the month after. The PEA envisions yearly output capacity reaching as much as 70,000 tons of battery quality lithium carbonate, and it stands out for attractive economics: an unlevered, pre-tax net present value of $5.9 billion on a 100% ownership basis, assuming an 8% discount rate, an internal rate of return of 26%, and a three-year payback period, plus average annual lithium cash operating costs of about $4,200 per ton and capital intensity of just under $50,000 per ton. It further features an upgraded, upsized mineral resource compared with the maiden resource estimate published last year, with some of North America's highest reported lithium-in-brine concentrations. The new indicated resource comes to 1.77 million tons lithium carbonate equivalent, or LCE, at an average lithium concentration of 562 milligrams per liter, while the upgraded inferred resource totals 2.13 million tons LCE at an average concentration of 572 milligrams per liter. The PEA also looks at a scenario built around a co-located bromine facility of 50,000 tons per year alongside the lithium operation. Given the considerable scale and quality of the resources, and potash's designation as a U.S. critical mineral in 2025, Standard Lithium and Equinor intend to assess further potential commercial opportunities for both bromine and potash. The Franklin PEA shows the strength of one of North America's largest and highest quality lithium brine resources. These newest results give us a solid foundation for advancing the Franklin Project as the first of our large-scale projects planned within a far broader East Texas position, and they underscore the scale and national importance of our resource footprint. That supports our longer-term aim of producing over 100,000 tons of lithium chemicals each year in Texas across multiple phases and projects, and we'll keep filling in our leasehold and pushing resource definition forward across that position. The joint venture has just begun additional drilling activity in the project area and will press ahead with technical de-risking of the project, aiming to move the Franklin Project to a preliminary feasibility study. I’ll hand things over now to Salah, who will go into more detail on our financial results and the financing for the SWA project.
Thank you, Andy. Regarding Q3, which ended September 30th, 2026, our net loss came in at $36.7 million, compared with a net loss of $6.1 million in the same period last year. The bigger loss was primarily due to a $41 million hit on financial assets linked to contingent FID payments from Equinor, driven by fair value remeasurements. A deferred income tax benefit of $10.9 million booked during the quarter partially offset that loss. Per our arrangement with Equinor, a $40 million contingent payment owed to Standard Lithium was contingent on reaching FID at the SWA project by January 1st, 2027. Based on our newest assessment of where things stand regarding our ability to take FID, along with the resulting change in the target date, we now don't anticipate hitting FID before that contractual cutoff. As a result, we reduced the contingent payment's carrying value to zero, and that generated a $31.4 million fair value remeasurement loss during the quarter. I want to emphasize strongly that this adjustment solely captures the anticipated timing of FID relative to the payment deadline, and it does not in any way signal a shift in our assessment of the overall probability of reaching FID, nor does it alter our view of the project's fundamental outlook or prospects. Actually, our confidence in being able to reach FID at SWA has grown stronger. We now have every offtake contract required to back our project finance process. Work on limited notice to proceed activities with our EPC contractors keeps moving forward. With our ECA project financiers, we have cleared the majority of diligence stages. We are also still working to lock in final terms and get definitive documentation ready for that effort. The other $9.6 million of fair value remeasurement loss in the quarter is tied to a distinct $30 million contingent payment in our Equinor agreement. That payment hinges on reaching FID at the Franklin Project, or at any of our other East Texas assets, by January 1st, 2029. Given the delay at SWA and our current emphasis on bringing the SWA project to FID and starting construction — plus the resulting shift in SWA project completion timelines — we anticipate that our attention, capital allocation, and execution focus at SWA will reduce the likelihood that we hit FID on our first East Texas project before the contractual deadline for that contingent FID payment. As a result, we remeasured that financial asset downward to $10.6 million. That adjustment isn't a sign we see any lower chance of reaching FID in East Texas. Quite the opposite: now that our PEA for the Franklin Project has been issued, showing enormous potential for resources, production, and value creation, we feel more confident than ever about our capacity to develop our East Texas leasehold positions. On operating costs, G&A came in at $3.1 million for the third quarter of 2026, essentially level with the same quarter a year earlier. Personnel costs came in higher, but that was offset by reduced consulting and professional fees, since we moved certain functions in-house as part of maturing the business. Costs for the demonstration plant came to $1.0 million, compared with $1.1 million in the same quarter a year earlier, because more of that work was directed toward and assigned to developing the Smackover lithium project. Our portion of the Smackover Lithium joint venture's loss came to $1.8 million, versus a $0.9 million loss in the prior year's