Good day, everyone, and welcome to HG Infra Engineering Limited's Q3FY26 earnings conference call, brought to you by Go India Advisors. Just a reminder that every participant line is in listen-only mode, and once the presentation wraps up, you'll have a chance to ask questions. If you require any help during this call, please press Star then zero on your touchtone phone to signal an operator. Kindly be aware that this conference is being recorded. I'll now turn the conference over to Ms. Selena Sheikh of Go India Advisors. Thank you. Over to you, ma'am.
Good evening, everyone, and welcome to the HG Imsha Engineering Limited earnings call, where we'll discuss the operational and financial performance for Q3 and 9M FY26. This call is hosted by Goindia Advisors. Joining us today are Mr. Harindra Singh, Chairman and Managing Director, and Mr. Rajiv Mishra, Chief Financial Officer. We need to remind you that today's discussion may contain certain forward-looking statements, and those must therefore be considered together with the risks the company faces. We now ask Mr. Harindra Singh to walk us through the company's business outlook and performance. After that, we'll open the floor for Q and A. Thank you. And over to you, sir.
Thank you, Serena. Good evening, everyone, and a warm welcome. Every one of you joining us on today's call. Here at HG Infra, we take immense pride and delight in having devoted more than 23 years to shaping the backbone of India's infrastructure, and we recently marked our 24th foundation day. As we look back on this journey with pride and move forward with purpose, it has been built on certain things. First, driven by passion and defined by quality. These enduring values keep guiding us as we construct infrastructure that propels India's progress. To meet India's evolving requirements, we are scaling for success, fast tracking innovation to build smarter, faster and safer infrastructure. We are entering new sectors such as solar energy, transmission and battery storage. Guided by the simple belief that infrastructure must be as dynamic, as diverse as the nation itself. The Union budget of 2627 has strengthened the road sector with higher allocation to the Ministry of road transport at 3.9 lakh crore rupees, up 8% year on year, and increased funding for National Highway Authority of India to 1.87 lakh crore. This enhanced investment is expected to accelerate development of National Highway, Expressways and greenfield corridors, leveraging our strong execution capabilities. AG Infra are well positioned to benefit from this momentum, with 45 plus road projects delivered, and our track record reflects engineering excellence, timely execution and durable quality.
By December 25th, the order book for our roads and highways segment is at 8,460 crores, which makes up roughly 62% of the total. At the same time, the Union Budget 2627 once again keeps its focus on rail infrastructure, with a capital outlay of 2.5 lakh crore set aside for Indian Railways to back network expansion, capacity enhancement and modernization. In line with that momentum, AGIL has deliberately diversified into rail and Metro infrastructure, with more than seven projects currently underway. Our footprint in this segment shows our developing technical expertise, disciplined execution and our ability to deliver complex infrastructure. Green energy also represents a substantial new chapter in AG's growth story, since we have already executed more than 350 megawatt, and the remaining 250 megawatt is expected to be finished by March 26th, out of a total 600 megawatt capacity order that comes with an integrated storage solution, which reinforces our emphasis on sustainable, future ready infrastructure. Let me start with a quick look at our operational highlights. As of quarter three FY26, the company's order book came in at rupees 13,624 crore, made up of 8,734 crore from roads and highways, 2,779 crore from railways and battle 1620 crore from base, and 394 crore for solar and transmission project, with the rest, 98, from other sectors. By segment, roads and highway accounts for 64%, then railways at 20%, renewables at 15% and the other segment at 1%.
