H.G. Infra Engineering Limited (HGINFRA) Earnings Call Transcript
August 14, 2025
Earnings Call Speaker Segments
Good day, ladies and gentlemen, and welcome to the HG Infra Limited Q1FY26 earnings conference call, hosted by Goindia Advisors. Please be reminded that every participant line will remain in listen-only mode, and once the presentation wraps up, you'll have a chance to pose questions. If you require help at any point during this call, just signal an operator by pressing Star followed by zero on your touchtone phone. Kindly be aware that this conference is being recorded. I'll now turn the conference over to Saloni from GO India Advisors. Thank you, and the floor is yours.
Good afternoon, everyone, and welcome to the HG Infra Engineering Limited earnings call, hosted by Go India Advisors, where we'll discuss operational and financial performance for the first quarter of FY26. Joining us on the call are Mr. Harindra Singh, Chairman and Managing Director, and Mr. Rajiv Mishra, the Chief Financial Officer. We must remind you that today's discussion may include certain forward-looking statements and must therefore be considered in conjunction with the risks that the company faces. I now request Mr. Harendra Singh to take us through the company's business outlook and performance, after which we will open the floor for Q and A. Thank you. And to you, sir.
Thanks, Saloni. Good evening, everyone, and welcome to HG Infra Engineering Limited's earnings call covering our Q1 FY26 results. On this call, we'll give you an overview of how we performed financially and operationally, talk through our strategy roadmap, and lay out our growth ambitions. We'll also spotlight the key initiatives taken during the year and share our vision for sustainable long-term expansion in FY26 and beyond. HG Infra Engineering Limited brings more than 22 years of proven expertise in constructing roads and highways, and it has built a strong reputation for quality and on-time execution in the road sector. On that foundation, we have now diversified into critical infrastructure domains including railways, Metro, renewable energy, and transmission projects. We begin FY26 with steady momentum, further strengthening our position as one of India's fastest growing infrastructure companies. As part of a strategic approach, we aim to draw roughly 30 to 40% of our order book from known road sectors over the next 23 years. Along these lines, during this quarter we successfully secured our first transmission project, valued at approximately 350 crore, in Orissa, and received 1/3 of best project from GUNL for 300 megawatt.
Adding this brings Best Project's total contracted capacity to 735 megawatts, which works out to 1,470 megawatt hours. It shows how we back the government's vision of a green and sustainable future, even as the country's per capita energy demand keeps growing. With these accomplishments, we are now positioned as the country's third largest Best player. Turning to updates in the infrastructure sector: on roads, the government has set a construction goal of 10,000 km of highways for FY26. NHI intends to award 124 projects covering 6,376 km at an estimated cost of 345 lakh crores, with HAM staying dominant through 84 projects spanning 4,714 km, and given this outlook we expect meaningful opportunities to win new projects over the coming months. For the year, the company plans to bid on 1 lakh crore worth of projects in the HAM and EPC segments, targeting at least 6,000 crores in project awards in FY26. Highlighting its strategic focus on securing large-scale, high-value contracts in roads, rail, and metro, government visions are anchoring major modernization and capacity expansion, and by 2030 Indian Railways will complete 100% electrification and broad gauge network expansion, cutting carbon emissions and improving efficiencies.
We're seeing thousands of kilometers of new rail lines under construction, and at the same time track doubling plus gauge conversion work is quickly boosting capacity and connectivity. Through this nationwide station redevelopment program, over 1200 stations are going to be transformed with world class facilities to improve the passenger experience — and this year the company plans to take part in bids worth roughly 5,50,000 crore. In these sectors the company is actively chasing railway and Metro opportunities, with the aim of securing projects worth approximately 15 lakh crore during the current financial year. On solar and bass, if you look at the country's total installed capacity, it has reached up to 220EAWR as of 31st of March 25th, and on top of those installed capacities, India has 169.4 gigawatt of renewable energy projects under implementation. As India moves toward the clean energy transition, the battery energy storage systems market is projected to grow from $7.8 billion in 24 to $32 billion by 2030, with 66 GWh of storage capacity planned by 2032. On the solar side, India has crossed 100 GWh of installed capacity, with over 2 added in 24 alone. So these strong policy backed tailwinds create a massive opportunity for infrastructure players like us to unlock value across both EPC and asset platforms.
For FY25 26, the company is aiming at a 5% share of India's total available battery market. The estimated order inflow for BEST comes to roughly 2000 crores, and that figure includes one secure project for which he already has backing of about 800 crore rupees, plus transmission and distribution, where the government envisions a robust, modern and green power grid to meet rising energy needs, with major investment in high capacity lines and advanced substation and HVDC system over the next decade, under the one nation, one grid, one frequency policy that has unified all regional grids, enabling one 12,250 megawatts of inter regional transfer for stable, reliable nationwide power. At HG, we aim to secure transmission and distribution projects worth at least 1,000 crore for the year, and one we have already backed is 350 crore. Given our strength, agility and steady growth, we are poised to capture emerging opportunities in renewables, power transmission and the road sector, as well as metro and urban infrastructure. With proven execution, technical expertise and industry expertise, we are ready to deliver large scale infrastructure projects that power India's long term development. Let me begin with a glimpse of our operational highlights: as of quarter 1 FY26, the company's order stood at 14,600 556 crores, comprising 9,623 crore from Roads and Highways, 2,912 crore from Railways and Metro, 1,620 from Beds, and 500 crore from Solar.
