Ladies and gentlemen, good day and welcome to the PSP Projects Limited Q1 FY 2026 earnings conference call. As a reminder, all participants' lines will be in the listen-only mode, and there will be an opportunity for you to ask questions after the presentation concludes. Should you need assistance during the conference call, please signal an operator by pressing star then zero on a touch-tone phone. Please note that this conference is being recorded. I would now hand the conference over to Ms. Pooja Dhruve, Company Secretary, PSP Projects, for the cautionary statements. Thank you, and over to you, ma'am.
Thanks, and good evening to all of you. It's my pleasure to welcome everyone to the PSP Projects Limited earnings call for analysts and institutional investors, where we'll discuss the financial results of quarter one. Please be aware that a copy of the disclosure can be found in the Investor section of the website as well as on the stock exchange. Any statement made on this call that reflects the future outlook, or that might be construed as forward-looking, needs to be considered together with the risks the company faces. I'll now hand the call over to the Chairman for his opening remarks. Over to you, sir.
Thanks, Pooja. Good evening, everyone. I'm speaking on behalf of the management team at PSP Projects Limited, and I'd like to welcome all of you to this earnings conference call, where we'll be discussing the quarter one FY 2026 performance. Our board meeting wrapped up this afternoon, and we've posted the relevant call details on the stock exchange as well as the company website. I'd also like to point out that a transcript of today's call will be made available on the portal. In quarter one FY 2026, the construction sector was hit by a shortage of labor, and PSP Projects faced the same situation. In the course of the quarter, we dealt with labor shortages during April and May 2025, and across FY 2026 there was a 37% shortfall in labor. Now for the positive side, as things stand today, we are at a 19% labor shortfall. Some minor impact from this, along with the monsoon, will also show up in quarter two FY 2026, but I'm confident the shortfall will shrink further beginning August 2025. Over the quarter, employee costs climbed to 6.8%, which typically sits in the 4%-5% range. Since the company has won new orders from Adani, we have brought on employees at various levels, so that impact is visible in the higher employee cost. Also, most of the newly awarded projects valued at INR 1,600 crores that commenced after March 2025 are all still in the early stage of construction.
This is the foundation stage. During this construction phase, labor deployment tends to run on the higher side, while labor availability was lower over the same period. So we took a negative hit on our profitability. Another smaller impact came from the monsoon. In Gujarat, the monsoon season started relatively early this year, so we saw some effect from that in June 2025. In this quarter, the company also had to book an additional expense of INR 4.5 crore because of new build projects as well. The company has reported an outstanding order book of INR 6,514 crore, which is a year-on-year growth of 11% as of June 30, 2025. Order inflow reported was INR 107 crore, excluding GST, of the current outstanding order book, with Adani projects making up 27%, and the remainder being non-Adani projects. Regarding order inflow for FY 2026, we expect new projects to be confirmed and service orders to come in from August 2025 onwards. Right now, we are at various stages of discussion and project workings are underway. We expect this to conclude soon. In quarter one of FY 2026, the company successfully completed eight projects. Construction of the residential project of Aster at Adani Shantigram.
For the High Street Villa project, we're providing precast components for the compound wall and drains to Larsen & Toubro. There's the Nestle phase two steel structure erection project, plus Ocean phase two at Sainath project. We also have the precast plant of DeepTech Limited, and the precast plant of Kutch Copper Limited at Mundra. A school building in Jodhpur, Rajasthan — its design and construction — has been assigned to us. On the previous con call, I brought up some projects that didn't get off the ground the way we had planned. I'd like to give updates on each one. With the Sintex building at Bridge City, the delays from the client side have now come to an end. The revenue shortfall this quarter stemmed solely from labor being less available. GBRC now has the client's approval, and work on that project is progressing well. At Science City, the project work is progressing well. During this quarter, we decided to shift from the conventional format to a modular format system — that's GemForm. As a result, work did take place in quarter 2026 on the project. But ultimately, thanks to this technology change, I'm now confident we'll see this project closed as per plan. With EMC, the problem still persists. Work is on hold because of land acquisition. At SMC, there's been a considerable delay in receiving drawings from the client side, and therefore work has been — the finishing hasn't been able to start.
