Vascon Engineers Limited (VASCONEQ) Earnings Call Transcript
November 4, 2026
Earnings Call Speaker Segments
Good day, everyone, and welcome to the Q2 and H1 FY '27 earnings conference call for Vascon Engineers Limited. <<operator_script>> I'd like to point out that this call is being recorded. At this point, I'll turn things over to Mr. Akhilesh Gandhi of Stellar Investor Relations. Thank you, and the floor is yours, Mr. Gandhi.
Thanks, Sid. Good afternoon, everyone. I'm Akhilesh Gandhi, speaking for Stellar Investor Relations, and I'd like to welcome all of you to the Vascon Engineers Q2 and H1 FY '27 Earnings Conference Call. On today's agenda, we'll be walking through the key operating and financial highlights covering the second quarter as well as the half year that closed on September 30, 2026. Joining us are members of Vascon Engineers' senior management team. Primarily, we have Mr. Santosh Sir, our Group CEO. Beside him is Mr. Somnath Biswas, Chief Financial Officer; and also with him is Mr. Raveesh Rao, Chief Executive Officer for the Real Estate segment. Before we get started, though, I want to point out that this call might include certain forward-looking statements, and those are entirely based on the company's beliefs, opinions and expectations as of today. What's said on today's call is not a guarantee of future performance and likewise carries unforeseen risks and uncertainties. In addition, the company assumes no obligation to update any forward-looking statements so as to reflect developments occurring after such a statement is made. Materials concerning the company's financial performance, the investor presentation included, have already been posted on the stock exchange. With that, I'll now hand things over to Dr.
Santosh Sundararajan will now give his opening remarks regarding how the company performed in the second quarter as well as the half year that concluded on September 30, 2026. After that, we'll open things up for a Q&A session. Thanks, and the floor is yours, sir.
Thank you. Good afternoon, everyone, and welcome to the Vascon Engineers Q2 and H1 FY '27 Earnings Conference Call. We appreciate you joining us today. I hope you've had a chance to review our financial results and the investor presentation, which are available on the stock exchange as well as the company's website. As we move through FY '27, our focus remains on accelerating project execution, strengthening our order book and improving cash flow efficiency and driving sustainable growth across our EPC and real estate business. Turning to our EPC business. EPC continues to remain the cornerstone of Vascon's growth journey. As of September 30, 2026, our total EPC order book stands at approximately INR 3,400 crores, comprising an external order book of INR 3,215 crores and an internal order book of INR 185 crores. This represents approximately 3.7x our FY '26 EPC revenue, providing strong revenue visibility. Our external order book has increased from INR 2,387 crores at the end of FY '26 with government projects accounting for approximately 63% of the order book. During H1 FY '27, we secured several significant orders, including the Qualcomm IT Park project in Bangalore for INR 660 crores, including taxes, along with the project from RBI and SBI and the government hospital in Wardha.
We've already locked in roughly INR 1,200 crores in new EPC orders, and our attention stays on hitting the FY '27 order inflow goal of INR 1,500 crores to INR 2,000 crores. Turning to how projects are progressing: Q2 FY '27 brought a solid rebound, helped along by better fund inflows into 2 big government projects that had run into cash flow difficulties in Q1 FY '27. Consequently, EPC revenue climbed to INR 251 crores in Q2 from about INR 148 crores in Q1 — a quarter-on-quarter jump of nearly 70%. Execution conditions are improving, and the projects we've newly won should start adding meaningfully from Q3 onward, so we're confident about generating stronger momentum in execution. Now for real estate: progress remains encouraging, backed by healthy sales bookings, fresh project launches and internal capabilities that keep getting stronger. Across H1 FY '27, our total booking value came to INR 152 crores — INR 66 crores in Q1 FY '27 plus INR 86 crores in Q2 FY '27, versus roughly INR 100 crores for the whole of FY '26. We additionally posted new sales bookings of about 68,571 square feet, with collections totaling around INR 43 crores. Tranquil Heights in Powai, our latest launch, drew healthy interest, booking INR 58 crores across 36 units in Q2 FY '27 and bringing cumulative bookings to about INR 75 crores.
