Good day, ladies and gentlemen, and welcome to the Q2 FY '27 earnings conference call of H.G. Infrastructure Engineering Limited, hosted by Go India Advisors. <<operator_script>> Kindly be aware that this conference is being recorded. I'll now pass the conference over to Ms. Saloni of Go India Advisors. Thank you, and the floor is yours, ma'am.
Good afternoon, everyone, and welcome to the H.G. Infra Engineering Limited earnings call, hosted by Go India Advisors, where we'll be discussing operational and financial performance for quarter 2 and the first half of FY '27. Joining us on the call are Mr. Harendra Singh, Chairman and Managing Director, and Mr. Vikas Jain, CFO. As a reminder, today's discussion may contain certain forward-looking statements, and those must therefore be considered alongside the risks the company faces. At this point, we'd like to request Mr. Harendra Singh to walk us through the company's business outlook and performance, after which we will open the floor for the Q&A. Thank you, and over to you, sir.
Thank you, Saloni. Good evening to everyone. I want to start by wishing you and your families a very happy Diwali and a prosperous new year ahead. May the coming Samvat bring happiness, success, and prosperity to all. India is progressing towards its vision of becoming USD 7 trillion economy by 2030 and USD 30 trillion economy by 2047, and infrastructure development will play a very critical role in achieving these ambitious targets. With sustained government focus on increasing investment by both public and private sectors, the government is witnessing -- the country is witnessing significant opportunities across roads, rails, power, and urban infrastructure. At H.G. Infra, we believe infrastructure development is not just about building physical assets. It is about connecting people, enabling businesses, and creating opportunities for economic growth. With our presence across 14 states and capabilities spanning roads, rails, metro, renewables, and emerging infrastructure segments, we continue to strengthen our position as a diversified infrastructure company. Let me briefly touch upon the key sector developments and opportunities. The roads and highways remain to be our core business segment, supported by government's sustained focus on highway expansion, improved connectivity, and infrastructure development under National Highway Vision 2047.
We anticipate that this segment will keep providing substantial opportunities for bidding and order inflow. Rail modernization, capacity expansion, and metro connectivity remain priorities for the government, and that is generating considerable opportunities for us. Through our ongoing rail and metro projects, we are strategically reinforcing our presence in this segment, and we are examining numerous opportunities as a pipeline. Turning to renewables and green energy, India's green energy transition is opening new avenues beyond solar generation, particularly in transmission infrastructure and energy storage. In transmission and distribution as well as BESS, we see significant long-term opportunities, and these are expected to play an important role in strengthening the country's power infrastructure. Overall, we remain confident about the long-term infrastructure growth story and the opportunities emerging across our focus segments. Our strategy is to leverage our execution capabilities, diversify our business portfolio, and pursue quality projects while maintaining financial discipline and operational efficiency. Let me begin with a glimpse of our operational highlights. As of September '26, the company's order book stood at INR 13,685 crores, comprising INR 8,792 crores from roads and highways, INR 2,883 crores from rails and metro, INR 610 crores from renewable projects, including BESS, and INR 1,400 crores from transmission and distribution.
By segment, road highways account for roughly 64%, railways 24% to 21%, and the remaining 15% comes from renewables and transmission projects. Now for the EPC project update. At this point, the Ganga Expressway and the UER are done, and the completion certificate for the UER, effective 20th February '25, was received on 23rd September '26. And quite recently, we also obtained the completion certificate for the Ganga Expressway. The Jamshedpur elevated road project is moving along nicely, at 70.82% progress. Neelmangala-Tumkur has reached 73.64% completion, is on track for timely delivery, and is likely to wrap up by March '27. The DLF project sits at an early stage, with just 6% completion, purely because of land-related constraints. We expect progress to improve over the coming months. The Pune-Shirur project, awarded by Welspun at a cost of INR 3,931 crores, is currently in mobilization, with work expected to pick up from quarter 3 FY '27 onwards once we receive the appointed date, which is likely within the month. On the HAM projects, the Karnal Ring Road project has hit 99% completion, and the company has already applied for the provisional completion certificate, which we expect any time, with COD targeted in quarter 4 '27.
