Thanks, operator. Hello everyone, and good afternoon — I appreciate you joining Riot Platforms' conference call covering our second quarter 2026 results. I'm Josh Kane, and I lead Investor Relations here; with me today from Riot are our Chief Executive Officer, Jason Les, alongside our Chief Financial Officer, Jason Chung. Over on the Riot Investor Relations website, our press release for the second quarter of 2026 is available, together with the earnings presentation that goes with it — both are meant to complement the prepared remarks we're delivering now, and they contain a look at specific non-GAAP items. Any non-GAAP financial measures we provide shouldn't be viewed as a replacement for, or as better than, financial performance measures put together under GAAP; we include them as extra clarification to help investors gain a deeper understanding of how the company performed in the second quarter of 2026. On this call, we'll be offering forward-looking statements about events that might occur down the road; such statements rest on management's present expectations and assumptions, and they carry risks and uncertainties. Results in reality may differ materially because of factors covered in today's earnings press release, in what we say and in the answers we give during this call, in the Risk Factors section of our Form 10-K and our Forms 10-Q — among them the one for the three months ending June 30th, 2026, which we anticipate filing later today — and in other documents we file with the Securities and Exchange Commission. Having said that, I'll hand things over to Riot Platforms' CEO, Jason Les.

Jason Les executive
#2

Thanks, Josh, and hello everyone this afternoon. Two things hold back the AI era — power and execution — and during this quarter Riot showed how it addresses each. In Q2 2026, Riot's data center business advanced in a major way, and it clearly confirms the assets, the team, and the strategy we've put together. After our initial data center lease with AMD earlier in the year, appetite for large-scale power data center capacity kept speeding up, and our response has been measured: the right deals, with the right counterparties, on the right conditions. It's a pleasure to walk you through where we stand today. Four main achievements shape this progress. First, at Rockdale, after the quarter closed, we signed a data center lease with a top-tier frontier AI lab, covering 191 MW of critical IT capacity. That makes a second data center lease for us at Rockdale. The AI lab agreement runs 20 years and should produce roughly $9.1 billion in total contract revenue, plus two five-year extension options that, if taken up, would lift total contracted value to about $16.1 billion. Combined with the AMD lease, Riot has now locked in approximately $9.8 billion of contracted data center revenue alongside two leading players in the AI ecosystem. Second, at Corsicana, there's been significant interest in our 1 GW of fully approved utility power. After reviewing many possible tenants, we narrowed things down and have now executed a non-binding LOI with a single tenant for the entire site, and we're deep into commercial and design negotiations on that deal. A transaction this large demands tight alignment across the design, commercial, and legal work streams, and those efforts are moving forward nicely. Meanwhile, we continue to push data center development at that location and to secure critical-path long lead time items, which keeps delivery timelines intact and execution risk minimal. Third, our growing partnership with AMD continues to see us deliver on schedule. Back in May, we finished and turned over to AMD the final stage of that first 25 megawatts, hitting both our timeline and our spending targets, and AMD has had equipment running there since January. Then in April, AMD used its option to grow, so the total amount it has under contract at our Rockdale location now comes to 50 megawatts of critical IT capacity. Construction is underway on that additional 25 megawatts, with the opening portion arriving before the year is out and the whole thing set to be delivered by May 2027. The fourth item: we secured the money required to support this expansion by continuing to liquidate Bitcoin held on our balance sheet along with output from our mining arm. Those funds remain our primary source for running the business and for covering the equity share of what we spend on data center capital projects. Our quarter ended with total liquidity of $1.2 billion, split between $666 million held in Bitcoin and $549 million in cash. That position reassures our partners, tenants, lenders, and shareholders about our ability to deliver. We treated 2025 as a period of preparation, and 2026 becomes the year we start executing. During the last seven months, Riot went from zero contracted data center revenue to 241 MW of signed capacity involving two counterparties that rank among the best in the AI ecosystem: AMD and, as of now, a leading frontier AI lab. Beyond that, a single tenant is now covered by a non-binding LOI across the entire Corsicana campus; the pace at which this came together reflects the approach, the properties, and the personnel we've spent the past two years bringing together. Under the agreement revealed today, which was signed directly with one of the world's top frontier AI laboratories, 191 MW of critical IT capacity will be provided at our Rockdale campus, marking the beginning of what we expect to become a substantial, long-term collaboration. As stated in the lease, Riot is constructing a bespoke Tier III data center that follows the tenant's most current design requirements, which have now been locked in. We're going to build on property we told you earlier this year we had bought; clearing and grading there are finished, and it taps existing power resources via the interconnection we already have running. Work on the site is underway now, and our current target is to hand over the initial 96 MW with rent commencing December 2027. Once everything is fully deployed in June 2028, the 20-year initial term kicks in, and base rent goes up each year. After that initial term wraps up, the AI lab can exercise two five-year extension options, and if it does, the overall contract revenue would reach about $16.1 billion. During the first term of the lease, we expect to generate total contract revenue of about $9.1 billion, plus net operating income estimated at $7.3 billion to $8.2 billion, based on an assumed NOI margin range of 80% to 90%. For illustrative capital expenditures, the figure falls somewhere between $11 million and $12 million for each IT megawatt. On the financing side, we've secured a $573 million interim financing facility through Morgan Stanley, and that will cover initial development CapEx while the investment grade backstop gets finalized. Later on today's call, Jason Chung will discuss what this means for our financing strategy. A partnership with a frontier company of this standing, committing 191 MW of mission critical infrastructure to Riot under a 20-year agreement, stands as definitive proof of what our team, our sites, and our execution capability can achieve at the highest level. Durable, high-quality contracted cash flow of precisely this sort is what we are constructing this platform to secure on behalf of our shareholders. Let's now turn to slide eight, where our delivery schedule is laid out. The AI lab lease capacity gets delivered across two phases. During Phase 1, the initial 96 MW of critical IT capacity arrives in December 2027, which is a swift timeline running from signing to first delivery. Then Phase 2 brings the rest of the capacity in June 2028, which finishes the entire 191 megawatt deployment. We're still on track to hit that first delivery, and we've taken a lot of the risk out of executing it on multiple fronts. Let's start with design. Our quicker design method begins with the tenant's basis of design, and right now both the complete design and the internal architecture are finished, so procurement is already underway. Second, delivery partners: Yates Construction has come on as our general contractor — since they've already worked directly with this tenant on development, we get a clearer view of both cost and schedule. Third, vertical integration. ESS Metron and E4A are part of the delivery plan, which accelerates substation work and reduces the risk tied to long lead equipment. Fourth, power. We’ve locked in the capacity we need through our active interconnection, and it lines up with project milestones. Number five, financing. That $573 million interim facility from Morgan Stanley lets us fund long lead procurement right away, which shields the delivery schedule while credit support gets finalized. Put all that together — power already in place, procurement moving early, design coordinated, our in-house capabilities, and financing — and we can deliver quickly with a lot of certainty. That de-risked rapid execution is exactly why this tenant chose Riot and Rockdale. Now let me move to AMD, where our deployment progress is still on track. During this quarter, we wrapped up the delivery of our first 25 MW of capacity, hitting both our budget and our timeline. AMD has begun operating within that first footprint, and Riot is now generating recurring, high-margin operating lease revenue from a tenant with an investment-grade rating.