On the EPC and highway project updates, we're at almost 99%. The Kangas project is finished, and we're applying for COD, which will likely come through in this quarter only. The Jamshedpur Elevated project is moving along well, with progress currently at 36.9%. The Neem Langla Tumkur project is picking up execution pace and has hit 54.4% completion. The appointed date for the DLF project has been declared as 30 December 25, and that project is in the mobilization stage. On HAM and highway projects, the Kandal Ring road is at 94.2% completion, showing steady progress, and is likely to get provisional completion in Q4FY26, as we shared last quarter. Provisional completion certificates for the Raiful Visakhapatnam Corridor 45 and OD 6 projects have already been received, and both remain close to completion. The Raipur Vishakhapatnam again AP project is also nearing completion, and we've received the provisional completion certificate with effect from May 25. All three projects of the Raipur Vishakhapatnam corridor — that's OD5, 6 and AP1 — continue to be on track for COD in the next few months. Only the Khamam Devrapalli for a cache 8 KD1 and 2, where the PCC has already been received, which are at 99.1 and 96.9% completed completion. Both packages are expected to be 100% completed in Q4FY26, the Chennai Tirupati ham project has reached 40.1%, the provisional appointed date for the Varanasi Kolkata corridor package 13 has been received with FRAC on 30th September 25th, and the project of package 13 stands at 19.4% — for package 10, the appointed date is expected to be received in quarter 4 26.
Regarding Kosi Panirama package number 6 of Ayodhya, the concession agreement was signed on 21st of June 25th, and the appointed date has recently been declared on 16th January 26th. For the narrow circuit project, financial closure was achieved and the appointed date was received with effect from 19 August 25th, with the project's exhibition standing at 3.4%. Project execution stands at 15.6%. Turning to progress on railway projects, the DMRC Metro project is 99% complete and moving along the scheduled timeline, targeting completion in Q1FY27. The Bilaspur Himachal Pradesh Railway RW project is 87.8% complete, with the target for completion in Q1FY27. The Kanpur Railway Station progress project is at 44.9%. The Dhule Nardana Railway project has achieved 35% progress, and the Gaia Sonnagar and Karanjigama projects are at 27.3 and 32.7% completion respectively. Progress across these projects was impacted due to abnormal rains, but it is expected to pick up. The appointed date for the New Delhi Railway Station project has been declared as 6 August 25 after the initial hiccup related to utility shifting and design. Execution is now at the initial phase with 6.9% completion. The appointed date of the newly awarded Thane Metro project has been declared as 11th January 26th, and the project is in the mobilization stage. On the solar project as of 31st December 25th.
Looking at where the project stands overall, physical progress is at roughly 95.8%. There were delays of a few months, and those came from the extended, intense monsoon conditions in Rajasthan, along with land-related difficulties that held back development of the transmission line infrastructure — so these projects slipped. Even with those constraints specific to the sites, the company has managed to carry out the project pretty much in step with the schedule it had planned. The company is deploying sufficient resources to bring all the plants into commission within the revised contractual timelines over the coming months. Commissioning of the antifacility will also make possible the drawdown of the remaining sanctioned debt and allow the outstanding liabilities to be cleared. Given the difficulties developers in Rajasthan have run into, the Ministry of New and Renewable Energy — that is MNRE — has once again extended the commissioning guidelines for the solar plant under Kusum Sea Scheme A and C, through 31 March 26. On the financing side, about 86% of the project debt required has been sanctioned, and of that roughly 74% has been disbursed. The remaining sanction and disbursements will probably take place after the installed plant is commissioned. Meanwhile, to close the funding gap and make sure the project is completed on time, the company has taken on additional working capital limits.
So as a result, the total debt at the company level has gone up for the time being, and that will come down over the next few months once we receive the solar balance disbursement of Rs.425 crore. As of December 25, the total equity investment in these solar projects is at 731crore. Right now, the total amount billed to The DISCOM is 72.88 crore, and 56.33 crore has been collected to date. On the best projects — there are three projects, two from GoNL and one for NVN, totaling 104,070 megawatt hour. The procurement process for the best project has been kicked off, and orders for long lead components such as the power transformer and GIS switch gear systems have been placed by the company, and exhaustive technical due diligence has been carried out for the DC block container with both overseas and domestic vendors. Final orders for the same are likely to be placed by March 26. In January 26 the company formed the SPV and purchased land for the Banaskarta project, and both projects have now received approval from the Connectivity Agreement. Financial closure of the Banaskara project is done, and DHOLERA is at an advanced stage of closure and is expected to be completed by March 25th.
