Home / Transcripts / PSP Projects Limited (PSPPROJECT) · January 30, 2026

PSP Projects Limited (PSPPROJECT) Earnings Call Transcript

January 30, 2026

BSE Limited IN Industrials Construction and Engineering earnings 56 min

Earnings Call Speaker Segments

Arpit Mundra analyst
#1

Thanks, Hina, and good evening to all of you. I'd like to welcome everyone to the Q3 FY '26 earnings conference call of PSP Projects Limited. Joining us to walk through the results and take your questions is the management team from PSP Projects: Mr. Prahaladbhai Patel, our Chairman and MD; Ms. Pooja Patel, CEO; and Ms. Hetal Patel, CFO. We'd like to note that what we discuss today may include certain forward-looking statements about future events and future performance. A number of factors could make actual results differ materially from those contained in the forward-looking statements. Please be aware that the audio of this earnings call is copyright material of PSP Projects, and it cannot be copied, rebroadcasted, or attributed in press or media without the company's specific written consent. I'd now like to hand the call over to Ms. Pooja Patel, CEO, for her opening remarks. Thank you, and over to you, Pooja.

Pooja Patel executive
#2

Thank you, Arpit, for that introduction. Good evening, everyone, and welcome to PSP Projects Limited's earnings conference call, where we'll discuss the financial performance for the third quarter and the 9 months ended December '25. Our Board meeting concluded earlier today. I'll start with the financial highlights for the quarter and the 9 months of the year. In Q3 FY '26, the company achieved its best ever quarterly revenue, reporting INR 771 crores from operations, which represents a 24% year-on-year growth and an 11% quarter-on-quarter increase. Revenue for the 9 months ended December '25 stood at INR 1,978 crores, reflecting 9% year-on-year growth. This improved performance came on the back of strong project execution, supported by better workfront availability and improved labor deployment. As of 31st December '25, the company's outstanding order book was INR 9,178 crores, registering 43% year-on-year growth. Within this, within-group projects account for 59%, while external projects make up the remaining 41%, that is INR 3,738 crores. We noticed that the order book breakup is missing from the current investor presentation. So we are sharing details of the major external projects for your reference. SMC high rise building INR 835 crores, Gati Shakti Vishwavidyalaya INR 325 crores, development of Dharoi Dam region INR 280 crores, construction of the Fintech building at GIFT City, Gujarat, INR 264 crores, Sabarmati Riverfront Development, Phase 2, INR 245 crores. Order inflow for the company during quarter 3 FY '26 came to INR 957 crores, marking a 151% year-on-year increase. Since inception, the company has completed INR 253 crores, with 82% from private clients and the remainder from government clients. At the end of the quarter, the company is executing 67 ongoing projects, of which 88% are in Gujarat, while the remaining 12% are spread across Karnataka, Uttar Pradesh, Delhi and Maharashtra. During quarter 3 FY '26, the company successfully completed 5 projects, and the major ones among those include Veer Savarkar Sports Complex Ahmedabad, one of the first stadiums for Commonwealth 2030, and aiming for the Olympics of 2036. Terminal 1 and Terminal 2 forecourt area development at Ahmedabad Airport, the Studio Building for CEPT University, and an industrial project for a Tea Processing Facility for Waghbakri Group. The company currently has a bid book of INR 6,600 crores, with 60% from group projects and 40% from external projects. We are pleased to say that within the external bid book, the company has emerged as the lowest bidder for the Ambaji Corridor Development Project, valued at INR 965 crores. Now let me share some project level updates. On SMC, we have completed major work of <<inaudible>> for the project. Currently MEC and finishing work is going on, and facade work will be starting soon. On RVNL, out of 3 buildings, 2 buildings <<inaudible>> is completed, and the third building is going on as per schedule. Currently, MEP and finishing activities are going on. Regarding the Dharoi Project, Phase 1 is currently in a handover stage, and for the Phase 2 project, all the major activities are proceeding according to schedule. Beyond that, in the matter of PSP versus Vivendi BNCMC, PSP Projects was granted a favorable Arbitral Award, which is dated 11th January 2026. Under that Arbitral Award, the Arbitral Tribunal has ordered BNCMC to make payment to PSP Projects of a principal sum of INR 61.44 crores. In addition, BNCMC must pay interest at 9% per annum, 1/3 up to the date of award, with 60 days from the date of award. With that, I would now like to hand the call over to our CFO, Ms. Hetal Patel, so she can share the company's financial performance.