Jason Les executive
#3

Regarding the second 25 MW, engineering work is essentially finished and building activity has begun, with the first 10 MW anticipated this November and the other 15 MW slated for May 2027. Just like the first 25-MW build, ESS Metron's engineering and manufacturing strengths are part of how we plan to deliver, which helps us stay on schedule and control costs. Past the 50 MW already under contract, AMD holds options to expand by as much as another 150 MW at Rockdale, which gives us a route to grow this relationship to 200 MW in time. Slide 10 presents Rockdale as it stands today on a pro forma basis. During 2026, Riot has locked in $9.8 billion of contracted data center revenue; together with the leading frontier AI labs and 191 MW under contract alongside AMD's 50 MW, Rockdale has transformed from a single-use Bitcoin mining site into a diversified data center campus, leased to two of the AI ecosystem's highest quality tenants on long-term, high-margin contracts. Examining each Rockdale lease more closely, AMD will add roughly $63.6 million in average annual revenue and $51 million in average annual NOI across 50 MW, with total capital expenditures of $170.2 million and full deployment arriving in May 2027. The Frontier AI Lab lease will add roughly $457 million in average annual revenue and $365 million- $411 million in average annual NOI on illustrative capital expenditures of $2.1 billion- $2.3 billion, with full deployment arriving in June 2028. Together, the two signed leases amount to $520 million in average annual revenue and $416 million- $462 million in average annual NOI over 241 MW. When we bought the land beneath the Rockdale facility, we envisioned it could turn into one of the nation's premier data center development campuses. That vision is now coming true. The tenant that selected Rockdale had a shared set of needs: certainty of power at scale, access to hundreds of megawatts at one location, and a developer that executes on mission-critical timelines. Riot came through on all three; in institutional real estate, assets that earn premium valuation share the same traits our portfolio now holds: extended lease terms, investment grade or equivalent tenant credit quality, and mission-critical infrastructure. Crucially, we have also diversified our tenant base across two independent high-quality counterparties, which substantially strengthens the overall quality of our portfolio. This is the asset profile we are building at Rockdale. Before I hand the call over, I want to discuss Corsicana because the commercial momentum at that campus is significant. We are in advanced commercial and design discussions, and the entire site is now under LOI to a single tenant. At the same time, we are continuing our development and procurement processes to de-risk execution timelines. Development of our first core and shell building is still underway, and we keep securing long lead items so that we can deliver full built-to-suit capacity on an accelerated basis once the lease is executed. Corsicana gives us one gigawatt of power that's fully permitted, located on land Riot owns, and it can back as much as 756 megawatts of critical IT capacity. We're eager to tell you more about how leasing is going at that site before long. An LOI isn't the same as an executed lease, but reaching this point shows how strong demand is right now for large-scale power with all approvals in place, and it shows that prospective tenants believe Riot can get the job done. All told, Riot currently holds roughly one gigawatt of capacity in our portfolio that is either under contract or in late-stage commercial talks; with that, I want to hand things over to Jason Chung, who will walk through our financing approach and the financial results for the quarter.

