Home / Transcripts / Riot Platforms, Inc. (RIOT) · October 30, 2025

Riot Platforms, Inc. (RIOT) Earnings Call Transcript

October 30, 2025

NASDAQ US Information Technology Software earnings 66 min

Earnings Call Speaker Segments

Josh Kane executive
#1

Thanks, Operator. Good afternoon, everyone, and thanks for joining Riot Platforms' Q3 earnings conference call. I'm Josh Kane, VP of Investor Relations, and with me today from Riot are Jason Les, our CEO, Benjamin Yi, Executive Chairman, Colin Yee, CFO, and Jason Chung, EVP and Head of Corporate Development and Strategy. Our third quarter earnings press release and the earnings presentation that goes with it are available on the Riot Investor Relations website; these are meant to complement today's prepared remarks, and they contain a discussion of certain non-GAAP items. Non-GAAP financial measures we provide shouldn't be viewed as a replacement for, or as better than, financial performance measures prepared under GAAP — they're included as extra clarifying items to help investors better understand the company's third quarter performance. On this call, we'll be making forward-looking statements about potential future events. Such statements rest on management's current expectations and assumptions and carry risks and uncertainties. Actual results could differ materially because of factors covered in today's earnings press release, in comments and responses made during today's call, and in the risk factors section of our Form 10-K and Forms 10-Q, including for the three months ended September 30th, 2025, which will be filed later today, along with other filings with the Securities and Exchange Commission. With that, I'll hand the call over to Jason Les, CEO of Riot Platforms.

Jason Les executive
#2

Thanks, Josh. Riot is currently turning itself into one of the most significant data center builders and operators in today's market. Demand for data center capacity cannot be satisfied and keeps rising, and our peerless collection of large-scale land and power assets means we are positioned to seize this opportunity in a major way. I'm extremely thrilled to share that several key milestones have been completed, along with additional strategic initiatives now underway, all forming part of building out our data center business and, on a wider level, part of Riot's continuing transformation. I'm pleased to share some news today: we're beginning core and shell construction on the initial pair of buildings at our Corsicana data center campus, which combined will deliver 112 MW of critical IT data center capacity. We've been securing long lead equipment and preparing to mobilize construction on those two buildings beginning in Q1 2026. This announcement was made possible by four key achievements during the quarter. Riot bought another 67 acres over the quarter, located directly adjacent to the Corsicana site we started with. That purchase makes it much easier to develop all 1 GW of our approved power capacity, and it let us wrap up the campus design for Corsicana, with the intention of converting the entire property into a 1 GW utility-load data center campus. We also completed the basis of design for our standard data center build, which has strengthened how we work technically with Hyperscaler, Neocloud, and Enterprise Customers, and we continued growing our internal data center know-how by bringing on seasoned talent in data center sales, design, engineering, and construction. Taken together, these accomplishments advance the work already underway to transform Riot into a data center enterprise that is large-scale and multifaceted. Money is going into expanding our data center business, since that lets us hold stronger discussions with prospective tenants and capitalize on competitive tension during leasing, with the ultimate goal of getting the most value possible out of our land and power asset portfolio. This 112 MW of critical IT capacity is just the first step we're unveiling from a development pipeline that already has close to 2 GW of secured utility-load power behind it. As our strategy advances and customer talks move forward, expect us to keep sharing additional development plans. Riot is evolving into a major player among data center companies driving the fourth industrial revolution — we've got a sizable portfolio of power that's ready to go, an exceptionally robust balance sheet, and the top-tier people needed to make our plans a reality. We've never seen stronger appetite for data center capacity, and speaking for everyone who holds stock in this company, we're thrilled to be going after the massive chance to create value that sits right in front of us. Riot holds a huge edge right now thanks to our portfolio of power and land that is fully approved — something no one else can match. Those sites sit in data center markets that are in high demand, and we've made real progress expanding our data center operations. That side of the business serves as the foundation, both for squeezing the most value possible out of the power portfolio we hold at present and for keeping up our growth and grabbing new opportunities down the road. Throughout this year, we've wrapped up third-party expert evaluations at our two main locations, Corsicana and Rockdale, brought data center and real estate development expertise onto our Board of Directors, and brought in financial advisors to help with talks involving strategic and financial partners as well as the wider leasing negotiation effort. Just recently, I'm happy to report that we've finished the basis of design for our data centers. Getting that basis of design done has let us go deeper in technical and engineering-level conversations with prospective tenants, start purchasing the long lead-time equipment we need, and start construction on our first two buildings. Later in today's call, we'll go over additional specifics regarding our basis of design. In addition, we've continued to make progress on infrastructure efforts at Corsicana — for example, the 600 MW substation expansion. The first 400 MW auto transformer for that expansion has arrived on-site and is currently being installed. It remains on track to be energized in Q1 of next year. The same applies to core and shell work on the first two buildings in our phase one development plan, which puts us in position to deliver full build-to-suit data centers in 2027. Turning to hiring, we've kept building out our data center team at a brisk pace; key leadership is now in place across product development, construction, engineering, sales, and marketing, and that has let us finish the basis of design and move quickly toward breaking ground. We'll keep carrying this momentum forward by adding more roles that strengthen our data center business and back our future leasing, operational, and growth objectives; we've made considerable headway on our design program, which will serve Corsicana and other sites, and we've finished a standardized data center basis of design that satisfies Tier 3 resiliency and efficiency expectations held by prospective tenants in the market. Advancing what we call our basis of design is really important whenever we're in discussions with prospective tenants regarding specs and customization. With our design philosophy, flexibility comes first, which lets us serve many kinds of potential customers and use cases. That adaptability extends across several building formats — one story, two stories, and three stories — allowing us to get the most out of campus capacity. On top of that, a seven-module, or seven-mod, format sits at the center of our design. Within that format, we've settled on a standardized seven-plus-one component approach: seven components, plus one additional component for redundancy. Whatever a tenant needs, our basis of design can be adjusted with ease. A single seven-mod equals one data hall, and that hall delivers 14 MW of critical IT load capacity. Two seven-mods sit on every floor, so that comes to 28 IT MW per floor. If a building has two stories, it would have four seven-mod data halls in total — two per floor — and that adds up to 56 IT MW. With three stories, you'd get six of those seven-mod data halls, which equals 84 IT MW. We're confident this fits squarely within the topography tenants want, and it also allows us to adapt easily to whatever a given requirement turns out to be. Should a tenant be after additional redundancy, that's something we can build in without much trouble, and the reverse is also true. Riot's basis of design lays the groundwork for how we develop our data centers, and it was engineered in a way that's deliberately repeatable outside of Corsicana, which lets us procure and receive equipment faster and more efficiently for future builds so we can move quickly on whatever market opportunities arise down the road. A key differentiator we're building at Riot is putting together a best-in-class in-house data center team whose expertise spans design, engineering, sales, procurement, construction, operations, marketing, and administration. As you can see here, this expanding team of ours carries deep, directly applicable experience in constructing and delivering mission-critical data centers; we've got the team in place to execute our first phase of construction and development, and together they've completed more than 200 data center projects amounting to close to 5 GW of capacity. Talent for data center development is highly sought after, and we take enormous pride in how much capability and experience we've already managed to bring on board at Riot.

