B2Gold Corp. (BTO) Earnings Call Transcript
November 6, 2025
Earnings Call Speaker Segments
We appreciate everyone joining us. I'm the conference operator. This is B2Gold's conference call covering the financial results for the third quarter of 2025. Please note that everyone is in listen-only mode and that this call is being recorded. Following the presentation, analysts will have a chance to pose questions. If you'd like to enter the question queue, press * followed by 1 on your phone's keypad. If you require help at any point during this call, you can alert an operator by pressing star and then zero. At this time, I'll hand the conference over to Clive Johnson, B2Gold's President and CEO. Please proceed.
Thank you, operator. Good morning, good afternoon, or good evening to everyone. I appreciate you being on the call. Our purpose today is to discuss the financial results for the third quarter of 2025. It was a robust quarter both operationally and financially at the Fekola, Masbate, and Otjikoto mines. On the production side, all three exceeded expectations in the third quarter, which led to cash operating costs per ounce coming in below what we had anticipated. On October 2 of this year, we announced that commercial production had been achieved at our newly constructed Goose Mine. That milestone was reached a mere three months following the inaugural gold. We anticipate many years of successful operations in Nunavut, working closely with our partners at the Kitikmeot Inuit Association. Goose's third quarter production was affected by the crushing capacity shortfall previously disclosed as well as a temporary delay in accessing higher grade Umwelt underground. We are now in the higher grade. To ensure a consistent feed of crushed ores to the mill, the company has implemented supplemental mobile crushing capacity. Permanent modifications are in progress and are expected to be implemented in 2026. Continuing to use the mobile crusher will help us operate at higher throughput until those modifications are implemented.
By year-end, we anticipate reaching design capacity of 4,000 tons per day. Mining underground at the Umwelt deposit began in late October 2025, and over the next few years it will contribute strongly as high-grade ore at Goose. In Nunavut, B2Gold announced an improved construction decision on the Antelope Underground Deposit. Output from Antelope is meaningful for raising gold production at the Otjikoto mine. We're leveraging the low-cost platform and extending the mine's life into the 2030s. With this strong gold price environment, B2Gold is well positioned to capitalize, with annual gold production of approximately 1 million ounces this year and gold capital spending at Goose now complete. The company is set up well to deliver significant shareholder value over the coming years. Before I turn it over to Mike for more financial detail, I just want to talk a little bit about the political situation in Mali. We've had some news come out that I think are, hearse, multiple headlines from some of the media talking about that it's imminent that a terrorist group organization is going to take over Bamako in the country of Mali. We think that is completely erroneous and is a great exaggeration of the situation.
Yes, fuel has presented some difficulties, especially in Bamako, but we keep operating the mine just as we have for a great many years, and no mining has been lost because of any political turmoil or situation connected to it. The mine is still running smoothly. We sit 500 kilometers away from Bamako. When we assess the situation, the government continues to hold popular backing among the population. In their eyes, those organizations cutting fuel supplies to Bamako are outsiders. Based on our understanding and the intelligence we have received, this is not a fight belonging to the people of Mali. Operations are continuing. It is encouraging to see backing from other governments, the United States and others. The U.S. stepped forward and issued support for the Mali military, stating they look forward to closer collaboration and to working together on intelligence. No Western company wishes to see Mali fall into other hands. Considerable international support is building. We feel very confident about our capacity to keep producing in Mali and to work very closely with the Mali government. We anticipate the permit for our regional mining and trucking work to the Fekola mill. It is imminent.
It wasn't long ago that we got the permit for underground operations at Fekola. We believe we're on schedule there. And again, none of the events currently unfolding in Mali have affected us. It's disappointing to see these irrational or inaccurate headlines circulating recently, among them ones that have damaged B2Gold's value. Given time, I believe we'll find that this is a situation that does not affect the mine. With that, I'll turn things over to Mike for a financial summary of the quarter.
