Good day, ladies and gentlemen, and welcome to the PSP Projects Q1 FY2027 earnings conference call, which is being hosted by Ernst & Young. Just as a reminder, every participant line will remain in listen-only mode, and once the presentation wraps up, there will be a chance for you to ask questions. If you require assistance at any point during this call, please signal an operator by pressing star then zero on your touchtone phone. Kindly be aware that this conference is being recorded. I will now hand the conference over to Ms. Krishna Patel from Ernst & Young. Thank you, and over to you.

Krishna Patel executive
#2

Thank you, Naksha, and good evening to all of you. I'd like to welcome everyone to the Q1 FY2027 earnings conference call of PSP Projects Limited. Joining us today to walk you through the results and take your questions is the PSP Projects management team, which includes Mr. Prahaladbhai S. Patel, our Chairman and MD; Ms. Pooja Patel, the CEO; and Ms. Hetal Patel, the CFO. Kindly be aware that what we discuss today might include some forward-looking statements concerning future events and future performance. A number of factors could lead to actual results differing materially from those contained in the forward-looking statement. Also, please be advised that the audio of this earnings call is copyrighted material belonging to PSP Projects and may not be copied, rebroadcasted, or attributed in press media without the company's specific written consent. That said, I now hand the call over to Ms. Pooja Patel, the CEO, for her opening comments. Thank you, and over to you, Pooja.

Pooja Patel executive
#3

Thanks, Krishna, for that introduction. Hello, everyone, and I appreciate your presence on the PSP Projects call covering the first quarter of FY2027. At 30th June 2026, our outstanding order book was INR 13,245 crores, which shows our robust 103% year-on-year growth and gives us strong multiyear revenue visibility. Within our total order book, group projects make up approximately 70%, while external projects account for the remaining 30%. The first quarter is traditionally a challenging period of the construction industry due to seasonal factors, including labor migration during festive and wedding season, as well as the initial onset of monsoon. Despite this industry-wide challenge, PSP delivered a strong 65% year-on-year revenue growth during quarter one FY2027. Our performance demonstrates the strength of our execution capability and the process achieved across key projects. Importantly, most of our major projects have now moved beyond the initial stage, involving excavation and underground works and entering the core construction phase, enabling improved execution momentum. During the quarter, we deployed the workforce of over 16,000 labor across project sites, reflecting the scale of our operation and execution readiness. As labor availability normalizes in the coming quarters, we expect construction activities and project execution to gain further traction.

Pooja Patel executive
#4

I'd also like to call attention to the way we keep investing in making the organization stronger. The higher employee cost this quarter mirrors our deliberate emphasis on building up leadership and project management capacity at multiple levels of the company. We've grown the team in key functions and geographies so that we're well placed to handle a substantially large project portfolio, while staying committed to on-time delivery, quality execution, and operational excellence. In the quarter, the company completed six projects and brought in order inflows of INR 630 crore, with 93% of orders from Adani Group. The major orders are the Adani Healthcare and Research Foundation project, Mumbai, the Airport Office Building at T1, Mumbai; refurbishment of the port user building, Mundra, and construction of skilled accommodation at the Green PVC Project, Mundra. The order book is diversified, with industrial projects at 39%, residential projects at 37%, government projects at 23%, and industrial projects approximately 1%. As for our current order book: please take note of the key projects and their outstanding contract values. Shri Ambaji Mata Temple, INR 962 crore. Shankaranarayana Constructions' high-rise building, INR 6.93 crore. Construction of the Fintech Building at GIFT City, Gujarat, INR 259 crore. Human Biology Centre at Science City, INR 248 crore. The biggest residential project in GIFT City, INR 202 crore.

Pooja Patel executive
#5

For the Dharoi Dam region development, the figure is INR 198 crore. Sabarmati Riverfront Development Phase two comes in at INR 187 crore. Our bid pipeline stands at INR 6,200+ crore, split 61% group projects and 39% external projects. Now I'd like to walk through a few project-level updates. At Shankaranarayana Constructions, core and shell activity is done, and full-fledged MEP interior works plus facade work are currently underway. At Rail Vikas Nigam Limited, two of the three buildings will be handed over shortly, and the hostel building's RCC is finished, with MEP plus interior works and facade work in progress. On Ahmedabad Airport and Cityside Development, we're at a different level, with RCC work proceeding in full force. For Ambaji Mata Temple, we're at the excavation stage, and some buildings are at the footing level. With that, I'll now hand the call over to Ms. Hetal Patel for the financial and further details.