Hetal Patel executive
#3

Thanks, Pooja. Good afternoon, everyone. Here's how the financials looked for the quarter that closed on December 31, 2025. Q3 FY '26 compared with Q3 FY '25. Operating revenue for the quarter came in at INR 771 crores against INR 623 crores, a rise of 24% year on year. EBITDA for the quarter was INR 52 crores versus INR 35 crores, up 47% year on year. The EBITDA margin stood at 6.73% compared with 5.67%. Net profit for the quarter reached INR 16 crores against INR 6 crores, a jump of 159% year on year. In the quarter under review, employee benefit expense rose from INR 33 crores to INR 41 crores year on year, largely because provisions for gratuity and leave encashment went up following application of the new Labor Code notified in November '25. The increase in depreciation from INR 19 crores to INR 24 crores year on year is mainly due to additions to the asset block during the current financial year. In Q3 FY '26 the company incurred CapEx of INR 80 crores. And year-to-date CapEx additions total INR 153 crores. Gross block stands at INR 762 crores and net block at INR 414 crores as of 31st December '25. I'd like to highlight a few important balance sheet figures as of December 31, '25. Long-term borrowing is INR 25 crores, including short-term maturities of INR 16 crores. Short-term borrowing is INR 364 crores, excluding short-term maturities of INR 16 crores. Net unbilled revenue is INR 648 crores. Trade receivables stand at INR 635 crores, and trade payables at INR 436 crores. Retention is INR 163 crores. Mobilization advance is INR 524 crores. Inventories of INR 344 crores consist of INR 175 crores of construction materials, INR 149 crores of work in progress and INR 20 crores of finished goods. Of the total sanctioned credit facility of INR 1,497 crores, the company utilized nonfund-based facilities of INR 703 crores and fund-based facilities of INR 294 crores, and the limit available for utilization is INR 500 crores. As of December 31, '25, the company holds a total of 64 fixed deposits of INR 215 crores, of which lien-free deposits account for INR 43 crores, FDs worth INR 147 crores are under lien with the banks for credit facilities, and FDs worth INR 25 crores have been given as a security deposit to the client. Work on hand as of December 31, '25, is INR 9,178 crores. This comprises 27% order values from government projects and 73% from private projects. Work on hand within Gujarat accounts for 82%, Maharashtra 14%, and the remaining 4% comes from other states. Outstanding value of projects from entities within the group makes up 59%, and external projects account for 41% of the total work on hand; that wraps up the update on the financials. And we are now open for the question-and-answer session. Thank you.

Shravan Shah analyst
#4

I have a couple of questions. First, about the guidance: last time we mentioned revenue of roughly INR 3,200 crores for FY '26. So with 9% growth in 9 months of the fourth quarter, the required rate is too high. Something like 86% growth, around INR 1,200 crores or so. So first, on the revenue side, how much are we expecting for the fourth quarter? And for the whole of FY '26, and if you can, for FY '27, how should one think about revenue? And also, if possible, could you break that down between Adani and non-Adani revenue? That would be helpful, sir.

Prahaladbhai Patel executive
#5

Shravan, first, to answer your first question about overall revenue for this year, I think we have committed somewhere around INR 3,100 crores to INR 3,200 crores, and we will stick to that number because we are confident that the projects now in <<inaudible>> will be able to make it up by <<inaudible>>. For the revenue <<inaudible>> is <<inaudible>>, but mostly it will land somewhere in the range of INR 4,000-plus crores; we are sure of that given the order book we have and the commitment we have made for next year.

Shravan Shah analyst
#6

Apologies, sir, regarding this year, did you mention INR 2,300 crores?

Prahaladbhai Patel executive
#7

It's INR 3,100 crores to INR 3,200 crores, and I already committed to that in the last call as well, so we're sticking with it. As far as planning goes, there probably won't be any issue achieving that revenue, given the pace at which work has been proceeding, and most projects are in the <<inaudible>> phase of finishing. So that revenue should be achievable. As for next year, it's too early to talk about revenue, but once we get through 2026, based on the commitment we made, it ought to land somewhere in the range of INR 4,000 crores to INR 4,500 crores at minimum <<inaudible>>.

Shravan Shah analyst
#8

All right, understood. So given how the work is progressing, sir, in the fourth quarter we ought to be able to hit a run rate of roughly INR 1,100 crores to INR 1,200 crores in order to reach INR 3,100 crores, INR 3,200 crores?

Prahaladbhai Patel executive
#9

Correct. Correct.

Shravan Shah analyst
#10

Yes. Sir, the second point concerns order inflow and margin. We still aren't seeing any improvement in margin. So how should one view the EBITDA margin for the fourth quarter, and for next year or perhaps the next 2 years as well — if someone wants to look at an 8% to 9% margin, which is what we normally used to guide toward, is it possible to achieve that in '27, '28? And for the fourth quarter, how can one — given that revenue will be significantly higher, can we see something like an 8%, 9% EBITDA margin in the fourth quarter itself?

Prahaladbhai Patel executive
#11

Please, Shravan, if you heard Hetal, she already mentioned that there is an incremental operating expense due to employee benefit, to the tune of INR 8 crores, and that applies to this quarter only. If you added it to INR 54 crores, which we have already shown as EBITDA, it comes to INR 62 crores; so if you take that part into account as well, then we have almost reached 7.71%. So what we told you was that we'll be near 7% to 8% this quarter and probably 8% to 9% on average, and that's still achievable. So although it shows 6.7%, 1% — interest or 1% directly because of this new Labor Code.

Shravan Shah analyst
#12

Also, sir, that INR 8 crores of labor loss in the fourth quarter — will that run rate keep going? Or is it a one-time thing that we've done?

Hetal Patel executive
#13

No, no, it's only a one-time effect. We've already taken that effect, this past service cost, so we've taken it to the P&L; and from next quarter on, there won't be any effect from this.

Shravan Shah analyst
#14

All right. All right. And sir, now as far as the INR 5,000 crore order inflow we already have, so how much more are we expecting in the fourth quarter? And that INR 965 crores would have been saved at the start, which we have already received from Adani. So I just want to clarify that.