Once every one of the best projects is finished and commissioned, the company anticipates yearly revenue of 225 crore from BEZ. On the transmission project, which is moving along nicely in line with the timelines, with the SPB being formed, the design done and the long lead items booked, here is where things stand on monetization of five New HAM Assets: with the PCC already received on August 25th, we signed a binding document with new Infra Income Opportunity Fund for divesting our HAM portfolio across five wholly owned subsidiaries. The security purchase agreement for all five projects was executed by us in the prior quarter. We had already begun the work of satisfying every condition precedent, including getting client approval, lender consent and completing the required representation warranties. Lenders' NOC has come through for Common Developery Package 1 and 2 and for the Raipur, which are government projects. For Package 5, NOC has been received from one of the senior lenders, and approval from the remaining two lenders is expected shortly. NHI has also approved the NOC of Khamman Devarapalli Package 2; for the remaining projects we are in continuous follow-up with NHI and the respective lenders and anticipate receiving the requisite required NOC within the next month.
Given where things stand right now, we expect to close the deal for at least 3 of the project SPVs during this financial year, and we anticipate roughly 500 to 600 crore as the first portion of consideration for this project. On the equity requirement for HAM projects, the total equity needed across 11 HAM projects comes to 1750 crore. As of December 25, 1242 crore has already been infused. From the balance, 117 is slated for infusion over three months this year, then 220 crore in FY27 and 171 crore in FY28. Turning to the financial highlights for quarter three FY26 and the nine months of 26 Channano Financials, revenue for quarter three FY26 came in at 1,450 crores, with EBITDA of 224 crore at a margin of 15.5%. EBITDA PAT for Q3FY26 was 97 crore, a PAT margin of 6.7%, versus rupees 137 crore and 9.1%. In quarter three FY25, revenue for nine months FY26 reached 4,313 crore, with EBITDA of 607 crore at an EBITDA margin of 14.1% PAT. For nine months FY26 it stood at 290 crore, a PAT margin of 6.7%, compared with 365 crore and a margin of 8.9% in nine months FY25.
If we look at gross debt on a standalone basis, it comes to 1545 crore. That breaks down into 914 crore of working capital, 631 crore of term loans, and current maturity trades. Limit and means of debt. Turning to the console number, revenue for Q3FY26 came in at 14.21 crore, with EBITDA of 309 crore, a 21% margin. PAT for Q3FY26 was 94 crore, a PAT margin of 6.6%, versus 115 crore at a margin of 9.1%. In Q3FY25, revenue for 9 months FY26 reached 3808 crores, with EBITDA of 775 crore and an EBITDA margin of 20.3%. PAT for 9 months FY26 stood at 245 crore, a PAT margin of 6Point4%, compared to 358 crore at a margin of 9.7% in 9 months FY25. An update on the recent CBI matter: as you are aware, the CBI and anti corruption bureau Patna conducted searches at our offices in the month of January. The necessary updates on the same have already been disclosed through the stock exchanges. We are giving our full support to the agencies in this matter and will keep updating investors through our disclosures on the stock exchange upon any material development, and I would like to mention that there has been no impact on the operations and financial position of the company.
Now moving to what comes next in strategy and how we see things shaping up: HG has delivered outstanding results on every measure, beating the odds, and has brought projects in on schedule with strong trust, passion, and quality. As all of you are aware, awards of new projects from NHIS have seen weaker momentum over the last 18 months. Still, based on our discussions with NHI, things appear set to pick up again, with fresh project bids coming in the 9 months of FY 26. During those 9 months of FY 26, we have secured new projects valued at 3300 crores to date, and we are fairly hopeful of adding projects worth roughly 4,000 to 5,000 crore by March 26. I will now pass the call to our IR advisor and ask that the floor be opened for the question-and-answer session.
