Home / Transcripts / Core Scientific, Inc. (CORZ) · February 26, 2025

Core Scientific, Inc. (CORZ) Earnings Call Transcript

February 26, 2025

NASDAQ US Information Technology Software earnings 48 min

Earnings Call Speaker Segments

Jon Charbonneau executive
#1

Good afternoon, everyone, and thanks for joining Core Scientific's call covering results for the fourth quarter of fiscal year 2024. Right now, everyone is in listen-only mode. Once management finishes speaking, we'll open things up for a question-and-answer session. I want to point out that some of what we discuss today includes forward-looking statements, which fall under the safe harbor protections of the Private Securities Litigation Reform Act of 1995. Such statements cover, without limitation, anything beyond historical or current facts that predicts or signals upcoming events or trends, forecasts, performance, or achievements, and they might use terms like believe, anticipate, expect, estimate, intend, project, plan, or similar words and phrases. These forward-looking statements rest on present expectations, forecasts, and assumptions, and they carry risks and uncertainties that could make actual results come out materially different. To learn more about those risks and uncertainties, we suggest you look at the risk factors covered in the company's annual report on Form 10-K as filed with the Securities and Exchange Commission, along with the special note about forward-looking statements found in the company's current report on Form 8-K filed today, plus the earnings release and slide presentation included with it. You can find today's presentation on our website, corescientific.com, under the Events and Presentations section. What's shared on this conference call is accurate only as of today, February 26, 2025. The company has no obligation to update any statements made today because of events or circumstances that happen afterward. Here with me today from Core Scientific are CEO Adam Sullivan and CFO Denise Sterling. With that, let's turn things over to Adam for his remarks.