In a similar vein, bookings at Orchids in Santacruz West came in at INR 25 crores for the quarter, which brought cumulative bookings up to INR 112 crores. Combined, these 2 projects accounted for roughly INR 83 crores out of the total booking value of INR 86 crores in Q2 FY '27. We've also moved forward on the Prakash CHS in Santacruz West, with all key approvals in hand, including IOD, CC and RERA. Bhoomi Pujan was completed recently, and prelaunch activities are now underway. Our strategy continues to center on asset-light redevelopment along with selective JV and JDA opportunities in Mumbai and Pune, backed by different capital allocations. We stay committed to hitting our indicative FY '27 sales booking target of INR 250 crores to INR 350 crores, while making progress toward our longer-term ambition of INR 1,200 crores to INR 1,500 crores in annual sales value by FY 2031. Turning to our financial performance. In Q2 FY '27, the company posted consolidated revenue from operations of about INR 252 crores, a rise of nearly 12% year-on-year. EBITDA came in at approximately INR 23 crores, up around 18% year-on-year. PAT, meanwhile, grew by approximately 14% to INR 13 crores. The quarterly results reflect recovery in EPC execution as well as continued operational efficiency.
For H1 FY '27, consolidated revenue came in at about INR 404 crores, versus INR 447 crores during the same period a year earlier. EBITDA was roughly INR 33 crores, against INR 53 crores in the equivalent period last year. It's important to note that H1 FY '26 contained a one-time gain of approximately INR 17 crores arising from the sale of an investment. Once you strip that out, the underlying EBITDA performance is still relatively resilient. Profit after tax came to approximately INR 15 crores, compared with INR 34 crores in H1 FY '26. On the segment side, EPC delivered EBITDA of around INR 41 crores versus INR 39 crores a year ago, and margins improved slightly, to approximately 10% from 9% previously, which reflects healthy operating profitability. From a balance sheet standpoint, net debt was approximately INR 156 crores as of September 30, 2026. We continue to focus on optimizing our funding structure and on strengthening cash flow efficiency. Going forward, we stay optimistic about the opportunities in both of our businesses. Within EPC, a strong order book, better execution momentum and a strengthened working capital position give us a healthy foundation for future growth. In real estate, encouraging sales traction, upcoming project launches and enhanced internal capabilities put us in a good position for sustainable expansion.
Accelerating execution stays at the top of our list, along with turning our solid order book into revenue, bettering cash flows, and expanding our real estate business in a disciplined way. We're still dedicated to sustainable growth, stronger profitability, and building long-term value for our stakeholders. On that note, I want to thank all of you for being with us today. The floor is now open for questions. Thank you.
<<operator_script>> Our initial question is from Himanshu Upadhyay with Steadfort.
So, I had a question about Orchids, alright? The presentation says 10 units have been sold, but the realization dropped from INR 37,000 down to INR 32,000. What's the reason behind that, since the project is nearing completion now, and why such a large decline in realizations?
What we did is—in Ganpati, around Ganpati, we had—and at that moment, we were about—I believe we were in the sixth slab, moving into the seventh slab. So at that time, we ran an investor scheme where people could pay 95% upfront and get a discount on it. So we sold it at roughly INR 31,000, INR 32,000 on average. That's why the price has dropped. But the collection for that is due by November. So in the October, November, December quarter, you would see significant cash flows coming in for that.
Alright, so let's take INR 25 crores — roughly INR 22 crores of that would come in...
Right. In October, we've actually already collected roughly 8 to 9 of that amount, and the rest should land during the following six months. Essentially, with Dussehra and Diwali coming up, our aim was to speed up collections so we could move construction forward, since we're directing every bit of cash flow we get from both sources toward paying down debt and funding construction. That's why we made that push.
And because Diwali is right around the corner, this scheme is still running after Ganpati as well. So is that scheme going on at present?
No, not at the moment. Not at the moment. That was a one-off action on our part, but at present we don't have anything like that in place.
Right. So — given that you just mentioned Dussehra and Diwali...
