Good day, everyone, and welcome to HG Infra Engineering Limited's Q2FY26 earnings conference call. Please be aware that every participant line is currently in listen-only mode, and once the presentation wraps up, you'll have a chance to pose questions. If you require help at any point during this call, just press star followed by zero on your touch-tone phone to signal the operator. Kindly be advised that this call is being recorded. I'll now turn things over to Ms. Saloni from Go India Advisors. Thank you, and the floor is yours, ma'am. Good afternoon, everyone, and welcome to HG Infra Engineering Limited's earnings call, where we'll discuss the operational and financial results for quarter two and the first half of FY26, hosted by Go India Advisors. Joining us on the line are Mr. Harendra Singh, Chairman and Managing Director, and Mr. Rajeev Mishra, Chief Financial Officer of HG Infra. We should remind you that today's discussion may contain certain forward-looking statements, so those must be viewed alongside the risks the company faces. We now request Mr. Harendra Singh Sir to walk us through the company's business outlook and performance, after which we'll open the floor for Q&A.

Operator operator
#2

Thanks, and the floor is yours.

Harendra Singh executive
#3

Thank you, Saloni. Good afternoon, everyone. I hope this festive season has brought life, prosperity, and joy to each of you and your families. May the coming year be filled with renewed energy, growth, and continued success for all. As we look ahead at HG Infra, our unwavering focus remains on building stronger connections between cities and driving our journey towards greater achievements. As we embark on this new summer, we reaffirm our commitment to elevating India's transportation infrastructure and advancing our initiatives in green energy, ensuring sustainable growth and a brighter future for all stakeholders. At HG Infra Engineering Limited, our journey spans more than 22 years dedicated to strengthening the backbone of India's infrastructure. In line with the nation's evolving needs, we are scaling for success by accelerating innovation and building smarter, faster, and safer infrastructure solutions. Driven by our belief that infrastructure should reflect the dynamism and diversity of India, we are strategically entering new sectors such as solar energy, railways, and battery storage. This commitment enables us to diversify our order book and secure high-potential projects in these emerging areas. Our proven execution capabilities, technical expertise, and decades of industry experience position us well for the next stage of growth, allowing us to create a sustainable long-term value for all stakeholders and play a pivotal role in India's ongoing infrastructure transformation.

Harendra Singh executive
#4

I feel a great deal of pride in what HG Infra has accomplished and in the potential still ahead of us. More than 20 years ago, this started out as an EPC business focused on roads, and today it has become a diversified infrastructure conglomerate. Road construction is still our primary strength — you can see that in the 17-plus highway projects spanning 10 states, with the highway segment accounting for 66% of our total order book. We have deliberately moved into promising verticals like railways, metros, solar, and battery storage, and most recently into transportation infrastructure. Our diversified portfolio now covers over 29 active projects across 13 Indian states, among them seven rail metro projects, and as of September 25 our order book is at INR 13,933 crores. Now for a few updates on the infrastructure sector. On roads and railways — the transportation sector under Vision 2047 for a Viksit Bharat — the Government of India is stressing a modern, sustainable, and efficient transportation network that serves the needs of a growing urban population. The emphasis is on decongesting roads, meaning clearing congestion through expressway expansion, smart traffic management, and building integrated urban infrastructure. Better road connectivity linking cities with rural roads is intended to spur economic growth and cut travel time.

Harendra Singh executive
#5

More than 26,000 km of highway projects have been awarded recently under Bharatmala Pariyojana, and by 2036 to 2037 there are plans to develop 50,000 km of expressway so that intercity mobility becomes seamless. At the same time, the railway sector is going through a major transformation, with greater electrification, advanced signaling systems, and safety upgrades that enhance speed and reliability. Already, more than 45,000 kilometers of rail routes have been electrified, and the government is targeting 100% network electrification by 2030. Major expansion plans are in the pipeline to add more than 40,000 kilometers of rail tracks within the next few years. Expanding the metro network in major cities is meant to promote public transport, reduce pollution, and ease pressure on road traffic. Taken together, these initiatives form the backbone of a sustainable, technology-driven transport ecosystem that supports India's goal of becoming a developed nation by 2047. With healthy project pipelines into road infrastructure and rail, we remain optimistic about securing a share of upcoming opportunities, which should support our growth prospects in the medium term. As for renewables, which are solar-based and green hydrogen, India's battery energy storage sector is entering a period of dramatic expansion, expected to scale from just 0.2 gigawatts in 2024 to nearly 66 gigawatts by 2032, unlocking more than $5 trillion economy in the market.