Jason Chung executive
#4

Jason, thank you. Our method for funding remains grounded in the same structure we outlined during prior calls. We sign leases with creditworthy tenants, deploy money productively by building out and completing our locations, and subsequently channel those funds into the next wave of projects. Throughout each stage of an asset's existence, we match it with the right form of financing — starting with land and greenfield work, moving through lease-up and pre-lease construction, and continuing to fully contracted, stabilized properties that offer the lowest capital cost. This quarter, that method shifted from a concept into real execution, and it rests on three pillars. To start, our balance sheet remains solid. When the quarter ended, we had over $1.2 billion in total liquidity. That breaks down as $666 million in Bitcoin plus $549 million in cash. Within that cash number, $77.5 million is restricted, and there are also 5,821 Bitcoin pledged against our $200 million credit facility — collateral that gets freed up as we reduce what we owe. As we've said before, Bitcoin continues to serve as our primary source of funding for the equity piece of our data center CapEx. We're still selling 100% of what we mine each month, and we've drawn down our Bitcoin holdings considerably while building up the cash on hand. Having more cash available has made our liquidity situation and future equity funding needs far clearer and more predictable. Because we didn't sell any common equity this quarter, this strategy also brings us closer in line with shareholders. Now, on to capital recycling. Last quarter, we mentioned the opportunity to unlock substantial value from the initial 25 MW of AMD capacity, which we delivered in May. Talks with a number of banks have progressed into advanced stages, and we expect the deal to wrap up before the third quarter is over. We anticipate that the money we borrow through this debt will end up being close to double what we originally put in as equity, which speaks to how carefully we underwrite and how much value we create. On top of that, this facility includes delayed draw capacity tied to AMD's second 25 MW as well as upcoming expansion, and that broadens the range of sources our capital comes from while keeping liquidity available for other new investments. Moving to the third point, capital redeployment: the funds generated by that first 25 MW loan are going to cover the equity needed for the Frontier AI lab lease at Rockdale, which lets us take lower cost capital and move it into projects with higher returns, all while stretching how far our balance sheet can go and reducing how much we depend on outside equity financing. You can see precisely how this sort of disciplined capital allocation plays out in real life on Slide 13. Here's the main takeaway: Riot's approach to financing fuels the expansion of development while opening up fresh sources of capital for the company, which means we lean less on outside equity funding for the projects we're working on now. On the left-hand side, that table shows how we're handling the AMD financing — for the first 25 MW we delivered to AMD, we're close to wrapping up a term loan worth about $180 million, with the size based on the stabilized value of that contracted asset. Our original CapEx budget came in at $90 million, and we covered all of it with cash already on our balance sheet, so this new facility will generate around $90 million in net new capital for Riot, effectively recapitalizing the deployment at roughly twice the amount we initially put in as equity. Now, regarding that second 25 MW facility: we have a $70 million delayed draw term loan at 85% loan to cost. That covers $69 million out of the $81 million in total CapEx we're projecting, so the net equity requirement comes to only $12 million. As a result, Riot can shift most of the CapEx funding to new sources and still preserve our balance sheet liquidity for upcoming projects. Turning to the table on the right side of the slide, we intend to recycle and redeploy this funding toward building out our Frontier AI lab, where illustrative capital expenditures land somewhere between $2.1 billion and $2.3 billion. We're looking at debt financing that should land somewhere between 80% and 90% loan-to-cost, which works out to $1.7 billion to $2.1 billion. That means the equity requirement would fall somewhere in the range of $210 million to $460 million. From that, we expect to subtract $180 million in term loan proceeds coming out of the AMD financing process, which brings the net equity needed down to somewhere between $30 million and $280 million. To put that in context, we have $1.2 billion in total liquidity on our balance sheet. And while we're finishing up that financing process, we've also secured a $573 million interim financing facility from Morgan Stanley, which we'll use to cover development costs for the project in the near term. Thanks to this arrangement, Riot is now able to get started right away on securing long lead equipment and covering other early development expenses, with no extra hold-ups or danger to the schedules we've committed to for delivery, and we can do all of that while keeping our liquidity intact. Our approach to capital allocation remains disciplined, and these projects are a reflection of that. Using the balance sheet we already have plus the proceeds we anticipate from the AMD financing process, our expectation is that we will cover the great majority of our net project equity. As we compound our way through this cycle, we'll hold onto high-quality assets that generate cash flow, even as we keep putting capital back to work to support further growth and reduce what we'll need from outside equity down the road. Now let's turn to the financial update for the second quarter, whose key figures appear on slide 15. During Q2 of 2026, Riot's total revenue came in at $174 million. That's up 14% compared with the same quarter last year, with the gains coming from both our data center business and our engineering business. On a GAAP basis, we posted a net loss of $237 million, which works out to $0.68 per diluted share, along with an adjusted EBITDA loss of $70 million. Just like we've seen in earlier quarters, more than $240 million of non-cash items are baked into these numbers. The biggest pieces: a $75 million mark-to-market loss tied to our Bitcoin holdings, $98 million of depreciation in amortization, and a $28 million impairment on mining-related construction items at Rockdale — something that stems directly from our choice to redirect that capacity toward data center development. When you add all of those non-cash items together, they came in higher than the quarter's total net loss, and they aren't a true picture of how our operations actually perform. Now, on the data center side of the business, we closed out the quarter with 25 MW of critical IT capacity up and running, and total segment revenue reached $23 million. Within that number, $4.9 million came from operating lease revenue, and it captures the full 25-MW AMD deployment that we handed over in the middle of May, generating an 84% operating lease gross margin — exactly the figure we shared with the market at the time the deal was announced. The fact that we went from signing in January to capacity that's fully commissioned and bringing in revenue in less than five months demonstrates the speed of execution our platform was built to provide. Looking at Bitcoin Mining now: during Q2, Riot's output was 1,587 Bitcoin, averaging 17.4 Bitcoin per day, and when the quarter ended, our deployed hash rate stood at 44.4 exahash per second — about 4.6% of the global network. Revenue from Bitcoin Mining reached $113.7 million, and hash rate utilization came in at an average of 87%, with some of the drag coming from minor downtime in Kentucky in May. Thanks to our power strategy, we captured $10 million in power curtailment credits — that's $6,335 per bitcoin mined — which brought net power cost to $0.036 per kilowatt hour, a figure that remains among the lowest in the entire industry. For the quarter, our direct mining cost came in at $49,912 for each bitcoin. Even though the average global network hash rate climbed 9% compared with a year earlier, that figure still leaves us among the most efficient operators in the industry. Power assets, along with the way we manage power, remain a cornerstone of the Riot narrative.