Prahaladbhai Patel executive
#15

Of the INR 955 crores, I think the split is something like <<inaudible>>.

Hetal Patel executive
#16

<<inaudible>>

Prahaladbhai Patel executive
#17

What portion of that comes from Adani <<inaudible>>, and what portion is <<inaudible>>.

Hetal Patel executive
#18

<<inaudible>>

Prahaladbhai Patel executive
#19

It is 100% Adani Group only.

Shravan Shah analyst
#20

All right. So I can mention that we've reached roughly INR 5,900 crores, INR 65 crores, so INR 6,000 crores, that's our order inflow up to now. So how much more might one expect by the end of March?

Prahaladbhai Patel executive
#21

Of that, INR 3,000 crores is currently under discussion.

Shravan Shah analyst
#22

So does that INR 3,000 leave out this INR 965 crores, or does it take them in?

Prahaladbhai Patel executive
#23

It leaves them out.

Shravan Shah analyst
#24

All right. All right, and from next year on, that INR 7,000 crores, INR 8,000 crores run rate — is that something we can view in terms of order inflow?

Prahaladbhai Patel executive
#25

We ought to view it according to our performance, if we're able to meet what the group requires. I think INR 7,000 crores, INR 8,000 crores should be taken into account for next year.

Vaibhav Shah analyst
#26

So regarding the problem you're having with the UP project — at this point there aren't any overruns in Q3, correct?

Prahaladbhai Patel executive
#27

Correct.

Vaibhav Shah analyst
#28

So the sole one-time item this quarter related to the labor court, and apart from that, the remaining costs are just normal?

Prahaladbhai Patel executive
#29

Yes.

Vaibhav Shah analyst
#30

And then second, regarding depreciation, is that INR 24 crores to INR 25 crores per quarter run rate going to hold going forward?

Hetal Patel executive
#31

Yes, that should hold, since INR 153 crores has already been added by us during this financial year. So each quarter ahead will feel that impact...

Vaibhav Shah analyst
#32

So what's the full-year CapEx figure we're aiming for?

Prahaladbhai Patel executive
#33

Right. Basically, this is meant to be used over the next 2 years, for most of the projects we've started for Adani Group, all of those projects involving new shuttering materials and new equipment such as cranes and other machinery. So this will be — in all likelihood, it will stay as part of depreciation. But at the same time, that revenue will begin next year.

Vaibhav Shah analyst
#34

And what's the CapEx target for the whole year?

Hetal Patel executive
#35

Sorry — the CapEx figure for the entire year?

Vaibhav Shah analyst
#36

Yes.

Hetal Patel executive
#37

So over the course of 9 months, we've expanded INR 153 crores, and beyond that we might be incurring somewhere around INR 40 crores to INR 50 crores.

Vaibhav Shah analyst
#38

So roughly INR 200 crores across the whole year?

Hetal Patel executive
#39

That's right.

Vaibhav Shah analyst
#40

And as we move forward into '27 and '28, will that pattern hold, or could there be some decline in CapEx <<inaudible>>?

Prahaladbhai Patel executive
#41

When you look at the portion of the project that we got from Adani Group, which comes to roughly INR 6,000 crores, and when you take 2% to 3% of that as the equipment share, that's about what we have spent. So likely starting next year, this project—which is already underway—will need somewhat lower CapEx cost, but for any new project the group brings forward, I think CapEx will be required, as well as deferred, but at most, on the order of—overall, we will hold to 3% to 4% of our total revenue, which we will all pay and which is what we have spent each year over the past few years as well.

Vaibhav Shah analyst
#42

Alright. Then finally, sir, about that Bhiwandi award — INR 61.4 crores — will that come straight to us, or could the client head back into arbitration and take it to a further court?

Prahaladbhai Patel executive
#43

The court has set a payment window of 2 months. So once those 2 months pass, if they don't approach the court, the amount has to be reimbursed; and again, past 60 days, the interest rate announced is 11%. Right now the interest from the announcement until today stands at 9%. Later, after the 60 days are done, interest becomes 11%; so let us wait and watch whether they go to another court or not.

Vaibhav Shah analyst
#44

All right, and sir, at this point what would our receivables from SDB be? As I recall, there was some amount still pending.

Prahaladbhai Patel executive
#45

Those receivables are still at the same level we had during the last quarter. The only difference now is that it will be paid with interest, as they have committed, but it remains the same as last quarter.

Vaibhav Shah analyst
#46

Sir, what was the number?

Hetal Patel executive
#47

INR 90 crores.

Prahaladbhai Patel executive
#48

90 crore rupees.

Rahul Kumar analyst
#49

On execution specifically, when you look at what we delivered in Q3, does that match what you were expecting? Or did the quarter bring any difficulties?

Prahaladbhai Patel executive
#50

No, this is what we anticipated, and last quarter I also mentioned that we would be — the issues over the last 2 to 3 quarters stemming from additional costs incurred on the UP-related projects have now been resolved. Broadly, the project <<inaudible>> we are handling is 60% from Adani Group, and most of the Gujarat projects come from others, non-Adani. I'd say it's in line with expectations, all covered within the INR 8 crores provision that was made, which it has perhaps <<inaudible>> it has created. Apart from that, 7% plus 1% comes to roughly 8%, and as I've already stated, we'll aim to reach 8% to 9% starting next year.