Harendra Singh executive
#6

Ambitious renewable energy goals, falling battery prices, and strong policy backing are driving this expansion, which places BESS as an essential infrastructure layer for grid stability and round-the-clock clean energy supply. As battery storage moves from early pilots into large-scale tenders and active deployment, both industry leaders and new entrants are placing bold bets across the value chain. At this pivotal juncture, HG Infra remains committed to speeding up BESS innovation, adding to India's energy self-reliance, and shaping a future-ready grid that delivers resilient, sustainable power to all. As India makes the shift toward green hydrogen as well as ammonia, and with the mission of reaching a green hydrogen level of 5 MMTPA by 2030, HG Infra will keep playing a pivotal role in that effort and has already taken the first step by taking part in the recent tender of Numaligarh Refinery Limited. That tender covers the supply of 10,000 tons of green hydrogen. A large component of green hydrogen's operational cost consists of RE power, which will have to come from a combination of solar, battery, and hybrid off-grid, and HG Infra has already secured this and is in the process of successfully executing it. The shift to green hydrogen carries a widespread strategic alliance with HG Infra's foray into providing clean energy solutions.

Harendra Singh executive
#7

On transmission distribution—the government is putting in place a strong, modern, green grid to serve growing energy demand, with big spending on high-capacity lines, advanced substations, and HVDC systems over the coming decade. Reinforcing interregional links and adopting smart grid technology alongside integrated renewable energy boosts reliability and backs a low-carbon economy. Through India's One Nation, One Grid, One Frequency, every regional grid is now unified, which allows 112,250 megawatts of interregional transfer for stable, dependable power across the country. In FY26, FY18, HG Infra intends to win transmission and distribution projects valued at 10,000 crores. It has already landed one project worth roughly 50 crores. We stay active in transmission and keep taking part actively in tenders coming up. As HG, strength, agility, and steady growth drive us, and we are positioned to seize emerging opportunities in renewable power transmission and the road sector. Backed by proven execution, technical expertise, and industry experience, we are ready to deliver large-scale infrastructure projects that power India's entire long-term supply chain. Let me start with a quick look at our operational highlights. At the close of quarter two, FY26, the company's total order book was INR 13,933 crores, made up of INR 9,163 crores from roads and highways, INR 2,720 crores from rails and metro, INR 1,620 crores from BEST, INR 132 crores from solar, and INR 296 crores from transmission and distribution.

Harendra Singh executive
#8

Looking at the segment split, roads account for 66%, rails about 20%, and renewables roughly 14%. Now for the EPC project update: the Ganga Expressway project — a highly prestigious one for us — is valued at around INR 14,800 crores and stands almost finished at 99%, and we expect COD at some point within the next few months. The UER project has already been finished and handed over, and it's open to traffic. We anticipate receiving the completion certificate shortly. The Khammam-Devarapalle project is progressing smoothly, currently at 23%. Execution momentum is building on the Nelamangala-Tumkur project, which has now reached 48%. Turning to HAM projects, the Karnal Ring Road project is at 82% completion, reflecting steady progress, and it is likely to finish in quarter four of FY25. As we shared last quarter, provisional completion certificates for the Raipur-Visakhapatnam projects 45 and 46 have already been received, and both remain close to completion, while the AP1 project, also nearing completion, had its provisional completion certificate dated May 25 received very recently. All of these projects — 45, 46, and AP1 — remain on track for 100% completion, that is COD, in quarters three and four of this year.

Harendra Singh executive
#9

On the Khammam-Devarapalle Project, PD1 and 2, PCC has already been received, and those are at 95.3% and 91.8% completion. We expect both projects to be 100% complete by quarter three and quarter four of this year. The Chennai-Tirupati HAM project is currently tracking well at about 28%. For Varanasi-Kolkata Corridor Package 13, the Appointed Date — the provisional appointed date — has been received with effect from 30th September 2025, and package 10 is expected to come in this quarter only. Package 13's project progress stands at around 13%. On Kosi Parikrama Package 6 of Ayodhya, where the concession agreement was signed on 21st of June 2025, the appointed date is likely to be declared this month, and project execution has just begun. For the Uncertain project, financial closure was achieved and the appointed date declared on 19th of August 2025, and execution stands at 4.2%. Now turning to railway projects. The DMRC project is nearing 92% completion and, per the scheduled timelines, is likely to be finished within this quarter. The Bilaspur-Anuppur project is around 75% complete, and we are targeting completion in quarter four 26, and the Kanpur Railway Station project is around 33%, where progress is quite slow because concourse execution has not yet started.

Harendra Singh executive
#10

But we do expect to pick up now. The Dhule-Nardana project has reached 17.9% progress. The Gaya-Son Nagar and uncertain projects stand at 15.4% and 13% completion. Abnormal rains hit progress badly across these projects, though we expect it to pick up in the coming quarter. For the New Delhi Railway Station project, the appointed date has been declared as 6th of August 2025, execution has begun, and the project is in its initial phase with 3.7% completion done. On the solar projects, during the last financial year HG Infra diversified into the renewable energy sector by securing 183 solar power plants with a total capacity of 700 megawatt DC, out of which entailing a total EPC value of INR 2,243 crores, excluding GST. The land lease agreement and the power purchase agreement with this firm have been done successfully, and as of now overall project progress stands at approximately 94.1%. Plant installation activity is advancing largely as per the schedule, though very few sites experienced delay because of the prolonged and heavy monsoon conditions. Despite the local challenges, the company remains confident of commissioning all plants within the contract timeline in the next few months. This progress will also facilitate drawing down the remaining debt, thereby supporting overall liquidity.