Baroda, land acquisition delays are still ongoing as of today. On the definitive agreement front, Adani Infra Limited has picked up 44,86,193 equity shares through the open offer, which works out to 11.32% of the company's paid-up equity share capital. The open offer settlement wrapped up on June 11, 2025, and every subscribing shareholder was duly paid for the shares they tendered in the open offer. Now let me move on to a few project updates, starting with Coca-Cola. That project, I believe, kicked off last August, and right now we're in good shape and size, since most of the structure work is done. At present we're handling the finishing portion along with the general development of the project. Gati Shakti Vishwavidyalaya — yes, we began that project only last year, and we lost a lot of time during last monsoon, with some delay this year too in April and May. Still, overall the buildings are out of the basement and standing at the first and second floor level. So the finishing activity and MEP will likely pick up pace now on the Gati Shakti Vishwavidyalaya project at Baroda. Palladium Mall — yes, this was the same project we launched last year in the April-May season, and we faced a lot of delay last monsoon as well.
We also experienced a delay this year. The drawings are all complete, and most of the basement work is now on schedule. So from August onward, the project should proceed normally going forward, without much trouble. That concludes my comments, and I'd now like to pass the call to Ms. Hetal Patel, who will walk through the financials in detail.
Thank you, sir. Good afternoon, everyone. Here are the results for the quarter that closed on June 30, 2025 — quarter one FY 2026 compared with quarter one FY 2025. Revenue from operations came in at INR 513 crores this quarter against INR 612 crores, a YoY decline of 16%. EBITDA for the quarter stood at INR 24 crores versus INR 73 crores, down 67% on a YoY basis. EBITDA margin was 4.77% against 12%. Net profit for the quarter was minimal — INR 13 lakhs versus INR 34 crores — a YoY drop of almost 100%. The fall in revenue from operations is largely due to a labor shortage, which PSR explained in his speech. In the quarter under review, the company had to incur additional expenses of INR 4.5 crores for the UP project, and other expenses include ECL provisions of INR 8.68 crores, compared with INR 4 crores in quarter one FY 2025. In quarter one FY 2026, the company incurred CapEx of INR 32 crores. Gross block as of June 30, 2025, is INR 627 crores, and net block is INR 322 crores. I would like to mention a few important balance sheet numbers as of June 30, 2025.
Turning to long-term borrowing, that stands at INR 44 crores, and that figure includes short-term maturities of INR 25 crores. Short-term borrowings come to INR 338 crores, which excludes those short-term maturities of INR 25 crores. Net unbilled revenue sits at INR 556 crores. Retention amounts to INR 137 crores. Mobilization advance is at INR 326 crores. Inventories total INR 344 crores, made up of INR 158 crores in construction material, INR 161 crores in work in progress, and INR 25 crores in finished goods. Of the total sanctioned credit facilities of INR 1,497 crores, the company has utilized INR 864 crores, excluding fund-based utilization of INR 202 crores, and INR 431 crores remains available for utilization. As of June 30, 2025, the company holds total fixed deposits of INR 268 crores, of which lien-free deposits are INR 74 crores. FD worth INR 169 crores are under lien with the bank for credit facilities. FD worth INR 25 crores have been given as security deposits to the client. Work on hand as of June 30, 2025, is INR 6,514 crores. A detailed bifurcation is available in the uploaded presentation. That wraps up the update from the financials, and we are now open for the question and answer session. Thank you.
Much appreciated. We’re moving into the question-and-answer portion now. To ask a question, you can press star and one on your touch-tone phone. If you’d like to be taken out of the question queue, press star and two. We ask that participants use handsets when asking a question. Ladies and gentlemen, we’ll pause briefly while the question queue is put together.