Hetal Patel executive
#6

Thanks very much, ma'am. Good afternoon, all. We'll walk you through the consolidated financial results for the quarter and the quarter that ended on 30th June 2026 — Quarter one of FY 2027 against Quarter one of FY 2026. Revenue from operations in this quarter came in at INR 853 crores, compared with INR 518 crores, which works out to a 65% rise on a YoY basis. EBITDA for the quarter stood at INR 55 crores against INR 25 crores, up 121% on a YoY basis. The EBITDA margin was 6.42%, versus 4.79%. Net profit for the quarter was INR 18 crores, compared with INR 37 lakhs, which is a jump of almost 50 times on a YoY basis. Net profit margin came to 2.12%, against 0.07%. In the quarter under review, employee cost rose from INR 35 crores to INR 46 crores, driven mainly by annual increments carried out in a three month and by headcount growing from 2,400 almost to 2,600. The rise in depreciation, from INR 17 crores to INR 26 crores, is mainly attributable to additions made to the asset block during FY 2026 as well as into Quarter one of FY 2027. In Quarter one FY 2027, the company incurred CapEx of INR 28 crores. Gross block stood at INR 793 crores as on 30th June 2026, and the net block is INR 472 crores.

Hetal Patel executive
#7

I'd like to go over some of the key consolidated balance sheet figures as of 30th June 2026. Long-term borrowing stands at INR 38 crores, and that figure includes short-term maturities of INR 19 crores. Short-term borrowings come to INR 217 crores, excluding those short-term maturities of INR 19 crores. Net unrealized revenue is INR 473 crores. Trade receivables sit at INR 745 crores. Trade payables are INR 356 crores. Retention — both long-term and short-term — is INR 222 crores. Mobilization advance is at INR 836 crores. Inventories total INR 362 crores, made up of INR 205 crores of construction material, INR 137 crores of work in progress, and INR 19 crores of finished goods. Of the total sanctioned credit facility of INR 1,497 crores, the company has utilized non-fund-based facilities of INR 678 crores, while fund-based utilization is INR 166 crores. The limit available for utilization is INR 653 crores. As of June 30th, 2026, the company holds total fixed deposits of INR 324 crores, of which lien-free deposits are INR 139 crores, and assets worth INR 185 crores are under lien with banks for credit facilities and given as security deposit to client. Work on hand on a consolidated basis as on 30th June 2026 is INR 13,245 crores, and the detailed breakup is provided in the uploaded presentation.

Hetal Patel executive
#8

That wraps up the financial update, and at this point we'll take questions in the question and answer session. Thank you.

Operator operator
#9

Thanks so much. At this point we’ll move into the question-and-answer portion. If you’d like to ask something, you can press star and one on your touchtone phone. Should you want to take yourself out of the queue, press star and two. We ask that participants use their handsets when posing a question. Ladies and gentlemen, we’ll hold briefly while the queue is put together. Our first question comes from Shravan Shah at Dolat Capital. Please go ahead.

Shravan Shah analyst
#10

Hello, sir. It's really good to see the substantial recent step-up on the execution side. There are a couple of things I'd like to understand. First, sir, regarding the guidance, just to get a sense: for FY 2027, the INR 4,500 crore revenue we were looking at, and even as we go forward, the 20%-25% kind of revenue growth we were looking at — does that remain intact?

Prahaladbhai S. Patel executive
#11

Sure, we can state that on average it will exceed 25%, so the figure could fall between INR 4,000 crore and INR 4,500 crore, and it will still stay on that same line.

Shravan Shah analyst
#12

All right. Now, sir, regarding margins, this quarter was also 6.4%. So we had been expecting something in the 7%, 8% range. Can we begin to see a figure of 7% plus starting from Q2, or would it perhaps be from the second half onward that we start to see that kind of number?

Prahaladbhai S. Patel executive
#13

Correct, from the second half onward we ought to land in that range. Even in this quarter, though, employee benefit expense came to INR 46 crore, equal to 5.39% of sales. April and May sales were lower in those first two months, and the third month delivered INR 319 crore while the earlier two together were INR 270 crore. That fact alone shows roughly 1% of extra expense stemming from turnover that did not materialize, and that is what creates the 1% gap. Add at least that INR 7 crore to INR 8 crore back into EBITDA, and it moves somewhat above 7%. Still, quarter three and quarter four should look better.

Shravan Shah analyst
#14

Regarding employee costs going forward from the second quarter, should we expect something similar, or perhaps a specific figure?

Prahaladbhai S. Patel executive
#15

Yeah. Look, on average we’ve typically been around 4% to 4.5%, or nearly 4.5% to 4.6%. This quarter, it’s close to 5.4%. That’s the major shift, since during the first two months—April and May—as you know, there was a tremendous need for labor and a shortage of workers at the site. Had that been turned into sales, it would be roughly 4.5%.