Harendra Singh executive
#11

When it comes to finances, roughly 89% of the debt funding we need has been sanctioned, and about 74% of the disbursement has already taken place. The rest of the disbursement, along with the remaining balance sanctions, will come after these installed plants are commissioned. Because those disbursements are still pending, we've borrowed from banks to bridge the gap so the projects finish on schedule, and as a result our overall debt is running on the higher side at 1,300 crores. Also, of the total equity requirement of 721 crores for these projects, 705 crores had been infused as of September 25. In the BEST projects, the company has executed binding agreements with GUVNL and NVVN for a 435 megawatt project, equivalent to 870 megawatt-hours, with completion scheduled for November 26 and December 26, respectively. In May 25, we secured an additional 600 megawatt-hour of projects from GUVNL, and the agreements for these are scheduled to be signed on November 25. With that, cumulative contracted capacity now stands at 735 megawatts, or 1,470 megawatt-hours. The procurement process for the BEST projects has been initiated, and the company has placed orders for key components such as the power transformer, switchgear system, and GIS, while vendors for BEST container supply have been shortlisted, and final orders for those are likely to be placed by January 25 or January 26.

Harendra Singh executive
#12

For all three of these projects, the equity requirement is still INR 500 crores, and we anticipate infusing INR 120 crores in FY26, with the balance coming in 27 to 28. Once all these BEST projects are completed and commissioned, the company expects INR 225 crores in annual revenue from BEST. Turning to monetization of five HAM projects — over the past few months, our leadership team held intensive discussions with a number of prospective investors about monetizing our second lot of five HAM projects. Those projects include Raipur-Visakhapatnam Corridor Package AP1, AP5, and 6, Khammam-Devarapalle Package 1 and 2, and our goal was to secure a partner able to bring both financial strength and sector expertise so as to maximize value for our stakeholders. In August 25, we executed a binding offer document with NIIF Asset Management Fund. Under this agreement, our holding company will sell 100% of its equity stake in these five fully owned subsidiaries that manage these HAM assets. This achievement reflects the successful execution of strategic negotiation and underscores strong market trust in the value of potential returns of these infrastructure initiatives. Further to this, we have also executed the share purchase agreement for the Raipur-Visakhapatnam AP6 package project recently, and the remaining four SPAs are targeted for execution in this quarter only.

Harendra Singh executive
#13

The transaction's enterprise value comes to INR 3,584 crores. Across all five HAM assets, the total investment stands at 767 crores, with equity investment and total debt obligation at 2,200 crores respectively. We've already begun meeting the conditions precedent under the binding offer, covering client approval, vendor consent, and other representations and warranties. Our expectation is to wrap up these formalities and close the deal during the current financial year. Strategic benefits of real significance will flow to the group from this transaction — the balance sheet gets stronger and relative leverage comes down, which boosts our financial flexibility. Funds realized this way can go toward new HAM bids, road extension, and other infrastructure opportunities offering high returns. In our view, this deal secures a robust valuation and sets the company up for accelerated growth and value creation over the years ahead. On the equity requirement for balanced HAM projects, the total equity needed across 11 HAM projects is 1,709 crores. As of September 25, 1,165 crores had been infused. Of what remains, 195 crores is slated for infusion six months from now, that is FY26, then 153 crores in FY27 and 186 crores in FY28. Turning to the financial highlights for quarter two FY26, this is the first half of FY26.

Harendra Singh executive
#14

Turning to the standalone financials, revenue in quarter two of FY26 came in at 1,154 crores, while EBITDA was 147 crores, giving an EBITDA margin of 12.7%. For quarter two FY26, PAT was 67 crores, a PAT margin of 5.8%, versus Rs. 89 crores and an 8.3% PAT margin in quarter two FY25. First half FY26 revenue on a standalone basis came to INR 2,863 crores, with EBITDA at INR 382 crores, an EBITDA margin of 13.4%, and PAT for the first half of FY26 at INR 193 crores, a PAT margin of 6.7%, compared with INR 228 crores and a margin of 8.9% in the first half of FY25. Looking at things on a consol basis, gross debt is INR 1,634 crores, made up of INR 550 crores of working capital debt, INR 400 crores of NCD, and INR 684 crores across term debt, current maturities, and fund limit. As for the consolidated financials, revenue for quarter two FY26 was INR 905 crores, with EBITDA of INR 206 crores and an EBITDA margin of 22.8%. PAC in quarter two FY26 was 52 crores, a PAC margin of 5.7%, against 81 crores and a PAC margin of 8.9% in quarter two FY25.