Thanks a lot. At this point we'll open things up for questions. If you'd like to ask something, just press star and one on your touch-tone phone. Should you want to drop out of the queue, press star and two; we ask that participants use handsets when posing a question. We'd also ask everyone to limit themselves to just two questions. If you have more, you're welcome to rejoin the queue. Ladies and gentlemen, we'll pause for a moment now while the question queue gets assembled. Our first question comes from Mohit Kumar of ICICI Securities. Please go ahead.
Yes. Good afternoon, sir, and thank you for the chance to speak. Sir, could you please give us an update on the appointed date for Nagpur? Regarding the Nagpur EPC orders, I believe there were 2 projects worth 42 billion — is there any risk that those orders could be cancelled?
The scrapping of these projects likely isn't part of the pipeline order under discussion at all. Land acquisition, which really has been affected lately due to the municipal elections in Maharashtra, is therefore proceeding at a pace unlike what we had before. So it appears that by April or May, 70% of the land, which is a prerequisite for the LOA to be issued, will be in place by then. We are checking with the authorities on what the latest update is.
So I’d expect the work may begin in H2F27. Given what we know right now, is that a fair assumption?
Yeah.
The second point is that, of course, the NHI tender pipeline has been rather weak for the past several quarters. What are you observing in terms of progress on the ground? Do you have hope for a sharp pickup over the remainder of the fiscal year, or do you think the progress will most likely come in F27? And will F26 again be a Dalia?
On the development side, and regarding getting signals from the authority, it’s quite encouraging what they’re doing. The pipeline is very long, and the land equation — which is a major precondition before the authority can award any project — was not there earlier either, and validation of DPR quality through their DPR cell is taking a while. The projects for which cabinet approval has already been secured total more than 60,000 crores. But then again, there are many additional projects where cabinet approval is likely to come through in the shortest possible time. So it’s just a question of a few months from now when these projects — around 6 lakh crore rupees, which they have put into their domain as well — would likely be awarded, not in this current year, the current financial year, but next year, definitely next year.
Regarding my final question on revenue guidance: do you still stand by the 65 billion figure for the fiscal year, or do you see any risk to that number?
There’s been some slackness along with the progress, and that’s because the monsoon lasted longer than usual. That’s one reason. And the monsoon’s retrieval — which has had an effect — has also impacted the project. But even so, we’re quite hopeful that we’ll surpass last year’s number, and we’re looking at the appointed date for Jharkhand package 10, which was supposed to be there but hasn’t been issued yet. It will likely be given to us only next month. So that has had an impact of around 2 to 300 crore rupees. Otherwise, we would be at or around last year’s number plus some percentage over that number.
Got it, sir. Thanks very much — and best of luck. Thank you.
Thanks. Ladies and gentlemen, if you'd like to ask a question, you can press star and 1. Our next question comes from Vaibhav Shah of JM Financial, who is on the line. Please go ahead.
Yeah. Sir, was there anything one-time in the EBITDA margin this time around?
My apologies.
Was there anything nonrecurring affecting that 15.5% margin? Because typical EPC margins are 15.5%.
That's the standard EPC margin. Nothing extra, no exceptional item, has been included in this figure.
All right, so what caused the tax rate to come in so much higher — 31 1/2% — for the quarter?
There was a sale last year. For MSME, 6 crores of provision has been made in the CEO for the tax matter. So because of that, it's a bit higher.
Second, when do we expect those solar projects to be finished, and alongside that, when do you see the debt starting to come down?
Regarding the 425 crore in debt that we still need to collect from this PV, flowing from the lenders to the SPV and then on to HG, it's likely that roughly 200 crore rupees will come in by March, with more following in April. That's because all of the commissioning has now been pushed back to March, given the local disturbances and the issues we've already encountered. A number of other companies have dealt with similar things. So in April and May, during quarter one, we would receive the full debt amount once we commission these plants in their entirety.
And for the incremental work as well, which involves spending roughly 400 odd crores, that too will require putting in additional money, right, to support the STV.