Shravan Shah analyst
#16

All right. For this quarter, we received INR 630 crore, and earlier we were anticipating INR 6,000 crore and nearly INR 5,000 crore from Adani Group. That figure is now going to stay unchanged for this year. In the second half, might we see a meaningful order come through?

Prahaladbhai S. Patel executive
#17

Yeah, likely we'll land in that same band—perhaps INR 400 crore to INR 500 crore higher or lower. Even so, we're still within that same plus INR 5,000 crore range, since a lot of other projects are being discussed that will come out in the second quarter and the third quarter. So our order visibility stays in that same range.

Shravan Shah analyst
#18

Right. And CapEx is likewise around 3% to 4% of revenue. In the quarter just ended, we spent INR 28 crore. Does that figure stay at the same level, or does it rise once execution picks up?

Prahaladbhai S. Patel executive
#19

Pretty much. It's really hard to pin down right now. That said, if you've got a handful of projects where the project itself is big, then CapEx might run a bit higher. Still, on average, I'd put it at roughly 3% to 4%.

Shravan Shah analyst
#20

All right, so for this quarter, sir, out of that total revenue of broadly INR 853 crore, what portion would come from the Adani Group? Just so we can get a sense, in terms of how execution of the Adani projects is picking up.

Prahaladbhai S. Patel executive
#21

Hetal, do you have it?

Hetal Patel executive
#22

Yeah. At the moment, we don’t have precise figures, but it should land mostly near 60%. Adani Group revenue will account for 55%–60%. That’s because we’re carrying out this RVNL work around that area, which is also a high-value project, SMP sales. Roughly 60%, we can say, will come from Adani Group.

Shravan Shah analyst
#23

All right, I understand. So this mobilization advance carries no interest at all, correct?

Prahaladbhai S. Patel executive
#24

Right.

Hetal Patel executive
#25

That’s correct.

Shravan Shah analyst
#26

On working capital — is there room for another step up there?

Hetal Patel executive
#27

Right, and that's something you can observe, since finance cost has come down versus earlier quarters. We've drawn less on our working capital facility, and we also hold surplus FDs. Looking ahead, we anticipate a bit more of a decrease there.

Shravan Shah analyst
#28

After that, across the following 2 to 3 quarters, our finance cost should essentially drop to zero, and we will be turning net debt-free.

Prahaladbhai S. Patel executive
#29

That’s a fair expectation.

Shravan Shah analyst
#30

Alright, thank you, sir, and best of luck to you.

Prahaladbhai S. Patel executive
#31

I appreciate that.

Operator operator
#32

Thanks. Everyone, if you'd like to pose a question, just hit star and one. Our next question is from Balasubramanian at Arihant Capital. Go right ahead.

Aswin Balasubramanian analyst
#33

Good evening, sir, and thanks very much for the chance to speak. Sir, where do things currently stand with how we're executing the Mumbai projects, particularly over on the Mahim and Matunga side?

Prahaladbhai S. Patel executive
#34

For Mahim, the first 2 blocks' foundation — the basic raft foundation — is complete, and we're now doing the first placement for work. Over in Matunga, piling work is underway. Before excavation, piling is what's happening first.

Aswin Balasubramanian analyst
#35

Alright, sir. Sir, how much do interest-free advances currently stand at? I believe Madhav covered the total mobilization figure. What portion of that is interest-free?

Hetal Patel executive
#36

The entire amount carries no interest.

Aswin Balasubramanian analyst
#37

Sure thing.

Operator operator
#38

Thanks. Our next question comes from Dhananjay Mishra at Centrum Broking. Go ahead, please.

Dhananjay Mishra analyst
#39

Yes, good evening, and congratulations on a really strong set of numbers. I just wanted to ask whether there's any update on this Commonwealth project. What's the status? When is it going to be addressed?

Prahaladbhai S. Patel executive
#40

Honestly, I'd say we still don't have a very clear picture. That said, things began moving a few days ago. A control room is now being set up for the Commonwealth development, the one slated to take place in Andheri. As of now, there's likely nothing documented or reported about when that tender might be issued. Just last week, we also heard that our Home Minister is going to attend this class group for the Commonwealth discussion as well. Perhaps in the next quarter we ought to hear something regarding what will unfold, since at this point it's high time that some of these projects got underway.

Dhananjay Mishra analyst
#41

All right, sir. Regarding this year's order inflow guidance, we haven't factored in anything from that area — whatever that INR 6,000 crore figure is.

Prahaladbhai S. Patel executive
#42

No — where government projects are involved, we aren't factoring in order inflow, not that portion of it. On the build pipeline side, we can take that into account, but as for order inflow, it only counts once the orders are cleared.

Dhananjay Mishra analyst
#43

Alright. Sir, is there any update regarding collections on this UT Medical project? Has there been any improvement, or does it remain the same?

