Home / Transcripts / Standard Lithium Ltd. (SLI) · May 11, 2026

Standard Lithium Ltd. (SLI) Earnings Call Transcript

May 11, 2026

TSX Venture Exchange CA Materials Metals and Mining earnings 40 min

Earnings Call Speaker Segments

Operator operator
#1

At this point I'm happy to hand today's call to Daniel Rosen, who serves as VP of Investor Relations and Strategy at Standard Lithium. Daniel, the floor is yours.

Daniel Rosen executive
#2

Thanks, and good day to everyone joining us. With me on the call are David Park, our CEO and Director; Andy Robinson, President, COO, and Director; Salah Gamoudi, Chief Financial Officer; and Mike Barman, Chief Development Officer. Before we get started, I want to remind you that certain remarks we make today—including those touching on company performance, expectations, and project timing—may qualify as forward-looking statements. Please also review the cautionary language regarding forward-looking statements that appears in our press release, as it applies to this call as well. At this point, I'll hand things over to David.

David Park executive
#3

Thanks, Dan, and I appreciate everyone joining us today. The first quarter and the year to date have been active ones for us as we keep moving the company's key milestones and deliverables forward. At our demonstration plant in Arkansas, we hit major operational milestones, among them the processing of more than 1 million barrels of live Smackover brine across the last six years. Our large-scale demo plant is the first of its kind, and it is critical to everything we've been able to accomplish at Standard Lithium. It's provided a robust data set to support the scalability and de-risking of our selected process technology and flow sheet. It has also strengthened our first-mover advantage within the Smackover formation, where we have the only shovel-ready project that's preparing to take a final investment decision, our Southwest Arkansas project. We've also been working diligently to advance the remaining work streams required prior to a final investment decision, and we've made meaningful progress on all fronts. In the first quarter, we announced our first binding commercial offtake agreement with Trafigura, a global commodities leader with an established presence across battery metals, including lithium. Smackover Lithium will supply Trafigura with 8,000 metric tons per year of battery quality lithium carbonate over a 10-year period, beginning at the start of commercial production.

David Park executive
#4

We will go through where each of the work streams that are left stands and how it backs our broader plan, which is still to take FID at the Southwest Arkansas Project and start construction in 2026. With that said, I'll hand things over to Andy.

Andy Robinson executive
#5

Thanks, David. We're happy to report that we've hit a number of significant operational milestones at the demo plant we run in El Dorado, Arkansas, where a full brined lithium carbonate flow sheet is in operation. To date, we have processed more than 1 million barrels of actual brine that was pumped in real time from the Smackover formation. That work was carried out across 15,000 direct lithium extraction, or DLE, cycles, and it satisfied the essential performance targets for the core process technology that will be deployed at the SWA project. Among those results are 95%+ lithium recovery along with 99%+ rejection of key contaminants, which lines up with the performance guarantees contained in our licensing agreement with Aquatech. It was accomplished using approximately 340,000 man-hours across six years of operation with zero incidents, which highlights Standard Lithium's firm dedication to operational safety and best practices. Our demo plant will keep functioning as a vital platform for optimizing the process flow sheet, gathering operational data, feeding engineering design, and training the core group of 38 engineers and operators so they are ready for commissioning and operation of our first commercial facility at the SWA project. Earlier this year, we set out four primary deliverables that must be completed before we take FID: executing contracts with the key construction vendors, obtaining NEPA approval from federal regulators, finalizing customer offtake agreements, and closing the project financing.