quarter, mainly because of greater development, commercial, and operating activity at the JV partnership level for SWA as we get closer to FID, and at East Texas as we keep both growing our leasehold position and deepening our knowledge of the resource. Interest income rose by $1 million year-over-year, reaching $1.2 million, which mirrors larger average cash balances. The foreign exchange effect was immaterial in this quarter after a July 1st, 2026 change to Standard Lithium's accounting policy, which shifted the functional currency at our parent company level from Canadian dollars to U.S. dollars. That change took effect because, at present and for the foreseeable future, most of the capital we raise and spend has been and will be denominated in U.S. dollars. We closed the quarter with a solid cash balance of $118.1 million and working capital of $114.4 million. Standard Lithium carries no term or revolving debt obligations that remain outstanding; during the quarter we put $19.3 million into Smackover Lithium, of which $11 million went to Southwest Arkansas and $8.3 million went to East Texas. Over the first nine months of the year, that amounted to $46.5 million for Smackover Lithium, or $26.1 million and $20.4 million for SWA and East Texas respectively. All of that moved us closer to the milestones we need before reaching FID at SWA — for instance, executing our EPC contracts and offtake agreements, advancing the ECA financing process, and getting limited notice to proceed work underway with our EPC contractors, which includes early engineering and similar activities that help de-risk our construction and commissioning schedules. That said, we aren't a single-project company, and we've continued growing our leasehold position, deepening our grasp of the resource, and further de-risking our East Texas projects, including getting the PEA ready for the Franklin Project. Through our existing at-the-market equity program, we brought in about $300,000 in gross proceeds in the third quarter, taking the year-to-date figure to $22.4 million. That marked a substantial pullback in activity, especially in the more recent months, given the weaker equity market environment. We will stay disciplined and prudent when it comes to any potential use of this program. Turning to financing for the SWA project, we remain in close contact with our chosen ECAs, among them the Export-Import Bank of the United States, Export Development Canada, and Export Finance Norway. Most of the key diligence workstreams are now concluded as we work toward final terms and definitive documentation. The SWA project is shovel-ready, and wrapping up the ECA process ranks among the last steps needed before we can actually pick up that shovel and begin digging. Right now our target is over $1.2 billion in senior secured project debt overall—higher than the up-to-$1.1 billion we first anticipated. We're actively pushing to finalize each outstanding lender funding condition, including a cost overrun facility, extra reserve accounts, and contingencies. Ultimately, that effort will determine the final capital funding needs for the SWA project. Any capital required beyond the senior secured project debt is expected to come from our $225 million Department of Energy grant — we anticipate having about $200 million of that remaining at the point FID is taken, given that we've been drawing on the grant as a cost share throughout the past year — as well as matching contributions from Standard Lithium and Equinor. The equity portion Standard Lithium must contribute will be supported in part by money raised through our equity offering last year, together with additional funding sources. We still believe that the size, design, and conditions of the debt we're arranging via the ECAs and a solid group of commercial banks are very appealing for the SWA project compared with the numerous other options we examined. We think this financing chance justifies far more than the substantial time and work required to complete it, and we anticipate demonstrating that before long. Under the present financing schedule, FID should occur by the end of Q1 2027, with building beginning shortly afterward; having said that, I'll return the floor to David.
Thanks, Salah. Last quarter we told you we anticipated wrapping up the customer offtake process and bringing out the Franklin PEA during the third quarter. Both of those are now done. These matter a great deal, and they represent many months of effort. Over at SWA, the commercial agreements we signed with LG Energy Solution and Trafigura give us a clear line of sight toward closing project financing, and they offer stronger confidence and validation as we get ready to move rapidly from development into construction. At Franklin, we now hold a foundational asset in East Texas that we can build on, while further strengthening the first-mover advantage we have in the Smackover Formation. This progress is the product of years of technical, engineering, and commercial effort from our team and our partners. Together with Equinor, our focus is on locking in financing, finishing the work required for FID, and being positioned to move promptly into construction once that decision has been made. We are dedicated to keeping you informed as that work moves forward. Before we take questions on the call, I want to welcome Ralph Alexander, who became an independent director on our board in October. Ralph carries more than four decades of leadership experience spanning energy, chemicals, power, and infrastructure, and we are eager to draw on his highly valuable and relevant expertise. Thanks once more for being with us today. Operator, I'll hand it back to you for questions.