No — regarding the exhibition, it's already more than 98% done. So the funds you're asking about for what's nearing completion — that isn't such a large sum; it's 3,540 crore rupees, which we needed in quarter four solely for full completion. So the money we'll be raising is 425cr coming from the SP through debt.
As of December, though, the order book for solar projects appears fairly elevated.
No, no — that's transmission and solar.
Right, right, right, understood. And sir, when should we expect work on the BSS projects to begin, and what's your guidance for FY27, given that—given the expectation that—revenue from the MSRDC projects would be considerably lower since it's likely to start in the second half. So what guidance would you give for 27?
With the current order book, our IOP plan is built around executing roughly 2,000 within this year. At that level, the best execution we're likely to have finished is for next year only — the full completion would land there. That's without even counting the Nagpur Chandrapur MSRDC project. As for what has to happen with the new projects we expect to pick up over the coming months, we're looking at about 1,500 crore rupees from the new project or the MSRDC project. All the others are already in place. Yes, as we said, just started or just one project yet to start would be enough to get us to 7,000 crores for next year.
Alright. Alright. And sir, what would that be? So when should we expect to get the appointed date for the mod? Sam.
We've begun 3% of the completed work as of late, and the appointed date was declared on 16th January. There's only a single project that's balanced where the appointed date hasn't been declared yet, and that's Jaran package 10. Yeah.
Alright. Alright, thanks, sir — that covers everything I wanted to ask.
Thanks, everyone. If you'd like to ask a question, just press star and 1. Up next, we have Shravan Shah calling from Daulat Capital. The floor is yours.
Hello sir. Sir, to revisit the first point again, on the revenue side. So you mentioned roughly 2,000 crore that we're looking at in the fourth quarter. So that stands. And in the. In the following year we're seeing something like 7,000-odd crore. So even if I. I look at it broadly, it would be a kind of 13 kind of growth that we're looking at. So I'm still not able to understand the shortfall that's there for FY26 — earlier we were looking for 2715% plus. So now again a 2300 crore shortfall exists for FY26. So for 27 previously we were looking at 7800-odd crore. So setting all that aside, what we're looking at in FR27.
Basically, that's the situation. The main cause of the shortfall for the year was the extended monsoon, along with the appointed date for this cross project being pushed back — Jaskan package 10. That's the reason, and we're fairly hopeful we'll pick it up, somewhere around 6,200-odd crore rupees, if we manage it during the year. As for the balance for 2025, 2026, 2027, we're estimating that at least 1,500 crore rupees for the company would come from the project where the appointment was made, which hasn't been issued yet — the alloy is still awaited — that's MSRDC, or any other project we're likely to secure in the coming months only. So beyond that 1,500, if you do your best, progress on all the other projects would yield around 5,500. So we've estimated that we'll be touching roughly 7,000 crore without much of a problem next year.
Alright. So on that 1800-odd crore we've already received as inflow up to now, and the 4,000 to 5,000 crore we expect by March — I just wanted a bit more clarity. So, two or three aspects. First, what's the value of the bids we've submitted so far? And also, could you break that down by whether it's MHI, MOS, railway, solar, BES, or some other sector? And how much more do we plan to bid — whatever tender pipeline is available now?
We've got roughly 14,000 crores of highway projects that are already in the bidding stage — EPC and HAM. Three of them are EPC5 HAM, and we're still waiting on those results. Then through March, we expect to bid 48,000 crores worth of projects. So those are the ones we're looking at. Beyond that, we're also lining up projects with private developers. Those are the opportunities we feel pretty confident will come through for us this year. On railway: we already have one project where we're the bidder, and the second one is a 4,600 crore project that's already been bid, with the bid yet to open. Then there's about 4,400 crores — 4,000 megawatts — of bids still to be submitted, and 2,760 megawatts of bids in progress where the results haven't come out yet.
Roughly what would that 1400 megawatts we completed in 2016 be worth? And the 760 that we intend to construct. On the EPC side, I'm especially—
If you were to ask that, the figure would come out to something in the neighborhood of 8,8000 crores.