Andy Robinson executive
#6

On the vendor contracts side, for the downstream part of the project — that's the piece with the central processing facility, covering the direct lithium extraction and battery quality lithium carbonate conversion process — we're using an engineering, procurement, construction, commissioning model, or EPCC. For the upstream portion, meaning the well field and the pipeline, we're going with an engineering, procurement, and construction management approach, or EPCM. Right now we're wrapping up agreements with the partners we've chosen for those two key roles, and we expect both to be finished in the second quarter, as we said before. Every one of these contracts has a limited notice to proceed clause so that key work items can move forward right away and the construction schedule can be optimized ahead of a final investment decision. Once we get a positive FID, a full notice to proceed will follow immediately. Turning to regulatory matters: the project has to undergo an environmental assessment under NEPA, which was triggered by our $225 million grant from the Department of Energy. The DOE is running that process, and after more than a year of review and engagement it's approaching its formal conclusion; per the federal permitting dashboard, we expect completion in the second quarter. We don't anticipate any additional mitigation measures or conditions being imposed, nor any further federal government reviews or approvals being needed, before we can take a final investment decision.

Andy Robinson executive
#7

On the whole, we've had robust backing from the government during this entire process for our project, which was granted a FAST-41 transparency project designation as a priority U.S. critical mineral project. Moving to our dual track processes for customer offtake and project financing, Smackover Lithium, together with our seasoned financial advisors, keeps delivering excellent progress. Given our planned nameplate capacity of 22,500 tons of lithium carbonate per year, we're aiming for roughly 80% of that output to sit under long-term offtake contracts. Our initial offtake agreement, signed with Trafigura for 8,000 tons, accounts for more than 40% of the targeted offtake. The partnership anticipates concluding agreements across all remaining advanced offtake negotiations by the third quarter. We stay focused on obtaining the best possible terms within these agreements so as to bolster our project financing efforts. Every material offtake term has to be settled before we can determine the final sizing and structure of the project finance package. The joint venture continues to feel confident in its capacity to secure a positive result in these customer negotiations, thereby enabling FID to be taken and construction to get underway in 2026. If we do start construction on that timeline, we anticipate reaching first commercial production in 2029. I'd like to wrap up my remarks by briefly addressing East Texas.

Andy Robinson executive
#8

We keep sharpening how we define our resource position by drilling more and running additional process test work at the Franklin Project and across the wider region. Our target is to put out a preliminary economic assessment, or PEA, for the Franklin Project during the second half of 2026, and we intend to follow it with a preliminary feasibility study, PFS, in early 2027. Laying out the project economics of that world-class resource matters so that this important and underappreciated piece of our asset portfolio gains further recognition. Work will carry on toward maiden inferred resource reports for the two other potential projects we hold in the area, and at the same time we will keep growing our leasehold footprint in East Texas. With that, I'll hand things to Salah, who will walk through our financial results.

Salah Gamoudi executive
#9

Thanks, Andy. For the first quarter that ended March 31, 2026, we posted a net loss of $2.7 million, compared with a loss of $1.6 million in the quarter that ended March 31, 2025. During the quarter, G&A edged down by $0.1 million, whereas demonstration plant costs rose by $0.4 million year-over-year. That modest decline in G&A shows our ongoing dedication to cost discipline, because even with headcount growth and more activity to support development of our project portfolio, we found offsetting savings in certain audit, legal, and consulting expenses. The demo plant increase came from higher personnel and supply costs tied to R&D activities, along with maintenance and site improvement work. As Andy mentioned, the work we do at the demonstration plant is critical and will remain a real differentiator for us. In addition, we recorded a non-cash foreign exchange gain of $2.2 million during the quarter. That foreign exchange gain resulted from holding significantly higher average U.S. dollar cash balances following our $130 million follow-on offering in October of last year, as well as from fluctuations in exchange rates between U.S. and Canadian dollars and the resulting non-cash accounting effect on those cash balances held by one of our Canadian dollar functional currency entities.

Salah Gamoudi executive
#10

Further down the income statement, below operating expenses, we booked a larger loss from joint ventures — $1.5 million this quarter, compared with $1 million a year earlier. The bigger figure comes from more operational activity at the Smackover Lithium partnership, tied to commercial and financing work, along with greater corporate and administrative support as development of the projects moves forward. On top of that, we took a $0.8 million loss on the fair value of our contingent FID payments — amounts Standard Lithium would get from our partner Equinor if we hit a positive FID at our SWA and/or East Texas projects by specified dates. That was mainly a result of revised assumptions about when milestones will land, not a shift in the overall likelihood of reaching FID. We also picked up $1 million more in interest income compared with the prior year, thanks to higher average cash balances. We closed the quarter in a strong position, with cash of $141 million and working capital of $139.5 million. Standard Lithium contributed $17.9 million of JV capital during the first quarter, split between $9.6 million for SWA and $8.3 million for East Texas. In Southwest Arkansas, those contributions let us keep pushing key project milestones forward as FID gets closer and keep advancing our technical and engineering work streams.

