Thanks for holding. Chuck here, the conference operator. Welcome to the Fortis Inc. Second Quarter 2026 Results Conference Call. Just a reminder that everyone is in a listen-only mode and this call is being recorded. Following the presentation, we'll have a chance for questions. To get into the question queue, press star, then one on your telephone keypad. If you need help during the call, you can signal an operator by pressing star, then zero. At this point I'd like to hand the conference over to Ms. Stephanie Amaimo, Vice President, Investor Relations. Please go ahead, Ms. Amaimo.
Thanks, Chuck, and good morning to all of you. I'd like to welcome you to the conference call covering Fortis's results for the second quarter of 2026. Alongside me are David Hutchens, our President and CEO; Jocelyn Perry, Executive VP and CFO; additional members of the senior management team; and the CEOs of certain subsidiaries. Before we get started on today's call, please be reminded that forward-looking information will be part of the discussion, and it carries the cautionary statement found in the supporting slideshow. The actual results may differ materially from the forecast projections that today's forward-looking information contains. Where non-GAAP financial measures appear in our prepared remarks, a reconciliation to the related US GAAP financial measures is provided in our second quarter 2026 MD&A. As well, all financial information we reference is in Canadian dollars unless otherwise specified. With that, David, over to you.
Thank you, and good morning to all of you. In the first six months of the year, our utilities kept delivering safe, dependable service as we moved our regulated growth strategy forward. From January through June, we put $2.7 billion into our systems and posted second-quarter earnings per share of 78 cents. More recently, we reached a milestone tied to a major opportunity that goes beyond our five-year capital plan: we received an Order in Council backing the expansion of the Tilbury LNG facility in British Columbia. We also issued our 2026 Sustainability Report today, which highlights the progress we've made in decarbonizing our energy mix, including a 38% cut in Scope 1 greenhouse gas emissions through 2025 versus 2019 levels. With close to half of our yearly capital plan invested by the end of June and our major capital projects performing well, we're still on track to invest $5.6 billion in 2026. At TEP in June, the second Roadrunner Reserve battery storage project went into service. This 200 MW energy storage system helps integrate renewables into the grid and can store 800 MWh of energy — sufficient to serve 42,000 homes for 4 hours when run at full capacity. Since our capital plan remains on track, we still anticipate average annual rate base growth of 7% through 2030.
Just last week, FortisBC got an Order in Council from the Province of British Columbia that approves a bigger Phase 1B expansion at its Tilbury LNG facility, which permits roughly $2 billion of total investment in regulated rate base. At present we have about $350 million within our existing five-year plan. That OIC also supplies the approvals needed to put in place an equity partnership with the Musqueam Indian Band, and it contains regulatory mechanisms designed to smooth cost recovery during the project's early years. The Tilbury 1B expansion backs LNG marine fueling services and encourages jobs and economic growth across the province. The project establishes the Port of Vancouver as a leading hub for LNG marine fueling and aids the shift toward lower-emission marine fuels. This is an exciting opportunity, and FortisBC will now move ahead to develop and refine project cost estimates, which are going to be reflected in our next five-year capital plan, expected to come out alongside our third quarter results. Although the project is still subject to certain regulatory approvals and permitting requirements, construction might begin as early as mid-2027 and could be in service as early as 2031. Regarding other opportunities beyond the plan, our teams keep making steady progress.
At ITC, the MISO long-range transmission projects tied to Tranche 2.1 are moving forward. As we've said before, ITC anticipates $3.3 to $3.8 billion US dollars of investment past 2030 for projects already awarded that aren't open to competitive bidding. When it comes to the Iowa Tranche 2.1 projects that go through a competitive process, ITC has put in bids on two opportunities, and MISO is expected to make those awards in the fourth quarter. At TEP, talks are ongoing with a data center customer over an incremental 300 MW of capacity to support a potential build-out of 600 MW at the first site. TEP is likewise in active negotiations regarding additional capacity at a second site, in the range of 500 to 700 MW, and keeps engaging with other large customers on further growth opportunities. Should agreements be finalized for these subsequent phases, we estimate new generation investment in the range of $1.5 to $2 billion US dollars would be needed. In Arizona, TEP and UNS Electric expect to submit new integrated resource plans to the ACC in the fall. The IRPs will support rising energy needs while accounting for clean, reliable, and affordable energy solutions. The IRP will feature a high-growth scenario that evaluates the impacts of potential incremental data center load beyond the 300 MW currently approved, along with a clean energy build-out scenario.