Harendra Singh executive
#15

For the first half of FY26, revenue came in at 2,387 crores, with EBITDA at 466 crores and an EBITDA margin of 19.5%. PAC in the first half of FY26 was 151 crores, a PAC margin of 6.3%, versus 243 crores and a margin of 10% in the first half of FY25. As we mentioned last quarter, the decline in consolidated revenue and PAC stems largely from removing inter-group transactions with SPVs of solar projects, which show up as capital work in progress in the consolidated accounts. From the September 24 quarter through this quarter, roughly 2,111 crores of revenue and a profit of 380 crores have been eliminated in the consolidated financials. While the standard results reflected EPC revenue and taxation, the tax cost stays in the consolidated results until the SPVs begin generating operational revenue, and after that margins will improve. Now on to our future strategy plans and the future outlook: in the year ahead, our priorities at HG Infra will center on sustaining a steady growth trajectory anchored by strong financial fundamentals. On the operational side, we aim to tighten working capital cycles, ensure on-time project delivery, strategically allocate capital, and enhance monetization efforts. Bold targets have been set for FY26, where we plan to secure INR 10,000 to 11,000 crores of new ordering flows, and by FY27, we intend to expand our non-road infrastructure portfolio to around 35%.

Harendra Singh executive
#16

As we look forward, our emphasis is on growing into building, construction, and real estate, green hydrogen, and other emerging sectors. Our team is working actively to seek out opportunities and make a meaningful contribution in those sectors. Simultaneously, our strategy keeps diversifying into high-potential areas like water management, tunnels, transmission and distribution, and smart urban infrastructure. We stay committed to reinforcing our digital and automation capabilities, improving ESG performance at the strategic level, and delivering scalable, impactful projects across diversified geographies. Taken together, these growth levers will propel HG Infra's evolution into a broader multi-sector infrastructure platform, generating long-term value at its core. HS, would you like to open the floor for the Q&A? Thank you very much. We will now begin the question and answer session. Anyone wishing to ask a question may press star and one on their touch-tone telephone. If you wish to remove yourself from the question queue, you may press star and two. Participants are requested to use the handset when asking a question.

Operator operator
#17

Ladies and gentlemen, so that management can take questions from everyone on the conference, we ask that you keep your questions to two per participant. We'll pause for a moment while the question queue is put together. The first question comes from Vaibhav Shah at JM Financial. Please go ahead.

Vaibhav Shah analyst
#18

Could you tell me what our HAM and solar receivables are? In the previous call, we laid out the solar receivables in quite a lot of detail — so have those come in yet? What are the receivables for solar and BESS? And HAM. On a total debtor basis — and you mean debtor, correct? Yes. So the total SPV receivables sitting in debtor come to roughly INR 255 crores for solar and 567 for HAM. The contract asset is INR 235 crores for solar, and for HAM it's 529. Okay. Sir, we observed a sharp rise in debt levels during the second quarter. Is there any reason behind that?

Harendra Singh executive
#19

Basically, there are three main areas where we've put the debt to work — where debt has gone up. The first is advances to our vendors: roughly INR 150 crores went into that, since we were procuring some of the core materials needed for BESS and BESS. Mobilization advance is another one — INR 250 crores of mobilization advance sits there. That has come down quite a bit, because on the newer projects we haven't been able to get any mobilization advance to date. Payables have also come down, where retention has been paid, since a lot of other projects we finished recently had vendors' retention payments made. Okay. But the last thing I covered in this remark: about INR 490 crores of debt in total is still to come from the HAM banks' disbursement. So that again feeds into this particular rise in debt, which was also the case in quarter one. So once it arrives, the debt should come down? Yeah. We expect the debt in quarter three and quarter four — a significant decrease is likely there, and we'll be roughly back around normalcy, as we were in earlier quarters.

Harendra Singh executive
#20

And finally, regarding margins, we've noticed some softening over the past two to three quarters. So did any burn-offs occur during this quarter? Margins came in at 12.7%, and how do you expect that to trend going forward? Margins were merely on track. There are very few projects — Ganga in particular — where we've taken a hit owing to the Change in Law. There's a likelihood we will take this to arbitration; we're going to pursue that kind of opportunity where it would get paid. It's a table kind of thing, but the client outrightly is not agreeing to it. So there's one number we discounted immediately into our quarter one. What was that amount? In the first quarter, it was around INR 40 crore, and then in the second quarter, it is around INR 35 crore. So going forward, is there any other expectation, or is it now over? Or are there any further ones? All projects are running very smoothly and perfectly within the right margins as we are instructed. There's only one project where we've taken a discount because we don't want to keep those numbers where margins are likely definitely there as per the contract conditions, but it may take a few quarters to realize that.