Prahaladbhai S. Patel executive
#44

Yes, close to three of the projects — the EOTs are nearly at the point of being signed. Just one day ago I was in Lucknow to talk over the final three projects as well. Likely within this week, or by the close of this month, or in the first week of August, we'll be in a stronger position to secure all of the EOTs. So the funds will become due, and once that money is in place, we expect the account should close around end of August or the middle of September.

Dhananjay Mishra analyst
#45

Right, so that covers both the receivable side and the unbilled portion.

Prahaladbhai S. Patel executive
#46

Yeah.

Dhananjay Mishra analyst
#47

Both of them are going to improve later on.

Prahaladbhai S. Patel executive
#48

Yeah.

Dhananjay Mishra analyst
#49

Understood, sir.

Prahaladbhai S. Patel executive
#50

The unbilled portion applies to the current quarter.

Hetal Patel executive
#51

On the unbilled side as well, we’re going to—

Prahaladbhai S. Patel executive
#52

Alright.

Hetal Patel executive
#53

We've got that locked in.

Prahaladbhai S. Patel executive
#54

Yeah.

Dhananjay Mishra analyst
#55

Alright.

Operator operator
#56

Thanks. Everyone, to ask a question you can hit star and one. Just a reminder for everybody on the call: to pose a question, press star and one. Our next question comes from Ayush Saboo with Choice Institutional Equities. Go right ahead.

Ayush Saboo analyst
#57

Right. Based on the EBITDA margin guidance you gave of 7%-8%, should we expect to hit that guidance in the first half or the second half of the financial year? And does any upside exist to that guidance — the 7%-8% EBITDA margin?

Prahaladbhai S. Patel executive
#58

I believe I've already responded to that, only regarding the second half. In the first half, as I mentioned, there's an employee cost that exceeds 5%. Once sales increase and we have full labor availability throughout the year, we should be in a better position in the second half of the year.

Ayush Saboo analyst
#59

I appreciate that.

Operator operator
#60

Just a quick reminder for everyone: if you'd like to ask a question, please press star and one. Our next question comes from Vaibhav Shah at JM Financial. Please go ahead.

Vaibhav Shah analyst
#61

Sir, could you give us any update on LCV receivables?

Prahaladbhai S. Patel executive
#62

Not clearly, no. That said, I do have one call left — I need to sit down with top management and the directors. I'll likely go over there next week, working around their schedule. They've asked me to come in for a conversation. What's behind it, I can't say — I don't know what favorable thing I've spotted there. Still, they did reach out and ask me to come meet about the receivables.

Vaibhav Shah analyst
#63

How much in receivables remains on the books at this point?

Hetal Patel executive
#64

90 crore rupees.

Prahaladbhai S. Patel executive
#65

INR 90 crore.

Vaibhav Shah analyst
#66

Alright. And then second, regarding margins, you brought up 7%-8%. Does that apply to the full year, or is it just for the second half?

Prahaladbhai S. Patel executive
#67

No, that should apply to the full year. But as execution pace picks up over the coming few quarters, we ought to be better placed to move past 7% to 8%.

Vaibhav Shah analyst
#68

Alright. Last question, sir: when we look at revenue on both the consolidated and standalone books, which projects account for that difference? Is Dharavi the reason?

Hetal Patel executive
#69

When you say standalone and console books, you're asking about the projects we carry out in the subsidiary company, is that right?

Vaibhav Shah analyst
#70

Yeah. How does standalone revenue compare with console revenue?

Hetal Patel executive
#71

Yeah. We've recorded roughly INR 80 crore in revenue at our subsidiary. Those are a few miscellaneous projects that we've picked up in that company.

Vaibhav Shah analyst
#72

So these are projects belonging to Adani Group?

Hetal Patel executive
#73

Yes, only projects from the Adani Group.

Vaibhav Shah analyst
#74

So at this point, whenever you provide that guidance, are we supposed to treat it as consolidated guidance?

Hetal Patel executive
#75

Yes.

Prahaladbhai S. Patel executive
#76

All of it will be provided solely as consolidated guidance.

Vaibhav Shah analyst
#77

All right, thank you, sir. That covers what I wanted to ask.

Operator operator
#78

Thanks. We'll take the next question from Rushabh at RBSA Investment. Your line is open, please go ahead.

Rushabh Shah analyst
#79

Hello there.

Operator operator
#80

Yes, sir. We can hear you clearly.

Rushabh Shah analyst
#81

Yeah, could you give us some detail on the order book?

Prahaladbhai S. Patel executive
#82

You're sounding a little unsteady.

Operator operator
#83

Pardon me for cutting in, sir. The audio on your end is cutting out.

Rushabh Shah analyst
#84

Is this coming through okay now?

Prahaladbhai S. Patel executive
#85

That's not clear.