Taking all of that together.
Combined, that's what we'll do. Whether we've already placed a bid or would want to place one.
Understood. And on the margin side, that 15% to 16% guidance we've had for a couple of years — will that stay as it is? Or are we running into competition, so that going forward the margin could end up lower?
Right now, for the project we already have in hand, we do have this margin—that's certain. But in the near future, as market trends are showing a bit of a correction signal, margins likely won't stay at that same number—they'd be around 14, or let's say that figure. So in any case, when we bid and try to look at revenue, we're not going to see 10 to 12% margins as a doable kind of margin for us. But we're focusing, we're looking at projects with 40% in any case for future bids.
Beyond that, we're open to having bot toll as well. Otherwise, we'd rather go with the subcontracting model.
No, no. This particular option hasn't been explored by us yet.
Yeah. And finally, just a few balance sheet items: inventory data, straight table mobilization, unbilled retention M data, solar data.
The mobilization advance comes to 260 crore. The stock position is 358 crores. Debtors total 1551 crore rupees. Within that, debtor ham debtors account for 579. Solar SPVs hold 330. So all of these SPVs — Ganga sits at 277 crore rupees. Others plus railway come to roughly 200 crore rupees. And the unbilled current asset is 1448 crore.
1,400. All right. And the trade table.
Solar and hand each have 700.
No, no. The total trade payable figure, which stood at 1177 at September.
The trade table figure comes to 1298 crore.
All right, though you mentioned the overall inventory figure.
Apologies for cutting in on what you asked for.
I understand, I understand. I'm finishing this point. This applies to everyone here. This isn't a question. I get it. So that's exactly what I'm asking. If the— if the promoter isn't facing an issue, then in my view you ought to stay quiet. Apologies, sir. Yes, yes. And consolidate and console cases.
Console. I don't have the correct figure in front of me. I believe we would be providing it. We'll circle back to you on that. Oh, and what you're asking about is the console debt.
Yeah. Gross debt for consoles, and cash for consoles.
That debt remains on my books — console debt of 6032 crore rupees. And console cash stands at 255 crore rupees.
And with BS equity up to this point, that same tank has been invested, and the remaining amount that needs to be put in during the fourth quarter and 2728.
Regarding solar, we've put in complete equity of 731 crore rupees. There's no additional need. The BS for this year should come to roughly 99 crore rupees. Up to now, 16 crore rupees has already been invested.
And 2728.
For 27 2020 through 2627, the overall equity requirement, hand included, comes to 605 crore rupees.
Understood, sir. Thanks. That covers everything else.
Thanks. Listeners, if you'd like to ask something, hit star and then 1. Up next we have Manish Gadda, an individual investor, on the line. Go ahead.
Hello sir, you should be able to hear me now.
Yeah.
Yeah. Hi sir, I have one query. Yeah. As of right now, over nine months, we've brought in revenues of roughly 3807 crore. So for the fourth quarter, what are you expecting — I mean, what is.
The consolidated figure comes to 3,800 crore rupees. And on a standalone basis, we've already reached 4,300 rupees. Typically, we count our turnover as what I'd honestly call the turnover on which — but for the last quarter, we expect to do around 2000 crores.
All right, and how about the EBITDA margin as well as the profit margin? Sir, are we looking at the same figure, or will it decline somewhat?
Approximately 15%. About 15, 15.
Alright sir, one more question on that. You mentioned you have that 4,000 to 5,000 crores of odd. You'll get the work in this quad. But how confident are you about getting that? Sir.
That has already been submitted, and we are also hoping for the advanced stage of certain for the private developers. So these are the—this is how we see it: around 4000 odd crore rupees, or fourth of our thousand crores of order, is likely to be added in this period up to March only.
Alright, sir. Understood. Thanks, sir. Wishing you the best.
Thanks. Ladies and gentlemen, if you'd like to ask a question, you can press star and 1. Our next question is from the line of Vivek Joshi, an individual investor. Please go ahead.