Like we mentioned last quarter, we've now received the provision completion certificates for the Raipur-Visakhapatnam corridors — OD-5, OD-6, and AP-1 — and for Khammam-Devarapalli Packages 1 and 2, which actually came in last year. So COD for these projects should land in quarter 3 and quarter 4 of FY '27. On Tirupati-Chennai, that HAM project is at 71.8% completion and moving along nicely, with the aim of finishing by 31st March '27. Varanasi-Kolkata Package 13 stands at 47% financial progress, while Package 10 has hit 18.6% completion. Kosi Parikrama Package 6 Ayodhya is at 42.4% completion and tracking per plan. The Narol-Sarkhej project is at 54.8% completion and still on schedule to finish on time. For the Gobindpur-Tangi-Capital Ring Road project in Odisha — that's Package 3 — the company signed the contract agreement on 24th April '26. Land acquisition is well advanced, and we expect the appointed date any time within a month. Moving to how the railway projects are doing: the DMRC Metro project has been 100% -- is 100% completed, and the handover process is underway. The Bilaspur Himachal Pradesh railway project has reached -- has achieved 98.3% completion and is slated for completion in quarter 3 FY '27.
On the Kanpur Railway Station project, we've reached 58.85% completion, although there have been some delays stemming from blocks that weren't available. The company has therefore applied for an extension of time, and that has been approved in principle for up to December '27. The Dhule-Nardana railway project stands at 57.6% completion, and here too the company has applied for an extension of time, since close to 11 kilometers of land is not available as of now. The Gaya-Son Nagar and Karajgaon projects have achieved 56.2% and 67.2% completion. And with work fronts also unavailable on these projects, the company has requested an extension on both of them. The New Delhi railway station project initially faced delay due to land clearances. Now it has gradually picked up, with completion reaching 18.36%. For the Thane Metro project, the appointed date has been declared as 11th January '26. However, this project is facing challenges related to land availability and local social issues as well -- socioeconomic issues. So the authorities are working aggressively to resolve these issues. Anuppur and Mirzapur -- the Anuppur and Mirzapur thermal projects are currently in the mobilization phase, with 2.43% and 1% completion, respectively.
On the solar project, as of September 30, '26, we've hit roughly 96% completion. Heavy monsoon, transmission line issues, land acquisition, and local disruptions have all caused delays in execution, but we're actively resolving those hurdles now, and we're putting the necessary resources in place to meet the revised contractual time lines — completion over the next few months, that's it. On the financial side, 89% of the required project debt is sanctioned, and the remaining balance of more than INR 215 crores is slated for release in quarter 3 and quarter 4 of FY '27, after the plant is commissioned. Operationally, we invoiced <<inaudible>> about INR 80 crores this financial year from 141 active plants, and we're targeting more than INR 250 crores in turnover — annual turnover — once all the plants are commissioned. On the BESS project, we've already executed a binding agreement with GUVNL and NUEL for 3 BESS projects. That's around 1,470 megawatt hours. Procurement of all long-lead items is in place, including BESS and PCS progress, with delivery expected by January '27. Civil works at Banaskantha and Dholera are approximately 80% and 60% complete, respectively, and the major material has already been received.