In the road sector, 30% of roads fall under the HAM model, while 36% are EPC projects. Railways make up 20% of the total order, and Solar and Belts contribute 11% and 3% respectively. This is an update on the EPC project: Ganga Expressway has reached approximately 97.4% completion and is on track for 100% completion by quarter 2 FY25. The Delhi UAR project has been completed successfully and handed over to the authorities, and we anticipate receiving the completion certificate shortly. The janshed put that elevated project is running smoothly with progress at 15.2%. The neem manga Tumkur project is gaining execution momentum and has reached 42.5% completion. Regarding the HAM projects, the Kernal Ring Road project has reached 77.1% completion, marking steady progress, and is likely to be completed in Quarter 4 FY25. As shared in our previous quarter, the provisional completion certificates for the projects of Raipur Veshakha Patnam corridor — that is OD 5 and 6 — have already been received, and both projects remain close to completion. Now the AP1 project of Raipur Visakha Patnam is also progressing towards completion with PCC recommended, and all these three projects continue to be on track for 100% completion, that is COD in quarter three FY26. Solid progress continued on if Khamam Devaratli, the project of KD1 and 2; the PCC has already been received. These projects are at 88.4% and 85.5% respectively, and both packages are expected to be completed 100% by quarter 2 and quarter 3 respectively.
The Chennai Durubati ham project has now reached 21.4%. For the Varanasi Ranchik packages — that is, package 10 and 13 on this corridor — the appointed dates are expected in quarter 3 of FY 2526, where substantial progress has been made on forest clearance. On Kosi Parigomba Package 6 Ayodhya, the concession agreement was signed on 21st of March June of 25, execution stands at 2.2%, and the appointed date is expected very soon. In the Naro Zurkesh project, financial closure has been achieved and the appointed date should come within the month only. As for the railway project, the DMRT project is progressing at around 82% in line with the scheduled timeline, and within the next three months it will be 100% complete. The Bilascore Arden L project is 69% complete; the Kanpur Railway Station project is at 26.42% completion, and execution is now in full swing following the initial design and land; the Ecuador railway project is at 13%. The Gayana Sonagar project and the Karanjigaon project stand at about 12.7% and 9.3% completion respectively. The appointed date for the New Delhi Railway Station has been declared as 6 August 25th. Execution will begin by the end of quarter two, FY26. And on the solar project that we spoke about during the last financial year, we are now at roughly 8070 plants completed.
With HG Infra, across 183 plants in total, that gives us 700 megawatts of BCA capacity, and of those, the company is directly accountable for 167 plants, carrying an estimated EPC value of 2,243 crores. On the financial structuring side, debt funding for this project is moving along nicely — roughly 83% of the funding needed had already been sanctioned as of June 25. We expect the remaining approvals, and the disbursements that follow, to be wrapped up in quarter two and quarter three. Turning to equity financing, the solar project calls for total equity investment of 721 crore, and by 30 June 2025 the company had put in approximately 610 crore across these projects, with the rest slated for deployment from quarter 3 through quarter 3 of FY26. On the Best project, as we mentioned last quarter, the company signed a binding agreement with GML and NVVN for 435 megawatts, which is 870 megawatt hours of project, with scheduled commissioning in November 26 and December 26 respectively. In May 25 we added 300 megawatts, or 600 megawatt hours of project, from GUNL, bringing cumulative contracted capacity to 735 megawatts, or 1,470 megawatt hours.
Once all these desk projects are finished and commissioned, the company expects annual revenue of 225 crores. From that point, the equity requirement across all three projects comes to roughly 500 crore, of which about 1 crore has already been put in, and the remaining 119 crore is expected to be contributed within this financial year, with the rest in financial year 27 and 28 respectively. Procurement progress for the Best project has kicked off, and negotiations on the key component are at an advanced stage. After our team's visit to China, we shortlisted a tier one Chinese supplier for the import based system and power conversion systems, and we will likely finalize the order for power transmission switching at etc. by 30 September 25th. This is a recent update on monetization of five new HAM assets, i.e. tranche two of HAM. Over the past few months, our leadership team held intensive discussions with several prospective bidders and investors to monetize our second lot of five HAM projects. Those projects are Raipur, Vishakhapatnam corridor od5, od6, ap1 and Khammam developer Lee package 1 and 2. Our goal was to secure a partner able to offer both financial strength and the sector expertise to maximize value for our stakeholders.