Harendra Singh executive
#21

So with that provision now finished, or could it still extend further into Q3 as well? No, no.

Vaibhav Shah analyst
#22

So we've finished covering the first quarter and quarter two. All right. And finally, regarding other income, that figure stands at 17 crores for the second quarter. So what's behind it being that high?

Harendra Singh executive
#23

I haven't come across that, since the FDR is in place as well, and some maturity would have been there. Beyond that, I really don't know. We'll see, and I'll follow up with you.

Vaibhav Shah analyst
#24

Alright. Alright, thank you, sir. I’ll call you back as well.

Operator operator
#25

Thank you. We ask that each participant keep their questions to two. Our next question comes from Shravan Shah of B&K Securities. Please go ahead.

Shravan Shah analyst
#26

Hello, and thanks, sir, for giving me the chance. I have two questions. First, on the broader top-line guidance: considering the relatively muted growth in H1, reaching 7,000 crore requires roughly a 19% growth rate in the second half. So how are we viewing that now?

Harendra Singh executive
#27

For the first half of this year, growth has come in pretty much in line with what we planned. We're at roughly 2,800 crores, which is about 10%–11% growth. So as far as the remaining portion goes, once the rains have subsided and the COD for this Varanasi Kolkata package begins to come through — all of that should show up within a few days — and package 10 would only be taken up next month.

Shravan Shah analyst
#28

So, with that in mind, we're estimating that a significant number would fall in quarter three and quarter four.

Harendra Singh executive
#29

So we're definitely not very confident that we'll hit 7,000, but somewhere in the 6,500 to 7,000 range would be our figure. By the end of this year, we'll be able to comfortably reach that. Okay. And for next year as well, previously we were looking at 8,000. So if we can get a 10,000 to 11,000 crore order inflow, then is 8,000 crore doable in FY27? With the balance order of about 14,000 crore, if we do around 4,000 crore in the balance, even if it's around 4,000 crore in the remaining part of the year, then we'd be left with 9,000 crore in the year. And again, with the likely addition of the new order, where now the orders even from the government or from any private land. Those are orders where we don't expect much of a delay in the appointed date. So whenever the orders would be placed, likely within a few months, the appointed date would be in, I say, there because of the land availability and everything has been improving a lot. So with that, we're expecting that we'll be touching around 7,800 to 8,000 crore in the coming year at about 15% growth as we are estimating.

Shravan Shah analyst
#30

So starting in Q3 and going forward, we'd expect EBITDA margin in that 15%-16% range, and that's a level we should sustain over the next two to three years.

Harendra Singh executive
#31

The margin is roughly at that level, since it has been affected by several of the projects I've already talked about. So those margins took a hit right away, in this quarter alone.

Operator operator
#32

Thanks. Our next question comes from Sarvesh Gupta at Maximus Securities. Go ahead.

Sarvesh Gupta analyst
#33

Good afternoon, sir. I just need one clarification again regarding the margin side. I believe in the previous quarter you also hinted that the bulk of the one-time provision tied to Ganga Expressway had been booked in that quarter alone. Yet in this quarter as well, we've seen the ₹35 crore figure that you mentioned. I'm not certain that even if I include it, whether it reaches the 16-odd% level, which was our normal track record on the margin side. So could you kindly help us with that? In half of the 21 projects where we took a hit, it isn't because the client is reluctant to pass on this claim. There is a change in law, and there is one COS.

Harendra Singh executive
#34

There's an interchange that was built as a variation, and we haven't treated it as revenue since the client might need some time to approve it as a variation claim. In NHAI projects, or this type of project, there are two distinct things, because the client always treats anything he has stated as something that will qualify your claim. So in this instance, we're factoring in that we may or may not qualify right away. So it's a question of time. Certainly, all these figures were taken with a provision, or a margin has been discounted on that basis. Otherwise, it isn't that the margins aren't there. They were all present, and we were likely to see this figure also arriving in upcoming quarters, within, I think, three to four quarters, which can be improved even.

Sarvesh Gupta analyst
#35

But for the second half, sir, can we now expect to return to our usual 15%-16% margin, or will it stay at 12%-13%?

Harendra Singh executive
#36

Our margins are solid, so we expect to return to that normal level.

Sarvesh Gupta analyst
#37

Alright. Second, sir, regarding ordering flows — if I calculate your ordering flows for the first half, it comes to only around 1,500 crores, versus the 11,000 crores expected at the start of the year. So what gives us confidence that, over the remaining four and a half to five months, we will be able to reach 10,000 crore in ordering flows?

Harendra Singh executive
#38

We have two major expectations right now. One is definitely at NHAI. Not much has happened in the first half, and due to land issues, the pre-qualification criteria, and several other factors, everything is now in place—with many projects approved, the bidding pipeline looks very strong, and they should be awarding contracts in the coming months. That's one area we're focused on. The second is that we've already successfully completed one of Adani's projects—this is a Ganga project. There too, given our strong relationship with them, we anticipate some private orders as well. In rail, roads, and private orders, we believe that over the balance of the next three to four months, we will be able to secure approximately INR 10,000 crores of orders.