Hello everyone, and thank you for the question. During the past week, Lithium Americas raised the capital cost for Thacker Pass by 30%. As they pointed out, the main factors were U.S. labor rates, which are affecting quite a few projects, along with inflation and tariffs. So my question is: how confident do you feel about the most recently published capital cost figure for Phase 1, and do you intend to revise it before FID next year? Thank you.
Thank you, Katie. We keep evaluating the situation and monitoring what our peers are doing. On our project, we don't anticipate cost pressure of that magnitude. As you'll see, the operations are different in nature, and so is the contracting approach. You may recall that our estimate of roughly $1.5 billion was based on a DFS and a FEED that took 18 months to complete; after that, in Q1 of last year — pardon me, the first half of last year — we signed with our EPC contractors, who confirmed those figures. In the contracts we awarded, we incorporated tariffs and escalation. On top of that, the contractor we selected provides its own craft labor, which differs from the scenario you mention. Our construction is also modular in nature and does not call for the extensive, complicated logistics and staffing that delivering on site demands. At site, I believe our construction peak reaches roughly 600 people, rather than the many thousands seen in some of the other operations referenced; furthermore, our contracting structure includes incentives for our contractors to finish on schedule and within budget. I'm confident that the guidance we've given so far is the best available at this moment; that said, we will update it in the first quarter, around FID, when we provide further guidance.
Great. A comparable question regarding the operating cost side: are there areas where you see possible cost pressure from inputs or reagents, or on the other hand, are there areas where you see room for optimization?
No, on the operating side we aren't seeing cost pressure that worries us. Over the six years we've run the demonstration facility, the team has concentrated heavily on creating a process and a flowsheet that reduced reagent use and held reagent costs as low as possible, out of concern that reagent costs could escalate. Reagents, power, labor, all of those, I think we're comfortable with the estimates we have for our operating costs.
Understood. Thanks, everybody — that helps a lot. I’ll hand it back over.
Hi folks, appreciate you taking my question, and this just builds on the previous one. Assuming you’re still at ease with that $1.5 billion capex figure, might you give us a bit more detail on the rationale behind the need for $1.2 million of de- — sorry, $1.2 billion of debt? Is it for funding reserve accounts, or a shift toward a higher view of the debt-equity mix? Whatever you can share would be useful. Thanks.
Absolutely. Salah, would you mind walking through that?
Absolutely, glad to. So we’ve got the $1.5 billion base capex, and that’s anchored in our FEED study and DFS. If you factor in the potential targeted senior secured debt of $1.2 billion, along with the $200 million grant, and then the split between us and Equinor on the remaining equity requirement — 45/55, with 55 to us — on the surface that looks like a pretty manageable burden. But what we want to make sure people understand is that within the senior secured financing process, there are extra contingencies layered on top of that $1.5 billion base capex — additional reserves, debt service reserve accounts, cost overrun facilities, minimum working capital balances — and those additional needs can push your total capital requirement above the base capex number. While we don’t expect to see, as David mentioned, a capex increase of an order of magnitude like some other projects globally that have been in construction or nearing construction, there are extra capital requirements we’ll have to solve for, and right now we’re working with the export credit agencies to pin down exactly what those figures are, and they remain subject to negotiation, which we’re hoping to wrap up here, as we’ve said, by Q1.
Thanks Salah, that gives me useful context. I'll hand it back over.
Hey David and team, I appreciate you taking the questions. I just want to follow up a bit on the financing side, and on that mark you guys made regarding those contingent payments. Just so it's clear, since the wording was somewhat difficult to follow, do you guys still have contingent payments that you expect to receive, and did you lose any because of this delay? Because I know you took the accounting adjustment, but is there still an opportunity to get Equinor to make these payments, or once this deadline passes do you not get the payment?