Denise Sterling executive
#2

Good afternoon, everyone, and thank you for joining us today. At the start of this call, I'll go over the key milestones achieved in the quarter and the fiscal year, and then hand it over to Denise, who will take you through our financials. After that, I'll discuss our growth strategy along with the considerable value creation opportunities in front of Core Scientific. Once that's done, we'll open up the lines for your questions. During our second quarter earnings call, we identified three growth catalysts that defined 2024: contracting the remaining HPC hosting capacity, expanding infrastructure capacity, and diversifying our customer base. Starting with HPC, we began by signing a 16 MW deal with CoreWeave in Austin, and we delivered that 30 days ahead of schedule. We then moved quickly to fully contract the original 500 MW of HPC capacity through a series of new 12-year agreements with CoreWeave. That contract carries total revenue potential of $8.7 billion over its term, amounting to approximately $725 million annually once fully operational. For reference, our total revenue for 2024 was just over $500 million, primarily from Bitcoin mining. Securing this landmark HPC contract marks a pivotal step as we transform into a leading data center business. Next, we made considerable progress in 2024 expanding our HPC infrastructure capacity by reallocating resources away from Bitcoin mining, growing existing sites, and acquiring new ones. As a result, we ended the year with contracted power above 1,300 MW. In the fourth quarter, we received approval to increase gross capacity at our Denton site by nearly 100 MW, equivalent to about 70 MW of critical IT load. Dallas remains one of the fastest-growing data center markets in the United States, and we believe our Denton facility is on track to host one of North America's largest GPU supercomputers. Separately, on the prior earnings call, we discussed our expansion into Auburn, Alabama, where we signed a lease-to-buy agreement at the AUBix facility. That site currently has 11 MW of critical IT load, and we're working closely with Alabama Power to secure a much larger power agreement. Given power constraints in the nearby Atlanta market and Auburn's strategic location, this site could become a significant development for the company. We're delaying major capital deployment until negotiations with potential customers conclude, keeping our investment optimally aligned with demand. Briefly on organic customer diversification: while we didn't sign another large HPC hosting customer last year, we're in active discussions and remain confident in our ability to diversify our HPC customer base. Turning to our capital structure, I'll let Denise cover the details, but we significantly strengthened our balance sheet in 2024, leaving us well-positioned to execute our growth strategy this year and beyond. Finally, I want to take a moment to express how proud I am of the strategic hires we brought in across the business last year. We're also pleased with our improved cost structure, including $0.033 per terahash and $0.037 per kilowatt hour, with additional savings to $0.042 and $0.044. We've brought in top-tier data center experts, and their track record demonstrates an ability to consistently deliver large, intricate construction projects. That's strengthened our leadership team and our capacity to execute, and we believe this deeper pool of talent underscores our commitment to growth and innovation as we continue our evolution into a premier data center operator. With that said, I'd like to hand it over to Denise, who'll dive deeper into our financial specifics. Denise? Thanks, Adam. I'm pleased with our financial performance in 2024, especially given the operational hurdles we navigated, namely the April Bitcoin halving and the deliberate shutdown of several active mining sites to free up space for our major HPC hosting deal with CoreWeave. Securing that agreement was a major leap forward for the company, providing a strong foundation for our ongoing transition toward HPC. Despite all these shifts, the financial results we reported demonstrate our operational expertise and left our balance sheet significantly stronger, positioning us well for a successful 2025; so I'll begin with an overview of our fourth-quarter financial performance. Total revenue was $94.9 million, down 33% from the same period a year ago, while Adjusted EBITDA came in at $13.3 million. Now to our segment results: digital asset self-mining revenue was $79.9 million, a 29% decline. The primary driver was 974 Bitcoin mined in the fourth quarter versus 3,042 in the comparable quarter last year, partially offset by a 130% year-over-year increase in Bitcoin's price. As of December 31st, 2024, we operated approximately 164,000 self-mining units, representing 96% of our total mining fleet, with the remaining 4% being hosted mining units. Digital asset hosted mining revenue was $6.5 million, down from the $30 million posted in the fourth quarter of 2023, as we wound down our hosted mining agreements, a trend we expect to continue this year. Finally, we generated $8.5 million in HPC hosting revenue for the quarter and, as expected, ended the year with 16.5 MW of critical IT load, which includes an additional 0.5 MW contracted during the fourth quarter. Turning to expenses, our 2024 average annual fleet-wide power rate of $0.04 per kWh beat our 2024 target guidance of between $0.04 and $0.04 per kilowatt-hour. Our average fleet-wide power rate in the fourth quarter was $0.03 per kWh. Slide seven has an overview of our segment mining economics. Gross margins for the quarter were 2%, 36%, and 9%, respectively, for digital asset self-mining, digital asset hosting, and HPC hosting. Within our HPC hosting segment, we also measured performance using a non-GAAP cash gross margin, which excludes the direct pass-through of power costs as well as non-cash items like stock-based compensation and depreciation; for the fourth quarter of 2024, our non-GAAP cash gross margin was 16%. Operating expenses for the fourth quarter of 2024 totaled $43.6 million, compared with $30 million in the same period a year earlier. During Q4 of 2024, our net loss came to $265 million, versus a net loss of $195.7 million during the equivalent quarter the prior year. If you move to slide eight: what it cost us in direct cash to self-mine a single Bitcoin in Q4 was $51,035, and the total cash-based hash cost across that quarter came in at approximately $0.33 per terahash. Let me now walk through the balance sheet, starting at slide nine. When 2023 ended, we had roughly $1 billion of total debt. Across 2024, through our Chapter 11 debt restructuring, we reduced that total debt figure by $270 million. Following that, we converted our secured convertible notes, which totaled $260 million, into equity, largely by way of mandatory conversion; not long after that, in August, we completed a $460 million convertible note offering, which allowed us to pay off $260 million of existing senior debt, eliminate restrictions and covenants, and lower the interest rates on those notes dramatically, from as high as over 12% down to 3%. Then, more recently, in December, we closed a $625 million convertible note offering carrying a very attractive 0% interest rate. Adding it all together, we entered 2025 with an unlevered balance sheet aside from our convertible notes, plus more than $830 million in cash — something we believe positions us well to execute our growth strategy. On the HPC capacity front, any expansion not yet under contract, whether that means additional power allocations at existing sites or entirely new locations, might require capital expenditures on our part. Once we announce new customer contracts and secure the additional capacity requirements, we'll provide more details regarding any outlays that become necessary. Since our focus is on growing the HPC hosting business, we don't expect to grow or refresh our Bitcoin mining fleet until we obtain the new Block ASIC chips in the second half of 2025. No further CapEx related to our Bitcoin mining business is planned for this year. Our pro forma fully diluted share count was approximately 501 million shares as of February 20th, as shown on slide 10. For 2025, we are currently modeling a statutory effective tax rate of 22%. Beyond that, we hold over $300 million in net operating loss carryforwards, which will reduce future cash taxes. With that, I'll hand the call back to Adam. Adam?