Basically, with these schemes, it takes a certain period before the cash flows start arriving. That's why we launched it during Ganpati — so that during the October, November, December quarter, we'd have sufficient cash flows coming in.
Also with the Tulip Phase 3, the realizations dropped from INR 6,500 down to INR 5,000. Was there any scheme as well...
No. So basically, that was the lowest-floor inventory. It's the final unsold stock remaining there. Those units were on the first and second floors, and they had pretty — they didn't come with good views and looked out onto other nearby buildings. That's the reason it went at a discount.
And beyond the great views, typically in Coimbatore, folks there tend to be more Vastu compliant. However, these units are not Vastu-compliant units.
Alright. Alright. And then one final...
Apologies — we dropped the connection there.
Yes. Can you hear me at this point?
Yeah, we can hear you clearly now.
Yes. So my question was about the projects we won recently. When do those projects begin to contribute to revenue now?
Regarding the Qualcomm project — the design falls within our scope, and after that we'll pursue the final round of approvals too. Excavation has begun at the site, so we can carry out a portion of our activities. However, for the work to reach full swing — really in full flow — I think that happens around Q4, starting in January. The same goes for the SBI project. For both of these projects, we anticipate full-scale activity getting underway by January.
And regarding a few of those projects that are progressing at a slower pace, where do things stand with them?
They've picked up now — Suphal and Sindhudurg. At both sites, we were stuck because a lot of cash flows from the client weren't coming through, and at that point the project had more or less reached a semi-standstill, a semi-demobilized kind of state. But over the last couple of months, cash flows have been arriving from the client, and they've expressed seriousness about scaling it up again. We've scaled up as well now. So those projects have begun peaking in terms of the monthly billing they can achieve.
And last, regarding Royal Rides — that's a project we won 1 year ago. With significant inflation running through the market and nothing having moved on that project for over 1 year now, what happens there? So how are you thinking about it, and where are we — or will we — be compelled, if this slips by another 1 year or 6 months, to carry out the business at the same rates we won it at?
No, that would never happen. You see, escalation clauses and base rate clauses are built into every one of our contracts as a general matter. And as you correctly pointed out, through no fault of ours, the project hasn't begun. So simply because the project was awarded to us a year ago, in every right -- we have every right to ask for escalations that aren't covered in the contract, if the project does start at all. But I'll also be candid about this: there's no indication from the ground that the project looks like it's starting in the next 5, 6 months either. So as of now, for all practical purposes, in our mind, we're just holding on to that order book for a few more months. And if really 6 months down the road, if there's still no action, we'll probably temporarily remove it from our order backlog.
<<operator_script>> Our following question is from <<inaudible>>, an individual investor.
I've got a few questions about the order pipeline and the real estate business. First, can you give us some color on the EPC bidding pipeline as it stands — which sectors are showing the strongest opportunity? And how do we expect the mix of government and private sector to evolve?
Yes. So in that sense, we're pretty much agnostic when it comes to department or building. We're prepared to take on any type of building in just about any city across the country. So we don't limit ourselves by building type. That said, when we have a choice available, we try to be selective regarding the client — whether government or private — the sort of client we want to work with, so that the odds of continued payment across the life of the project are higher. At present, you'd notice that we've been stating on the last few calls that we want to raise the ratio toward private. For the last 2, 3 years we were heavily skewed toward government. And so we made a conscious effort, and the last few orders we bagged have been in the private sector. So as it stands, government exposure in our order book is about 60%, which is good, and we're fine anywhere between 50% and 60% — 65% is okay. So on this ratio, we'd be happy if we can maintain something along these lines going forward. Bidding pipeline — we're bidding continuously every month, we do put in a lot of bids, both government and private.
Our business development team is out in the field constantly, hunting for private jobs. And we do — we're hopeful, as I mentioned in my speech, that we've set a target, since last year we fell short of our order booking goal by roughly INR 400 crores, INR 500 crores. So for this financial year we've adopted a more aggressive target of around a couple of thousand crores. We've already completed INR 1,200 crores, and another INR 800 crores is definitely a goal we have in mind before the year ends, and we're working on it, and I'm quite positive it will happen.
