Riot Platforms, Inc. (RIOT) Earnings Call Transcript
November 4, 2026
Earnings Call Speaker Segments
Thank you, operator. Good morning, everyone, and welcome to Riot Platforms' third-quarter 2026 earnings conference call. This is Josh Kane, Head of Investor Relations, and joining me today from Riot are Jason Les, Chief Executive Officer, and Jason Chung, Chief Financial Officer. The third-quarter 2026 earnings press release and the accompanying earnings presentation can be found on the Riot Investor Relations website; they are intended to supplement today's prepared remarks and include a discussion of certain non-GAAP items. The non-GAAP financial measures we provide should not be viewed as a substitute for, or as superior to, financial performance measures prepared in accordance with GAAP, and we include them as additional clarifying items to help investors better understand the company's third-quarter 2026 performance. The figures we’re giving you for lease revenue and net operating income on our Corsicana lease are management estimates shown before tenant reimbursement amortization—something that, under lease accounting rules, will bring reported lease revenue down across the lease term. You can find how we’re presenting these numbers explained in the presentation’s footnotes. On this call, we’ll be offering forward-looking statements regarding possible events in the future. Such statements are based on what management currently expects and assumes, and they carry risks and uncertainties. Real outcomes may vary significantly because of items covered in the earnings press release issued today, in remarks and answers given on this call, and in the risk factors portion of our Form 10-K and Forms 10-Q — among them the one covering the three months that ended September 30th, 2026, which is set to be filed later today — along with additional filings made with the Securities and Exchange Commission. On that note, I'll hand things over to Jason Les, CEO of Riot Platforms.
Thanks, Josh, and good morning to all of you. We're delighted to share today that Riot has executed the biggest lease agreement in the company's history: a 15-year triple net powered land lease covering our entire Corsicana campus with a leading frontier AI lab, which represents 910 megawatts of critical IT capacity. This deal is the strongest proof so far of the company Riot has evolved into: a top-tier digital infrastructure developer that serves the leaders at the cutting edge of the AI ecosystem. With this lease, Riot has 1,151 megawatts contracted across three agreements — involving AMD and a top frontier AI lab — every one of them inked this year, totaling about $38 billion in contracted data center revenue, or $72 billion if all extension options get exercised. When fully deployed, we expect these leases to generate $2.2 billion in average yearly net operating income, at an unlevered yield on cost of roughly 28% across our lease portfolio. Four accomplishments show where we stand today. To start with Corsicana: our agreement with that frontier AI lab ought to generate approximately $28 billion of contract revenue over the initial 15-year period, and close to $54 billion assuming both of the five-year renewal options are taken up. Most of my remarks today will focus on this deal, because it does more than simply add scale — it fundamentally changes the shape of Riot's business. A year ago, Bitcoin's price determined our cash flow. As of now, with the deals we've already signed fully deployed, virtually all of the cash flow we expect will derive from long-term leases with major players in the AI ecosystem. On top of that, this structure lowers our capital intensity to about half of what a tier 3 build would require, leaves operating and technology risk in the tenant's hands, and was built with financing in mind. Next, at Rockdale, construction and long-lead procurement are moving forward on our 191-megawatt frontier AI lab deployment, which is still on track to deliver its first phase in December 2027. We're finishing up credit support for the project's debt financing with a high investment grade counterparty, and meanwhile the Morgan Stanley interim facility is covering development costs. Third, we continue to deliver for AMD. The 25-megawatt buildout is proceeding on schedule and within budget. The next 10 megawatts will come online this month, and the entire expansion is expected to be online in May 2027, bringing AMD's total online capacity to 50 megawatts. The bank project finance process for the AMD lease continues to advance and should close shortly. Fourth, our financial position remains solid; we have sold down most of our Bitcoin treasury to fund our data center business, bringing our holdings to just over 2,400 Bitcoin at quarter-end. We've also paid off the whole $200 million Coinbase credit line, which frees up all the Bitcoin we'd pledged as collateral. We ended the quarter with $950 million in total liquidity: $748 million in cash, counting restricted cash, plus $202 million in Bitcoin. So far in 2026 we haven't brought in any equity capital, and Jason Chung will walk through more on that later in this call, but for now we don't anticipate issuing equity to fund any of the projects we've announced. Taken together, all this gives Riot a data center portfolio backed by long-term, high-margin contracts, a number of non-dilutive ways to fund development, and the flexibility to direct future cash flows toward whatever use creates the most value per share. Now let's turn to the Corsicana announcement. Ever since we started transforming into a top-tier digital infrastructure developer, we've concentrated on getting the most value we can—adjusted for risk—out of our big