Jason Les executive
#3

The data center group that we currently have assembled is a major edge when it comes to making sure prospective tenants and partners feel assured about our capacity to deliver at scale. Those in-house data center team strengths get additional support from our engineering operation, made up of ESS Metron and E4A Solutions, which delivers integrated manufacturing, commissioning, and maintenance know-how. These mutually supporting businesses generate real synergies and boost our capacity to move quickly on a growing data center development pipeline. During September, we closed on a set of parcels amounting to 67 acres that sit contiguous to our original Corsicana site, for total consideration of $40 million. Riot recognized this tract early on as the optimal location for near-term development of our data centers, and I'm pleased to provide an update on what this purchase has made possible for us. Because the new parcels sit so close to our Corsicana site, development can move fast — they are directly adjacent to the site we already have, so no extra easements or transmission work will be needed, which might otherwise have pushed delivery timelines out. The favorable condition, gradient, and position of this new parcel let us get development underway quickly and reinforce confidence in our delivery timelines. Above all, the added acreage we now hold beside our existing Corsicana site guarantees that we can fully use our 1 GW of fully approved power on Riot-owned land for data center purposes, all within a connected campus layout. Along with the earlier land purchases announced last quarter, Riot now holds 925 acres in the surrounding Corsicana area, locking in long-term development flexibility and fully finishing all land acquisitions needed for potential build-outs. Our enlarged footprint at Corsicana has let us finalize our campus design for the whole site, which we expect to unfold over two development phases. Phase one's development will cover 504 MW of critical IT load, made up of six 56 MW buildings plus two 84 MW buildings, distributed across both the excess developable acreage at our original Corsicana site and the newly acquired parcel directly next to it. As announced previously, core and shell work on buildings one and two is already underway, and we expect the first building to be finished in Q1 2027. How quickly phase one proceeds overall will depend on tenant commitments and leasing momentum, and we are sequencing capital expenditures to maximize power-to-value conversion. Phase two will consist of three 56 MW buildings totaling 168 MW of critical IT load and will, in time, eventually replace our existing Bitcoin mining data centers. Finishing our data center designs has let us move forward on delivering full build-to-suit Tier 3 data centers; with the launch of the development phase for our first two 56 MW buildings at our Corsicana site, we will start construction in Q1 2026 on the core and shell of those first two buildings. The main structure of the data center, along with generator buildings and finished power yards, will be built out and enclosed as part of the core and shell construction. This includes an open interior featuring working elevators, docks, logistics spaces, lighting, fire protection, and security. It will also cover the initial work on electrical, plumbing, and HVAC infrastructure, which is needed to enable the full data center build-out and tenant fit-out. Core and shell building construction will happen in stages, and the first building is anticipated to finish in Q1 2027, after which comes complete fit-out of the data hall with IT equipment, cooling, and power delivery systems. The initial stage of core and shell construction takes the most time but requires the least capital within the build-out, with an expected total development cost of $214 million, or roughly $1.9 million per IT MW across the first two buildings. Starting construction on this schedule, along with buying long lead-time equipment, lets us offer certainty in leasing talks regarding our forecasted energization in 2027. As leasing discussions move forward, we will share cost estimates and timelines for the build-out and delivery of the complete, full build-to-suit for the first two 56 MW data centers. For its Bitcoin mining business, Riot has long concentrated on upholding three strategic pillars: operating at significant scale, producing at low cost, and keeping a strong balance sheet. Those pillars served as the basis for Riot's vertically integrated method in Bitcoin mining and for creating a distinctive portfolio of large-scale powered sites backed by substantial cash and Bitcoin on hand. Our approach to the Bitcoin mining business has shifted as our strategy has evolved. Rather than viewing Bitcoin mining operations as the final objective, we now treat them as a means to an end, and that end is getting the most value from our megawatts. Eventually, that means shifting the megawatts in our power portfolio toward data center development. Ready-for-service power in desirable locations is becoming ever more scarce and valuable, and that is what creates the basis for the tremendous value creation opportunity in front of us. Turning megawatts into money is how we convert that advantage straight into shareholder value. Bitcoin mining remains a highly useful instrument for monetizing Riot's large-scale power portfolio, and our Bitcoin mining business remains very profitable. We will keep using the opportunity Bitcoin mining provides to obtain power and generate robust cash flow, which we will use to fuel the continuing transformation of our business as a whole. We have just gone over our Power First strategy, which is the foundation of our business's evolution. On slide 15, we wanted to give some background on the substantial size and scale underlying Riot's power portfolio. Whereas numerous peers talk about pipelines of prospective projects, Riot's portfolio, which totals over 1.8 GW, is fully approved and available right now. This puts Riot among the largest data center power portfolios in North America. Location also matters greatly. On this slide, you're looking at total megawatts—but every megawatt isn't created equal. Roughly 1.7 GW of our overall capacity sits in the Dallas and Austin areas, which rank among the most desirable data center markets nationwide, giving us strong proximity to established Hyperscaler and enterprise core architecture as well as tenant demand. Slide 16 lays out enterprise value per megawatt for a selection of peers in Bitcoin mining. We see that as a helpful way to understand how the market currently prices power portfolios. Several companies positioned to Riot's left have disclosed lease agreements and watched their valuation multiples get re-rated substantially. Right now Riot trades at a notable discount relative to that peer group, even though we hold one of the industry's biggest, fully approved, and readily available power portfolios. As we carry out our data center strategy and turn megawatts into contracted data center leases, we expect the market will progressively reassess what our power portfolio is really worth through a data center lens, which should drive a re-rating and multiple expansion in our valuation too. Zooming out, as the market matures, we think investors will increasingly draw distinctions based on power quality—that means location, cost of power, schedule certainty and interconnection—along with the credit quality and profitability of the projects and leases underneath.