Mr. Singh, there's just one thing I'd like to get clear. Could you shed a bit more light on the CBI's visit to our premises, and on whether any employees were involved in any form of illegitimate activity?
Regarding that matter, everything that has been reported has already gone to the stock exchange from our side. So beyond that, there's nothing further with us, so to speak, as far as updates go. Therefore, should any update come about, we will provide it.
The filing we'll submit to the stock exchange makes no mention of whether any employee had any involvement. Because we're seeing three senior executives leave the company dramatically. So is there any involvement by those executives, by any employee, or by anyone in management in any of these activities? Hello.
Right, this isn’t anything new that’s connected to this specific matter.
And so, what kind of update can we get on this? I mean, what was the reason behind the CBI coming?
No, but once more, the thing that counts is subjugation, and whatever actions we took on the abation matter would be provided to the stock exchanges. The stock exchanges, as a channel of communication.
And not to the shareholders. Is that right?
No, it can be shared, but there isn't really any update. We've already seen it.
No, no—I'm not after any kind of update here. All I want to know is why CBI showed up. You see, each time folks from CBA YT arrive, they bring along some kind of explanation—something along the lines of, we're here regarding such and such a matter. So could you just shed a bit of light on that for us?
From my perspective, CBA has no grounds for looking anywhere. They have their own justification. They did so. And whatever the event was, we have updated the stock exchange. So no transaction has taken place, nothing is going on. That has been updated.
Thanks, everyone. To ask a question, you can press star and one. Shravan Shah from Daulat Capital is up next. Go ahead.
Yes sir, so far across the nine months, how much capex is going forward? We used to save minimal capex. So that trend remains.
What type of capex are we talking about? Equipment. So, on a standalone basis, how much capex is involved? Hardly — I think it's more like 30, or 5, or rupees invested during this particular nine months, and nothing major would be done, because the projects we have are a mix of that. So we do have a good amount of machines and equipment.
Right. So that figure you mentioned — 1,545 crore, odd — maybe around 200 crore. Once the solar disbursement comes in, it would come down, or that's one piece of it. And second, apart from that, are there any further options when it comes to the reduction, by the merchant, and how should one then look at it for FY27 onwards — the date.
Okay, so there have basically been two main factors here. The first one is the solar debt. The second is the data and the current receiver — they're saying this is the current asset. So this is a very high all-time high. Because the projects we're at this stage with are roughly 10 bit-size projects, solar included. There's a 12 big-size project that's right at this particular verge, where some unbuild is there, contractor set, and certain debtors have gone high. So once we're 100 at this stage, completion is being done and the cod is being done, and whatever unbilled is being built and the debtors would be received. So this will give a significant relief to the debt.
Understood. And then, on this DES you mentioned, the whole 1600 crore order book that exists will be executed by FY27, or half of it in 2728.
Regarding battery, roughly 85% of the best would be finished by March, since the third best actually has a timeline running through June 27.
And regarding the railway segment—so out of the roughly 2,800-odd crore currently, how much can one achieve?
From this project, we'll be doing about 1700 crore rupees.
Thanks to everyone joining. To ask a question, you can press Star and one. Manish Gadda, an individual investor, is on the line with our next question. Please go ahead.
Hello sir, apologies for coming back to you on this. Our profit margin has been going down. What is causing that?
During the past 3 quarters, it had been shrinking, and that came from some modifications — specifically, revised profit forecasts on a handful of projects, most notably Ganga and Sonar, plus at least 1 more project under NHI. At this point, those have settled down.
Since the prior quarter also reported 6.7%.
No, no — I’m not referring to the pat. What we’re discussing is the.
I mean the pack margin. The PAC margin too — it’s fallen from 9% to 6.7%, and that’s the reason behind it.
Regarding the tax rate — I believe one of the exceptional items that affected it ultimately comes to 25%, but this time it's 32%, owing to a kind of provisioning that's being done for tax provisioning related to last year.
Alright.