power portfolio. Our lease with a top frontier AI lab achieves that goal. You'll notice this deal is structured differently from our Rockdale leases, and that's deliberate: it mirrors the exceptional value an asset like Corsicana carried in the market. During the process we talked with several counterparties and weighed various structures, and in our opinion what we're announcing today is a fantastic result for extracting value from our crown jewel asset, especially when you factor in risk. Rather than having Riot design and build a tier 3 data center, the agreement we signed with the frontier AI lab at Corsicana is a triple net powered land lease. Riot supplies the land, the power infrastructure, and the powered pads, whereas the frontier AI lab buys, installs, owns, and runs a modular compute deployment on those pads, using a design the tenant created, and carries every operating cost, power included; this split of duties reshapes the capital equation. We anticipate total project capital of about $6 million per IT megawatt, which is roughly half the capital intensity of our tier 3 build at Rockdale. That breaks down as $2 million per megawatt for sitework and electrical infrastructure that Riot will build out, plus $4 million per megawatt that Riot will hand back to the tenant to cover its costs. The key point is that these reimbursements come phase by phase, and only once each phase has been delivered and has started paying rent. This deal's structure also shifts the power math. Our original tier 3 basis of design had Corsicana supporting up to 756 IT megawatts. With this lease in place, that same 1 gigawatt of utility load now supports 910 IT megawatts — which means 20% more leasable capacity out of power we already own and control. To wrap up, the lease was structured with financing in mind: project debt calibrated to the contracted rent, a rent credit provision should that debt fail to materialize on comparable market terms, and Riot's equity portion anticipated to come from existing liquidity. Jason Chung will soon detail the funding plan further. Now I'd like to address the economics behind this announcement. Across the initial 15-year term, the lease should produce total contract revenue of roughly $28 billion — about $1.8 billion in average yearly rent, factoring in escalators and prior to the lease accounting amortization of tenant reimbursements that Josh mentioned. Since the tenant covers nearly all operating expenses under the triple net structure, we project an NOI margin of about 99%, which works out to roughly $1.8 billion in average yearly net operating income across the term. Measured against total capital of $6 million per IT megawatt, or about $5.5 billion, that produces an unlevered yield on cost of roughly 33%. At that yield, the project recovers its capital in about three years, with no leverage involved, on a 15-year lease. We expect full deployment of the first phase in September 2027, with the entire campus delivered by July 2028, and the frontier AI lab holds two 5-year extension options past the initial term. This ranks as one of the largest single data center leases ever disclosed in our industry, and among all leases in our portfolio it has the lowest operating and capital risk profile. Toward the bottom of the slide, you can see how the deployment is structured across three phases: 400 megawatts in September 2027, which is roughly 10 months away; 200 megawatts in January 2028; and the remaining 310 megawatts in July 2028. The full 910 megawatts will be delivered within two years of signing. Slide 9 details which party is responsible for what under the lease, since that division of responsibilities is what drives the risk reduction. Riot's obligations appear in the left-hand column. We construct and supply the powered pads along with medium voltage power supply, and we hold ownership and maintenance responsibility for the high and medium voltage power infrastructure feeding those pads. Within operations, our involvement is confined to the power infrastructure we own, landscaping, and security at the campus perimeter. Regarding the tenant side, the frontier AI lab handles procurement, installation, and ownership of the compute modules; it covers 100% of actual utility costs, which include demand, capacity, and tariff charges, structured as a pure pass-through without any markup. Under a triple net structure, the tenant likewise bears all operating expenses, and over the term it is accountable for any alterations and lifecycle capital expenditures, excluding Riot-owned power infrastructure. We pay rent on all 910 critical IT megawatts whether or not we use them, and for every phase the rent starts within 60 days of that phase's power pad being handed over. As for Riot, the risks we're not taking on are development of the data hall, operation of the mechanical and cooling systems, SLA exposure across hundreds of megawatts of compute, the expense of redesigning whenever chip generations shift, power price risk, and utilization risk. What stays with us is the portion of the value chain we control best: land, power, and the infrastructure that brings it. The way this deal is put together differs fundamentally from the majority of data center leases you could compare it to, and it delivers considerably more value to Riot shareholders, since the risks tied to building, sourcing, delivering, and running data center projects day to day are much lower. We've established a split of duties that shortens how long it takes before rent starts coming in from the tenant and safeguards that rental income across the lease period. With that said, I'll pass it over to Jason Chung, who will walk us through how Corsicana will be financed.