Operator operator
#86

Could you address the handset, sir?

Rushabh Shah analyst
#87

Hi there.

Prahaladbhai S. Patel executive
#88

Yeah.

Rushabh Shah analyst
#89

Sure, if you could offer any insight regarding the order book.

Prahaladbhai S. Patel executive
#90

Apologies, we honestly can't hear your voice very clearly at all.

Rushabh Shah analyst
#91

All right. Let me give it another shot.

Prahaladbhai S. Patel executive
#92

Yeah.

Operator operator
#93

Ladies and gentlemen, to ask a question you can press star and one. A reminder for all participants to press star and one if you'd like to pose a question. Anyone wishing to ask something may press star and one on their touchtone telephone. Our next question comes from the line of Vishal Periwal from PL Capital. Please go ahead, Mr. Vishal.

Vishal Periwal analyst
#94

Yeah, thanks for the chance. Just a few data points. Regarding the order book we have, 13,000 odd crores, how much of that comes from the Dharavi side? The proportion.

Prahaladbhai S. Patel executive
#95

I don't have a precise number for what's coming from the Dharavi side, but I believe there are 2 Dharavi projects that are counted in this order book.

Hetal Patel executive
#96

Three thousand.

Vishal Periwal analyst
#97

Alright.

Prahaladbhai S. Patel executive
#98

Roughly INR 3,000 crore — that's the figure, correct?

Vishal Periwal analyst
#99

INR 3,000. Alright. Broadly speaking, at that Adani meeting a couple of months ago, when we were there, they were projecting a sizable opportunity that we could see. For us, what's probably a figure one might consider, since the size is quite large — any ballpark number you can share regarding what we're targeting from this opportunity?

Prahaladbhai S. Patel executive
#100

Are we discussing Dharavi?

Vishal Periwal analyst
#101

Sir, the location is Dharavi.

Prahaladbhai S. Patel executive
#102

Dharavi is a development project. There's a first part, which is redevelopment, and then a second part, which is developing the Dharavi land once it's been vacated. As far as the redevelopment goes, that will take at least 4 to 5 years, maybe 6 years. Once those 6 years are up and the entire redevelopment is finished, then that land gets vacated, and the fresh development on that land will come after 6 to 7 years. Right now, of the first two large projects being announced for Dharavi rehabilitation — the ones we're doing — since these two houses have to be built within a span of 5 years, I think by the time we finish some of the projects, we could get another opportunity of the same size later, after 2 years. At present, we're the first one to write a rejection. If we can build up our capabilities in Mumbai, then we'll get more and more chances. Since they have a fixed timeline for building 2 lakh houses, there may be a few other players who can also participate in the Dharavi redevelopment project.

Vishal Periwal analyst
#103

So, just to go back over what you said — the new opportunity for Dharavi will only come about once we've delivered these two projects. Is that right?

Prahaladbhai S. Patel executive
#104

No. It's not just two projects — the entire Dharavi redevelopment first calls for 2 lakh houses to be constructed. Once those 2 lakh houses get built in phases, after three years, if we can deliver 40,000 or 50,000 houses, then those 40,000 or 50,000 houses will be moved out of Dharavi to this different new redevelopment location. After that, those lands will be vacated, and only then will the new development of Dharavi begin.

Vishal Periwal analyst
#105

All right, understood. Regarding what your presentation covered, we've put roughly 16,000-plus workers on the project site. Just to grasp how intense that is — how has this figure typically looked historically, and it's reaching 16,000 crore. For context, could you give the earlier figures, what was it before?

Prahaladbhai S. Patel executive
#106

It's really hard to give that earlier figure, since it hinges on the type of work underway at each project. Right now, what I need sits in the 16,000 to 17,000 range, and we're nearly done meeting the needs of every project. At peak load, you could say another 3,000 to 4,000 will still come in over the next one or two quarters, as more and more activities kick off at each project. Certain projects are at the foundation stage, certain ones are in finishing, and certain ones are in MEP. It all hinges on which kind of activity is happening. If it's purely core and shell, then the need is somewhat smaller. But once core and shell wraps up and finishing, MEP, and all of that is underway, there will also be demand from the various trades.

Vishal Periwal analyst
#107

Alright, that's everything I had to cover. Thanks a lot, sir.

Prahaladbhai S. Patel executive
#108

Thanks.

Operator operator
#109

Thanks. Our next question comes from Jainam Jain at DAM Capital. Your line is open.

Jainam Jain analyst
#110

Thanks for letting me ask. Sir, to start, I'd like to get a sense of how costs have been affected by the rise in raw material prices. Of the overall order book, what share is fixed-price in nature?