Adam Sullivan executive
#3

Thank you, Denise. When we think about what lies ahead for 2025, our plan is to keep leveraging what we do well — constructing appealing, sizable infrastructure. The main priorities for this year are, first, broadening who we serve by bringing on additional HPC clients. Second, delivering successfully on the HPC agreements already signed; and third, growing our capacity both through organic means and via strategic M&A. To begin with broadening who we serve: that ranks as the company's number one objective for this year, with the aim being to secure sufficient contracts that CoreWeave accounts for under 50% of critical IT load by the close of 2028. Right now we're holding active talks with dozens of prospective customers, among them the bulk of hyperscale providers plus a number of sizable enterprise firms. Demand is still robust, though we're encountering far more due diligence than we did during the first half of 2024. That increased scrutiny stems from the wave of new market entrants making bold capacity commitments without the concrete power agreements to support them — similar to what happened recently when a hyperscaler pulled contracts from companies that had exaggerated their available power. Our demonstrated history and locked-in power agreements distinguish us under these conditions, and we won't grow our footprint unless we feel a high degree of confidence in our ability to deliver for additional customers. Turning to priority number two: delivering on the HPC agreements already signed. Today we announced a major expansion of our relationship with CoreWeave at our Denton facility, which will take that site to full capacity. This fresh agreement contributes roughly 70 MW of critical IT load and amounts to approximately $1.2 billion in added contracted revenue across a 12-year term. With this most recent expansion, our overall contracted value with CoreWeave has now surpassed $10 billion — a figure encompassing our Austin, Texas agreement — and spans about 590 MW of critical IT load once everything is fully online. Within that total, slightly more than 570 MW represents capacity we're converting at existing sites to HPC, where we anticipate 75%-80% cash gross profit margins. We consider this among the biggest HPC deployments anywhere in the United States, and CoreWeave's ongoing demand already exceeds their supply, which strikes us as a robust indicator of their business health and growth potential. Under this newest agreement for the extra 70 MW, we'll be funding $1.5 million in capital expenditures per megawatt, while under earlier agreements CoreWeave bore those costs. In exchange, we'll gain from full rental payments throughout the first two years of the contract, since no CapEx credit will be tied to this new agreement. Going forward, we now anticipate having delivered roughly 250 MW of HPC capacity to CoreWeave by the conclusion of this year, with the complete 590 MW going live in early 2027; that marks a change from our earlier timeline and mirrors both the scale and complexity of the project, especially the addition of an incremental 70 MW of critical IT load. These things create a number of lasting difficulties, and we worked through them alongside CoreWeave. During that effort, we made design improvements meant to squeeze more out of the GPUs, and both sides settled on fresh timelines for delivery. Those measures have pushed our schedule out a bit, but we think they leave us better positioned to deliver stronger, more efficient infrastructure that keeps pace with what our customers need from HPC. Priority number three for us is growing our HPC capacity, both on our own and via strategic M&A. After the 70 MW expansion in Denton we announced not long ago, we think we can bring on another 300 MW across sites we already have by the close of 2027, which is up from what we said last quarter. We're also seeing meaningful greenfield chances, and our target is to add roughly 400 MW of fresh capacity within the next three years; when it comes to M&A, we're actively chasing deals in the markets where we already operate while also weighing carefully whether to move into new ones. That covers buying stabilized data center assets or book-but-not-built projects tied to strategic customer contracts, which gives us more predictable revenue; this fits nicely with our bigger goal of getting our largest customer under 50% of total critical IT load by the end of 2028. To wrap up, my excitement about the momentum we've brought into this year has never been higher. Our team is completely fired up and sure of our capacity to carry out our growth strategy, which we think will create substantial value for every one of our stakeholders. I want to say a heartfelt thank you to our clients, our industry partners, and above all our devoted teammates for everything they keep doing and the support they give. I'd also like to thank our current shareholders personally. Your belief in what we're building has mattered enormously in getting us here, and none of this would have happened without you; so with that, let's open it up for your questions.

Darren Aftahi analyst
#4

Hey, everyone. I appreciate you fielding my questions, and it's nice to see the capacity growing. If I can ask two things: first, Adam, could you go into a bit more depth on the permitting timeline and what might be stretching it out? Second, regarding the Alabama location, I understand you've said you won't put too much money in until talks with prospective customers and Alabama Power are further along. So where do things stand with them? Is there a feasibility study completed? How fast could this move forward? Any extra detail would be great. Thanks.