I'm glad to share that this week we signed a binding offer document with the new Infra Income Opportunities Fund. Through this agreement, our holding company SGS will sell 100% of its equity stake in the five wholly owned subsidiaries that manage these HAM assets. This milestone represents the culmination of a well-tested negotiation process and shows market confidence in the quality and profitability of these infrastructure projects. The enterprise value of the entire transaction stands at 3585 OT4 crore, and the total equity invested in these assets and the total debt obligation across all five assets are 767 crore and 2200 crore, respectively. Soon we will begin the process of meeting the conditions precedent under the binding offer, which include client approval, lender's consent, and other representations and warranties. We expect to complete these formalities and close the transaction within this financial year. This transaction will bring significant strategic benefits to the group by strengthening the balance sheet and reducing leverage, thereby enhancing our financial flexibility. The realized funds can be redeployed into our new HAM road expansion or other high-return infrastructure opportunities.
We think this transaction delivered a strong valuation and puts the company in position for faster growth and value creation over the coming years. On the equity requirement for the HAMP projects: across the remaining HAMP projects, the total equity needed for 11 HAMP projects that are balance is 1,066,604 crore rupees, and as of June 25, 997 crore had been infused, with the remaining 298 crore scheduled to be done in nine months of FY26, followed by 183 crore in FY27 and 187 crore in FY28. Let me now walk through the other significant updates from Quarter 1 FY26. The company has won its first transition project from PFC Consulting Limited under the boot model, with a project cost of roughly 350 crore, for establishing the Interstate Transmission system in the Eastern Region Generation Scheme 1 in Orissa. The project duration is 35 years from the date of commissioning. In addition, the Company has received a project for military engineering services valued at 117.8 crore for creation of integrated material handling facilities at Naval Dockyard in Mumbai. Turning to the Financial Highlights of Q1FY26, revenue for Quarter 1 FY26 reached 1,709 crore, with an EBITDA of 236 crore and an EBITDA margin of 13.79%.
For the first quarter of FY26, PAT was 125 crore, giving a PAT margin of 7.34%, versus Rupees 140 crore and a margin of 9.27% in Q1FY25. On a standalone basis, gross debt is at 1049 crore. That figure includes 664 crore of working capital debt plus other term loads and maturities. Turning to the consolidated financials, revenue for quarter one FY26 came to 1482 crore, with EBITDA of 268 crore and an EBITDA margin of 17.52%. PAT for quarter one 26 was 99 crore, a PAT margin of 6.7%, compared with 163 crore at a margin of 10.64% in quarter one FY25, as we also informed you in the last two quarters. The decline in consolidated revenue and PAT stems from eliminating intergroup transactions with solar SPVs for solar projects, which are recorded as capital work in progress in the consolidated accounts. Whereas standard results reflect EPC revenue and taxes, the tax cost stays in the consolidation results until those SPVs begin generating operational revenue, and after that margins will improve. Let's explore what's next as we turn to our future strategy plans, since we are confident of aiming for an ordering flow of around 11,000 crore in FY26, with a clear data backed strategy to secure 75% from roads and railways, where our execution capacity outpaces competitors, and 25% for rapidly expanding verticals.
Our long-standing leadership in roads and highways keeps fueling our core growth, but we aren't sitting back. Seeing tougher competition and pressure on margins, we're acting proactively to reshape the portfolio so we create value over the long term. We're moving aggressively into high-growth, decent-margin areas such as Basin Transmission Distribution, building on our deep engineering routes and a proven record of execution. This isn't merely diversification — it's targeted expansion into future profit pools. Our unwavering emphasis on strategic bidding, cost control, and technology-driven project management is meant to protect and grow margins, keep debt to a minimum, and maximize returns for shareholders. Put simply, we're positioned for faster growth and stronger returns. A diversified pipeline, financial discipline, and bold sector bets are the key levers as we redefine ourselves as the future-ready multi-sector infrastructure leader delivering outside value to our investors year after year. I'd now like to hand the call over to the Goindia team for further deliberation and future for the further question answers.
Thanks so much. We're moving into the Q&A portion now. If you'd like to pose a question, just hit Star and one on your Touchstone phone. To drop out of the queue, press star and 2. We ask that participants speak through their handsets when asking. So that management can take questions from everyone on the call, kindly keep it to two questions per participant. If you have a follow-up, please rejoin the queue. Ladies and gentlemen, we'll pause briefly while the queue is put together. Our first question comes from Shravan at Dollar Capital. Please go ahead.
Thanks, sir. Starting with the most recent 5M deal — so if I calculate it, or 3584 crore is the EV, and against the equity and debt figures you cited, 767 and 2200 crore, the sum comes to 2967. That means the equity value we're receiving works out to 617 crore as against 767 crore put in. In other words, that's a price to book of 0.8 times. Please correct me if I've got that wrong.
Yeah, we're basically at stage 3584 now, which is the right point. The debt stands at 2200 crores. On top of that, 767 crores of equity in total has been put in.
But sir, I still can't grasp the reason we're selling at 0.8 times price to book.