Prahaladbhai S. Patel executive
#111

As we've mentioned each time, the majority of projects—every Adani project—operate on pass-through costs. Adani's projects haven't seen much of an impact. 30% of the order book, which is consistently part of our order book, was around INR 5,500 to INR 6,000. The recent projects are nearly finished. Rail Vikas Nigam Limited, as Pooja already mentioned, will be completed by October. The Shankaranarayana Constructions tower will be finished by next June 2027. Dharoi package 1 is done; package 2 is underway. Ambaji is a new order for me, so it hasn't had much impact since things are improving somewhat now. We can say that some activities at Shankaranarayana Constructions and Rail Vikas Nigam Limited were affected because aluminum and copper costs rose a little.

Jainam Jain analyst
#112

Alright, sir. For my second question, following the acquisition by the new parent, are there any new segments that we're planning to enter?

Prahaladbhai S. Patel executive
#113

Sorry about that. Could you say your question one more time?

Jainam Jain analyst
#114

Sir, once Adani has acquired us, do we have any plans to move into a new segment? Are we completely planning to enter a new segment?

Prahaladbhai S. Patel executive
#115

No. When it comes to our expertise and the infrastructure we've built up, we'll aim to stay in construction only. But that means constructing anything — industrial, data center, commercial, water, hospital, whatever — just not projects that have nothing to do with buildings.

Jainam Jain analyst
#116

Alright, sir. That covers what I needed. Thanks very much, and best of luck.

Prahaladbhai S. Patel executive
#117

Thanks.

Operator operator
#118

Thanks. We'll take our next question from Rushabh with RBSA Investment. Your line is open.

Rushabh Shah analyst
#119

Okay, can you hear me at this point?

Prahaladbhai S. Patel executive
#120

Yeah.

Rushabh Shah analyst
#121

Yes. I just wanted some clarity on the order book. What might that figure be at the end of March? Is there anything we can share on that front?

Prahaladbhai S. Patel executive
#122

As we've already mentioned to you, I believe we'll be looking at an order book of roughly 5,000 to 6,000 crores. If we get through that, we can execute over 4,000. You can work out what will remain in the order book between those — in that same range plus 1,000.

Rushabh Shah analyst
#123

All right. Sir, I’d like to ask something as well. On the northern side of the state, and in Gujarat and Maharashtra, are they looking out for any major projects? Perhaps even projects.

Prahaladbhai S. Patel executive
#124

No, right now our attention is on our own projects plus the Adani projects. What we're trying to do is get our order book to a 75% to 25% split. Yes, 25% non-Adani and 70% to 75% Adani. As far as visibility goes and where the orders stand, we have enough visibility for the next two years. So at this point we won't be moving into any different region. We'll stay focused on Gujarat and Mumbai only.

Rushabh Shah analyst
#125

Alright, regarding that Dharavi work you brought up, how large is the overall order pool the Adani Group is looking to carry out? And within whatever has to be built for the Dharavi project, what portion would fall to PSP Projects? Is there any

Prahaladbhai S. Patel executive
#126

Giving you an exact share figure is tough, and as I said a couple of minutes back, this is a five-year-long project and they need to deliver 2 lakh houses. If we perform well over the next one and then after two years, we'll get the first site of refusal where Dharavi is concerned. But to finish the project in five years and build 2 lakh houses so that the evidence can be shifted into the new houses and the redevelopment of the Dharavi land can be taken up after five-six years — they may hand it to some other contractors as well. Still, PSP Projects will always hold a better edge when it comes to being part of this Adani Group company.

Rushabh Shah analyst
#127

Regarding capability, since we hold right of first refusal on those first two major instruments, what steps have been taken over the past six months or nine months to make sure we don't stumble on execution — or so that we can at least beat expectations?

Prahaladbhai S. Patel executive
#128

Right, that's exactly what I meant when I said employee expenses this month have come up somewhat. We're growing the team—expanding it so we can scale ourselves to 1.5x to 2x compared with last year. So we're in the middle of building ourselves out so that we can handle more and more orders from Adani Group and get their project delivered on time.

Rushabh Shah analyst
#129

All right, thanks very much.

Operator operator
#130

Thanks. Our following question comes from Jainam Shah at Equirus Securities, whose line is now open — please proceed.

Jainam Shah analyst
#131

Yes. Hello, sir—can you hear me okay?

Operator operator
#132

Yes, sir, we can hear you clearly.

Jainam Shah analyst
#133

Yes. Just a single question. You referenced the building side and also brought up the data center portion. I just wanted to verify whether we have any particular order from the data center, perhaps only the APC work for the building? Do we intend to get into that? What size might we be considering? Since this is a segment that could, shall we say, push our order book much further ahead. What is your thinking regarding that segment? Will it be, say, 10%-20% of our group, or is it simply something we are beginning right now?