I'll take that one Joe. Thanks for the question. Regarding the milestone payment for Southwest Arkansas, that payment will be lost in its entirety if we don't meet a year-end FID. What we're saying at this point in time is that we're now targeting first quarter FID, and I think the best assumption is that we will not get that $40 million payment from Equinor.
All right. So with that in mind, did that play a role in the move from $1.1 to $1.2 on the debt, or is there now an equity requirement that isn't covered? How should we think about what losing that payment means?
Well, those are actually two separate matters. At one point, we thought that with the export credit agencies, we could source as much as $1.1 billion, and today we think there's potential to source more than $1.2 billion. That mostly reflects the ECAs completing their technical, commercial, and financial diligence and telling us the amount of debt they think the project can support. That's a separate matter from the $40 million issue. Having said that, had we been in a position to collect that $40 million, Standard Lithium would need $40 million less equity contributed into the project. Salah, I don't know whether you'd like to put that a different way, whether you'd like to add something or phrase it differently?
No, David, I believe you framed that accurately. It amounts to a one-for-one rise in the equity we'll have to provide so we can reach FID at Southwest Arkansas for our share of the capital contribution tied to our 55%. Previously, we were set to get the $40 million; since our base case now targets a Q1 '27 FID, that point will fall after the date when we're able to collect that $40 million, so the $40 million has to be sourced from somewhere. It could come from a range of places, specifically our balance sheet, which holds a sizable cash position as of this disclosure, and also any kind of incremental capital we raise through this process. There's a second FID payment — without going too deep into the details, but simply to be clear — there's an East Texas FID payment of $30 million, and it would take effect if we reach FID on our first East Texas project by 1/1/29. On a probability-weighted basis and on a discounted basis, we've still reflected that in our balance sheet, and we continue to hold some expectation that we might be able to collect that East Texas payment.
Okay. All right, I appreciate the extra detail there, Salah — that helps. All right folks, I'll hand it over now.
Good afternoon, everyone. From what I understand, you're shovel-ready under the limited notice to proceed — so once FID happens, how fast can you shift from development into construction?
Thanks, Dan — good question. As you mentioned, the team keeps working under that limited notice to proceed. With that in place, we believe we're moving engineering forward, and our contractors are moving their conversations with vendors forward as well. Assuming a first quarter FID — a first quarter FID — we should be starting construction and be very active in the second quarter; at this point, we plan to hit the ground running.
Understood. I suppose I'll just pivot a bit here, but after the Franklin PEA came out, have your views on sequencing changed, I suppose, as it relates to SWA 2 and Franklin?
What I'd say is that giving a firm answer right now would be premature. Obviously, the Franklin Project is a highly attractive asset and ranks as a high priority for us over the longer term. Priority one at present is reaching FID on Southwest Arkansas Phase 1 and starting construction; alongside that work, we'll keep up our exploration program in East Texas, and hopefully at some point next year we'll make a call regarding brownfield funding on whether we move forward with brownfield Southwest Arkansas or the Franklin Project next. Priority one at present is Southwest Arkansas Phase 1.
Got it. I'll hand it over, thank you.
Good afternoon, and thank you. Two two for me. Regarding that $1.5 billion budget, the initial version carried a 12% contingency. I know the exact figures aren't final yet, but with inflation where it is, would it be reasonable for us to anticipate a bigger contingency of 15% to 20% added onto re-marked prices?
It's fair to say that figure did have contingency in it. When Salah refers to cost overrun facilities, other contingencies, and other reserve accounts, those are contingencies beyond that amount which the export credit agencies want us to have in place. Salah, I don't know if you'd care to add anything to that?
No, Eric, what I'd say on that point is that these remain terms still being negotiated and discussed. A precise set of numbers on what the contingency percentages are and how we're looking at them isn't something we can give you. The DFS produces an estimate at a given point in time, built on extremely detailed engineering and analysis, along with statistical analysis backing it up, but the ECAs need to cover and gain comfort on additional risks beyond that. So, would we anticipate contingencies increasing above and beyond what a definitive feasibility study contains? Yes, that's very typical, and it falls within the market trends and practices we've observed on other projects. Do we anticipate the base capex figure, contingency included, rising by an order of magnitude like what we've seen in certain other recent lithium project developments? At this time, we don't expect that.