Thanks, Clive. As Clive mentioned, from a financial standpoint, we had a strong quarter. I mean, GAAP earnings came in at one cent per share, though several non-cash derivative market adjustments affected them. Once those one-time items are adjusted for, the company's earnings per share stood at $0.14 of adjusted earnings. Clearly, you can see the benefit from the strong average gold sales price we saw during the quarter, which continues now. The company recorded revenue of approximately $783 million in Q3. That included $144 million related to delivery of just over 66,000 ounces under the company's gold prepay obligations. By the end of October, we had made another delivery into those obligations. We have now delivered into one-third of what we owe there. That leaves us just under 200,000 ounces that we will need to deliver into by the end of June. We're in good shape there. Operating cash flows totaled $171 million in the third quarter and/or before working capital adjustments, $180 million, which is another strong result. It highlights the continuing cash-generating potential of our assets and the strong gold price environment. On the balance sheet side, we continue to remain in a strong financial position with cash and cash equivalents of $367 million at the end of the quarter.
Over the course of the quarter, we drew down — and as we said last time, we drew down $200 million on the revolver. That simply assisted us in managing through certain working capital timing differences that we have, particularly as we deliver into the prepays. We will keep doing that. Given these gold prices, we anticipate repaying some or all of it by year-end. I would say that overall, we retain excellent financial flexibility to deliver to the prepays, complete our other sustaining and growth initiatives, continue to fund the health, the exploration programs that we have, and I think continue to return capital under our share buyback plan. I think that is the summary I want to touch on in the financial sections, and with that, I will turn it over to Bill for an operation project update.
Okay, thank you, Mike. Now that Goose has two commercial production lines running, the emphasis shifts toward stable operations and reliable output at nameplate capacity. The cause of the crushing problems that hurt performance in the early part of Q3 has been pinpointed, and we've put a temporary solution in place by using the mobile crushing unit. Engineering and design work is underway for permanent upgrades to the primary crusher and secondary grinding circuits as well as installation of surge bin capacity, and a finalized study along with a remediation plan is due in December 2025. The mobile crusher should keep being used until those modifications are completed. Because of the crushing capacity shortfall and temporary delays in reaching higher-grade ore at Umwelt underground, B2Gold has lowered its 2025 gold production guidance for the Goose Mine to a range of 50,000 to 80,000 ounces. Underground mining at the Umwelt deposit began in late October 2025, and the company anticipates underground operations will ramp up rapidly over the final months of 2025, positioning the operation well for its first full operating year in 2026. The company reaffirms the near-term and long-term gold production estimates for the Goose Mine, including a forecast of roughly 250,000 ounces of gold in 2026 and roughly 330,000 ounces of gold in 2027, plus average annual gold production of approximately 300,000 ounces across the initial full six years of operation, based only on existing mineral resources.
For the opening nine months of 2025, notable construction work included finishing the mining at Echo Pit and commissioning that pit as a TSF, which involved building the winter deposition infrastructure. Mining at the Umwelt open pit got underway ahead of schedule, and full ramp-up was reached in the second quarter of 2025. Work carried on at the Umwelt underground, including development of fresh air arrays one and two to support stope ore production in the fourth quarter of 2025. Also underway: continued dewatering at the future Llama Pit site, commissioning of three large glycol heating systems, excavation and foundation construction for the camp's Arctic corridor, and construction of a mechanically stabilized earth wall for the reclaim tunnel. In Mali, the site kept up its strong 2025 performance, again beating gold production expectations in the third quarter. Cash costs per ounce also came in lower than expected. Notably, Fekola Underground is likewise outperforming expectations, even though operations there began earlier in Q3, on July 30, 2025. At Masbate, the operation continues to do well, with a world-class safety record. Mine throughput has substantially exceeded expectations in 2025, and we expect steady production in the fourth quarter. At Otjikoto, open pit and underground mining went very well in the third quarter, with production also coming in above expectations.
In Q3, the company gave the go-ahead on a development decision for the Antelope deposit. We've also finished additional optimization work, and we think pre-production capital costs can come down to $105 million from the $129 million established in the PA. Output from Antelope could lift gold production at the Otjikoto mine to roughly 110,000 ounces across the life of the Antelope Underground mine. With that said, I'll hand things back to Clive to introduce the Q&A.
Appreciate that, Bill. Operator, let's open it up for questions.
Thanks. We're moving into the analyst Q&A portion now. If you'd like to ask a question, press star followed by one on your phone's keypad. A tone will confirm that your request has been received. Should you be on a speakerphone, lift the handset first before you press any keys. To take back your question, press * and then 2. Our first question is from Ovais Habib at Scotiabank. Go ahead, please.
Thanks, Operator. Morning, Clive and the B2Gold team. Nice quarter — congratulations. I've got a few questions, beginning with Fekola. Fekola Underground looks like it's ramping up quite nicely. What grades do you expect as we head into 2026? And do you have a target in mind for ore tons mined and the grade at Fekola Underground?