At our utilities, the priority for capital investment stays on what operations actually require and how customer bills are affected. As we mentioned last quarter, ITC and UNS both show clearly how load growth and cost-effective capital projects can deliver benefits to customers. Adding to that discussion, we also expect continued expansion of the LNG markets to deliver rate benefits for customers in British Columbia. To start with, sales of LNG into the expanding marine fueling market tied to our current Tilbury 1A facility have given customers a rate benefit of roughly 1.5% since 2024. The next expansion, FortisBC's Tilbury 1B facility, is expected to build on that rate benefit. In addition, greater demand served through the Eagle Mountain Pipeline project will raise utilization of FortisBC's gas system and, once it is complete and in service, is expected to deliver a rate benefit of approximately 1.5%. Taken together, through operational efficiency, disciplined capital planning, and innovation, the Fortis utilities remain laser-focused on finding better ways to cut costs and support customer affordability. Our dividend remains a core component of our investment thesis. We have shown that we can grow the dividend responsibly, having raised it for the past 52 consecutive years while keeping a disciplined approach to balance sheet strength.
As we look forward, our confidence stays firm in the guidance of 4% to 6% yearly dividend growth through 2030, backed by our strategy of regulated growth. At this point, I'll hand the call to Jocelyn so she can give an update on the financial results for our second quarter.
Thanks, David, and good morning to everyone. For the quarter, net earnings came in at $396 million, or 78 cents per common share — that's up 2 cents from the second quarter of last year. At ITC, EPS rose 2 cents, mainly from ongoing capital investment and the associated growth in rate base, partly offset by higher finance costs and stock-based compensation expense. UNS added a 2-cent increase, driven by greater retail electricity sales, including the effect of warmer weather. That gain was tempered by the timing of operating costs, along with regulatory lag tied to rate base growth that isn't yet reflected in customer rates. EPS at our Western Canadian utilities was up 1 cent, largely on capital investment. The corporate and other segment reflects unrealized losses on foreign exchange contracts, higher finance costs, and lower earnings from the disposition of FortisBelize in the fourth quarter of 2025, partly offset by the timing of income tax recoveries. Although it isn't shown on the slide, Central Hudson's results were consistent with the second quarter of 2025, as rate base growth was offset by the timing of quarterly revenue. Earnings for our other electric segment were likewise comparable quarter-over-quarter, as earnings growth in that segment was offset by the impact of the FortisTCI disposition completed in the third quarter of last year.
Currency movements cost us 1 cent this quarter, and EPS took a 1-cent hit from more weighted average shares issued through a dividend reinvestment plan. Looking at the year to date, earnings came to $897 million, or $1.76 per common share. The same drivers we covered for the quarter largely explain the year-to-date results, plus a handful of other items worth flagging at Central Hudson and UNS Energy. Over the six-month stretch, Central Hudson gained 3 cents, mostly on rate base growth and the timing of operating costs. At UNS, EPS fell 3 cents, as stronger retail sales were offset by weaker wholesale margins, the timing of operating costs, and regulatory lag on rate base growth that isn't yet reflected in rates. During the first half of 2026, our utilities issued $2.1 billion of long-term debt, and our funding plan is still on track. As we've said before, we expect to fund our capital plan mainly through cash from operations, utility debt, and our dividend reinvestment plan. In May, S&P reaffirmed our A- issuer and BBB+ unsecured debt credit ratings along with a stable outlook, and Fitch likewise reaffirmed the corporation's BBB+ issuer and unsecured debt credit ratings and stable outlook.
All told, our liquidity and how we intend to fund ourselves underpin our investment-grade credit ratings. As Dave noted, we anticipate putting out our fresh five-year capital plan during the earnings call for the third quarter, and we'll tackle our updated funding plan then. Turning to regulation, the TEP general rate application is still moving forward. In the quarter, the hearings wrapped up and the administrative law judge granted an extension to the procedural schedule, meaning a final ruling on the rate case should come out by November 17th. That's all from me. I'll hand the call back to David now.
Thanks, Jocelyn. To wrap up, we've turned in a solid first half and kept our attention squarely on the things that count most: running our utilities in a safe, dependable, and affordable way. Our execution focus has two clear parts — the annual capital plan is on schedule, and we're moving ahead on opportunities that go above and beyond that plan. With a disciplined strategy and a diversified regulated portfolio behind us, we're still confident in our capacity to meet the rate base and dividend growth outlook through 2030. That's all from me. I'll hand the call back to Stephanie now.
Appreciate that, David. That brings the presentation to a close. Right now, we'd like to begin the call and take questions coming in from the investment community.