Over to you, Shravan.
Our first question comes from Shravan with Dolat Capital. Go right ahead.
Hello, and thanks for taking my questions. I have a couple of things to ask. I'll start with guidance and then move to a more detailed question. So, regarding revenue, EBITDA margin, and order inflow for FY 2026, what does the updated guidance look like?
What about order intake?
Looking at FY 2026, what figures should we expect for order inflow, along with revenue and EBITDA margin?
Based on what those companies have confirmed, we're currently among the top eight or nine groups for projects valued at INR 8,000 crores to INR 9,000 crores. It's possible that order inflow for this year might land in the range of — if I put it this way — somewhere between INR 7,500 and INR 8,000.
Alright.
Regarding the guidance, the reason we set it out is that we ran into a significant issue during the first quarter, and it will carry over into the second quarter. I also mentioned previously that I would provide revenue guidance once the first two quarters are complete. That's because all the projects we expect to receive from the group company are set to begin somewhere in the second quarter or perhaps the third quarter. It would be better to give revenue guidance after the second quarter's work is finished. On EBITDA margins, we remain in the same range we have consistently cited, which is 8%-9%.
All right. Looking at Q2 itself, regardless of what the difficulties might be — whether that's the labor shortage plus the extra provision, all of it as it stands now, since as you're noting, the labor shortage has eased — from Q2 itself, could we begin to see something like an 8% or 9% margin, or will that mostly show up in the third and fourth quarters? And is there any additional provisioning still outstanding for any of the UP or any other project?
No, at UP there’s actually nothing pending right now. This time around, too, there’s an INR 5 crore expense that has come up, because most of those projects are located in Anand, and since the hospitals aren’t operating, people aren’t taking care of the project. The department isn’t looking after it in a very efficient way. So the cost we’re incurring today is largely because the project isn’t being well-maintained by them. So we aren’t sure, but yes, it won’t be more than INR 5 crore, and it can stay within INR 5 crore. Some cost could still come in the second quarter. But going by my first quarter’s experience, why did this expense arise on the UP side, because I was aware the projects had already been handed over. Why is this cost coming up? But the problem with the department is that the closure of the project hasn’t happened. They’re taking undue advantage of the contractor, and that’s how it has happened.
Looking at Q2 itself, is it possible we begin to see EBITDA margins in that 8%, 9% kind of range?
Yeah, that should be Q2 or Q3, though honestly I'd also expect it just in the Q2 quarter.
All right. Other than Adani, we aren't considering any additional order inflow at this point. That INR 7,000 crore to INR 7,500 crore figure that —
Like we mentioned previously, whenever there are prestigious projects we're able to bid on. One of Gujarat's big projects, Shri Ambaji Corridor Development, has arrived. That tender was rejected, and only a single tender came in. That tender might come up within these months. If we probably qualify, we'll bid for projects of that kind. But for the most part it will come from Adani, so you're right about that.
All right. So with that in mind, let's see — regardless of whatever the comparable run rate might be, we could achieve INR 500 crore, or perhaps INR 600 crore, or possibly even less than that during Q2. As for the second half, how should one think about it, since the new orders we're currently considering sit at INR 7,000 crore to INR 7,500 crore — from where, and when, can execution begin to show up? Looking at next year, suppose this materializes by, say, December. Out of that INR 7,000 crore to INR 7,500 crore, how much could one expect in terms of revenue for next year?
Yes. If you look at that INR 7,500 as an order inflow, it will likely begin in the third quarter's first month. I'm saying this because most of our projects are at the basement stage, since we handle the majority of them for real estate. Revenue from that probably can be expected to arrive to some extent only in the final quarter. So our guidance is that project revenue will stabilize in the second quarter as well. Any new orders that come in during the second quarter, we close them in terms of proceeding with the work in the third quarter. The basement portion probably can only start after that, in the fourth quarter.