Adam Sullivan executive
#5

Sure, absolutely, and thanks for asking, Darren. On permitting, it was really one specific site of ours, and when we were planning that site's expansion, we needed to complete extra permitting steps tied both to the expansion and to a fairly significant design change made during that effort, which was really about optimizing for efficiency and optimizing for that asset's scale. We've now moved beyond that stage, and we're quite confident because at that location we have construction underway, contractors on hand, and people on the ground, so we know things are progressing in line with the schedule already before us. On your second question about Alabama, at present we're in a position of strong confidence in our ability to obtain additional MW there. As soon as those commitments come through, that's when we'll start putting more capital into that site. You also need to consider the distinction between having a signed customer and us getting ready for that customer. So clearly, a substantial amount of capital will go in once that new customer contract is signed. Before then, though, CapEx will be limited, though not zero, for getting that site closer to pad-ready status.

Jon Petersen analyst
#6

Excellent. Nice work on the CoreWeave expansion. Could you perhaps walk us through the economics? I believe you said during this call that you'll be paying $1.5 million upfront rather than taking a CapEx credit. How should we view the rents? Apart from that, should we treat the rents for this arrangement as being identical to those from the prior one?

Adam Sullivan executive
#7

That's right, precisely. Nothing at all has changed, so in roughly a bit more than 2 years, from a rate standpoint, those contracts are going to appear the same.

Jon Petersen analyst
#8

All right, so I do appreciate the objective of getting CoreWeave to under 50% of revenue by the close of 2028. To pull that off, I believe you'd have to secure significantly more power during this year, on top of bringing on more customers. So perhaps you could just walk us through the milestones that must be reached over the course of this year for you to stay on track toward that?

Adam Sullivan executive
#9

Right. What we're really focused on there is bringing them under 50% of critical IT load by 2028, and that work is underway right now. We've discussed being able to keep growing at sites we already have, and that's a competitive situation, since we're receiving guidance on how much extra power we'll be able to secure at a number of our current sites, plus some of the new ones too. Those are very appealing locations. Building blue-chip assets is what we're centered on these days, and we want those blue-chip assets paired with blue-chip clients. So that's where our attention sits today, and we'll keep executing and buying additional sites to bring more capacity online, lock in more contracts, and hit our target of bringing them under 50% by 2028.

Analyst analyst
#10

I was kind of hoping we could dig a bit deeper into why capacity slipped this year, plus how the data center designs ultimately got locked in. What proved to be the toughest part — shifting architectures, supply chain issues — and going forward, once you're adding more capacity, will those facilities be built to spec so they can handle GB300s or Rubin architectures too? Thanks.

Adam Sullivan executive
#11

Yeah, sure; and your final point is exactly correct. When we look at developing infrastructure for the GB200s and the GB300s, that effort demands certain incremental design adjustments. And during Q4 of last year, we ran into some added permitting obstacles. A portion of that stemmed from greater complexity and scale. On other fronts, at different sites, we simply had to revisit and verify our permits, given that supply chains remain tight when you project into 2026. And something we were determined to get right was having the proper equipment lined up on the proper schedules for our site plans. That meant altering certain designs so they matched the equipment we could actually obtain and still meet the timelines we'd committed to. So we saw a handful of extra delays there. Still, on the whole, we feel very confident about the delivery schedules we've laid out today. And we think we can reach those timelines.

Analyst analyst
#12

And, you know, I also want to touch on possible worries about Microsoft reducing capacity with CoreWeave — though in our view, the contracts aren't set up that way. But let's suppose, for argument's sake, that there's a chance CoreWeave's contract revenues decline. From where you sit, how would you folks explain the effect of that? And could CoreWeave ultimately move ahead either with or without Microsoft? And maybe any thoughts on the demand side there?

Adam Sullivan executive
#13

Yeah. I mean, apart from what they've said publicly, I'm not able to speak to anything specific regarding the relationship between CoreWeave and Microsoft. That said, CoreWeave keeps growing. You can see that not just with Core Scientific, but really all over the world and internationally. So based on what we're observing, demand on CoreWeave's side is much stronger than what we saw in 2024. A lot is happening in the market right now that we're seeing, and that's actually fueling ongoing demand and flow toward CoreWeave. So we're thrilled about continuing to expand alongside them at Denton. And Denton will be one of the biggest supercomputers in the United States, and it's going to be a flagship asset for CoreWeave. So we're really excited to keep growing our relationship with them.