Thank you, Jason. Slide 10 carries a simple point. Through the Corsicana lease structure, our capital requirement comes down, and we gain several routes for funding the remainder — none of which relies on equity issuance. To begin with the capital needed: across 910 IT megawatts, total project costs come to roughly $5.5 billion, made up of $3.6 billion in tenant reimbursements at $4 million per IT megawatt plus $1.8 billion for sitework and infrastructure at $2 million per IT megawatt. As Jason mentioned, those reimbursements arrive only once each phase is delivered and the tenant starts paying rent, so we never fund reimbursements in advance of contracted cash flow. Turning to where that capital comes from: our plan, labeled path A on the slide, is to fund Corsicana using non-recourse project debt sized to contracted rent. At an illustrative loan-to-cost financing ratio of 80% to 90%, that produces non-recourse project debt of about $4.4 billion to $4.9 billion, drawn as sitework is finished and as every phase is delivered and starts paying rent. Riot keeps the full contracted rent minus debt service, while our cash equity covers the balance — about $500 million to $1.1 billion — against roughly $1.2 billion of near-term liquidity, a topic I'll return to on slide 18; we expect to launch this financing process in 2027, before the first phase delivery. The lease also shields us should that debt fail to be available on comparable market terms. In such a case, the tenant would fund reimbursements at the outset and recover them as credits against rent, amortized across the remaining lease term. Under this path B scenario, no external financing would be needed to fund reimbursements to the tenant, and Riot would keep flexibility to fund the $1.8 billion of sitework costs using cash, debt, or a mix of both, based on rent credit-adjusted cash flows. Those rent credits would carry an implied interest rate of 12%, and path A remains our base case. This structure provides Riot with three non-dilutive layers of funding for Corsicana: non-recourse project debt, the lease itself, and our own liquidity. No single source of capital is required for this project, and under either path Riot will still own the land, the power, and the site infrastructure, collecting 15 years of take-or-pay rent on 910 IT megawatts, while the tenant funds and owns the compute. With that, I'll hand it back to Jason Les for an update on Rockdale and AMD.
Thanks, Jason. Now, on Rockdale, I want to cover what's happening with both our frontier AI lab and AMD. On the left-hand side, you can see the schedule for the 191-megawatt lease we signed with a leading frontier AI lab, announced last quarter, which should bring in roughly $9.1 billion of contract revenue across its initial 20-year term. This marks Riot's first full tier 3 data center project, and it's hitting its ready-for-service dates on time and on budget. Two factors got us here. First, we locked the design with the tenant early, which allowed us to hold advanced discussions and start procurement with key suppliers for long-lead equipment. Next, we're leveraging our in-house engineering resources at ESS Metron and E4A Solutions, along with numerous vendors that our tenants favor, which eliminates the majority of timeline risk; construction is already progressing, and the initial 96 megawatts are expected to be operational by December 2027, while the other 95 megawatts should come online in June 2028. Regarding funding, we're completing arrangements for credit backing on the project's debt from a counterparty with a high investment grade rating, and project finance preparation is advancing simultaneously, with the launch to occur after signing. In the interim, the Morgan Stanley bridge facility is covering procurement and construction costs, and the timeline is not dependent on the timing of that closing. Now regarding AMD: the initial 25 megawatts came online and reached full stable operation during May 2026, while the complete 50 megawatts remain on schedule for service readiness in May 2027. AMD stands as the demonstration of how Riot performs. Our in-house engineering, our own switchgear production, and a design tailored to what the tenant needs allowed us to move from signing the lease to a stabilized 25 megawatts within four months. AMD continues to hold options to expand by as much as another 150 megawatts at Rockdale. On Slide 12 you can see all three leases side by side; during 2026, Riot has locked in roughly $38 billion in contracted data center revenue spanning 1,151 megawatts of critical IT capacity with top participants in the AI ecosystem. The table lays out each lease, and I want to draw out three key takeaways from it. First, on the totals: we're looking at roughly $2.3 billion in average yearly revenue and $2.2 billion in average annual NOI once fully deployed, against total capital of $7.7 to $7.9 billion — that works out to an unlevered yield on cost of about 28%. Second, on margins: NOI margins range from 80% at AMD, to between 80% and 90% for the frontier AI lab tenant at Rockdale, up to around 99% at Corsicana, since the tenant there covers nearly all operating costs under the triple net structure. Third, on timing: AMD hits full deployment in May 2027, the frontier AI lab tenant at Rockdale in June 2028, and Corsicana in July 2028. Every one of the 1,151 megawatts is operational inside 20 months. Add AMD's choices to grow by another 150 megawatts, and the contracting opportunity comes to roughly 1.3 gigawatts. Contracted revenue, a set capital budget, and a transparent financing approach—those are the basics on which we believe Riot should be assessed from here on. Slide 13 shows how lease income climbs as each phase starts operating. At present, 25 out of our 1,151 leased megawatts are live. Come the close of 2027, that figure grows to 546 megawatts, once AMD's second 25 megawatts, the initial 96 megawatts for the frontier AI lab at Rockdale, and the opening 400-megawatt phase at Corsicana are all brought online. Once Corsicana's second and