When it comes to Choraniya, the land formalities and design work are moving forward, and we've gotten in-principle bank sanction. So once these 3 projects are commissioned, they should bring in roughly INR 225 crores of annual revenue. Our expectation is that these 2 projects will be commissioned by March, with Choraniya following at some point in June '27. On the power transmission side, the company is pushing its portfolio forward across Odisha, Uttar Pradesh, and Jharkhand, where things have started moving on regulatory approval, engineering procurement, and on-ground execution. PSA has been executed for all 3 projects. At Angul, Odisha, <<inaudible>> has already come through, foundation work is progressing, and tower erection is going very smoothly. At Jamshedpur, Jharkhand, route alignment is complete, and land acquisition is also underway. In Mirzapur, Uttar Pradesh, land has been identified, and the lease agreement with the concerned authority is under execution. Engineering and procurement activities are progressing across all these projects, and for Angul we have received the financial closure, while for the other projects financial closure is targeted for the coming quarter. That's the update on the 5 new HAM assets that have been monetized. So in quarter 2, the company successfully transferred 51% of its shareholding in OD-5, receiving partial consideration of INR 103 crores.
The rest of the holdback money should come in during quarter 3 and quarter 4 of FY '27, assuming the relevant commercial CODs are achieved and specific purchase items are completed. During quarter 2 of FY '27, the company also collected INR 92.3 crores as a partial release of the holdback tied to all 4 earlier assets. Taken together, the company has now received INR 857.46 crores up to September '26. Of the overall consideration, the remainder is anticipated to arrive in quarter 3 and quarter 4, contingent on final COD and satisfaction of the applicable conditions. As for the fifth HAM asset, Raipur-Visakhapatnam AP-1, the company has already obtained the NOC from NHAI as well as from the lenders, and it expects to finish the equity transfer of the AP-1 project in quarter <<inaudible>> of FY '27. On the equity needs across all projects, the total equity called for by all HAM, transmission, BESS and solar comes to roughly INR 3,050 crores. And as of September '26, INR <<inaudible>> 1,846 crores has been put into these projects. The balance equity is to be infused over the latter half of this year as well as FY '28 and FY '27. Now let me turn to the financial highlights for quarter 2 and the first half of this year.
On a standalone basis, revenue came in at INR 883 crores, with EBITDA of INR 105 crores and an EBITDA margin of 11.9%. PAT for quarter 2 was INR 32 crores, a margin of 3.6%, versus INR 67 crores at a margin of 5.8% in quarter 2 FY '26. For the first half of FY '27, revenue hit INR 1,790 crores, with EBITDA of INR 182 crores and an EBITDA margin of 10.2%, and PAT for the first half of FY '27 was INR 60 crores, a PAT margin of 3.4%, compared with INR 193 crores and a margin of 6.7% in first half FY '26. Standalone gross debt is at INR 1,595 crores. That's made up of INR 714 crores of working capital debt, INR 400 crores of NCD, and INR 482 crores of term loans and current maturities, plus trade limits and other debt instruments. With collection expected from receivable monetization proceeds, we're aiming to bring standalone debt down to INR 900 crores by the end of this year. Turning now to consolidated financial revenue for quarter 2 FY '27, it reached INR 974 crores, with EBITDA of INR 250 crores and an EBITDA margin of 25.6%.
For quarter 2 of FY '27, PAT came in at INR 80 crores, which works out to a PAT margin of 8.2%; that compares with INR 52 crores and a margin of 5.7% in quarter 2 of FY '26. Turning to the first half of FY '27, revenue was INR 2,074 crores, with EBITDA of INR 553 crores, giving an EBITDA margin of 26.7%. PAT for that same first half of FY '27 was INR 35 crores, a PAT margin of 1.7%, versus INR 151 crores at a margin of 6.3% in the first half of FY '26. Our target for order inflow in FY '27 is INR 10,000 crores to INR 11,000 crores, and we had secured roughly INR 5,500 crores of that up to quarter 2 of FY '27. Growth prospects continue to look strong for us in roads, rails, metros, and power transmission, helped along by infrastructure investment that is coming and by government initiatives. Our ongoing priorities are high-quality projects, disciplined bidding, and execution on time, while we also broaden our footprint in emerging infrastructure segments. Given a diversified project pipeline and prudent financial management, we believe we are well placed to drive sustainable growth and to deliver long-term value to our stakeholders. At this point I will hand the call over to our IR advisor and ask them to open the floor for the Q&A session.