All right, I'm just attempting to get this straight. Right now we hold an order book of INR 6,100 crore, and on top of that we bring in roughly INR 7,000 crore to INR 7,500 crore odd. That puts us near INR 13,000 crore to INR 14,000 crore, and then add whatever else we'll be executing, say perhaps INR 2,500 odd crore. So by the close of this, INR 11,000 crore to INR 12,000 crore would sit there. For next year, how should one view it — is a revenue of about INR 4,500 crore something one can easily achieve? Is that a fair way to look at it?
Sure, saying INR 4,500 is easy for all of us, since the order book is now going to be a multiple of 2x to 3x. That means next year we should have no trouble reaching revenue of INR 4,500 crore.
On the working capital side for this, there are two aspects. First is employee cost. Whatever we have right now this quarter, INR 35 odd crore. Beyond that, how much more could one consider at an absolute level, the skill we need to bring in since we still have to secure the additional orders. That's one, and second, on the working capital front, how much more, because of this, might working capital rise or could it fall? As a result, on the debt level, how might one view the gross debt level?
Look, when it comes to working capital or debt, we ought to be in a stronger position by the close of the second quarter, or at the latest by the end of the third quarter. Any orders we receive from the Adani Group — that's figuring on 5%-10%. Initially, when the project kicks off, it's 5% mobilization, and after mobilization is done, there's another 5%. Even taking into account INR 7,500 crore of order info from the group alone, we'd be getting a minimum of INR 750 crore as an advance. So working capital probably shouldn't be a problem, and whatever working capital we're drawing today from the bank's fund base can be brought down to a basic level by the end of the third quarter.
Okay, one last thing just to clear this up, sir. On the project-by-project order book, all the figures we've put in the presentation are identical to what they were in the FY 2025. Is that a printing error, or is there simply no execution happening on any of those projects?
No, that's not a typo. No, it's not possible for every figure to match. That could represent the overall project value, but the work still left to be done has to be different.
No, it's identical. That's exactly what I'm asking you about, sir, for a —
All right, once more — we'll go over it again. Shravan, let me take another look.
Alright, no problems at all, sir. Thanks very much, and best of luck to you. Thank you, sir.
I appreciate it.
Thanks. Just a quick reminder for everyone: to ask a question, you can hit star and one. Our next question comes from Vaibhav Shah at JM Financial. Go ahead, please.
Sir, you noted an ECL provision of INR 8.7 crore, and in Q1 of last year it was INR 4.5 crore as well. Which project does that relate to?
Look, the ECL provision is calculated based on how long the receivables have been outstanding. We apply a higher provision rate to the bracket of all new receivables. So that's one provision. And as for Pandharpur, we've now provided for it in full. So out of INR 8.68 crore, we've set aside roughly INR 4 crore for the Pandharpur project. So as things stand, the entire INR 17 crore that was receivable from Pandharpur has been provided for.
So should we anticipate some figure in Q2 as well regarding the ECL side, or is it likely that everything has already been done for the existing book?
For Q2, it's possible, because look, this is driven entirely by the formula — the ECL formula — that we apply to the receivable numbers. So some level of provision can also arise in Q2, depending on where the receivables stand.
Even if Pandharpur has come to an end.
Yes, we’ve already supplied that even for Pandharpur.
What does the receivable figure come to at June?
Yeah, as of 30th June, that's INR 525 crore.
Okay, so on a quarter-over-quarter basis, we've also seen debt go up quite sharply — an increase of roughly INR 100 crore. Is that because of higher working capital?
Sorry — you were saying something about that.
On a quarter-over-quarter basis, gross debt has risen from INR 270 crore to INR 382 crore.
Yes. That's largely driven by a few of the CapEx acquisitions. As I mentioned earlier, we've incurred INR 32 crore of CapEx. On certain of that CapEx, we're required to pay 100% in advance. That's the reason it went up. To some degree, yes — owing to this higher working capital requirement, we ended up borrowing that amount.