third phases plus Rockdale's second phase come online by the middle of 2028, the full 1,151 megawatts will be operating. On the revenue side, lease income rises from about $23 million in the current year to approximately $250 million in 2027, $1.8 billion in 2028, and $2.3 billion in 2029 — the first full year in which every phase is in service. That ramp is significant for two reasons. First, it forms the revenue foundation against which Riot will be valued going forward. Second, it serves as a meaningful funding source in its own right, because rent generated by the earlier-delivered phases will help pay for phases that come later, a topic we'll cover further on slide 18. Slide 14 lays out our approach to capital allocation. Once those 1,151 megawatts are under contract and the contracted assets are fully deployed, generating over $2 billion in yearly NOI, the real question is no longer whether Riot can get leases signed — it's how we'll put the cash those leases generate to work. Every dollar we allocate gets measured against a single standard: will it deliver the most value per share? We look at three ways to use capital, and each one is weighed against that standard. The first is expanding the power portfolio — constructing or acquiring energized megawatts for data centers we'll develop later, but solely in cases where the return, adjusted for risk, sits comfortably above our cost of capital and stacks up well against the portfolio we already hold. Second, keeping our financial flexibility intact: project-level debt that carries no recourse to Riot, plus capital that gets recycled from one project into the next, which is exactly what we're doing with our AMD financing. Third, giving capital back to shareholders when our own shares offer a better return than the next project would, or once our growth is fully funded. As contracted cash flows start coming online, returning capital turns into a real and recurring part of this evaluation. Four criteria fit under all three: returns well above our cost of capital, leverage sized to contracted rent, liquidity sufficient to fund every announced commitment, and equity only where an investment is meaningfully accretive on a per-share basis. That explains why we haven't brought in any equity capital during 2026 and why, given the projects we've already announced, we don't anticipate needing to. Our thinking is straightforward: a portfolio with the strongest risk-adjusted profile generates the steadiest cash flows, and those steady flows open up the broadest set of options for compounding value on a per-share basis. Before turning things over to Jason Chung, I'd like to take a moment to walk through our pipeline for future growth. Since Corsicana is now entirely leased and Rockdale is largely committed, further expansion is going to come from fresh development capacity, and we're chasing that through five verticals: adding capacity at our current sites by way of extra acreage and utility relationships; buying and developing grid-powered land that has near-term approved capacity; self-generation behind the meter in places where grid constraints make it necessary; corporate acquisitions that deepen our engineering, products, and services platform; and strategic partnerships along with joint ventures. That pipeline will be pursued with the identical discipline that built the portfolio you see today. Right now we are deeply engaged across each of these avenues, with teams dedicated to forging Riot's future growth. Every possible use of our money will be evaluated alongside the risk-adjusted returns already secured and against all our other capital options. Having said that, I'll now pass it to Jason Chung for the financing update and our quarterly results.
Thank you, Jason. I want to start by returning to the four financing principles we laid out earlier this year, and show how each is being carried out in a tighter credit market—one defined by higher interest rates, credit-led spread widening since September, and lenders digging deeper into tenant credit, power, and delivery track record. First, liquidity: our response to a more volatile market and the Bitcoin drawdown has been to turn Bitcoin into cash ahead of committed equity needs, keep no collateral pledged, and manage liquidity against each project's equity requirement. Through this year to date, we've sold 20,264 Bitcoin, generating $1.5 billion, fully repaid the $200 million facility from Coinbase, and released all 5,821 Bitcoin we had pledged, finishing the quarter with $950 million in liquidity. On the second point, access: we've put front and center the three things lenders examine most closely—tenant credit, power that's already interconnected and energized, and a delivery track record backed by our in-house engineering, manufacturing, and procurement. We're cultivating relationships across a range of funding sources so diversification is maintained. This covers roughly $750 million in facilities that have closed or should close before long: the $573 million interim facility with Morgan Stanley and the $180 million AMD term loan plus a delayed draw facility, while the Rockdale and Corsicana project financings advance behind those. Third, cost: since tenant credit and structure are what drive spreads in today's market, we align the credit basis to each individual project. For Rockdale, AMD holds investment grade status as a tenant, and we expect the term loan to price near SOFR plus 250 basis points—about $0.01 per diluted share, with power at roughly $0.032 per kilowatt hour. Rockdale also involves our lease with a leading frontier AI lab, which should carry high investment grade credit support, and we are steering that debt toward bond execution. At Corsicana, the lease is built to be financeable: capital needs are much lower than for tier 3 builds, it's a triple net lease, delivered capacity is take-or-pay, and reimbursements come phase by phase once rent begins. Fourth, discipline: our project financings will be non-recourse to Riot and sized to contracted rent, and spend gets