<<operator_script>> Our first question comes from Vaibhav Shah at JM Financial.
When it comes to asset monetization, we've already sold our 100% stake in 4 assets. Initially, we said the equity value was INR 1,384 crores. Since the investment is roughly INR 850-odd crores, the gain should come to about INR 530 crores. So what will the tax impact be? And when will that amount show up in the P&L, because so far in the standalone accounts we aren't seeing any major accruals on the P&L side?
So essentially, as we've discussed over the previous 2 quarters, these are the 4 projects that we've already monetized. Therefore, there isn't a gain into equity, because of the net worth of all those 4 assets. So at least in OD-5 and OD-6, we've taken a significant loss on that net worth. So collection is nearly — INR 550 crores of collection is still to come in from the 4 projects plus 1 project that hasn't been monetized yet, like AP-1. So INR 550 crores of collection remains outstanding, which we expect in quarter 3 and quarter 4.
And after that collection takes place, what gain would we then be recording in the standalone accounts?
On a standalone basis, that would come to roughly INR 70-odd crores, and it's probably going to show up in quarter 3 — or more likely, quarter 4.
A gain of INR 70 crores?
Right. So that's because of the consolidation — the gain from consolidation, which ties to the net worth figure. So if you look at the net worth, it was actually showing that different number, along with the collection, or the amount of consideration, so I can point you in detail to our finance team, and they'll give you the full details.
Second, regarding the revenue guidance, what would revenue guidance and margin guidance be for FY '27? And could you shed some light on how execution is progressing in Pune-Shirur and what our revenue targets are for that in this year and next year?
Right now, there are 2 large projects — one is Pune-Shirur and Odisha, the CRR project, one of the transmission projects, as well as the Mirzapur projects. These are all INR 6,000 crores of projects, and the appointed date is expected within this month, by mid of December at the latest. So in quarter 4, we expect all these projects to be generating that revenue, and mobilization has already been completed across all of them. By the end of this year, we expect to be at roughly INR 6,000-odd crores, if you look at it. Also on the margin side, there is significant — there is now considerable significance, since we are at around 11% because a few projects incurred huge losses. We would now be in the 13% to 14% EBITDA range for quarter 3 and quarter 4, and going forward from there.
Since the first half brought in just INR 1,800 crores of revenue, we posted INR 4,200 crores in the second half — that's 50% more than the second half of last year. So on that front, we have a lot of confidence.
Okay, so essentially every one of these projects where the appointed date is immediately expected <<inaudible>> — that is, being expected. So we — under any scenario, we'd be doing somewhere around INR 3000 — INR <<inaudible>> 4,500 crores down to INR 3,000 crores in quarter 4. So that gives us — this is — there's tremendous confidence — we're confident enough that we'd be able to handle that portion, since mobilization has already been completed across all of those projects.
<<operator_script>> Our next question comes from Shravan Shah at Dolat Capital.
Just a couple of things from me. First, one point to clarify. That order book figure of roughly INR 13,700 crores — about INR 65 crores. Has the unbilled revenue been taken out of it? I simply want to ask: when this gets executed, will the whole amount be booked as revenue, or will it be that figure less the unbilled revenue?
I'd say the contract asset really relates to work that's already been performed. As for the contract asset, or unbilled revenue, the execution has already happened — that's true in terms of physical progress. On the financial side, well, all that remains is collection. So again, once we bill them, once we invoice them, the collection will follow. The work itself is already done. So this comes to a net figure of INR 13,800-odd crores, net of all projects, with the remaining portion still to be executed.
All right. So unbilled revenue isn’t part of this. To put it simply, whenever we execute — suppose we execute all of it over the next 2 years — that figure will turn into revenue, the exact figure.
That's right.