Alright, got it. Just one quick follow-up on that point. Are there any significant projects out there where we're currently positioned as the L1 bidder and waiting on the official award?
Nope. Right now, I don’t know of any.
All right, I understand. And turning to Prakash CHS — with the key approvals now in hand and the Bhoomi Pujan done — when should we expect the formal launch?
So the way we're handling it right now is that we're running what's called a close circle soft launch, or a prelaunch, which is typical for this segment. So November and December are dedicated to the prelaunch activities. And January is the month when we're aiming to bring it to market in full.
And what sort of sales reaction are we getting while we're still in the prelaunch stage?
Giving a number at this point feels quite preliminary, though the reaction so far has been favorable. That site is a big one—a redevelopment spanning 1 acre, which is uncommon in Santacruz West Off Juhu Tara Road. Typically, projects in that area involve just one story, meaning a single-tower redevelopment. In this case, we're working with a sizable plot. The ticket sizes also make for a highly premium offering. So things look good at present, but it's too soon to say anything about a figure.
Understood. Alright, understood. Sir, would you be able to give us an update on the Thane land parcel? Has anything moved forward, or has there been any word from the government side on this?
No. Up to this point, nothing meaningful has moved. You're also aware that the Maharashtra government itself is dealing with a fair amount of cash crunch, along with all these other issues. So that acquisition doesn't look like it will go through right away. Let's hope for the best and that things improve. And until that acquisition goes ahead, whatever efforts we're making to consolidate the land, that work is likewise in progress. But you know that finalizing the land deal takes its own sweet time to secure the right kind of deal. Otherwise, it's a very -- the price keeps coming in a certain way. So execution on the 25 acres is in progress. We hope to get it as soon as possible, but it's very difficult to give a timeline on this aspect. So probably at that level, for 1 year, we don't see any revenue recognition from any substantial movement of that kind on the Thane land. But we are continuously focusing. So if any positive development happens, we'll update all of you.
Alright. Got it. And just one final thing, sir — given how real estate bookings picked up in H1, how should we think about collections from here? And as construction moves forward across projects, should we expect collections to get meaningfully better?
Yes, yes, certainly. So there would be 2 — I mean, in our case, collections come from 2 formats, correct? First is sold inventory, and the second is unsold inventory, which we bring to the sale. As things stand now, from the Orchids standpoint, Orchids is basically at the seventh, eighth slab. We'll have construction-linked payments, tied both to slab work and to the finishing milestones. So that's where the majority of cash collections should come in. That said, Powai Tranquil Heights would also generate collections, because as you can see, we've sold roughly INR 75 crores worth of inventory and the total collection is only about INR 5 crores, INR 6 crores. So typically, at booking, around 20%, 25% gets collected. So that too will come in during Q2. And Onyx would be prelaunch. So it will basically be 10% of the booking amount. So as an estimate, I think we'd be somewhere in the range of roughly INR 40 crores to INR 50 crores of collection quarter-on-quarter going forward.
<<operator_script>> Our following question is from <<inaudible>>.
Nice work on the better execution this quarter. I’ve got a few questions about the EPC business and the real estate growth strategy. First, our EPC order book is strong at about INR 3,400 crores, and roughly 63% of that is government projects. I’d like to understand how the new orders stack up against our current projects on margins and payment terms. Are we seeing better overall quality in the order book?
No, I'd put it this way: I wouldn't claim we're expecting any dramatic margin gains or changes to payment terms, since most of these terms are standard. What I would say is that we've held firm to our focus on low-risk clients — better clients, ones whose likelihood of honoring the terms is much higher. Broadly speaking, the profit percentage and the paper terms are pretty much unchanged, but what really determines actual profit is how things play out across the contract period. So overall, client quality matters far more than what's written on paper. And on that front, I'd say we've been quite selective. We've also been fortunate to land a strong client like Qualcomm this year, along with SBI and good brands that won't hesitate to pay on time.
Alright, alright. Now turning to real estate — with 40 years of EPC experience behind us and solid construction capabilities in-house, does that hand us an edge when we go after redevelopment projects in Mumbai and Pune? And on top of that, does it let us push for better terms or reach stronger profitability at the project level than traditional developers do?