released as each financing closes. On cost, we've negotiated—and will keep negotiating—fixed price and guaranteed maximum price contracts, with more visibility and control coming from our in-house manufacturing and procurement. Those four principles produce the line at the bottom of the slide: no equity raised in 2026, and none currently anticipated to fund any of our announced projects. Moving to the following slide, we'll outline the capital sources sitting senior to Riot's equity. That leads me to slide 18, where we address a question investors frequently ask: how can Riot cover all of this without selling equity? Let's begin on the uses side. For Corsicana and Rockdale combined, the total capital for the projects is roughly $7.6 billion to $7.8 billion — more precisely, $5.5 billion goes to Corsicana while $2.1 billion to $2.3 billion is set aside for Rockdale — and on top of that there is additional AMD CapEx that we plan to finance through the AMD bank facility, which is in the process of being finalized. Inside that number, project-level debt — non-recourse to Riot and sized against the contracted take-or-pay rent at an illustrative 80% to 90% of project capital — should land at about $6.1 billion to $7 billion. What's left is an illustrative Riot cash equity requirement of roughly $800 million to $1.5 billion, invested as development moves forward starting now and running through mid-2028 as each financing closes. Now let's go through where that capital comes from. Near-term liquidity is approximately $1.2 billion, made up of $950 million in cash and Bitcoin, $110 million of other anticipated near-term inflows, and $180 million in proceeds from the AMD term loan that we expect to be available at closing. On top of that, after Corsicana's final phase is handed over, the rent already contracted from Corsicana phases 1 and 2 plus our Rockdale tenants adds about $900 million before debt service. That lifts total cumulative sources to roughly $2.1 billion — above Riot's cash need in every leverage scenario in the illustrative range: $1.5 billion at 80% loan to cost, $1.2 billion at 85%, and $800 million at 90%. Timing is on our side. Because reimbursements are paid out only once each phase is delivered and producing rent, the sources come in ahead of the uses. And that number still leaves out other non-dilutive funding sources we didn't put in that chart. First, contracted rent from Corsicana phase 3. Second, the land, substations, and power infrastructure Riot already owns at Corsicana could potentially be contributed as sponsor equity and counted toward lenders' equity requirements, which would cut our cash needs even further. Third, refinancing stabilized lease-backed assets releases Riot equity from completed projects for the next phase — exactly what we're doing with AMD. And fourth, a future parent-level facility, like a corporate revolver, to cover early-stage development costs and working capital, drawn only when needed. Put simply, Riot has multiple layers of non-dilutive funding sitting ahead of any equity issuance, and right now we don't expect to issue equity to fund any announced projects. Moving to our third-quarter financial results on slide 20. Riot's third-quarter 2026 results showed total revenue of $181 million, up 1% from the same period last year. Data center and engineering revenue increased by $46 million, which helped offset weaker Bitcoin mining revenue, given an average Bitcoin price 38% lower than in last year's third quarter. GAAP net income was $4 million, or $0.01 per diluted share, while adjusted EBITDA reached $191 million. Net income takes in $124 million of depreciation and amortization, $21 million in stock-based compensation, and an $18 million non-cash impairment, partly offset by a $172 million gain on the change in Bitcoin's fair value, which sits inside adjusted EBITDA. Turning to our data center segment, we finished the quarter with 25 megawatts of critical IT capacity that was both contracted and delivered. That segment generated $18 million in total revenue, including $8 million from operating leases at an 80% operating lease gross margin — right in line with the economics we had underwritten — plus $10 million of tenant fit-out, which fluctuates with the development cycle. Annualized, base rent from that initial 25 megawatts comes to roughly $31 million, matching the AMD economics on slide 12, and it steps up as the next 10 megawatts come online this month. On to Bitcoin mining: Riot's third-quarter output was 1,637 Bitcoin, averaging 17.8 Bitcoin daily. We closed the quarter with 44.9 exahash per second deployed — roughly 4.9% of the global network. The quarter's average operating hash rate was 36.2 exahash, reflecting summer curtailment under our power strategy, including the 4CP program. Those curtailment efforts produced $25 million of power credits, or $15,067 for each Bitcoin mined, lowering our net power cost to 3.2 cents per kilowatt-hour — among the lowest in the industry. As a result, mining cost us $39,265 per Bitcoin directly, before depreciation. We ended the quarter holding 2,418 Bitcoin. At the September 30th closing price of $83,554, that holding was worth $202 million. For comparison, we held 11,380 Bitcoin at the close of the second quarter. The reduction was intentional. Data center development has been funded mainly through our Bitcoin treasury, and we expect to keep selling nearly all the Bitcoin we mine. Revenue in our engineering segment came to $47 million, over twice the year-earlier figure, with a 15% gross margin. That margin reflects a sizable, low-margin cable procurement order at E4A. We anticipate an improved mix in the fourth quarter, which should lead to higher margins. Our backlog is $142 million, and data center work makes up more than 90% of it. We have deliberately reserved some capacity for Riot's own projects; ESS Metron provides the switchgear for Rockdale and should do the same for Corsicana. Segment detail for all of our businesses is in the appendix. I'll now hand the call back to Jason Les.