Jason Les executive
#4

Everything we're doing centers on making progress along those fronts. At this point, I'll hand things over to our CFO, Colin Yee, so he can walk everyone through the financial results for the third quarter.

Colin Yee executive
#5

Appreciate it, Jason. For Q3 2025, Riot brought in total revenue of $180.2 million, which is made up of Bitcoin mining plus engineering revenue, compared with $153 million during the prior quarter — a quarter-over-quarter increase of 18%. Q3 net income reached $104.5 million, or $0.26 per fully diluted share, compared with net income of $219.5 million, or $0.58 per fully diluted share, in the previous quarter. Non-GAAP adjusted EBITDA for Q3 came to $197.2 million, versus non-GAAP adjusted EBITDA of $495.3 million in the quarter before. During Q3, Riot mined 1,406 Bitcoin, compared with 1,426 Bitcoin in the preceding quarter. That slight sequential decline in Bitcoin production resulted from global hash rate growth of roughly 8%, which exceeded the approximately 3% hash rate growth that Riot had deployed. Partly offsetting that were continued improvements in our operating efficiency and utilization rate, which reached 86% in Q3. We raised our utilization rate in Q3 while also relying more heavily on our power strategy, through which we generated $31 million in power credits, lowering our net power cost to $0.32 per kilowatt-hour — and, when adjusted, that equates to $0.032 per kilowatt hour — reinforcing our position as a low-cost leader in the industry. Riot ended Q3 holding 19,287 Bitcoin, with a market value of $2.2 billion as of the close of the quarter. I'll now turn the call over to Jason Chung, Riot's EVP of Corporate Development and Strategy.