Prahaladbhai S. Patel executive
#134

Right now, our focus is on Gujarat and Mumbai — and Mumbai specifically, as we’ve already said, will be a better portion of Dharavi only. Regarding data centers in Mumbai and the new data center coming up in Visakhapatnam, I think as of now we’re not that part. Later on, we don’t know, because again it’s just part of a building only. That could come into our order book. Since we’re going to develop in Gujarat, like Dholera, there are two lands. One is for the data center, and the second is for defense. Those kinds of work can come in the future. As of now, we’ll be focusing on airports, city-side airports, regional realty, their own requirement of a housing colony at Mundra and Madhi city. Madhi city — both the projects — that can come later. First, we’ve already started in Mumbai, and Mumbai it will come after three to four months. Probably these two projects we can consider can be a part of PSP. One is already a part of PSP; the second can be a part of PSP in the future.

Jainam Shah analyst
#135

Understood, sir. All right. That's all from me. Thanks.

Operator operator
#136

Much appreciated. Our following question comes from Urviben Patel at Infinite Wealth Advisors, whose line is now open. Ms. Urviben, are you able to hear me?

Urviben Patel analyst
#137

Hi there.

Operator operator
#138

Yes, sir, we can hear you.

Urviben Patel analyst
#139

Can everyone hear me?

Operator operator
#140

Yes, sir.

Urviben Patel analyst
#141

Sir, I'd like to ask what revenue we brought in from the Precast side during this quarter.

Prahaladbhai S. Patel executive
#142

Look, I believe we don't break out revenue specifically for the Precast side, since the projects we're handling are also part of Precast. There's no separate identity for it, but I think we're improving more and more. Across the year, capacity at the Precast plant sits in the range of INR 200 crore. We'll be executing roughly INR 150 crore to INR 200 crore over the year, whatever the project may be. As for getting an exact revenue figure for Precast, we don't have that number, but generally you can understand that Precast is able to generate revenue of INR 200 crore from the plant side.

Urviben Patel analyst
#143

Understood, sir. Could you give us an approximate figure for the Precast margin, sir?

Prahaladbhai S. Patel executive
#144

That's genuinely a core piece of the business, so it stays within the same margin as the people we're working with. As of today, we aren't working for any other projects except Adani. Previously, we were doing some infrastructure work for L&T. Now our focus is purely on buildings, and those buildings are also tied only to Adani Group.

Urviben Patel analyst
#145

Understood, and thanks.

Operator operator
#146

Thanks. Our following question comes from Shravan Shah with Dolat Capital. Go right ahead.

Shravan Shah analyst
#147

Hello. Sir, just to clarify the Dharavi situation. That order book of INR 3,000 crore that we have — if we convert it into house count, does it cover the full 45,000, 50,000 homes we intend to build, all included in this INR 3,000 crore order book, or would the figure actually be lower than that?

Prahaladbhai S. Patel executive
#148

No, the figure will be smaller. That said, you're right: at INR 3,000 crore, every house falls between INR 10 lakh and INR 12 lakh. If you take 350 square feet at INR 3,500 per square foot as the construction cost, that works out to roughly INR 10 lakh for each house. Which means INR 3,000 crore translates into 30,000 homes we're building at present. Altogether there are 2 lakh homes. So if we look at Dharavi development in its entirety, it comes to 2 lakh homes, and of that total we're currently putting up 30,000 to 32,000 houses through these two projects.

Shravan Shah analyst
#149

Right, so once those two projects are finished, that’s when we can take on the new one — or it could even be work made up of this ongoing effort — and we can also take other Dharavi projects as well.

Prahaladbhai S. Patel executive
#150

Shravan, we need to keep in mind that for most countries, once a project has been settled and it goes beyond the basement and the first to second floor, all the remaining floors are typical. The greater complexity lies at the foundation stage. Once any good site has been settled, you can always begin a new site. But that depends on how well we are established in Mumbai and how we are performing on these two projects. Once we are stable on these two projects, we can always take up a third or fourth Dharavi project.

Shravan Shah analyst
#151

Right, understood. Hetal, for this quarter the tax rate came in at 35%. Looking at the full year, should we expect the usual 25% tax rate, or will it land on the higher side?

Hetal Patel executive
#152

No, it'll be a little higher, because some expenses aren't deductible for tax purposes, so that's a permanent difference. For the year, it will come in slightly higher.

Shravan Shah analyst
#153

Alright. If we consider the cash balance compared with what we report — as of March, we had roughly close to INR 430 crore, INR 431 crore in cash. Against that, as of June, would the cash level be just about the same, INR 400 odd crore?

Hetal Patel executive
#154

Regarding cash — you're asking —

Shravan Shah analyst
#155

Cash and bank, which is what shows up on the balance sheet as what we report.