Second, we secured an Ahmedabad Airport Cityside Development project worth roughly INR 600 crore last year in Q4. I couldn't spot that project in the order book sheet included in the PPT. Did we overlook listing it there, or has something been cancelled or has the scope changed?
We'll verify that. We'll verify it once more.
No, I believe the project is there, but I think it must have slipped past them. We'll look into it.
Alright. Sir, second, when we examine how the order book moved quarter over quarter, there's a gap of about INR 300 crore. Did we cancel any orders during the quarter?
Yes, to some degree, a handful of projects. One project we've closed short. That project is still running, though the execution amount has been cut back. That's the FRF DCL, and that may have produced the effect in the work on end.
Sir, could you tell us what our CapEx guidance is for FY 2026 and FY 2027?
It'll fall within that same 3%-4% range, since every one of these projects comes from Adani Group and they're large-scale, so it could go from 5%±. Apart from that, it stays the same.
Sir, you said previously that SMC had some payment delays, which meant no work was done in Q1. Is that right?
No, no. There's no such thing as a delay in payment, and we haven't done any work. It's purely that payments are arriving on schedule. The sole issue was the labor problem, and because of that we couldn't execute in a major way, largely during the first part.
What revenue figure are we aiming for from the SMC project in FY 2026? Previously, our goal was to finish the bill in FY 2027. Do we still expect that, or will it push into FY 2028?
No, it can’t extend past FY 2027, since the work has to be finished and we’re on our path because all the finishing activities have now begun. They wrapped up just before March. The facade was completed before this quarter as well, and the facade has now been approved too, plus we’ve already placed orders for the materials on our side. In maybe 1.5 or 2 months — around the end of the second quarter or the start of the third quarter — we’ll be in a better position to handle all the activities tied to MEP, civil, finish, interior, and facade.
All right, sir. But right now, just 30% of the work has been completed, correct? The original value is 34, and 960 is the outstanding order.
So what you're saying is that the working value comes to just 33, correct?
Yeah.
That's correct.
All right. Thanks, sir. I’ll rejoin the queue by calling back.
I appreciate that.
Thanks. We’ll take the next question from Aayush Saboo at Choice Institutional Equities. Your line is open — please go ahead.
Yeah, hi. What margin should we expect from the businesses outside Adani, from the order book that isn't Adani? And do we apply the same internal hurdle rates to these others as well?
For non-Adani business, our guidance has consistently been 9%-10%. We gave that same 9%-10% guideline previously and again last year, and we expect the same from Adani Group. So it isn't the case that Adani Group will carry a lower margin while other projects carry a higher one.
All right. For FY 2027, what would the order pipeline from Adani look like? That would help give a rough approximate guidance. What is the Adani order inflow for FY 2027?
Your voice is breaking.
How much Adani order inflow might we see in FY 2027? Looking one year ahead, can you offer any guidance on that?
That's exactly what I said — it will fall in the INR 7,000 to INR 8,000 range.
Alright, so for FY 2026 and FY 2027. That's going to be
Not at all. I'm referring strictly to FY 2026. Right now, the two projects under discussion are the ones already in build. What I've laid out reflects what we expect from Adani Group during this year alone — not the following year. As for next year, we'll still need to see which new projects they bring forward at Dharavi and Mumbai Airport.
So, can you give us a rough idea of what order inflows might look like next year? Would they fall in that same range — two or three?
For this year, we’re able to provide guidance on the projects currently being discussed. As for next year, which projects will come from their side is something we still need to work on, and probably even if they have that projection for next year, they’ll be able to give the guideline after two quarters.
All right, thanks.
Thanks. We’ll take the next question from Ankita Shah at Elara Capital. Please go ahead.
Sir, what type of projects are we expecting from Adani Group? Have we identified a pipeline of projects?