Brett Knoblauch analyst
#14

Thanks, everyone. I really appreciate it. Perhaps just briefly regarding the delays, so to speak, or the pushback and the timing. I just want to confirm I understood you correctly. You now anticipate critical IT load for this year to reach 250 MW. Is the 16.5 included in that, and previously you were expecting, I believe, 270 plus the 16.5?

Adam Sullivan executive
#15

Yes. Thank you, Brett. Yes, that is right. What's happening is simply that a single 40 MW building is being shifted to early 2026, and you are completely correct. That figure does include the 16.5 MW.

Brett Knoblauch analyst
#16

All right. And I believe a number of inquiries came our way after DeepSeek, which really shook up the sector. In your talks with customers since DeepSeek, what have you noticed? Has anything actually shifted, or is demand equally strong — or perhaps even stronger — from that point on?

Adam Sullivan executive
#17

Based on everything we've been hearing across all of our conversations, folks are looking to pick up the pace. We're getting far more detailed asks when it comes to sites for developments and where they'd want to put up buildings, but on the whole, the DeepSeek news landed pretty heavily on the public markets. From all that we've observed when it comes to actual demand, it keeps climbing and those talks keep moving along quite nicely, so our view is that DeepSeek was somewhat of a head fake for the wider markets, yet on the whole, it hasn't altered what demand looks like for us.

Greg Lewis analyst
#18

Yeah. Hey, thanks. Good afternoon, and I appreciate you taking my question. Hey, Adam. Could you expand a bit on something? You brought up enterprise customers as a possibility. That's an area we seem to be hearing about more, outside of just the hyperscalers. As you possibly widen the customer base past only the hyperscalers, and it appears latency is a major problem for them. Maybe scalability is a major problem for them too. When you consider possible enterprise customers, does that create additional sites that might be in a sort of hype, does that create additional sites perhaps within your portfolio and other places that perhaps beneath a hyperscaler footprint wouldn't be viable, yet through an enterprise it could be?

Adam Sullivan executive
#19

That's an excellent question. When we look at those two distinct customer bases, hyperscale clearly wants a very particular set of criteria that varies by geography, often far, far bigger than what gets considered on the enterprise side. So yes, definitely. A few smaller sites that still have low latency capabilities are getting looked at for enterprises. But on the whole, one thing we're considering is that we want longevity across every one of our assets. And so we're thinking about having hyperscales at minimum as anchor, possibly a single tenant. And when they act as anchor, being able to fill the remaining capacity with enterprise clients too. So regarding demand, does it create additional sites with enterprise? Definitely. However, we're concentrated on blue-chip assets with blue-chip clients, and both of those groups are included in that.

Greg Lewis analyst
#20

All right. That's really useful. Thanks a lot.

George Sutton analyst
#21

Thanks. Adam, there were a couple of points you made that seem slightly contradictory. I just want to confirm I understood you properly. On one side, folks want to go quicker, yet you brought up sizable rises in due diligence. Could you reconcile those for me?

Adam Sullivan executive
#22

Yes, of course. When it comes to going quicker, that's really regarding delivery schedules. Getting through the due diligence work sits in a separate bucket of the equation; they express a desire to hand over sites within a given timeframe, yet that also demands that people get those sites nearer to pad-ready, nearer to powered shell; and a piece of this is about filtering out plenty of folks who think they belong in the data center industry simply because they hold power and land. That alone doesn't turn you into a data center provider; and that's truly the distinction here for Core Scientific. We hold the power, we hold the land, and we hold the team capable of delivering those assets. And that's what pulls us into these discussions. And they want to go quicker on delivery schedules. As soon as a contract is signed, they want a firm delivery date. That's truly the distinction there. I hope that reconciled it for you, George.

George Sutton analyst
#23

That makes sense. Then I have another question about the $1.5 million per MW you'll be putting up under this newest contract. My guess is that during a negotiation, with the balance sheet you have now, you're able to take that on quite easily. So you'd prefer to recognize the revenue event at the point it happens. Is that right?

Adam Sullivan executive
#24

Yes; that certainly was among the things we weighed. Denton is a one-of-a-kind asset, a phenomenal asset. And this gives us a terrific chance to keep growing our relationship with CoreWeave; so we're quite pleased with how the economics turned out on it.

Analyst analyst
#25

Hello, Adam and Denise. I appreciate you taking the question. What I'd like to ask about is CoreWeave and whether the AI neocloud business model stays healthy over the long term. After DeepSeek came out, I believe there was arguably some uncertainty regarding how GPU rental pricing power would be affected down the road if AI models became more commoditized or spread further into open source. Perhaps you could share your perspective on that, and then second, whatever detail you're able to offer about how confident you are in the durability of the CoreWeave contracts and the business model over the long term. Thank you.