Rahul Kumar analyst
#51

All right. All right. Sir, my question was really, when it comes to carrying out the projects, is that in line with what you expected?

Prahaladbhai Patel executive
#52

Sorry, could you repeat that?

Rahul Kumar analyst
#53

What I was asking is this: regarding how the project is being executed, how much of the construction and completion work have you finished? Does that match what you expected? Or did you run into any challenges?

Prahaladbhai Patel executive
#54

Look, it's always better to have more and more — as we said, we can do better and better. But what typically happens involves the environment, meaning the deployment of labor, how available labor is, and the weather; these 3 conditions we've always hoped would go smoothly. Still, depending on what type of project it is, some projects may lack clearance on design or clearance on approvals, and that can land during the good construction season. All the same, I think we may come in roughly INR 50 crores short; apart from that, it's within my expectation.

Rahul Kumar analyst
#55

All right. All right. All right. So, through that quarter, I mean, did anything come up that worked in your favor? And has that kind of gotten better?

Prahaladbhai Patel executive
#56

No, I wouldn't say so. Possibly it does, I suppose, depending on what kind of project it is and whether the funds are available, there can be a shortfall of 8% to 10%, but not really the kind of labor crisis that we typically see during the April to June season. So on the whole, there can be a shortfall of 8% to 10% depending on the situation and where the project is located.

Rahul Kumar analyst
#57

Alright, alright. And I believe you said 14% of the projects we're handling — that are done in Maharashtra. So on that point, what's the receivable situation like there?

Prahaladbhai Patel executive
#58

Yeah. The main project we're working on right now is the mine, and that project already, the <<inaudible>> has <<inaudible>> excavation since excavation of the last layer is underway. So by March, most likely, we should be in a position to begin the foundation, and from that point on we'll be able to bring in more revenue.

Rahul Kumar analyst
#59

Right. Right. On that project, though, are you running into any cash flow challenges?

Prahaladbhai Patel executive
#60

No. There's no need as things stand. As of today, that project doesn't have any cash flow issue, since the investment comes from Adani Group — most of the money <<inaudible>> from Adani Group.

Rahul Kumar analyst
#61

All right, understood. And it seems to me that during this quarter the gross margin declined sequentially, I believe by 70 bps. What would have caused that?

Prahaladbhai Patel executive
#62

As I mentioned earlier, we took a hit of INR 7 crores to INR crores on the — stemming from the labor court decision, and that produced a drop of 1.5%; absent that, last year it stood at 6.5% to 6.71%, and it could have reached 7.71% had that labor court impact not been taken.

Rahul Kumar analyst
#63

No, what I really had in mind was the gross margin line, rather than the EBITDA margin line.

Prahaladbhai Patel executive
#64

The gross margin. What you were getting at is how it moved from one quarter to the next?

Rahul Kumar analyst
#65

Yeah. Compared with Q2, my sense is that it's down 70 bps.

Hetal Patel executive
#66

<<inaudible>> cost, construction cost, is that what you mean?

Rahul Kumar analyst
#67

Yes. Together, construction expense along with materials cost.

Hetal Patel executive
#68

A lot of these projects have just begun, correct? That means they're still at an early stage of execution. So margins could take a hit during those initial phases. As we said last quarter as well, we've launched many new projects. So for that reason, that impact may show up on the <<inaudible>>. So for that reason, that impact can be <<inaudible>>.

Rahul Kumar analyst
#69

Understood. Understood. Understood. All right. And I think regarding the order flow side, I think if I look at Q2 compared with Q3, I think we've actually seen the institutional and government order book go down; so could you help us get a handle on the trends on that 2 front, how does it look, say, right now compared with September?

Prahaladbhai Patel executive
#70

When it comes to order inflow, now that we're a partner with Adani Group, we're getting a lot of inquiries from their side. And we'd like to keep our market presence by thinking about 15% to 20% and non-Adani and 75% to 80% from Adani group. And that's how — we're also not bidding for the smaller projects on the government side. And the project we've bid of INR 967 crores of this Ambaji corridor, it was one of Gujarat's largest and most prestigious projects where we've already <<inaudible>> and we're waiting for that order; so order inflow in terms of government or the non-Adani will be on a selection basis because as far as the group is concerned, we've got plenty of work to do.

Rahul Kumar analyst
#71

All right. All right. And at the moment, how does the order book break down between Adani and non-Adani?

Prahaladbhai Patel executive
#72

40%.

Rahul Kumar analyst
#73

All right. So essentially, that 40% ought to drop to 20%, and as a result of that you're seeing some — okay. Understood.

Vishal Periwal analyst
#74

I believe one question concerns inflow. In the PPT you mentioned order inflow of roughly INR 5,000-odd crores. Yet when we look at the order book, which we usually provide each quarter, the inflow appears to be, well, a somewhat different figure. So some orders are also being cancelled; is it fair to understand that?

Hetal Patel executive
#75

Well, essentially, look, when certain orders are — when certain projects finish, we have to foreclose a certain amount, since even in this quarter we closed some orders. So the order value — the remaining order value has to be short closed; because of that, and also within existing orders there are some where we short closed a certain amount, that amount has been reduced. So that amount may be the differentiator.