Salah Gamoudi executive
#11

When it comes to East Texas, that contribution mainly goes toward deepening what we know about the resource, keeping our leasehold footprint growing, and staying on the road toward a preliminary economic assessment, which a preliminary feasibility study would then follow. A key element of the Final Investment Decision for SWA is locking in an appealing and thorough project finance package. According to our DFS, roughly $1.5 billion of base project CapEx — plus possible cost overrun facilities, reserve accounts, or other incremental capital needs — is expected to be funded through a mix of senior secured project debt, our $225 million grant from the DOE, and the respective funding contributions of Standard Lithium and Equinor. The joint venture aims for about $1.1 billion in total senior secured limited recourse project debt, backed by three leading major Export Credit Agencies — among them the Export-Import Bank of the United States and Export Finance Norway — together with a strong syndicate of commercial banks. Proceeds from our equity raise last year will support the remaining 55% pro rata equity contribution that Standard Lithium is required to make. Anything beyond base project CapEx requirements — cost overrun facilities, contingencies, minimum working capital balances, or reserve accounts — is still subject to negotiation with the lenders, with quantums yet to be determined.

Salah Gamoudi executive
#12

We’ve already gotten indications of interest from the ECAs and commercial banks that go beyond the overall project debt we’re targeting. On top of that, the early responses came with indicative terms that lined up with what we had expected, and they confirmed some of our assumptions about cost, tenor, structure, and the conditions that are typical for project debt facilities like this. While we’re waiting for the remaining commercial offtake agreements to be finalized—which will in the end settle the size and structure of the SWA project debt—we’re continuing to move forward in the meantime on key project financing work related to due diligence, structuring and documentation, credit and other approvals, so that we’ll be in a position to reach financial close and draw down soon after. Put another way, the offtake process isn’t slowing down the project financing work streams, and we’re still on our targeted timelines. I’ll now hand it back to David for closing remarks.

David Park executive
#13

Thanks, Salah. We're fully aware of just how significant 2026 is for Standard Lithium, since we're moving toward a final investment decision on the first phase of the Southwest Arkansas Project. As we wrap up all the remaining work over the next few months, we'll share updates promptly, and we'll keep you informed on how we're tracking against our plan — which is still to approve FID and start construction in 2026. Standard Lithium remains in an extremely strong position, ready for growth thanks to a portfolio of high-quality, scalable assets, including those in East Texas, and we're set to be a leading domestic producer of critical minerals in the United States. Thanks once more for being with us today. Operator, back to you.

Operator operator
#14

We're moving into the Q&A portion now. Should you wish to pose a question, hit star followed by one on your keypad to get into the queue. If you change your mind, just hit star one a second time to pull it back. So that the audio comes through as clearly as possible, we'd ask you to lift your handset while speaking. And if your line is muted on your end, don't forget to turn the mute off. Sit tight for a moment while we put the Q&A list together. Our first question is from Max Yerrill at BMO Capital Markets. Your line is open. Please go ahead.

Max Yerrill analyst
#15

Hi everyone, and thanks for taking my question. While you were going through the vendor contracting process, I was just curious about how these costs are tracking relative to what you perhaps anticipated at the outset. Thanks.

David Park executive
#16

Much appreciated, Max. Andy, perhaps you should take that question—you're nearer to it.