Jason Chung executive
#6

Thanks, Colin. Turning to Q3, the benefits of Riot's large-scale, highly efficient Bitcoin mining operations, combined with our unique approach to power, showed up clearly in how profitable our Bitcoin mining business was overall. In that green-highlighted column, you can follow, one step at a time, the primary factors that drove profitability for our operations during Q3 2025. At the top line of our Bitcoin mining business, those factors include the average global network hash rate, Riot's average operating hash rate, the average network hash price, and how much Bitcoin we mined in total during the quarter — all of which together yielded third-quarter Bitcoin mining revenue as reported of $160.8 million. During Q3, our direct cost for each Bitcoin totaled $46,324. We mined 1,406 Bitcoin in that period. Applying that figure yields $95.7 million in reported gross profit from Bitcoin mining, which works out to a 59% gross profit margin. Riot's SG&A across the third quarter was $69.8 million. Non-cash stock-based compensation expense accounted for $32.9 million of that. That leaves Riot's total cash SG&A at $37 million for the quarter. Within Riot's total cash SG&A, there was also $7.5 million tied to temporary litigation costs and advisory fees, plus expenses related to our engineering business. When we separate out SG&A into its cash and non-cash components, the goal is to provide investors with the clearest possible picture of what our key operating segments are really worth. This quarter, our Bitcoin mining and engineering operations showed remarkably strong profitability, and moving forward, we'll keep using the substantial cash flows that our efficient, scaled operations produce to fuel the continued rapid buildout of our data center platform. Our engineering business is a core asset that sets Riot apart in a unique way as we expand into developing data centers at a large scale. In a setting where long lead electrical infrastructure is one of the biggest bottlenecks to development, having the manufacturing set from end to end in-house gives Riot potent strategic advantages. We assembled our engineering platform by purchasing ESS Metron in December 2021 and E4A Solutions toward the end of last year. It merges production, design engineering, and service work into one vertically integrated operation, with data center-grade power systems as its main focus. Although lead times for essential parts have grown longer across the market, owning and managing these functions ourselves inside Riot gives us several advantages: we directly oversee the build-out of critical long lead items, we gain thorough insight into the supply chain, we extend how long equipment stays in service, and we end up with a lower total cost of ownership plus substantial overall CapEx savings for Riot. According to Wall Street analysts, low and medium voltage switchgear ranks among the hardest items to source for data center projects, and our engineering business stands as a top supplier in that space. Bringing these development capabilities in-house lets us substantially reduce risk around the tightest parts of the development cycle. The benefits go beyond cheaper units — we also safeguard schedules, maintain design standards, and make on-time delivery predictable. Those advantages produce value you can measure directly, and they lower the risk involved in converting our megawatts into data center development that creates value. Following the purchase of ESS Metron, Riot has achieved roughly $23 million in total capital expenditure reductions tied to buying equipment up to now, and we expect continued savings along with logistical advantages that will grow in step with expansion in our data center operations. Our operating model keeps scaling in an efficient way, and because our operations have gotten bigger, the outcomes of the effort we've invested in cutting SG&A proportionally and achieving a sturdier cost structure as we move toward developing data centers are now showing up. Over the last 4 quarters, SG&A has stayed about level, even as our revenues climbed by over 110% compared with a year earlier, which shows the substantial economies of scale Riot currently benefits from. This proportionate SG&A decrease rests on 3 main pillars, every one of them put in place across the last several quarters and each becoming more and more evident in our financial results. First, the Rhodium settlement and asset acquisition; during the quarter before this one, we completed settling that legacy hosting contract, which had earlier produced continuing losses as well as litigation expenses. Settling the litigation and acquiring the assets lowered legal expenses and removed a future burden on earnings. Second, a decrease in stock-based compensation. We've already called attention to the accounting effect of the one-time special awards issued during 2024. Non-cash charges tied to that one-time grant, around $25 million each quarter, will fall to roughly $8 million in Q3 2026 and after that drop away completely, substantially lowering non-cash stock-based compensation expense. Third, a progressively more disciplined internal budgeting process; across Riot we've strengthened our accountability-based budgeting and tracking system. Teams today work toward clearer targets, with monthly variance reviews, which produces better predictability in run rate SG&A, stronger coordination between departments, and an ongoing improvement cycle — all of which will matter greatly as we bring on new hires and systems to support business development for our data centers. Taken together, the effect shows up in our Q3 results. Revenue rose to about $180 million, an 18% increase from the prior quarter, even as total SG&A declined and also got much better on a proportionate basis. Crucially, we're combining cost discipline with targeted hiring in essential areas where those hires link directly to growing our data center development capabilities; we're streamlining our cost base, cutting non-recurring burdens on earnings, and have greatly enhanced run rate visibility. What this produces is an organization that is structurally leaner, able to scale data center development with more operating leverage and higher earnings quality as time goes on. I'll hand things back now to Jason Les for closing remarks.

Jason Les executive
#7

Thank you, Jason Chung. At this moment, Riot occupies an unusually strong position. The reason is a combination of advantages that no competitor in our industry can replicate. First, we hold significant power capacity that is shovel-ready in the primary markets where need is greatest. Second, we have a seasoned and credible data center leadership group along with a development organization. Third, our balance sheet is solid, underpinned by more than 19,000 Bitcoin as well as $400 million in cash on hand. Fourth, we enjoy meaningful access to the capital markets. Fifth, our Bitcoin mining operations are large-scale and efficient, generating hundreds of millions of dollars in revenues and cash flows, and those will fund the growth of our data center business. Finally, our management and operations teams are experienced and battle-hardened. With this framework and these strengths in mind, our mission is unmistakable. Riot is going to maximize value throughout our whole power portfolio, aiming to guarantee that all of our available power capacity in pipeline gets fully utilized, so that no stranded power capacity is left behind. We will steadily move power capacity toward data centers, grow our power assets strategically by using Bitcoin mining wherever it gives us an advantage, and give our shareholders greater exposure to assets that accrete value. We sit strategically at the intersection of soaring compute demand and limited power availability, which offers attractive potential for creating shareholder value. Operator, we'll now take questions on the call.

John Todaro analyst
#8

I appreciate you taking my question, and congratulations on all the headway, everyone, particularly over at Corsicana. Wonderful to witness. Clearly, quite a few leases have now been inked in this area. Could you provide us with an update, specifically regarding the talks you're having with prospective tenants for those initial few builds, and what remains to be done on your end to secure a finalized lease? Then I have one more question.