Understood, alright. Thanks, and then the second thing would simply be what minimum level of Franklin spending keeps progress intact there, the PFS in 2027? Thanks.
Salah, would you mind handling that one?
Sure. I’d say we haven’t issued specific guidance on that, Eric, but when you compare it with the capital requirements for SWA, it will be far, far smaller. I think historically, for our share of the capex that has gone into East Texas, we’ve spent in the range of $20 to $40 million each year. My expectation is that this might even be toward the lower end, in terms of the level of spending we would expect to carry out in East Texas so we can keep moving those projects forward. As we’ve said, and as I’ll repeat, restating what David mentioned earlier, our focus is on taking FID at Southwest Arkansas, putting capital into Southwest Arkansas, and reaching production at Southwest Arkansas. That is this company’s number one goal at this point in time. We are not a company with only one project; we will keep developing others, but Southwest Arkansas is number one and our primary focus.
Thanks, that's great.
Thanks, great. So having listened to what you said regarding Equinor's payment deadline, I'm a bit surprised nobody seemed open to revisiting that requirement, given the offtake was already secured, and my guess is Norway ECA involvement likely wouldn't have happened or been included if Equinor weren't the partner. Does that suggest the Standard-Equinor relationship is cooling a little, that they weren't willing to show some flexibility around the payment condition?
Noel, excellent question. Let me start by saying our ties with Equinor stay very strong. We collaborate with them constantly. Their people are mixed into the joint venture group at every level, and we collaborate with them on a routine basis. On top of that, we keep an open line of communication going with their senior leaders. They're genuinely enthusiastic regarding the Southwest Arkansas project, and they're putting in hard work right next to us in an effort to reach a positive FID before the first quarter ends. From a strategic standpoint, getting this finished is something they're eager to see, and they'd like to see it finished as fast as it possibly can be. To put it plainly, this was one of the terms that got negotiated at the time the joint venture was established. A deadline was attached, along with an incentive. We didn’t hit the target, and that shortfall wasn’t caused by them; that’s simply the situation we’re in now. This doesn’t reflect how dedicated they are to the project, and our collaboration remains strong.
Thank you. One point I was curious about: might you expand a little on the mechanics of the Trafigura option regarding your option for the extra 4,000 tpa of offtake under Standard's option?
Certainly. Mike, could you give us some detail on that?
Absolutely, that’s not a problem. During the contract term, the Trafigura option can be exercised in any year to have Trafigura take as much as an extra 4,000 tons for the year that follows. What makes that option useful is the substantial flexibility it gives us in how we use it and how we pursue other regions or chances for offtake that are strategically or financially advantageous. In effect, the Trafigura option serves as a backstop. As an example, we were very focused on securing long-term offtake, as you saw with the two contracts we hold for 10 years. For most customers, 10 years is an unusually long duration, so we can now consider, for instance, a wider range of offtake in which we secure a five-year contract and then rely on the Trafigura option as the backstop for the remaining five years so the lenders’ obligations are met. Our process benefited greatly from the Trafigura option, and it gives us the greatest flexibility as we move forward while also satisfying the lenders’ obligations regarding a volume commitment.
Great. I was just wondering whether you have any thoughts on the lithium macro picture at this point, because I forget the baseline price — oh, $2,400 — that's assumed in the East Texas PEA, and right now prices are sort of below that. I was just wondering if you had any thoughts on where pricing stands at the moment?
Sure, great question. We still believe that long-term pricing in that range of $20,000 to $25,000 a ton is the right range to use; we see long-term demand growth that needs new builds to come online, and incentive pricing for those new builds to come online. Based on our dialogue with our end customers as well as with others who would like to buy our product, and also frequent dialogue with leading industry consultants, we still think that something in and around $22,000 is the right long-term price forecast.
Great, thanks a lot.
That covers all the questions we have for now, and that brings today's call to an end. Thanks for joining us. You're free to disconnect at this point.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Standard Lithium Ltd. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Standard Lithium Ltd. earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.