It isn't 1.8 times, I think — it's not 0.8 times. You see. The figure you're looking at is 3584 crore in enterprise value. Debt accounts for 2200 crore. So what we'll actually receive net comes to 1384 crore, set against an equity investment of 767 crore.
All right, all right, all right, all right. That's on me, that's on me. Understood. Second. And then this cash we will be getting by.
Apologies,
That. The amount of cash and the timing for when we get that cash.
We expect that for two of the projects, the COD and then the NOC with firm lenders and clients could be handled within the coming three months, by December, and then another three probably by March.
So if you could break that down by value, how much will we be receiving in FY26, and?
Every total amount. What we're expecting is that we'd get this within FY26. So only by December 2025 — say, for this particular quarter, quarter three of FY27, 26. Tentatively, two of the projects could be completed as a transfer, and the remaining 2, 3 will be finished by March 26th. So everything would be wrapped up within the year only.
All right. All right. And after that, then whatever that gap turns out to be, we'll report it as an exceptional gain in the standalone books.
Of course.
Regarding the equity transfer.
Yes, that's right. Correct.
Yeah. So turning now to operations. Sir, so this.
I'd ask that you please return to the queue for any follow-up questions.
Alright.
Thanks. Our next question comes from Vaibhav Shah at JM Financial. Please go ahead.
Yeah. Sir, when should we expect to get the appointed dates for the AMP projects, particularly the VRK ones?
So we have five projects where we anticipate the appointed date. One of them, which came in quite recently, is the New Delhi delivery session — that's on 6 August. Next week, we'll have the appointed date for the Ahmedabad HAM project, and after that, in September, we should be able to get the appointed date for both Jharkhand projects. That's 10 and 13 of the Varanasi Kolkata corridor, and the last remaining one is the Ayodhya project. We expect to receive the appointed date for that one sometime in November.
Sir, and what are the expectations regarding LOA for output central, for both packages?
So those projects where land acquisition is currently at around, say, 42%. The minimum needed for issuance of alloy is 70%. So it will probably take another—it will take another three to four months. So by December, we expect the LOA could be released.
So, out of those five hams — four hams from ad spending — what revenue are you factoring in? And also for the MSRDC project for FY26.
We aren't factoring in anything from the MSRDC project, because once the alloy is available, the appointed party will probably be announced. So we're not counting on it. We don't anticipate much from those projects. But beyond those, there are four hams where we're aiming for roughly 1200 crores in total order execution across these four hams during this year.
So where do receivables stand right now, and within that, how much is HAM and how much is solar?
Most of what we have in receivables comes from HAM and solar alone. For solar SPB, receivables sit at roughly 458 crore rupees, while HAM projects account for 395 crore rupees within that total figure. The overall amount comes to 1360 crore rupees.
So you're anticipating that solar receivables will drop significantly. So at what point do you expect the overall.
A few things have taken place. We disbursed roughly 300 crore over the month — or should I say over the quarter. From that 300 crore, we were able to collect, let's say, the figure that stood at the same level and is unchanged. So the closing number as of March 25th stays where it was. That means only those 300-odd crores of disbursement could take place within this year. But at this point matters are moving very quickly, since 83% of the sanction is complete. And funds are being released to us by the banks via the SPV. HG INFI is receiving this as well. So come September and come December, let's say we would be at 100% — we would be recovering all of the receivables from the SPV to the banks.
Alright sir, one last thing — I missed the beginning, the opening commentary. What's our guidance for revenue and EBITDA margin for the full year? And what caused the margin hit in 1Q — we saw 1011 crore of one-offs booked as impairment losses, and in Q4 it was 5 crores as well. So what exactly are these entries?
So I think that's the reason behind the 2.2.5% immediate EBITDA correction we've seen. There's one item we had been expecting — the change in law on the Ganga Expressway. There's a change in law related to a royalty revision, right? So in this Adani project, we're eligible to receive any variation, like change in loans. The variation comes to us from the client. Whatever the client approves. So as of the recent trend, we're revealing the facts that they are likely — that the change in law approval is not likely to be there within this particular year. So it will take time. It's going to take time. So we have corrected our number by around 40 crore rupees. So because of that number, there is a deep correction in the EBITDA margin. Otherwise, in none of the other projects has the margin correction been done.
So the full impact has been removed at this point, or at least some of it we’re able to explain.
I'll ask.
That's 43 crore rupees, and 11 crore of it is an exceptional item, if you look at it. So that's there. A provision has been made, and roughly 43 crore related to Ganga Expressway is what we've adjusted in our margin.
Alright, thanks. I’ll rejoin you on this.
Thanks. We'll take our next question from Sarvesh Gupta at Maximal Capital. Please go ahead.
Good afternoon, sir, and congratulations on the transaction. So.
Pardon me for cutting in. The volume on your end is quite faint.
Has it improved at this point?
Yes, sir. Thanks.
Yeah. So sir, congratulations on the deal. Just to pick up where the last question left off. You know, earlier on we were reliably able to hit an EBITDA margin of around 16%. I think in the last quarter we came in at about 15%. And now, this quarter, we've delivered something like under 14. So. So you said. So what you're saying is that 14 crores is an exceptional item for this quarter.