Thanks. At this point we'll move into the question-and-answer portion. If you'd like to be placed in the queue to ask a question, press star followed by one on your phone. A tone will sound to confirm your request. Should you be on a speakerphone, lift the handset first before you press any keys. If you want to take your question back, press star followed by two. Today's first question comes from Maurice Choy of RBC Capital Markets. Go ahead, please.
Thank you, and good morning to all of you. I'd say it's probably fitting for BC to be front and center here. So perhaps as my opening question, could you walk us through what comes next for Tilbury 1B, and likewise give us an update on the larger Tilbury Phase 2? I appreciate that, and I'd assume Phase 2 carries some rate advantages for customers as well, on top of all the others.
Thanks, Maurice. Roger has been waiting for this one, so I’ll hand it straight to Roger, FortisBC’s CEO. Roger?
Thanks, David. And thanks for the question, Maurice. I might also try to get ahead of a few of the other questions, beginning with Tilbury 1B. The project as a whole, together with the Order in Council from the government, has essentially three parts. There's the marine jetty, the liquefaction expansion, and a 230 kV power line that will supply power for the electric-drive liquefaction. Those three parts fall under the OIC. As for next steps, we're continuing to assess and design plans to deal with the conditions that arose from the environmental assessment certificate the provincial and federal governments gave us in 2024, and after that to design the liquefaction and power requirements for the TLSE. That work will begin in earnest, and we're hoping to be in construction on Tilbury 1B at some point in 2027. We're also wrapping up agreements with the Musqueam regarding their equity investment. The percentage they might take is confidential at this stage, but we're working to finalize the limited partnership agreement that would let them make a direct equity investment in this project. For Tilbury 2, just as a reminder, Tilbury 2 has two components. The first is the Tilbury storage tank, which replaces one of the existing tanks at Tilbury that was built and commissioned in 1971, since that facility is essentially at end of life.
Regarding the Tilbury storage expansion—for which we secured BCUC approval during 2025—construction will begin once the EA is granted. There's no direct rate benefit attached to that project. Its main purpose is really resiliency, though with tank capacity rising to as much as 3 Bcf versus roughly 0.6 Bcf at the existing facility, we'll see some gas supply advantage, since we can manage summer-winter gas cost differentials and thereby broaden our gas supply capabilities on the system. Beyond that, however, it's essentially about resiliency against system disruption and peak weather events. Tilbury 2 also offers as much as 2.5 million tonnes per annum of liquefaction. That one is further out. Should it ultimately be built, it would be structured to deliver rate benefit, but it's too early to know what those rate benefits could be. I hope that addresses the questions.
Perhaps a brief follow-up: what's the timing on when those projects could get sanctioned?
Regarding the Tilbury 2 projects, we anticipate the EA later in the current year. We're in what I believe is the mandated 151-day review period, which will conclude at some point in Q4, after which it will go to cabinet. At that stage, cabinet has a 30-day window to approve the environmental assessment certificate. Should that schedule hold and the Environmental Assessment Office request no further process, a decision on Tilbury 2 — covering both the storage tank and the added liquefaction — ought to arrive later this fall.
Got it. To wrap up with Arizona, I guess there's still selective opposition to data centers here in the US, and I know you pointed to some rate benefits on one of your slides. At TEP, have you seen any recent shift in the way your customers come at negotiations — whether that's the pace, the terms, or anything along those lines?
There's clearly been some resistance to data centers around the US, for a range of reasons. One thing our industry hasn't told effectively enough, I'd say, is how these kinds of projects can benefit our customers on rates. That's the point we're working to communicate in Arizona and wherever else we can, just like everyone else, data center developers included, since the story really is a positive one. You can see it in our deck: that rate benefit for customers, and that's only from phase one of Project Blue. The customers themselves, meaning the data center customers, are quite focused on getting the design right, and they're plainly willing and able, and there have been numerous conversations and commitments, etc., at every level of government, be it federal, local, and with utilities and the data centers and hyperscalers too. All of us are fully aligned on ensuring no cost shift occurs and that the costs required to build and serve those customers aren't allocated onto the other customers.
Everyone agrees these data centers must pay for themselves and then provide extra. That is the source of it. The extra portion is what delivers the advantages we see, bringing down other customers' rates because those data center users, through their usage, share a genuinely substantial share of the system's total fixed costs. Our message is that all of us carry an identical message. Getting people to hear it is somewhat difficult.
That’s great. Thanks for that, and best of luck with it.
Appreciate that, Maurice.
We'll take our next question from Ben Pham at BMO. You have the floor.