Thanks, Jason. If you turn to Slide 22, you'll get a picture of how the year adds up for us. Execution is what has characterized 2026. In January we completed the purchase of land at our Rockdale site and signed our very first data center lease — with AMD. Then in May we delivered AMD's initial 25 megawatts, on time and on budget. In the third quarter we signed a 191-megawatt lease at Rockdale with a leading frontier AI lab. And since then, we've signed the 910-megawatt lease at Corsicana with that same frontier AI lab. From here on out, delivery is the whole game. AMD wraps up in May 2027; Corsicana's first phase and Rockdale's first phase follow by the end of 2027; and every remaining phase is delivered by July 2028. Twelve months ago, Riot had no data center lease revenue at all. By 2029, contracted lease revenue reaches approximately $2.3 billion a year, and each megawatt behind it is already under contract. All that remains between now and then is execution — and that is precisely what this team has delivered all year long. When we shared at the start of this year the potential we saw in our power portfolio, we gave a total portfolio net operating income range of $1.6 billion to $2.1 billion; with the leases signed this year, we now expect to exceed the top end of that range, with average annual NOI of roughly $2.2 billion on contracts already in place. We still have more room to grow through the unleased power capacity that remains at our Rockdale and Kentucky sites. On top of that, the vast majority of that NOI carries meaningfully less delivery and operational risk than standard data center leases in the market. Now that our existing portfolio is substantially leased, growth from here will come from the pipeline I described earlier, pursued with the same discipline and weighed against every other use of our capital. Our priorities going forward are clear: deliver AMD, Rockdale, and Corsicana on schedule and within budget; complete the Rockdale and Corsicana financings and broaden access to additional sources of liquidity; and put capital to work where it is most accretive, whether that means developing our power pipeline or returning capital to shareholders. Riot is a data center infrastructure platform. We hold the scarcest inputs in this industry: land, fully approved power, and the infrastructure needed to deliver it. We've leased that capacity to leaders across the AI ecosystem on long-term contracts, with different solutions for different customer needs. The result is a portfolio built for superior risk-adjusted returns, with multiple non-dilutive ways to finance development, and a company with the cash flow and discipline to put every dollar to its highest and best use; on behalf of our entire management team, I want to thank our shareholders, our tenant partners, the communities we serve, and our employees for their continued support. With that, we'll now open the call up for questions. Operator?
Hi everybody, congratulations on Corsicana — that really does look like a solid lease. I want to ask about Rockdale. Given the cost overruns the industry has dealt with lately, why are you confident that $11 to $12 million a megawatt for CapEx development costs at Rockdale will be sufficient? And following up on that, what share of that project cost is fixed or under contract at this point? Which portions could still move? If costs end up above your estimates at Rockdale, who carries that risk?
Appreciate the question. I'll start with Rockdale, then talk about Corsicana along the same lines, and after that get into who holds the risk here. Regarding Rockdale, what gives us confidence is the effort we put in before signing. One of the main points we've emphasized to the market over the last several months is that signing a lease isn't just about securing power—it's also about the product being built for the tenant. That's why we invested heavily in design and pricing before we committed to a number. Because of that, our design has reached a fairly advanced stage, and we're finalizing costs and phases with our general contractor. As each scope matures, the GC puts that trade package out for competitive bids, and the complete scope is placed under a guaranteed maximum price, working toward a final GMP for the whole project. We're closing out that guaranteed maximum price with our general contractor today, and we anticipate about 70% of the overall budget will fall under the GMP. That's also the crucial thing about when costs become fixed; it's not tied to hiring a GC; it happens once a scope enters GMP, and that's precisely where our attention is at the moment. The remainder of the Rockdale budget covers OFCI, which we've already started procuring, and we anticipate finishing the ordering of that equipment within this month. As a result, we're confident in keeping our estimate in the $11 to $12 million per megawatt range for the Rockdale build. You may not have raised Corsicana, but while we're on this topic I'll address it too. It's structured differently, and our exposure is much smaller there. About 70% of the capital we have in it is a capped contribution, structured as a tenant reimbursement for modules the tenant is buying on its own, so that figure won't increase. At Corsicana, the remaining spend is smaller in scope, and within that reduced scope, first, our procurement process for the OFCI portion of that development is already underway, and we expect to finish ordering the longest-lead items by the end of the year; then, beyond OFCI, we will use GMP contracts, just as we do at Rockdale. Now, finally, regarding who bears the risk: in our leases, the lines are drawn clearly. First, if the tenant changes what it wants, the tenant pays. Each lease includes a change order procedure in which modifications get priced in advance and are either reimbursed or rolled into rent alongside schedule relief. Second, after a scope falls under that GMP I mentioned, any costs beyond that price become the contractor's responsibility, and when it lands below, we split those savings with them. Third, certain risks remain ours; those include scope outside the GMP, site condition expenses, and the OFCI equipment I referenced that we purchase directly. Those aren't passed along to tenants. Rather, we handle them by procuring our critical equipment early, addressing tariff and material escalations via contracts containing escalation tables, plus carve-outs and contingencies we retain, and by holding reserves for labor should the market tighten. While a GMP won't wipe out every risk—and I'm not going to pretend otherwise—our confidence in the $11 to $12 million per megawatt numbers we've given for Rockdale comes from how it was designed from the start, the locked-in pricing across phases, and lease language that plainly states which party covers which costs.