All right, all right, understood. Sir, to return to what Vaibhav raised and dig a bit deeper into it: could you break it out by segment? Because the figure we have in front of us is revenue of roughly INR 4,200 crores. And correct me if I misheard, we're looking at INR 3,000 crores to INR 3,500 crores of revenue in the fourth quarter. If that holds, then for the third quarter we're looking at something similar, around INR 800 crores to INR 900 crores of revenue. So to go further, segment by segment, if you could specify for the second half how much revenue we're looking at in HAM road EPC — and there, obviously, Pune-Shirur is the big one — then railway, solar, BESS transmission, each segment, if you could specify, that would give much more confidence that we can achieve this kind of revenue?
Sure, regarding the battery side, those <<inaudible>> 2 projects are probably going to be commissioned. So on that basis, we're building in about INR 350 crores from that in the second half of this year — INR 350 crores — plus roughly INR 300 crores of transmission revenue that should also come through. So that's about INR 340 crores plus INR 300 crores from transmission. And on rail metro, we expect to reach a top line of roughly INR 1,400-odd crores in this half of the year, if that includes New Delhi, the RVNL balance portion that hasn't been billed yet, as well as the Gaya project, Aurangabad, Dhule, Thane Metro — which has only just begun, where a small portion has just been picked up. So these — and even Kanpur Railway station — so these come to almost INR 1,400 crores. So all together that's around INR 2,000 crores, with the balance coming from all 6 HAM. So the 5 HAM are being pushed aggressively and are at a very advanced stage, like Jharkhand Package 10 and 13 — the major contribution would come from these 2 projects. So roughly around INR 700-odd crores is to be executed across these 2 projects, Jharkhand Package 10 and 13.
There's <<inaudible>> that would get executed within that. And then you have other projects such as Narol, Ayodhya, and Tirupati. Those 3 are HAM projects, and again they should bring in roughly INR 600-odd crores during this particular phase of 2 quarters. On Pune, we expect to be at about INR 600-odd crores there as well, which is likely where we'll land, and we're already seeing mobilization happen, with utility shifting at an advanced stage. So this project will deliver at least INR 600 crores over this next half of the year. So taken together, plus certain projects such as Tumakuru and the Jamshedpur EPC project, with some small portion being the balance of HAM projects that are being monetized, including in Karnal where a small portion is the balance — so roughly INR 200 crores. So it's likely we'd be around — doing about INR 4,200 crores of projects, along those lines.
Understood. So then, as you mentioned for the second half, we'll be looking at a margin in the 13%, 14% kind of range, and going forward as well, in '28, we will be seeing a similar 13%, 14% kind of margin? And regarding order inflow specifically, how much have we bid? And there too, I just wanted clarity, particularly on the road side, obviously, we would be looking at that. So recently, the UP — many, many projects got canceled, the tenders which were there as part of tenders. So I just wanted to understand how much — how many projects across the different segments that we have bid, of that bid is yet to open, and how much more we are likely to bid, so that we can get an idea that whatever we are looking at, INR 5,000 crores, INR 6,000 crores more inflow in this second half?
Beyond that, there are additional projects as well — if you mean projects other than NHAI HAM or <<inaudible>>. Not many projects exist. We have already bid on roughly INR 7,000-odd crores worth of projects, and results are still pending. Railway projects come to about INR 5,000 crores. So if we're looking at why we're confident that we would see at minimum INR 5,000 crores to INR 6,000 crores of new orders awarded across the 5 months — looking at a state like MSRDC, those projects that had been canceled have already been re-invited. So the invitation is out there. <<inaudible>> has already been floated. Also, the state government — the Rajasthan government — RSRDC is going to bid for their 2 expressway in the coming 4, 5 months. NHAI has the pipeline, which gives us confidence that even rail metro — in metro, we have already bid on projects, a big one of INR 1,300 crores in Jaipur Metro and one in Delhi Metro. Ahmedabad Metro has a few big-sized projects, such as an INR 7,000 crores project, or 4, 5 projects there. So this looks like a mix of opportunity where we are hopeful, and transmission too, but we are quite hopeful that we would be able to just add this number.