Sure, we’ve put together a number of the projects we’re currently in discussions about. There’s the residential colony at Mundra — INR 1,250 crores — from Adani. The second is a township at Mundra, at INR 2,300 crores. A museum at Ahmedabad, INR 100 crores. Temple development — as I mentioned, this is the government tender we plan to bid on — around INR 800 crores. That’s the second one; then a residential project at Dharavi, INR 830 crores. Infrastructure work, a commercial tower at Shantigram, INR 100 crores. Development work at Ahmedabad Airport, INR 610 crores. Residence at Shantigram, Ahmedabad, INR 550 crores. A hotel at Shantigram, INR 580 crores. An institutional building at Shantigram, INR 750 crores. Those are the projects under discussion with them.
All right. We anticipate delivering margins comparable to the ones we've called out in the guidance on this. You'll only move forward with it if that threshold is met — is that right?
Yeah.
Understood. Thanks.
I appreciate it.
Thanks. Just a reminder for everyone: you can hit star and one to ask a question. Our next question comes from Balasubramanian A at Arihant Capital. Go ahead.
Good evening, sir. Sir, I'd just like to get a handle on the labor shortage situation. Right now it stands at 37%, with a 19% shortfall. When do you think we could see a full recovery where that labor shortage is concerned? If you wouldn't mind sharing a few of the main reasons — what exactly is driving the labor shortage out there, whether it comes down to salary or a lack of facilities — and how are we tackling this issue relative to the industry? Because unless these labor problems get resolved, none of the numbers we're talking about are going to materialize. Those are my first questions, sir.
Look, the facilities and infrastructure we offer our labor force are on par with, or even below, what other peer group companies provide. The reason is definitely the market—April and May are the season when people go off to get married. It's genuinely early. If you follow this, there were 2 Eids, and both of those Eids fell close together, within 15 to 20 days, in June. That's probably the sole cause of the shortfall. And we should also grasp one more point. Whenever we launch a project after March, that's the stretch when workers tend to head back home because of marriages and all of that. Otherwise, when we kick off a project, they'd rather not begin one that started in April. If projects have begun in November or December, they get continuity, so they can hold on to a bit of 50%, 60% labor for projects already awarded to them that they're working on. As for what you're asking—how we can mitigate—we are definitely thinking at a high level about technology: how to cut down, how to make the work simpler, how to bring more and more technology into the organization, how to make use of that solid level of shedding so that we can deploy fewer laborers and get more work done.
We're also purchasing certain technologies from PERI for producing table forms. So in slab work too, we can pour 50 cm of slab in a single go, and it can be lifted straight up to the floor above. So we clearly see that the labor situation won't do the organization any favors, and that will keep going through the whole year. The country's economy is expanding quickly day by day. So we're taking that aspect very seriously as well. At the same time, we're converting unskilled labor into somewhat skilled labor. Some of those skills we can train them in here too, since unskilled workers are still obtainable from Odisha and West Bengal. So there as well, we're working on training some unskilled people to turn them into skilled labor for skill-level work. So the company is quite serious about easing this shortfall-of-labor requirement. But the seasonal effect is likely the only thing hitting us. Apart from that, we've launched so many initiatives that can bring our labor requirement down to 30%, 40% less than what we needed across the last few years of our experience.
Alright, sir. Second point: for the Dharavi projects, there are roughly 5,200 interim residential homes for families that have been displaced. What I'd like to get a sense of is the timeline on those projects and what the execution steps look like. Could you share what the size of the opportunity is within the Dharavi project itself, what the saleable GDP value is, and what share we might be able to capture?
Look, Dharavi is a rehabilitation program, and the housing built for the Dharavi project is going to be handed over to the people who live in Dharavi. From our side, it's purely a contract where we have to build the houses according to the group's requirements. There's nothing like that — what the sale price will be, or what price we're going to charge the people who are going to stay there in Dharavi. That's not our concern. Our concern is simply to construct that portion. As for where the work stands right now, we're in the process of sheet piling to create the basements. Other than that, the project is meant for 36 months. Probably, maybe in October, November, we'll be in a better position to answer your question once the basement gets started and the excavation is finished.