Hey, that's wonderful. Thanks so much, and congratulations once more.
Hi, everyone, good morning, and nice work on the Corsicana deal.
Thanks, Stephen.
I'd like to dig a little deeper into the deal. The specifics really interest me, and you've given us plenty of strong detail — it's pretty compelling. Could you maybe start by taking us through how you thought about going with one tenant for the whole site, and how that process unfolded and ultimately got signed?
Appreciate the question. From our perspective, it became obvious very early that the entire site would be taken down by a single tenant. We concluded that this was both the optimal result for Riot and the outcome most likely to happen. Two factors explain that. First, although the site could be split up, doing so would add operational complexity and cut the amount of leasable space, which in turn would lessen the overall value created. Second, essentially every prospective tenant we approached showed interest in the whole site. It is such a valuable asset. If a party is at ease with a portion of the site in this constrained environment, it stands to reason that they would want the entirety. Once we reached that conclusion, we evaluated multiple structures and prospective tenants, eventually choosing the approach we felt would deliver the strongest risk-adjusted returns for shareholders. Recall our Q2 earnings call in August: we stated on that call that we held an LOI covering the whole Corsicana site, totaling 756 critical IT megawatts. As talks with our tenant progressed, circumstances shifted, and we finally arrived at a structure that secured for Riot the appealing economics such a site as Corsicana requires, while giving our tenant what it needed to meet its accelerated time-to-compute goals. Though it isn't a conventional built-to-suit arrangement, it's an outstanding result for Riot. Another point on the structure and how we arrived here: it let us provide greater capacity than the 756 megawatts we initially anticipated under that first LOI. We now stand at 910 total critical IT megawatts under a take-or-pay agreement. That happened because our tenant sought to maximize the site's overall potential capacity, even if that meant utilization levels varied at certain times of the year. No matter the utilization, once delivery is complete, Riot collects rent on all 910 megawatts. So the tenant ends up with more usable capacity, and we end up with a larger capacity base on which we earn rent. All in all, it's a situation where everyone comes out ahead: we can generate meaningful average yearly NOI while putting up far less money than a conventional construction would require, and our tenant simultaneously got to roll out the speedier modular approach they were after.
Understood—that's quite clear. Several aspects of this transaction caught me off guard, and the 910 megawatts was one of them. Perhaps just a single follow-up. I'd like to hear you expand a bit on the deal's actual structure and economics. Many investors, myself included, were picturing something closer to a conventional tier 3 build at Corsicana. Could you elaborate on what led you to proceed with this structure, and how this transaction should be viewed alongside others we've observed in the market? You've already outlined somewhat your thinking on why this deal is appealing. I simply want to confirm I grasp, from your vantage point, what makes it the most appealing.
Certainly. Since the beginning of our transformation here, we've stated that maximizing shareholder value on a risk-adjusted basis was our objective. We take enormous pride in how this transaction achieved that; in our view, it's a hallmark structure, combining best-in-class yield on cost with a best-in-class risk profile. What this deal produces is a triple net rental rate at the high end of the range for tier 3 data center builds, yet we're only required to spend half the CapEx of a typical tier 3 build. Our CapEx scope here greatly constrains our procurement and construction risks, and combined with the operation responsibilities we continue to hold, the outcome is a substantial reduction in execution risk. Here, it genuinely is the best of both worlds. What's more, we see this transaction as a direct response to the risk investors are watching in our sector. Procurement and development here aren't just substantially limited relative to a traditional tier 3 build—that lower CapEx also brings down the financing needed for equity and debt alike. Combine that with the lease mechanism we described in our prepared remarks, under which reimbursements to the tenant—70% of our capital spend on this deal—may be satisfied via rent credits should reasonable financing terms prove unavailable, and our financing risks are substantially constrained. Delivery and financing: these two risk domains, both areas of investor focus, are ones this structure addresses, all while still delivering an incredibly attractive rental rate and underlying economics. The key point is that no compromise was required. Lastly, this structure brings us revenue and starts cash flow significantly sooner than a typical tier 3 build, with the first phase delivering in September 2027. For a typical tier 3 deal announced today, such a delivery date would be impossible. In our view, this marks a fresh milestone for the industry when it comes to creating value and doing so on a risk-adjusted basis. This result is something we take enormous pride in.