No, no, no — that’s where I’m setting the record straight. In the prior year, during the last quarter, a provision of 5 crore was made — aside from what the auditors had already carried out — for long-overdue receivables taken as a whole. As of today, total provisioning against the debtors, meaning this current asset of receivables, stands at 74 crore rupees. Okay. That’s one development; the other item is the 43 crore rupees. This is a change-in-law matter that we don’t anticipate recovering very soon. Within the fear, as far as the Adani project goes, where there’s a back-to-back arrangement with Upida, so there we aren’t looking at it right away. So we’ve corrected that figure — the margin — by 43 rupees.
Okay, but have we evaluated that? Every one of the projects.
So, what accounts for that gap? Apart from that, every other project is tracking in line with the margins we anticipated, and.
And have we finished everything we needed to do on all the projects, or are there additional future provisions we still have to take starting in Q2? Should we be expecting a normalized margin of 15, 16%?
It will probably just be normalized margin. So we aren’t seeing — we’ve never factored in things like that. When the current asset or unbilled revenue involves a contract or different lanes, we normally have certainty around those figures. Only then would we keep it. Otherwise, we did what we did last quarter. So the provision is being made based on their contractual auditor’s obligations.
All right, all right. Now, regarding the road order, what should we expect at this point? Because even during this quarter—you know, over the last 2, 3 quarters and the last 6 quarters—the industry hasn't received orders, but we've remained hopeful since NHAI had a pipeline. So, you know, what's the expectation now, and has tangible work actually been done on their side? And as far as our pipeline goes, where do we stand, and what percentage are we looking to sort of win in the near future, etc.?
Lately, sentiment has improved quite a bit. As of the press release, they've already announced the project pipeline—those to be awarded, say, within this year alone. It's a lengthy pipeline: over 5 lakh crores of projects, including BOT, HAM and EPC. Beyond that, the long-awaited correction has come, and the pre-qualification criteria have been released—both in EPC and HAM. That gives us relief in the sense that the pipeline exists, but there are only two riders. One is DPR quality, where DPR checks take so much time, and land accretion, which has always been the truly critical area—a gray area, rather—where progress and any claims arise. So in that sense, they're just guaranteeing that 80% of the land, per the contract, should be in place prior to alloy issuance. These two factors are taking a bit of time, but we're very hopeful, and I think the ministry is very optimistic about awarding at least 3.5 lakh crores of orders within this year alone.
So we expect that traction to be there from November, December onward, and not many projects are likely to be awarded.
What is our revenue guidance for the full year this year? Sir.
It’s unchanged. That’s 7,000 crores. In quarter one we recorded roughly 13.5% year on year, and it should stay around that range.
Alright, sir. Understood. Thank you, and best of luck to you.
Much appreciated. We now have a question coming from Vinit with Investech. Your line is open. Hello, Mr.
Hello there. Yes. Can you hear me clearly?
Yes, sir.
Hello. Hello. Good afternoon, sir. I just wanted to double-check the revenue growth guidance figure. Given that many of our projects are presently at the L1 stage — the Maharashtra orders, 3, 4 HAM projects where appointed dates are still pending — and if you take out a lot of these projects, our executable order book right now is under 10,000 crores. With that in mind, how confident are you that we can reach 7000 crores? And what exactly should drive such a strong execution or conversion into revenues?
So, take a look at the projects where we're really far along in completion — things like Ganga, Odisha, all the OD5 6, AP1, KD1 2, and even Kernal. Whatever balance remains on those will get finished. That's one thing. And then again, solar, plus a meaningful chunk of best execution, should contribute within this year itself. Now, on the other railway projects, progress wasn't great early on because of design and land problems. That has now picked up, and in quarter 2, 3, 4 of this year we're looking at roughly thousand crores of execution in railway alone. As for the new projects where the appointed date is going to be — they've been declared — including New Delhi radio station, that's around 15 crore crores of execution likely in quarter two, three and four. So putting it together, we'd be around 7,000 crore even without counting anything coming from the Nagpur Chandrapur projects.
Got it? Yes, sir. And sir, even with the margin guidance you've given, our margins this quarter came in a bit lower. How confident are you about achieving a 15 and a half, 16% EBITDA margin for the full year? I ask because the required run rate to reach that is now somewhat higher — we'd need to consistently deliver 16, 16 and a half percent EBITDA margins across the next three quarters just to get anywhere near the EBITDA margins we achieved last year.
In essence, this is just about monitoring the margins. If something isn’t ensuring the same for us—well, it’s simply a question of timing: during either Q4 or Q1 of this year, we saw the margin dip; apart from that, every project we handle carries decent margins, and those are the kinds of projects we take on. And with margins likely falling in the 15% to 16% range, we’re quite hopeful that by year end we will keep up that same pace.
All right, so over the next 3 quarters, we should return to margin levels of 15, 16%.