Sir, regarding these 5,200 displaced homes, when will this project get underway, and what's the timeline for completion?
As I mentioned, the project is already underway, and right now we're producing sheet piling for the basement excavation.
Understood. Yes, thanks, sir.
Thanks. Our following question comes from Deval Shah at RBSA Investment. The line is yours.
Hello there.
Yes, sir.
Good evening, everyone. My question is particularly about the Mumbai project. What we hear is that Adani Realty is becoming really aggressive in the Mumbai market. Besides the Dharavi, we also have the Motilal Nagar redevelopment project and the Bandra project. I just wanted to understand what the likelihood is of us getting the lion share of these other two redevelopment projects as well as the city side development in Mumbai?
Look, when it comes to the group, they're the sole partner in this business. They also have a partnership in IPDC. IPDC focuses mainly on projects tied to ports and industry. The chance will most likely land with PSP, provided we can manage that many projects simultaneously. It's really about constructing the project rather than securing the quarter projects — whether or not we end up with that particular project. If we can demonstrate results on the ground and show we're able to handle it, then for most projects, we'll always be the first choice.
Sir, is it fair to assume that we're also scaling up the team in Mumbai? I just wanted to get a sense of that. In anticipation of —
So yes, a team is already in place in Mumbai. I believe 13, 14 people have already been appointed. We're also opening a small new office in Mumbai so that projects can be managed directly from there. We're working to mobilize more strongly and build ourselves up in terms of management and scalability in Mumbai.
Alright, thanks. Best of luck.
Thanks. Just a quick reminder for everyone: to ask a question, hit star and one. Our next question comes from Keyurkumar at Niveshaay. Go ahead.
Hi there, yes. My question concerns the CapEx figure you cited of INR 32 crore — where is that CapEx being allocated? I believe I missed the unbilled revenue portion. How much unbilled revenue was there this quarter?
Yes. Unbilled revenue comes to INR 556 crore, and the CapEx is primarily plant and machinery — that covers formwork for several new sites as well as cranes for those new sites.
Alright, my second question concerns the precast business. Within our precast operation, how much capacity is being used for internal needs, and how much is being used for external sales — meaning what we sell to outside customers? If you're able to say, what share of precast output goes into our own projects?
Look, it isn't really about giving you a percentage split between what we do for the market and what we do in-house. That hinges on what the building requires and what the client requires. Earlier, we weren't doing a great deal on the building side. Over the last two years, if you look, we've already completed the majority of the infrastructure projects. If you've seen the bullet train project, we've supplied a lot of material worth more than INR 300 crore, INR 200 crore. During the past year, we built roughly 12 lakh square feet of warehousing facilities, which we could deliver at a quicker pace, and those putting up a warehouse worth INR 15 crore or INR 20 crore can't find a good contractor, so the project gets finished on time. From here on, we have three or four projects for the group as well, which we've started right from the foundation. Once the foundations are done, it moves to precast. It will proceed in both directions. Mostly it will go to our in-house work, but if there's a big requirement from outside the group too, we'll supply some materials to outside groups as well, to customers.
So for the captive and the outside project, there's no percentage?
No. That’s something we can define that way. It depends. Like I mentioned earlier, we weren’t doing too much work on building before. Now we’ve started, and we’ve initiated 4 buildings that are roughly 60, 70 m in height. If we’re working on 4 buildings and we’re already engaged with our own work, it may not be easy for us to take outside orders. It depends on the production capacity and what’s required at site. If there’s a gap in between to supply some materials in 1 month or 2 months, we can take up that order. But probably that won’t be an issue from now on, because this technology is now being accepted easily by the market and on a high-rise scale. High-rise buildings too—people have accepted them. So probably the group, we will be having our own captive production in that way.