Adam Sullivan executive
#26

Sure. I'll take your first question, and after that we can return to your second one. Based on what we observe regarding demand for CoreWeave's business, they can enter into long-term contracts, and that represents a quite strong signal of demand for the existing generation or the newest generation of GPUs that are being released. If CoreWeave's business model were entirely built around an hourly-based system, there are companies out there structured that way, and those companies are far less valuable than CoreWeave is. So we believe, given the way they're structuring their contracts, that we have high confidence in their continued ability to deliver. I'd love for you to ask your second question just because I hope I covered your first one clearly.

Analyst analyst
#27

That was excellent. Thanks. The second one was really just, once more, I suppose, addressing your assurance regarding those agreements over the long haul. I mean, you essentially just covered that. And the AI neocloud business model broadly speaking over the long term, that would be wonderful. Yeah.

Adam Sullivan executive
#28

Yeah, certainly. Winners are absolutely going to emerge, and losers are absolutely going to emerge in this scenario. It's an expanding sector right now. We keep witnessing additional uptake. We're observing every one of these neocloud providers keep increasing their contracted revenue; it's certainly an thrilling period for the industry. And I believe the people who ink big deals with big enterprise clients will end up being the winners over the long term here. And I believe that's what we're observing among a handful of these neocloud providers. But I believe only a handful of winners will exist in this industry.

John Todaro analyst
#29

Fantastic. Thank you. Hi, Adam. Congratulations on yet another lead — wonderful to see that. I've got one question plus a follow-up. To start, regarding the upgrade or expansion of Denton alongside CoreWeave, did you hold talks with any other hyperscalers, or was it only CoreWeave? Then my follow-up concerns the push-out piece.

Adam Sullivan executive
#30

Absolutely. Denton was a location we truly had earmarked for CoreWeave; we did speak with additional hyperscalers and other clients about those megawatts. As we mentioned regarding the potential of 300 MW at other sites already in existence, we are currently in discussions with other prospective customers about that; and honestly there's no assurance that anything of that sort would go to CoreWeave, since what we're really aiming to do right now is keep diversifying our customer base. And our current sites serve as excellent campuses for us to accomplish that.

John Todaro analyst
#31

Great. Got it. Then I just want to confirm what I have regarding the push-out; so my understanding is that a single 40 MW building was delayed until 26. So do we still have that 200 MW by Q2 2025 as a target, the one from the initial press release? Or, I suppose, just those first couple hundred megawatts, when should we expect them to be operational?

Adam Sullivan executive
#32

Our target is really the year-end number. What I'd say is that there was push-out across the schedule because of those delays, and that was really one of our major campuses, so the timeline here is something that is elongating by a few months, so I would say the expectation is that the timeline for each of the megawatts to come on, the ramp schedule for these megawatts to come on, is a little bit later than was originally thought to happen.

Kevin Dede analyst
#33

Hey Adam, and Denise — I appreciate you letting me join. To circle back to the rollout Jon brought up, could you describe how much of the impact came from permitting versus equipment? That part still isn't very clear to me. Sorry, Adam — what's actually the main problem?

Adam Sullivan executive
#34

Yeah, no, I'm glad you asked, Kevin. What I'd say is that in the course of growing that site, we needed to make sure we had plenty of equipment ready within the time frames we were aiming for. Because of that, we had to bring in various kinds of equipment for particular portions of the build-out. That made the permitting side more difficult, simply because so many separate items of equipment needed to be ordered before we could bring this added capacity online at that location. So supply chain and permitting both played a role, and everything came together at once. That combination, taken as a whole, is what ultimately produced these delays.

Kevin Dede analyst
#35

To narrow it down on the hardware side, are we talking UPS units, Gensets, B200s, or the networking links that you're waiting on?

Adam Sullivan executive
#36

The GPUs aren't the issue at all. Part of it sits with the electrical gear, and part of it comes down to the overall design. So there isn't a single component I can point to. Honestly, it's a wide mix right across the board.

Kevin Dede analyst
#37

Got it. Thanks, Adam.

Adam Sullivan executive
#38

Thank you, Kevin.