All right. So roughly the same sort of inflow — INR 8,000 crores, INR 10,000 crores or more — even if, say, there's a delay of 1 or 2 months, and it lands by March, or perhaps April or May. So broadly a comparable inflow in FY '28 as well is something one can look at, so that what we were previously considering in terms of the INR 7,000 crores kind of revenue in FY '28 — can that be achieved?
That's entirely possible.
<<operator_script>> Our following question comes from Harshul Sharma, who is calling in from AS Advisors.
Sir, could you give us some color on what the guidance would be for the fiscal and FY '28?
As we’ve been saying, we’re aiming—at least with this past 1 year and this year—that we won’t have that much revenue because of slow awarding and an <<inaudible>> delay, but I’m quite hopeful that we would be doing around INR 7,000 crores in '28.
Sir, when do you think we might start to see an improvement in order inflow?
The orders are in place already. It's just a question of timing, which has been the situation—land acquisition and the DPR are all sitting at NHAI and ministry level. We're seeing that the traction exists, and we're fairly hopeful that this year roughly 1,200-odd kilometers will likely be suggested—that's what they're aiming to award. And other projects such as MSRDC, UPEIDA, and even in the state of Rajasthan. These are state expressways for roads. On rails, I believe some large projects already—the tenders exist. These are INR 1,000 crores to INR 5,000 crores projects involving rails and new lines like metro as well. So the pipeline is a mix across all these sectors—it's a mixed pipeline, and we're quite hopeful that we'll be able to secure it.
<<operator_script>> Our following question comes from Deepak with Svan Investment.
I just wanted to look into this sharp rise in commodity prices. If you could shed some light on our energy vertical, first on the BESS. And second, the projects we've secured from April onward, particularly the large <<inaudible>> ones — how should we view the margin profile on those projects? And in the battery side, when it comes to these shifts in product prices or lithium prices, is it a full pass-through mechanism, or how should we think about all of these assets?
Regarding highways, certainly, we've observed the commodity pressure, though it's being shielded through real-time price escalation for bitumen and crude POL. On rail projects, there has been an impact, and we've absorbed that hit, which will persist—what we've seen is that it won't be a large figure, since we don't have many rail projects involving OHE and S&T-type <<inaudible>> work in civil; that portion isn't affected much. Steel, cement, and aggregate don't carry a particularly big impact. With bitumen, it's there. On transmission, BESS has taken a hit. But again, we had taken that into account—earlier, margins in BESS were quite high. Now they've been around 12%, whereas previously it was expected to be 20-plus, due to the dollar and currency as well as battery prices. But that has been covered and factored in as of now. In transmission, where aluminum and copper feature and commodity prices have risen somewhat 30% to 40% plus versus the number we bid, we've nonetheless incorporated price escalation into our bid consideration, which has already been covered in our budget.
So we probably won’t take a severe hit from the commodity increase.
<<operator_script>> Our following question comes from Rahul Bhutra, who is on the line from Anand Rathi.
I just want to get a handle on this — I'm noticing interest income is rising because of a contract modification. Could you give me some color on what that was about?
On interest income, essentially we have a handful of projects in Maharashtra where we got roughly INR 18 crores, and that has been recorded under other income.
Sir, other than interest income, is there any revenue that comes into our top line?
No, no.
Is that because of the change to the contract?
Nope, nope, that's not the spot.
And then secondly, sir, I notice that during this first half we've put roughly INR 350 crores into contract assets. So — and what we've observed over time is that our contract asset keeps growing. So what's driving that, sir? Is there some slowness when it comes to billing — to securing approval for our bills — and which segment is making the contract assets grow?