Vishal Periwal analyst
#76

All right, all right, all right. Since I believe that figure works out to roughly INR 3,700-odd crores, and the report...

Hetal Patel executive
#77

No, it can't be that high; that's only for this year, somewhere between INR 100 crores and INR 150 crores.

Vishal Periwal analyst
#78

Yes, of course, ma'am. Then, regarding the inflow we receive from the group, I mean Adani Group, what kind of project is it? Is it mostly real estate? The reason I ask is that we've noticed the residential share has grown in the segmental order book as well as in the institutional one, where generally we handle work for, say, educational institutes or, I mean, hospitals; so I just wanted to check.

Prahaladbhai Patel executive
#79

No. Where Adani Group is concerned, I think we hold a smaller order book from realty. The majority of the projects are institutional or their own CapEx, whether that's a residential colony for their Mundra Plant or a residential colony for the Dharavi Project. A few projects relate to airports, and a few relate to their own institutional requirement at Ahmedabad, but not much on the realty side.

Bajrang Bafna analyst
#80

Sir, congratulations on both the growth and the execution side. So my question is about Dharavi. If you could give some guidance on what the development is, because in the recent BMC elections we saw all 5 blocks won by non-BJP candidates from the Uddhav camp and the Shinde, the other NCP camps. So how do you see whether this will create some sort of delay mechanisms or some sort of chaos there on the development part? How do you view this development with respect to the Dharavi project? And also some insights on the Commonwealth Games side, how is the progress, when are the tenders expected and how is this thing going to go through?

Prahaladbhai Patel executive
#81

First of all, this is news I'm hearing from you, that there was — the participant has won the election; so anyway, it is actually not my job who is going to rule as corporators or how it is going to impact us. But until now, there is no impact, and we should not worry about that impact either, because it is, at the end of the day, a group level call; we are just a part of construction. And as far as construction is concerned, we are almost at the finishing of excavation and probably maybe 1 or 1.5 months we'll start the foundation.

Bajrang Bafna analyst
#82

All right. So sir, regarding new order intakes on the Dharavi side, is there any broader guidance or guideline you can provide, and how much would we probably expect in the near to medium-term time frame?

Prahaladbhai Patel executive
#83

We are discussing one more Dharavi project, which is on the Matunga block, and it will be in the range of INR 2,000 crores.

Bajrang Bafna analyst
#84

All right. And in the near term?

Prahaladbhai Patel executive
#85

Yeah. For the most part, it ought to be done by March.

Bajrang Bafna analyst
#86

All right. And sir, regarding the Commonwealth Games tendering and what's expected there?

Prahaladbhai Patel executive
#87

On Commonwealth, an announcement will be made, and I think what we're picking up from news reports — it's the same thing you hear and the same thing we hear. But what we probably know better when it comes to tenders and so on is that a few tenders are going to come for both stadiums, which are yet to be announced. So we're waiting for those tenders to arrive, but technically it falls within INR 7,000 crores to INR 8,000 crores. That said, it won't be a single one — it may perhaps get split into 2 or 3. So we're still waiting to see how the tender starts and how it will be awarded.

Bajrang Bafna analyst
#88

All right, so does this fall into FY '27? We shouldn't expect anything before March, correct?

Prahaladbhai Patel executive
#89

No, no, no. My view is that it won't wrap up during these 3 months. The government ought to be able to finalize it ahead of March and put the tenders out, but as far as contracting goes on our side, <<inaudible>> it could happen next year.

Prajwal Rathore analyst
#90

There's just one point I'd like cleared up. As for the subsidiary we hold, PSP Projects, and the Proactive subsidiary — are any projects being executed there? The reason I ask is that revenue on the consolidated figure has risen compared with the stand-alone number, and previously those two were roughly alike. So what's the right way to think about that subsidiary? And what kind of work and orders is it handling?

Prahaladbhai Patel executive
#91

Well, there are one or two reasons we've made that subsidiary a bit light. We're picking up a few MEP orders, which will form part of new construction, so some of the MEP orders we take in that part. Additionally, certain projects get allocated across labor and materials, so in that area as well we've treated the supplier materials as carrying some profit, and orders get divided into two — services and material. That split is typically something some clients require when they're bringing the project to completion. So they generally request a two-part ordering setup, where one part covers material and service and the other covers material...

Balasubramanian A analyst
#92

Sir, at an earlier point, the Dharavi project got pushed back because of excavation and...

Prahaladbhai Patel executive
#93

Sir, could you speak a bit louder, please? I believe there's quite a lot of noise coming from the surroundings.

Balasubramanian A analyst
#94

Okay. Currently audible, sir?

Prahaladbhai Patel executive
#95

Still little louder, please.

Balasubramanian A analyst
#96

Yes, sir. Sir, regarding the Dharavi project, it got delayed because of excavation and sheet piling, so how is the progress looking at the moment?

Prahaladbhai Patel executive
#97

Is the Dharavi project being denied?

Balasubramanian A analyst
#98

No, no. Excavation and sheet piling have held it up.