Bill?, I can’t give you the precise grade, though my recollection is that we were aiming for roughly 4.5 grams. That’s 4.5 grams, with throughput of around 1,500 tons per day. You can work out the arithmetic on what that comes to. It’s roughly along those lines. Keep in mind that these represent replacement ounces of low grade.
Bill, thanks for that. Bill, regarding how quickly things are moving at Fekola Underground and the pace of development there, is everything on track, and do you feel good about what you'll be producing in 2026?
Yes, certainly. Byrnecut is the contractor — the very same one we've worked with in Namibia. We have a really solid relationship with them. In fact, development has either matched or run ahead of plan essentially from start to finish.
Thanks. Let me move swiftly to the Fekola regional permit — I understand we're anticipating that permit by the close of 2025. On the question of pre-development work or anything your team can undertake ahead of receiving it, or is it essentially the case that you're fully prepared the moment the permit arrives — you'd begin pre-stripping right away and then start hauling ore?
Actually, we are doing some pre-stripping at this point. Approval has been granted for us to go out and handle some clearing and grubbing. All of that work is underway. Obviously, we're bringing people on board and securing the equipment. Honestly, we are placing a modest amount of capital at risk, based on everything we've been told that this permit is on its way.
Understood — thanks. Turning quickly to Goose: the underground grade appears to be improving as we head into Q4. Are development rates rising too? This is a question that's also arisen at other mining operations. Do you currently have the appropriate personnel and equipment in place?
We definitely have the right people in place. Keep in mind that this is remote mining—remote stope mining. That makes it a specialized skill. And we do have the right people on site at this point. We see it coming up as planned.
Alright. Appreciate it. That's all I've got, everyone. Thank you.
Appreciate it, Ovais.
Anita Soni from CIBC World Markets has the next question — go right ahead.
Hello, good morning, Clive and Bill. I just wanted to ask a few questions on Goose. I wanted to understand the key drivers of the cost increase. Obviously, sorry, into the fourth quarter. Obviously, there are lower tons that are going to be pushed, and that's going to impact the numbers. How do you expect that to evolve into next year? I mean, you maintain the production guide for next year. I'm just trying to get an understanding on what we should be thinking about on costs. Are they going to be as indicated previously, or will there be some impact?
Yes, this is Mike. Anita, just on the cost side: for the fourth quarter, our guidance moved up, and per-ounce costs are somewhat higher, as you noted, than what we had previously. The production costs that had been budgeted for Q4 were lost there, but we brought the ounce guidance down to 45,000 ounces simply because we got into the higher-grade stopes somewhat later and because of total production for the quarter. I don't believe those reflect where costs will go in the future. It's simply a result of the ongoing ramp-up. Regarding costs looking ahead, the 250,000 that Bill mentioned and beyond that into the later years of mine life — we have no changes to those at present. We're working on next year's budget. And also an updated, sort of, upside mine case that we're examining. I think we have nothing new to release on those right now. The key point certainly is that these Q4 ounces are ramp-up ounces. Costs tied to them shouldn't be extrapolated into anything in the future. We've aimed to be fairly conservative in that guidance. We had to re-guide Goose down just for the fourth quarter.
In that guidance, we've aimed to stay conservative and give her room to reach what the queue requires.
Alright. Bill, sorry — could you give me some sense of what's really happening with the holdup? Accessing Umwelt? What caused the delay?
What caused the hold-up was a shortage of equipment parts for Sandvik, and after that, operators to run it. It's one of those situations where, in Canada, you figure these things arrive on a very fixed timetable, and that simply didn't occur. We've fixed the situation. The people are on site at this point, and we have the right drilling media. It's been resolved.
Okay. Sounds good. Thanks. That wraps up what I wanted to ask.
Appreciate it.
Don DeMarco from National Bank has the next question. Go ahead, please.
Thanks, Operator. Morning, Clive and team. Appreciate you taking my question. Perhaps to start at Goose — you're weighing a few different options for the crushing, for optimizing the crushing. Among the options you're considering, we look forward to the results of your report and so on. What's the potential magnitude of that range of solutions, just to move away from that mobile crushing? The cancer of the CapEx and stuff like that.