Hello, and thank you. Good morning. You said you expect an update to the CapEx plan in the fall. I wonder if you could discuss whether there might be a chance to consider a longer horizon beyond the five-year plan, particularly given that the Tilbury expansion runs through 2031. You also have the ITC transmission opportunity, and on top of that, your backlog appears more visible than it was compared with last year.
Ben, clearly from a planning standpoint, quite a few of the things we undertake stretch past that five-year window. The integrated resource plans are a prime example, along with the LRTP projects — obviously, many items we examine over a longer horizon. Given that forecasts of that kind usually diverge and carry fairly wide error bars once you move beyond five years, it would genuinely be difficult to publish, say, a five-year capital plan — or one extending past five years — without attaching a whole bunch of caveats. We'd rather stay with — and I wouldn't call five years a short stretch by any means — but we recognize that's precisely why we aim to offer color on what's happening across our portfolio, over and above the plan discussion, and to split those into items we see in the coming five years, items we could essentially fold into the current five-year capital plan, and, more importantly, items that push that growth past the five-year plan. We try to provide color on that, yet laying out numbers that far ahead — I'm not sure it would prove all that beneficial.
All right, understood. Returning to the Tilbury expansion—have you had sufficient opportunity to consider what it means for the balance sheet, including the CapEx you factored in? I realize the First Nations component remains TBD, but across the range of scenarios you examined, does it include potentially considering an ATM?
Ben, it's Jocelyn here, and I appreciate the question. Tilbury is going to be folded into our broader review of the five-year plan. There's no question that this is placing helpful pressure on how much we are spending, but we need to nail down the timing for Tilbury specifically, along with when and how these investments will come into play. We will examine every funding option at our disposal, with the goal of keeping our credit metrics in check. That is an area we plan to dig into more deeply in the fall.
Understood — thanks.
Our following question comes from Mark Jarvi at CIBC Capital Markets. You have the floor.
Hello, and good morning to all of you. I realize we'll be receiving the CapEx update, but regarding the Tilbury project specifically, is there anything that hints at how the CapEx would be profiled? Would there be substantial sums prior to 2030, or does most of it arrive in the early 2030s?
We haven’t assembled that yet. Naturally, there’s a pattern to how CapEx gets spent, and on big projects it usually begins gradually and builds over time. As I said in the remarks, we could see this online as early as 2031. As we spend capital, remember we also get AFUDC on these projects as well. There’s still a whole lot of modeling that has to be done. Once we have that shape in there, we’ll let you know. That kind of goes to that prior question. The shape of capital matters too, not just the overall size of the capital plan.
Got it. In just the past two days or so, there's been some encouraging commentary from large load involving the Michigan LDCs, plus Alliant over in Iowa. What's your take — any fresh perspective on the ITC discussions with those local distribution companies about speeding up investments to support large loads in those areas?
Krista, would you like to take that one? She is clearly quite plugged into those discussions with our biggest customers — CMS, DTE, and Alliant, as it happens. Krista?
Morning, everyone. Our outlook is still quite bullish. We’re having genuinely constructive discussions with the big data centers. We’re collaborating closely with those customers you mentioned, since transmission obviously can take quite a while. We’re in active talks with them. Right now, everything we’ve made public is what we have, and we’re holding to that figure — roughly 8 GW of extra load in our queue. Naturally, that doesn’t guarantee all of it will materialize, but it truly sits in our pipeline. That part we haven’t finalized yet.
Would you say the bulk of that is loads seeking locations where they can tap into transmission and generation that's already there, or do you see some upgrades being needed, particularly with how quickly some of these customers want power?
Honestly, there isn't a hard-and-fast guideline when it comes to transmission. What we're observing is that a large load can run anywhere from $10 million up to $100 million, correct? And because of the point you just raised — speed to power — we're putting a lot of effort into steering them toward locations that require fewer upgrades, since those projects need to be energized within 2 years or less, and building a new line would obviously take far longer than that. So from where we sit, we're actively guiding them to spots where less upgrade work is needed, and that still gives us a benefit through rate relief for our customers.
All right, that's excellent. Thank you, everybody.
Michael Long from Barclays is up with our following question. The floor is yours.
Hi, thanks for taking my questions. Regarding the TEP rate case, the procedural schedule clearly shifted so that a decision comes after the November election. I'm just wondering how you're feeling about this in the rate case more broadly, coming out of the hearings that happened in May?
We're feeling good. I'll hand things over to Susan so she can offer some detail from Arizona. I think it's fair to say we definitely weren't surprised that the final decision on the TEP rate case got pushed back a bit because of the November elections. Susan, would you like to share some detail on where we stand?