Sarvesh Gupta analyst
#39

All right. And then finally, regarding the MSRDC project, that INR 4,000 crore book isn't there for us to execute. So in that kind of situation, and with most of the ordering flow, let's say, coming through over the next one and a half quarters, I'm not sure how much you'll actually be able to execute. So are we being too optimistic about INR 7,800 crores of revenue run rate next year, given that very little order book will remain to be executed next year?

Harendra Singh executive
#40

So when you look at the total order book, if you simply set aside this MSRDC order, it would be about balanced — roughly INR 4,000 to INR 5,000 crores. So those are the orders, and nearly all of that work has to be completed in FY27, except, I think, no more than INR 4,500 crores that would fall beyond FY27. So there's one area where we believe — and that's the orders we're likely to win now. These are the projects we're expecting, where the tentative time, the time we actually take economically, is one to two years from the award date to the appointed date. So this won't be the case with future orders, because it's only a time when the orders — if you just look from the LOA to the appointed date — it would be around two to four months at most. So this gives us the opportunity, and we see it as confidence, that we would be able to secure the orders and also be able to deliver this much of an amount of orders.

Sarvesh Gupta analyst
#41

Alright. Thanks. And that covers everything.

Operator operator
#42

Thanks. Our next question comes from Vishal at Antique. Go ahead, please.

Vishal Periwal analyst
#43

Yes, sir. Thank you for the chance to follow up. Regarding that roughly 14,000 crore, aside from the master order, is there any other project where the appointed date is still pending?

Harendra Singh executive
#44

Right, sir. As things stand, the appointed date we've already secured is for the Ayodhya project, and that should come through in just a few days. Then there's the Jharkhand project — that's Varanasi, Kolkata, package number 10 — which will follow only in the next month. So the only appointed date still outstanding would be the one for this MSRDC project.

Vishal Periwal analyst
#45

So altogether you're referring to four projects in total, and that includes the one in Maharashtra, where the AD is still pending — is that right? Correct.

Harendra Singh executive
#46

Alright, thank you, sir.

Vishal Periwal analyst
#47

And then secondly — just one last item — regarding the financial close on that project where we hold asset ownership through an SPV structure, even for solar, is there any update you could give us, sir?

Harendra Singh executive
#48

We’ve already locked in the financial closure — roughly 89% of the total project has been sanctioned, and 74% of total disbursement has taken place. Even so, a large portion of the disbursement still remains to be done. That said, we’ve moved forward to about 94%. There’s one bank, SBI, that is essentially waiting, because over the next two months we need to finish nearly the whole project. Within that window, the remaining 11% would be sanctioned and disbursed, and whatever has already been sanctioned would be disbursed a few months from now. Beyond that, on financial closure, we are at BOT. One of the sanctions we have already received is from PNB Bank, and very recently, I believe a few of the other banks have also participated in the financial closure. For both BESS projects, we expect to submit the financial closure by November and December.

Vishal Periwal analyst
#49

All right, sir. I believe that covers everything on my end. Thanks.

Operator operator
#50

Thanks. Our next question comes from Parth with JM Financial. Go ahead.

Parth Shah unknown
#51

Hi there. Thanks for the chance to ask. When should we expect work on the BESS projects to begin? Yeah. Starting the BESS project is kind of a yes. No. When are we able to begin? On execution, we've already begun in the places where land is available, engineering is underway, and payments have already been made for advances on transformers, GIS, and other systems. So we've already started on both of these projects. Then can we expect any meaningful revenue to be booked from the BESS project in the latter half of the financial year? Yeah.

Harendra Singh executive
#52

Roughly INR 150 crore to INR 250 crore or so, I believe, would be carried out within the CM itself. I missed one thing you mentioned — the MSRDC revenue for FY27. Could you repeat that once, sir? Right now, for this order, we're still waiting on the land, which is not yet in — say around 70% as per the LOA terms. That's why the delay has occurred. But once the land is available, there isn't much difference between the appointed date and the LOA. In that case, we think that after this year wraps up, by the time the appointed date arrives, a significant amount of work would get done on MSRDC projects in the following years, FY27. So can we expect it in this financial year, or at the beginning of FY27? We're expecting it by the end of this year only. And can we expect revenue of around INR 500 crore from this project this year? Not within this year. We aren't expecting any revenue this year. We aren't recovering anything. And in FY27? In FY27, definitely more than 50% would be completed in FY27 out of that total of INR 2,000 crore.

Parth Shah unknown
#53

All right. Thanks. Thanks, sir. That's all I had to ask.

Operator operator
#54

Thanks. Before we move on to the next question, we'd like to remind everyone that you can press star and one to ask a question. Our next question comes from Uttam at Axis Securities. Please go ahead.