Jason Chung executive
#5

We've consistently described Riot as a power-first organization, and our net power cost, along with our capability to oversee power trading, demonstrates that top-tier industry knowledge. To wrap up, at the close of the quarter we held 11,380 bitcoin on our balance sheet, with a quarter-end value of $666 million, calculated using a closing price of $58,527 on June 30th. This marks a substantial decrease in our bitcoin holdings, since we keep using that inventory for data center development. As discussed in our financing strategy, our bitcoin treasury is a crucial financial asset that we've kept leveraging to finance the build-out of our data center platform. Moving to slide 16, we look at our data center segment results in greater detail and compare the second quarter results with the first quarter. Even at this early point in our build-out, we're seeing the start of the high margin recurring revenue ramp we've been referencing; we achieved an 84% operating lease gross margin and expanded AMD contracted capacity to 50 MW during the quarter. Recurring operating lease revenue climbed to $4.9 million in the second quarter, an increase of over 400% from $900,000 in the first quarter, fueled by delivering the full 25 MW to AMD in May; that revenue produced $4.1 million in gross profit at an 84% gross margin. Tenant fit-out services revenue came in at $18.3 million, a decline from $32.2 million in the first quarter, producing $2.4 million in gross profit. As a reminder, fit-out revenue reflects the procurement and installation of customer-specific equipment reimbursed by tenants on a cost-plus basis, and it will naturally vary with the development cycle; overall, the data center segment produced $23.2 million of revenue and $6.5 million of gross profit in the quarter. Although total segment revenue was lower quarter-over-quarter because of reduced tenant fit-out activity, gross profit rose 174% on the strength of the recurring lease revenue mix. This is precisely the evolution we've described. To put this trajectory in perspective, recurring lease revenue of $4.9 million this quarter builds toward roughly $64 million in average annual revenue and to roughly $520 million in combined average annual revenue once the Frontier AI Lab development reaches full deployment, adding highly predictable infrastructure-grade cash flows into our consolidated P&L. Our engineering segment, ESS Metron and E4A Solutions, keeps serving as a key competitive advantage, fueling our ability to deliver critical data center components promptly. Engineering revenue was $37.3 million in the quarter, more than three times the $10.6 million from a year ago, while gross margin expanded from approximately 7% to over 27%, with the data center sector representing approximately 90% of our $177.1 million backlog. Importantly, the conversion cycle of backlog into revenue has sped up significantly because of the 25% increase in manufacturing capacity we brought online in 2026. We're also continuing to strategically hold back capacity for Riot's own data center growth. Just to remind everyone, inside our engineering segment, ESS Metron builds low and medium voltage switchgear along with power distribution units — these rank among the most tightly constrained long-lead items in the data center supply chain. We're very happy about how ESS's financial results keep getting better, but standalone profits were never the point of this story. ESS and E4A serve as crucial pieces of Riot's vertically integrated model. As we execute on our data center deals, Riot Engineering supports the procurement process for our data center strategy in an important way. That process gives us more control over the supply chain, lowers the risk around delivering schedule-critical equipment, and produces significant CapEx savings. Roughly $23.8 million cumulatively for the acquisition of ESS Metron in December 2021 by itself; this vertical integration mattered greatly in getting the initial AMD capacity delivered on schedule, and today it's fully woven into the delivery plan for the Frontier AI Lab build-out. At this point, I want to hand things back to Jason Les for closing remarks.

Jason Les executive
#6

Jason, thank you. To close, I want to offer some context about the pace at which we're operating. In January, we shared news of the Rockdale land acquisition and completed our inaugural data center lease, signed with AMD. Come May, AMD's first 25 MW had been brought to completion. And now, we've disclosed a 191-megawatt lease — valued at $9.1 billion — with yet another of the world's most significant AI firms. Going forward, AMD's buildout concludes in May 2027, whereas the phased deployment from the top Frontier AI labs begins with 96 MW in December 2027 and wraps up in June 2028, bringing our total delivered contracted capacity to 241 MW. We've also included the letter of intent we signed covering the whole Corsicana campus, and we've positioned that site to support about 1 GW of leased critical IT capacity, within an overall power portfolio above 2 GW of utility power. With the AMD and Frontier AI lab lease now signed, we've contracted an estimated average annual NOI somewhere in the range of $416 million to $462 million. This quarter is defined by four themes, and those same themes will define Riot going forward: rapid delivery, de-risked execution, plus a strong balance sheet and disciplined capital allocation. From that, our priorities for the remainder of 2026 follow directly. Deliver the contracted megawatts to AMD and keep the AI lab build-out moving forward both on schedule and on budget. We need to get the Corsicana letter of intent finalized as an actual lease and secure inexpensive project funding whose terms reflect how strong our tenants and locations are. On top of that, we continue to aggressively build out our power pipeline and will look for value-enhancing opportunities that generate compounding returns throughout our portfolio. Riot occupies a position where two critical bottlenecks of the AI age meet: power and the ability to get things done. We think our platform's quality, scale, and cash flow visibility will grow clearer as we continue turning our power portfolio into contracted data center leases with the world's best counterparties; what we hold includes over 2 GWs of utility power and two of the most attractive data center development sites in the U.S. Funding development on value-accretive terms is possible thanks to our balance sheet, backed by our financial strength, our operating cash flows, and access to institutional capital markets. Then there's our team, a world-class data center organization that is delivering for AMD, building for the leading Frontier AI lab, and advancing our next wave of leasing discussions. Our approach is repeatable. We focus on leasing space to tenants with strong credit, obtaining cost-effective financing, constructing in a careful manner, and redeploying our capital. This strategy is built to generate compounding returns across numerous transactions and numerous locations. Along with the whole management group, I'd like to express gratitude to those who hold our stock, those we work with, and the people who work here for standing behind us as we pursue this promising chance; at this point, we'll turn the call over to questions. Operator.