Yes. Yes, it does. I mean, because we're both the EPC and the real estate player, so definitely, as you mentioned, the redevelopment projects we're getting — the people there are glad to see what we can execute. We're able to show them plenty of projects we've completed, not just for ourselves, but for other companies and the government sector too. So that definitely helps shift how they see us — as a quality builder. And on the margin side, of course, if we're the contractor ourselves, then we get the contracting margin as well as the real estate margin of the project.
Right, right, right. I just wanted to understand how we intend to grow this business while keeping capital needs fairly low. What are the main return metrics we look at before we take on a new project?
So again, we've consistently described ourselves as being in a glorified EPC role when it comes to the real estate side of our business. We've therefore made it very clear that capital — equity or debt — won't be deployed by us toward buying land. What we'll pursue is joint ventures. What we'll pursue is redevelopment, where the land is already available. And our approach has also been — even now, with higher FSI in most locations — that in practice, even when base FSI land can be secured through a joint venture or redevelopment structure, premiums and TDR costs frequently have to be spent upfront before a project can be launched. So I'd regard these, in a sense, as land investments still. And where that isn't being provided by the landowner under our JV agreement, we'd then seek another partner at the project level in most cases — an equity-level, project-level partner — who would help fund these. And we'd direct our equity, our expertise, our bandwidth and time toward sales — toward the product we'd consider for designing, launching, marketing and sales, using our brand effectively, using our design and real estate expertise effectively, and then proceeding to contracting and construction.
That's the area where we're aiming to put our strongest effort. So in that direction, our capital will also be deployed to the fullest extent.
Understood. Understood. Understood, sir. And then finally, when we consider the business as a whole, we have a solid EPC order book, execution momentum that is getting better, and encouraging traction in the real estate segment, correct? I simply wanted to get a sense of how management views Vascon's growth trajectory across the coming 2 or 3 years? Which of the businesses do we expect to serve as the main growth driver? And in what way should we think about the company's overall revenue growth and profitability as these businesses scale up?
Yes. So look, on the EPC scale-up — I mean, roughly 5 or 6 years back, we sat at the bottom on both EPC and real estate, with both generating very low revenues, far below the bare minimum required even to cover our overheads. Across the last 4 or 5 years, EPC has turned that around, and we're now near INR 1,000 crores. Even though we stayed flat at INR 1,000 crores these past couple of years, I think that breather was necessary, since we had grown rather quickly from INR 300 crores up to INR 1,000 crores. And going forward now, we're eyeing 15% to 20% year-on-year growth over the coming 3 or 4 years. It's a steady-state kind of situation in which our bank guarantee limits, our execution capabilities, all of it grows organically year-on-year, and we'll aim to grow at about 20%. Turning to real estate, the growth we expect over the next 4 or 5 years would be considerably higher in percentage terms. I think we've already mentioned it in the speech — Raveesh has joined us, and Raveesh has taken 6 months to fully grasp the capabilities of the firm.
He's actually now established a goal for the company to hit roughly INR 1,200 crores to INR 1,500 crores in sales by FY '30, '31. So we're allowing ourselves a 4-, 5-year window for growth in which, starting from where we are now — under INR 200 crores of sales last year — we aim to expand 5x across the coming 5 years. And the main reason is, naturally, that we've been performing far beneath our potential as things stand; INR 100 crores, INR 200 crores isn't a figure that matches Vascon's credibility. And so certainly, on that front, the year-on-year growth percentage over the next 5 years is going to be considerably higher than EPC.
<<operator_script>> Our following question is from <<inaudible>>, an individual investor.
Nice results. My question concerns the ESOPs. The company has granted a sizable quantity of ESOPs lately. Could management explain the reasoning behind these grants and what they are meant to achieve?