Really helpful, and congrats again.
Thank you.
Thanks a lot for taking my question, and congratulations on the transaction and everything you've accomplished. First, before we discuss Corsicana, I'd like to ask about Rockdale. Jason, could you perhaps refresh us a little on the AMD options and the structure in place there — what remains pending or what's currently under exclusivity when it comes to incremental capacity, and perhaps the total incremental capacity still available to be leased at Rockdale, and also whether you might consider pursuing a structure similar to the one used at Corsicana with respect to what could be available at Rockdale for future leasing, just as we think about capital requirements going forward. Many thanks.
Thank you, Paul. Regarding Rockdale, AMD has an option on another 150 megawatts, and we stay in tight contact with them about what their capacity requirements are. Naturally, there's nothing further I'm able to disclose at this point, but when you factor in those options along with the remaining capacity at the site, you end up with roughly 200 to 250 critical IT megawatts that are still available to lease. Our frontier AI lab also has interest in taking more capacity, and my expectation is that Rockdale's leftover capacity will in time be absorbed by one or both of the tenants we already have there. Should that not happen, it's fine. There's a lot of strong interest waiting in the wings, and I'm confident about how we'll get that site fully leased. I also think what's happened recently makes this capacity more valuable here. For the rest of the build-out at Rockdale, I'd expect it to follow the kinds of developments you already see there — whether that's expanding the type of product AMD has, or another tier 3 build deployment like the one the frontier AI lab has. We definitely see a path to leasing up the remaining capacity at that site as we keep progressing on our strategy.
Thank you very much for that. Perhaps I could ask a follow-up about Corsicana. According to the timeline, 400 megawatts is phase 1. How should we view the Bitcoin mining capacity that's currently operating in relation to that phase 1 delivery, and what might the decommissioning timeline look like for it, since I believe that capacity matches what you've been running at the site? Thanks so much.
Yeah; to reach the first 400-megawatt tranche, we won't have to shut down Bitcoin mining, but as we get ready for the second phase, we will need to take it down. I don't yet have a schedule for you. As we move forward here, we'll share more details about what to expect, but you can probably expect Bitcoin mining capacity at that site to start ramping down sometime in the summer of 2027.
Great. Thanks so much, and congratulations once more.
Hi there. With the uncertainty surrounding last night's elections, I wanted to ask whether there's any risk to what you can provide and deliver at either your Rockdale or Corsicana campus. Given the political results, how do you see your capacity going forward?
Thanks for that question. I know that's definitely top of mind for investors going into this morning. On this point, I think it's important to be abundantly clear about Riot's position. Our sites — Rockdale at 700 megawatts and Corsicana at 1 gigawatt — these interconnections, this power, is already fully approved. These locations have actually been running for a long time, each drawing hundreds of megawatts. We have a lot of confidence in where we stand regarding both of them. No further approvals are required in order to move forward with development at these sites, and Rockdale, where we've started two data center projects during this year alone, is a good illustration of that. On top of that, since we've operated at both locations for many years, we already enjoy solid, established ties with the surrounding communities. Take Rockdale — we've had a presence there for roughly seven years. We're deeply engaged—we interact with them routinely—and those ties matter a great deal to us. The surrounding community is where most of our workforce comes from, so those connections are significant. Since these facilities are up and running and their interconnects have already been approved, we're quite confident about where we stand with them.
Right. I take it that gave you a certain edge, or at least some reassurance, when it came to signing with the top AI lab you were already running and had a presence at. Would that be fair to say?
Absolutely. The fact that these sites are up and running — and here that means Corsicana — is the strongest possible proof point when it comes to the power interconnect. Another thing that helped us get this deal executed was demonstrating the time to power we could achieve at that location. A substation is already there on site, the expansion of that substation is already underway there, and that made this site extremely valuable and let this deal be completed on the terms it was.
Great, thanks.
I'd like to thank everybody for joining us today. We feel enormous pride in everything we've achieved not just through this transaction but also in all the strides made so far this year. An incredibly strong portfolio has been assembled by us. Once more, I want to express gratitude to our staff, our investors, and the community where we do business for their backing throughout the years; we couldn't be more thrilled about this coming phase of execution ahead of us. Thanks to you all; we'll talk with you on our 10-K call in a few months.
That concludes today's call. You may now disconnect.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete Riot Platforms, Inc. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to Riot Platforms, Inc. earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.