Stephen Byrd analyst
#7

Hi, everyone. Nice work on the deal and the LOI. That's really exciting.

Jason Les executive
#8

Thanks, Stephen.

Stephen Byrd analyst
#9

Yeah, that's fantastic news. I'd like to begin with the deal's economics, and I was hoping you might address the CapEx range — more specifically, how you got to that CapEx range.

Jason Les executive
#10

Of course. I appreciate that question, Stephen. The fresh lease at Rockdale comes with an initial base contract value totaling $9.1 billion in revenue across its term, which runs slightly more than 20 years after the initial deployment. This lease, similar to the majority of leases we've observed, includes annual escalators consistent with market precedents out there. Across the lease term, our NOI margin is anticipated to fall between 80%-90%. We already possess solid experience running Rockdale for AMD, and we've devoted considerable time to putting together a very strong operations team that assists in shaping this guidance. Over roughly the last year, we've truly invested heavily in expanding this operations team. Turning now to your CapEx question, the illustrative range we provided draws on three components. First, our teams along with the tenants have devoted substantial time to design work, so we know precisely what we're constructing and how what we're constructing will satisfy the tenant specifications. Second, we've completed considerable work around procuring long-lead items. Since this design is already laid out, we've managed to make headway on that. We possess strong visibility into how pricing will shape up for each of the individual components. And finally, we've collaborated with a general contractor who has previously handled projects for this tenant and has provided us visibility that helps solidify these figures; that has given us truly good clarity regarding labor availability and pricing to fully deliver this project. Once you combine all of these factors, it gives us a really solid grasp of CapEx, which, I should note, incorporates a healthy contingency reserve. That's because a good amount of effort has already gone into planning and preparing this deal across the preceding months from both of our teams. Taken together, all of this yields a return on cost perspective that is very strong, particularly for a customer whose profile and trajectory match those of a leading frontier AI lab; it also, in my view, reflects the continued and ever-improving strength of the market and demand for this kind of large-scale infrastructure, which arrives alongside the level of certainty in power delivery that Riot's able to offer.

Stephen Byrd analyst
#11

That is great news; those details really assist us. Could you perhaps elaborate on the bridge financing you have put in place? I simply wanted to verify whether it will be enough to handle, in essence, the build cost for the near term that you are about to take on here?

Jason Les executive
#12

Jason Chung, would you like to address that?

Jason Chung executive
#13

Absolutely. Thank you, Stephen. Regarding the financing side, the framework we've established was intentionally designed to roll out in phases. That interim financing arrangement with Morgan Stanley provides immediate funding for long-lead equipment, procurement, and additional development expenses tied to this tenant lease. What's notable is that the tenant fully secures it, meaning those near-term construction costs carry tenant credit backing right from the outset. Building on that, our plan is to complete the takeout financing for this interim facility over the next few months, once the investment grade backstop is finalized. At that point, we expect pricing in line with the increasing volume of backstop AI infrastructure transactions we've observed in the marketplace. This lease was crafted with financing considerations built in from the very beginning, and we have several avenues toward appealing long-term financing no matter how the credit support process wraps up. That being said, we do anticipate it wrapping up shortly, and diligence has progressed considerably. I'd rather not jump ahead of that process by getting into specifics about parties or terms at this stage. What I'd direct your attention to is the end result: we remain confident about securing investment grade level financing economics for this project.

Stephen Byrd analyst
#14

Excellent. I really appreciate it.

John Todaro analyst
#15

Hello, everyone. Congratulations on securing that lease. The economics per megawatt appear quite favorable. I wanted to inquire about Corsicana — it's encouraging to see the LOIs covering the entire site, and it will involve a single tenant. You've mentioned many times previously that the whole site could potentially go to just one tenant. My assumption is that points toward a hyperscaler, but could you share anything further? Also, how have the Corsicana discussions progressed over time?

Jason Les executive
#16

Absolutely. To start, John, it's amusing to reflect on earlier earnings calls. I had been posing that question, and historically we were hesitant about revealing LOIs. I should mention that all the deals we announced before this one also had an LOI at some stage prior to moving forward into a lease, and we made the decision not to make that public. Everybody understands that LOIs come with uncertainty. Our confidence in the progress we're making here is very strong. With this particular situation, we wanted to let the market know that we have an LOI covering the whole site with one tenant, aiming to provide visibility into how this process works. I'd say it demonstrates how far we've come with the counterparty as we work toward getting the deal signed. When it comes to marketing this asset, Riot has been extremely deliberate, since this is the most valuable asset we have and the one with the highest demand. I want to point out that only by the close of 2025 did we finally hold every piece of land required, giving us the physical site needed to construct a complete, unified Tier III data center campus — one that draws on the entire 1 GW of power available at Corsicana and satisfies what today's market demands in terms of design. As a result, our full marketing push for the location, backed by a thorough plan, did not get underway until this year began. Before we went out to talk with potential tenants—and we've discussed this before—we wanted to make sure we had a carefully developed strategy that could hold up under the toughest scrutiny you'd get from the very best, top-tier counterparties available. That's resulted in quite a few discussions with all sorts of different parties, and we've been deliberate about directing our attention toward the counterparties that make the most sense. With a site the size of Corsicana, the process is incredibly thorough, and for any tenant considering it, this is no minor commitment. If you consider what the rent on a lease for the whole Corsicana site might amount to, once everything is fully built out, you'd be talking about more than $1 billion each year. Given that, it's understandable that regardless of how strong the location's advantages are, neither side can afford to be anything but extremely cautious about the shape of the final agreement, since that's the only way to secure the most favorable results — and that applies equally to both parties. The level of commitment is enormous on each side, and getting there demands a huge volume of work across technical development, construction, operations, legal matters, and commercial negotiations. This one is bigger than the deals we previously made public, and bigger than Rockdale too. We've been putting a great deal of intensive effort into this. There is a prospective tenant we have made a commitment to during this effort, and an LOI has been signed with them. We want to be careful, and we fully recognize that a number of unexpected developments could still occur in this effort, and uncertainty remains around it. Even so, being open regarding how far we have gotten matters to us, and once there is additional information to provide about this effort, we will bring the market up to date in the months ahead.