Jason Les executive
#9

Certainly. Once more, I appreciate that inquiry. There's nothing I can say about any particular talks currently underway, yet here's what I can share: our present standing in the marketplace gives us a great deal of encouragement. Naturally, everyone knows there is this tremendous surge happening with AI, and together with it comes an appetite for electricity that cannot be satisfied, and it continues expanding across every participant in the market: Hyperscalers, Enterprise Customers, Neoclouds. Every one of these firms faces severe constraints on power. Only this week — specifically during earnings calls held yesterday among Hyperscale companies — we picked up further remarks suggesting that, if anything, the power bottleneck is getting worse. It appears data center infrastructure expansion will probably continue for years ahead. Their demand keeps rising, and they continually believe they will manage to catch up, yet they never do. In the past they attempted to build independently, and at present they seek third parties to lease from so they can fulfill their data center requirements. Meta remarked that they continually think they are either being too aggressive or being extremely aggressive and overbuilding, and they continually discover they have come up short instead. Plenty of favorable remarks that I believe confirm the approach we are pursuing and confirm the worth of the assets we hold. I would also note that we place great emphasis on high-quality prospective tenants; the reason is that we place great emphasis on constructing this data center business at Riot upon a solid foundation. Such tenants carry immense power needs and CapEx budgets, yet they are also extremely cautious about committing to the projects they seek. They require substantial certainty regarding delivery timelines and those ready-for-service dates, and they want very little risk concerning power approvals and permitting and matters of that kind. That explains why we have labored so diligently and have devoted the time to undertake these essential measures that de-risk our sites and guarantee maximum credibility so we can deliver against the timelines they seek. We have accomplished that through the team we installed, finishing our basis of design, and now progressing with technical and engineering discussions, and now kicking off development of the core and shell buildings at Corsicana. What I would say is that every step we have taken was taken to position Riot ahead of top-tier prospective tenants and set us up to execute on leasing and then align our capacity to deliver with the timelines that these. One more thing I will mention is that everything you hear regarding how short the market is on power for at least the coming few years and how frantic demand is for anybody able to reliably deliver power inside that window — that is entirely true. We have repeatedly heard from leading industry experts, from partners, and prospective tenants about. The case working from the commission holds strong validity regarding the power available. There's still a lot of interest coming our way regarding that site; we're feeling quite positive about the current state of things; the actions we laid out earlier in the year — which we saw as essential for getting Corsicana prepared and positioned as appealingly as possible for development — are now done; we believe we're sitting in an excellent spot to keep moving ahead. That's really what's driving the news we shared today about kicking off core and shell construction at Corsicana. That covers it; wonderful. Extremely useful. As a quick follow-up, you brought up the tight power situation, something we're all clearly observing too. Given that, is there any extra power available out there that your team might still secure? Are you still feeling at ease? Is there simply more capacity out there that perhaps you could bring in to grow the pipeline? Maybe, say, power that could come online prior to 2028. Could you perhaps lay out some of that as well on the supply side and what more you might be able to obtain. Sure. We're working very hard to expand our power pipeline past the 1.7 GW we currently hold at Corsicana and Rockdale. I'll hand that question to Jason Chung for additional detail. Appreciate it, Jason. Thank you, John, for asking. We're staying quite busy examining ways to grow our power portfolio. A great many chances keep landing on our desk. Our team invests considerable effort assessing each of these possibilities. Even so, we currently have an enormous value-creation opportunity in front of us, and that genuinely is where management's main attention lies. We do review opportunities and will move when one is attractive enough for us to pursue, though possibly with a somewhat elevated bar for where we direct our time and resources, considering what our power portfolio still requires in terms of development today.

John Todaro analyst
#10

Understood. Appreciate the answers, gentlemen. Thank you.

Paul Golding analyst
#11

Thank you very much, and congratulations on the site progress and the basis of design. I'd like to ask — it sounds like proactively starting construction on that 112 MW of core and shell isn't a shift in approach, since you're still pursuing prospective Hyperscale tenants. Could I ask, regarding maybe Jason Les's remarks about enabling the best possible negotiations and gaining leverage in them, whether you could shed some light on how having those shells built before a deal is signed — one that might arrive later — plays into these conversations and where it factors in? Does the lead time let you command a higher price? Is it perhaps assisting you in drawing in counterparties with stronger investment-grade ratings? A follow-up regarding the ESS Metron and engineering segment remarks. Seeing how much revenue has expanded there and the backlog that has accumulated, how do you plan to balance third-party engagements for that segment against internal ones, given the project you're doing at Corsicana? Thank you.

Jason Les executive
#12

Thank you, Paul. I'll address your question. Your question has two parts, so let me take the first part. The first point I'd like to emphasize is that, to be clear, what we're announcing today regarding the core and shell development is not a change in our strategy. What I'd like the market to grasp is that this is a reveal of our strategy and how we understand we can serve the market best in this location. Our focus is owning and operating build-to-suit data centers, and the team we have at Riot is fully capable of delivering on that. What we offer the market, which matters greatly to every kind of customer, but especially Hyperscale customers, is a project with risk removed. I believe that comes across. Our power approvals are secured. We hold up to 1 GW of utility power in Corsicana. That power is operational today. We can show customers that this power is valid. We have a team whose experience runs deep in constructing the sort of data centers we're discussing — build-to-suit tier three data centers in the configurations Hyperscalers seek. We also hold a balance sheet capable of backing this project's development. With today's announcement, we're demonstrating that core and shell construction for the data center is already in progress. Every one of these factors lets us convey the degree of certainty around power ready-for-service dates that Hyperscale tenants demand. Another point I'd like to make is that what we announced today in the development and the core and shell represents the initial step toward eventually building out a complete tier three data center. What we're discussing is shell. That comes to $214 million, or $1.9 million per IT megawatt; in fact, it's slightly more than merely a powered shell. Along with the watertight structure itself, we're finishing out generator buildings, elevators that are completely functional, admin spaces that are fully completed, systems for controlling security access, and distribution of power. What we're really constructing is done in such a manner that we supply the elements we're aware every Hyperscaler is going to need, and we're situating these structures so that they can turn into tier three data centers quite fast once tenant specs get locked in. That's possible because our crews possess deep expertise and understanding when it comes to putting up this kind of data center and grasp how to make them work for any prospective tenant, all while giving that tenant room to satisfy their own particular specs. We're additionally buying equipment and securing our delivery schedules at this point, so the completed data center can align with when Hyperscale and Enterprise Customers typically make their purchases. I realize that's quite a bit, so allow me to wrap up with this. The strategy we're carrying out puts us ahead of the best tenants out there and gives us greater certainty regarding how and when we'll come through for them and come through on constructing complete build-to-suit data centers. All of this falls within the framework of getting the most value out of the assets we hold. In the end, my belief is that what we announced today signals how confident we are in our strategy and in our team's capacity to build out the data center business successfully on the timeline we picture. Your question about engineering. ESS Metron and E4A Solutions, which together make up Riot's engineering business, bring plenty of strategic advantages. Our main motivation for buying these companies is to gain control over our supply chain and reduce its risk; additionally, in our presentation, Jason Chung discussed the cost synergies we're capturing there too. Riot actually represents a modest share of ESS Metron's business as a whole. Data center projects account for 90% of ESS Metron's business — in fact, several of the largest such projects in the nation, ones I'm sure you're familiar with. Their own business keeps expanding, and they can juggle the internal demand coming from Riot alongside the rising demand shown by the growing backlog across all those data center projects nationwide.