Uttam Kumar analyst
#55

Appreciate the chance to ask. Sir, my question is about the bidding pipeline as it stands now for HAM EPC and for Metro projects as well. On the previous call, you gave us some sense of securing projects in Metro too, and also from the battery storage services market. If you could shed light on how much we have bid in HAM EPC and for Metro Railway and Metro, and for other projects too. So as of today, what we have bid comes to roughly INR 12,000 crores in total bids already submitted, where we are still waiting on results. That is about INR 7,000 crores across HAM and EPC projects in various sectors, and around, let's say, BEST and this solar, about INR 5,000 crores. And when it comes to the bidding pipeline, if you look at INR 65,000 crores of orders, where land acquisition is almost done and things are at an advanced stage from NHAI, covering HAM and EPC, we are not counting any BOT project in this.

Harendra Singh executive
#56

The ministry is also looking to bid on projects worth about 70,000 crores during this year. So that adds up to roughly 135,000 crores that we're considering for the year, including the bid pipeline from NHAI and the ministry. Beyond that, we've already finished one of the large projects with Adani as a client, namely Ganga. So we expect they are also talking about a few of the projects they already have, to see about working with us as an EPC partner. Okay. And sir, would the margin stay the same? And what we're getting on the expected Ganga project — if we take on some projects with Adani going forward, or would it be lower than that? We expect that on similar terms, we'll be taking a call on similar terms. It will be the same margin as what we bid in Ganga. And the last one, what will the timeline be for the asset monetization that we've already done with you? So across all five projects, we've received the PCC and the NOC and the other obligations, which we've already started. So we believe that the COD — as soon as we receive the COD, and as soon as we get the NOC permission from the client, which will likely take no more than one to two months at most from now.

Harendra Singh executive
#57

So come January — going on into January or February — two of those projects will be underway. And by March, all three of the balance projects will be finished, within this year alone. And sir, on enterprise value, if I'm not mistaken, those transactions came to INR 3,584 crores. So the enterprise value stands at INR 3,584 crores. Of that, INR 2,500 crores goes to debt, and INR 1,384 crores is the total sum that SG would receive. Okay. That's all from my side, thanks everyone.

Uttam Kumar analyst
#58

And I want to wish each of you the very best. Thank you.

Operator operator
#59

Thanks. We’ll take our next question from Mohan Kumar at ICICI Securities. Mohan, go ahead.

Mohan Kumar analyst
#60

Yes. Good afternoon, sir, and thank you for the chance to speak. My first question, sir, is whether I could ask you to explain the change in law that affected how we booked margin this quarter. What exactly does it relate to? So the change in law is essentially the aggregate that gets taken or purchased from outside the state — that is, the interstate project cost. There's been a substantial fee hike on that in UP. So any aggregate you buy from outside the state of UP, that duty gets charged. With that, this qualifies as a change in law. And there's also a royalty change that likewise qualifies as a change in law. So across any of UPEIDA's projects, they have never paid this change in law. This is the first time. With NHAI, it's a normal trend. Okay? So that's why they're looking at this particular event, which is the first time, and they may or may not consider it. That's why we've taken that. Even though a legitimate claim exists, so we've already obtained the legal opinion. So if they deny that, then we'll take this to our petition.

Harendra Singh executive
#61

But our work is for Adani, correct? So the money has to reach Adani, and then Adani passes it along to us. Is that the right way to understand it?

Mohan Kumar analyst
#62

Yes, both of those things.

Harendra Singh executive
#63

The contract makes it clear that whatever we receive from the client, UPEIDA, as a complete agreement, that alone will be passed on to us. Understood.

Mohan Kumar analyst
#64

Got it. My second question concerns the NHAI pipeline. From what I recall, NHAI gave us quite strong visibility, stating they would bring an order inflow of roughly INR 3.6 trillion during the fiscal. Are you seeing indications of that materializing, or do you believe the figures will be far, far lower, and is there any outlook or color you can share on the pipeline as it stands right now? So NHAI and the ministry are definitely bullish on a strong pipeline, because for the last one and a half years very little has happened — almost two years, really.

Harendra Singh executive
#65

To reiterate, the bidding pipeline remains robust, and it's largely Greenfield-type projects. In HAM, EPC, and BOT, it's a combination of all three. Altogether, that comes to roughly no less than six lakh crores. But obviously, we can't expect all of it to be completed during this year. So we anticipate that, owing to land. There's a directive from the ministry as well as the finance that bidding should happen, and projects should be awarded only when 80% or 90% of the land is available as per the contract. Previously, the practice was that even with 30, 50% of the land available, projects were still put up for awarding. So now their measures are stricter. And the second thing is DPR quality. So they're looking at this again, okay, whatever DPR we prepare. So the DPR shouldn't contain too many variations that cause time loss as well as variations. So these are the two major factors impacting bidding. Apart from that, the pipeline is very strong. So we do expect, yes, it's definitely taking time. But many projects that they believe, and we also expect, would be bid within the financial year.