Prahaladbhai Patel executive
#99

In fact, it isn't delayed — the thing is, that project calls for going down into a basement, and in Mumbai the excavation work is really difficult until the sheet piling is finished. So first came the sheet piling, which was quite extensive given how big the basement is. And beyond that, once you pass 6 meters, there is always the project where it is <<inaudible>>. So that too takes a bit of time. Blasting isn't permitted for us. So those 2 activities are probably typical in Mumbai, but at least we're now in a good spot in that the excavation will almost be finished, at the most, within the next month.

Balasubramanian A analyst
#100

All right, sir. Sir, the QIP proceeds are being used to repay debt, and what net debt-to-EBITDA ratio are you targeting by the end of this year? And how much interest cost should we expect, say, starting next financial year?

Hetal Patel executive
#101

Sorry, could you repeat that question, please?

Balasubramanian A analyst
#102

Madam, the QIP proceeds are mostly being used to repay debt, so what net debt-to-EBITDA ratio are you targeting by the end of this year? And how much interest cost savings can we expect?

Hetal Patel executive
#103

The QIP we did 2 years back, right? So at that time, we proposed that the funds would be utilized for that. Now the situation is that we have utilized our working capital facilities. But at the same time, we have incurred around INR 150 crores of CapEx for this year. Even last year, we incurred a huge amount of CapEx. So against that, we haven't borrowed any long-term term loan against any equipment; so that is the reason our fund-based facilities utilizations are improving. At the same time, we have to pay advances to suppliers also because our high-value items, they need terms of advances; and because of that, that fund-based facilities need to be expanded for that.

Balasubramanian A analyst
#104

So would it be fair to say that CapEx is mainly covered by internal accruals, or are we considering any debt for that, madam? Because earlier the annual CapEx guidance stood at roughly 3 to 4 percentage of revenue, but we are also planning high-value cranes for precast. So that would take it to 4 to 4.5 percentage of sales.

Hetal Patel executive
#105

Yes. So P.S. sir has already said that this CapEx of INR 200 crores for this quarter might not occur at the same level next year. So the revenue generation will take place over the next couple of 2 years or so. It's like — yes, as you said, 3% to 4% we have to incur; so that revenue will be generated in the next financial year.

Balasubramanian A analyst
#106

All right. That Bhiwandi claim involving INR 250 crores, along with the INR 100 crores arbitration, is still in progress. So when might we see a favorable outcome? And is there any contingency? If one exists, how would it show up in our financials?

Hetal Patel executive
#107

On the Bhiwandi claims, Pooja Ma'am already said during her remarks that the arbitrator has given us a favorable response, and roughly INR 61 crores has been awarded, plus interest up to the date of — up to the date they make payment. So that arbitration process has concluded.

Hemkesh Khattar analyst
#108

At the prior earnings presentation, management gave guidance pointing to an order book of roughly INR 14,000 crores to INR 15,000 crores by the close of FY '26, since they anticipated substantial order flow arriving from Adani Group. So do we remain confident about hitting that order book by the end of the financial year?

Prahaladbhai Patel executive
#109

Look, the present outstanding order book stands at about INR 9,100 crores; so if we get INR 2,000 crores to INR 3,000 crores, which is what we expect by March, then that would land in the range of INR 12,000 crores minus the quarter. So we may not get to INR 14,000 crores, but it will fall in the range of INR 11,000 crores to INR 12,000 crores.

Hemkesh Khattar analyst
#110

All right. Then the other point — could we discuss the EBITDA margin? The EBITDA margins you expect from Adani projects, are they within that same 8% to 10% band you've guided to? Or do they sit at the lower or higher end of it?

Prahaladbhai Patel executive
#111

We've already stated it would fall between 8% and 9%; at no point did we say 8% to 10%. But likely, as we described it — cost plus a percentage — it probably will, and should, come in between 8% and 9%.

Bhavin Modi analyst
#112

I just wanted to ask, given the recent rise in commodity prices, could that have an effect on our margins? And how should we think about it going forward?

Prahaladbhai Patel executive
#113

Look, on the commodity margin, it's mainly aluminum and copper. All those projects we're doing with the government, or where there's a fixed price contract, that gets covered in price variation with the RBI index, so that can have a bit of an impact; but as far as Adani Group projects go, anything tied to rising commodity prices is not going to hit the PSP profits.

Bhavin Modi analyst
#114

So would the price increase basically work as a — would it basically function as a pass-through for Adani projects?

Pooja Dhruve executive
#115

Yeah, that's a pass-through. Yeah, a full 100% pass-through when it comes to Adani Group.

Shravan Shah analyst
#116

Hetal, could you tell me what cash and cash equivalents stood at as of December? In September, that figure was INR 192-odd crores.

Hetal Patel executive
#117

Sorry, I didn't catch the cash and...

Shravan Shah analyst
#118

For September, cash and cash equivalents stood at INR 192-odd crores. So what would that figure look like in December?

Hetal Patel executive
#119

Well, our cash and cash equivalents are largely made up of certain deposits whose maturities fall within 3 months, correct? So the better thing to discuss is the total deposit level; this time around it sits at INR 215 crores; and I believe in September it was higher, somewhere around INR 230 crores; so to that extent, it has come down.

Shravan Shah analyst
#120

All right, but when it comes to how we report the balance sheet — the way we did it in September — that bank and cash total comes to roughly INR 192-odd crores. So compared with that, if I look at it, would the figure really be just INR 10 crores, INR 15 crores lower?

Prahaladbhai Patel executive
#121

Yes.