The goal behind it is precisely the same. Generally speaking, ESOPs exist to retain senior staff. Over roughly the last 15 years, the company has put this instrument to good use. We tend to roll out the scheme about once every 4 to 5 years. That has helped make sure senior staff stay on, even when the company is in a difficult stretch and we cannot hand out the usual increments each year and year-on-year — just like, I mean, as you can see, real estate right now is in a phase where we need growth across a 4, 5-year window. And we may not be in a position to keep awarding annual increments at very high levels in order to hold on to talent. So the ESOP gives a longer term — it is a retention instrument with a longer horizon, where what senior management does ties directly to the share price in the end, which is what all of us are here for. And — so I mean, it helps — we have seen before that it does help. We succeeded in keeping most of our senior team across the last 15 years; barely 5% to 10% would have departed.
The remaining ones are with the company. So we view this as a pretty effective tool for maintaining stability at the top of the firm.
Alright. And could you share what revenue guidance the company has set for FY '27? Also, what margins does the company expect for that year?
These are forward-looking figures, so I want to make clear they're only estimates. We're aiming for roughly 5% to 10% improvement over last year on the top line this year, since real estate will hopefully wrap up a project or 2, and EPC should equal or beat last year's results. So overall, we ought to top last year's top line by around 10%. On the bottom line, last year included a one-off sale with Hyatt, and that won't recur this year. No one-off items are expected this year. So any profit we show would be organic profit from operations. In EPC, we've recorded about 10% in EBITDA across the first 2 quarters. That should edge up marginally, as the next 2 quarters look stronger on the top line. In Q3 and Q4, we'd be running 30% above the first 2 quarters. And naturally, profit, PBT, EBITDA — all of it would rise by a percentage point or so. In real estate, our margins generally run double those of EPC, but those will show up in the results.
Speculating on what that exact figure will look like by year-end would be really difficult. It hinges on which project wraps up and which revenue we end up recognizing.
Our next question is from <<inaudible>>, an individual investor.
To start, congratulations on the impressive results and the very strong order book. My first question concerns the recent cancellation of our INR 131 crore Reliance Industries order for the Jamnagar project. Could you help us understand what caused that cancellation? Was it something specific to that project, perhaps tied to commercial considerations or something along those lines?
Yes, I believe I covered this on the last call as well. So they did give us a job in Jamnagar, and right after the award we had nearly begun mobilizing. But after that point, they made a significant change to the design of the entire construction methodology, which amounted to altering the contract terms themselves. As a result, the price we had quoted was neither sustainable nor valid. So we raised the matter with them, and then by mutual agreement it was more or less decided that, in the best interest of both sides, going for a retender was preferable, and that begins with canceling the old order. So this worked in our favor rather than trying to execute an old order that had become skewed incorrectly owing to the shift in construction methodology.
All right, understood. So, as we can see, construction hasn't begun yet, correct? So should we expect — I mean, should we assume there won't be any material impact on FY '27 revenue or profitability?
It wasn’t merely started — it was canceled. So there’s no material impact at all, nothing, no investment, nothing has been done, apart from some 1, 2 manpower; nothing has been done.
Nothing at all. As far as we’re concerned, that story has ended.
We’ve already announced the cancellation in the exchange as well.
Understood. So, are we currently pursuing or putting in bids for EPC opportunities within the data center segment?
Yes, that’s correct.
Ladies and gentlemen, since nobody else has a question, that brings the Q&A portion to a close. At this point I'll turn the conference over to Dr. Santosh Sundararajan, who will offer closing remarks.
Thank you all for joining and for the thoughtful questions you raised. Looking forward, we will keep concentrating on tighter execution, staying disciplined with our finances, and seizing growth chances in both EPC and real estate. Our commitment stands to produce sustainable expansion and build long-term worth for our stakeholders. Before we wrap up, I want to extend, on behalf of the whole Vascon Engineers team, warm Diwali wishes and a prosperous New Year to each of you. May this festive period deliver joy, sound health and achievement to all of you. Should you have any additional questions or need information, please don't hesitate to contact our Investor Relations partner, Stellar IR Advisors. Many thanks again for your ongoing confidence and backing. We anticipate connecting with you over the upcoming quarters. Have a wonderful day.
That brings our Vascon Engineers Limited call to a close. We appreciate everyone taking the time to join us. You’re welcome to disconnect your lines now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Vascon Engineers Limited transcript - plus 133,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Vascon Engineers Limited earnings transcripts and 133,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.