Harendra Singh executive
#66

And after that, I don't expect any hold-ups in the years ahead.

Mohan Kumar analyst
#67

Sir, thank you. And I wish you all the best. Thank you.

Operator operator
#68

Thanks. Before we move on to the next question, we'd like to remind everyone that to ask a question, you should press star and one. Our next question comes from Parth Parekh of JM Financial, on the line. Please go ahead.

Parth Parekh unknown
#69

Thanks again for the chance to address this. Sir, at what point should we anticipate better execution on the railway station development? You never actually said that execution has already begun. The improvement will most likely come in the urban area, definitely. But as for the land and utility shifting that was meant to happen, substantial progress has been achieved there. So we anticipate roughly INR 130 crores of execution during this year alone. A meaningful share should therefore be completed inside this financial year, now that we have launched the project. At present it is moving quite aggressively.

Harendra Singh executive
#70

And should we anticipate getting the monetization funds before this year wraps up? Yes, absolutely. Since we're making progress and the COD is anticipated, across all 5 projects, COD should come through within just the next 4 to 5 months. So this is the mandate we've set: both the COD and the NOC from the client—those 2 items are what's needed time-wise for the transition to take place.

Parth Parekh unknown
#71

All right, thanks — that covers everything I wanted to ask.

Operator operator
#72

Thanks. Our next question comes from Vineet at Investec. Go ahead.

Vineet Naran unknown
#73

Good afternoon, sir. Sir, there are various news articles suggesting that the Maharashtra MSRDC orders might be canceled and put up for rebidding — what are you hearing from government authorities about how they should proceed, given that land acquisition is still at around 30%-35% levels? So you're right. Land acquisition is the only issue here. So basically, there are two things. One is definitely that without the land, nothing can be done — unless that happens, the LOA or appointed date cannot be declared. So they are looking at this as almost one and a half years, roughly, say, only one and a half years has passed. But they are keeping it — definitely, once anything is to be done, it will take another six to eight months. So they are expecting this order to be given. And right now the land acquisition is being taken quite expeditiously. Earlier, there was almost dullness for around six months. So now it is being actively taken. And every month, we are seeing that 10%-12% land is being added into their kitty. So with that, I think it's only a reverse argument.

Harendra Singh executive
#74

Okay. But sir, do you expect these MSRDC orders to go for re-tendering in any case, or are you fairly confident? What have the discussions with the awarding agencies been on this? As of today, there's no news of that sort suggesting these will be canceled and re-tendered. It's simply a question of time where the land acquisition is not, say, in line with the contract. Understood. Understood. And sir, my second question was your comment on the foray into the building residential building segment and also green hydrogen. If you can shed some light on it, what type of orders are we looking for? How are we qualified? Will we initially go through the JV route? Which type of orders will we be targeting in those areas? As such in hydrogen, because all the refineries have been mandated to deploy or just install these hydrogen plants which require green power. So one of the projects which we already have bid with the JV partner only in the Numaligarh refinery, so that gives us that particular sense that if we are setting up the plant where green hydrogen is one area where the revenue would be coming back by the total operational expense, which is the green power.

Harendra Singh executive
#75

The green power setup would be considerably larger than the green hydrogen capex. So what we’re looking at is something where L&T is the only player to date. They’ve secured two orders from 25 and 1. The same applies across all the refineries — this has to be done. And the government is also examining many other public sector undertakings where the mandate has been given to set up the plant. This is one area we’ve picked together with one of the trusted partners we’ve brought into our fold, which does hold the patent for setting up the plants along with indigenous components, which are now the prime requirements for the bids. As far as this goes, apart from that, if you’re looking at the opportunities in buildings — residential buildings or commercial buildings — we’re examining that opportunity once we’ve finished the Kanpur project. So it’s mostly done. The total building portion is already complete. So we don’t need any qualified, say, JV partners. So we’re looking at that opportunity where building construction can be undertaken in the government or the private sector. Understood. And up to what sizes would we qualify in the case of government orders there?

Harendra Singh executive
#76

That's not a big figure. Initially, it would be somewhere between INR 300 and 500 crores. Alright.

Vineet Naran unknown
#77

All right, that's clear. Many thanks, sir. Many thanks.

Operator operator
#78

Thank you. Since participants have no more questions, I'll now pass the conference to management for closing remarks. Over to you, sir. Thanks for being with us today. We stay confident about continuing to succeed, and we're available to take any additional questions. So don't hesitate to contact us or our advisor, Go India Advisors. Thank you. Good day. Thank you. On behalf of Go India Advisors, this conference is now concluded. Thanks for joining us, and you may disconnect at this point.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete H.G. Infra Engineering Limited transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to H.G. Infra Engineering Limited earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.