Okay, so essentially, what we've observed is that wherever the debtors were, we've seen a substantial decrease — but debtors as of March, and now the number where collection is happening at a fairly significant pace. However, contract assets — a significant amount is stuck with the railways, because of the milestones and commissioning, since in those particular projects there are certain conditions under which roughly 10% of the total amount would only be paid once we commission the entire project and hand those projects over. So right now this is a significant amount — around INR 580-plus crores into railways. And others do have a mix of it, but the HAM project again has a significant number, where these projects that we already have monetized — and Karnal ring road, including Karnal ring road even. So they are the projects where certain COS variation items, and even in the Adani project Ganga Expressway, there's a variation item, which is around INR 180-odd crores from UPEIDA — already has <<inaudible>> sanctioned has been there. But then there is a certain amount of variation which is yet to be approved from Adani. So there's a mix of these 6 HAM projects — around INR 700-odd crores, which we are likely to collect in quarter 3 and quarter 4.
This contract asset, which has now grown significantly — it's reached INR 2,100 crores — should come down to roughly INR 1,200 crores to INR 1,500 crores, or about INR 1,500 crores, by the end of March. So collections of around INR 800-odd crores are likely to come in.
<<operator_script>> Our following question comes from Shravan Shah of Dolat Capital.
Sir, to start with a few balance sheet figures: so the whole contract asset of INR 2,165 crores—that would be the unbilled revenue as of September, correct?
Yeah, yeah.
All right, on mobilization retention money and HAM, solar, Ganga Railway, BESS debtors — if you could be specific there...
Mobilization comes to roughly INR 502 crores to INR 515 crores. When you include retention in the debtor figure, the debtor amount stands at INR 840 crores, with INR 203 crores in retention for that entire asset portion. Stock sits at approximately INR 495 crores. I believe advances to suppliers have climbed quite high, since we have booked all the material, and the GST balance with the authority is INR 288 crores. The cash bank balance is about INR 163 crores. On borrowings, we already have <<inaudible>>, and trade payables have fallen considerably from INR 1,633 crores to INR 1,188 crores now.
Yes. Sir, could you give us the debtor figures for HAM, solar, railway, and BESS?
So, approximately as I described regarding the HAM — the contract asset portfolio. Now, in HAM once more, SPV solar stands at roughly INR 236 crores, transmission comes to about INR 70 crores, BESS and transmission. HAM, once again, is a substantial figure, around INR 500 crores within HAM. Rail represents a quite minor share, and a certain sum has come in from Adani, even INR 113 crores.
Understood. And regarding the other income you pointed out for this quarter — the INR 18 crores for Maharashtra — so starting in Q3, will other income return to its usual run rate of INR 3 crores, INR 4-odd crores?
No, there are certain conciliation claims where we might end up getting these, but the amount would not be very significant.
Alright. So where CapEx is concerned, we've spent INR 66 crores during 1H. How much more should we expect in the second half, and how should one think about CapEx for next year?
CapEx — the major CapEx is entirely the Pune projects, where we're doing the launches and the other things; we aren't putting very much into equipment investment, but those are the shutters, et cetera, which would come to roughly INR 50-odd crores, which by the balance part of the year.
So for next year, should we expect CapEx in a similar range — something like INR 100 crores to INR 120 crores?
Yes, that's right.
All right, all right. And sir, on the Karnal Ring Road as well, when it comes to monetization, will that also be completed by this March? And broadly, how much could one look at in terms of value — the same kind of 1.5x price to book that one can look at?
No, it's probably not going to happen by March, since after we get the PCC there's a 6-month cooling period, and then we'll be seeking this monetization permission from NHAI, and the bank piece is going to take at least 8 to 10 months from now. And although we've received the <<inaudible>>, this offer from an investor, the number likely wouldn't be that large for this project because of the price indexing. But again, it's quite likely that within the 2 months we're going to close, we would be able to close this.
So the deal should close within the next 2 months. As for receiving the cash, though, you mentioned it would take 8 to 10 months...
Most likely during the second quarter of next year.
Alright. And with the 5 total that we've monetized, so from INR 1,384 crores, we've received — what's still to come is roughly INR 550 crores, which we'll be getting in the third and fourth quarter, and plus the AP-1. So that amount will be part of the pipeline as well — including all of it, INR 550 crores, okay. Including the AP-1. Okay. Got it. And sir, just the dates — from around INR 1,600 crores, we're looking at INR 900 crores by this March. So on the finance cost, right now INR 50 crores, INR 51 crores this quarter. So how should one think about the finance cost from the third and fourth quarter onward?