John Todaro analyst
#17

That's excellent. Really useful, and plenty of detail there. So, following up about that same location: could you expand a bit further on where development stands right now, and whether anything at the foundational level remains to be completed before the full gigawatt can be supported, plus what the capacity phasing would look like?

Jason Les executive
#18

Sure. So even as those in-depth active conversations carry on, work at the Corsicana site has kept moving forward, and that matters because it lets us keep making headway that eventually leads to Tier III capacity being delivered. At this point, though, we aren't locking ourselves into designs, decisions, or spending that would constrain us to particular tenant specifications or a particular design. What we are doing is pushing ahead with horizontal work as well as procuring long lead equipment for the items we feel certain can serve whatever requirements a tenant eventually brings, whether that's tied to the LOI we currently have or something else. Regarding our updates, I'd say it's likely too soon to speak to that in specific terms, since all of it depends on final design choices, specifications, and the negotiations involved. Throughout this process, as you work through multiple revisions of a tenant's design, you end up making trade-off decisions pitting delivery dates against particular features or requirements that might need somewhat more time to deliver. So there's a constant push and pull in our talks with customers, aimed at satisfying what they need on both timeline and technical fronts; these conversations remain active. They take place regularly, and we look forward to carrying them forward toward a lease.

John Todaro analyst
#19

Excellent. Thanks for sharing that, and once more, congratulations on everything you've accomplished, everyone. It's genuinely good to witness.

Jason Les executive
#20

Thanks, John.

Paul Golding analyst
#21

Thank you very much, and I'll add my congratulations on everything that's been accomplished. My question is probably about Rockdale. Would you walk us through how the remaining AMD options are structured? Jason, I recall you saying there are still 150 MW of options that haven't been exercised. Beyond explaining the structure of those, perhaps you could also shed some light on whether this new AI frontier lab lease of 191 MW has any effect on those options or on the relationship with AMD. Clearly, pricing looks very strong given the recent announcement, and I'm just curious whether that changes anything for the AMD options. Thanks a lot.

Jason Les executive
#22

Thank you, Paul. Starting with the AMD options. Their lease carries two options, and the first one is an expansion right covering another 50 MW, which, if they use it, would take their total IT capacity at Rockdale up to 100 MW; back in January we signed an initial 25-MW lease with them. In April they put through a 25-MW amendment to that, so 50 MW is what's left under that original 100-megawatt option. This extra 50 MW would be more or less the same type, build out, and economics as the 50 MW they already have. The second AMD option covers another 100 MW of capacity, and it can only be leased if they fully lease the first 100 MW of the lease. That second 100 MW of capacity comes with several restrictions and guardrails that matter for preserving Riot's flexibility. While we're on AMD, one thing I want to point out is that AMD was featured in a really interesting CNBC segment recently about all the progress they're making in their AI hardware business, and much of that interview was filmed at our Rockdale campus, which they now call their Mega Lab. What's really exciting for us is that in this interview they say they're using this Mega Lab to test and commission their brand new Helios Rack AI platform. For anyone interested, our presentation appendix has a slide with a few interesting screenshots from that piece and a link to the interview, which shares a lot of good information about what they're doing. I believe the second part of your question was whether this new deal has any impact on AMD's position regarding its expansion options. We can't comment on or speculate about our tenants' motivations. That said, if you look at what AMD has said publicly, even if the entire expansion option went to AMD, based on public statements, it still wouldn't be enough to fulfill their power demand; so, we have 700 MW of capacity out at Rockdale, and we're moving forward with commercial discussions across that site and at Corsicana, and our primary strategic objective is to lease up this full portfolio.

Paul Golding analyst
#23

Thank you, Jason. Let me ask a brief follow-up on that point. Regarding the 25 MW, where the design work for AMD at Rockdale is almost finished — about that wording, that the design is still almost finished, do different terms apply, or perhaps incremental economics, if a design differs from the earlier 50 MW? What's the right way to think about that? Thanks.

Jason Les executive
#24

I don't know precisely which remarks you mean. What I was trying to make clear is this: the initial 100 MW uses a particular design type that we have already delivered with them. That one comes with reduced CapEx and faster deployment schedule. It applies across all 100 MW. For the next 100 MW, there's somewhat greater flexibility to construct a new kind of capacity, whatever specifications they may seek. Should we reach a stage where they completely use their first 100-megawatt option, and then they wish to discuss the 100 MW, part of that would involve working with them on whatever design they are seeking.

Paul Golding analyst
#25

Got it. Thanks a lot.

Jason Les executive
#26

Sure. Appreciate it, Paul.

Jason Les executive
#27

Logan here, filling in for Mike. Appreciate you taking the question. Congratulations on everything that's been accomplished. Our first one: now that two leases are signed, could you clarify how much capacity remains at Rockdale that's available to lease? And is there any preference between current tenants and new ones when it comes to taking that capacity? Thanks. Yeah, Logan, appreciate the question. Yes, Rockdale still has additional capacity. At present, Bitcoin mining and AMD are located at that site, and we're now going to construct a development for a new tenant. We'll keep using Bitcoin mining to monetize the capacity that's available until we find the right lease or leases to take the remainder of that capacity. Regarding tenant preference, our only preference is for a tenant or tenants who will pay the strongest economics and who carry the necessary credit rating or backstop enabling us to get the best financing outcome possible. That, in the end, is what translates into the strongest returns for our shareholders. We value the relationships we have. We intend to grow both of them considerably. However, should the right counterparty come along wanting to take capacity and the terms work, we'd examine that very seriously too.