Hetal Patel executive
#156

Yes.

Shravan Shah analyst
#157

Okay, combining those.

Hetal Patel executive
#158

Yes. It'll be at that same level. Mostly, it will be a little higher.

Shravan Shah analyst
#159

Alright, thanks.

Operator operator
#160

Thanks. Our following question comes from Sanjay Kohli of Goldstone Capital, who is on the line. Please proceed.

Sanjay Kohli analyst
#161

Good evening, and congratulations on the strong sales growth this quarter, particularly with improved working capital — that's really encouraging. Prahalad, you brought up these pass-through cost projects. What margin are you retaining on those?

Prahaladbhai S. Patel executive
#162

The real focus is cost plus a percentage on the total project cost. It isn't about what margin sits on pass-through. Nearly all the materials, whatever we purchase, are always a pass-through. After we grasp the cost side, we set one base as a cost. When we compute cost plus percentage, we apply one X cost, and when we buy it, a difference exists, and that difference has already been paid in the running bill. Hello?

Sanjay Kohli analyst
#163

Hello.

Prahaladbhai S. Patel executive
#164

Yeah.

Sanjay Kohli analyst
#165

All right, I still haven't gotten a complete grasp of it.

Prahaladbhai S. Patel executive
#166

Regarding cost plus percentage, that applies to the project's total cost. So whatever amount we've settled on for overhead, profit, profit on material, and profit on labor, it arrives as one consolidated figure, and that will fall in the 20%-25% range, which is typically where we land. As for each individual material, there isn't a separate percentage per material. That's the point I'm trying to make.

Sanjay Kohli analyst
#167

Right, so the margin gets determined, and whenever that material ends up being used, all of it is already built into the material.

Prahaladbhai S. Patel executive
#168

That's right.

Sanjay Kohli analyst
#169

When it comes to the ongoing billing, that's all built in.

Prahaladbhai S. Patel executive
#170

Right. So it's an item rate contract, and the materials you're using carry a base rate at the time you quote. But when you actually purchase them, any difference — whether it goes up or down — that gap gets settled again through the bills.

Sanjay Kohli analyst
#171

All right. For these cost-plus projects, what's the range — the low end and the high end?

Prahaladbhai S. Patel executive
#172

That's not at all the case. What you were trying to reference is the inflation-related portion of the material — the one that's still underway, correct?

Sanjay Kohli analyst
#173

No, the pre-decided cost-plus — on the last two you mentioned, most of the Adani projects were cost-plus. So what range would that be? 10%-20%, or something along those lines?

Prahaladbhai S. Patel executive
#174

As we mentioned before, regarding the Adani project, the total EBITDA level falls within the 6%-7% range. When we discuss projects that are deep PSE, we've consistently operated at an 8%-9% range. Therefore, at the EBITDA level, you can think of it as a cost-plus formula of 7% at EBITDA.

Sanjay Kohli analyst
#175

Yeah, so that's really tightly controlled. It isn't a wide range at all. It's a very small one.

Prahaladbhai S. Patel executive
#176

Yes.

Sanjay Kohli analyst
#177

The variation between projects is quite narrow.

Prahaladbhai S. Patel executive
#178

Execution always varies by 1%-2%. Every project type has its own standard rates. Working in Mumbai, the difference comes to 3%. Working in Mundra, that difference is 1.5%. So it hinges on the kind of project you're handling, and at times on which overheads we've factored in — that's the project type. On the overhead side, we can then also achieve a saving of 1.5%. So that's one example. After we've gone through it for one or two years, we'll have a clear picture of how this cost-plus formula is complete, but mathematically it comes out at seven.

Sanjay Kohli analyst
#179

Alright, thank you.

Prahaladbhai S. Patel executive
#180

Thanks.

Operator operator
#181

Thanks. Ladies and gentlemen, we’ll treat that as today’s final question. At this point, I’d like to turn the conference back to management for closing remarks.

Pooja Patel executive
#182

We appreciate everyone being here today and taking an active part in this earnings conference call. Our shareholders, the analysts who cover us, and all our stakeholders have our sincere thanks for their ongoing trust, confidence, and support. We hope your main questions have been answered and that we've given you a clear view of how PSP is performing, its growth plan, and the outlook for FY 2027. If anything further comes up, don't hesitate to contact our investor relations advisor at EY, who will gladly coordinate with us and help you offline. Thank you.

Hetal Patel executive
#183

Thanks to all of you.

Prahaladbhai S. Patel executive
#184

Much appreciated.

Operator operator
#185

Ernst & Young here — that wraps up today's conference. Thanks for being with us, and at this point you're free to hang up your lines.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete PSP Projects Limited transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to PSP Projects Limited earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.