Paul Golding analyst
#13

Thank you very much.

Greg Lewis analyst
#14

Hello, and good afternoon — I appreciate you taking my questions. Jason, I'd like to hear a bit more about phase one: specifically, your thinking on the sequencing, and why you decided on two buildings rather than one or three, plus how we should view the timing around construction of the shells. Is the next phase really going to hinge on the customer, with us essentially waiting to see what the customer wants before moving the shells forward?

Jason Les executive
#15

Yes, thanks for asking, Greg. As for the core shells, development is already underway. Here's what stands out: Corsicana is a site where we're already up and running. Naturally, the substation there is live as well. For these initial two buildings, the pad is finished — this project is quite far along, so only the structures themselves remain, with construction kicking off in Q1 2026. We're targeting completion of the first core and shell during the first quarter of 2027. Since what we're putting up goes somewhat past a standard core and shell — internally we refer to it as core and shell plus — once that's done, we can move very rapidly toward delivering build-to-suit turnkey data centers. Our development roadmap is only getting started. At Corsicana, the campus can handle a minimum of 672 megawatts of IT load, and what we're putting out there now is only 112 megawatts. How quickly we reveal additional projects will hinge, in my view, on what the industry needs and how fast talks with customers move along. Given the demand we were observing and the nature of the conversations we were having, we believed it was critical to kick off development immediately. As our strategy advances and discussions with prospective counterparties move forward, you should expect us to share news about further developments. All right. That's really useful. Adding more buildings is a fairly straightforward process for us. The two buildings we've been discussing here are just the start. Should a customer come to us needing far greater capacity than those provide, we're set up to quickly launch further developments that serve their requirements. That puts us in a strong spot to stay flexible and move aggressively on schedules.

Greg Lewis analyst
#16

All right. That's really useful. I know there's likely much more to cover regarding Corsicana. I was hoping we might hear some perspective on Rockdale. When we consider it, clearly everybody has described Corsicana as among the top data center locations in the U.S., because of its scale, its size, and how close it sits to Dallas. Could you share a bit about your thinking on Rockdale? Does that require us to truly finish building out Corsicana before we shift and begin pursuing opportunities at Rockdale, or do you believe we might be able to pursue both at the same time?

Jason Les executive
#17

Yes. Thanks for bringing up Rockdale, Greg. Rockdale possesses many of the same traits that make Corsicana such a compelling location for data center growth. Much like Corsicana, Rockdale features large-scale secured power that is active and running right now, 700 MW fully approved, with electrical infrastructure already built. Remember, we already run one of the biggest Bitcoin mining data center campuses anywhere in the world at that location. It is a live operating facility, and it also offers abundant land, water, and fiber capable of meeting potential tenant needs, and it sits very near Austin, a top technology hub. Taken together, we believe this positions Rockdale as a highly appealing site. Above all, having that power approved and in use right now substantially reduces the risk of development execution from a prospective tenant's standpoint, and that provides them with more confidence in what's possible. Currently, we are working to boost how attractive Rockdale is for prospective tenants with high credit quality. As we do that, we keep our attention on Corsicana as our near-term development opportunity. Right now, Rockdale gives Riot added optionality for future expansion of our data center business; at the same time, our mining operations there keep producing solid cash flow and help fund our expanding data center business. Corsicana is the near-term priority for data centers, yet Rockdale represents the next logical phase in that process. I want to stress that Rockdale should not be excluded from our development pipeline while we keep working to get the site ready for tenants in the interim. I have confidence in our capacity to execute there.

Greg Lewis analyst
#18

That's really useful. Thanks. Have a good evening.

Reggie Smith analyst
#19

Hi, everyone. Nice work on everything you've accomplished. I've got 2 quick things to ask. I really like that you're considering how to get the most out of the electrons at both of your locations. I was wondering, where do you stand right now on Neocloud? Could you walk us through the upside and downside of turning into a Neocloud similar to Iron or another company, and what your thoughts are there? I have 1 follow-up. Thanks.