Logan Hennen analyst
#28

Great. To build on that, could you add more capacity at Rockdale beyond the 700 MW it has now? If you were able to obtain that power, would more land be required? Thank you.

Jason Les executive
#29

Yes, Logan, we think expansion of available power is possible at Rockdale and in fact at every one of our sites. That's something we monitor closely and, to be clear, are actively working toward. Obviously, it's too soon to make any commitment about whether this can happen, particularly given all that's underway and how far we might be able to go down the road. At Rockdale, 200 buildable acres make up our site, and we've been quite deliberate and careful regarding the way we develop this site so that the campus's availability is maximized as part of a wider strategic plan for the campus. I believe we're in a strong position to have the chance to secure additional power at that site and carry it out there should that be approved.

Logan Hennen analyst
#30

Thank you. Congrats on the quarter.

Jason Les executive
#31

Thank you.

Brett Knoblauch analyst
#32

Hi, everyone. I appreciate you taking my question. Congratulations on completing both the AMD deal and the new lease. Regarding the Corsicana LOI, how would you characterize the conditions on your side, or what steps do you and the prospective tenant need to take to move it from an LOI to something like a definitive lease? If you had to list two or three bullet points, which would they be?

Jason Les executive
#33

Yes. I appreciate that question, Brett. Clearly, I'd rather not dive into too many details here, but as I sort of said during the remarks, carrying out a build of this magnitude is a major undertaking. A great deal of design, legal, and commercial effort goes into something like that. I believe the intensity felt by each party grows in proportion to the number of megawatts involved. So with Corsicana, this is a development spanning multiple years; it's as much as 756 MW of development throughout the acreage we've purchased there. That means we have to plan with great care, and it means the tenant has to carefully plan their own capacity, ensuring that what we construct can hit the timelines they need. They need certainty that what we build will be the right kind of design, both at present and for the first phase of delivery as well as the final phase of delivery. So it's a major effort, yet this represents a significant portion of the power assets in our portfolio. This is an agreement that we will be living with and performing under for 15, 20 years, whatever the ultimate term of that lease turns out to be. Our management team — we hold a meaningful stake in this company — and for that reason we think about how we develop this portfolio across a very long horizon. So it's about doing solid work and progressing through the process as fast as we're able, while staying diligent to ensure we deliver what our tenant is looking for and can deliver what our tenant wants.

Brett Knoblauch analyst
#34

Thanks, Jason. Regarding the de-risked aspect, this AI lab lease seems like a fairly de-risked build. You discussed somewhat how ESS Metron will have a part to play there involving some of the electrical equipment. I believe you brought up substation equipment, if I'm not mistaken. What I'm wondering is what electrical work is required, considering that site was already operational and drawing power for mining?

Jason Les executive
#35

That's a good question. To start, with any new development, you're constructing, at minimum, new low voltage and medium voltage systems throughout all the buildings. So you're buying an enormous amount of equipment — equipment that currently represents a supply chain bottleneck, which is exactly why having ESS Metron in-house gives us an edge and truly de-risks this. High voltage work is also required for this new building. We've already locked in the transformers for it as part of our ongoing long-term campus planning strategy. So we've placed ourselves in a very strong position thanks to the decisions we've made previously when it comes to procurement, and that's why we can sign a lease right now in the summer of 2026 and deliver 96 MW in a little over one year from now.

Brett Knoblauch analyst
#36

Great. Thanks so much, Jason. I really appreciate that, and congratulations once more.

Jason Les executive
#37

Thank you, Brett.

Jason Les executive
#38

Hey, thanks a lot, and congrats on the new deal. I'll throw in my congratulations too, I suppose. Could you maybe provide a bit more detail about your pipeline and how you expect that to shape up? Is there a preference on your end between, say, grid connectivity or behind the meter? Yeah, that's a fantastic question, Brian, since it's a space where Riot is genuinely invested. We've got data center teams focused on design, development, leasing, and construction, which produces the lease we're announcing today. We also have a distinct team focused on locating the right future assets so we can keep replicating our successful data center strategy. As I've said before, what we're building at Riot isn't just about Rockdale and Corsicana. The goal is a data center platform that lasts for the long haul. Those two sites are just the beginning. Right from the start, Riot's management team and Board made a conscious decision: to get the best returns for shareholders, we needed our own capabilities in data center design, construction, and operations. Those teams exist today, and they're putting in hard work to deliver data centers in Rockdale, Corsicana, and Kentucky. With that said, this significant investment was made so we could expand our current tenant relationships and build new ones, replicating this business model at additional sites that we can bring into our power portfolio. To make that happen, we're focused on creating a business that's built to last and can be repeated, with crews that have deep expertise in getting data centers delivered for tenants with high expectations. Every single week, we look at a minimum of 10 new locations, and our people invest a tremendous amount of effort into this, carefully evaluating what would strengthen our power portfolio. That said, we take great care to avoid bringing in assets that only produce an impressive-sounding figure for a portfolio that exists on paper. What we aim to do is put money behind locations we think have a real shot at turning into top-tier data center sites — ones that can hold up under the close examination of hyperscaler and enterprise tenants and the tough due diligence those tenants put them through. We currently have several initiatives that we're quite enthusiastic about. In response to what you asked, Brian, that covers projects connected to the grid as well as those located behind the meter. When the moment is right, we're eager to tell you more about this expanding power portfolio; nevertheless, it's definitely an area where we have a hand in things, and carrying it through is our clear aim as we put our strategic plan into action.