Nick Giles analyst
#39

Thanks, Operator. Good afternoon, everybody. Adam, congratulations on securing yet another contract with CoreWeave. I appreciate your target where CoreWeave accounts for under 50% of critical IT, but that suggests you're signing at minimum an equivalent volume with other clients. You've laid out 700 MW across current and future locations by 2027, so should we take it that the difference would also be new customers, or might that 130 be divided between a new client and perhaps one additional tranche with CoreWeave?

Adam Sullivan executive
#40

Yeah. We've laid out the 300 and the 400 figure; that refers to critical IT load megawatts, so roughly 700 MW. Looking ahead, if we hold 590 of CoreWeave contracts, the 700 we have available is truly where we'll be concentrating on bringing in new clients. So that's part of our aim to push them under 50%, which means having sufficient capacity on hand and sellable so we can bring them down to that level.

Nick Giles analyst
#41

Understood, that clears things up quite a bit. Perhaps you could also shed some light on what we ought to expect regarding the size and timing of those additional client agreements in the period ahead?

Adam Sullivan executive
#42

Sure. Basically, at this moment, we are holding talks with most of the hyperscalers and having discussions with big enterprises. Those opportunities actually account for a number of the biggest chunks of capacity we can sell, along with our capability to start driving that figure under 50% far more rapidly. We're also evaluating additional clients. Such deals would be the kind we'd turn to in the event a hyperscaler or big enterprise chose not to take an entire campus, though those client discussions keep developing throughout the early portion of this year. We're quite enthusiastic about our ability to sell more capacity, and we feel confident that we can close additional client agreements during this year involving new clients.

Joseph Vafi analyst
#43

Hi, Adam. Hi, Denise. I'd like to join in congratulating you on the Denton expansion. Perhaps you could give us a sense of — compare and contrast the trade-off between — I think everyone gets that diversifying revenue is a positive, but it really appears that with CoreWeave, you potentially have far less capital intensity on new builds compared with what some other players in the sector might have. So how do you view that trade-off between potentially higher CapEx on new contracts versus greater revenue with CoreWeave? Then I have a quick follow-up.

Adam Sullivan executive
#44

Yeah. No, I appreciate the question. We view this business over the long term. We don't see this as a five-year business. This is a 20, 30, 40-year business. So as we consider growing this enterprise across the next few years, having revenue diversification from other clients will only benefit us — not just from a credit-rating standpoint in a high CapEx industry, to start positioning ourselves to aim at becoming investment-grade over the next three to five years; but also, truly, we're viewing this business as a far more stable, free cash-flowing business that all of our investors can understand. Right now, with a majority of our revenue coming from CoreWeave, that's something we must keep working on to ensure that we have a business three years from now, four years from now, that's coming from multiple different sources and investment-grade counterparties that can really demonstrate how strong a company we have.

Joseph Vafi analyst
#45

Absolutely. Appreciate the additional detail. At this point, we still haven't observed a large number of contracts within this sector. From what it sounds like, the tempo of conversations involving providers as well as those aiming to procure keeps broadening. Even this early on, has anything shifted when it comes to pricing talks with customers, despite the fact that, from where we sit, there isn't really a solid picture yet of where pricing stands right now? Many thanks.

Adam Sullivan executive
#46

Right. What I'd say is that pricing depends heavily on geography and also on proximity. In other words, how robust an asset we possess. Because of that, you need to approach it from several angles. Certain markets unquestionably command premium pricing throughout the industry; these rank among the tier-one markets. Beyond that, it ties straight into the latency involved, along with how close things sit to that key metropolitan market, which means a degree of price discovery exists. A great deal of price discovery occurred during 2024. Price discovery is turning into. We're beginning to establish pricing, essentially a pricing foundation, across quite a few different markets. So I'd put it this way: pricing is genuinely settling throughout 2025. What we anticipate is that once 2026 arrives, we'll be standing on far more solid ground regarding where that ends up.

Analyst analyst
#47

Good evening, Adam and Denise. I appreciate you both taking the time to address my questions. During this call, there was some discussion regarding increased scrutiny stemming from the wave of lower-quality data center operators that have entered the market. Could you provide additional detail on how the current supply and demand situation actually looks? Also, do you get the impression that hyperscalers might start flexing their muscles more in the future, and what effect would that have on the terms being agreed upon with those counterparties?