Hetal Patel executive
#122

Yes, that’s right — look, this cash margin — the cash balance here is going to decline under 3 separate rates. But if what you’re after is strictly short-term current-asset cash, it should sit at roughly the same level. At present it stands at INR 48 crores.

Shravan Shah analyst
#123

Excuse me, ma'am, what was the amount...

Hetal Patel executive
#124

It's INR 48 crores, and that covers solely short-term maturities of 3 months.

Shravan Shah analyst
#125

No, what I was doing was comparing one balance sheet figure with the other. So in September, the way we present the balance sheet, if you look there, it was roughly INR 192 crores, INR 56 crores and INR 136 crores — those 2 numbers were sitting there. So it was against those that I was checking.

Hetal Patel executive
#126

So it's just the same cash, with cash equivalent at INR 48 crores.

Shravan Shah analyst
#127

All right. And then, secondly, on this arbitration, suppose we receive it by the end of March, this INR 61 crores, INR 62 crores — how would that be reported in the P&L? The whole amount would come into revenue and there would be no cost — so the entire thing would flow through to the EBITDA level, and there would be a tax — at the normal tax rate?

Prahaladbhai Patel executive
#128

Yes.

Hetal Patel executive
#129

Yes.

Shravan Shah analyst
#130

And that 9% interest — any rough sense, if it were to come by March, so when does this 9% start from?

Prahaladbhai Patel executive
#131

Up to now, if you work it out from the award date through today — from the initiation date through today, the figure stands at INR 79 crores as of today. So likely by March, there will be an addition of INR 2 crores to INR 3 crores, so we can say it will be approximately INR 80 crores.

Shravan Shah analyst
#132

Right, understood. And sir, regarding the Adani Group's other projects, especially on the airport side — the 2 projects we have in Ahmedabad — how have we begun work there?

Prahaladbhai Patel executive
#133

We're nearly past — 60% — 75% of the basement is done, and at some levels we're already on the ground floor as well. So that project — both projects, the one inside the airport and the one outside — all of them are proceeding at full speed.

Bhavik Shah analyst
#134

Sir, to start off, could you tell me how the bid pipeline currently looks for Adani projects and for non-Adani projects?

Prahaladbhai Patel executive
#135

Well, for Adani it stands at INR 3,900 crores, and the remainder comes to INR 2,600 crores, so the overall order pipeline adds up to INR 6,500 crores; of that, I believe the temple development at Ambaji accounts for INR 965 crores, where we have already submitted the lowest bid.

Bhavik Shah analyst
#136

Sorry, sir, could you repeat that last line? I couldn't hear it.

Prahaladbhai Patel executive
#137

The group project bid pipeline stands at INR 3,900 crores, while the non-Adani figure is INR 2,600 crores. Within that INR 2,600 crores, INR 965 crores relates to temple development at Ambaji, which we've included in the bid pipeline, though that tender has closed and we remain in the running. We're awaiting that order, as Pooja mentioned; so of this INR 2,600 crores, there was the Ambaji temple project at INR 965 crores, a commercial project at Thane of roughly INR 850 crores, which is a private project. There's Umiya Dham at INR 500 crores, a residential tower for SG at GIFT city at INR 253 crores, and an industrial plot acquired at Mankol for INR 100 crores.

Bhavik Shah analyst
#138

Got it. And sir, when it comes to Adani, the Matunga project accounts for INR 2,000 crores; so what makes up the remainder?

Prahaladbhai Patel executive
#139

They have various kinds of projects at various sites. It is a blend of regional growth, with some projects being — if you compare with the Mundra township, certain projects relate to airports. So whenever a project begins, it enters our bid pipeline.

Bhavik Shah analyst
#140

Got it. And sir, from this pipeline, we're expecting INR 2,000 crores to come in during this Q4, correct?

Prahaladbhai Patel executive
#141

Yes.

Bhavik Shah analyst
#142

Alright. And sir, what guidance would you give for next year where inflows are concerned? How much do we expect in, let's say, FY '27?

Prahaladbhai Patel executive
#143

We've already stated that minimum order inflow will be there — at least INR 7,000 crores to INR 8,000 crores coming from the group as and when we begin with this outstanding order of INR 11,000 crores to INR 12,000 crores this year. And if next year we manage to reach revenue of INR 4,500 crores, then from the group side there will be an addition of at least 1.5 to 2x. So on average, INR 7,000 crores to INR 8,000 crores would be added from the group.

Vaibhav Shah analyst
#144

Yes. Sir, back in September our order book stood at roughly INR 9,900 crores, and at present it's INR 9,200 crores. And we've booked approximately INR 880 crores worth of orders. So applying the formula, the order book arrives at about INR 10,000 crores. That leaves a gap of approximately INR 800 crores in the order book. Yet Hetal Ma'am said that only about INR 100 crores was taken out or the scope was trimmed. So how do you account for that gap?

Prahaladbhai Patel executive
#145

Two major projects...

Hetal Patel executive
#146

No, actually, there are INR 143 crores reduction and cancellation only.

Vaibhav Shah analyst
#147

What was the order inflow amount for the quarter?

Prahaladbhai Patel executive
#148

A portion of the project scope has been cut back, which means the order got revised, and for a few of the projects the value was split as well.