Jason Les executive
#20

Yes, Reggie, I appreciate the question; we're constantly trying to get the most value out of our megawatts. That's a topic we consider and assess at all times. In our view, the ideal initial move for Riot to capture maximum value is to concentrate on this build-to-suit colocation approach. Our sites sit in highly attractive places. They come with highly attractive ready-for-service dates. We think the greatest way to realize value at present is to construct data centers and get them leased to top-tier tenants. That's the reason we're centered on projects capable of supporting a broad range of the market. We're centered on constructing data centers able to satisfy the requirements of any Hyperscalers, able to support every kind of Enterprise Customers, and able to support Neoclouds too. Naturally, that means it might support an in-house Neocloud operation should we choose to pursue that path. That's something we'll consider and are currently assessing, though build-to-suit is the top priority at present. We're not ruling that out, but as of now, build-to-suit is the direction you're headed.

Reggie Smith analyst
#21

Great. So, for my second question: over the past two months or so, we've watched a number of transactions get signed in this sector. In my view, none of those have the prime positioning that you two enjoy, given how near you are to a big metropolitan area. Are conversations with customers increasing, or do you figure you're seeing a larger share of inference customers, of site inquiries? When a deal does get signed, should we anticipate stronger pricing on account of your positioning relative to other locations? Or, at the very least, are you advocating for that? My assumption is that this becomes a bargaining point where your team is thinking, "We hold excellent sites, so whatever might have been accepted at a more isolated site, we will demand a premium for." Is that the correct frame?

Jason Les executive
#22

Yes. In my view, it's our sites' positioning, along with the fact that we're ready to serve sooner, that puts us in a position to land the strongest deal available. Given what we hold, we're confident we can demand highly attractive economics. There are two sides for us. One is the economics of the deal that we're confident we can lock in using the assets we hold, and the other is the caliber of tenants that we're confident we can bring in using those same assets. Based on how much interest we've already gotten, I'd tell you we're quite confident right now that we could readily sign a contract with a Neocloud. What we're aiming at is constructing a platform capable of serving a variety of prospective tenants: Hyperscalers, enterprises, and Neoclouds. Our top goal is to establish our data center business atop a solid foundation. In our view, that means that given what we hold, we can draw top-tier tenants, and that—past mere name recognition and past whatever financial terms we secure in the lease—delivers advantages to Riot when it comes to creating value and obtaining appealing project financing terms. It's two sides, Reggie. Our assets, in our view, can both demand highly attractive economics and, thanks to the properties themselves, draw very high-caliber tenants.

Brett Knoblauch analyst
#23

Hi, everyone. Thanks for taking my questions. I believe it was only as recently as June that you hired Jonathan to sort of head up the data centers team. I'm wondering where else on the hiring side you've brought people in and how much further hiring you still need to do? Or do you feel that team is more or less fully built out now?

Jason Les executive
#24

Yes, indeed. I appreciate you asking that. A key focus we keep returning to is expanding our workforce. The approach we take is to grow that workforce in step with whatever stage the company has reached. Picture a pendulum, if you will: the initial push emphasizes roles in development and engineering. Once that development and engineering phase moves forward, momentum shifts toward sales, and later it shifts toward operations. During the third quarter we brought on several important new people, which puts us in position to carry out the development portion of our business. Naturally, we continue to bring in more talent in that area, yet we already possess the people required to move ahead. Quite recently we filled a sales role — our Senior Vice President of AI Hyperscale Sales — because the emphasis is now shifting away from development and more toward sales. I would describe ourselves as extremely happy with the caliber of people we have managed to draw to Riot. I view that as proof of how good our assets are. Our power, our capital, and every other strength Riot possesses. It has turned Riot into a highly appealing destination for seasoned data center professionals to advance their careers and get the chance to help build something enormous starting from nothing. The speed at which we have added some remarkable people to our bench has delighted me. As that pendulum keeps swinging, you will keep seeing us add more of those people to match the business cycle we find ourselves in.

Brett Knoblauch analyst
#25

Great, thanks. So as a follow-up — I’m not sure whether you addressed this or it slipped past — regarding that 400 MW being allocated to Bitcoin mining at Corsicana: is that possibly the final power source you’ll tap as you continue expanding on the AI side? I suppose the question is whether you’ll continue Bitcoin mining until that power is needed.

Jason Les executive
#26

So, yeah, if you look at slide 11 in the earnings deck, there's a campus layout there, and basically we're splitting it into 2 phases. Phase one involves constructing on every bit of the unused land we have at Corsicana. What that means is we keep enjoying the robust cash flow generated by that location, which currently ranks among the biggest Bitcoin mining sites anywhere in the world. While we're putting up the other buildings there, that location keeps producing and throwing off significant cash flow for us. After the land we have available is used up — and under our plans, that would involve constructing roughly 504 MW of critical IT load — then the phase two option, or part of the plan, would involve building on top of where the existing Bitcoin mining buildings sit and adding the remaining 356 MW buildings, the last critical IT capacity at that location. Our plan is to ultimately replace that, and how quickly that happens will depend on customer demand, on the marketplace dynamics we're observing, and on how our leasing is going. Everything is viewed through the goal of getting the most value out of every megawatt we have, aiming to leave no power unused as we push hard to expand the data center business. In the end, our goal is for that whole site to become a 1 GW utility-load data center campus.

Brett Knoblauch analyst
#27

Great. Thanks so much.

Mike Grondahl analyst
#28

Hey, appreciate it, everyone. I wanted to build on what you said earlier about growing the pipeline. Are there any targets set internally for how far you might extend that pipeline by the close of 2026 or during 2027? And second, over the coming 90 to 120 days, which steps matter most for getting the next stage delivered?