Thanks to everyone involved. To ask a question, you can press Star and one. Vaibhav Shah from GM Financial is up next. Go ahead, please.
Sir, if we assume the LOA arrives from MSRDC during the first half of this year — we took the L1 in May 24, so there's nearly a two-year gap — would the bid get revised, or could that affect our margins?
On the revision and all that, there isn’t really any update. Each time, it’s a matter of a bit of validity that we keep extending. So we’re fairly hopeful, since land acquisition is proceeding at the project level with our team on site. They’re seeing the land position and so on. So we’re fairly hopeful that it will be awarded very soon. But it’s just a question of the government side—whether that availability has ended.
But if we—if we go with the bid we turned in two years ago, won't that hurt the margins on the project once we execute it?
No — if we simply leave that figure out, it sets the line. Suppose those orders aren't there, then we'd have fewer orders regardless, which is a balancing order — if that's basically what you're getting at — and then orders in the months ahead, in the year ahead, would need to be added just to keep up that streak of roughly 10% to 15% year-on-year growth.
The way I was looking at it is this: had the lo arrived a year sooner, we'd already be about 50, 60-odd percent along in executing the project by now, so what value would we have built in during that bidding period? And once we begin execution, say at some point in the second half, what would we be doing?
In any scenario, margins aren’t going away, because when these kinds of projects are done, there’s price escalation. So whatever applies from the base date would be added onto this for the price escalation—whether it’s negative or.
So it does include a PVC clause.
Yes, a PV clause is included.
Oh, all right. Thanks. Hey, just one more thing — what's the order going to be?
Please get back in the queue. If you have any more questions.
Of course.
Thanks. We’ll take the next question from Bhavan Modi at Anandra team. Your line is open — please go ahead.
Thanks for having me. So on the previous call, there was some discussion regarding, you know, the inflow from the Adani group. What's the status on that?
The discussion is at an advantage. We have submitted our re, and they are two twice the negotiation of the further terms and condition has been discussed. Say one more bit or few more bits also has been in advance stage of discussion with Adani group and one more group.
And so, that applies to every one of the road projects, or is it, you know —
Roads and rail.
And then, on the previous call, you also brought up, you know, moving into building construction as well as the green hydrogen area. So has there been any progress on that front?
Yeah, green hydrogen. As of yesterday, only that bed existed, but we weren’t in the race — we stood at L3. Still, in the future we would also be looking to be in hydrogen.
All right, so where do we stand on order inflow for the year to date?
For the year, that comes to 3,300 crore for the day.
Thank you. Thanks.
Thanks. The next question comes from Ishita Lodha at Swan Investments, on the line. Please proceed.
Hello, sir. Thanks for the chance to ask. Sir, could you give some clarity on the execution guidance for FY27 — how much do you expect to come from roads, railways west, and sonar? Also, as a follow-up, would you let us know the order inflow target for FY27 for future growth?
As has already been indicated, we're looking at roughly 10 to 12% year over year as far as FY27 is concerned — approximately 7,000. And regarding guidance for order inflow, we're aiming for somewhere around 10 to 12,000 in orders during the year FY26 27.
Of that 7000 crore in execution, 1500 is expected to come from the new project.
We've therefore taken into account that, from the projects already underway — which include the Varanasi Kolkata package 10 — and leaving aside this MSRDC project, roughly 5500 crore would come from that work already started. Adding this one, plus the projects likely to come up soon, MSRDC included, we're looking at 1500 crores for those projects.
Thanks, ladies and gentlemen. We’ll treat that as the final question for today. At this point, I’d like to pass the conference back to management for closing remarks. Gentlemen, over to you.
Thanks for being with us today. Our confidence in carrying on with this success hasn't changed, and we're ready to take any additional questions. Don't hesitate to get in touch with our advisor Goindia Advisors. Thank you.
Thanks from Goindia Advisors. That brings this conference to a close. We appreciate everyone taking part. Your lines can be disconnected now.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete H.G. Infra Engineering Limited transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to H.G. Infra Engineering Limited earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.