Andy Robinson executive
#17

Yeah, absolutely. That makes sense. Thanks, Max. Yeah, I mean, clearly the DFS remains fairly up to date, and so does the FEED study that served as its foundation. Much of the original vendor buildup that fed into it is still quite recent. Obviously, we'll be issuing limited notice to proceed to the two main contracting entities in the very near future. Once that happens, they'll be refreshing some of the expected costs through vendor outreach. Where we've been monitoring pricing so far, we haven't seen it shift meaningfully. In our pricing model right now, we've built in allowances for escalation and tariffs as part of the contracting vendor engagement process. We've been watching it closely, and that will get formalized as we move through that LNTP process before we take the final investment decision. Hopefully that answers your question, Max.

Max Yerrill analyst
#18

Appreciate that. Maybe just one more, then. Since the point when you all began the offtake pricing talks, lithium prices have rallied enormously. Have any of the goalposts shifted regarding possible floors or ceilings compared with when those offtake discussions started? Any detail you could offer on that would be extremely useful.

David Park executive
#19

Yes, thank you very much, Max. That's a solid question. Over the past year, lithium carbonate pricing has improved significantly. You know that well. Because of this, beginning around Q4 and continuing into Q1 of this year, more counterparties returned to the table and were able to offer pricing mechanisms that suited us and supported our financing, compared with what we saw last year. Probably the clearest way to put it is that our discussions now have greater depth, and we're running a competitive process to finalize our offtake agreements. As you know well, we already have our first agreement signed with Trafigura for 8,000 tons. At this point we're working with several counterparties to wrap up agreements. We believe we know which counterparties those will be. We have a solid sense of the volumes, the duration, and the pricing mechanisms, and we feel far better about this than we did last fall.

Max Yerrill analyst
#20

Excellent. Appreciate it, everyone. I'll hand things back to the queue now.

Operator operator
#21

Anthony Taglieri from Canaccord Genuity has the next question. Your line is open, so please proceed.

Anthony Taglieri analyst
#22

Good afternoon, everyone, and thanks for taking my questions. Perhaps just regarding CapEx at the project level for this year, what would be a sort of reasonable expectation for spending there, given that, you know, construction is probably going to begin toward the end of the year? Some thoughts on that would be helpful. Thanks.

David Park executive
#23

Andy, would you like to handle that one, or should we pass it over to Salah?

Andy Robinson executive
#24

Perhaps Salah could take that question? That would be helpful, yes.

Salah Gamoudi executive
#25

Absolutely, glad to. What I'd say is this: looking ahead, as Andy said, we're going to bring the EPC contractors on under a limited notice to proceed, and that's ultimately where the final CapEx figure will come from. Once procurement work has begun and you've got actual live quotes from vendors, that's the point at which we can pin down a specific number. Generally speaking, I'd note that we don't anticipate a very large swing, as Andy said, since the FEED study behind the DFS was completed quite recently and it entailed considerable direct engagement with vendors, gathering quotes, and so forth. Going forward, though, we do need to factor in additional items that can arise with respect to capital needs. Contingencies could be necessary within our debt financing process, as Max said earlier on this call — cost overrun facilities, debt service reserve accounts, minimum working capital balances, and similar items — and those can push your capital requirements beyond the base CapEx needed to actually construct the facility. We'll be working to pin that down going forward, both on the EPC contracting side and in our negotiations and talks with the project lenders.

Anthony Taglieri analyst
#26

Alright, thanks a lot. Perhaps regarding East Texas, is there any preliminary perspective or broad outline you could offer us, specifically in relation to SWA when it comes to economics? For instance, how ought we to approach, you know, modeling this project going forward, I suppose before the PEA, clearly?

David Park executive
#27

Andy, would you like to begin with that item?

Andy Robinson executive
#28

Yeah, absolutely. Anthony, it's — obviously, we haven't put out any economics assessment for the Franklin project, nor for any of our land holdings over in East Texas, as of today. One point I'd make is that from what we've seen across our experience over many years, lithium grade matters enormously when it comes to the economics of DLE-based projects. When we go from the Southwest Arkansas project, where, you know, our average grade kind of sits in the 400s to 500s milligrams per liter lithium, into East Texas, there we're typically seeing 500 plus, you know, into the 6s and 7s and even into the 8s. In East Texas, we expect that factor to work strongly to our advantage. I think that's going to be, you know, interesting and positive down the road. We're in the process of picking a vendor to finish the PEA right now. We expect to get it out as, you know, as soon as we can. It's going to land in the second half of this calendar year. You know, we expect the economics to look favorable, frankly. These are world-class resources. The assets are, you know, quite incredible when you look at just the size and quality of them.