Yeah.
Alright. Alright. Thanks a lot. Thanks.
Thanks. We'll take the next question from Vishal at Antec stock broking. Go right ahead.
Yes sir. Thank you. Yes sir. Appreciate the chance to speak. In your opening remarks, you said 83% of the debt for the solar is sanctioned. So have we drawn down anything from that side?
No, no. Look, there’s a gap between sanction and disbursement. We’ve drawn down only about 60%. Even though our progress stands at roughly 58% — well, about 80, 78% actually — so there’s a shortfall. A gap of roughly 30% separates what we’ve progressed from what we have. The loan has been disbursed. Disbursement of the loan has happened. So that’s it.
Yes. My apologies, sir — apologies.
So the sanction is 83%. The remaining 17% of the sanction is still awaited. Wherever the work is progressing, under whatever sanction has been granted, there’s only partial disbursement, or just a few of the plants where disbursement hasn’t happened yet. So in July and August, September through November, we—whatever and whenever—we’re going to finish the whole thing by December. So we’re hopeful that as we. So 45% of the balance disbursement would be done—43, 4%.
Okay, so you have to look at what the total debt is that we've taken on for this solar as of right now.
So it comes to roughly 1100-something crore rupees. 1100 in total. I can't recall the exact figure at the moment. It's 11 8.
All right, all right. That had to do with working capital — just wanted to check, you know. OK. Second thing, sir: on the battery energy storage, you mentioned that the equity being put in is 500 crore. And if financial closure is done at, say, 80, 20, then the project cost works out to roughly 2,500-odd crore. That's one. And the second, I mean, when we're putting in cost, it's not.
The cost of these projects exceeds roughly 1,800 crores. All three. All three of the best projects. At present, this project stands at about 1,800 crores plus GST. And the total debt. The equity committed comes to 500 crore. That represents 25% of the overall project cost. And our remaining amount is debt, out of the total debt. After we commission this project, we should be able to receive roughly 300 crores in grant funding from the government across all three of these projects.
All right, so 1800 plus GST, and I'm 300 crore grand — that gives us the total project cost.
When you take 1800 plus GST and subtract 500, the equity comes to 15 records of bed. And at under 300 rupees, that would leave more than 1200 crores of debt outstanding after the grant is settled.
All right, understood. I’m in. That one’s on me. Yes. 1800. Okay. So, then, I think.
My apologies for cutting in, Mr. Vishal. Please rejoin us for the Q4 follow-up questions. Thank you. Our next question comes from Jam Jain of ICICI Securities. The line is yours.
Thanks very much for the chance to speak. Sir, I was hoping to get a few data points regarding working capital. Could you give us the figures for inventory, trade receivable, contact assets, trade payable, and contract liability?
So inventory comes to the same figure — 519 crores. That covers inventory and working capital. Let's say you're asking about tickets: 60 crore rupees. And current assets stand at 1310 crore rupees.
1400. Oh, my apologies — I didn't catch your contact asset number. Alright then, trade tables and contract liability.
My apologies.
Trade payables, along with contract liability.
The contract liability is trade payable. So trade payable. Just a minute. Trade payables is around 1324 crore rupees. And
Alright.
Liabilities come in at roughly 1200 and something. My belief is that it's 1200.
Alright.
However, the figure is approximately 1200.
1,200 crores. All right.
Since Datab already has trade payables on record, right? Yeah, 130024 crore rupees. That's right.
All right, that clears it up for me. Thanks a lot.
Thanks. We’ll take the next question from Shravan on the Dollar capital line. Go ahead, please.
Hello sir, just to finish this up — what's the standalone cash and bank balance? Sir,
162
162? Yes, sir. 162 cr.
That's right. That's right.
And what's the amount for retention money? And what about unbilled revenue?
With that 1310 in mind — 1310.
Alright. 11310.
We have a debtor of 1360 crore rupees. There's also roughly 170 crore rupees held as retention and deposit.
Okay. And what's the amount of the mobilization advance? Sir?
382.
Okay. And sir, regarding this 500 crore BE equity. You mentioned 1 crore. We've put in another 119 crore during this year. And uh, next year will be the remaining. The balance entirely in FY27.
A portion of that would be completed next year. Next year, 100187 crore rupees. And the remainder would likely be finished in the 28th, since the first project is scheduled for completion in FY27.
All right, then. So for this year it's 120 crore, the following year 187 crore, and the remainder will be in
That is accurate.
Okay. Alright. And sir, could you say again the ham equity that will go in during this year and the next one for 28? I caught the number 187, but what's the balance across 26 and 27?
The projected figure is. The balance stands at 997, which, as they put it, has already been completed. So, as you can see, the projection for the year comes to 427.
Alright.
That figure represents the overall total, inclusive. All right. All right, my apologies. So the overall figure encompasses solar as well as BEST. If you'd like it broken out that way. On equity — the balance for the year, which includes BEST — the amount stands at 427 crore rupees. Is that right?
No, sir, no.