There's no question in my mind that the finance cost stems from the very sharp rise in debt. So by bringing it down to that level, in quarter 3 and quarter 4, approximately, we expect finance cost of roughly INR 80-odd crores. Next year, the financials will likely stabilize at INR 110 to <<inaudible>>.
<<operator_script>> Our following question comes from Rahul with Anand Rathi.
Sir, regarding this contract liability, which we see has gone up by INR 273 crores — can we say this is a mobilization advance received for the Pune-Shirur project? Is that the right way to understand it?
Correct — that's more than INR 170 crores coming from Pune-Shirur, which is one of the projects where we've already gotten a certain amount.
Understood. Now, secondly, sir, returning to contract assets: can we view this as the high point, with the figure declining from here as we carry out more projects? Because what we observe — even after completing the entire monetization process, perhaps only in part — is that our debt levels are not coming down. It is getting stuck in working capital. So how should we look at it? Is this the maximum working capital we are seeing, and from this point onward it should begin to fall?
So the plateau has pretty much been hit just in the last quarter. Now a significant drop is likely to be there — be it, say, if you look at the debt part, if you look at the contract asset part, where the balance sheet is showing this number. And then the realization by the end of this year is going to significantly reduce the debt, because contract asset is likely to come down by almost INR 700 crores to INR 800 crores by year-end. Debtor would be in a similar range to where we are now, and creditors would be in a similar range as of now.
Sir, just one last question about the technical side. As I understand it, we bid on every package of the Link Expressway of UPEIDA. Yet for some technical reason, we ended up disqualified. So what was the reason behind that technical disqualification?
We had roughly 5 to 7 contractors who got disqualified, or I believe it was for a minor technical reason, and that was probably all missed.
Understood. So, sir, are there any technical challenges of that kind that would exist in the MSRDC projects, or now that they are being protected?
For the MSRDC projects being invited at this point, the qualification criteria applied are identical to those we met roughly 3 years ago when we qualified for that work. That part hasn't changed. So the bid stage involves only the RFP, not the RFQ.
Our following question comes from Vaibhav Shah at JM Financial.
Sir, when should we expect to get the appointed date for Package 3 of the Capital Region Ring Road?
Around the end of November, into the first week of December. That applies to Pune and Shirur alike, and to this project as well.
Alright, so the revenue we're seeing in Pune, roughly around INR 130-odd crores in the first half, that's mainly due to utility shifting and...
There are specific pre-op costs, along with globalized costs, and those existed previously too — it's essentially a project. So we split that out so we could capture the cash flows and billing. That was a minor amount, and it was already present before.
So the goal is approximately INR 700 crores in revenue for FY '27 coming out of Pune-Shirur — is that right?
You’re absolutely right about that.
<<operator_script>> Our following question comes from Arpan Gandhi of A.J. Capital.
I'd like to ask, when might we start to see margins improve? And when could margin levels get back to roughly 15% and above, the way they were in the prior fiscal?
At this point, given the current situation, it doesn't really seem that way, because of geopolitical commodity prices and also competition across the whole infrastructure space — we aren't really confident that in the next 1 to 2 years that's going to be there...
<<operator_script>> Ladies and gentlemen, that was the final question from the participants. I would now like to pass the conference over to management for their closing remarks. Thank you, and over to you, sir.
Appreciate everyone being here today. Our confidence in carrying on this success hasn't wavered, and we're ready to take on whatever other questions you have. Don't hesitate to get in touch with us or with our IR adviser.
Thanks. That wraps up this conference on behalf of Go India Advisors. We appreciate you joining us, and at this point you can disconnect your lines.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete H.G. Infra Engineering Limited transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to H.G. Infra Engineering Limited earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.