Brian Dobson analyst
#39

Great, thanks — that helps. If I could squeeze in one more question: do you have any role in Texas's batch process?

Jason Les executive
#40

I appreciate you bringing that up, since I'd like to set the record straight for everybody right away: the batch process does not apply to Riot's current Texas locations, Rockdale and Corsicana. The reason is that those sites already hold power allocations governed by interconnection agreements that have been in place for a long time; they've been up and running for a number of years, and we want that point to be completely unambiguous from the start. Within ERCOT in Texas, the batch process is still taking shape, and we continue to stay deeply involved through our power teams, our corporate development teams, and our public policy teams. The sheer volume of interconnection requests coming from data centers has put ERCOT in a situation unlike anything it has faced before. Something we frequently tell our investors is that keeping the grid reliable for customers who are already connected comes first for ERCOT, and in our view that works in favor of properties such as ours. At places like Rockdale and Corsicana, the power is already in place, which gives tenants certainty because it won't be tied to any upcoming studies or approvals. Looking ahead to the coming year, we believe there will be fresh chances to either acquire or expand involving sites that wind up receiving a new allocation through ERCOT's batch process. As I mentioned, this is a space we're watching closely and doing diligence on. Offering a bit of wider perspective on how things have unfolded, and on Governor Abbott's recent letter, our overall view is that Riot stands to benefit. It's true that the batch approach has made securing additional power harder, yet that difficulty is precisely what raises the worth of the sites we already hold. ERCOT finds itself working through a tough set of circumstances, having to contend with numerous phantom interconnect requests as well as developers of lesser repute. The grid operator is genuinely attempting to put rules in place that will clear those out. And when you consider what Governor Abbott wants data centers to adopt going forward for newly built facilities, that aligns with the practices Riot already follows. Being responsible members of the communities we operate in matters to us. That covers funding our own infrastructure, covering the cost of transmission improvements, adopting closed-loop water cooling, and supplying our own water. Those are all things we've concentrated hard on putting into practice at the sites we run today. If you've visited any of our sites, you've witnessed this firsthand. Our goal is to ensure each project gets built the right way. So, to wrap it up, I believe this has put us in a position to pursue fresh opportunities, keep serving as strong partners to ERCOT and the communities around us, and make the sites we already own even more valuable.

Brian Dobson analyst
#41

Great, thanks a lot.

Martin Toner analyst
#42

Oops. Hi, everyone. I’m very grateful that you took my question. It’s fantastic to see both of these — well, this excellent transaction, plus another possible one waiting in the pipeline. I believe it would help if the two of you restated the way you’re handling this transaction involving the AI lab, the bridge financing, and then converting that into an investment-grade backstop. Could you please explain why you have such confidence that this is essentially guaranteed?

Jason Les executive
#43

I appreciate the question, Martin. I’ll hand it to Jason Chung.

Jason Chung executive
#44

Hi Martin. Earlier, we chatted briefly about this facility and the way it lets us cover certain long lead equipment purchases that need funding right away, plus some extra development expenses. It's proven to be a genuinely valuable instrument, ensuring we've got the money available now to kick off procurement without delay and avoid jeopardizing our schedules, all while keeping our balance sheet liquid as we wait for that great backstop investment. Without diving too deep into the details right now, like I said before, I'd rather not say too much; we've held discussions with everyone involved, including the tenants and the possible backstop provider. We anticipate wrapping up those talks pretty soon. Confidence is high on our end, considering how thoroughly both counterparties have examined everything. That's exactly the kind of thing this bridge, or interim facility, was designed to enable. With that said, I also noted earlier that we've added further contractual safeguards to guarantee that no matter how things turn out, we'll be shielded, and we've locked in investment-grade or investment-grade equivalent terms for what that takeout financing will ultimately resemble.

Martin Toner analyst
#45

Excellent. Many thanks. Just quickly, how should we think about the timing pattern for the $2 billion of CapEx tied to this 200 MW deal?

Jason Chung executive
#46

Absolutely. Regarding this specific deal, as we've talked about, Phase 1 consists of that initial 96 MW, which will be handed over in December of 2027. The long lead equipment procurement — the transformers, chillers, switchgear, and so forth — is already in progress, and the Morgan Stanley interim financing facility that we've arranged is backing that effort. Our expectation is that CapEx will truly accelerate during the back half of 2026, likely reaching its highest point in the first half of 2027, before carrying forward into early 2028, when the Phase 2 delivery arrives in June 2028. If we consider that together with the AMD build-out for the extra 25 MW, the combined peak project-level CapEx across both is likely to land around Q2, somewhere between Q2 and Q3 of 2027. That said, it's crucial to keep in mind that the vast bulk of the CapEx spending on both of these will be financed at the project level. The AMD financing facility will be in place, and it will feature a delayed draw mechanism allowing us to fund further AMD options as we exercise them. Then there's the Morgan Stanley interim financing facility, along with the eventual takeout of it. We're feeling very confident about the financing structure we've established, and about how it sets us up to ensure we can meet our delivery milestones on schedule.

Martin Toner analyst
#47

That's quite useful. Thanks a lot, Jason.

Jason Chung executive
#48

Thanks.

Jason Les executive
#49

Thanks, operator, and I appreciate all of you being with us on today's call. It's a real point of pride for us to share word of this historic new agreement. Everyone here is genuinely enthusiastic about how far we've come, and we can't wait to keep you updated as we reach further milestones under our strategic growth plan; we'll be together again in 3 months. Thanks so much.

Operator operator
#50

That wraps up today's session, everyone. We appreciate each of you for being here. You're free to hang up at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Riot Platforms, Inc. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Riot Platforms, Inc. earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.