Andy Robinson executive
#29

These assets are of very high quality and lend themselves extremely well to DLE processing, along with expansions of the flow sheet, you know, that we're going to build at SWA phase I. Our aim is to take all of that extensive learning from the demo plant and from the engineering and FEED studies for SWA phase I and carry it over, translating it into higher grade assets in East Texas. We believe that will make for a good story.

Anthony Taglieri analyst
#30

That's great, thanks. Then perhaps just one more if I could. Have offtakers begun posing questions to you regarding East Texas — for instance, when you figure that project might actually be producing? How is that beginning to factor into these conversations? I'd imagine the obvious focus is SWA at present, but I'd also imagine that, as an offtaker, they would be considering longer-dated production schedules and where you could ultimately end up.

David Park executive
#31

Yeah, I'll take that one. What I'd say is that the off-takers we're speaking with are folks who want a partnership with us that lasts a long time. The negotiations themselves are very much centered on Southwest Arkansas, but their appetite for a long-term partnership with Standard Lithium goes past Southwest Arkansas. They're quite drawn to what we could do in East Texas, so we can keep growing together.

Anthony Taglieri analyst
#32

Much appreciated — I’ll make sure to share that.

Operator operator
#33

Eric Boyes from Evercore ISI has the next question. Your line is open, so please go ahead.

Eric Boyes analyst
#34

I appreciate you taking my question. First, we devote considerable time to discussing how sensitive things are to lithium prices and CapEx, but could you perhaps address the variability in production volume with DLE, if there is any, in Southwest Arkansas?

David Park executive
#35

Andy, would you like to take that one?

Andy Robinson executive
#36

Absolutely, Eric. So at Southwest Arkansas, phase 1, we've built the facility so that, in effect, lithium carbonate output is the limiting factor, if you will. We start from the annual volume of lithium carbonate we want to produce, and then everything else — including the brine supply — is designed around that figure. Given the quality of the resource at Southwest Arkansas, put simply, we have more brine available than the operation of that facility requires. What that means is that, because the resource is so large relative to the production facilities, we expect to run at nameplate capacity for very long stretches — multi decades of operation. There will be some small natural fluctuations in annual capacity, but in simple terms, we have a plant whose good, even production capacity can be more than supplied by the resource. That's roughly the overall philosophy. On an annual basis, we wouldn't anticipate large-scale fluctuations at the plant. Naturally, that is the foundation for the long-term offtake contracts we are also in the process of finalizing and signing.

Eric Boyes analyst
#37

Alright, thanks for that. My follow-up is also about East Texas. Realistically, how much of that Southwest Arkansas engineering package could you actually replicate in that area? And which parts of the design would probably have to change, or would likely change? Thanks.

David Park executive
#38

That question is yours to handle, Andy.

Andy Robinson executive
#39

Sure, I’ll take that question. We consider ourselves very lucky, and one factor behind our presence in the Smackover, Eric, is that from an engineering and flow sheet design standpoint, the brine geochemistry is genuinely quite comparable as we move from one area where we operate to the next. Put simply, we can carry over directly a substantial portion of the flow sheets—whether for the demo plant or for Southwest Arkansas—into East Texas. In fact, East Texas is somewhat easier. For the most part, there’s no sour gas to handle within our project areas. Some sections of the flow sheet can be reduced or eliminated when we transfer from Southwest Arkansas to East Texas. That will be beneficial. Largely, we are proceeding with a comparable flow sheet. We certainly expect to be able to bring established vendors from Southwest Arkansas—naturally, established contracting partners from Southwest Arkansas—into East Texas. Broadly speaking, the core philosophy for why we are in the Smackover is that we can, to a significant degree, duplicate our flow sheet, add simplicity, add efficiencies, and preserve key vendor, supplier, and contractor relationships so that we can minimize redesign cycles, minimize shortened timelines, increase efficiencies, optimize where it makes sense, and so on.