As we discussed earlier — remember, the first one back when we were in Denver was really the idea of a fairly minor adjustment. Clearly, we've fallen short on that. So we have an outside consultant coming in who will give us a report in December. I really don't want to, once again, tell you in Denver and then have to reverse course. It's still a small magnitude relative to fixing it and achieving a throughput.
All right. I suppose whatever conclusion you reach — I mean, you’ve got the CLIF event ahead, and choices need to be made so things line up with that, and you’d have people in place on the ground as required, I’d think.
You've got that right.
All right, so regarding the regional permits in Mali, we're expecting to receive them by year-end. The schedule for securing those permits has been a bit fluid. What's driving that? I mean, you have solid communication with the government. You've visited there several times. Is the government prioritizing something different? From where you sit, why has the timeline been pushed back repeatedly?
My sense is that we're caught up in Mali's bureaucratic process as we navigate through the different tiers of approval. As we understand it most recently, it sits right at the final stage of approval, and we expect that for sure before the year is out and perhaps very soon.
All right, we’re looking forward to it. Yeah, I saw that report as well — once you have that and the rest of the prep work done, you’ll begin stripping immediately, and we’re eager to see all of it. Output reflected in next year’s guidance. That’s everything from me. Thanks.
Bill mentioned that some preliminary work has already gotten underway at the site. Thank you, Don.
We’ll take questions from analysts again now—just press star and then 1. Our next question is from Kerry McCreary at Canaccord Genuity. Go ahead, please.
Morning, everyone. This one might be for Mike. During the last quarter you pulled $200 million, and I noticed that $50 million has been repaid. As you work through those prepaid payments, do you expect you'll need to tap the credit facility?
I believe you'll see that play out. As you mentioned, if gold prices hold at the levels we're seeing now through the fourth quarter, then our expectation is that we'll have repaid a substantial portion of that line — possibly the whole thing — by the time the year ends. I think you'll see us draw on it a bit as we go through Q1 and Q2, purely to manage timing, the prepaid deliveries, and the fact that we've already received the cash for those. Once that's done, the line gets repaid, and it's off to the races. My expectation is we'll treat it as a temporary interquarter tool, with fairly small draws. Going forward, we're in those cash flow harvest years.
Regarding capital expenditures at Goose, Q3 spending came in somewhat above our forecast, perhaps reflecting normal seasonal patterns in Nunavut. Could you offer any guidance on what growth capital at Goose we should anticipate for Q4?
If you look at the budget we published for the second half, I'd say it came to $176 million. We didn't provide a breakdown, though the weighting leaned heavily toward Q3. For Q3 the budget was approximately $130 million, and then $45 million to $46 million for Q4. In Q3, CapEx as recorded in the financials was $157 million. That figure includes a number of site general costs and commissioning costs that we wound up capitalizing, purely because of how the ramp-up timing fell out — those had been budgeted as operating costs. We ended up capitalizing them, so they ran through the CapEx line. On a like-for-like basis, the hard assets in the budget came in at $120 million, against a budget of $131 million plus those site G&A costs. On the capital side, on the pure CapEx side, we set a budget. We're essentially right on budget.
During Q4, we increased Goose's capital budget by $15 million—it moved from $45 million up to $60 million. That's really the key driver. We still have a fair number of people onsite who are being phased out gradually, but a few more remain there than anticipated, for a bit longer. We put that $15 million in. For Q3, thinking about it in terms of capital and operating costs, we came in basically on budget. It's just a matter of the split and how things landed. We capitalized certain site G&A and some commissioning costs we hadn't expected—that was simply costs shifting between two budget areas. For Q4, include $15 million of CapEx for the quarter. It rises from $45 million to $60 million.
All right, that's useful. Thank you, Mike.
That brings the question-and-answer portion to an end. I'd now like to hand the conference back to Clive Johnson, who may offer some closing remarks. Please go ahead.
All right. Thank you, Operator. As we noted at the start, it was a solid quarter both operationally and on the financial side. We're eager to keep moving forward with the ramp-up at Goose and to sustain the strong results we've been delivering at our other operations. Should any follow-up questions come up, please don't hesitate to contact Michael McDonald, and he'll connect you with the appropriate person to get them answered. We appreciate your joining us today.
That concludes the conference call for today. Your lines can now be disconnected. We appreciate your participation, and we hope you have a pleasant day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete B2Gold Corp. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to B2Gold Corp. earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.