So where it's just roads, that figure comes to 298.
The 298 crore figure refers to the entire FR 26 year, or the remaining 9 months.
Twenty-six: nine months. After that, 183. Then 185.
83 and 185. All right, so that's the total. Got it. And on transmission, what amount of equity is required? And how much will we be investing this year and next year?
This year it's 10 crore rupees. Next year, 25. And then another 22 crore rupees in FY28. So when you look at the overall figure, for this year it comes to 4:27. Then next year, 438. And the year after that, 388. The total commitment balance is 997.
All right, all right, understood, understood. Yes. And sir, only to—yeah, yeah, yeah. I’ll do it, I’ll do it — I’ll finish this, I’ll finish this. Sir, only to clarify the provision on this EBITDA margin: this quarter, you mentioned a provision of 74 crore. To date, how much of that had been done by effort? 25. And in Q1, how much have we done—and what you’re referring to, the 43 crore, is that still left to be done, or…? Yeah, it is. It’s part of the 74 crore for Ganga.
Out of the total 74 provisions, just 5 were made during this quarter. The earlier provision would stay at 5 rupees. However, for this year, a quarter of 43 crores is not the provision. It's the margin we've taken on the Ganga expressway project owing to one of the items. This is a change in law that we were likely expecting. It could take some time.
All right, all right, all right. So perhaps this will fall under other expenses, or somewhere like that. It's going to be included in that 43 crore on which we've taken a hit.
On the cost side—actually, no, hold on, that's not cost. What it really comes down to is that the margin decline is already reflected. It isn't a provision. The margin decline is already reflected.
Alright, alright, alright. Understood, understood, understood, understood. Yes. Thanks, sir.
Thanks. We'll take the next question from Mohit at ICICI Securities. The line is yours.
Good afternoon, sir. Thanks for the chance to ask. My question concerns the deal, sir. What tax implications will apply to the realized gains? And what would the tax implications be for the gains that arise from this deal?
The amount we'll put toward lowering debt comes to 2,200 rupees.
No, apologies regarding the tax—the tax consequences. The tax that gets paid on those realized gains. Right.
We haven't figured that out at this point.
Got it. And have you set aside any allowance for the python of the asset? And also, will we be handling the maintenance work once the asset has been transferred to the new owner?
No, no. This is a case of selling the asset outright. These are outright transactions.
Any rofer for the... for the pipeline of the future asset? No. Right.
No. I think the asset we’ll likely still have is Karnal inroad, and we’re probably looking to sell that one further. So it’s getting close to completion. So by June or September of the following-next period—say by FY26 and FY27—we expect to close the deal.
So will we be handling the maintenance work on this?
Apologies for cutting in, Mr. No—no, no.
We aren’t carrying out any maintenance work on these—on these projects. This is purely a sale of the project. The whole transaction amounts to selling it off.
Got it. Thanks. Best of luck. Thanks.
Thanks. Our next question comes from the line of Path at JM Financial. Please go ahead.
Hello, sir, and thanks for the chance to speak. I'd like to ask whether you could put a number on your benefit time, and also whether any bids have gone out for which the results haven't been announced yet.
Apologies,
Could you give us some sense of the size of our bid pipeline?
Could you say something about the bid pipeline?
And also, if we've placed bids on any projects for which the results haven't come out yet.
So across all 3 sectors, we've put in roughly 16,000 crores of projects where we're still waiting on bid results. Beyond that, the pipeline — as we already explained, since it's a pipeline, a massive highway pipeline — we expect to be building about 1 lakh crores of highway, roughly 50,000 crores of railway, and another basin solar projects going forward, and out of these bid submissions we're expecting we should get at least 10,000 crores.
Sir, could you put a number on that solar build pipeline of 1000?
On the solar side, the bid pipeline — so to speak — operates under a different setup. It's the strongest, and solar too, since roughly 20,000 crores of orders for the year haven't been awarded yet. And in transmission as well, there's a bid pipeline of around 50,000 crores plus available today.
All right, thank you, sir.
Thanks. Our following question comes from Vishal with Antique Stock Broking, so please proceed.
Yeah. Yes, sir. Thanks for following up. So, regarding this battery energy storage system, has the equipment been awarded?
We've completed the first round of negotiations. Our team is currently in China only. So they'll be returning very soon, and then probably all the remaining negotiation and due diligence — within a month at most, we should be able to close it.
All right, understood. And. However.
I'd ask that you keep yourself muted while management is talking, since there are.
Alright, alright, that's fair.
I'm hearing some voices on your end.
Sorry, sorry. Let me just ask a question. Yeah, I'll ask a question and then mute. So maybe a follow-up on that. I think if we award a project now, then probably, you know, the costing comes in the range of, you know, maybe 0.8 cr per megawatt hour, and the project cost that we have mentioned comes to almost, like, you know, 1.2, 1.3 megawatt per hour. So I mean, can the project cost actually go down? Because if you are awarding now and battery prices have corrected in the last six, eight months.