Andy Robinson executive
#40

We genuinely aim to modularize wherever possible and, where it makes sense, replicate from one project to the next as much as we reasonably can, so that we capture those production efficiencies in both construction and, afterward, operation.

Eric Boyes analyst
#41

Much appreciated. I'll hand things back now.

Operator operator
#42

Joseph Reagor from Roth Capital Partners has the next question. Your line is open, and you may proceed.

Joseph Reagor analyst
#43

Hey, guys. Appreciate you taking the questions. Most of what I wanted to cover has already been asked, but I've just got one broader-picture question. I've been noticing a lot more discussion about, across multiple oil field locations, the possibility of recovering other minerals — not only lithium, but from the brines and from the waste waters — and also some government backing for this, you know, things on the critical minerals list being rarer. Is there any opportunity there for you guys? I'd guess probably too late with Southwest Arkansas, but maybe with East Texas you could add other potential minerals to your revenue profile?

David Park executive
#44

Absolutely. I'll begin here and then hand things over to Andy too. To begin with, you're right. For the Southwest Arkansas project, our focus is entirely on lithium. My view is that you shouldn't factor that into any expectation for a revenue stream. When it comes to East Texas, we do have the chance to go after other minerals, and on that note I'll pass it to Andy to expand on it.

Andy Robinson executive
#45

Hi Joe. So, in that first inferred resource estimate, we laid out the possible bromine and potash resources that exist there too — and both are high quality and quite large. As we progress toward the PEA, I think we still haven't decided whether to fold potential economics from those other resources into it. We certainly recognize there are some very high-quality resources present. Those are the ones identified up to now — bromine and potash. There could also be that additional potential within the Smackover brines out in East Texas. From a straightforward grade and size standpoint, I think those are probably the ones we're going to push forward and look into a bit more down the road.

Joseph Reagor analyst
#46

All right, I appreciate the context. That covers everything on my end.

Operator operator
#47

Theo Genzebu from Raymond James has the next question. Your line is open — please go ahead.

Theophilos Genzebu analyst
#48

Yeah, great, thanks guys. I guess I’ve just got one left over. Just regarding NEPA — I believe it was said previously that there was something like a public comment or commentary period. Could you give us an update on that, or on how it’s progressing? I know you expect the process to wrap up by the end of the second quarter. Any additional insight you could offer there would be great.

David Park executive
#49

Yeah, that's a good question. We're feeling quite confident about where we stand regarding the NEPA process. The period for public comments has ended. In our view, the report is either complete or very close to it, and we're hoping for some positive developments on that front during this quarter. Things have progressed — the process has kept moving forward — and along the way we haven't run into any negative surprises.

Theophilos Genzebu analyst
#50

All right, that’s good to hear, and it sounds constructive. You’ve addressed the questions I had, so I appreciate everyone’s time today. Thank you.

Operator operator
#51

Noel Parks from Tuohy Brothers Investment Research has the next question. Your line is open — please proceed.

Noel Parks analyst
#52

Hello there, and good afternoon. Hearing the conversation up to now regarding brine characteristics and brine content across the various target regions you have was quite interesting. From the initial South Arkansas demo through Southwest and now on to East Texas, I'm simply curious about reservoir characteristics and whether they're actually also reasonably uniform throughout these differing Smackover regions. Things like pressure, and how they act during a depletion replenishment cycle — I'm just wondering whether any variation exists there.

David Park executive
#53

That one is yours, Andy.