Vaibhav Shah analyst
#149

However, that entire figure comes to INR 143 crores, correct?

Executive executive
#150

Certain scope has been reduced and a few projects have also been canceled; it's a combination of both effects.

Prahaladbhai Patel executive
#151

Yeah, it's a combination of the two things. A portion of the projects got revised upward, and a portion of them were also canceled.

Vaibhav Shah analyst
#152

So if you combine both of those things, what's the overall impact?

Prahaladbhai Patel executive
#153

The impact comes to INR 800 crores.

Vaibhav Shah analyst
#154

Alright, alright. Then sir, second thing, inside the INR 9,000 crores order book we hold right now, is there any Dharavi work in there?

Prahaladbhai Patel executive
#155

We've already — Dharavi — Mahim, we've already mentioned that Mahim falls within the Dharavi project.

Vaibhav Shah analyst
#156

And how much is that order worth?

Prahaladbhai Patel executive
#157

It comes to INR 1,300 crores.

Vaibhav Shah analyst
#158

And there's another INR 2,000 crores that we're looking at in the near term — is that the Matunga one?

Prahaladbhai Patel executive
#159

Yes, from Matunga.

Analyst analyst
#160

Could you give me the order book breakdown once more, ma'am?

Hetal Patel executive
#161

What sort of breakdown do you mean?

Analyst analyst
#162

As far as the closing order book goes, the PPT doesn't include the breakdown. Could you go over that once more?

Hetal Patel executive
#163

Yes, I covered that already. Let me just say it again. So government accounts for 27% of order value in the closing order book and private entities make up 73%, right; and within Gujarat it's 82% and Maharashtra 14%, and within that group projects are 59% and external projects 41%.

Analyst analyst
#164

Yes. I was hoping you could give me that breakdown by project.

Hetal Patel executive
#165

All right. Let me walk you through the project-by-project split. SMC highrise building stands at INR 835 crores. Gati Shakti comes to NR325 crores, and the Dharoi Dam project is at INR 280 crores. The Fintech building, INR 264 crores. Sabarmati Riverfront project INR 245 crores. Those are the major external projects we have mentioned.

Balasubramanian A analyst
#166

What's the utilization right now for the precast facilities? And at present, what's our construction level in terms of — how much is external versus internal consumption, and what about external precast orders? And on the external side, are we aiming at industrial, residential, or infrastructure clients for precast solutions? And second, what's the one-time impact tied to labor code implementation in Q3?

Prahaladbhai Patel executive
#167

We've already answered that this is a one-time impact, and as far as precast goes, at present I think 80% to 90% is captive only; we have a few orders from <<inaudible>> mostly inhouse for our projects and Adani projects.

Balasubramanian A analyst
#168

Excuse me, sir, on utilization — are you running at a full 100%?

Prahaladbhai Patel executive
#169

Yes.

Balasubramanian A analyst
#170

Sir, are we running at full capacity, or are we at 50% to 60% utilization?

Prahaladbhai Patel executive
#171

Yes. Right now, we are at a stage where the plant is utilized at 100%.

Bajrang Bafna analyst
#172

Sir, I'd just like to get a clearer picture here. You've given guidance of normalized margins in the 8% to 9% range at the EBITDA level. But looking at depreciation alone, which is presently running at about INR 23 crores each quarter, and then there's CapEx of nearly INR 200 crores that we're doing this year, which will show up next year in depreciation cost. And finance cost is also at roughly INR 40 crores, that kind of run rate at the moment; so I'm just trying to work out what net margin would be there on FY '27 if we assume an EBITDA margin of 8% to 9%? So what normalized net margin could we probably expect?

Prahaladbhai Patel executive
#173

Look, if we take into account the depreciation and finance cost, it's slightly lower, and depreciation stays where it is, then there can be an improvement of 1.5% to 2% on the net margin.

Bajrang Bafna analyst
#174

Apologies, 3% increase to what?

Prahaladbhai Patel executive
#175

Between 1.5% and 2% on top of the current 2.14%, which means it could reach 3.5% to 4% of net.

Bajrang Bafna analyst
#176

Right, 3.5% to 4%. Got it. And sir, this year — during the last quarter, we discussed roughly INR 3,200 crores of top line for FY '26. I was somewhat absent at the beginning. So does that figure still hold, or will it be revised downward?

Prahaladbhai Patel executive
#177

It should land between INR 3,100 crores and INR 3,200 crores, as we had been stating.

Bajrang Bafna analyst
#178

All right. And for next year, is INR 4,500 crores a reasonable assumption? Or will that figure come in lower?

Prahaladbhai Patel executive
#179

As things stand today, that's a reasonable assumption. We should be in a position to give you a clear guideline either in the first quarter or in the second quarter of 2027.

Pooja Patel executive
#180

Appreciate it, Hina, and hello everyone; management at PSP Projects Limited thanks all of you for being with us on today's post earnings call. We trust that most of your questions have been answered. Should anything further come up, you're welcome to contact me or our Investor Relations partner, EY, and they will get in touch with you offline. Hina, at this point we can wrap up the call. Thank you.

Operator operator
#181

That brings this conference to a close on behalf of PSP Projects Limited. We appreciate your participation, and you can now disconnect your lines.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete PSP Projects Limited transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to PSP Projects Limited earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.