Jason Les executive
#29

At this moment, there aren't any objectives we're making public, though I'd note that we understand how valuable power is, and we know we're capable of obtaining it. Riot has shown it can obtain power at scale — one slide in our deck shows this — at a scale that competes with the largest data center firms globally. If you hold an edge, you use it. Our aim is to use that edge and apply whatever tools we have available to bring additional power into our pipeline. In the end, the story wouldn't stop with Corsicana or Rockdale alone, but would continue with other sites we add to that pipeline. Beyond saying that building this pipeline is a strategic priority at Riot, there's nothing more I can offer. As for the most important steps across the next 120 days, I believe those will focus on development moving forward at the two core and shell projects we're announcing today; to hit the timelines we've set out here, we anticipate starting construction in the first quarter of 2026. On our side, we'll keep pushing forward on development and on more detailed designs for what we're developing. What we'll do internally is carry on the technical outreach we've already been doing, talking with possible parties and possible tenants so that we keep moving toward a design matching their requirements. Someone outside wouldn't be able to observe that progress, but from the inside, that's what we're focused on over the next 120 days.

Mike Grondahl analyst
#30

Nice work on the HPC milestone, everyone.

Dillon Heslin analyst
#31

Hi, appreciate you fielding my questions, and congratulations on what's happening at Corsicana. To start, Jason, you said the Corsicana design might be repeatable outside of Corsicana. Does that mean a separate master site design for Rockdale isn't necessary, or can you explain a bit more about what you meant?

Jason Les executive
#32

Appreciate that. Yes. What we call our basis of design is something that will work in any location where power is available to us. That basis of design exists today, and applying it to a given site is the step we refer to as localizing that standard design for the particular site. The land profile at whichever location determines the specific layout, yet the same kind of building gets constructed. Because a standard design is in hand, we can be far more efficient when it comes to procuring equipment and coordinating schedules with contractors and those contracting partners, development partners, construction partners, since everyone knows precisely what is being built. That same standard design gets adjusted at the endpoint for particular tenant specifications and afterward localized at whatever site it sits on. As I mentioned, campus layout, meaning where buildings actually go, will hinge on the site's land profile. That's why this basis of design mattered so much to us. It's truly the cornerstone of our entire development program at Riot for data centers; we aren't simply building a data center for Corsicana; we're building a design we can keep refining and deploy wherever we manage to secure access to power.

Dillon Heslin analyst
#33

Great, thanks. To follow up on that: once those initial two PowerShell Plus units wrap up at some point during Q1 2027, is that the milestone prospective tenants have to witness you hit before talks about a lease can move forward, or are you in conversation with them the whole way through?

Jason Les executive
#34

The whole way through is how we'd be engaging with them. I believe that's the schedule; that's when the core and shells are set to be finished. A key reason we kicked off this core and shell work is that it opens the door to a more productive conversation with prospective tenants. Our expectation is that we'd be further into our sales and leasing efforts even before those core and shells get done.

Dillon Heslin analyst
#35

Great. Thank you.

Nick Giles analyst
#36

Hey, thanks for fitting me in. So my first question: right now you've got $330 million sitting on the balance sheet, and clearly quite a bit of Bitcoin too — $214 million for the core and shell. What I want to know is whether there are other significant capital expenditures we ought to be factoring in for 2026, things like deposits on long lead time items, or any other pieces in motion we should keep in mind? My sense is you've mostly finished the land acquisitions you intended to make, but any detail would be appreciated.

Jason Les executive
#37

Our complete 2026 CapEx budget hasn't been published yet, but given the development plans we shared today, at this point the bulk of it would be that $214 million for the first two core and shells. That said, it doesn't mean we aren't making any progress on the long lead time equipment. Even with no deposits, we've managed to lock down most of the equipment needed for those first two buildings. Naturally, we also have in-house capabilities we're leveraging to secure supply chain. Our approach to securing this long lead time equipment is highly capital efficient. It all ties back to the strategy of positioning our capital deployment and ensuring those two items stay closely synced up. Through our development strategy, we're always set up to move quickly to the next step based on what the tenant wants.

Nick Giles analyst
#38

Thanks for that, Jason. If I could squeeze in one more. You said something about 672 MW of critical IT being roughly the floor at Corsicana, as I recall. That would suggest a PUE slightly under 1.5, I believe. What I want to know is whether anything is being done right now to make that better, or what steps could eventually raise the critical IT megawatts at Corsicana?

Jason Les executive
#39

Yeah. Before I answer that, I wanted to tack on one additional point regarding the earlier question you raised. Beyond the cash sitting on our balance sheet, restricted cash included, we currently hold roughly $400 million in our sizable Bitcoin position. On top of that, we run a strong Bitcoin mining operation that throws off solid cash flows, and that truly is a hugely important and valuable instrument for financing all the buildout we have underway. As for your newer question about PUE, what we've presented is essentially our base case. That represents the baseline PUE we're aiming to hit. Naturally, any gain in PUE translates into better economics for us. Our base case sits at approximately 1.49, and at this point we're aiming to do better than that, and the stronger the PUE we can get, the stronger the eventual economics our projects deliver.

Nick Giles analyst
#40

Everyone, thanks for all the detail. Keep putting money to work, and good luck.

Jason Les executive
#41

I'd like to express my gratitude to each of you for tuning into today's earnings call. We couldn't be more thrilled about how far we've come and the strategic milestones we're unveiling right now. I'm eager to report additional developments as we achieve them, and to reunite with all of you on the earnings call that comes next. Thanks so much.

Operator operator
#42

Thanks. That brings our call to a close. We appreciate everyone for joining in. At this point, you're free to hang up.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Riot Platforms, Inc. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Riot Platforms, Inc. earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.