Adam Sullivan executive
#48

As the landscape has evolved throughout 2024 and many newcomers have come into this industry, one thing we've observed is that a lot of these hyperscalers evaluate certain sites and would prefer simply to purchase them from companies lacking the expertise to truly develop them and get them across the finish line. Obviously, they are locating other partners to assist with construction, design, and so forth. However, based on our current vantage point, I'd say hyperscalers aren't really flexing their muscles in that way. Instead, they are focused on making certain they finish every step and all the due diligence. Considering what took place at the close of last year involving certain contracts with hyperscalers that ultimately got terminated, the key issue is making sure those hyperscalers direct their capital toward places where they have confidence. There was such a frantic scramble during 2024, particularly in the earliest months, when everyone was simply attempting to secure as much power as possible. And now, from where we stand, things appear somewhat different. These companies want to be certain they are constructing assets in the correct locations and that they possess the appropriate exposure for the demand outlook they foresee for that particular location.

Analyst analyst
#49

I appreciate the additional detail. For my next question, have you noticed any shifts in demand for inference versus training workloads following DeepSeek and other recent prominent headlines? I'd simply like to hear your take on how that might affect your site acquisition strategy going forward. Thank you.

Adam Sullivan executive
#50

Yes, certainly. What we're observing right now is significantly less emphasis on certain bigger training campuses, and far greater attention on spots that offer improved, closer proximity to major metropolitan areas. So I'd describe the demand — or the way we approach site evaluation — as being considerably more targeted and far more concentrated on locations nearer to major metropolitan areas, compared with certain moments last year when we were certainly assessing particular sites located farther out yet possessing larger power capacity.

Rosemary Sisson analyst
#51

Thanks. I just wanted to build on what you said, Adam, regarding being close to big metropolitan regions. Does that suggest you might be considering growing beyond the markets where you currently operate — perhaps moving into the East Coast or the West Coast when those chances come up?

Adam Sullivan executive
#52

Yes, of course. Rosemary, I appreciate that question. What I'd say is that at this moment we're putting up one of the biggest data centers anywhere on the East Coast. That gives us quite a bit of assurance in our capacity to keep growing into additional markets. In this case, we're set to rank among the biggest providers serving Dallas; we think much the same holds true for Atlanta. So entering more cities is definitely something we're pursuing; though it does look somewhat different, since our knowledge of the utilities in a given spot may be thinner. On that note, at present we work with 7 utilities. We keep broadening those ties throughout that group; therefore, whenever we assess a new location, we follow a highly careful, utility-first approach, making sure a solid partnership and connection with that utility exists, so we can be certain firm power is there for us when we bring a client in.

Rosemary Sisson analyst
#53

That's intriguing. Alright, so as a quick follow-up, at present there's a substantial amount of cash sitting on your balance sheet, which you could deploy to cover the initial outlay for a number of these data centers, just as you indicated you'll be doing with this Denton expansion. Is that how you see it? What's your perspective on that? You also brought up wanting to hold an investment-grade rating. So my assumption is that eventually you might issue debt in order to finance part of that. What's your thinking when it comes to that capital allocation choice?

Adam Sullivan executive
#54

Right. So I'd put it this way: when we think about contracts down the road, more capital deployment is going to be required. As this business keeps expanding over time, it's going to mature and come to resemble some of our other publicly traded peers in the data center space, as we aim for leverage ratios, as we aim for a variety of metrics that matter in the data center industry. Our company will go through a maturation period in which, from a capital structure standpoint, we start to look a lot more like them. So that's essentially what that remark means — we're going to need to put capital to work on deals in the future. We understand that. In a high CapEx industry, we want to make sure we've positioned ourselves correctly to secure the lowest cost of capital we possibly can.

Jon Charbonneau executive
#55

Appreciate all of you being on today's call, and I'm eager to talk with each of you over the next several weeks and months. Thanks. Many thanks to you all. Be well.

Operator operator
#56

Thank you. That brings us to the end of today's teleconference and webcast. You can go ahead and disconnect your line at this point, and we hope you have a wonderful day. We appreciate you joining us today.

Read the full transcript via the API

You're viewing the first half of this call. Get the complete Core Scientific, Inc. transcript - plus 132,000+ transcripts from 7,000+ companies, speaker segments and full-text search - through the EarningsAPI REST API or hosted MCP server.

Get an API key View API docs →

For developers and AI pipelines

Programmatic access to Core Scientific, Inc. earnings transcripts and 132,000+ others is available through the EarningsAPI REST API and the hosted MCP server. Quarterly plans from $162 - full transcripts, speaker segments, full-text search, and the /api/v1/transcripts/recent polling endpoint for ETL pipelines.