All right, the final question concerns our precast capacity: how would you define utilization, what is it currently, and if we ran at peak level, what would the maximum potential revenue be?
Look, I think at the outset, when we kicked off and got this precast facility going, our aim was roughly INR 400 crore to INR 500 crore in revenue that we could bring in just from the precast plant. At this point we've probably got to 50%+ or so. So over the coming one to one and a half years, we'll be able to drive more and more revenue, up to a level of INR 500 crore.
Alright, thanks.
Thanks. Our following question comes from Vivek Lodariya, who is with Nirbhay Asset Management, on that line. Please proceed.
Hello there. Yes, can you hear me?
Yeah.
Good evening. One thing I picked up on: cost of materials consumed, as a share of total expense, jumped sharply to 38.51% in quarter one, compared with 30.03% in quarter one FY 2025 — that works out to an increase of more than 800 basis points on a year-on-year basis. Could you help us understand what the main reason is for this spike? Was it raw material prices going up, a shift in the project mix, or something else?
Look, within construction we handle civil work, MEP, and interior fit-outs. The mix of materials shifts somewhat based on what the project requires. For MEP, materials make up roughly 80%-90% while labor accounts for 10%. On the major civil side, when we're doing core and shell, it comes to 45%-50%. At the finishing stage, it's 70%-30%. Because our portfolio spans all these project types — a few are pure core and shell, a few combine core and shell with finishing, and on some we deliver core and shell, finishing, and MEP together — these components can't be compared directly at 100% against revenue, since you have to understand which activities dominated during that particular quarter.
I'd like to find out whether the company is at present putting in a bid for the Dharavi redevelopment project, or is taking part in it in any capacity — whether directly as a project or through any joint venture or anything of that kind.
No — we're quoting directly, and we're in talks with the Adani Group, since the project belongs to one of its group companies. Dharavi is a group company project, so our discussions are happening directly with them. It's not as though we're bidding, or even doing a JV with anyone else.
Okay. If we’re at 100%, or say around 10%, or —
Which figure is the full 100%, and which one is the 10%?
We're — hi there.
Hello there.
Since that person isn’t responding, we’ll go on to the following one. Our next question comes from Balasubramanian A at Arihant Capital, on the line. Please proceed.
Thanks again, sir, for the chance to address this. Sir, within that INR 6,150 crore order book, what portion is fixed price, and what portion comes from variable priced contracts? As for the upcoming inflows in the INR 7,000 crore to INR 7,500 crore range, can we expect a greater share of fixed price contracts, or more variable price ones?
Look, when it comes to the group, nearly every project is not fixed price. It's an open price structure where cement and steel carry a base rate, and any movement in the major materials is a risk they bear. So by and large it's an item rate contract, and that will keep going with a lot of basic rates. Also, at the stage of each individual activity, there's a clear return worked out through discussion of the rates, and those rates will plainly depend on the kind of work to be executed. So my view is that for new projects, there won't be any fixed price contract. Right now, I can't give you an exact answer on what percentage is fixed price versus item rate contract. We will share that percentage with you out of that INR 6,100 crore — how much is fixed price and how much is item rate. The exact percentage, I don't know.
Alright, thank you.
Thank you. Since that was the day's final question, I'll now pass the conference to management for their closing remarks. Over to you, sir.
I appreciate everyone being on today's earnings conference call. Thank you for your backing and for placing your confidence in us. We trust that we've managed to answer the majority of your questions. Should anything further come up, feel free to contact our Investor Relations advisor, EY, and they'll get in touch with you offline. Thanks once more to everyone, and good evening.
Much appreciated. Much appreciated. That brings this conference to a close on behalf of PSP Projects Limited. We appreciate your participation, and at this point you're welcome to disconnect your lines. Thank you.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete PSP Projects Limited transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to PSP Projects Limited earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.