Okay, good morning, and thank you for that question, Mike. As Dave said, we anticipate the judge will issue a recommended opinion and order quite soon. Since we just filed our briefings, I believe we're fairly close on many of the issues, especially when it comes to alignment with the staff, ACC staff. We differed on ROE, and in the filing we made recently, TEP decreased to 9.75, which means the increase we're now requesting is 10.2%. That reflects the effect of the ROE change. We're optimistic, I think, that the judge will incorporate the ARAM, the formula rate, and I believe opinions varied regarding what the deadband ought to be, but on the whole, I think the ARAM's design will probably end up looking much like what we received for UniSource gas. I think we'll have a clearer picture once the briefings, which have just been released, are reviewed, and then after the judge's recommended opinion and order, we expect a decision likely in November, with implementation occurring in December. I think we're coming quite close to wrapping things up so that it's finished by the end of the year.
Thanks. Staying with Arizona, you obviously mention the Project Blue data center and the chance to expand there — that $1.5 to $2 billion opportunity. I was just wondering whether you could say more about what else is in your pipeline in the state, where things stand with that opportunity, and anything you can share on that would be helpful.
Susan, over to you.
When you mention pipeline, I take it you mean the gas pipelines?
He’s referring to the pipeline of projects like Project Blue that we have, but what comes after those.
Absolutely. We still have a pipeline of 8 to 10 GW for data centers sitting in our queue, though the Hermosa Mine is also about to come online. Copper World likely falls toward the back end of the five-year plan we've laid out. Beyond that, we have additional manufacturing, and even certain current customers that are expanding. Growth in Tucson isn't solely about data centers. We're seeing a fairly broad range of opportunities.
Excellent. I appreciate your answering my questions. Once more,
If you'd like to ask something, press star followed by one. We'll take our next question from Eli Josien at J.P. Morgan Securities. You may proceed.
Morning, everyone. Perhaps staying on Arizona, I wanted to turn to politics for a moment. Clearly, the primary results came out only a few days back, so I was hoping to hear your perspective on them—did anything catch you off guard, and would that have any bearing on the regulatory approach you're taking across the state?
I'll handle that question, Susan. I still spend a great deal of time in Arizona, so I'm fairly current on the politics down there. I wouldn't describe it as a surprise. With three people competing for two seats in a primary, predicting how that vote will divide is difficult. From the standpoint of our regulatory strategy, it makes no difference to us. We'll also see how the general election plays out, but ultimately, this involves two of the five commissioners whose seats are up. Even if commissioners changed entirely, a full turnover in that body, there would still be three whom we have come to know and have built relationships with across the last couple of years, or for several years in the case of some commissioners. We do not alter our regulatory strategy because of an election. We collaborate with whichever regulators hold those positions and strive to advance sound, solid policy that lets us support what matters most to our customers. That does not shift from one election to the next.
Understood. I'm aware that Arizona has drawn plenty of commentary, but perhaps this final question about the IRP. We're all aware the filing deadline sits in October. Could you briefly restate the spectrum of possible results we might see emerge from that IRP, and how those results would shape the range of opportunities available to you in Arizona?
At this point, aside from the one scenario from the old IRP, we don’t truly have a set of outcomes yet — we’re genuinely awaiting what these results show. After that, naturally, we go through a whole variety of scenarios during this exercise. We select one as, say, the portfolio we recommend for filing with the commission, and clearly the remaining scenarios go in as well. Ultimately, that’s the point where we begin examining how that scenario shapes up, and whether it makes it through the Corporation Commission’s process. As we move through this exercise, we’ll be factoring in some of those investment opportunities and will begin communicating them at that stage. As of now, we haven’t put out all the scenarios and how they look, but they will be released, and it’s something people can review. It will be at a very high level — net present value revenue requirement for those portfolios — but it will show the investments required and which years they’re required in. For folks like you all on the call, it’ll supply some of the data to do a back of the envelope and see what would be required across those different time frames.
Excellent. I appreciate the added detail.
Absolutely.
That wraps up our Q&A portion. I'd now like to hand the conference back to Ms. Amaimo for any closing comments. Please go ahead.
Thanks, Chuck. That's all we have for now. Everyone, thank you for joining our conference call for the second quarter. If you need anything else, please reach out to Investor Relations, and have a great day.
That wraps up today's conference call. Feel free to disconnect your lines now. Thanks for joining us, and have a pleasant day.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Fortis Inc. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Fortis Inc. earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.