You're likely right on that. I'd say there's been some correction over just the past 6 to 8 months. And based on what we've estimated for the costs ahead and the discovery tied to the price we're currently negotiating at, there's a chance of upside — we'd see at least a 10% upside on the margin side.
Alright, that helps, sir — thank you. And I’ll rejoin the queue. Thanks.
Appreciate it. Our following question comes from Madhavendra Kumar, an individual investor, who is on the line. Kindly proceed.
Yeah, hello there. Hi.
Yes sir, we can hear you. Go ahead, please.
Sir, there's one thing I'd like to get clear on — how HM projects actually work. I mean, we've sold this project. So is this completed revenue now that we're selling it, or what? Could you walk me through how that works?
Sir, I’m not able to follow what you’re saying.
The project we're selling—how this selling works is that these product projects are finished and revenue has been good. And now we're selling to release capital.
These projects are roughly 85 to 90% finished. So once we've gotten the provision completion into these projects, we've begun to see these monetization proceeds start coming in. So by the six months — within those six months, the whole completion should be done, and we are finishing up. And by the time we finish, we'll be obtaining the NOC, and we're going to sell this.
Right. So the sale happens once everything is finished and all the revenue has been recorded. Got it.
<<inaudible>>.
Following up, do you expect execution and growth to get better starting with this quarter? The quarters ahead.
There was a dip in execution.
During the recent quarter — this Q1 — I believe we came up a bit short on the execution side. So starting with Q2, that's where execution comes in.
It's actually been pretty strong, coming in at just about 13% plus. Yet that's the sole issue here. It isn't a matter of execution risk at all. It's simply a dip in margin, which we've observed owing to the margin correction amounting to more than 40 crore rupees. As I've already explained.
The amount we bring in and the trajectory we're on both remain below where they should be.
I’d like to ask you to get back in the queue for any follow-up questions, please. Thank you. Our next question comes from Shan at dollar capital. Please go ahead.
Hello sir. When you add it all up, what does the cash come to? Sir.
I don't believe I have the console member available right now. I'll have my CSO follow up with you.
Right, understood. And then, sir, regarding the 7,100 crore of revenue we're looking at — from what I gathered, the remaining projects where we're at 70%-plus completion, that comes to roughly 1500 crore, or 50-odd. Those we will finish. As we already said, there are also four HAM projects at a thousand-odd crore — 1700 crore. We've come that close. If I add it all up, around 4300-odd crore sits there. So I'm just trying to get a sense of the leftover projects — obviously the Maharashtra one, where we're saying no revenue is being factored in. So the main revenue that's likely to come, then, would be Chennai Cherupati, and Kosi Parikrama perhaps, and perhaps Bilaspur and Jan Kipur railway. So if you could help us with the remaining railway projects, apart from Bilaspur and Jan Kapur, how much additional revenue are we likely to get in the balance?
We expect the whole completion to happen in DMRC Metro, and the Belas project would be 100 completed. Things will wrap up very quickly from now on, since the initial brown is a brownfield project. So at New Delhi railway station this would be. We're expecting roughly 200 of execution within the year. So that's about 1100 crores of railway execution we expect in nine months. And besides that, there's a solar 500 crore that we already total will be done, and around 300 will be coming from best. So putting this together, if you consider the new ham ward four four ham, where the appointed rate is being declared at around 1200 to 1300 crores. So this comes to, say, even more than 5,400 crore rupees, which is probably the number that's coming. This is balance which we done in.
All right, all right. And then for next year, as we guided earlier, we'll be posting revenue of more than 8,000 crore in FY27.
Yeah, that comes to roughly 8,000 crores. Correct.
All right. All right. Understood. Thank you, sir. And finally, sir, regarding capex — last time around we stated there wouldn't be much capex this year. Fine. Fine. In any case. Fine. And even for the following year, it would only be very minimal.
We’ve got really strong gross work, and the project is nearly finished. That means our whole fleet of construction equipment is now available to be deployed for projects worth roughly 8,000 non thousand crores.
All right? All right. All right. Understood, sir. Thanks very much. Best of luck.
Thanks, ladies and gentlemen. We'll treat that as the final question. At this point, I'll turn the conference over to management for their closing remarks.
Thanks for being with us today. It’s been a strong year, defined by solid financial results, a growing order book, and a dedicated team. We stay confident about our continued success and our ability to exist. If you have any further questions, please don’t hesitate to contact our advisor, Goindia Advisors. Thank you.
Thanks, everyone. That wraps up this conference on behalf of goIndia Advisors and HG Infra Limited. We appreciate your participation, and at this point you're welcome to disconnect your lines.
Read the full transcript via the API
You're viewing the first half of this call. Get the complete H.G. Infra Engineering Limited transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.
Get an API key View API docs →For developers and AI pipelines
Programmatic access to H.G. Infra Engineering Limited earnings transcripts and 132,000+ others is available through the
EarningsAPI REST API and the hosted MCP server.
Quarterly plans from $162 - full transcripts, speaker segments, full-text search,
and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.