Andy Robinson executive
#54

Sure, no problem. Hey, Noel. Yeah, so clearly that package of bromine facilities down in southern Arkansas—you know, it's been running for 60 years at this point—so there's an enormous body of information there about the way the Smackover reservoir produces and can also be reinjected. We've been able to draw on, you know, just a truly massive quantity of data, Noel, regarding how that formation behaves. As, you know, as we've progressed through, obviously we're dealing with a package of leases across Lafayette and Columbia counties for the Southwest Arkansas project. Over the years, I think we've been remarkably and pleasantly surprised by how productive that project area is. We've got some really high-quality rock, and we're very, very confident in its capacity both to produce brine and then to reinject the, you know, the tail brine, the waste brine, spent brine back into the formation so that pressures are maintained for production spanning multiple decades. As we moved into East Texas, you know, it's fair to say that, based on what we've learned in the region working alongside LANXESS over there—very large footprint, you know, they hold 150,000 plus acres of leases in Union County in Arkansas—and all of the work that we've carried out in and around Southwest Arkansas, we were highly deliberate when we began the work in East Texas 5 years ago.

Andy Robinson executive
#55

We know how to identify the optimal zones of porosity and permeability within the formation, where those zones sit in the formation, how to site projects, and so on. Since we had that substantial first-mover edge in the Smackover, as our footprint has grown, I believe we've been quite deliberate and consistent about assembling lease packages and project positions so we can fully capitalize on the parts of the Smackover that, put simply, we know perform best. Your point is a fair one, because from a reservoir standpoint the Smackover is highly variable. Certain areas have lower porosity and, as a result, lower permeability. Other areas have more complex geological structures featuring considerable faulting and flow discontinuity. Those are precisely the areas we deliberately steered clear of when we began five years ago in East Texas. I think we've been highly intentional about where we've placed our Smackover projects so as to benefit from the same reservoir characteristics that we've come to understand through working on the LANXESS projects and in Southwest Arkansas. I hope that addresses your question, Noel.

Noel Parks analyst
#56

It absolutely does, and I think, from that, it's fair to say that regarding the sort of competitive lead you'd hold over other entrants or other players who perhaps aren't so active at present, it would appear to reinforce that even further. Put another way, you can't simply leap in and lease whatever remains unleased and then expect great results in every location.

Andy Robinson executive
#57

Right. I won't comment on what others are doing with their projects, but the reservoir quality certainly isn't uniform across space — it changes both east to west and north to south, across the formation and along it. I think, yes, as a developer you have to be extremely intentional about selecting the right rock, the kind that will genuinely support production. That's essentially been our approach from day one, and it's something we've applied very purposefully as we've grown our footprint and the resources in that area.

Noel Parks analyst
#58

Great. Turning to the offtake financing side, I was just wondering about the partners you're in discussions with — several of them, I'd imagine, are the usual names one would expect to have an interest in lithium. I was just curious whether any of those parties are themselves working alongside other strategic or financial parties. I suppose what I was getting at is that, compared with a few years back, when capital tied to EVs was fuelling much of the interest — and now you also have AI power capital, plus energy storage, so to speak, pushing into the picture. I just wondered whether, whereas a few years ago you'd be talking to one particular kind of manufacturer, it's now that manufacturer plus some other kind of fund, for instance, that's eager for lithium exposure, coming in alongside them.

David Park executive
#59

That's a good question. On the offtake side, I'd say from the very beginning our focus has been on finding partners or customers who have strong balance sheets and exposure to different segments of the lithium market. Right now we're in discussions with players representing all of those various demand nodes for lithium. We're being very careful not to concentrate everything in the EV basket. Having exposure there is obviously important. It makes up a very large portion of the market, but it isn't the only portion. We're going to ensure we have exposure to the AI and data center trade as well. We're in discussions with all of those parties. On the project financing side, I'd say again it's Export Credit Agencies that we're speaking with regarding the provision of non-recourse or limited recourse financing for the project.

Noel Parks analyst
#60

Alright, thank you very much.

Operator operator
#61

That brings us to the close of the question-and-answer portion. Today's call ends here. Thanks for joining us. You're welcome to disconnect at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Standard Lithium Ltd. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Standard Lithium Ltd. earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.